) ) SSCL#356 SUPERCONDUCTING SUPER COLLIDER LABORATORY SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 )

SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) )

SSCL#356

SUPERCONDUCTING SUPER COLLIDER LABORATORY

SSC PROJECT MONTHLY PROGRESS REPORT

JULY 1991

)

Page 2: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

1:30 - 1:40

1 :40 - 1:50

1:50- 2:00

2:00- 2:30

2:30- 2:50

2:50 - 3:10

3:10 - 3:30

3:30 - 3:50

3:50- 4:00

JULY DOE MONTHLY REVIEW AGENDA

AUGUST 23, 1991

Opening Remarks Joe Cipriano/Ed Siskin

Project Overview Paul Reardon

Administration Division Bob Van Ness

Accelerator Design & Operations Division John Rees

Accelerator Systems Division Ted Kozman

Magnet Systems Division Tom Bush

Conventional Construction Division Jon Ives

Discussion

Closing Joe Cipriano/Ed Siskin

' •

Page 3: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) ) ) ) )

INTRODUCTION

The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in

conditions (red, yellow, green) from the previous month's report are marked with an asterisk. This report is intended to

summarize Divisional status; additional information is available through the responsible organizations. Backup documentation

and signatures are on file with the Project Cost, Schedule, and Reporting Group.

The Monthly Progress Reports are distributed electronically. All authorized SSCL personnel can access distribution via a

locked folder on the PMO server. All DOE recipients will receive a copy via QuickMail. Hard copies will be provided to

other Laboratory and University personnel who are PC based, or do not have computers for E-mail. Retrieving, printing, and

security of the Monthly Progress Report will become the responsibility of the authorized recipients.

Page i

Page 4: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

TABLE OF CONTENTS

SECTION PAGE

INTRODUCTION ........................................................................................................................................................... i

TABLE OF CONTENTS ............................................................................................................................................... ii PROJECT MANAGER'S OVERVIEW ........................................................................................................................ 1

BASELINE SCHEDULE ....................................................................................................................................... 10 ADMINISTRATION DIVISION ................................................................................................................................. 13 ACCELERATOR DESIGN AND OPERA TIO NS DIVISION .................................................................................... 21 ACCELERATOR SYSTEMS MACHINE STATUS .................................................................................................. 25

ACCELERATOR SYSTEM STRING TEST (ASST) ........................................................................................... 26 LINEAR ACCELERATOR (LINAC) ................................................................................................................... 29 LOW ENERGY BOOSIBR (LEB) ........................................................................................................................ 32 MEDIUM ENERGY BOOSTER (MEB) ............................................................................................................... 34 HIGH ENERGY BOOSIBR (HEB) ....................................................................................................................... 36 COLLIDER ............................................................................................................................................................. 38 TEST BEAMS ........................................................................................................................................................ 39

ACCELERATOR SYSTEMS DIVISION ................................................................................................................... 41 MAGNET SYSTEMS DIVISION ............................................................................................................................... 47

CONVENTIONAL CONSTRUCTION DIVISION .................................................................................................... 63

PHYSICS RESEARCH DIVISION .............................................................................................................................. 75 LABORATORY TECHNICAL SERVICES DIVISION ............................................................................................ 83 DIRECTORATE DIVISION ....................................................................................................................................... 87

Page ii

c c c

Page 5: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

PROJECT MANAGER'S OVERVIEW

Page 1

Page 6: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

PROJECT MANAGER'S STATUS REPORT

DESIGN ~ PRODUCTION ~

CONSTRUCTION 181 RESEARCH & DEVELOPMENT 181 PART I

I. IDENTIFIERS:

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZATION(S)

Project Manager's Overview Accelerator Design & Operations Division Accelerator Systems Division Magnet Systems Division

ld. OFFICE CONT ACT Conventional Construction Division Physics Research Division

Robert Morse (ext. 4013) Project Management Division Laboratory Technical Services Division

le. PROJECT MANAGER Administration Division Directorate

Paul Reardon (ext. 3087)

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status

LAST PERIOD THIS PERIOD

COST G G Green Yellow Red Ill =•C··•·

*

~ .. ~ SCHEDULE 1•·•··········•.!t.•• G G TECHNICAL G G

OVERALL PROJECT

*Pending CCB approval.

Page 2

f f • • c

Page 7: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

PROJECT STATUS REPORT PART I PROJECT MANAGER'S OVERVIEW 2b. PROJECT MANAGER'S NARRATIVE HIGHLIGHTS (See item 5 for details on problems and variances)

WBS

1.1.2.1.12 Linac RF System

2.1.6.25 String Enclosure (ASST)

2.4 Campus

3.1.4 Engineering Standards

4.2.1 Accelerator R&D

4.2.1 Technical Specifications

4.5.1 Director's Office

Selected Drift Tube Linac and Coupled Cavity Linac Klystron suppliers.

Completed foundations and steel erection.

Completed Title II Design for Magnet Test Lab. Completed West Campus Preliminary Design Requirements Document.

Completed Guideline 4.1, "Description and Maintenance of Engineering Guidelines Standards and Practices".

Submitted corrector magnet procurement packages (for collider) to DOE for approval.

Issued three (3) specifications.

Issued call for Letters of Intent for the second major detector.

Page 3

Page 8: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

PROJECT STATUS REPORT PART I PROJECT MANAGER'S OVERVIEW 5. SIGNIFICANT PROBLEMSN ARIANCE ANALYSIS 5a. PROBLEMS, IMPACT ON PROJECT, CORRECTIVE ACTION RESPONSIBLE

PROBLEM IDENTIFICATION IMPACT CORRECTIVE ACTION GROUPS 2.2.2.1.1 IR4 Underground Hall and Significant increases in scope from Composite CCB package in process to CCD,PB/MK, Shaft Structure - Rescoping of mechanical baseline will have cost and schedule address scope changes for Interaction ADOD and electrical systems and underground impact. Regions (IRl, IR4, IR5, IR8). design requirements.

3.1.2, 3.1.3 Cost & Scheduling - Mid-July 1991 Integrated Project Schedule Workshops to be held August 19-23 to PMO Development of Integrated schedules and (IPS) completion not achieved. Potential finalize IPS by August 30, 1991. Draft development of new Work Breakdown delay in implementation of WBS. WBS ready for review in August. Structure (WBS).

4.2.1 ASST - Building Current schedule projects a 2 week delay Working on partial BOD - Contractor is CCD,ADOD, Construction. in the Beneficial Occupancy Date (BOD) currently ahead of this revised plan, PB/MK

of ASST Building. schedule recovery is expected.

4.2.1.6 Collider - Relocation of utility Increased peak voltage as a result of power Proposed reduced spacing of niches and ADOD shaft resulted in increased system feed locations. increased number of voltage dumps will complexity. improve system reliability. CCB package

will be submitted.

4.2.1 Development/Approval of Six (6) to fifteen (15) week slips expected Continued attention on expediting ADOD Technical Specifications. in issuance of remaining specifications. specifications. Three (of 22 total) have

been issued to date. Sb. ITEMS REQUIRING PMO/DIRECTORA TE/DOE ACTION

NIA NIA NIA NIA

Page 4

Page 9: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

PROJECT STATUS REPORT PART II PROJECT MANAGER'S OVERVIEW 8. MILESTONE LOG

SIGNIFICANT MILESTONES ACCOMPLISHED SINCE LAST REPORT BASELINE DA TE ACTUAL DATE WBS

1.1.6 Start corrector magnet procurement for Collider September 91 July 91

SIGNIFICANT MILESTONES OPEN BASELINE DA TE FORECAST DA TE

2.4.2 Start Magnet Test Lab Construction June 91 August 91

2.4.22 Magnet Development Lab Beneficial Occupancy April 91 September 91

KEY MILESTONES UPCOMING - NEXT THREE MONTHS BASELINE DATE FORECAST DA TE

2.1.6.25 ASST Beneficial Occupancy September 91 October 91

2.1.2 St.art Linac Facility Construction August 91 February 92*

* No technical system impact, BeneficiaJ Occupancy Date expected to be met.

Page5

Page 10: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Item#

l

2

3

4

CCB Date

7/24/91

c

SUMMARY OF PROJECT MANAGEMENT DECISION PAPERS

July 1991

SUBJECT

Proposed HEB Change (fune)

Application of Three Shaft Design Concept - N20 through N4S

Conventional (warm) Magnet design for HEB to Collider Transfer Line

Set spacing and quantity of Niches and Alcoves to Accommodate The Orientation of the Spools in The Collider Tunnel

Description

CCB ACTIONS (This reporting period)

Net Project Impact *Dollars Sched

DATE

7/3/91

7/3/91

7/11/91

7/15/91

CCB Action

DOCUMENT NUMBER

El 1-000015

El 1-000016

Ell-000017

El 1-000018

DOE Comments Action

CCSR El2-000044 Systems Engineering Budget Transfer -0- NIA Approved To DOE For Approval

Page 6

• c •

Page 11: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Superconducting Super Collider Networ~ Stetuo Dete• 21JUL91 Gr1nh1c Produced b• PMD on 16AUG91

wes NUMBER WBS/CDDE DESCRIPTION

i I. TECHtlICAL SYSTEM

I I. 01. 01 I I 1. 01. 02 I i 1.01.0J I

I 1.01.04

! 1

1.01.os

\ 1. 01. 05

i I .01. 06

: 1. 01. 06

1. 01. 06

:1.01.07

1. 01. 08

1.02.01 ' i 1. 02. 02

I I. 02.0J

: 1.02.oJ

1. 02. OJ

1.02.03

I I. 02. 04

2.01 .01 j

2. 0 I. 02

2. 01. OJ

2. 0 I. 06

2.01. 06

2.01 .07

MANAGEMENT/SUPPORT

LINAC SYSTEM

LES SYSTEM

MEB SYSTEM

HEB START INSTALLATION

HEB SYSTEM

l•t COLLIDER 1/2 SECTOR - START MAG.INSTALL'

FIRST COLLIDER HALF SECTOR - START COOLDOWN

COLLIDER SYSTEM

TEST BEAMS

GLOBAL ACCELERATOR SYSTEM

SYSTEM MANAGEMENT

HEB MAGNET PRODUCTION

COM AUTHORIZ. ro INCUR cosrs

START FIRST HALF SECTOR COM DELIVERY

FULL RATE PRODUCTION DECISION ON MAGNETS

COLLIDER RING CCRJ MAGNET PRODUCTION

SSCL EOUIPMENT/TOOLING

CONVENTIONAL CONSTRUCTION

CONVENTIONAL CONSTRUCTION ADMINISTRATION

LINAC

LEB

START SSC CIVIL CONSTRUCTION

COLLI DER

TEST BEAM

)

COMPARATIVE SUMMARY BARCHART

PROJECT SUMMARY LEVEL. PART 1 Ba•elone Ma•ter Schedolel Ver. 12, Rev• 7

SSCL MONTHLY PROGRESS REPORT BY WBS (Calender i• In Fiocel Yeerol

l9o 1991I199211993119941199sl1995J1991l 199sl 1999

I I I I I I I I I ////////////////// /////// / ///7-77//////J

"~••••lltz:/'u':u'':z::;,,'.'.:z:/'u':u':'u''.'.:Z: ''2:2'".:u'::-2171 I I I I I I I ////////////////// / / /

////////////////// '',"'~I I I I I I I ... I .. ~~I •.. I . . I I I j I lzzz4zzzzzzzzz;'.7zzl: j

I I I . tc ~Ml* I I I I I I I I TMI I I I //////////////////

I

I 1' L-1 -~-.--r--.,-,-r-r--->,....,...--JI 1' 1' z z z z 4 z z 21 ////////////////// )/////////////////////

//////////////////

lzzzz;zzzz;zzzzz~zzzzjzzzz~zzzzJ

'VM1

//////////////////

i I I

I i I I I I I · I I I I I I I

I ', I 2 2 j / /1

I I I •IMI I

I I IZZZZZZZZJ

I I

. I l

I L-~. -,~~,,~--r-,,~,~,~,~~,/~--r-,,~,~,~,~-,-,/~/.....,.~,~-r-/,-/~-,-//~--,--//.,.....,,/ ~-r-//h

I I~, ~~~~~~~1·

1

I I

1 1 tzzzzzzza 1 1

I I I I I -l I I I I I I

I

I I

I

I I

119901 1991 I 1992 I 1993 I 1994 I 1995 I 1996 I 1997 I 1998 I 1999

I

I I I I I I

I I I I I

I I

ool

2000 I

Orn111 10• f'RJJUHWI

BASEL! NE .. DJECTED FINISH FINISH

SEP99 SEP99

MAR95 JUN95

OCT95 NOV95

JUN96 JUN96

AUG96 JUL96

MAY98 MAY98

JUN94 SEP94

MAR95 AUG95

SEP99 SEP99

SEP96 NAY96

SEP99 SEP99

SEP99 SEP99

SEP97 SEP97

NOV90 15NOV9 A

APR94 JUL94

APR94 JAN95

SEP98 SEP98

SEP92 APR9J

SEP99 SEP99

OCT92 APR93

MAR94 APR94

MAR91 I JNAR9 A

APR97 MAY97

NOV94 OCT94

IL----.J-1

BASELINE ACTIVITY ACTUAL ACTIVITY r z z "'PROJ. CRITICAL ACT. 0-oRIG. CRITICAL MS vPROJECTED MILESTONE

... , ,,,ORIG. CRITICAL ACT. 1zzzz1PROJECTED ACTIVITY *-BASEL!NE MILESTONE .-ACTUAL MILESTONE .-PROJ'TEO CRITICAL MS

-'=============================================================================================================~

)

Page 12: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Superconducting Super Col/1der Network Status Date• 21JUL91 Graohlc Produced bv PMO on 16AUG91 was NUMBER WBS/COOE DESCR (PT I ON

2.

2.02.01

2.02.01

2.02.02

2.02.03

2.02.04 2.02.os

2.03.02 1 I 2. 03.03

I 2 • 04 • 01 I

!i ~:~::~! 2. 05. 0 I

! 2. 05. 01

! 3

3

I 3

3. 01. 01

3.02.01

4.

