  • Appendix: 1 Service Item Descriptions

    Mobily_Swap_Implementation

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 2 of 67 Issue 2013-02-08 printed: December 11, 2013

    Table of Contents 1. Implementation (Generals) ................................................................................ 5 2. 00033403 C antenna line (For complete Feeders Per site) ............................ 6 3. 00038272 I 7-8 antenna line basic (1 run up-to any length) ........................... 7 4. 00038304 I Flexi BS RF modules ...................................................................... 8

    5. 00047199 I Flexi BS system module ................................................................ 9

    6. 00001357 I panel antenna up to 3m ............................................................... 10

    7. 00038290 IC FO cable basic............................................................................ 11

    8. 00001382 IC IP hub type device ..................................................................... 12

    9. 00038297 IC LAN cable basic ......................................................................... 13

    10. 00045202 IC remote RF module feed basic (Per site) ................................... 14 11. 00039294 InstM Flexi BS ................................................................................. 15

    12. 00073261 BTS INST. MATERIALS .................................................................. 16

    13. 00007502 M LAN cable basic .......................................................................... 17

    14. 00045205 M remote RF module feed add (2x5m) .......................................... 18 15. 00045204 M remote RF module feed basic (2x20m) ..................................... 19 16. 00038731 M singlemode FO cable basic ....................................................... 20

    17. 00000890 Multiple travel ................................................................................. 21

    18. 00056303 On site BS integration .................................................................... 22

    19. 00001513 Rem BTS/BSC/TCSM modules ...................................................... 23

    20. 00001485 Site survey BS site ......................................................................... 24

    21. 00001487 Transport DOP/Site to Site 0-3,5t regulr ....................................... 25

    22. 00001344 I BSC ................................................................................................. 26

    23. 00001383 IC lamp panel ................................................................................... 28

    24. 00001390 I MHA-TMA ....................................................................................... 29

    25. 00001413 ICIntg PIU ext ................................................................................... 30

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 3 of 67 Issue 2013-02-08 printed: December 11, 2013

    26. 00001515 Rem proprietary PCM ...................................................................... 31

    27. 00001516 Rem subrack server or IP hub device ............................................ 32

    28. 00003379 I blade server chassis ..................................................................... 33

    29. 00003934 Site survey core ............................................................................... 34

    30. 00003957 Rem cabinet BSC-RNC .................................................................... 35

    31. 00033865 Travel low ......................................................................................... 37

    32. 00033872 Travel TRS ........................................................................................ 38

    33. 00033875 Rem cabinet BSC-RNC add ............................................................ 39

    34. 00038266 I 1 5-8 antenna line basic (1 run upto any length) ........................ 41 35. 00038268 I RDSA Cables (For Diversity Sharing) .......................................... 42 36. 00038285 I floor mount 19-23 cab ................................................................... 43

    37. 00038559 InstM BSC ........................................................................................ 44

    38. 00038637 InstM packaging for cables ............................................................ 46

    39. 00038638 InstM packaging for PIUs ................................................................ 47

    40. 00038640 InstM packaging for cabinet ........................................................... 48

    41. 00039295 I indoor Flexi BS cab ....................................................................... 49

    42. 00040307 I ODF block or module .................................................................... 50

    43. 00040308 M ODF block (48 ports) ................................................................... 51 44. 00038565 InstM TCSM ...................................................................................... 52

    45. 00001361 I TCSM .............................................................................................. 53

    46. 00073251 Implementation BTS 2G and UMTS900 for swap .......................... 54

    47. 00073252 BTS Implementation TDD LTE for Swap sites .............................. 56

    48. 00001347 I diplexer ........................................................................................... 58

    49. 00001504 Rem MHA-TMA ................................................................................ 59

    50. 00001509 Rem omni or panel antenna up to 2m ............................................ 60

    51. 00007508 M floor mount 19-23 open frame .................................................... 61

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 4 of 67 Issue 2013-02-08 printed: December 11, 2013

    52. 00038286 I floor mount 19-23 open frame ...................................................... 63

    53. 00007509 M floor mount 19-23 cab ................................................................. 64

    54. 00073254 Implementation BTS Modules Re-arrangement ............................ 66

    55. 00073255 BTS Modules Removal and Installation ......................................... 67

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 5 of 67 Issue 2013-02-08 printed: December 11, 2013

    1. Implementation (Generals)

    Includes These activities are included for every service item:

    Unpacking the delivery Inventory checking of the delivery and discrepancy reporting Preparation of documentation for the work performed under the specific service item as part

    of the site folder or link folder Waste disposal including transportation, recycling of the waste according to our

    environmental requirements and cleaning of the site in relation to and in the scope of the works performed under the specific Service Item.

    Installation planning activities for base station or transmission sites, which may include the following

    Preparation of Site Layout drawings and sketches based on existing site documentation and drawings as part of the Site Folder for one network element or a site with all related equipment (DC power supply, 19-inch frames or cabinets, feeder and antenna lines, antennas, peripherals, lamp panels).

    Listing of Ancillary Materials and determining their quantities (can be part of the Site Folder or Link Folder) for the site or the network element and all related equipment.

