SPS 200 MHz RF Upgrade. Eric Montesinos LIU-SPS coordination meeting 06 June 2013. Intervenants. New BAF3 RF building. Building BAF3 Integration studies completed Enquiry ‘Etude Genie Civil’ sent out Final comments today Construction starts Fall 2013 Building ready mid-2015 all inclusive. - PowerPoint PPT Presentation
Citation preview
SPS 200 MHz RF Upgrade
Eric Montesinos
LIU-SPS coordination meeting 06 June 2013
Intervenants
15 August 2012 2LIU SPS RF
Dep-Group Persons
BE-RF Eric Montesinos, Charles Julie, SPS power team, Thomas Bohl, Wolfgang Höfle, Urs Wehrle, Elena Shaposhnikova, Philippe Baudrenghien
BE-ABP Ghislain Roy (BE space manager), Patrick Bestmann, Yannis PapaphilippouBE-ASR Emmanuel PaulatBE-BI Christian Boccard, Patrick OdierDGS-SEE Guillaume Fontana, Cécile PintoEN-CV Mauro Nonis, Glen MasonEN-EL Guillaume Gros, Joël Lahaye, Christophe CrombezEN-HE Caterina Bertone, Pascal Brunero, Serge Pelletier, Yann SeraphinEN-MEF Frédéric Galleazzi, Yvon Muttoni, David McFarlane, Antoine KosmickiGS-SE Luz-Anastasia Lopez-HernandezTE-VSC Paolo Chiggiato, Antonio MongelluzzoTE-MSC Jérémie Bauche
3LIU SPS RF
New BAF3 RF building
Building BAF3 Integration studies completed Enquiry ‘Etude Genie Civil’ sent out Final comments today• Construction starts Fall 2013• Building ready mid-2015 all inclusive
15 August 2012
Amplifiers
Drivers (SSA): MS completed : 17 companies selected TS written to be sent out soon (pending YL1530
decisions)• FC December 2013
Finals (SSA or Tetrodes): MS completed : 7 companies selected TS written Will be sent out once Driver will be
adjudicated• FC December 2013
Combiners (3 dB above 100 kW)• After Finals have been selected
Transmission lines (coaxial, 345 mm outer)• Same as Combiner
15 August 2012 4LIU SPS RF
Drivers16 SSA
Final16 PAs
3 dBcombinersand power loads
120 m and 180 mCoaxial lines
To cavity input 120 m away
From Beam Control
1/16 splitter
May 2013 Amplifiers Schedule
23 May 2012 5LIU SPS RF
2013 2014 2015 2016 2017 2018
JulyIT sent
DecemberFC Order placed IT : Invitation to Tenders
FC : CERN Finance CommitteeFAT : Factory Acceptance TestsCERN AT : CERN Acceptance TestsLD Tests : Long duration tests
: Long Technical Stop, No beams
MarchFirst Series FAT
MarchPre-series FAT
OctoberCERN approval for Series Production
(after LD tests)May
Pre-seriesCERN AT
DecemberLast SeriesCERN AT
JunuaryIT sent
JuneFC Order placed
DecemberFirst Series FAT
MarchCERN AT
SeptemberMayCERN approval for Series Production
(after LD tests)
DecemberPre-series FAT
DecemberLast SeriesCERN AT
Drivers
Finals
LSS3 rearrangement LS1
15 August 2012 6LIU SPS RF
HBW kicker
BPWA:319 to 31101
AEWB:319 To 31510
• HBW Damper will be prepared• BPWA and AEWB new locations have
been validated• ECR validated
Schedule : Summer 2013
June 2013 Schedule
15 August 2012 7LIU SPS RF
2011 2012 2013 2015 2016 2017 20192014
Studies
Tendering
Construction
Installation
CommissioningStart up
2018
Studies
HBW (kicker and Pickup)
New power couplers
Cavities pickups vacuumCV, EL
Studies
Authorizations
Construction
Services (CV, EL) Startup
Spare sections
LLRF Design and proto
LLRF TestsLLRF Series
New RF Building
LSS3 Tunnel Integration
New RF Power Amplifiers and LLRF
6 months cavities re-arrangement2 months RF Power conditioning
4 months LLRF commissioning
Coaxial Lines
8LIU SPS RF
Spending profile
23 May 2012
Item 2012 2013LS1 2014 2015 2016 2017 2018
LS2 Total
Building Civil Engineering(Natacha)
Basement 4000 CHF/m2
First floor 2000 CHF/m2 450 150 3’100 800 4’500Building Ventilation(Mauro) 350 100 850 1’000Electrical Network High Power(Joel)
Study, documentations, HV transformers, cabling, accessories 100 200 500 800
First RF Power Amplifier(all inclusive)
1100 kW x 7.5 CHF/W(based on 800 MHz 2010 prices) 350 5’450 3’500 200 9’500
Second RF Power Amplifier 1100 kW x 7.5 CHF/W 1’500 4’000 1’500 7’000Coaxial lines 2 x 25 x 6 m x 6500 CHF/6m 200 300 500Cavities modifications 4 x 150 kCHF + 2 x 100 kCHF 400 400 800Main power Couplers 10 x 100 kCHF 200 300 300 200 1’000Beam Control 2 x 700 kCHF 100 400 600 300 1’400
Total 450 500 3‘950 8’000 7’000 5’400 1’500 26’500
2012 2013 2014 2015 2016 2017 20180
50001000015000
kCHF
Red : initial profileBlue : New profile
THANK YOU FOR YOUR ATTENTION!