Upload
lecong
View
245
Download
13
Embed Size (px)
Citation preview
Springvale MPPS Water Treatment Project
Construction Environmental Management Plan
SMPPS-O-00-M13-00-03
DOCUMENT CONTROL
Rev Date Revision Comments Prepared by Reviewed by Approved by
0 18/08/2017 Draft for internal review Elena Ivanova
Project Manger
Jonas Ball
Linchpin Environment
1 27/10/2017 Final Elena Ivanova
Project Manger
Jonas Ball
Linchpin Environment
Huw Thomas
HSEQ Lead
Page: Page 2 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
CONFIDENTIALITY CONDITIONS All information whether oral, electronic, printed or graphic contained in this document or obtained by you from VANZ (Information) is confidential to VANZ and shall not be used by you other than for the purpose of reviewing this document and the proposal contained herein. You shall not copy or reproduce any Information except when, and then only to the extent, reasonably necessary for the purpose of reviewing this document and the proposal contained herein. Upon receiving notice that our proposal has not been accepted, and if notified by VANZ, you shall destroy, in a secure manner, this document and any Information. You shall ensure that any employee or any other person to whom you supply the Information is bound by the terms of these conditions.
Page: Page 3 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
DEFINITIONS AND ACRONYMS Table 1 – Definitions and Acronyms
Term Definition
AIMS Abergeldie’s Integrated Management System
AHIMS Aboriginal Heritage Information Management System
BCSI Baseline Contaminated Site Investigation
BMP Biodiversity Management Plan
BMS Business Management System
CoDC Conditions of the Development Consent
DP&E Department of Planning and Environment
EIS, 2016 Environmental Impact Statement
EI&C Electrical, Instrumentation & Controls
EMP Contractor’s Environmental management Plan
EMS Environmental Management System
EP&A Act Environmental Planning and Assessment Act 1979
EPA NSW Environment Protection Authority
EPL Environmental Protection Licence
JSEA Job Safety & Environment Analysis
CEMP Construction Environmental Management Plan
Contractor Abergeldie Contractors Pty Ltd
CLM Act Contaminated Land Management Act 1997
Customer Springvale Coal Pty Ltd and NSW EnergyAustalia Pty Ltd
ML/day mega litres a day
MPPS Mount Pipe Power Station
PAC Planning Assessment Commission
POEO Act Protection of the Environment Operation Act 1997
SMPPS WTP or Project Springvale MPPS Water Treatment Project
PM Project Manager
PMP Project Management Plan
REA Reject Emplacement Area
SWMS Safe Work Method Statement
WTF Water Treatment Facility
WTS Water Treatment System
VANZ or Veolia Veolia Australia and New Zealand
WARR Act Waste and Resource Recovery Act 2001
WHS Act Work Health and Safety Act 2011
Page: Page 4 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
TABLE OF CONTENTS
Section 1 Introduction ..................................................................................................... 6
1.1 Background ....................................................................................... 6 1.2 Scope and Objectives........................................................................ 7 1.3 Supporting Management Plans ......................................................... 8 1.4 Veolia’s Overall Management System ............................................... 8
Section 2 Statutory and Policy Considerations .......................................................... 11
2.1 Relevant Environmental Legislation ................................................ 11
2.2 Other Requirements ........................................................................ 14
2.3 Summary of Licensing and Permit Requirements ........................... 15
2.4 Conditions of Development Consent ............................................... 15
Section 3 Project overview ........................................................................................... 18
3.1 Project Overview ............................................................................. 18 3.2 Project Location ............................................................................... 18 3.3 Project Phases ................................................................................ 20 3.4 Construction Hours .......................................................................... 21
3.5 Predicted Construction Impacts ....................................................... 21
Section 4 Implementation of the CEMP ....................................................................... 27
4.1 Roles and Responsibility ................................................................. 27 4.2 Subcontractor Management ............................................................ 29
4.3 Training and Awareness .................................................................. 30
4.4 Stakeholder Management Plan ....................................................... 30 4.5 Incident and Emergency Response ................................................. 31 4.6 Notification and Action Protocol ....................................................... 32
4.7 Emergency Contacts ....................................................................... 33 4.8 Pollution Incident Management ....................................................... 34
4.9 Environmental Performance Criteria ............................................... 35 4.10 Contingency Plan ............................................................................ 36 4.11 Performance Reporting ................................................................... 36
Section 5 Monitoring and Review of the CEMP .......................................................... 38
5.1 Monitoring and Inspections .............................................................. 38
5.2 Auditing ........................................................................................... 38 5.3 Review of the CEMP ....................................................................... 39
5.4 Corrective Action ............................................................................. 40
Appendices ..................................................................................................................... 41
Appendix A - Copy of the Development Consent .......................................... 41
Appendix B1 - Water Management Plan ........................................................ 42 Appendix B2 - Biodiversity Management Plan ............................................... 43 Appendix B3 - Aboriginal Cultural Heritage Management Plan ..................... 44 Appendix B4 - Construction Noise Management Plan ................................... 45 Appendix B5 - Construction Traffic Management Plan .................................. 46 Appendix B6 - Stakeholder Management Plan .............................................. 47 Appendix B7 - Construction Waste Management Plan .................................. 48 Appendix C - EPL requirements – EPA Clarifications .................................... 49
Appendix D - Pre-Construction Compliance Report ....................................... 50
Page: Page 5 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
TABLES Table 1 – Definitions and Acronyms .............................................................................................. 3
Table 2 – Licencing and Permitting Requirements ....................................................................... 15
Table 3 – Development Consent Requirements .......................................................................... 16
Table 4 – Construction Operating Hours ..................................................................................... 21
Table 5 – Air Control Measures ................................................................................................... 24
Table 6 – GHD Mitigation Measures ............................................................................................ 26
Table 7 – Visual Mitigation Measures .......................................................................................... 26
Table 8 – Summary of Key Roles and Responsibilities ................................................................ 28
Table 9 – Training and Awareness Methods ................................................................................ 30
Table 10 – Environmental Risks .................................................................................................. 32
Table 11 – Communication Mechanism ....................................................................................... 33
Table 12 – Project Emergency Incident Reporting Contacts ........................................................ 34
Table 13 – Environmental Performance Criteria .......................................................................... 35
Table 14 – Summary of Contingency Measures .......................................................................... 36
Table 15 – Summary of Monitoring and Inspections .................................................................... 38
FIGURES Figure 1 – Integrated Services Management Flowchart ................................................................. 9
Figure 2 – Project Overview ........................................................................................................ 18
Figure 3 – Project Location .......................................................................................................... 19
Figure 4 – Land Ownership ......................................................................................................... 19
Figure 5 – Incident Response Flow Chart .................................................................................... 34
Page: Page 6 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
SECTION 1 INTRODUCTION
1.1 Background
This Construction Environmental Management Plan (CEMP) and supporting management plans
have been prepared to comply with the Conditions of Development Consent granted on 19 June
2017 (CoDC) for the construction of the Water Transfer System (WTS) from existing Springvale Mine
dewatering facilities on the Newnes Plateau to a new Water Treatment Facility (WTF) located at the
Mount Piper Power Station (MPPS).
Springvale Coal Pty Ltd has collaborated with EnergyAustralia Pty Ltd to develop the above, which is
known as the Springvale MPPS Water Treatment Project (SMPPS WTP) (Project).
The Project includes the following major elements:
A system to transfer (approximately 15 km ) up to 42 mega litres a day (ML/day) of dewatered
mine water from the existing gravity tank forming part of the approved dewatering facilities on
the Newnes Plateau to a new WTF to be located at the MPPS site (see Figure 2 below).
A WTF incorporates desalinisation processes to reduce the salinity in mine water to a
standard suitable for either industrial reuse or environmental release.
Transfer of treated water from the water treatment plant to the MPPS cooling water to
contribute to the demand for make-up water.
Transfer via a new 2.4 km pipeline and discharge of any excess treated water not able to be
reused within the MPPS cooling water system to Thompsons Creek Reservoir.
Transfer of residual material from the pre-treatment process to the existing reject
emplacement area (REA) at the Western Coal Services Site.
Installation of a crystalliser to provide further treatment of the additional salt load generated
within the MPPS cooling water blowdown system.
The project would remove the current need to discharge a large amount of mine water to the drinking
water catchment, and provide a beneficial reuse of this water in the operation of the MPPS. This
project will improve environmental outcomes and water quality within the upper Cox’s River
catchment area.
Veolia has been selected as specialist water services company to finance, design, construct, test and
commission, operate and maintain the Project. The duration of the operations and maintenance
phase is 15 years. This arrangement is documented under a Water Treatment Services Contract to
be entered into between the Springvale Coal Pty Ltd, NSW EnergyAustalia Pty Ltd (Customer) and
Veolia.
Veolia has selected Abergeldie Complex Infrastructure Pty Ltd (Contractor) as the construction
subcontractor for the Project. Abergeldie will be responsible for the design, construction and
commissioning of the WTS, including the Mine Water Transfer Pipeline, Residuals Transfer Pipeline,
Treated Water Pipeline connecting to Thompsons Creek Dam and a new WTF. Abergeldie shall also
be responsible for the design and construction of the civil and buildings portion of the WTF as well as
the mechanical and EI&C construction, based on Veolia’s design.
The NSW Department of Planning and Environment (DP&E) has assessed the State Significant
Development (SSD 7592) in accordance with section 89(C) of the Environmental Planning and
Assessment Act 1979 (EP&A Act). DP&E has delegated SSD 7592 to the Planning Assessment
Commission (PAC) for determination under the Minister’s delegation of 14 September 2011. The
PAC determined the development application for the Project on 19 June 2017 as well as two
Page: Page 7 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
modifications associated with the Project: Wester Coal Services – Residuals Emplacement
Modification (SSD 5579 MOD1) and Springvale Mine Extension Project (SSD 5594 MOD2).
This CEMP has been prepared to detail the processes and procedures adopted by Veolia to identify,
manage and control construction environmental aspects and impacts associated with the Project.
The project area contains significant environmental values, including threatened flora species,
aboriginal artefacts and significant amounts of native vegetation.