I 4 • 01

i 4.01

I 4. O I

I 4 • 01

i 4. 0 I

I 4. 01

: 4, 01

I 4. 01 4.02.0I

: 4 .02. 01 I 4.02. 02

CONVENTIONAL CONSTRUCTION

NOTICE TO PROCEED CNTPJ EXPERIMENT HALLS WN REGION

WS REGION

EN REGION

ES REGION

SUPPORT FUNCTIONS

PRIMARY SYSTEMS - ON-SITE SECONDARY SYSTEMS - ON-SITE

CENTRAL LAB/OFFICE AREA MAGNET LABORATORY

ENVIRONMENTAL HEALTH FACILITIES

A/E-CM LETTER CONTRACT ~ NTP

ARCHITECTURAL ENGINEERING

PROJECT MANAGEMENT

BASELINE VALIDATION COMPLETE

SEIS RECORD OF DECISION CRODl

PROJECT MANAGEMENT OFFICE

SYSTEMS ENGINEERING

R~D & PRE-OPERATIONS

START LlNAC 600 MEV COMMISS!ON!NG LEB START COMMISSIONING

MEB START COMMISSIONING

MEB TEST BEAMS AVAILABLE

HEB START COMMISSIONING

COLLIDER - START COMMISSIONING CBEAMl

BEAM TO EXPERIMENT-ENO OF PROJECT/BEGIN OPER

ACCELERATOR PRE-OPERATIONS

ACCELERATOR SYSTEMS STRING TEST P-1 COMPLETE

ACCELERATOR R~D

MAGNET R~D

1 4.03 LAB ADMINISTRATIVE SERVICES

4.04 LAB TECHNICAL SUPPORT 1 4.05 LAB DIRECTORATE

COMPARATIVE SUMMARY BARCHART B•sel ine Master Schedule! Ver. 12. Rev. 7 PROJECT SUMMARY LEVEL. PART 2 SSCL MONTHLY PROGRESS REPORT BY WBS

...

...

<Calendar is In Fiscal Years)

9011 991 I 199211 993 I 1 994 I 1 99s I 1 996 I 1 997 1 99g J 1 999 oo I i I I I I I I I

i l1 rz~zz~;1~zzzz~zzzz;zzzz;J J l J

I I I 11z1zzzz1zzz222zzzz2z}1'. I .. I · J ·

I I ~ " ,

I I I IZZZ7ZZ7ZZZZZ2222777 /( . t. I ' ' I I' tZZZZZZZZZ22ZZZZZZZZd'

j I I lz2zz2zz/22222222)i · I I I I //////////////////1 I I I I I

11

12z2zzz2zzz11zzz%i' I I I I I 1zzzzzz2za I 1 1 I I

I im .

I \HI

I ~:I I I I I I I I I I

/////////////////////////////////////// I I

I I

I

I I

I

I I

I

I I

I

I

I I

I

I

I I

I

I

I I

I

I I

!

' I I I I I I

'~Ml I

////////////// / 7/ //

I *.Mi I

///////////////////~ /////j//////77///////

/////////////////////////////F///////////

Dr•••n 101 PRJSUMW2

BASEL! NE ••DJECIED FINISH FINISH

JUN9J

DEC96

JAN97

AUG98

SEP99

NOV96

DEC94

MAY95

JAN97

MAR92

MAY96

AUG90

FE899

JUL90

OEC90

JUN9J

DEC96

FEB97

NDV98

DEC99

FEB97

FEB95

JUN95

OCT9J

JUL92

MAY96

I TAUG9 A

MAY99

01 JUL9 A

01 FEB9 A

SEP99 SEP99

SEP99 SEP99

OCT94 OCT94

OCT95 OCT95

JUN96 JUN96

JAN97 MllR9T

SEP98 SEP98

MllR99 MllR99

SEP99 SEP99

SEP99 SEP99

OCT92 NOV92

SEP99 SEP99

SEP99 SEP99

SEP99 SEP99

SEP99 SEP99

SEP99 SEP99

i 4.06 LAB EXPERIMENTAL SUPPORT / / / / / / / / / / / / / / / / / //77,-,,,,,-;-7,,,, 7 , / /7 // / SEP99 SEP99

~4~·~0~1:..__L_!P~R~I~M~E~C~O!_!N~T~R~A~C~T~O~R~·~s~F~E~E~S'.._ __________ ..L·~···•li:/z;::;:/::~//;:;z::.;1/c;2/:z:;;://:::;z::.;//::;z::.;11~~//2::;:/~z::.;11::7?;:;7~7::;7z::;:7:7~7~z:;772::;:7::7~7;:7~7:::::z::.;//~/;:~//~z::.;//~,/;:~/~~ ..... rs~E~P~9~9..JS~E~P~9~9-~ 1990 I 1991 I 1992 I 1993 I 1994 I 1995 I 1996 I 1997 1998 I 1999 2000 I

IL------LB,r..SELI NE ACTIVITY

~""""'ORIG. CRITICAL ... er.

f

•••r"cTU,r..L ACTIVITY

I z z z z I PROJECTED ,r..CT! VI TY

r ~~Ji PROJ. CRITIC,r..L ACT.

*-e,r..SELINE MILESTONE

0-0RIG. CRITICAL MS \TPROJECTED MILESTONE

.-... CTU ... L MILESTONE ,..-PROJ'TED CRITICAL MS

Page 13: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Superconducting Super Collider COMPARATIVE SUMMARY BARCHART 8a9eline Ma., t er Schedule I Ver-. 12. Rev. 7

Network Statuo Date• 21JUL91 PROJECT SUMMARY LEVEL PART 3 SSCL MONTHLY PROGRESS REPORT BY WBS Graahic Produced bv PMO on 16AUG91 (Calendar i. in Fiscal Ye a r ol 0 ..... 11 ID• ,RJSUf1Wl

was HUHBER WBS/CODE DESCRIPTION /9011 991 11 99211993I1 994 I 199s/1996r1 9911199s11 999 001 BASEll NE PJIDJECTED FINISH FJliUSH

15 E YFER ! 11Et/ T AL S 1 Sf EflS I I I I I I I I I i 5 BOD LARGE EXPERIMENT HALLS I I I I I I *.Mr· I I I I JAN96 FEB96

5 EXPERIMENTAL SYSTEMS A I I I I I I I SEP91 SEP91

I I

5.01 EXPERIMENTAL SYSTEM R&O .... SEP99 SEP99 ////////////////// //////// , / 7 -;; 7 -/ / / / / / /

5.02 BEGIN CONCEPTUAL DESIGN FOR DETECTORS I ~Ml: I I I I I I I I . /3 : I FEB91 01 MAR9 A

5.02 WEST DETECTORS - START COMMISSIONING I I I I I I I I I Ml I MAR99 MAR99

5.02 DETECTORS .... SEP99 NOV99 ////////////////// ///////////77777///////

I EXPERIMENTAL SYSTEM COMPUTERS .... SEP99 SEP99 I 5. 03 / , , / / / / / / / / / /777 /7777777/7///////1

I I I I I I I I T I I I

I I I I I I I I I I i I

i I I I I I I I I I I ' I I I I I I I I I I I

I I I I I I I I I I I I I I I I I I I I I I

I I I I I I I I I I i I I I I I I I I I I i I I I I I I I I I I I

I I I I I I I I I I ' I I I I I I i i I I

i i I I I I i I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I

11990 I 1991 I 1992 I 1993 I 1994 I 1995 I 1996 I 1997 l 1998 I 1999 I 2000 I II 1 BASELINE ACT!YI TY ACTUAL ACT 1Y1 TY !"' z z ... PROJ. CR 1T1 CAL ACT. <>-ORIG. CRITICAL MS yrPROJECTED MILESTONE

iii;'\:'\;, ORIG. CRITICAL ACT. 1zzzz1PROJECTED ACTIVITY *-BASELINE MILESTONE .-ACTUAL Ml LES TONE "f"PROJ'TED CRITICAL MS

Page 14: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

BASELINE SCHEDULE

WBS DESCRIPTION BASELINE PROJECTED* EXTENDED DESCRIPTION

(DEC 90) (A Indicates actual date)

3.0 Baseline Validation Complete JUL90 I JUL90 A Completion of docwnents and briefings on Baseline Cost Estimate & Schedule and Supplemental Concept Design Report.

2.5.1 A-E/CM Letter Contract AUG90 17 AUG90A DOE Approval and release of a letter contract, pending a full

&NTP contract, for PB/MK to begin formal design & construction work.

1.2.3 CDM Authorization to NOV90 15 NOV90A DOE permission for the CDM contractors to incur costs toward

Incur Costs their contract in beginning the Collider Dipole Magnet industrial program.

3.0 SEIS Record of Decision JAN91 I FEB91 A Secretary signature and formal filing of the Environmental Record

(ROD) of Decision. This allows non-reversible project construction to begin.

5.2 Begin Conceptual Design FEB91 1 MAR91 A Start the detector concept design and Title I conventional facilities

for Detectors design effort

2.1.6 Start SSC Civil Construction MAR91 13MAR9IA The first construction notice to proceed after the SEIS ROD. The first facility is the EI Infrastructure.

2.2.1 Notice to Proceed (NTP) JUN93 JUN93 The first notice to proceed for construction of the experimental

Experimental Halls (interaction region) halls; IR-4 and IR-1. 1

4.2.1 Accelerator System String Test OCT92 NOV92 Cooldown, power up and testing of the 1/2 cell with accelerator

(Phase !)Complete components including the string test of 5 Collider Dipole magnets of industrial fabrication.

Variance Remarks

1 = Forthcoming CCB request to reconcile dates.

* =These dates are current projected dates from schedule updates and pending Change Control Board proposals.

Page 10

• • • •

Page 15: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

WBS DESCRIPTION BASELINE PROJECTED* EXTENDED DESCRIPTION

(DEC 90)

1.2.3 Full-rate Production Contract APR942

Awarded on Collider Magnets

1.2.3 Start First Half Sector CDM APR942

Delivery from vendor plant

1.1.6 First Col!ider Half Sector - JUN942

Start Magnet Installation

4.1 LINAC Scan Commissioning OCT94

(600 MeV)

1.1.6 First Collider Half Seclor - MAR952

Start Cooldown

4.1 LEB Stan Commissioning OCT95

5.0 Beneficial Occupancy of Large JAN96

Experimental Halls

Variance Remarks

2 ::: CCB Request in process to modify baseline schedule.

(A indicates actual date)

JAN95

JUL94

SEP94

OCT94

AUG95

OCT95

JAN96

SSCL award of the full rate production contract(s) for collider magnets requires prior DOE approval.

Start Delivery of the first contractor production magnet (CDM) from the contractor's dock to the MAAS.

Start magnet and spool installation after completion of tunnel finish-out including power, lights & ventilation and primary technical components e.g. piping, electrical components cryogenics, etc.

Start commission with beam of the full 600 MEY LINAC and signoff after suitable checkout of engineering and safety systems.

Cooldown of the first complete half sector (EI-Fl) and the concurrent power safety check of a full half sector. Requires last magnetic component (472 15M, 8 13M, 96 CQM & 96 spools) delivered to tunnel 4 months prior to this date.

Beginning of the LEB beam commissioning installation and suitable checkout of the subsystems and safety signoff. Requires the LINAC to be able 10 provide test beam.

Beneficial occupancy of !he experimental (interaction region) halls. This BOD includes lighting, power & ventilation, etc. and is 9 months after the first BOD where just the unfinished chamber is turned over for technical survey.

* ::: These dales are currenl projected dates from schedule updates and pending Change Control Board proposals.

Page 11

)

Page 16: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

WBS DESCRIPTION BASELINE PROJECTED* EXTENDED DESCRIPTION

(DEC 90) (A indicates actual date)

4.1 MEB Start Commissioning JUN96 JUN96 Beginning of the MEB commissioning after installation and suitable checkout of the subsystems and safety signoff. Requires the LEB to be able to provide test beam.

1.1.5 HEB Start Installation AUG96 JUL96 HEB installation of major technical components after completion of tunnel out fitting (e.g. power, lights, ventilation) technical components include piping, electrical components cryogenic components, spools, magnets etc.

1.1.4 MEB Test Beams Available JAN97 MAR97 Completion of the MEB and test beam commissioning activity so that beam for detector component testing is available some fraction of the time.

4.1 HEB Start Commissioning SEP98 SEP98 Beginning of the HEB commissioning after installation and suitable checkout of the subsystems and safety sign off. Requires the MEB to able to provide test beam.

5.2 West Detectors - MAR99 MAR99 Beginning of the Detector commissionings. Includes operable

Start Commissioning beamline through detectors to support Collider commissioning.

4.1 Collider - MAR99 MAR99 Beginning of the full Collider beam commissioning after sector

Start Commissioning (Beam) testing is successfully completed. Requires the HEB to be able to provide beam. Requires accelerator components to be previously installed and checked in both IR halls.

4.1 Beam to Exp. SEP99 SEP99 Completion of the Collider and West detectors and Collider

(End of Project/Begin Operations commissioning activities. The SSC is now ready to perform experiments in two experiment (interaction regions) halls.

Phase)

Yarjance Remarks

* = These dates are current projected dates from schedule updates and pending Change Control Board proposals.

Page 12

• f • '

Page 17: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

ADMINISTRATION DIVISION

Page 13

Page 18: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A TUS REPORT

DESIGN 0 PRODUCTION 0 CONSTRUCTION 0 RESEARCH & DEVELOPMENT 0 PART I

1. IDENTIFIERS:

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZATION(S)

Administration Personnel Procurement

Id. DIVISION/OFFICE CONTACT Finance Minority Affairs

Carol Matteson (ext. 5053) MIS Records Management

le. DIVISION MANAGER

Robert L. Van Ness (ext. 1540)

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL

OVERALL DIVISION ASSESSMENT Green Green Green Green PREVIOUS DIVISION ASSESSMENT Green Green Green Green

Page 14

Page 19: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

4.3.2

4.3.7

Accomplishments

4.3.2

)

ADMINISTRATION DIVISION

Develop, implement and maintain the Laboratory's Financial Reporting and Accounting System in accordance with GAAP (Generally Accepted Accounting Principles) and DOE Orders. Ensure SSC Laboratory compliance with DOE, DOL regulations, policies and procedures addressing equal opportunities and procurement.

