Sections and Cavity One section : 11 drift tubes A cavity is composed of sections of cavity One 4 sections cavity April 19, Eric Montesinos / CERN-BE-RF-SR
Citation preview
Eric Montesinos / CERN-BE-RF-SR
SPS point 3New RF building
LIU-SPS-200 MHz Power Upgrade
April 19, 2011
SPS 200 MHz RF power: some history
The RF-SPS started up in 1976 with two accelerating cavities (technical specs were written in 1971)
For the new role of the SPS as proton-antiproton collider, since 1980, there are four cavities operating @ 200 MHz in the SPS
April 19, 2011
2
Eric Montesinos / CERN-BE-RF-SR
201020001976TWC#1 / TX1 TWC#2 / TX2
199019801975
1978TWC#3 / TX3
1979TWC#4 / TX4
1980TWC#1 / TX1+TX2TWC#2 / TX3+TX4TWC#3 / TX5+TX6TWC#4 / TX7+TX8
RF amplifier
1 mWCoaxial transmission line125 to 160 meters
Accelerating cavity
Terminating loads
Configuration of one of the four 200 MHz power plant
1 MW
Sections and Cavity
One section : 11 drift tubes
A cavity is composed of sections of cavity
One 4 sections cavity
April 19, 2011
3
Eric Montesinos / CERN-BE-RF-SR
Cavities redistribution
2011 : 4 cavities2 x 4 sections
2 x 5 sections
+ 3 spare sections
2018 : 6 cavities2 x 4 sections
4 x 3 sections
+ 1 spare section
April 19, 2011
4
Eric Montesinos / CERN-BE-RF-SR
2011 amplifiers
Two ‘Siemens’ Amplifiers(2 x 1MW RF ~ 450 m2 +
100 m2)
Two ‘Philips’ amplifiers(2 x 1 MW RF ~ 500 m2 +
200 m2)
April 19, 2011
5
Eric Montesinos / CERN-BE-RF-SR
2018 : Proposed two new power amplifiers
Two new power amplifiers will be build :2 x 1.7 MW peak RF
Efficiency ~ 50 % ->2 x 3.4 MVA ~ 7 MVA peak
April 19, 2011
6
Eric Montesinos / CERN-BE-RF-SR
One line (input cavity ~120 to 180 m away)
Drivers:16 SSA 8 kW
From Beam Control
Final16 Tubes110 kW(g = 12 dB)
3 dB combiners and power loads
plus 120 to 180 m Coaxial lines
- 0.6 dB - 0.2 dB = - 0.8 dB
Tetrodes = 1.4 MW + 0.8 dB
= 1.7 MW / 16 = 110 kW
1/16 splitter
2018 : Proposed two new power amplifiers
Could be : 2 x 1.7 MW Klystron 2 x 4 x 450 kW Diacrodes 2 x 8 x 225 kW IOTs 2 x 8 x 225 kW tetrodes
Equivalent to ‘Siemens’ ~ 500 m2 + 200 m2
2 x 16 x 110 kW Tetrodes Equivalent to ‘Philips’ ~ 500 m2 + 200 m2
2 x 1800 x 1 kW SSA Equivalent to 10 x SOLEIL ~ 500 m2 + 200 m2
SOLEILamplifiers
April 19, 2011
7
Eric Montesinos / CERN-BE-RF-SR
New RF building
Point 3 is the best area even if we need a new building
New building between BA3 and BB3 in front of 929 RF workshop : Ground floor
20m x 25m = 500 m2 First floor, metallic:
10m x 25m = 250 m2
April 19, 2011
8
Eric Montesinos / CERN-BE-RF-SR
RF workshop
Siemens
Philips
800 MHz
Faraday Cage
Damper ?
New RF building
Amplifier study
Tunnel integration
New RF Building
April 19, 2011
9
Eric Montesinos / CERN-BE-RF-SR
RF amplifier
1 mWCoaxial transmission line125 to 160 meters
Accelerating cavity
Terminating loads1 MW
New RF Building
Project estimates
April 19, 2011Eric Montesinos / CERN-BE-RF-SR
10
Item StaffFTE years
Total price(FSU
included) kCHF
Building Civil Engineering(Michael Poehler)
Basement (30 x 30) m2
x 4000 CHF/m2
First floor (15 x 30) m2 x 2000 CHF/m2
2.5 4’500
Building Ventilation(Mauro Nonis)
based on Isolde last study 1.5 1’000
Electrical Network High Power(Joel Lahaye)
Study, documentations, HV transformers 2 x 2 MVA, HV cubicles, HV cabling,
HV accessories
1.5 800
Draft schedule
April 19, 2011Eric Montesinos / CERN-BE-RF-SR
11
StudiesMS
InstallBuild new hardware
Year 4Year 3Year 2Year 1 Year 5
BuildingServices
RF :
Building :
20172014201320122011 2015 2016 2018Year 6 Year 7
Tendering
Commissioning
Studies and authorizations
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 702000400060008000
100001200014000
01234567
Budg
et
FTE
year
Cavity re-arrangement
within a LS (>6 months)
Persons in charge
April 19, 2011Eric Montesinos / CERN-BE-RF-SR
12
BE-RF : Eric BE-Space manager : Paula Civil Engineering : Natasha, Michael Integration : Yvon, Frédéric CV : Mauro, … EN : François, … Transport : ? … Safety : Enrico, Cristiana, … Fire detection, alarms : Christophe
April 19, 2011Eric Montesinos / CERN-BE-RF-SR
13
Thank you very much
?