1.2 Scope and Objectives
This CEMP responds to the Environmental Management Strategy (EMS) required under CoDC
Schedule 4, condition 1 for construction phase of the Project. Approval has been obtained from the
Secretary under CoDC Schedule 4, condition 3 to phase the submission of the EMS. Three stages
have been approved namely construction, commissioning and operations.
This Construction EMS includes:
the strategic framework for environmental management of the Project;
identification of the statutory approvals that apply to the Project;
description of the role, responsibility, authority and accountability of all key personnel
involved in the environmental management of the Project;
describe the procedures that will be implemented to:
o keep the local community and relevant agencies informed about the construction and
environmental performance of the Project;
o receive, handle, respond to, and record complaints;
o resolve any disputes that may arise;
o respond to any non-compliance;
o respond to emergencies;
copies of any plans required under the CoDC; and
a clear plan depicting all the monitoring to be carried out in relation to the Project
construction.
While the Environmental Management Strategy is predominantly an externally oriented document,
containing commitments to specific stakeholders, this CEMP is the chief internal document for
environmental management of construction and commissioning of the Project.
The objectives of this CEMP are to:
Provide a working environmental management tool to follow during the construction phase
of the Project;
Comply with relevant environmental legislation, including the Conditions of Development
Consent (refer to Appendix A) relating to the construction phase of the Project and the
recommendations provided in the Licensing Guide (EPA NSW, 2016);
Provide a means of implementing the recommended mitigation measures for the key
environmental issues, associated with construction of the Project, identified in the
Environmental Impact Statement (EIS) prepared by GHD in 2016;
Define roles and responsibilities of the project management team and contractors during the
construction phase of Project;
Page: Page 8 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Provide a guide for the interaction with relevant government authorities and other relevant
stakeholders, including the community during the construction phase of the Project.
This CEMP and supporting management plans have been prepared to provide the management
measures to be implemented to minimise potential adverse impacts on the environment during the
construction phase of the Project.
This CEMP is a live document and outlines the management strategies and control measures which
will be reviewed and updated, where necessary, to reflect changes introduced by the construction
project team, site specific outcomes, non-conformances and recommendations arising out of
inspections, meetings and audits.
1.3 Supporting Management Plans
The Project has planned to take actions to address significant environmental aspects, compliance
obligations and the risks and opportunities they present, as well as its objectives. These have been
incorporated in the supporting management plans to provide the management and control measures
to be implemented to minimise potential adverse impacts on the environment.
These plans are listed below and presented as separate documents in Appendix B.
Water Management Plan (Refer to Appendix B1);
Biodiversity Management Plan (Refer to Appendix B2);
Aboriginal Cultural Heritage Management Plan (Refer to Appendix B3);
Construction Noise Management Plan (Refer to Appendix B4);
Construction Traffic Management Plan (Refer to Appendix B5);
Stakeholder Management Plan (Refer to Appendix B6);
Construction Waste Management Plan (Refer to Appendix B7).
1.4 Veolia’s Overall Management System
Veolia has developed and implemented a Business Management System (BMS) to assist in meeting
the corporate objective of its water operations through sustainable development.
In the case of the CEMP and environment programs in Veolia generally, ISO 14001:2004 and ISO
31000:2009 are used as the base standards when constructing environmental systems for each
project. Veolia has an excellent environmental management record of accomplishment and will bring
to the project companies and personnel with substantial experience of delivering outstanding
environmental performance.
The integrated structure is described in Figure 1 below.
Page: Page 9 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Figure 1 – Integrated Services Management Flowchart
Contractor will manage construction works under Abergeldie’s Integrated Management System
(AIMS). AIMS brings together and cross-references safety management, environmental management
and quality management systems, which are all third party certified to ISO and AS/NZS standards.
Contractor’s environmental obligations for the Project include compliance with applicable
environmental legislation and guidelines including Veolia’s environmental policies and procedures,
and requirements and commitments of the project governance documents outlined in this plan.
1.4.1 Environmental policies
Veolia’s business strategy is guided by five elements: our business, our customers, our people, our
environment and our community. These elements shape all aspects of Veolia’s current and future
performance. Its corporate policies and practices are linked to delivering excellence in one or more of
these elements.
Veolia has developed a suite of company-wide policies in support of the sound management of its
facilities. All policies have been endorsed by Veolia’s Executive Committee and are reviewed
periodically. All Veolia employees are required to commit to the implementation of these policies.
Veolia environmental policies support minimisation of emissions to land, air and water and the wise
use of natural resources. This commitment is documented in Veolia’s environmental and
sustainability policies (see below).
1.4.1.1 Environment policy
Veolia is committed to minimising the environmental impacts of its operations and continually
improving its environmental performance within a framework of sustainable development by:
effectively managing our significant environmental impacts, monitoring progress and
reviewing environmental performance against objectives and targets on a regular basis
driving continual improvement, and meeting the requirements of ISO 14001 environmental
management systems standard as part of the integrated business management system
Page: Page 10 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
complying with applicable environmental legislation, contractual and other necessary
requirements related to our activities and assist customers and suppliers to use products
and services in an environmentally sensitive way
striving to ensure that our policies, objectives and achievements are communicated to all
persons working for and on behalf of the business and to educate and train employees and
ensure competence in environmental issues and the environmental effects of their activities
preventing pollution and harm to the natural, heritage and built environments and to reduce
the use of all raw materials, energy and supplies
consulting with relevant stakeholders, taking into account local environmental conditions and
working with local communities to achieve shared and lasting outcomes.
All managers, employees, contractors and visitors are responsible for being aware of, and complying
with this policy.
1.4.1.2 Sustainability policy
For Veolia, sustainable development means adopting business strategies and activities that meet the
needs of Veolia and its stakeholders today, while protecting, supporting and enhancing the human
and natural resources that will be needed in the future. This outcome is expressed clearly in Veolia’s
Sustainability Policy:
Being ethically responsible, to create value in what we do, and to use sound risk and hazard
management principles in conducting our business. As part of its ‘non-negotiables’ Veolia
will comply with all relevant legislation including pollution prevention and will strive to
develop and improve our integrated business management system to support a consistent
and disciplined approach to business processes. We will ensure that appropriate resources
(both internally and externally) are utilised to assist in achieving our goals.
Partnering in innovation and to understand and support our customers in achieving their
business objectives.
Attracting and retaining diverse and talented employees. This will include providing
development opportunities so our employees are continually learning, communicating,
providing workplace consultation, and creating an ‘Always Safe’ workplace, with an
aspiration of no workplace injury or illness for our employees, visitors and contractors.
Continually designing and implementing sustainable solutions to develop access to
resources and to protect and replenish them. Additionally, Veolia is committed to providing
environmental leadership in its operations and solutions, which includes the management of
its own environmental impacts, improving waste, water, energy and carbon outcomes, as
well as protecting and conserving biodiversity and natural capital.
Working closely with local communities to achieve shared and lasting outcomes. Additionally
Veolia will engage with government, policy makers, advocacy groups, industry associations
and other stakeholders in the areas which we operate to create better value and outcomes
in sustainable practices.
Page: Page 11 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
SECTION 2 STATUTORY AND POLICY CONSIDERATIONS
This section provides an overview of the environmental planning and statutory context for the
construction of the Project. It also provides a discussion of the Project construction in the context of
Veolia’s corporate environmental and sustainability policies.
Veolia is committed to complying with all of its legal obligations and other voluntary commitments
made by the company. Compliance to applicable regulatory requirements concerning the
construction of the Project will be achieved through:
identifying and accessing legal and other requirements which are directly applicable to the
organisation;
consulting and involving relevant government agencies;
internally communicating relevant information regarding legal and other requirements;
continually auditing, reviewing and upgrading company systems, management plans and
supporting documentation; and
providing relevant training.
2.1 Relevant Environmental Legislation
2.1.1 Acts and regulations
This CEMP has been developed in the context of the following key NSW legislation:
2.1.1.1 Environmental Planning and Assessment Act 1979
PAC reviewed this State Significant development (SSD 7592) and the two related modifications and
granted Development Consent for the ‘State Significant’ development on 19 June 2017 in
accordance section 89(E) of the Environmental Planning and Assessment Act 1979 (EP&A Act).
These conditions are required to:
prevent, minimise, and/or offset adverse environmental impacts including economic and
socials impacts;
set standards and performance measures for acceptable environmental performance;
require regular monitoring and reporting;
provide for the ongoing environmental management of the Project.
2.1.1.2 Protection of Environment Operations Act 1997
The main object of the Protection of Environment Operations Act 1997 (POEO Act) is to regulate air,
noise, water and land pollution. As well as imposing a general requirement not to cause pollution, the
Act also allows pollution to occur through a system of licensing. Both the mines and power station
are licenced under the POEO Act.
The EIS confirms that the Project will require the modification of existing Environment Protection
Licences (EPL) held for the Springvale Mine, Angus Place Colliery and the MPPS.
The EPL modifications are required to allow the transfer of mine water to the new WTF and for the
transfer and management of residuals and brine to the Springvale Coal Services Site and MPPS.
The Springvale Mine EPL will also be required to be modified to amend the timeframes to achieve
Mine Water discharge limits for the Springvale Mine (which replicate the modification being sought in
relation to the Springvale Mine Extension Planning Approval discussed in the EIS).
Page: Page 12 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Consultation has been undertaken with the EPA regarding EPL requirements for the Project and the
EPA has confirmed that the EPL is not required for the construction and operation of the Project
under Schedule 1 of the POEO Act. As noted above the Project will result in modifications to the
existing EPLs of MPPS and mining facilities. (Refer to Appendix C – The EPA’s email with
clarification).
2.1.1.3 Water Management Act 2000
The Water Management Act 2000 aims to facilitate the sustainable and efficient use of water in such
a way that benefits the environment and communities.
The Water Management Act 2000 provides for the preparation of water management plans that
outline arrangements for water sharing, water source protection and drainage management. The
Proposal site is located within the area covered by the 2010 Metropolitan Water Plan (NSW Office of
Water, 2010); the key aims of which are to:
provide a secure supply of water to meet the medium-term needs of Sydney, while planning
for long-term goals;
protect the health of Sydney’s rivers;
ensure water supplies are adequate throughout drought.