Description

Finance

Minority Affairs

Assisted Divisions in entering the FY91 institutional budgets in the Budget Forecast System.

Established a task force to coordinate the year end closing and the new year opening lab-wide activities.

Began developing means for segregating and reporting equipment purchased with Texas funds.

Developed provisional FY92 labor rates.

Completed a semi-annual summary report of DOE owned Plant and Capital Equipment from FY85 to May FY91 for use by

DOE Chicago to close out the Central Design Group contract.

4.3.7 The Director of Minority Affairs briefed the Women, Hispanic, and Black Caucuses on the Public Law 101-514 and Small and Disadvantaged Business Opportunities held in Washington, D.C. and met with the New York State Governor's Office of Minority Affairs to develop a referral system of providing the Governor's Office with SSC procurement opportunities. The EEO/AA Manager participated in the NAACP National Covention in Houston, contacted all schools in our proposed HBCU Co-op Program for final feedback, and tentative recruiting schedule and attended the National Urban League

conference and Georgia Tech Minority Career Fair in Atlanta.

Issues and Concerns None

Corrective Action N/A

Condition Green

roe Wanda Mizutowicz DATE: August 15, 1991

Page 15

Page 20: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

Accomplishments

LABORATORY FINANCIAL OVERVIEW Projected FY91 Funding vs YTD Contract Summary

TO RECEIVE FUNDING IN A MANNER THAT DOES NOT IMPEDE THE TIMELY PLACEMENT OF PROCUREMENTS.

Description

CONTRACT MODIFICATIONS THUS FAR HA VE KEPT PACE WITH SSCL COMMITMENTS. MOD 19 TO THE CONTRACT RECEIVER IN JULY.

Issues and Concerns OPERATING FUNDS NEARLY COMPLETELY OBLIGATED.

Corrective Action

Condition

POC

MONITOR OPERATING FUNDS VERY CLOSELY FOR THE BALANCE OF FISCAL YEAR TO STAY WITHIN BA CEILING.

GREEN

G. HILL DATE: August 15, 1991

Page 16

f •

Page 21: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

LABORATORY

ALL FUNDS PROJECTED FV91 FUNDING VS VTD

CONTRACT SUMMARY

(KS-TPC)

100 ----=

a;r r-DI CEC JAN FEB MAR APR MAY JUN JL Y PLG SEP

8/13/91

WJ REQUISITIONS

it COMMITMENTS

11111 a:sr

·X FUNDING TREND

.a- ACTUAL FUNDING

Page 17

Page 22: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

LABORATORY FINANCIAL OVERVIEW Labor and Labor Related Costs

Goa I TO ENSURE ADEQUATE BUDGET TO COVER ALL EXISTING AND PLANNED LABOR AND LABOR RELATED COSTS.

WBS Elements Description

Accomplishments BUDGET PLANNING IS ADEQUATE TO COVER EXISTING AND PLANNED LABOR AND RELATED EXPENSES.

Issues and Concerns COSTS CONTINUE TO LAG BEHIND PROJECTIONS.

Corrective Action: RE'EV ALUATE PROJECTIONS IN LIGHT OF HIRING AND FINALIZED BUDGETS AND REDIRECT EXCESS DOLLARS TO M&S.

Condition: GREEN

POC G. HILL DA TE: August 15, 1991

Page 18

f f

Page 23: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

LABORATORY ALL FUNDS

140000

120000

100000

80000

60000

40000

20000

0

JULY FY91 LABOR AND LABOR RELATED COSTS

($'S In Thousands)

)

EXPENSES CLASS:

3 9 - 4 8

121932

Em Labor & Rel Budget

Ill Labor & Rel Actuals

89 {]- Labor & Rel Proj

-Ir Direct Labor Budget

-<>- Direct Labor Actuals

CCT f'DJ CEC JAN FEB MAR APR MAY JUN JUL PLG SEP

YTD URA, EGG FTEs = 874.5 AVG COST/FTE = 54.2 K$ INCL FRINGE

Page 19

Page 24: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

LABORATORY ALL FUNDS JULY FY91

PROJECTED COSTS & COMMITMENTS

VS ACTUALS

100000 +------1

0

CCf t'-0/ C£C JAN FEB MAR MAY JUN JUL PlG SEP

APR

EXPENSE CLASS:

Labor & Related: 39-48

M&S Subc, L&U: 49-53

CUMULATIVE

WI M&S and Subct Cost & Commits

Actuals

Ill Labor & Related Costs Actuals

• M&S and Subct Cost & Commits Plan

-l:r- Labor & Related Costs Plan

DOES NOT INCL: CTRL FAC (28.4), CONT (11.4). DOE W/HELD (6.9), MGMT RES (7.6), FWD FUNDING (2.6)

Page 20

f • f •

Page 25: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

ACCELERATOR DESIGN AND OPERATIONS DIVISION

Page 21

Page 26: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT STATUS REPORT

DESIGN 0 PRODUCTION 0

CONSTRUCTION 0 RESEARCH & DEVELOPMENT 0 PART I

1. IDENTIFIERS:

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANlZATION(S)

ADOD Linac High Energy Booster

ld. DIVISION/OFFICE CONT ACT Accelerator System String Test Low Energy Booster

Don Edwards (ext. 3020) Collider Medium Energy Booster

le. DIVISION MANAGER Beam lines

Don Edwards (ext. 3020)

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status

GROUP TECHNICAL COST SCHEDULE OVERALL

Linac Green Green Green Green

LEB Green Green Red Green

MEB Green Green Red Green

HEB Green Green Red Green

Collider Green Green Green Green

ASST Green Green Green Green Beam lines Green Green Green Green

OVERALL DIVISION ASSESSMENT Green Green Red Green

PREVIOUS DIVISION ASSESSMENT Green Green Red Green

Page 22

• c • • •

Page 27: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements

4.2.1

Accomplishments

ADOD

To supply the necessary deliverables to support the project milestones.

Description

Accelerator R&D

Good progress on specification preparation:

Signed Off - Linac Segment 3a, Linac Facilities 3b, LEB Segment 3a;

)

In Signature Process - LEB Facilities 3b, HEB Segment 3a, Linac Beam Transfer 3b, ASST 3b;

In Fonnal Review - Linac Accelerator 3b, MEB Segment 3a, HEB Beam Transfer 3b, Collider Segment 3a;

First Draft Complete - LEB Beam Transfer 3b, Collider Magnet 3b, Collider Accelerator 3b, HEB Accelerator 3b;

Rough Draft Complete - LEB Accelerator 3b, LEB Beam Transfer 3b, MEB Accelerator 3b, HEB Magnet 3b, Collider Accelerator 3b;

Rough Draft Started - MEB Facilities 3b, MEB Beam Transfer 3b, HEB Facilities 3b, Collider Facilities 3b.

Issues and Concerns Preparation of most 3A and 3B specifications are behind schedule.

Corrective Action Proceed with approvals so that the major portions of the specifications are available for use.

Condition Green

POC Don Edwards DA TE: August 15, 1991

Page 23

Page 28: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

ADOD FY91-92 DELIVERABLES

WBS Deliverables Baseline Schedule Current Projection Condition Appraisal

4.2.1 LINAC Final Design Review Aug91 Aug91 Green

4.2.1 Set Coordinates, All Accelerators Apr91 Apr91 Complete

4.2.1 Magnet Requirements Completed

IBB Jun91 Aug91 Red

MEB Jun91 Aug91 Red

HEB Jun91 Jul91 Red

4.2.l RF Requirements Completed

I.EB Jun91 Aug91 Red

MEB Jun91 Aug91 Red

HEB Jun91 Jul91 Red

Page 24

• • • • • • •

Page 29: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

ACCELERATOR SYSTEMS MACHINE ST A TUS

Page 25

Page 30: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

4.2.1

2.1.6

Accomplishments

4.2.1

Issues and Concerns

4.2.l

Corrective Action

4.2.1

Condition

POC

ACCELERATOR SYSTEM STRING TEST (ASST)

Demonstrate operation of a half-cell of industrially produced collidcr magnets.

Description

Accelerator R&D

(String enclosure/N 15 service buildings)

Completed Iron-work for string enclosure August 5, and a roof and side casing installation.

Backfilled pits for refrigerator building.

Completed conduit work in floor for compressor building.

Began cool down for 40mm five dipole string at FNAL on August 5.

PDR presented for electronics racks and cable trays on July 30.

Racks installed in electronics trailer. Orders placed for TIST AR slow controls electronics.

Issued SPR Spool bid packages (bids due August 12-13).

1. Staffing requirements. 2. Software for controls system. 3. KPS/SEDALCO work around in Sept - Oct still not resolved; SEDALCO reports delay in delivery of compressor

building due to change order for under floor conduits. 4. ER spool installation may interfere with manpower for ASST.

1. Appointed J. Weisend (Cryo Group) technican supervisor, P. Kraushaar design layouts, W. Robinson data analysis. 2. ASD assignment of programmers to Grey's residence at El will allow day-to-day contact with ASST team. 3. PB/MK trying to work up an integrated schedule for KPS installation; PB/MK negotiating with SEDALCO to

minimize compressor building delay. 4. KPS developing installation schedule. Green

Thomas Dombeck (ADOD); Ted Kozman (ASD); Craig N. Trimble (CCD) DATE: August 15, 1991

Page 26

• • • • •

Page 31: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements

1.1.6

2.1.6.25

2.1.6.2.2.1

2.1.6.2.2.2

Accomplishments

1.1.6

2.1.6

Issues and Concerns

l.1.6

2.1.6

Corrective Action

1.1.6

2.1.6

Condition

POC

ASST (Continued)

Demonstrate collider operation of a half-cell of industrially produced magnets. Description

Collider

String Enclosure (Cryo Alcove & Shop)

Nl5 Service Building

Compressor Building

Completed vendor Critical Design Review and testing of the first article magnet power supplies. Completed string foundations.

I. There is a potential problem with protection for a quadrupole magnet connected in series with the five dipole magnets during a quench.

I. BOD delayed thru bid protest to October 14. 2. Process change order for underslab conduits between buildings (not included in general package). 3. Pennanent electrical power for testing (HCEC power line).

1. Need decision on whether or not quadrupole will be installed 1-3. Interface Working Group resolved major critical path design issues.

Green Thomas Dombeck (AOOD); Ted Kozman (ASD); Craig N. Trimble (CCD) DA TE: August 15, 1991

Page 27

Page 32: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

TMR 3 YEAR TERM COMPARATIVE SUMMARY BARCHART

Report: ASST w/ Level 1&2 Mi I es tones Ba~e I 1 n~ Ma5ter Schedule: Ver. 12. Rev. 7

SSCL REVIEW SUMMARY BY WBS Superconducting Super Col I ider Network Stotu• Dote• 21JUL91 Groohlc Produced bv PMO on 12AUG91 lColendor 19 In Fi•col Years) DI'•••"• ID• A!f-SU"

wes NUMBER WBS/CODE DESCR Ip TI ON I 2.01.06 COLLIDER

ASST FACILITY - FINAL DESIGN REVISIONS

STRING TEST FACILITY -CONSTR.NTP

STRING TEST FACILITY & El BLDGS. -ISSUE RFP

STRING TEST FACILITY lBODJ -COMPLETE

CONVENTIONAL CONSTR. DESIGN & CONSTRUCTION

4.02.0I ACCELERATOR R&D

ACCELERATOR SYSTEMS STRING TEST P-1 COMPLETE

POWER SYSTEMS

SPOOL PIECE

CRYOGENICS

UTILITIES

CONTROLS

INSTALLATION

TESTING

4.02.02 MAGNET Rt.D

lST COM lDCA313J AVAILABLE FOR INSTALLATION

STH COM CDCA317J AVAILABLE FOR INSTALLATION

1990 I 1991 I 1992 I 199.3

I '1 '1 . ii '1 i ii I I . I I ! I I I I . 1 I I I I I I I I : : 1 : .i,~ ·: I i i i I I I I I I I I '•. MZ I I I I I I I l

II I I I I .~MZ I I 'I I I '1 I I

I I I I I I '~Mz: I I I I i 11-,;......:..-'-'--"--'-'-~""--'--'.--'--'--~-'--'-'-/-'.-,1 /~J, . I I I ! I I 1 1 1 1 1 1 1 r-1 'I 'I 1 1 1

I I I I I I I I I I I .~· I I I I 11· I I I I I I I ·-~!~Ml I I I I ////// ////////! . I I I

I l I I I I //////////////!· I I I I I~ r--'--'-:-..!...-'--'--'-+'-/-'---//-=--/-/,;_/~ /-/'--/--!) ,1 i I I I I I I ·r11

1

---iz:./,.22/~z//~:'I : I I I I I I 1 1~~~-+'-'--'-~~I I 1

, I I //////////////J I l

I I I 1 '1

I I I I l I I I I I /////////////-:} . I ' : I i i i i i i i i I ! I 1

1 rz~~· I i I I I I I I I I I i I I I I I I I I I I I I ~M2 1 I I I I I I I I I I I I I . ;JM~ I I I I

I BASELINE bROJECTEO FINISH FINISH

MAR91 07MAR91

APR91 i 3MAR91

FEB91 28MAR91

SEP91 OCT91

SEP91 OCT91

OCT92 NOV92

AUG92 JUL92

MAY92 JUL92

MAR92 APR92

JAN92 OEC91

JUN92 JUL92

JUN92 JUL92

SEf'92 NOV92

JAN92 JAN92

APR92 llPR92

A

A

A

I I I I I I I I I * · I I I I l1----1--1-o_u_AD_-~A-VA_I_L_A_B_LE~l-O_cc_4_0_4_1~~-~-~-~~4!~~-1-!--~!~:4!-~~-l-~~~l--~+~-+---1---!--~l1--~: +I-~~. ~M~2~1-,--.,-1l----,-~+l--.,---,--~1--,---+-MA_R_9_2_~M-A-Y9_2 __ i

11---..JL-------------1...,.-1.l _..L....I ,--1. 1'----·41 _..L....1 ---.11'--_-1..1.1.-4-I _11.--_·~1 ~..i...1 _11-_ _.i,I ~-..1-I --r-L----'----1 '1-------------------------------------------------~'------~1~99~0~----~l--------~·9~9~1 ________ .1.-1 ______ ~·~9~92 ________ ~1 ____ ~1~99~3'----~1=--------.--------1

i .,__ ___ _._I BASELlNE ACT rvr TY •••• ,ACTUAL ACTIVITY ~rJ"~4"~4f'~4"~J PROJ. CRITICAL ACT. <)-ORIG. CRITICAL MS \J'PROJECTEO MILESTONE

i ~,,,,]ORIG. CR! T!CAL ACT. l//////A PROJECTED ACTIVITY fr-BASELINE MILESTONE ~-ACTUAL MILESTONE .,,.PROJ'TED CRITICAL MS

• • • •

Page 33: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements 1.1.2.1.2 1.1.2.1.3 1.1.2.1.4 1.1.2.1.5 Accomplishments 1.1.2.1.2 1.1.2.1.3

1.1.2.1.4 1.1.2.1.5

Issues and Concerns 1.1.2.1.2 1.1.2.1.3 1.1.2. l.4 1.1.2.1.5 Corrective Action 1.1.2.1.2

1.1.2.1.3 1.1.2.1.4 1.1.2.1.5 Condition 1.1.2. l 2.1.2 POC

LINEAR ACCELERATOR (LINAC)

Design, Construct and Commission a 600 MeV H- Linac with high reliability and low transverse emittance to supply beam to the Low Energy Booster (LEB). Description Ion Source/Matching Radio Frequency Quadrupole Drift Tube Linac Coupled Cavity Linac

Installed Emmitance Measuring Unit and commissioning is in progress. Verified Vane tip machining programs. Issued Electroforming RFP. Scheme proposed which may reduce the number of RFQ Drift Tube Linac (DTL) buncher amplifiers. Scheme developed to power both DTL/Coupled Cavity Linac bunchers from a single klystron amplifier. Provided LANL with end-to-end design information for detailed critique. Quadrupole Magnet design ready to go out for prototyping for the Coupled Cavity Linac.

Smooth integration of computerized data acquisition and controls into Ion Source/LEBT operation. Lack of schedule float in an essentially linear fabrication schedule. Lack of experienced manpower to manage acquisition of DTL. Outstanding decisions: will Chinese provide CCL? will we build 1 GeV linac now?

Submitted request to Controls Department for long-tenn personnel commitment, holding weekly co-ordination and planning meetings between Linac, I&D and Controls section leaders. LANL shops working overtime to make up some lost time. LANL will post an rf structures expert at SSCL full time. Proceed full speed with engineering development and support efforts to reach decisions and prepare contingency plans.

Green Green Warren Funk(ADOD); Deryl Earsom (CCD) DATE: August 15, 1991

Page 29

Page 34: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 1.1.2.1.8 1.1.2.1.12 1.1.2.1.18,19 2.1.2 Accomplishments 1.1.2.1.8 1.1.2.1.12 l.1.2. l.l 8, 19 2.1.2 Issues and Concerns 1.1.2.1.8 2.1.2

Corrective Action 1.1.2.1.8 2.1.2

Condition 1.1.2.1 2.1.2 POC

LINAC (Continued)

Design, Construct and Commission a 600 MeV H" Linac with high reliability and low transverse emittance to supply beam to the Low Energy Booster (LEB). Description Quadrupole Magnets RF System Instrumentation, Controls Linear Accelerator Conventional Construction (including beam transfer to LEB)

Reviewing alternative design prepared by Indian lab. D1L and Coupled Cavity Linac klystron suppliers chosen. Contract being prepared. EMU controls implemented and operational. Title I Design Report and Cost Estimate submitted July 31, 1991.

Management of an Indian contribution of the pulsed quads. l. Projecting 6-month schedule slip in issuance of construction Notice to Proceed, resulting in a projected 17 day slip in

baseline BOD from December 11 to 28, 1992. 2. Need to minimize revisions in requirements and scope and "freeze" the design concept for the Title II phase.

Communications with donor lab being improved. 1. None. No technical system impact identified. 2. Definitize requirements prior to Title I review (July 22, 1991). Decisions on Scope.

Green Green Warren Funk(AOOD); Deryl Earsom (CCD)

DATE: August 15, 1991

Page 30

Page 35: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Superconducting Super Collider LONG TERM COMPARATIVE SUMMARY BARCHART Baseline Ma 9 t er- Schedule I Ver. 1 2. Rev. 7

Network Sta tu• Date• 21JUL91 TMR Report: LI NAC w/Level 1&2 Mi I es tones SSCL REVIEW SUMMARY BY WBS Greoh1c Produced bv PMO on 12AUG91 <Calender I• in Fi•cal ye a r • l 01'•••n• ID• LIM·SUl't

was NUMBER WBS/COOE DESCRIPTION 18911 99011 99111 99211 99311 99411 99511 99611 99711 99811 999 20001 BASELINE l>ROJECTED

FINISH FINISH

I I I I ! I I I I. 0 I. 02 LI NAC SYSTEM I I I I*: I I I I SET COORDINATES• LI NAC I I

DEC90 01APR91 A WM

I I I I I LINAC RFO/OTL/SCL CFORl I l~M2: I DEC92 DEC92

I I I I I I I I TECHNICAL SYSTEMS

I I I JAN91 JAN91

I I I I I ION SOURCE I I I I APR92 MAY92 77 7

I I I I RFO I l ' I I I APR9J MAY9J 777771/

I I I

I I I I I I OTL / / /7777 / /771 MAR94 MAR94

I I I I I I I I CCL ////////////-i JUL94 JUL94

I I I I I I I I POWER SYSTEMS JAN94 JAN94 //////////_!

I I I I I I I I RF SYSTEMS

I //////////// I I I JUN94 JUL94

I I I I · INJECTION I I ~zzzzzzzzzzzz z~i I I I MAR95 JUN95

I TESTING I I 1"'i:::ial· · I I I JUL94 JUL94

I I I I I T I I I I I 2. 01. 02 LI NAC I I I I I : I I I I I I LINAC TRANSPORT I. TRANSFER LINE 800 , ~M21 I APR9J APR9J

I I I I I I I I I

I I LINAC MAIN BUILDING FACILITY COMPLETE

I I , 1:7M2 I I FEB9J APR9J

I I I I I I I CONVENTIONAL CONS TR. OE SIGN g, CONSTRUCT I ON i i /////// ' i I I I I i FEB9J APR9J '

4.01 ACCELERATOR PRE-OPERATIONS I I I I I I I I I I I I i START LI NAC 600 MEV COMMISSIONING I I I I I : ~Ml I I I I I OCT94 OCT94

I I I I I I :a I I I I I i COMMISSIONING APR95 APR95

I I . I I I ' ; . ' I I , I I '

! 6 OPERATIONS I . I ' 1 I . I . I . I I . I I . I . I I I I I I I I I I I

. I

I OPERATIONS . I . I . I I . I . I '!//////////////////~ SEP99 SEP99

! 11 1 BASEL! NE

119891 1990 I 1991 I 1992 I 1993 I 1994 I 1995 I 1996 1 1997 I 1998 I 1999 2000 I

ACTIVITY ACTUAL ACTIVITY rzz41PROJ. CRITICAL ACT. 0-0RIG. CRITICAL MS vPROJECTEO MILESTONE

l'°''',ORIG. CRITICAL ACT. I z z z z I PROJECTED ACTIVITY *-BASEL I NE Ml LES TONE .-ACTUAL MILESTONE T"PROJ'TEO CRITICAL MS I

Page 36: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

1.1.3

2.1.3

4.2.l

Accomplishments

2.1.3

4.2.l

Issues and Concerns

2.1.3

4.2.1

Corrective Action

2.1.3

4.2.1

Condition

POC

LOW ENERGY BOOSTER (LEB)

Meet the overall Laboratory Goals to start commissioning by early FY96.

Description

l.EB

Low Energy Booster Conventional Construction (including beam transfer to MEB)

Accelerator R&D

Initiated Title I Preliminary Design. Circulated the frrst draft of the LEB magnet Advance Acquisition Plan. Power systems PDR was successfully completed in July.

Projecting two-month slip in issuance of construction NIP. The current schedule shows the start of commissioning to be August 31, 1995, allowing seven months before the start of commissioning for the MEB, with the RF system as critical path.

None. Projecting early turnover for installation. No FY funding impact.

Complete and finalize the magnet requirements so that the Preliminary Design Reviews can be held

2.1.3 Green; Yellow (ScheduJe)-ASD; Red (3N3B Spec Schedule) -ADOD

Richard York (ADOD); Ted Kozman (ASD); Dery! Earsom (CCD) DATE: August 15, 1991

Page 32

• • •

Page 37: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Superconducting Super Collider Network Statu• Date• 21JUL91

LONG fERM COMPARAflVE SUMMARY BARCHARf Ba.el ine Ma•ter Schedulel Ver. 12. Rev• 7

TMR Report: LEB w/ Level 1&2 Milestones SSCL REVIEW SUMMARY BY was Gr ooh I c Produced bv PMO on I 2AUG91 Orh•"• ID• LEI-SUH (Calendar i• in Fi•c•I Year•)

~1991 \1992\1993\199411995\1996\1997\1998\1999\2000\ was NUMBER WBS/COOE DESCRIPTION BASELINE PROJECTED

FINISH FINISH

I I I I I I I I I I I I I I I I I I I I I I I I I I I i I I I I I I I I I I I I

/,,////////////////)),. I I I I coNTRoLs I 1

lz1

zzzz;zzzziza I I I I I : INSTALLATION I I l l :&q I I I I I I I SAFETY I " i I I I I I ,t,PR95 M,t,R95 i1----f--------~------~-~-~~--f-_:_·~i__.:__:_~·~t.-.:l___.:l=Z=Z~Z::::Z=Z~Z==Z~Z~Z==Z~Z::::+Z=Z~d~·:___~l~~41__:__:_~·-J-.-:'__:__:_· 4,__:___:__:_J--.:l__:._:__~1------J--~--~ i 2 01 0 3 L EB . I . I I I . I . I I . I . I l

! . . LEB• FACILITY COMPLETE I I I I~· : I I I I I I

!. I I I I v~2 : I I 1·. 1· ,., I

CONVENTIONAL CONSTR. DESIGN & CONSTRUCTION : I / / / / / ( / ,,, /I/ A I I I I I I lt--~-+--u_T_I_L_1r_1_E_s_~-------------l----+1·_._~+-+l-'---'-----li_.._~_.___.i'--'-'-B~·-~1·~..__-+-l __ 4l __ ---1l~--'1----~'·~-'--'--l-M"_R_94--+"-P_R9_4_--I i 4.01 ACCELERATOR PRE-OPERATIONS l I I I I I I I I I

I I I I I I I I I I I I I I I ~,,. * I I I I I I I I I . I v. ~

21 I I I

:.: t-----+--c_o_MM_1_s_s_1 o_N_l_NG-------------+--'+-1 __ ·+-+-1 __ ·_+-1 __ ·_+-1 __ ·_+-1 __ ._@.,.....__· -·-+--1 __ ·_1--:-1 __ ·_1--:-1 __ 11--:-~~-+M-AR_9_s_-+F_E_B9_s_--I ) 6 OPERATIONS i i . i ' i i I l . I I J

i1-____ -1, ___ o_P_E_RA_T_1_o_N_s ______________________________ .L..,_·~1.__...,..,._L.j_I__, __ · ~'----~·-.j_1----·~1 ______ .1--l~;=/=:;::://~/~;;://~~/==//~~7~//=:::;//~~,~,_,.,.,,.,.......,-LS-EP_9_9 __ ...Ls_EP_9_9 __ --J :1--------------------------------------------------~1~90~11__:1~99~1--1-.1~19~9~2~1_.:1~99~3:__1-.l~19~9~4~1_.:1~99~5:__1-.l~l9~9~6~1_.:1~99~7--L--1~19~9~8_.l_.:1~99~9:..,_,1--2~0~0~0-..._l ______ -r-______ ~

1•~--1•'----'- BASEL! NE ACTIVITY

1.01.03 LES SYSTEM I I I I ' l I

I . iM I I I I I

I l l i I ~' I .-'--4---'---'---'--"--'---'-~-'---'->, . I I

~ / / / / ; / / / / I/ / / / . /I ,, / '/ I ~////;////:,/T7'0-7 I

. 11-'--1 ~--' /,_, __ ,___;. //-"'-/1 .....;/_/_-'--,,--',, __ ,,'---'-,

7--'--;7_'_'_;...,: I I

", / / ~ / } / '/ / , / -/I/ / , J I

I :LLL1 I~: I I .. [2] I . . I

~////;////:////!//.A I

SET COORDINATES• LEB

TECHNICAL SYSTEMS

POWER SYSTEMS

DIPOLE MAGNETS

OUAORUPOLE MAGNETS

RF SYSTEMS

UT Ill TIES

VACUUM

EXTRACT I ON

I NS TRUMEN TAT I ON

LES START COMMISSIONING

LEB COMPLETE COMMISSIONING

·--ACTUAL ACTIVITY rzz41PROJ. CRITICAL ACT. 0-oRJG. CRITICAL MS vPROJECTED MILESTONE

APR91 Ol,t,PR91

JUN95 JUL95

MAY95 JUN95

MAR95 MAR95

M,t,R95

AUG95 JUL95

JUN94 AUG94

FEB95 AUG94

JUN95 JUL95

0Cf95 NOV95

SEP94 MAR95

M,t,R95 OCT94

DEC93 J,t,N94

DEC93 J,t,N94

AUG95 AUG95

M,t,Y96 FE896

i .. ,,,ORIG. CRITICAL ACT. 1zzzz1PROJECTED ACTIVITY *-BASELINE MILESTONE .-ACTUAL MILESTONE ,..-PROJ'TED CRITICAL MS

Page 38: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 1.1.4 4.4.4.1 4.2.1 2.1.4 Accomplishments 4.4.4.1

4.2.1 2.1.4 Issues and Concerns 1.1.4

4.4.4.1

2.1.4

Corrective Action 1.1.4

4.4.4.1

2.1.4 Condition POC

MEDIUM ENERGY BOOSTER (MEB)

To provide an accelerator which will accelerate protons from 12 Ge V /c to 200 Ge V /c for injection into the HEB and to provide test beams, on a schedule to meet major milestones. Description MEB System MEB Accelerator R&D Medium Energy Booster Conventional Construction (including beam transfers to HEB bored tunnel for Test Beam)

Issued 3A specifications for formal review. Completed draft of Preliminary Design requirements for MEB conventional construction. MEB dipole and quadrupole magnet designs are under evaluation at Fennilab. Started work on the kicker power supply requirements and the design of the MEB central LCW cooling plant. Continued preliminary design requirements with the working group.