The construction of the Project will have a minimal impact on the quality and quantity of water
discharged from the Site, and will minimise the demand for potable water at the Site.
2.1.1.4 Waste Avoidance and Resource Recovery Act 2001
The Waste and Resource Recovery Act 2001 (WARR Act) is the principal piece of legislation
governing waste and resource management in NSW. The Act seeks to maximise the utility of
resources including waste, and minimise disposal of resources to landfill. A Waste Management Plan
has been prepared in consideration of the objectives of the WARR Act including:
encouraging the most efficient use of resources;
reducing environmental harm;
ensuring that resources are managed against the waste hierarchy of avoidance, resource
recovery, and then disposal;
diversion of waste from landfill;
ensuring industry takes part in reducing and dealing with waste;
achieving integrated, state-wide waste and resource management planning and service
delivery.
2.1.1.5 Contaminated Land and Management Act 1997
The principal object of the Contaminated Land Management Act 1997 (CLM Act) is to establish a
process for investigating and, where appropriate, remediating land that the Environmental Protection
Authority (EPA) considers to be contaminated significantly enough to require regulation. Under the
CLM Act, contamination of land is defined as:
“the presence in, on or under the land of a substance at a concentration above the concentration at
which the substance is normally present in, on or under (respectively) land in the same locality, being
a presence that presents a risk of harm to human health or any other aspect of the environment”
(CLM Act, s5).
Page: Page 13 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Land may be considered contaminated even if it became contaminated partly, or entirely, by the
migration of contaminants into, onto or under the land from other land.
The soil at the WTF site shows elevated levels of some contaminants and further investigations into
the site are planned including the installation of groundwater monitoring wells. Based on the results
of further investigations the WTF site may require some remediation before construction. A
Remediation Action Plan will be developed and implemented if required.
2.1.1.6 Roads Act 1993
The objectives of the Roads Act 1993 are to:
set out the access rights to public roads;
establish procedures for opening and closing public roads;
provide for the classification of roads;
establish the Roads and Maritime Services and confer functions associated with road works
and maintenance to the Roads and Maritime Services and other roads authorities.
The Act regulates the carrying out of various activities on public roads. Approval under the Act would
be required for any pipeline crossings of public roads and for any temporary modifications to traffic
arrangements (eg. lane closures) to allow construction to be undertaken.
2.1.1.7 Forestry Act 2012
The main objective of the Forestry Act 2012 is to authorise forestry activities and for the management
of Crown timber land and land owned by the Forestry Corporation of NSW.
As the pipeline will be partially located on land owned by the Forestry Corporation of NSW, an
occupation permit (or a modification to the existing permit) will be required.
2.1.1.8 Work Health and Safety Act 2011
The main object of the Work Health and Safety Act 2011 (WHS Act) is to provide for a balanced and
nationally consistent framework to secure the health and safety of workers and workplaces by:
protecting workers and other persons against harm to their health, safety and welfare
through the elimination or minimisation of risks arising from work or from specified types of
substances or plant;
providing for fair and effective workplace representation, consultation, cooperation and issue
resolution in relation to work health and safety;
encouraging unions and employer organisations to take a constructive role in promoting
improvements in work health and safety practices, and assisting persons conducting
businesses or undertakings and workers to achieve a healthier and safer working
environment;
promoting the provision of advice, information, education and training in relation to work
health and safety
securing compliance with this Act through effective and appropriate compliance and
enforcement measures;
ensuring appropriate scrutiny and review of actions taken by persons exercising powers and
performing functions under this Act;
providing a framework for continuous improvement and progressively higher standards of
work health and safety;
Page: Page 14 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
maintaining and strengthening the national harmonisation of laws relating to work health and
safety and to facilitate a consistent national approach to work health and safety in this
jurisdiction.
The Act requires that workers and other persons should be given the highest level of protection
against harm to their health, safety and welfare from hazards and risks arising from work or from
specified types of substances or plant as is reasonably practicable.
2.1.2 Project Specific Applicable Regulatory Requirements
An Environmental Impact Statement (EIS) for Project has been prepared by GHD Pty on behalf of
Springvale Coal Pty Ltd and NSW EnergyAustralia Pty Ltd to support the development application.
The EIS has been prepared using a risk-based assessment approach to identify and evaluate
environmental, social and economic aspects associated with the Project.
This has been achieved through a process of ongoing engagement with stakeholders from
government agencies and the community, risk assessment to identify and scope key environmental
assessments of the impacts and development of appropriate safeguards to mitigate any such
impacts for the Project.
2.2 Other Requirements
2.2.1 Relationship of the CEMP to ISO 14001:2004
As discussed in Section 1.4, this CEMP forms the basis of the EMS for the construction phase of the
Project. The CEMP is consistent with ISO 14001:2004 Environmental management systems -
Requirements with guidance for use.
2.2.2 Other Requirements
In addition to the requirements discussed above, this CEMP is being developed in accordance with
the Guideline for Preparation of Environmental Management Plans (DIPNR, 2004). Other
environmental standards, guidelines and documentation are included in the relevant supporting
management plans, which are included as appendices to the CEMP.
Page: Page 15 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
2.3 Summary of Licensing and Permit Requirements
Table 2 provides a summary of the Licence and Permits that will require, in addition to Development Consent for the Project construction.
Table 2 – Licencing and Permitting Requirements
Legislation/ Guideline Approval/ Licence
Assessment Authority
Status Responsibility
Road Act 1993
(section 138) Approval RMS
Approval to construct pipeline across highway reserve
Contractor
Road Act 1993
(section 183)
Consent
(Road Occupancy Licence)
RMS
Contact RMS to determine if the Licence is required.
If required, the Licence to be issued prior to works commencing within three (3) metres of the travel lanes in the Castlereagh Highway
Contractor
Road Act 1993
(section 138) Approval
Lithgow City Council
Approval to construct pipeline across local road reserve
Contractor
Road Act 1993
(section 183)
Consent
(Road Occupancy Permit)
Lithgow City Council
Permit to be issued prior to works commencing on Wolgan Rd
Contractor
Crowns Land Act 1989 Approval Lithgow City Council
Approval to be issued prior to any groundwater extraction
Contractor
Forestry Act 2012
(section 60)
Occupational Permit
Forest Corporation
Permit to be issued prior to works commencing within Newnes State Forest
Customer
Water Management Act 2000 and Water Act 1912
Approval NSW Office of Water
Approval to be issued prior construction of pipeline infrastructure within 40m of water source
Contractor
Inclosed Lands Protection Act 1901
Consent/Lease Agreement
Owner of the Land (Janette Winifred Hunt)
Consent to assess the land to be issued prior construction of pipeline infrastructure
Customer
Inclosed Lands Protection Act 1901
Consent/Lease Agreement
Owner of the Land (Springvale Centennial)
Consent to assess the land to be issued prior construction
Customer
Inclosed Lands Protection Act 1901
Consent/Lease Agreement
Owner of the Land (EnergyAustralia)
Consent to assess the land to be issued prior construction
Customer
2.4 Conditions of Development Consent
Refer to Appendix A for the conditions of the Development Consent for the Project. Conditions of approval relevant to the construction phase have been incorporated within this CEMP.
A Pre-Construction Compliance Report (refer to Appendix D) details the relevant conditions of
consent addressed in each supporting management plans which address the management and
control measures to be implemented in a manner to minimise adverse impacts on the environment
during construction phase.
Page: Page 16 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Condition 1 and 2 of Schedule 4: Environmental Management and Reporting of the Development Consent provide details regarding the Environmental Management Strategy and Management Plan Requirements for the Project, as outlined in Table 3 below.
Table 3 – Development Consent Requirements
Relevant Conditions of Consent
(Schedule 4) Definition
CEMP Document Reference
Environmental Management Strategy
1
Prior to the commencement of construction, the Applicant must prepare an Environmental Management Strategy for the development to the satisfaction of the Secretary. This strategy must:
1 (a) provide the strategic framework for environmental management of the development Section 1.2
1 (b) identify the statutory approvals that apply to the development Section 2
1 (c) describe the role, responsibility, authority and accountability of all key personnel involved in the environmental management of the development Section 4.1
1 (d)
describe the procedures that would be implemented to:
keep the local community and relevant agencies informed about the operation and environmental performance of the development;
receive, handle, respond to, and record complaints;
resolve any disputes that may arise;
respond to any non-compliance;
respond to emergencies
Sections 4.4-4.8
1 (e)
and include:
copies of any plans approved under the conditions of this consent; and
a clear plan depicting all the monitoring to be carried out in relation to the development.
Section 1.3
Section 5
1 Following approval, the Applicant must implement the Environmental Management Strategy Section 1.1
Management Plan Requirements
2 The Applicant must ensure that the management plans required under this consent are prepared in accordance with any relevant guidelines, and include:
2 (a) detailed baseline data Section 1.1
2 (b)
a description of:
the relevant statutory requirements (including any relevant approval, licence or lease conditions);
any relevant limits or performance measures/criteria;
the specific performance indicators that are proposed to be used to judge the performance of, or guide the implementation of, the development or any management measures
Section 2
Section 4.9
Section 4.9
2 (c) a description of the measures that would be implemented to comply with the relevant statutory requirements, limits, or performance measures/criteria Section 3.5
2 (d)
a program to monitor and report on the:
impacts and environmental performance of the development;
effectiveness of any management measures (see c above)
Section 5.1
2 (e) a contingency plan to manage any unpredicted impacts and their consequences Section 4.10
2 (f) a program to investigate and implement ways to improve the environmental performance of the development over time Sections 5.2
2 (g)
a protocol for managing and reporting any:
incidents;
complaints;
non-compliances with statutory requirements; and
exceedances of the criteria and/or performance criteria; and
Section 4.6
Page: Page 17 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Relevant Conditions of Consent
(Schedule 4) Definition
CEMP Document Reference
2 (h) a protocol for periodic review of the plan. Section 5.3
Annual Review
5
By the end of March each year, the Applicant must submit a review of the environmental performance of the development for the previous calendar year to the satisfaction of the Secretary. This review must:
Section 4.11.2
5 (a) describe the development (including any rehabilitation) that was carried out in the past year, and the development that is proposed to be carried out over the next year; Section 4.11.2
5 (b)
include a comprehensive review of the monitoring results and complaints records of the development over the past year, which includes a comparison of these results against the:
relevant statutory requirements, limits or performance measures/criteria;
monitoring results of previous years; and
relevant predictions in the EIS.