Overall MEB schedule shows criticality due to Test Beam Area Commissioning time to meet MEB Test Beam A vaailable milestone. 1. Ministraight space extremely tight. 2. Continued concern over main magnetic element design. Projecting 6 month schedule slip in issuance of construction Notice to Proceed but no slip i projected BOD date versus Baseline date.

Review commissioning plan - probable logic revision to allow overlap of MEB and Test Beam Area commissioning to preserve both Level 1 milestone dates. 1. Focused attention on space budget by Mechanical Engineering. 2. Possible minor magnet relocation. None. No technical system impacted as all BOD's are projected to be met. Green Rod Gerig (ADOD); Ted Kozman (ASD); Jack Clifton (CCD) DA TE: August 15, 1991

Page 34

• • • •

Page 39: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Superconducting Super Collider LONG TERM COMPARAT[VE SUMMARY BARCHART Baseline Master Schedule• Ver. 12. Rev. 7

Network Stetu• Date• 21 JUL91 TMR Report: MEB w/ Level 1&2 Mi I es tones SSCL REVIEW SUMMARY BY WBS Greohic Produced bv PMO on 12AUG91 (Calender I• in FIScal Ye• r 9) Or••tnt ID1 ttEl·Sun

llBS NUHBER WBS/COOE DESCRIPTION II 1991 1992l1993l1994l1995l1996l1997l1998l1999 20001 BASELINE PROJECTED FIN[SH FINISH

I. 01. 04 MEB SYSTEM I I I I I I I I I I SET COORDINATES• MEB I . ,M I I I I I I I I I APR91 01APR91 A

I I I I I I I I I I POWER SYSTEMS JUN96 JUN96

I .///////////////////////A

I I I I I I I I I DIPOLE MAGNETS

I ///////////////////////~ I I I APR96 JUN96

I I I I I I ,·

OUAORUPOLE MAGNETS I ///////////////////////,,!' I I I I APR96 JUN96

I I I I I RF SYSTEMS I

I,

I I I I MAY96 MAY96 .. 11-11111111111111,

i I I I I I I I I I I UTILITIES AUG95 AUG95 ////////////////////11' '

I ' I " ' I I I ' I I I I : VACUUM : I : : : l/ZZZZZZ/ZZ///ZZZ/h APR96 JUN96 i I I I I I ' . . I . I . . I . I . .

INSTRUMENTATION MAY96 JUN96 i

I ///////////////////////A

I I I I i

I I I I I

I z z z z z z z z z z z z z z z z z z ~1 · INSTALLATION I I I I I I

APR96 JUN96

I I TESTING I I I I :~: I I I I JUN96 JUN96

I

2. 01. 04 MEDIUM ENERGY BOOSTER !MEBl I I I I I I I I I I I MEB• FACILITY COMPLETE I I I I fM2. I I I I I JUL94 JUL94

I I I I I I I I I i CONVENTIONAL CONS TR. DESIGN & CONSTRUCTION .JUL94 .JUL94 I /////////////t I I i i I i I

4.01 ACCELERATOR PRE-OPERATIONS I I ! I I I ! I I

I I I I I I I I I I I

: "Ml MEB START COMMISSIONING I j I I j I I I I JUN96 JUN96

' I i,12 . ' I I I I I I I I I MEB COMPLETE COMMISSIONING JAN97 DEC96

: I I I I I I

'* I I I MEB TEST BEAMS AVAILABLE I '~M'. JAN97 MAR97

i I I I I I I I I I ! COMM! SS ION I NG ·9J· OCT96 OEC96 ' I I I I I I I I I

: I I I I I I I I I I i 6 OPERATIONS

i I I I I I I I I I OPERATIONS I I I I I I I I / / / / / , , /

, SEP99 SEP99

11 1991 1992 1 1993 1 1994 I 1995 I 1996 I 1997 I 1998 1 1999 2000 I

BASELINE ACTIVITY ACTUAL ACT IV I TY rzz41PR0J. CRITICAL ACT. 0-0RJG. CRITICAL MS \TPROJECTEO MILESTONE

i;;'' ! ORIG. CRITICAL ACT. I z z z z I PROJECTED ACTIVITY *-BASELINE MILESTONE .-ACTUAL MILESTONE .,-PROJ'TED CRITICAL MS

Page 40: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

4.2.1

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

HIGH ENERGY BOOSTER (HEB)

Meet the overall Laboratory goals to start commissioning prior to FY99.

Description

Accelerator R&D

Started work in preliminary design and the 3A and 3B specifications.

None.

None.

Green

Dave Johnson (ADOD); Ted Kozman (ASD) DA TE: August 15, 1991

Page 36

• • • •

Page 41: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Superconducting Super Collider

Network Stetu• Date• 21JUL91 Greohic Produced bv PMD on 12AUG91

TMR LONG TERM COMPARATIVE SUMMARY BARCHART

Report= HEB w/ Level 1&2 Milestones

Ba•el one Ma.ter Schedule! Ver. 12, Rev. 7 SSCL REVIEW SUMMARY BY WBS

was NUMBER WBS/CDDE DESCRIPTION

I .01.os HEB SYSTEM

SET COORDINATES• HEB

HEB START INSTALLATION

POWER SYSTEMS

CORRECTION MAGNETS

SPOOL PIECE

(Calendar I• in Fi•cel Year•)

I 91 11 99211 99311 99411 99sl1 996l1 99111 99811999200012001 I 02 I ' I ' i ' i ' I ' I I ' i I I I I i, I I I I I 11'., I I I I I

///////////// 7777////////>AI I I I j I 1

1vzzzzzzzzkJ I j j j I

I I : 'r 7 z. 7 /(I 7 7 7 7 7 7 ) /I , I . I I 111.

i I I lzzzzz/::;;::;;~zzz~ I I ; UTILITIES I I I :lzzzzzzzzzzzk I .. I I I I

CRYOGENICS

RF SYSTEMS

BASELINE 0ROJECTED FINISH FINISH

APR91 29MAR91

AUG96 JUL96

JUN98 SEP98

MAY96 SEP96

NOV96 FEB97

JUL97 MAR97

FEB98 APR98

APR97 MllY97

llPR98 MAY98

JUN98 JUN98

A

I vAcuuM I I I : : I z z z z z z z z z z z z z z z z'r I I I I I INSTRUMENTATION I zzzzzzzzzzzzzzzzzzzl I I I I lr----t---IN_S_T_AL_L_A_T_IO_N ______________ 1--~~:~L.:..l:_,_,........._,_~...,...~·~·~'=Z~Z~Z~Z~Z~Z~Z=/d/=Z~Z~Z~z~z~zdz~}=a+-:-.....,.....,.---,-,-.,.--c-i---;---;-,-+.-r-r....,.--f-JU_N_9_8_+s-E_P9_8_---4

1.02.02 HEB MAGNET PRODUCTION I : I : I I I I I : I : I : I : I CONTRACT AWARD

DIPOLE MAGNETS : *.vM~ : I I I I I I I I I I SEP91

AUGO!

NOV91

JUN98 ' 1~' ~...,.._...,...~~..,....,....,.....-.-.-r...,....,......m----1____,il . r z z z z z z z z z z z z z z z z z z z ; z z z z z z a. 1 I l~---1-~0~U~A~O~RU~P~O~L~E~M~A~G~N~ET~S~-----------L_:.___~~/~~//~/~/~~//~/~~//~/~~//~/~~,~/-'~,~~/,~/~~,,~/~~,~/?;;;f'_t_:_l_:_~·~l_:.___-'--.!'-~'~~·~'_:.___..:____:_~~JU~N~98~_J:J~U~N9~8---l : 2. 0 [. 05 HEB I I I I I I I I ' I ' I ' I

APR96 APR96 I ST BOD HEB. H20 EAST TO H60 I 1· I I I ~M2I I I I I I

I 2NO BOD HEB. H20 WEST TO H60 i I I ~ ' I I I I JUN96 JUN96

it-----t--c_o_N_v_EN_T_1_o_NA_L_c_o_Ns_T_R_._o_E_s_1_GN_&_co_N_s_T_Ru_c_T_1_o_N_-J-_~~1--·_,_:_.;..l_:_~"=zd}=2~·=z~z='z~z~z~z~z=zdz=z~;~:~i1'--_·~i _ ___.::_.L.:.l-,-~·~1 -.,......,·-~1 ....,...~·~1 --,--,.--l-oE_c_96_-+J-AN_9_r_---4 ACCELERATOR PRE-DPERAT IONS ' '1 ' '1 II II I 1' ' '1 JM! :11 ' '1 '1'

HEB START COMMISSIONING \J

HEB COMPLETE COMMISSIONING I I I I I I I I ~M2 I I I COLLI DER - START COMMISSIONING (8EAMl I I I I '~ 1· I I COMMISSIONING I I : I I : I ' I '8:' I '

4.01

i 4. 02. 0 I ACCELERATOR R&D : I ' ' I ' ' I : : ' I : ' ' I ' : l I : I ' I : I I : i POWER SYSTEMS I lzzzzzz ;zzzzzzJ I I I I . I I I I CORRECTIONMAGNETS ////////// .. !· I I I I I I I

SPOOL P 1 E CE r--.W..I ~l=z=z=z=z=z~z=z=z=z=z=z=z=%~1~: _LI -'--. I I I I I I INSTRUMENT AT I ON / / / / /,, / /,, / / , / / /7 -,; ,, ,'

SEP98 SEP98

MAR99 MAR99

MAR99 MAR99

MAR99 MllR99

JUL95 JUL95

NOV93 FEB94

DEC94 FEB95

MAR96 MllR96

I 6 OPERATIONS I I I I I : l : I : I I ' I ;.,_ __ __..___o_PE_R_AT_I_ON_s ________________________ --L.....---J...'+-1 __ ~1 ____ ·~1 ___ ·_+-1 __ ·~'----·~1.....,.. __ ~1---·41___.,.~ .... ij.-,~·-1~=--·41-,.,..,........._._sE_P_99 __ ~s-EP_9_9 __ -I

I 1991 I 1992 I 1993 I 1994 I 1995 l 1996 I 1 997 I 1998 I 1999 2000 I 2001 l 2002 I

11 ~1 --~1 BASELINE ACTIVITY

"''' 1 oRJG. CRITICAL ACT.

---ACTUAL ACTIVITY !" z z Ji PROJ. CR! TI CAL ACT.

1zzzz1PROJECTEO ACTIVITY *-BASELINE MILESTONE

0-DRJG. CRITICAL MS \TPROJECTED MILESTONE

.-ACTUAL MILESTONE .,.-PROJ"TEO CRITICAL MS

Page 42: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 4.2.1 2.1.6.2

Accomplishments 4.2.l

2.1.6.2 Issues and Concerns 4.2.1

2.1.6.2 Corrective Action 4.2.l

2.1.6.2

Condition POC

COLLIDER

Develop design and specification of 20 TeV Collider. Provide tunnel segments and servicing shafts in support of major milestones. Description 3B specifications, integrated schedule N15 Shafts and N15 to N20 Tunnel Segment N20 and N25 Shafts and N20 to N30 Tunnel Segment N30 to N45 Shafts and N30 to N45 Tunnel Segment

3A Specs sent out for signature. Work on integrated collider schedule progressing. CSA doing pilot project of modeling West Utility. Working groups formed to define requirements for Nl5 to N20 tunnel finish design. Working group formed to define specs for IR quad alignment. Workshops: Beam Loss Monitoring for the SSC. Held NIS Magnet Shaft Pre-Bid Meeting. Bids will be received on August 20.

I. Decision on niche spacing and extra dump switch required. 2. Information for IPS still missing. 3. Evaluate eliminating underground string test in lieu of 1st half-sector cooldown by 6 cell test. 4. Decision on CAD system to model West Utility interfaces required. Larger tunnel diameter may require change in tunnel elevation to provide required shielding at collider low cover areas.

1. Proceeding with niche spacing evaluation. CCB package needs to be prepared. 2. Continue work on ASD. 3. Discussion with ADOD and ASD, prepare CCB package. 4. Discussion with CCD and ASD. The A-E/CM has been tasked to perform a Collider Tunnel Elevation Study which will address tunnel elevation, construction costs associated with different elevations, and land areas affected at the low cover areas. 4.2.1 Yellow (3N3B Spec Schedule); 2.1.6.2 Green Rainer Meinke (ADOD); Tracy Lundin (CCD) DA TE: August 15, 1991

Page 38

• • • •

Page 43: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements

1.1.7.1

2.1.7

Accomplishments

1.1.7.1

TEST BEAMS

Design and build 200 GeV Test Beams and Calibration Hall.

Description

Test Beams

Test Beams Conventional Construction

Completed new optics design based on 40' separation between calibration areas.

Entered current (40') layout into the site-wide footprint database.

Began specification of conventional facilities. On track for September 1 completion.

2.1.7 Formed working group to develop Preliminary Design Requirements for test beam tunnel in MEB design and construction package.

Issues and Concerns None.

Corrective Action N/A

Condition Green

POC John McGill (AOOD); Jack Clifton (CCD) DATE: August 15, 1991

Page 39

Page 44: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

This page intentionally left blank.