Section 5.3
5 (c) identify any non-compliance over the last year, and describe what actions were (or are being) taken to ensure compliance; Sections 5.2&5.4
5 (d) identify any trends in the monitoring data over the life of the development; Section 5.3
5 (e) identify any discrepancies between the predicted and actual impacts of the development, and Section 5.3
5 (f) analyse the potential cause of any significant discrepancies; and Section 5.3
5 (g) describe what measures will be implemented over the next year to improve the environmental performance of the development Section 5.3
Progress Reporting
7 The applicant must monitor the status of the development and submit a quarterly progress report to the Secretary. The Report must:
7 (a) be submitted within 3 months of 19 June 2017 and every 3 months thereafter until the opration of the Water Treatment Plan; Section 4.11.1
7 (b) describe the development (including any construction) that was carried in the past 3 months, and development that is proposed to be carried out over next year; Section 4.11.1
7 (c) Identify any poetical delays and describe measures to ensure that the Water Treatment Plan is operational by July 2019: and Section 4.11.1
7 (d) Be made publically available on the Applicant’s website;
to the satisfaction of the Secretary Section 4.11.1
Page: Page 18 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
SECTION 3 PROJECT OVERVIEW
3.1 Project Overview
The Project includes the following major elements:
A system to transfer (approximately 15 km ) up to 42 ML/day of dewatered mine water from
the existing gravity tank forming part of the approved dewatering facilities on the Newnes
Plateau to a new WTF to be located at the MPPS site (see Figure 2 below).
A WTF incorporates desalinisation processes to reduce the salinity in mine water to a
standard suitable for either industrial reuse or environmental release.
Transfer of treated water from the water treatment plant to the MPPS cooling water to
contribute to the demand for make-up water.
Transfer via a new 2.4 km pipeline and discharge of any excess treated water not able to be
reused within the MPPS cooling water system to Thompsons Creek Reservoir.
Transfer of residual material from the pre-treatment process to the existing reject
emplacement area (REA) at the Western Coal Services Site.
Installation of a crystalliser to provide further treatment of the additional salt load generated
within the MPPS cooling water blowdown system.
Figure 2 – Project Overview
3.2 Project Location
Springvale Mine is underground coal mine located in the western coalfield of NSW, approximately 15
kilometres (km) west of Lithgow. The MPPS located about 8 km west of the Springvale Mine pit top
at Lot 363 Boulder Road, Blackmans Flat, NSW (see Figure 3).
Page: Page 19 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Figure 3 – Project Location
3.2.1 Property
The remainder of the Project is located within land owned or under access agreements with the
Springvale (unincorporated joint venture with participants Centennial Springvale Pty Limited (as to
50%) and Springvale SK Kores Pty Limited (as to 50%)) and land owned by Energy Australia Pty Ltd.
Construction of the pipeline for the Project is predominantly located on Springvale owned lands as
shown in Figure 4 some section of the pipeline will across land owned by Forestry Corporation of
NSW, Crown lands and privately owned property. Approval for access these lands will be obtained
subject to compliance of this Plan (Refer to section 2.2).
Figure 4 – Land Ownership
Page: Page 20 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
3.2.2 The Project Application Area
The Project Application area comprises a number of infrastructure elements primarily including a
10m wide linear pipeline corridor extending between the existing Gravity Tank on Newnes Plateau
and the Water Treatment Plant location within the MPPS site.
The Project application area is partially situated within the Newnes State Forest, extending from the
east on Newnes Plateau to west into lower lying vegetated and disturbed lands. In these portions of
the Project application area, connected vegetation occurs for a distance of greater than two
kilometres to the north, east and south-east. Being a State Forest in these portions of land, the native
vegetation is periodically selectively logged but there are no areas of clear felling of native
vegetation.
The Newnes State Forest is connected to the Gardens of Stone National Park and Wollemi National
Park to the north, Blue Mountains National Park to the east and Ben Bullen State Forest to the north-
west.
The western half of the Project application area is situated on largely disturbed lands due to existing
farming lands, roads, easements and mining lands. Remnant vegetation exists to the south of the
pipeline, which tentatively connects to the northern side. Castlereagh Highway creates a wide
disconnection between vegetation tracts further north, and that situated to the north of these western
portion of the Project application area.
The proposed water treatment plant site at MPPS has been extensively cleared and modified for
construction of the power station and associated infrastructure.
3.3 Project Phases
The implementation of environmental controls for specific risks will be applied through various
phases of the Project. Key project phases, where environmental controls and opportunities will be
assigned to implementation, are:
Pre-construction: planning, design and procurement phases (August 2017–October 2017);
Construction: delivery phase of the project, includes vegetation removal and earthworks
(October 2017–December 2018).
Commissioning: commissioning phase of the project includes testing of all systems and
components of industrial plant to according to the operational requirements (January 2019–
May 2019);
Operation: operational phase of the project includes accepting and treating mine water at the
water treatment facility according to the operational requirements (June 2019–June 2034).
Post-construction; occurs in sections of the project area which are no longer required for construction
activities. At this stage, project areas will be re-instated to their previous condition, including re-
instatement of vegetated areas.
The Construction period of the Project would be approximately 19 months, commencing in October
2017.
Page: Page 21 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
3.4 Construction Hours
The proposed construction activities will be restricted to the construction hours specified in Table 4.
Table 4 – Construction Operating Hours
Activity Day Hours
Construction
Monday - Friday 7:00am – 6:00pm
Saturday 8:00am – 1:00pm
Sunday & Public Holidays At no time
3.5 Predicted Construction Impacts
Construction environmental impacts for the project were identified and evaluated in the EIS through
reviewing the Project in the context of the existing environmental and operational settings within
western coalfields; engagement with government and community stakeholders and through a
preliminary environmental risk assessment process.
A summary of the key potential environmental impacts that will require management prior to, during
and post-construction of the project, are listed below and form the basis of the environmental risk
assessment.
3.5.1 Surface Water Quality
Sensitive receptors located in proximity to the Project application area include Wangcol Creek and
Coxs River. Erosion and sediment controls will be developed for the both the WTF site and for
installation of the WTS in accordance with Managing Urban Stormwater: Soils and construction 4th
edition. “The Blue Book”. Erosion and sediment controls will be implemented to avoid pollution of
waterways and the MPPS stormwater system.
To ensure suitable control are addressed during the construction, management strategies for
disturbance of soil on site, sedimentation and erosion control measures have been detailed in the
Water Management Plan (Refer to Appendix B1).
3.5.2 Biodiversity
A comprehensive biodiversity assessment was undertaken for Project as part of the EIS, which
included survey effort, desktop analysis.
The key biodiversity impacts of the project relate to the clearing of vegetation in a 10 m wide linear
pipeline corridor extending between the existing Gravity Tank on Newnes Plateau and the WTF.
Project will trigger the following direct impacts:
removal or modification of up to 27.84 ha of native vegetation and associated habitat for
threatened fauna species with potential to occur in a 10 m wide linear pipeline corridor;
removal of approximately 67 hollow bearing trees.
The impact assumptions will be confirmed prior to construction through the completion of
preclearance surveys to validate offsetting requirements.
However, by observing careful construction techniques through the course of Project construction
opportunity (i.e. use of pre-clearance surveys and minor route adjustment) exists to avoid impacts on
individual threatened plants and hollow-bearing trees. Biodiversity management strategy is described
in a Biodiversity Management Plan (Refer to Appendix B2).
Page: Page 22 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
3.5.3 Aboriginal Cultural Heritage
Based on the aboriginal cultural heritage assessment undertaken in the EIS, seven Aboriginal
Heritage sites were found in the vicinity of the Project application area. These include three artefact
scatters, three isolated finds and one scarred tree site. These are located within 30 meters of the
Project application area boundary; however, none is in the Project application area.
The project alignment has been modified since the EIS was prepared and now intersects with one of
the artefact scatter (AHIMS # 45-1-0237). Where the project alignment intersects with AHIMS # 45-1-
0237, the Project consists of a subsurface pipeline, approximately 8 metres underground. The
pipeline will be constructed with a directional drilling machine that will be launched approximately 300
metres away from the site. AHIMS #45-1-0237 will therefore be avoided by the Project. A ‘no go
zone’ will be installed around the site to ensure its protection from potential surface impacts.
The significance of these sites is low and no Aboriginal Heritage sites would be impacted by the
Project. Nonetheless, details of control measures to minimise potential impact on the aboriginal
cultural heritage are outlined in the appended Aboriginal Cultural Heritage Management Plan (Refer
to Appendix B3).
3.5.4 Noise and Vibration
A noise and vibration impact assessment was undertaken in the EIS for the construction phase of the
Project associated with construction activities at potentially affected receivers.
The noise levels are predicted to meet the Interim Construction Noise Guideline, (DECC, 2009) at all
the times and at all identified residential receiver locations.
Based on EIS modelling, it is not anticipated that excessive noise impacts will occur at residential
receivers throughout the construction program. Any likely exceedance has been identified to be
limited to the receivers located along pipeline route subject to short-term elevated noise levels during
pipeline trenching and construction.
In the event of noise exceedances or complaints received, a review of construction activities, plant
and equipment will be undertaken to resolve the issue. Noise management and mitigation measures
are outlined in the appended Construction Noise Management Plan (Refer to Appendix B4).
No vibration impacts on human comfort and structural damage are expected. Nonetheless, details of
control measures to minimise potential vibration impacts are outlined in the appended Construction
Noise Management Plan (Refer to Appendix B4).
3.5.5 Traffic and Transport
An assessment of the traffic and transport impacts was undertaken as part of the EIS for the
construction phase of the Project. The Project will generate additional vehicles movements on the
Castlereagh Highway, Chifley Road, Newnes State Forest Road and it is considered to have
negligible traffic impacts.