Page 40

• • • • • • •

Page 45: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) ) )

ACCELERATOR SYSTEMS DIVISION

Page 41

Page 46: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A rus REPORT

DESIGN ~ PRODUCTION 0 CONSTRUCTION ~ RESEARCH & DEVELOPMENT ~ PART I

1. IDENTIFIERS:

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION Division Office

Accelerator Systems Mechanical Engineering Electrical Engineering

ld. DIVISION/OFFICE CONTACT RF Engineering Controls

TedKozman (ext. 3825) Instrumentation and Diagnostics le. DIVISION MANAGER Cryogenics Systems

TedKozrnan (ext. 3825) 2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL Division Office Green Green Green Green Mechanical Engineering Green Green Red Yellow Electrical Engineering Green Green Green Green

RF Engineering Yellow Green Yellow Yellow Controls Green Green Green• Green Instrumentation & Diagnostics Green Green Green Green Cryogenics Systems Green Green* Yellow Yellow

OVERALL DIVISION ASSESSMENT Green Green Green Green PREVIOUS DIVISION ASSESSMENT Green Green Yellow Yellow

• Change from last month.

Page 42

• • c c c c •

Page 47: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements

4.2.1

Aecom plishm en ts

)

ACCELERATOR SYSTEMS DIVISION

Description

Accelerator R&D

Held Critical design review for the ASST Spool Piece.

Held Preliminary Design Reviews for the LEB Energy Storage System Inductor, the LEB Ring Magnet Power Supply, and the ASST Cable trays and equipment racks.

Completed source selection on Klystron bids and submitted correction magnet packages to DOE for approval.

Additional funding to complete FY91 effort for ER string test approved.

Issues and Concerns Koch - PB/M-K installation interface requires much attention.

Corrective Action None.

Condition Green

POC TedKozman DATE: August 15, 1991

Page 43

)

Page 48: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

c

ACCELERATOR SYSTEMS DIVISION

FY91 Deliverables

WBS Milestone Baseline Schedule Current Projection

4.2.1 Start refrigerator fabrication for ASST Nov90 Nov9oA

4.2.1 Magnet supports - order prototype for ASST Dec90 DecwA

4.2.1 4cm prototype spool available for ER string Jun91 Aug91 test

4.2.1 Power supplies, quench protection Jul91 Feb91A procurement st.arted

1.1.2 LINAC RFQ procurement started Dec90 Dec90A

1.1.2 Start procurement of klystrons and power Feb91 Feb91A systems

1.1.2 LINAC final design review Aug91 Aug91**

1.1.6 Start procurement of El cryoplant with the Nov90 Nov9oA ASST/MTL

1.1.6 Start corrector magnet procurement for collider Sep91 Jul91A

A Milestone complete

**Series of reviews: RFQ--4/91, CCL--11/91, DTL--12/92

c

Condition Appraisal

Complete

Complete

Red

Complete

Complete

Complete

Green

Complete

Complete

Page 44

Page 49: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

WBS

4.2.1

1.1.6

4.2.1

1.1.2

1.1.2

1.1.2

1.1.2

1.1.3

1.1.3

1.1.6

)

ACCELERATOR SYSTEMS DIVISION FY92 DELIVERABLES

Milestone Baseline Schedule Current Projection

Two Spools completed for ASST Mru92 Dec91

Cryogenic 4 K Plant - Commissioning Apr92 Apr92 Complete

Accelerator Systems available for Cooldown Apr92 Apr92 for ASST

Start SCL Procurement for Linac Oct91 Nov91

Start DTL Fabrication for Linac Oct91 Feb92

Linac RFQ Completed Jul92 Jul92

Delivery of Klystrons and Power Systems Jul92 Jul92

LEB Magnet Engineering Complete Dec91 Dec91

Start Procurement Process for LEB Jun92 Jun92 Dipole/Quadrupole

E2 Cryoplant - Start Procurement Jun92 Jun92

Condition Appraisal

Green

Green

Green

Yellow

Red

Green

Yellow

Yellow

Green

Green

Page 45

Page 50: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

This page intentionally left blank.

Page 46

• • • • •

Page 51: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) ) )

MAGNET SYSTEMS DIVISION

Page 47

Page 52: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A TUS REPORT

DESIGN 181 PRODUCTION 0 CONSTRUCTION 0 RESEARCH & DEVELOPMENT 181 PART I

1. IDENTIFIERS:

la. PROJECT TITI..E/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORG ANIZATION(S)

Magnet Systems Division Engineering Test Production

ld. DIVISION/OFFICE CONTACT Quality Assurance Business Management

Ken Mountain (ext. 1161) Fenni National Accelerator Laboratory Lawrence Berkeley Laboratory

le. DIVISION MANAGER Brookhaven National Laboratory Space System Division

Tom Bush (ext. 2023) Westinghouse Electric Corporation

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL WBS 1.2.1 Program Management Green Green Green Green WBS 1.2.2 HEB Magnets Green Green Green Green WBS 1.2.3 Collider Ring Magnets Green Green Green Green WBS 1.2.4 Magnet Equipment & Tooling Green Green Green Green WBS 4.2.2 Magnet R&D Green Green Green Green

OVERALL DIVISION ASSESSMENT Green Green Green Green PREVIOUS DIVISION ASSESSMENT Green Green Green Green

Page 48

c c c c c • c

Page 53: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) ) )

DIVISION PROJECT ST A TUS REPORT PART I

2b. DIVISION MANAGER'S NARRATIVE HIGHLIGHTS

1.2.1 PROGRAM MANAGEMENT

MAGNET SYSTEMS DIVISION

Developing schedules to comply with the CDM program SSCL functional resource projections. Loaded budgets in Cobra at the work package

level and identified the earned value.

1.2.2 HEB MAGNETS

Dipole Magnets: Preparations for proposals evaluation underway. SEB nominated and briefed. Released formal RFP.

Quadrupole Magnets: Finished final CEN/SACLA Y draft subcontract. Submitted draft subcontract to France for review and comments.

1.2.3 COLLIDER RING MAGNETS

Collider Dipole Magnets: Definitized contract with GD and WEC executed effective July 12, 1991. Completed negotiation for WEC

involvement at BNL: Submitted contract files to DOE for review/approval.

Quadrupole Magnets: Definitized contract with Babcock & Wilcox executed July 8, 1991.

1.2.4 MAGNET FACILITIES EQUIPMENT AND TOOLING

MDL: The coil winding machine was setup and debugged at leased facility. First run of QSE cables have been wrapped.

MTL: Feed can specification completed and released for procurement. Software ready for test of rotating coil field harmonic system at BNL.

4.2.2 MAGNET R&D

FNAL: All coils (inner and outer) for magnets DCA 311 through DCA 315 have been wound. Magnets DCA 312 has completed final end

assembly. DCA 311 is in yoke and skinning. GD has full complement of 26 at the FNAL site.

BNL: First dipole being assembled.

LBL: Completed magnet QCC 401 and shipped to SSCL.

SSCL: Completed practice winding for DSA 101.

Page 49

)

Page 54: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

1.2.2.l

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

MAGNET SYSTEMS DIVISION

HEB Dipole Magnets

Provide reliable HEB Dipole Magnets on schedule and within budget.

Description

HEB Dipole Magnets

Received HEB Dipole Magnets Proposals on July 29, 1991.

1. Lack of finalized level 3A and B spec is critical.

2. FY92 budget allocation compared with SSC and subcontrnct task requirements.

1. Provide level 3A and B specifications.

2. Revise budget allocation or modify HEB schedule/task requirements.

Green

Dave Fortunato

c

DATE: August 15, 1991

Page 50

• c c

Page 55: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) )

Goal WBS Elements 1.2.2.2 Aecom plishments Issues and Concerns

Corrective Action

Condition

POC

MAGNET SYSTEMS DIVISION HEB Quadrupole Magnets

Provide reliable HEB Quadrupole Magnets on schedule and within budget.

Description HEB Quadrupole Magnets Finish final CEN/SACLA Y draft subcontract and shipped to France for review. I. Lack of level 3A and B specifications are critical. 2. Formal relocation policy approval. 3. Completion of contract with CEN/SACLA Y.

I. Provide level 3A and B spec.

)

2. Establish an approved relocation package for SSCL personnel moving to CEN/SACLAY.

3. Work with CEN key decision makers. Green

Dave Fortunato DATE: August 15, 1991

Page 51

Page 56: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal WBS Elements 1.2.3.1 Aecom plishments

Issues and Concerns

Corrective Action

Condition

roe

c

MAGNET SYSTEMS DIVISION 15 Meter CDM/13 Meter CDM

Provide reliable collider dipole magnets on schedule and within budget. Description WBS Elements 15 Meter CDM 1.2.3.2

Description 13 MeterCDM

General Dynamics, leader, and Westinghouse, follower, contracts were definitized effective July 12, 1991. Conducted the first monthly program reviews with General Dynamics. Conducted technology transfer session at FNAL for leader/follower. Completed negotiations for industry involvement at BNL in magnet assembly and provided contract files to DOE for review and approval. Obtained DOE approval to proceed with actions to have leader procure follower tooling, cryogenic plant and certain test instrumentation. Conducted a number of detailed technical meetings with leader relative to contract start. I. Hiring of a subcontract administrator and support personnel sufficient to support these major contracts. 2. Ability of the SSCL to support the review of subcontractor procurement actions without impact to schedule. 1. Continue to bring program requirements to management attention. 2. Test procurement review process with initial subcontractor purchases and adjust process and resources as required. Green

Herb Trenham DATE: August 15, 1991

Page 52

• c c • c

Page 57: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

1.2.3.3

Aecom plishments

Issues and Concerns

Corrective Action

Condition

roe

MAGNET SYSTEMS DIVISION Collider Quadrupole Magnets

Provide reliable collider quadrupole magnets on schedule and within budget.

Description

Collider ring Quadrupole Magnets

Issued definitive contract.

Conducted technical and management interface meetings.

Completed curing, collaring and yoke/skinning tooling presses review and provided recommendations to B& W for incorporation prior to release of RFP' s.

Initiated activity to support the issue of compliance with ASME boiler and pressure codes.

Need to estimate impact on program of compliance with ASME boiler and pressure codes.

None.

Green

Sol Shapiro DATE: August 15, 1991

Page 53

Page 58: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

1.2.4.1

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

MAGNET SYSTEMS DIVISION MDL Tooling

Equip the Magnet Development Lab (MDL) with tooling to support magnet production plans.

Description

MDL Tooling

Cable wrapping machine (ordered form dour) was set up in a leased facility in Waxahachie. Debugging is complete and first run of QSE Cable has been wrapped.

Design of long Quad Collaring Press remains on hold while the current concept of using the Dipole Collaring is evaluated.

Decision made by Engineering/Production on lack of need for long quad collaring press. The press should be eliminated from the tooling schedule.

Green

Ron Wood for David Bailey DATE: August 15, 1991

Page 54

• •

Page 59: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

2.4.2.2

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION Magnet Development Lab (MDL)

Support MSD PBOD of April 1, 1991 and a BOD of August 1, 1991.

Description

Magnet Development Lab (MDL)

Exterior skin complete; interior finish proceeding.

Interior CMU walls and studs for second floor drywall under construction.

Beneficial occupancy: High Bay August 15, 1991; Offices September 15, 1991.

Interim electrical power (Hill County).

Fire pumps scheduled delivery September 20; installed September 30.

Final negotiations on large modification 13.

Expedite and monitor resolution of remaining issues.

Yellow (Cost)

Craig N. Trimble DATE: August 15, 1991

Page 55

Page 60: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

1.2.4.2

Aecom plishments

Issues and Concerns

Corrective Action

Condition

roe

MAGNET SYSTEMS DIVISION MTL Equipment and Tooling

Design and test the measurement and control instrumentation which will be used to evaluate superconducting magnet perfonnance in the Magnet Test Laboratory (MTL).

Description

MTL Equipment and Tooling

Isolation amplifiers successfully tested on Rev. 2 PC boards.

Feed can specification completed and released for procurement.

Prototype cryogenic termometry instrumentation and software now running (test planned at final in August).

Software ready for test of rotating coil field harmonic system at BNL calibration facility.

1. Installation of LHe refrigerator in MTL conflicts with MTL construction schedule.

2. 33mm ID for CDM beam pipe impacts magnet measurement instrumentation design.

1. Negotiation ongoing with Koch for joint occupancy of MTL during construction.

2. Evaluate options for reduced instrumentation size and alternate warm bore designs.

Green

Mark Coles DATE: August 15, 1991

Page 56

c • •

Page 61: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

2.4.2.1

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION Magnet Test Lab (MTL)

Support MSD with a BOD of April 1, 1992 and a PBOD of January 1, 1992.

Description

Magnet Test Lab (MTI..)

Title II design, 100% completed review. Title II - 100% steel package in bid period. CCD incorporated in the MTI.. bid package accelerated completion dates of March 15, 1992 for MTI.. Service Building and July 15, 1992 for substantial completion of the MTI.. building. Funding for technical systems elements, Refrigeration Area, Compressor Building.

Joint MSD/CCD CCP approved action for additional technical and conventional funds; CCB set for August 8.

Yellow (Schedule)

Craig N. Trimble DATE: August 15, 1991

Page 57

)

Page 62: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

4.2.2.3

Accomplishments

Issues and Concerns

Corrective Action

Condition

roe

• •

MAGNET SYSTEMS DIVISION

2.5 Micron Conductor

Continue the development of 2.Sµm conductor in support of the HEB Magnet Program.

Description WBS Elements Description

Continue process development for 2.Sµm 1.2.2 Supply prototype conductor for HEB magnet conductor. programs requiring 2.Sµm conductor

Completed IGC/ASI negotiations process in development, if successful, allows 2.Sµm fabrication for the same cost as 6µm.

Contract preparation in process.

Supercon negotiations are stalled. Continuing discussions to reach rational price agreement.

Hitachi negotiations scheduled for August. DCAA audit completed.

1. Contract preparation is difficult in parallel with 6µm workload.

2. Long delays in contract approval process may impede the schedule.

3. Premature to kill 2.Sµm program in light of JGC/ ASI process potential.

1. Relieved SCA of all responsibility except for wire and cable procurements.

2. Providing direct support to SCA by members of conductor group for document preparation, etc.

3. Continue 2.Sµm program for this year with IGC/ASI, as a minimum, to verify if new process yields manufacturable results (three full-size billets already in process at IGC on IR&D, first yielded successful results).