The Castlereagh Highway is expected to continue to operate within the Roads and Maritime Services
recommended operating performance standards.
Page: Page 23 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
A risk assessment will be undertaken for the site to identify the potential traffic hazards by the
Contractor at the commencement construction works, and any changes required to the management
strategies will be reported. The risk assessment will be updated as required during the construction
works. Traffic management strategies outlined in the appended Construction Traffic Management
Plan (refer Appendix B5).
3.5.6 Other Environmental Impacts
3.5.6.1 Soils and Contamination
The Project construction includes boring, pipeline trenching and clearing, regrading and building
infrastructure for the WTF and WTS. The WTF application area contains significant amount of fill
(mine overburden).
Jacobs was commissioned by Veolia to undertake a Baseline Contaminated Site Investigation (BCSI)
for portions of land to be occupied by the WTF and the WTS associated with the Project in August
2017.
The objective of the BCSI was to assist Veolia in obtaining sufficient information to assess baseline
soil and groundwater contamination conditions of the site (comprising the WTF and the WTS) to
support both the lease agreement and ongoing environmental monitoring requirements during
operation of the WTF and WTS. The BSCI assumed that the WTF sites will be considered a
commercial industrial land use. For the WTS there would a variety of different land uses from
commercial/industrial in the coal services areas and to natural land uses in the Newnes State Forest.
Based on the results of the fieldwork program, site observations and results of the laboratory
analysis, contamination was not identified in soils beneath the WTF or the WTS that would impact
upon construction and/or operation of the project in consideration of a commercial / industrial land
use.
Based on the results of the BCSI, the risk of existing significant contamination being present at the
WTF site areas that will be disturbed by construction and operations of the facility is considered to be
low. Should surplus material be generated during construction of the project and requires off-site
disposal, this material will be classed the NSW Waste Classification Guidelines (EPA, 2014) and
disposed to a licensed facility.
Groundwater beneath the WTF sites contains elevated concentrations (i.e. concentrations above the site acceptance criteria) of some heavy metals and hydrocarbon compounds. This is likely to be from groundwater coming in contact with overburden material containing remnants of coal, however, this can not be conclusively determined. At the time of the BSCI, groundwater was only encountered in two groundwater wells (7 wells installed) to the limit of the investigation (approximately 10m bgl). These wells were located in the northern most portion of the WTF within the operational areas of the MPPS and therefore dewater in unlikely to be required.
However if groundwater levels increase and dewatering of groundwater is required to facilitate
construction, this water will need to be managed to prevent discharge and impacts to the fresh water
ecosystems of the Coxs River and associated tributaries (Wangcol Creek and Sawyers Swamp
Creek). Prior to any discharge of water (if encountered) during construction, water quality
investigations be undertaken to quantify actual risks (if present) to receptors and to assist in the
selection of appropriate disposal options.
In addition, the disturbed areas during construction phase will be progressively rehabilitated except
those areas where permanent access roads are being established.
Page: Page 24 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
To ensure suitable control are addressed during the construction, management strategies for
disturbance of soil on site, sedimentation and erosion control measures have been detailed in the
Water Management Plan (Refer to Appendix B1).
3.5.6.2 Bushfire Risk
Based on the assessment of bushfire risk undertaken as part of the EIS, it was defined as high risk of
fire being experienced during construction phase of the Project. The bushfire risk of the Project has
been reduced through incorporation of mitigation measures and avoidance measures in the design.
In addition, a Bushfire Risk Management Plan for construction phase of the Project has been
developed and outlined in the Biodiversity Management Plan (Refer to Appendix B2).
3.5.6.3 Construction Waste
Construction of the Project will generate waste in the form of packaging and excess materials,
wastewater and sewage from the worksites. Waste generated during commissioning of the WTF will
be managed in accordance with a Brine and Residuals Disposal Plan, which will be prepared to
satisfaction of the Secretary prior to the WTF commissioning.
Management strategies for waste generated during the construction phase of the Project is aimed at
implementing effective controls, correct classification and disposal methods including reuse and
recycling where possible and are detailed in the Construction Waste Management Plan . Any
materials deemed beyond their useful life shall be disposed at the appropriately licensed facility.
A Construction Waste Management Plan has been prepared in consideration of the Waste
Avoidance and Resource Recovery Act 2001 and is attached as Appendix B7.
3.5.6.4 Air Quality
There is potential for construction activities to cause impacts to the community, residential areas and
other dust sensitive receptors. However, the majority of dust generating activities will be undertaken
a significant distance from any sensitive receivers. Control measures, outlined in Table 5 below, will
be undertaken by Contractor to minimise dust emissions during construction of the Project and do
not result in nuisance to adjoining properties, significantly impact neighbouring amenity and health, or
result in excessive community complaints.
Environmental Site Inspection Forms will be used to report on effectiveness of dust control measures
and any additional mitigation measures that may need to implemented during adverse meteoroidal
weather conditions (high wind conditions).
Table 5 – Air Control Measures
Control Measures and Safeguards Responsibility Timing/ Frequency
Targets:
No community complaints regarding nuisance or health impacts resulting from dust generated by construction activities;
zero environmental fines or prosecutions relating to dust and air emissions.
Identify dust generating activities and dust-sensitive adjacent land uses prior to commencement of construction.
Environment Nominee Prior to commencement of construction
Prior to commencement of construction ensure appropriate mitigation measures are implemented for identified dust generating activities.
Environment Nominee Prior to commencement of construction
Provide advance notice to residents prior to commencing dust generating activities. Environment Nominee A minimum of five days in advance of planned dust generating activities.
Cesate of dust generating activities during adverse weather conditions Construction During high wind conditions
Page: Page 25 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Control Measures and Safeguards Responsibility Timing/ Frequency
Mangers/Engineers
Limit vehicles to specified routes to construction sites and ensuring speed limits are adhered to.
Construction Mangers/Engineers
During construction
Use of dust suppression techniques if required such as watering to maintain moist conditions of exposed areas, works area and stockpiles.
Construction Mangers/Engineers
During construction
Maintenance of any excavated soil stockpiles and handling areas in a condition which minimises windblown or traffic generated dust.
Construction Mangers/Engineers
During construction
Stockpiles are to be located as far as practicable from sensitive receptors. Construction Mangers/Engineers
During construction
Construction equipment will be properly maintained to control smoke emissions from motor vehicles, which will not exceed 10 seconds after start up. Hire agreements will contain provisions to stand down equipment which has excessively smoky exhaust as defined by DECC.
Construction Mangers/Engineers
Prior to commencement of construction
Minimise disturbed areas as much as possible Construction Mangers/Engineers
During construction
Progressively rehabilitate/seal disturbed areas to minimise the potential for windblown dust.
Construction Mangers/Engineers
Immediately after working areas and access roads are constructed
monitoring and cleaning of roads as required by street sweepers; Construction Mangers/Engineers
During construction
Cover all loads leaving the site and importing materials to site in a manner which ensures that no dust or other material is emitted from the truck.
Foreman During construction
Switch off engines of plant parked next to residents and areas of sensitivity such as schools when not in operation.
Foreman During construction
Start-up of vehicles will, where practicable or relevant be undertaken away from areas of sensitivity such as schools.
Foreman During construction
Ensure that there is no open burning or incineration. Foreman During construction
In the event complaint is received regarding air quality, the Environment Nominee will conduct an
investigation to determine the potential parameters of influence that could have led to the
exceedance.
The investigation will examine:
the quantity of exposed areas, which may potentially generate dust;
whether there is potential to revegetate these areas;
whether there were any identified days of excessive high wind during this period;
the number of water-trucks operating within the area during the this period; and
an examination of construction activities conducted during this period.
If deficiencies are identified and non-compliances with the environmental requirements observed, an
Environmental Inspection Report or Environmental Improvement Notice will be issued and relevant
actions/mitigations will be enforced.
3.5.6.5 Greenhouse Gas
A Greenhouse Gas Assessment was undertaken in the EIS to identify activities and measure
emissions from the Project. Green gas emissions associated with the construction phase have not
been quantified. Nevertheless, the mitigation measures have been identified to minimise energy
usage during construction phase.
Page: Page 26 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Mitigation measures, outlined in Table 6 below, will be undertaken by Contractor to minimise energy
usage during construction of the Project.
Table 6 – GHD Mitigation Measures
Control Measures and Safeguards Responsibility Timing/ Frequency
Targets:
To comply with National Greenhouse and Energy Reporting Scheme (2011).
Prior to commencement of construction ensure that earthmoving equipment and on-site vehicles are be fitted with exhaust controls in accordance with the Protection of the Environment Operations (Clean Air) Regulation 2010.
Environment Nominee Prior to commencement of construction
Ensure that the exhaust systems of construction plant, vehicles and machinery will be
maintained in accordance with manufacturer specifications. Construction Mangers/Engineers During construction
Ensure that the all trucks leaving the Site carrying waste will be filled to the maximum
amount allowable, depending on the truck size, to reduce the number of traffic movements
required.
Construction Mangers/Engineers During construction
Make certain that the only lighting left on overnight around the Site office will be security or
emergency/access lighting. Construction Mangers/Engineers
During construction
In accordance with the National Greenhouse and Energy Reporting Scheme (2011), the Contractor
or site nominee will also record all fuel, utility and materials used during the construction phase for
Veolia’s emissions reporting obligations.
3.5.6.6 Visual
Potential visual impacts and changes to the local amenity, as a result of the construction phase of the
Project, were assessed in the EIS.
This assessment indicated that during construction the visual impact would be minimal. Construction
works associated with the pipeline will move along the route and have potential impact on any one
area for a short period of time. Compounds and set down areas will be small in scale and established
for short durations.
The WTF infrastructure will not be visible form any towns including Portland and will be visible from
mine and MPPS sites.
Mitigation measures, outlined in Table 7 below, will be undertaken by Contractor to minimise visual
impacts during construction of the Project.
Table 7 – Visual Mitigation Measures
Control Measures and Safeguards Responsibility Timing/ Frequency
Targets
To ensure that outlined mitigation measures are implemented accordingly.
Design WTS to incorporate non-reflective material to help them blend into existing
environment. Project Manager Prior to commencement of construction
Complete construction work in accordance with construction program to minimise any
delays. Construction Mangers/Engineers During construction
Remove all waste generated by proposed work from site as soon as it is practicable and
disposed appropriately. Construction Mangers/Engineers During construction
Rehabilitate trenched section of pipeline on the Newnes Plateau as soon as practicable
following pipeline installation. Construction Mangers/Engineers
During construction
Replace, repair, re-instate or restore a surface and/ or property disturbed or damaged by
the proposed works to pre-existing or better conditions prior to works re-commencing. Construction Mangers/Engineers
During construction
Page: Page 27 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Control Measures and Safeguards Responsibility Timing/ Frequency
Remove all vehicles, construction equipment, material and refuse relating to the works on
completion of works. Construction Mangers/Engineers
At the completion of construction
Maintain the site in an orderly manner and ensure the construction site is kept tidy and
rubbish free. Foreman During construction
Minimise the spread of materials stockpiles, waste and vehicle parking. Construction Mangers/Engineers
During construction
Prior to commencement of construction ensure that finishing and colours for WTF will be
similar to existing buildings at the MMPS to assist with blending into its setting. Project Manager
Prior to commencement of construction
3.5.6.7 Non - Aboriginal Cultural Heritage
A review of applicable State and Federal heritage register was undertaken to identify any non-
aboriginal heritage items within vicinity of the proposed site. There are two historic non-aboriginal
heritage items identified in or abutting the Project application area: the Cottage (I191) and the
European Surveyor’s Tree (EST JN1).
Based on the assessment of construction impacts on any non-aboriginal heritage has been
undertaken as part of the EIS, it was noted that these items of heritage significance adjoin to the
project application area and thus are unlikely to be directly impacted by the Project. Mitigation
measures, outlined below, will be undertaken to minimise impacts to no-aboriginal heritage during
construction of the Project.
Should an item of non-aboriginal heritage significance, or suspected significance, be discovered
during construction, all work in the vicinity of the area will cease and the Project Environmental
Nominee will be contacted as soon as possible to determine the subsequent course of action. In the
event that suspected human skeletal remains are discovered, all works will cease and the NSW
Police and the NSW Coroner’s office will be contacted.
3.5.6.8 Socio-Economic
Based on the assessment of construction impacts on any socio-economic has been undertaken as
part of the EIS, it was noted that construction of Project may have the potential impacts on local
residents located within 650 meters of the WTS construction through temporary increase in noise
and dust levels. The community engagement strategy and communication pathways have been
developed and are outlined in section 4.4 of this Plan.
SECTION 4 IMPLEMENTATION OF THE CEMP
It is essential that all personnel associated with the construction phase of the Project comply with the
legal, contractual and environmental requirements in this CEMP and other plans and legislation.
All necessary approvals with respect to the planning and implementation of the construction phase of
the Project will be obtained by Veolia and/or by the Contractor as directed in section 2.2 of this Plan.
All relevant conditions of licences, permits, consents and approvals are to be adhered to during
construction phase. Copies of all licences, consents, permits and approvals will be held on site.
4.1 Roles and Responsibility
Environmental management is the responsibility of all individuals and organisations involved with the
Project. Project personnel and subcontractors will be made aware of environmental issues for the
Page: Page 28 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Project and their responsibilities through induction, training and awareness methods detailed in
Section 4.3 below.
The roles and responsibilities of personnel specifically responsible for implementation of this CEMP
are summarised in Table 8 below. This includes the Environment Nominee, who is appointed by the
Project Manager to control implementation of this CEMP. The Environment Nominee is granted
authority by the Project Manager to stop a particular task or activity in circumstances where
environmental controls have not been implemented to prevent harm to the environment, or
environmental controls have been shown to be ineffective or inadequate. In such circumstances, the
Environment Nominee will prescribe corrective action that will be implemented before work
recommences.
Consultants (e.g. Egologist, Environmental Planner, and Designer) will be appointed for the duration
of the Project when required to work alongside environmental personnel, construction personnel
WTF designers and engineers to advise on aspects of WTF and WTS design/construction, culverts,
chutes, drains, lining materials and timing and assist with environmental issues.
Table 8 – Summary of Key Roles and Responsibilities
R – Responsible, A – Accountable, C – Consult, I ‐ Informed
Responsibilities and Accountabilities P
roje
ct M
anag
er (
PM
)
En
viro
nm
ent
No
min
ee
Co
nst
ruct
ion
Man
ger
s/E
ng
inee
rs
Su
per
viso
rs/
Su
per
inte
nd
ent/
Fo
rem
an
Wid
er p
roje
ct T
eam
Ultimately responsible for environmental management performance of the Project R A C C I
Review, authorise and ensure implementation of the CEMP R R C I I
Assign environmental responsibilities to project personnel I R A C I
Ensure appropriate environmental training is identified and training is provided to project personnel where required C R C I I
Monitor environmental performance to ensure compatibility and continued effectiveness with the policy and objectives
A R C I I
Participate in the review of the Project's Environmental Management System C R A I I
Ensure correct and ongoing implementation of CEMP C R A C I
Liaise with project staff for ongoing monitoring and maintenance of environmental controls C R A C C
Ensure reporting of near misses, non‐conforming incidents and practices C R A A C
Conduct and report regular inspections and monitoring requirements I R C C I
Ensure actions relating to environmental non‐conformances, incidents and/or inspections are
actioned and closed out in a timely manner I R C C I
Actively participate in and facilitate SQE Risk Management workshops I R C I C
Assist with updating of CEMP as required I R C I I
Prepare Project monthly environmental reports I R C I I
Liaise with client environmental representative C R A I C
Manage and track compliance with all statutory requirements, environmental approvals, licences, and permits relating to the project
C R A I C
Page: Page 29 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
R – Responsible, A – Accountable, C – Consult, I ‐ Informed
Complaints management in consultation with Community and Stakeholder Manager, where it related to complaints of an environmental nature.
I R C I C
Ensure environmental controls are established prior to commencement of construction activities C R A A C
Ensure ER participates in the preparation of SQE Risk Management documentation I R C I A
Identify and report environmental non‐conformance I R C C C
Ensure and verify that corrective action is taken when required for non‐conforming work I R A A A
Ensure that CEMP requirements are communicated to all personnel under his/her control C R C C C
Be aware of all approval/contractual conditions relating to his/her area of work R R R R R
Perform surveillance and monitoring of environmental controls to ensure that they are established and maintained
I R A A C
Ensure rectifications of environmental controls are carried out as required I R C C C
Comply with project approval and environmental management conditions C R A A C
Ensure no reuse of any materials into a receiving environment without prior approval I R A C C
4.2 Subcontractor Management
The relationship between Veolia, Contractor and subcontractors will be managed through an
overarching Project Management Plan (PMP). The PMP has been prepared by Veolia to cover all
activities from design to operations.
All Contractor and subcontractor personnel share responsibility with the Project team for
environmental management and performance. Veolia will ensure that relevant plans, procedures and
other documentations associated with the Environmental Management System are made available to
Contractor and subcontractors as required to fulfil any responsibilities they may have, and to
communicate any requirements or responsibilities to subcontractors.
All parties will manage their respective responsibilities for the ongoing implementation of the PMP
until the end of the project.
Page: Page 30 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
4.3 Training and Awareness
Environmental training and awareness will be provided as detailed in Table 9.
Table 9 – Training and Awareness Methods
Training Outcomes Responsibility
Inductions
Project personnel (including subcontractors) will undergo a Site Induction prior to commencement on site Inductions will include but are not limited to:
Purpose, objectives and key issues of the CEMP
Conditions of environmental licences, permits and approvals
Emergency response procedures and reporting processes for environmental incidents
Responsibilities and key contacts
Induction records will be maintained to confirm that all relevant personnel have been appropriately inducted
Inductions will be regularly reviewed and updated as required e.g. when significant changes occur on-site or within the environmental management framework of the project
Project Manger
Pre-start meetings
Pre-start meetings will be undertaken at the beginning of each day before work commences with all project personnel (including subcontractors as required) and managed by Contractor
Specific environmental issues relevant to the day’s work, e.g. working hours, will be raised and discussed at these meetings as required, and included in all SWMS/JSEA’s
Contactor
Toolbox meetings
Environmental awareness training will be provided to the workforce (including subcontractors) via weekly held toolbox meetings
Toolbox meetings will be recorded in the Project Pack
Any relevant outcomes or findings of environmental site inspections or audits shall be communicated to on ground personnel for improvements to be made
Positive feedback shall also be presented at these meetings
Contractor
Specialised Training
Spill prevention and control procedure
Erosion and sediment control plans
Vegetation clearing procedures
Awareness of waste management and the procedures to follow for proper waste recycling and disposal
Contractor
Internal Training Risk Based Investigation. Environment
Nominee
SQE Alerts. Distributed at tool box meetings and posted on notice boards Project Manager
4.4 Stakeholder Management Plan
Veolia is committed to meaningful stakeholder engagement. Key external stakeholders for the project
are state and local government departments and statutory authorities that are responsible for issuing
relevant environmental approvals and permits as well as community groups. Liaison with these
stakeholders at each phase of the project is critical to ensure that all of the legislative and statutory
obligations are met, all received complaints are investigated and addressed. Key stakeholders have
been consulted in the pre-planning phase and will continue to be consulted during, and in some
cases, after construction.
Page: Page 31 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Ongoing consultation with the community will be undertaken to ensure that timely information is
provided to assist in minimising disruption or inconvenience. The Project Manager and Contractor will
be responsible for providing advance notice of changed traffic conditions, which may affect the local
community.
Given the minor nature of works external to the site, communication methods, which may be
considered, include:
letterbox drops to the local neighbourhood;
public notices in local newspapers;
direct consultation for individual properties identified as directly affected.
Details in relation to community liaison, complaints handling, reporting and record keeping,
applicable to the construction phase can be found in Stakeholder Management Plan (Refer to
Appendix B7).