Green

Don Capone DATE: August 15, 1991

Page 58

• • • •

Page 63: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal WBS Elements 4.2.2.3

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

MAGNET SYSTEMS DIVISION

6 Micron Conductor

Qualify conductor vendors for the SSCL Magnet Programs requiring 6µm conductor. Description WBS Elements Description Complete process optimization to ensure 1.2.3 Supply prototype and preproduction adequate fabricability conductor for magnet programs requiring

6µm conductor Doe approval for SEI subcontract received July 161h. Work has begun. AISA approval pending. Remaining contracts in final review. Continued technical reviews as required by contract. TSC reviewed week of July 23, IGC review will occur in August (this is the last review to perfonn). Vendor liaison offers accepted, one fluent in Japanese. Two started this month, final liaison starts August 9th. Already making good progress toward program monitoring. I. Still behind the curve on contract preparation, but things are improving. 2. Worst case schedule of August 1st start dates is not achievable. This will now reduce the two months of float available

for the CDM Cable deliveries. 3. Long lead time required for foreign travel makes rapid monitoring of problems difficult. Regular technical review not

a problem. I. Emphasis on first inner and outer subcontracts to support CDM program. 2. New preliminary CDM schedule indicates October 1992 for prototype start date (originally August 1992). This may

provide extra float. Projected first deliveries still two months ahead of CDM requirements. 3. Putting in foreign travel requests now for anticipated travel requirements. Green

Don Capone DATE: August 15, 1991

Page 59

Page 64: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

MAGNET SYSTEMS DIVISION Major Project Milestones

WBS Milestone Baseline Schedule Current Projection

1.2.3 CDM Authorization to incur costs Nov90

1.2.3 Full-rate production contract awarded on Apr94*1 collider magnets

1.2.3 Start first half sector CDM delivery from Apr94*1 vendor plant

* 1 CCB action in process to modify baseline schedule dates to reflect actual work schedule.

*2 Note that GD did not incur costs until May 91.

A Indicates actual date.

• • • •

Nov90 A*2

Jan95

Jul94

Condition Appraisal

Green

Green

Green

Page 60

Page 65: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

WBS

4.2.2.2

1.2.3.1

1.2.3.1

1.2.4

4.2.2.3

1.2.3.l

1.2.3.3

4.2.2.2

1.2.3.1

1.2.4

A Actual

MAGNET SYSTEMS DIVISION FY91/92 Deliverables

Milestone Baseline Schedule Current Projection

Complete Testing of 1st Lab Prototype Quad May91 May91A Cold Mass

Start GD assembly of dipoles at FNAL Jun91 Jun91A

First Scm Long Magnet Assembled Sep91 Sep91

Start Magnet Lab Tooling Procurement Oct90 Oct90A

Collider S/C Dipole Magnet Cable Vendor Jan91 Jan91A Qualification program started

CR Dipole Development started in Industry Feb91 Apr91A

CR Quad Development started in Industry Apr91 Jun91A

Quad string test delivered to ASST Mar92 Mar92

All string test delivered to ASST May92 May92

Complete Installation of Magnet Lab Tooling Sep92 Sep92

Condition Appraisal

Green

Green

Green

Green

Green

Green

Green

Green

Green

Green

Page 61

Page 66: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

COLLIDER DIPOLE MAGNET MILESTONES

CDM Milestone Baseline Finish Projected Finish

Contract Negotiations Complete Mar91 Mar91A

Contract Award - Letter Mar91 May91A

Technology Transfer Start Apr91 Apr91A

Contact Award (Definitized) Apr91 Jul91A

Industry Team at FNAL May91 Apr91A

Industry Team at BNL Jun91 Aug91A

System Design Review Mar92

Preliminary Design Review Mar92

1st Prototype Magnet Start Oct92

1st Prototype Magnet Complete Mar93

Last Prototype Magnet Complete Nov93

1st Preproduction Magnet Start Nov93

1st Preproduction Magnet Complete Jan94

Critical Design Review Feb94

LRIP Readiness Review Apr94

Last Preproduction Magnet Complete Jun94

First LRIP Magnet Shipped Jul94

Production Readiness Review Nov94

Last LRIP Magnet Shipped Jun95

Annex III Award Jan95

Production Phase Start Jun95

Last CDM Delivery Jun98

A Actuals Page 62

• • • • •

Page 67: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

CONVENTIONAL CONSTRUCTION DIVISION

Page 63

Page 68: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A TUS REPORT

DESIGN ~ PRODUCTION 0

CONSTRUCTION ~ RESEARCH & DEVELOPMENT 0 PART I

1. IDENTIFIERS:

la. PROJECT TITLE/NUMBER (DE-AC02-89ER40486) lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZA TION(S) CCD Division Office

Conventional Construction Program Management Department ld. DIVISION/OFFICE CONT ACT Requirements Planning Department

Robert K. Tener Engineering & Design Department le. DIVISION MANAGER Construction Department

PB/MK Team Jon R. Ives TNRLC

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL 2.1.1 CCD Administrntion Green Yellow Green Yellow 2.1.2 thru 2.1.5 Injector Green Green Green* Green

2.1.6 Collider Green Green Yellow Green 2.2 Experimental Halls Green Green Green Green 2.3 Infrastructure Green Green Green Green 2.4 Campus Green Green Yellow Green 2.5 A-E/CM Green Red Green Green

OVERALL DIVISION ASSESSMENT Green Green Yellow Green PREVIOUS DIVISION ASSESSMENT Green Green Yellow Green

* Change from last month.

Page 64

• • • • • • • •

Page 69: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 2.0

Accomplishments

2.1

2.2

2.3

2.4

2.5

Issues and Concerns

Corrective Action

Condition

roe

CONVENTIONAL CONSTRUCTION DIVISION Conventional Facilities

Description Conventional Facilities

Received PMO budget for staffing CCD to 61 positions by September 1992. Received Linac Title I design for review. Started LEB Title I design. Issued Invitation to Bid for N15 Magnet Shaft. Awarded instrumentation subcontract for Exploratory Shaft.

Submitted Tier II Schedule for IR4 and IRl Halls to PMO.

Completed Title II designs for Sewage Treatment Plant (Phase II) and for Hoyt, Arrowhead and N15 Perimeter Roads. Completed Environmental Compliance Plan for N15 shafts and first tunnel segment, for Linac, and for Exploratory Shaft.

Completed MTL Title II design. Completed West Campus Preliminary Design Requirements Document.

PB/MK project management and administration provided 37 task completions and/or continuations.

1. Development of integrated cost and schedule systems.

2. Baseline cost estimate does not cover A-E/CM PM&A costs.

1. PMO activities underway to develop integrated cost and schedule systems.

2. Change Control action to reflect A-E/CM PM&A costs to cover scope of contract as negotiated.

Green

R.K Tener DATE: August 15, 1991

Page 65

Page 70: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

• •

Goal

WDS Elements 2.3.2 2.3.3

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION NlS (El) Infrastructure

Provide necessary infrastructure to support BOD of each completed facility.

Description Infrastructure - Primary Infrastructure - Secondary

Draft Environmental Compliance Plan inventory/permits for LCW plant. Completed 100% Title II Final Design Plans for Phase II of Sewage Treatment Plant. Completed 100% Title II Final Design Plans for N15 Perimeter Road. Completed 100% Title II Final Design Plans for Hoyt Road. Completed 90% Title II Preliminary Design Plans for Nl5 Infrastructure. Accepted as Final Environmental Compliance Plan for Nl5 Shafts and Nl5 to N20 Tunnel. Completed 100% Title II Final Design Plans for Arrowhead Road. Access for Staking/Surveying/Testing Secured for HCEC Electric Line.

Baseline Cost Estimate. TNRLC condemnation of Parcel 156 could delay construction of Arrowhead Road.

Change Control Panel approved, action and forwarded to PM for identification of funding, the construction of Arrowhead Road and N 15 Sewage Treatment Plant, neither of which are in the BCE. TNRLC to expedite acquisition process for Parcel 156.

Green

Richard Wiebe DATE: August 15, 1991

Page 66

• • • • •

Page 71: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements 2.3.2 2.3.3

Aecom plishm en ts

Issues and Concerns

Corrective Action

Condition

roe

CONVENTIONAL CONSTRUCTION DIVISION Collider Infrastructure Other than NlS (El)

Provide necessary infrastructure to support BOD of each completed facility.

Description Infrasbllcture - Primary Infrasbllcture - Secondary

Environmental Compliance Plan inventories and permits drafted for N20, 25, 30, 35, 40, 45, shafts and tunnels N20 to N45.

Off-site road improvements (county roads).

Action plan to be developed by Infrastructure Steering Committee (SSCL, DOE, 1NRLC, PB/MK).

Green

Richard Wiebe DATE: August 15, 1991

Page 67

)

Page 72: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 2.3.2 2.3.3

Accomplishments

Issues and Concerns

Corrective Action

Condition

roe

• •

CONVENTIONAL CONSTRUCTION DIVISION West Campus (Injector) Infrastructure

Provide necessary infrastructure to support BOD of each completed facility.

Description Infrastructure - Primary Infrastructure - Secondary

Draft Environmental Compliance Plan inventory/permits for LEB. Began evaluation of access roads to accommodate most recent plans for Central Office, Linac, & IR's. Accepted as final the Environmental Compliance Plan for the Linac and the Exploratory Shaft. Significant progress on HVAC alternatives study - final to be complete August 15, 1991. Work on cooling pond studies advanced.

Initial analysis of road alternates indicates that an adequate system should be achievable close to baseline; needs final detailed estimate to confirm.

Estimate underway.

Green

Richard Wiebe DATE: August 15, 1991

Page 68

• • • • •

Page 73: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goals

WBS Elements 2.1.6.26

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION Exploratory Shaft (IRl Location)

To provide large scale, in-situ, Lesl input for the design of underground structures in Eagle Ford Shale rock strata and detector support systems. To provide shaft access to the ulilily bypass and/or experimental facilities, at the IRl location. Final function and finish­out to be determined.

Description Exploratory Shaft (IR 1)

Sile preparation for arrival of drill rig. Shaft collar construction underway. Geotechnical Instrumentation subcontract negotiated and signed. Instrument procurement underway.

None.

None.

Green

Chris Laughton DATE: August 15, 1991

Page 69

)

Page 74: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements 2.2.2.1.l

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION IR4 Experimental Facilities; Underground Housings

Conceptual Underground Design of the IR4 Experimental Facility Housings.

Description "IR4" Underground Hall and Shaft Structures

Floor Load Conceptual Design requirements redefined for SOC. New scheduling being input to IPS. Completed new estimate of conventional facility costs. Significant scope and cost increases over baseline for Experimental Facilities.

Cost and scope reconciliation action being planned.

Green

Chris Laughton DATE: August 15,1991

Page 70

• • • •

Page 75: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) )

Goals

WBS Elements 2.5

Accomplishments

Issues and Concerns

Corrective Action

Condition

POC

CONVENTIONAL CONSTRUCTION DIVISION Site Development (Master Plan)

Develop a fully coordinated Site Development Plan to guide project planning and design.

Description Site Development Plan (Master Plan)

Transmitted comments from SSCL, SSC Project Office and TNRLC on Site Development Plan to A-E/CM.

Incorporating review comments and final printing of the Site Development Plan.

Site Development Plan to be printed and distributed in August.

Green

Robert W. Sims DATE: August 15,1991

Page 71

Page 76: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

• •

CONVENTIONAL CONSTRUCTION DIVISION

Major Project Milestones

WBS Milestone Milestone Level Baseline Schedule Current Projection 2.0 Start Civil Construction 1 Mar91 Mar91A 2.4.2.2 Magnet Development Lab BOD 2 Apr91 Sep91 2.4.2.1 Magnet Test Lab BOD 2 Mar92 Jun92 2.1.2 Linac Construction Start 2 Aug91 Feb92 2.1.6.25 ASST Construction Start 2 Apr91 May91A 2.1.6.25 ASST BOD 2 Sep91 Oct91 2.1.6.2 Nl5 Magnet Shaft Construction 2 Mar91 Sep91

Start 2.1.6.2 N15 to N20 Construction Basic 2 Jul91 Jan92

Tunnel Start 2.1.6.2 N20 to N30 Construction Basic 2 Apr92 Apr92

Tunnel Start (Revised Baseline) 2.1.6.2 N30 to N45 Construction Basic 2 Apr92 Apr92

Tunnel Start (Revised Baseline) 2.1.3 LEB Construction Start 2 Apr92 Jun92 2.l.4 MEB Construction Start 2 Jul92 Jan93 2.3.2 Infrastructure, Campus Construction 2 Aug92 Oct91

Startl 2.3.2 Infrastructure, Injector Construction 2 Oct92 Dec91

Startl 2.2.2 Experimental Halls Construction Jun93 Apr93

Start

A Actual

* Change from last month. 1 Accelerated schedule, dependent on approval of accelerated funding.

• • • •

Condition Appraisal Green Red Red Red

Green Green Red

Red

Green

Green

Red Red

Green

Green*

Green

Page 72

• •

Page 77: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

A

*

CONVENTIONAL CONSTRUCTION DIVISION FY91 Deliverables

WBS Milestone Baseline Schedule Current Projection

2.4.2 MDL Completed (BOD - High Bay) Apr91 Aug91

2.1.6 ASST Construction Start Apr91 May91A

2.1.6 ASST BOD Sep91 Oct91

2.3.3 Infrastructure and Utilities Construction Start Apr91 Mar91A

2.4.2 MTL Construction Start Jun91 Aug91

2.1.2 Linac Facility Construction Start Aug91 Feb92

Actual

Change from last month.

Condition Appraisal

Red

Green

Yellow*

Green

Yellow

Red

Page 73

Page 78: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

WBS

2.1.6

2.3.3

2.4.2

2.1.3

2.1.4

CONVENTIONAL CONSTRUCTION DIVISION FY92 Deliverables

Milestone Baseline Schedule Current Projection

Collider-First Sector Construction Start Oct91 Jan92

N15 Roads Completed Oct91 Feb92**

MlL Completed (BOD) Mar92 Jun92

LEB Facility Construction Start Apr92 Jun92

MEB Facility Construction Start Jul92 Jan93

Condition Appraisal

Red*

Red**

Red

Red

Red

* Collider construction sequencing has been rescheduled. Baseline date revision approval and acceptance by PMO will eliminate Red condition. * * Phased completion will support MDL, ASST, and MTL as each is completed.