4.5 Incident and Emergency Response
A key objective of this CEMP is to identify potential risks, and to develop, and maintain measures to
manage them. Notwithstanding this, Veolia recognises that unforeseen incidents can arise.
Veolia operates under an Emergency Response Plan whenever a major incident, emergency or crisis
could lead to public health, safety or environmental issues.
Veolia’s approach to incident and emergency response management includes:
Risk Analysis - The identification of hazards and risks that could impact the community,
environmental and operational implications.
Prevention – The planning and documentation of prevention and mitigation activities for all
major hazards, and allocation of responsibility for their implementation.
Preparedness – The development, implementation and review of specific incident
management plans and processes to manage identified risks, the training of staff, and
establishment of facilities to ensure the company can respond effectively to an incident.
Response – The issue of warnings and establishment of processes for effective notification
of incidents, and mobilisation of resources to combat the incident or threat.
Recovery – The return to normal operations, management of debriefs, and implementation
of lessons learnt from the response process.
The following priorities are adopted when combating an incident / crisis:
protection of human life and welfare;
protection of the environment; and
protection of Veolia’s assets.
4.5.1.1 Risk Assessment
The Veolia Board and executive management team are committed to a coordinated approach to risk
management throughout the company’s operations, ensuring any issues that could affect the
company’s and stakeholder’s performance, values, or reputation are identified and addressed.
The environmental risk management process used by Veolia is consistent with ISO 31000:2009 –
Risk Management and Veolia’s Risk Management procedure (PR-ANZ-13-444-2). The process is
Page: Page 32 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
implemented throughout the business and is focused on the following major environmental risks
categorise in Table 10.
Prior to the commencement of the construction works, Contractor will undertake a risk assessment to
identify the potential hazards and environmental risks and document in the Safe Work Method
Statement/ Job Safety & Environment Analysis (SWMS/JSEA) required work methods.
The risk assessment will be updated as required during the construction works and any changes
required to the management strategies shall be reported to Veolia.
Table 10 – Environmental Risks
Hazard Impacts (human
health&/or environment) Inherited
Risk Level Pre-emptive Actions
Residual Risk Level
Sediment laden water off site, including mud tracked onto roadways
Environment Medium Construction Environmental Management Plan (CEMP) - implement controls identified in the ESCPs (as detailed in the WMP)
Low
Pollution of land or stormwater from hydrocarbon spills from machinery or fuel storage
Human Health and/or Environment
Medium Plant Hazard Assessments;
Daily plant checklists ;
CEMP and supporting management plans implementation.
Low
Generation of dust from mobile equipment/vehicles and exposed areas
Human Health and/or Environment
Medium Cessation of dust generating activities during adverse weather conditions (e.g. strong winds);
Limiting vehicles to specified routes to construction sites and ensuring speed limits are adhered to;
Dust suppression on site at all times ;
Trucks to cover loads.
Low
Impacts to local receivers (High School, properties, businesses) due to noise, vibration and visual pollution
Human Health and/or Environment
Medium Comply with approved construction hours Communicate with staff and community the approved hours of work/ program;
Implement controls identified in the CNMP.
Low
Bushfire Human Health and/or Environment
High Implement management controls identified in the Bushfire Risk Management Plan
Medium
4.5.1.2 Incident Investigation
All incidents will be documented, and where required, due to the severity or ongoing nature of the
incident, investigations conducted and action plans established in order that the event does not occur
again by Contractor. Further guidance on when investigations are required is detailed in Figure 5
below; Veolia representative will be appointed to participate in an incident investigation as required.
Where lessons are learnt from the investigation or current procedures are identified as being
ineffective, the CEMP will be revised by ER to include the improved procedures or requirement. An
environmental investigation includes the following basic elements:
identifying the cause, extent and responsibility of the incident;
identifying and implementing the necessary corrective action;
implementing or modifying controls necessary to avoid a repeat occurrence of the incident;
identifying the personnel responsible for carrying out the above actions;
recording any changes in written procedures required.
4.6 Notification and Action Protocol
Any notifiable environmental incidents or potential incidents associated with the Project construction,
with actual or potential significant impacts on people or the biophysical environment, will be notified
Page: Page 33 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
as soon as practicable to DP&E, Lithgow City Council, other relevant agencies and Customer. This
notification will be followed by a written report within 7 days of the incident.
A notifiable environmental incident is a pollution incident where there is a risk of causing or
threatening material harm to the environment. A pollution incident includes a leak, spill or escape of a
substance or circumstances where this is likely to occur. Material harm includes onsite and offsite
actual or potential harm to:
the health or safety of humans;
the environment; or
property damage resulting in significant costs to remediate
If a notifiable environmental incident occurs, Veolia staff and Contactor will immediately notify one or more of the following personnel (refer Section 4.6.1.1 Emergency Contacts):
Project Manager
Environment Nominee
That person/s will then decide whether to notify Customer, DP&E or both. The Customer will notify
the EPA. Where these regulators are notified, other regulatory authorities that require notification
include:
Lithgow City Council within which jurisdiction the incident has occurred;
Ministry of Health;
Rural Fire Service;
Office of Environment and Heritage;
Forestry Corporation of NSW; and
Any other relevant authorities.
Table 8 below lists the mechanisms to be followed in the event that a pollution incident has the
potential to impact the surrounding community, in order to minimise the risk of harm.
Table 11 – Communication Mechanism
Pollution Incident Scenario
Potential Impacts What to do Who to Notify Communication
Mechanism
Sediment laden water, mine water, hydrocarbon or chemical entering stormwater drain/ discharge to environment
People and waterways environment
Bund area, block stormwater drain to prevent further pollution
Environment Nominee, Customer, Lithgow City Council, Immediately during clean-up of incident
Door knock
Telephone/ E-mail
Dust Air quality issues, loss of amenity
Cease works immediately Environment Nominee, Customer, adjacent businesses and school
Door knock
Telephone/ E-mail
Noise/Vibration Noise/Vibration, loss of amenity
Cease works immediately Environment Nominee, Customer, adjacent businesses and school, Lithgow City Council
Door knock
Telephone/ E-mail
Fire People and environment Cease works immediately Environment Nominee, Customer, Rural Fire brigade
Telephone
Door knock
4.7 Emergency Contacts
The following are the internal emergency contacts for the project construction, refer to Table 12 below.
Page: Page 34 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Table 12 – Project Emergency Incident Reporting Contacts
Position Name Phone Number Email
Project Director Nick Stokes-Hughes +61 428 672 115 [email protected]
Project Manager Tom Roche +61 438 880 470 [email protected]
Environmental Representative Elena Ivanova +61 4155 566 20 [email protected]
4.8 Pollution Incident Management
Incidents will be responded to as outlined in the incident response flow chart (Figure 5).
In summary:
1. STOP WORK and NOTIFY INTERNAL Supervisor and Environment Reprsentative
2. PREVENT further environmental contamination/ spillage / pollution etc. (if safe to do so)
3. CONTAIN environmental contamination/ spill / pollution
4. CLEAN UP environmental contamination/ spill / pollution
5. NOTIFY EXTERNAL as described in section 4.6 of this Plan.
Figure 5 – Incident Response Flow Chart
Incident Occurs
Person who caused or discover the incident
Contact Project Manger, ER or Construction Manager and advise nature, extent and
exact location of incident
If it is safe to do so, attempt to control the incident, otherwise move to a safe location
and await further instruction
Assess Response Capability/ Notify external assistance if required
Log the incident and complete appropriate reporting measures via Vault, Veolia’s SHEQ
system/ Contactor incident management system
Proceed external notification, if required
Complete Incident Investigation and Reporting process
Review contingency measures and implement changes from the lesson
Ensure site is remediated/ clean up
Page: Page 35 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
4.9 Environmental Performance Criteria
The installation and maintenance of physical environmental controls on site will be the responsibility
of the Contractor, Project Manager and Supervisors. The environmental objectives and performance
criteria described in section 2 of this Plan are addressed in the supporting management plans for key
specific environmental aspect the Project. The objectives and performance criteria have been
developed based on Federal, State and Local Legislation, the Customer’s Project Scope
Requirements, the CoDC. They guide management and mitigation measures that minimise impacts
to identified environmental and social values, and guide performance, monitoring and contingency
plans for the project are outlined in Table 13.
Table 13 – Environmental Performance Criteria
Environmental Aspects
Objectives Performance Criteria
Aboriginal Cultural Heritage discovery of Aboriginal cultural heritage.
Comply with approved Cultural Heritage Management Plan (CHMP). Prevent accidental harm to previously undiscovered items of Aboriginal heritage items.
All pre – construction, during construction and post construction management recommendations within approved CHMP to be implemented. Follow contingency requirements set out within approved CHMP in the event of unexpected discovery of Aboriginal cultural heritage.
Water Quality
Minimise impacts to surface water.
Minimise erosion and sedimentation on site. Prevent sediment-laden water or material from site entering nearby environmental receptors including waterways, stormwater and vegetated areas.
Comply with Water Management Plan.
Integrate Water Sensitive Urban Design opportunities into the design to manage stormwater runoff from project site and Implement sediment controls in accordance with Managing Urban Stormwater: Soils and construction 4th edition. “The Blue Book”.
Implement the Water Management Plan.
Biodiversity Minimise impacts to native vegetation and fauna.
Restrict native vegetation removal to only that identified for approval.
Minimise impacts to fauna by using an appropriately qualified wildlife handler.
Minimise impacts to Tree Protection Zones for trees to be retained.
No increase in diversity or coverage of weed species within the construction corridor and immediate area.
Maintain habitat connectivity in surrounding landscape.
Implement the Biodiversity Management Plan which includes weed management mitigation measures.
Follow Vegetation Clearance Procedure.
Noise and vibration Minimise amenity impacts to local community/residents Implement noise and vibration control measures associated with construction in accordance with the Construction Noise Management Plan (CNMP). Follow contingency requirements set out within approved CNMP in the event of non-compliance and then additional noise mitigation measures are assessed as being required.
Traffic and Transport Minimise impacts to the local community and traffic flow. Implement Construction Traffic Management Plan.
Contamination Beneficial reuse of contaminated soil on site to occur where possible.
Avoid contaminating soil, groundwater and surface water as a result of the project works.
Reuse of contaminated soil to be in accordance with the National Environmental Protection (Assessment of Site Contamination) Measure.
Test any waste soil in accordance with a Waste Classification Guideline and disposed of soil at appropriate licenced facilities if required.
Implement on site controls for identified soil contamination and in accordance with EPA Guidelines relating to contamination.
Construction Waste
Minimise generation of waste. Monitor waste levels and ensure diversion of materials from landfill where possible.
Implement Waste Management Plan
Air Quality
Mitigate hazards and prevent nuisance and unnecessary interference or disturbance with people or property.
Minimise the environmental impact and effect of the works on local community groups.
Implement dust control measures discussed in section 3.5.6.4 of this Plan.
Monitor dust levels to occur and implement mitigation measures as required.
Page: Page 36 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Environmental Aspects
Objectives Performance Criteria
Bushfire Risk Minimise bushfire risk Incorporate mitigation measures and avoidance measures into design
4.10 Contingency Plan
Where significant risks to environmental or heritage values, that were previously unknown, are
identified during Project works, then contingency measures will be implemented to ensure impacts
are minimised.
A summary of contingency measures detailed in the supporting plans to the CEMP are outlined in
Table14 below. Table 14 – Summary of Contingency Measures
Risk Contingency Measures Plans references Responsibilities
Removal of mature vegetation providing habitat and community benefit.
An ecologist will conduct pre-construction surveys to confirm if any additional threatened species are present other than that already approved
If new threatened species are located other than previously identified, the vegetation will be fenced off with “no go zone” signage and approval requirements will be confirmed in consultation with OEH. If required, approval will be sought from relevant regulators.
Section 4.3of the Biodiversity Management Plan
Environment Nominee Project Manager / Contractor
Noise exceedance
Vibration impact
Elevated levels of noise or vibration may be identified either by receipt of a noise complaint from a third party suggesting that there is an excessive noise from the Project Construction or by detection of noise as a result of the routine monitoring by site personnel.
Monitor noise and vibration levels to confirm validity of amenity impacts/complaint and implement further noise and vibration controls if required.
Section 3.5 of the Construction Noise Management Plan
Environment Nominee Project Manager / Contractor
Discovery and/or accidental damage to items of Aboriginal cultural heritage significance
Implement contingencies set out within approved Aboriginal Cultural Heritage Management Plan, including ‘stop work’ upon discovery/damage to item.
Sections 6.2&6.3 of the Aboriginal Cultural Heritage Management Plan
Environment Nominee Project Manager / Contractor
Erosion of exposed areas mobilises sediment into environment
During periods of high rainfall monitor and maintain erosion and sediment controls frequently determine if further controls are required to increase effectiveness.
In the event sediment laden water enters the environment, control and contain the source to prevent further pollution of stormwater.
Section 5.3 of the Water Management Plan
Environment Nominee Project Manager / Contractor
Dust Emissions If visible dust is evident from the project area, review the use of dust suppression measures during periods of dry weather and implement more effective controls.
Cessation of dust generating activities during adverse weather conditions (e.g. strong winds).
Section 3.5.6.4 of this CEMP
Environment Nominee Project Manager / Contractor
4.11 Performance Reporting
During the construction phase of the Project, the Contractor/ Environment Nominee or site nominee
will collect and record all environmental performance data for Veolia’s reporting obligations. Veolia
will provide report to the Customer relating to compliance with contractual and Customer
requirements under the contract obligations.
Page: Page 37 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
4.11.1 Progress Reporting
The progress of the Project will be communicated to Secretary (DP&E), predominantly through the
quarterly progress reports. The Project Manager will be responsible for preparing the progress
reports including:
detailed summary of the construction activities were been completed in the past three
months (as built report);
forecast completion date including indication of any poetical delays;
year look-ahead program including mitigation measures to ensure that WTF is operational
by July 2019;
progress photographs.
The quarterly progress reports will be published on the Veolia website (http://www.veolia.com/anz/)
and will be available for all interested parties.
4.11.2 Annual Reporting
By the end of March each year, Veolia’s suitable qualified person will prepare annual review of the
Project environmental performance (refer to sections 5.3 and 5.4 of this plan) for the previous
calendar year and prepare an Annual Report, which will be submitted to Secretary (DP&E).
Page: Page 38 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
SECTION 5 MONITORING AND REVIEW OF THE CEMP
5.1 Monitoring and Inspections
The Project’s environmental performance will be tracked through monitoring and inspections as detailed in Table 15.
Table 15 – Summary of Monitoring and Inspections
Type of Control Actions
Inspection Environmental Nominee will perform daily informal environmental inspections during the site establishment, construction and site demobilisation phases. Throughout construction at a minimum one weekly documented environment and sustainability inspection is to be completed.
Inspection checklists and any corrective actions identified will be recorded in the Project Management System.
Monitoring Environmental Nominee will perform weekly environmental monitoring during the site establishment, construction and site commissioning phases.
Details of specific monitoring requirements is included in the supporting management plans attached to this CEMP.
Monitoring results and any corrective actions identified will be recorded in the Project Management System.
Calibration of monitoring equipment
Monitoring equipment will be calibrated in accordance manufacturing instruction
Monitoring equipment will be calibrated prior to use
Any equipment identified as having doubtful accuracy or precision will be removed from use and recalibrated
Where any monitoring equipment is found to be out of calibration, the validity of the previous monitoring results will be assessed and documented
Records of equipment will be recorded via Project Management System.
Specialist surveys, inspections and monitoring
Certain specialist environmental inspections, performed by consultants and sometimes third parties are required prior to or during certain Project activities including but not exclusive to:
Pre-clearance surveys of the Project area by a qualified ecologist to demine flora species to be removed;
Baseline contamination assessment by a qualified consultant to assess level of contamination presented on site;
Soil sampling and analysis of contamination status;
Monitoring of tree clearing and inspection of trees for presence of fauna requiring capture and relocation, veterinarian care or euthanasia,
Weed identification and eradication services. A qualified subcontractor visits the Project area at least annually, preferably during times when weed growth is most common such as autumn and spring and identifies the presence of any weeds;
Noise monitoring if required in response to noise complaints.
5.2 Auditing
5.2.1.1 Internal audits
Business system audits are conducted to support continuous improvement by ensuring that the
management system and the business process are regularly assessed in a consistent and
systematic manner and in accordance with Audit Procedure (PR-ANZ-1-475). These audits include
the EMS.
The CEMP compliance audits will be undertaken by suitably qualified and experienced Veolia Safety, Health, Environment and Quality personnel not directly associated with the project and in accordance with the audit schedule.
The audits will verify:
effectiveness of the system to meet business objectives;
whether the actions carried out conform to the stated intention of the management system;
Page: Page 39 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
adequacy of implemented controls to minimise high risk activities;
compliance with company policies, legislation and industry standards;
compliance with contractual and Customer requirements;
whether the stated objectives in policy documents are being met;
identify areas for continuous improvement.
5.2.1.2 External audits
As part of Veolia’s commitment to having each of its operational sites certified to ISO 14001, external
certification and surveillance audits will be conducted by a registered certification body.
5.2.1.3 Audit findings
Audit findings will be reported to management and management system representative(s) of the
Project for inclusion in the management review processes.
Non-conformances and opportunities for improvement identified through internal and external audit
processes will be recorded, reported and responded to via the company’s electronic issues
management system.
5.3 Review of the CEMP
Annual management reviews of the Project CEMP and the environmental performance of the Project
will assess the continuing suitability, compliance with legislative requirements, adequacy and
effectiveness of the on-site environmental management measures implemented.
The inputs to the management review process will include (but not be limited to):
internal and external audits findings;
incidents management and investigation of non-conformance events, incidents, near misses
and management of all complaints received;
implementation of all compliance and legislative changes as identified at a corporate level; and
training and awareness;
monitoring results of the previous year; and
analysis of potential cause of any significant discrepancies between the predicted and actual
impacts of the Project construction phase.
The output of management review will include any decisions and actions related to:
possible changes to the management plans, procedures, practices, objectives and targets
associated with the environmental management of the Project construction;
improvement of the effectiveness of the EMS and its processes; and
resource needs.
System reviews are carried out at least annually by the Veolia’s suitable qualified person, which will
include a desktop review of the Project and CEMP and supporting plans, with the same agenda as
the Management Review and presented to the Project Manager.
The CEMP may be reviewed more regularly due to a change in construction activities, where
objectives are not achieved.
The updated plan will approved internally by the Project management and if it deems necessary, the
CEMP will be provided to relevant stakeholders for review and comment if required and forwarded to
the Secretary of DP&E for approval.
Page: Page 40 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
5.4 Corrective Action
Corrective and preventative actions may be identified from inspections, audits, non-conformances,
incidents, management reviews and complaints. Once identified an Action Plan could be developed
as an overarching document that will provide complex direction for improvement of different elements
of the Project (e.g. quality, safety, and environment) or be specific for Project Environmental
Management (FM-ANZ-2-231 Action Plan – Veolia template).
Management reviews are scheduled to assess the progress of implemented corrective action, its
adequacy and effectiveness. Reviews are undertaken in accordance with the corporate Business
Planning Activity Timeline outlined in the Business Planning Procedure (PR-ANZ-2-442).
Page: Page 41 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
APPENDICES
Appendix A - Copy of the Development Consent
Page: Page 42 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B1 - Water Management Plan
Page: Page 43 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B2 - Biodiversity Management Plan
Page: Page 44 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B3 - Aboriginal Cultural Heritage Management Plan
Page: Page 45 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B4 - Construction Noise Management Plan
Page: Page 46 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B5 - Construction Traffic Management Plan
Page: Page 47 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B6 - Stakeholder Management Plan
Page: Page 48 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix B7 - Construction Waste Management Plan
Page: Page 49 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix C - EPL requirements – EPA Clarifications
Page: Page 50 of 50 Document: SMPPS-O-00-M13-00-03 Date: 27.10.2017
PLAN Construction Environmental Management Plan
Printed documents are uncontrolled versions. Check printed copies against the current electronic version for validity.
Appendix D - Pre-Construction Compliance Report