Page 74

• • • • •

Page 79: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

PHYSICS RESEARCH DIVISION

Page 75

Page 80: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A TUS REPORT

DESIGN 0 PRODUCTION 0 CONSTRUCTION 0 RESEARCH & DEVELOPMENT ~ PART I

1. IDENTIFIERS:

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZATION(S)

Physics Research Division SSC Library Services Id. DIVISION/OFFICE CONTACT Experimental Facilities Support

Experimental Systems-Detector R&D Newton Norman (ext. 6035) Experimental Systems-Detectors

le. DIVISION MANAGER Experimental Systems-Detector Computing SDC Collaboration--LBL

Fred Gilman (ext. 6113) GEM Collaboration 2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL SSC Library Green Green Green Green Experimental Facilities Support Green Green Yellow Green Experimental Systems-Detector R&D Green Green Green Green Experimental Systems-Detectors Green Green Green Green Experimental Systems-Detector Computing Green Green Green Green SDC Collaboration--LBL Green Yellow Green Green GEM Collaboration Yellow Yellow Red Red OVERAU DIVISION ASSESSMENT Green Green Green Green PREVIOUS DIVISION ASSESSMENT Green Green Green Green

Page 76

• • • • c

Page 81: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal

WBS Elements 4.6.3 5.1 Aecom plishments

4.6.3

5.1

5.2

5.3

Issues and Concerns

Corrective Action

Condition

POC

PHYSICS RESEARCH DIVISION

Provide required support to Laboratory divisions.

Description WBS Elements

Experimental Facilities Support 5.2 Detector R&D 5.3

Description Experimental Detectors Experimental Computing

The first draft of the SDC Experimental Facilities User Requirements (SEFUR) document was transmitted to the Conventional Construction Division.

Work is in progress on defining a test beam configuration for the SOC detector; the baseline hall was determined to be too small, and the beam-configuration will be modified to accommodate a larger hall.

Obtained DOE concurrence on 28 Memoranda of Understanding for SSC Detector Subsystems R&D.

A new collaboration, GEM, submitted an Expression of Interest (signed by more than 300 physicists from over 50 institutions) to propose a major detector complementary to SOC.

The Program Advisory Committee recommended a call for Letters of Intent for the second major detector. The SSCL staff reported on the civil construction schedule and the criticality of defining the experimental hall requirements by January 1992.

Completed design changes of each subsystem for the reconfiguration of the Physics Detector Simulation Facility (PDSF). Implementation of each subsystem is underway and on schedule, with approximately 50% of the implementation completed.

None.

None.

Green

N.Norman DATE: August 15, 1991

Page 77

Page 82: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

PHYSICS RESEARCH DIVISION Major Project Milestones

WBS Milestone Baseline Schedule Current Projection Condition Appraisal

4.6.3 Test beam configuration and coordination Feb91 Apr91A Yell ow (No impact on defined baseline expected)

4.6.3 Developed physics lab for detectors for test Feb91 Feb91A Green beam monitoring

4.6.3 Test beam optics defined. Apr91 Apr91A Green 4.6.3 Resource requirements for LOI detectors Dec90 Dec90A Green

defined. 4.6.3 Begin detector and support facilities design for Feb91 Feb9 l for SDCA Green

proposal stage. Dec91 for GEM Red (Could cause delays in proposal)

4.6.3 Develop detector assembly and installation Sep91 Sep91 Green schedules

5.2 Letters of Intent submitted from the Nov90 Nov9oA Green collaborations

5.2 PAC recommendations for large, general Dec90 Dec90A Green purpose detectors

5.2 Choose two large, general purpose detectors to Jan91 SDC Jan9IA Green be supported to full proposals GEM Red (Could cause delays

Dec (earliest) in defining overall experimental program)

5.2 Begin conceptual design reports for large Feb91 SDC Feb91A Green detectors GEM Red (Same as above)

Dec (earliest) 5.2 Prepare preliminary construction schedules Sep91 Sep91 Green

and drawings for detector subsystems 5.3 Acquire and install 500 MIPS of distributed, Mar91 Mar91A Green

UNIX-based computing hardware for detector simulation

5.3 Begin detector physics simulation work at Mar91 Mar91A Green SSCL

Page 78

A Complete

c . c c c c c

Page 83: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

WBS

4.6.3

A Complete

PHYSICS RESEARCH DIVISION FY91/92 Deliverables

Milestone Baseline Schedule Current Projection

Test beam configuration and coordination Feb91 Apr91A defined

Developed physics lab for detectors for test Feb91 Feb91A beam monitoring

Test beam optics defined. Apr91 Apr91A

Resource requirements for LOI detectors Dec90 Dec90A defined.

Begin detector and support facilities design for Feb91 Feb91 for SDCA proposal stage. Dec91 for GEM (earliest)

Develop detector assembly and installation Sep91 Sep91 schedules

Start prototype detectors for test beams Oct91 Oct91

Identify magnet alternatives for test beams Oct91 Oct91

Establish compliance with ES&H design Oct91 Oct91 criteria

Have full operation of detector Technical Oct91 Oct91 Information Center

Test beam facility requirements set Jan92 Apr92

Complete detector and facility design for Apr92 Apr92 proposal stage

Condition Appraisal

Yellow (No impact on baseline expected)

Green

Green

Green

Green Red (Could cause delays

in proposal)

Green

Green

Green

Green

Green

Green

Green

Page 79

Page 84: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

PHYSICS RESEARCH DIVISION FY91/92 Deliverables

WBS Milestone Baseline Schedule Current Projection Condition Appraisal 5.1 Develop wire alignment and tensioning Apr91 May9IA Yellow

devices for muon chambers Prototype chambers

constructed and gas mixtures tested

5.1 Develop prototype VLSI test subcircuits for Jun91 May91 Green front end electronic subsystems • New design of time to

voltage converter chip • Strawtube tracker chip

for level I trigger 5.1 Continue small test prototype calorimeter Sep91 Sep91 Green

modules for beam and radiation damage tests April 91A • BNL Liquid Argon

module in BNL beam. • Scintillator-plate module

made for Fermilab test.

May91 • Liquid Argon module

assembled at SSCL, beam test at BNL in June.

June 91A • Beam test of Scintillator-plate module at Fermilab

5.1 Continue testing prototype straw tube, fiber Sep91 Sep91 Green and silicon tracking test devices Mar91

Successful test of photon yield with 4 meter scintillating fiber

A Complete Page 80

• • • •

Page 85: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

WBS

5.2

A Complete

PHYSICS RESEARCH DIVISION FY91/92 Deliverables

Milestone

Letters of Intent submitted from the collaborations

PAC recommendations for large, geneml purpose detectors

Choose two large, general purpose detectors to be supported to full proposals

Begin conceptual design reports for large detectors

Prepare preliminary construction schedules and drawings for detector subsystems

Complete conceptual design reports for large detectors which include:

A. Establishment of detector hall rqmts.

B. Establishment of facility rqmts.

Complete PAC reviews for large detectors and associated facilities

Start procurement of magnet and steel for large detectors

Complete the detailed technical evaluation and review of large detector proposals

Baseline Schedule

Nov90

Dec90

Jan91

Feb91

Sep91

Nov91

Feb92

Mar92

Sep92

Current Projection

Nov90A

Dec90A

SDC Jan91A GEM

Dec (earliest)

Feb9 l for SDCA GEM

Dec (earliest) Sep91

Apr92

Jun92

Jun92

Sep92

Condition Appraisal

Green

Green

Green

Red (Could cause delays in defining overall

experimental program)

Green

Red (Same as above)

Green

Red (SDC proceeding; GEM could cause delays in defining

overall experimental program)

Red (Same as above)

Red (Same as above)

Green

Page 81

Page 86: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

.,

WBS

5.1

5.3

A Complete

PHYSICS RESEARCH DIVISION FY91/92 Deliverables/Milestones

Milestone Baseline Schedule Current Projection

Start Large SSC calorimeter modules Start prototype SSC detector tracking devices Initiate procurement of tooling for prototype SSC detector construction Develop VLSI circuits for front end electronics with radiation hard design Acquire and install 500 MIPS of distributed, UNIX-based computing hardware for detector simulation

Begin detector physics simulation work at SSCL

Acquire and install up to 4000 MIPS of distributed, UNIX-based computing hardware for detector simulation

Establish full physics simulation effort at SSCL

• • •

Apr-Sep92 Jan-Sep92

Sep92

Mar-Sep92

Mar91

Mar91

Sep92

Sep92

• •

Apr-Scp92 Jan-Sep92

Sep92

Mar-Sep92

Mar91A

Mar91A

Sep92

Sep92

Condition Appraisal

Green Green Green

Green

Green - More than 1000 MIPs on schedule and

within budget

Green

Green

Green

Page 82

Page 87: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

) )

LABORATORY TECHNICAL SERVICES DIVISION

Page 83

Page 88: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT STATUS REPORT

DESIGN 0 PRODUCTION 0 CONSTRUCTION 0 RESEARCH & DEVELOPMENT 0 PART I

1. IDENTIFIERS: 4.4

la. PROJECT TITLE/NUMBER DE-AC02-89ER40486 lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZATION(S)

Laboratory Technical Services TX- Technical Publications TH- Technical Support Management TJ- Facilities Engineering Services TK- Materiel & Logistics Services TL- Fabrication Shops

Id. DIVISION/OFFICE CONTACT TM- General Computing TN- Project Design Support

Jerry Davis (ext. 1788) TP- Communications TQ- Computer Operations

le. DIVISION MANAGER TR- Engineering Standards/Support TS- Metrology & Calibration Labs

E. Jack Story (ext. 5010) TT- Protective Services TU- Staff Services TW- Technology Transfer

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status GROUP TECHNICAL COST SCHEDULE OVERALL

OVERALL DIVISION ASSESSMENT Green Green Green Green

PREVIOUS DIVISION ASSESSMENT Green Green Green Green

Page 84

• • c • c c •

Page 89: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

Goal

WBS Elements

4.4

Accomplishments

LABORATORY TECHNICAL SERVICES DIVISION

Provide high quality technical support services, in accordance with the approved FY91 Scope of work, within manpower

and budgets.

Description

Laboratory Technical Services

Construction of Phase II, 175 offices, was completed. Laboratory and shops (100,000 square feet) bid documents were

completed. Installation of new 10 kva UPS was completed July 16 and connection of the telephone system to UPS is expected August 16.

Magnet inter-connect components and accelerator prototype spools were fabricated in the Interim Shops facilities.

The ASST offices at the N-15 site were established.

Issues and Concerns None.

Corrective Action None.

Condition

roe Green

Jerry Davis DATE: August 15, 1991

Page 85

Page 90: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

This page intentionally left blank.

Page 86

• • • • • •

Page 91: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

DIRECTORATE DIVISION

Page 87

Page 92: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

DIVISION PROJECT ST A TIJS REPORT

DESIGN 0 PRODUCTION 0 CONSTRUCTION 0 RESEARCH & DEVELOPMENT 0 PART I

I. IDENTIFIERS:

la. PROJECT TITLE/NUMBER (DE-AC02-89ER40486) lb. REPORTING PERIOD SUPERCONDUCTING SUPER COLLIDER LABORATORY July 1991

le. MANAGING DIVISION lf. PERFORMING ORGANIZATION(S)

Directorate Director's Office External Affairs

Id. DIVISION/OFFICE CONTACT Legal Counsel User's Office

Neil Baggett Environment, Safety & Health le. DIVISION MANAGER Planning

International Coordination Raphael Kasper Education

2. DIVISION MANAGER'S PERSONAL ASSESSMENT: 2a. Summary Status

GROUP TECHNICAL COST SCHEDULE OVERALL Director's Office Green Green Green Green External Affairs Green Green Green Green Legal Counsel Green Green Green Green User's Office Green Green Green Green Environment, Safety & Health Green Green Green Green Planning Green Green Green Green International Coordination Green Green Green Green Education Green Green Green Green

OVERALL DIVISION ASSESSMENT Green Green Green Green PREVIOUS DIVISION ASSESSMENT Green Green Green Green

Page 88

• • • • • •

Page 93: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

)

Goal WBS Elements 4.5.6 4.5.8 Accomplishments 4.5.6

4.5.8

4.5.9

Issues and Concerns Corrective Action Condition POC

DIRECTORATE DIVISION

To oversee and direct Laboratory activities Description ES&H International Coordination

WBS Elements 4.5.9

Description Education Office

Five Earthwatch students spent two weeks in the Office of Environment, Safety and Health (ES&H) learning about monitoring and mitigation of SSC environmental impacts. Conducted meetings to receive input from area city managers, superintendents from affected school districts, and Ellis County officials for monitoring the socioeconomic impacts of the SSC. The Office of International Coordination (OIC) is presently working to coordinate the upcoming US-USSR working group and technical group meetings. KEK in Japan requested a delivery schedule of all components in the list presented to the Japanese government by DOE. Discussions are well advanced regarding a possible Israeli in-kind contribution to the SSCL which could amount to $IM/year. The Laboratory received a letter from the Argentine Atomic Energy Commission indicating their interest in participating in the SSC. Education staff met with staff members from Governor Ann Richard's Office and the Texas Education Agency to discuss SSC participation in a state wide computer network called TENET (Texas Education Network). The Texas Higher Education Coordinating Board has awarded a third Carl Perkins grant to the University of Houston (Office of Technology) to facilitate the integration of SSC technology into community colleges within the state. An Adopt-A-Magnet workshop was conducted for elementary teachers in Hammond, Louisiana. Staff assistance funds for development of the Adopt-A-Magnet program have been requested in a proposal to DOE to accelerate and expand the program into fifteen states by the end of March 1992. SSC education staff met with education heads at SLAC and LBL, and toured facilities at the Exploratorium, the Lawrence Hall of Science, and Technology 2000. None. None. Green Raphael Kasper DATE August 15, 91

Page 89

Page 94: SSC PROJECT MONTHLY PROGRESS REPORT JULY 1991 · The July 1991 Monthly Progress Report consolidates divisional status reports by machine, as appropriate. Changes in conditions (red,

. \ • f • • • •