    Implementation supervising activities for a network element being implemented on a Base Station or Cellular Transmission or core site, which may include the following

    Supervising of implementation activities at site in line with local implementation processes (including participation in the Pre Installation Site Meeting (PSIM), coordination of the implementation activities at the site.

    Verification of delivery-, installation-, commissioning-, integration- and customer signoff phases according to the contract scope.

    First line technical assistance for field teams and act as main contact with project team for fault resolution.

    Reporting of site-specific implementation progress to project management and updating of project tools.

    Controlling, scheduling and progress monitoring of field based implementation resources.

    Compilation of Site or Link Folder from documents created in course of the implementation throughout the implementation process until customer signoff.

    Ensuring the site quality.

    Excludes These activities are excluded from the service item, if not indicated in the includes section of that specific service item

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 6 of 67 Issue 2013-02-08 printed: December 11, 2013

    2. 00033403 C antenna line (For complete Feeders Per site) Commissioning of antenna line

    Service Commissioning of the antenna line in its complete length including antenna measurements. Project specific processes and work instructions with limitations and thresholds to be reached are applicable and will be defined accordingly. The interface for the measurements (top of BTS or internal jumpers) will be defined from the project. As standard measurements can be counted tests such as Return Loss, Cable Loss, Antenna Isolation Test and Distance To Fault. The measurement equipment such as SiteMaster has to be calibrated and must fulfill the specifications given from the project.

    Excludes Installation of antenna. Installation of antenna line Installation of active and passive antenna line components, such as Bias Tee, MHA, diplexer, triplexer, combiner, etc. Testing of any other equipment than feederline and antenna.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 C Antenna Line 100 % 1 pcs 2 Return Loss Measurement 100 % 1 pcs Processes, work instruction and

    measurement limits according the project are applicable

    3 Cable Loss Measurement 100 % 1 pcs Processes, work instruction and measurement limits according the project are applicable

    4 Isolation Test Measurement 100 % 1 pcs Processes, work instruction and measurement limits according the project are applicable

    5 Distance To Fault Measurement 100 % 1 pcs Processes, work instruction and measurement limits according the project are applicable

    6 Documentation 100 % 1 pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 7 of 67 Issue 2013-02-08 printed: December 11, 2013

    3. 00038272 I 7-8 antenna line basic (1 run up-to any length) Installation of a 7/8" antenna line basic any length (As required on site)

    Service Collection of materials from the DoP/WH and its delivery to site Dismantling and reassembly of the cable entry or gland. Installation of 1 run 7/8" feeder cable in the required length with fixing accessories (clamps, cable ties), grounding kits and waterproofing materials, labels and connectors. Installation of jumper cables with fixing accessories, waterproofing materials and labels, Termination of the antenna line to the Base Station. Termination of the antenna line to the antenna including waterproofing of the outdoor connector (if antenna exists).

    Excludes Installation of antenna. Installation of active and passive antenna line components, such as Bias Tee, MHA, diplexer, triplexer, combiner, etc. Installation of cable support structures. Installation of any other type of RF feeder cable. Commisioning of antenna line and antenna

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Feeder Cable Installation 100 % 1 run Incl. Grounding and waterpr. 2 Jumper Installation 100 % 1 lot Incl. Sealing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 8 of 67 Issue 2013-02-08 printed: December 11, 2013

    4. 00038304 I Flexi BS RF modules Installation of Flexi base station RF modules

    Service Collection of equipment and materials from the DoP/WH and its transport / delivery to site Installation and fixing of Flexi base station plinth on floor if required. Installation of grounding cable for the Flexi base station plinth with fixing accessories (cable ties), labels and connectors (lugs) up to the required length including testing of the complete cable run. Installation of Flexi base station RF modules including casing, fixing of earthquake protection screws, front and back covers if applicable. Installation of grounding cable between Flexi base station RF module and Flexi base station plinth or the nearest grounding point with fixing accessories (cable ties) including testing of the complete cable run if applicable. Installation of delivered internal power cabling between Flexi base station RF modules and system module, including fixing accessories (cable ties). Installation of delivered internal databus cabling between Flexi base station RF module and system module, including cleaning of optical connectors and fixing accessories (cable ties). Preparation and Installation of Jumpers (including clamps and Weather proofing) as required on site from the RF module to the Antenna. Testing of the Jumpers (VSWR etc) if required and attach test report. Installation of RDSA cables and FO cables between 2G and 3G modules as per given site configuration Re-configuration / Re-commissioning of existing 2G BTS if required Azimuth and Tilt Adjustment for antennas if required on site.

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 9 of 67 Issue 2013-02-08 printed: December 11, 2013

    5. 00047199 I Flexi BS system module Installation and installation testing of Flexi base station system modules

    Service Collection of equipment and materials from the WH and its delivery to site. Installation of integrated transmission plug-in unit (Flexi base station system module). Installation of Flexi base station system module including casing, fixing of earthquake protection screws, front and back covers if applicable. Installation of grounding cable between Flexi base station system module and Flexi base station plinth with fixing accessories (cable ties) including testing of the complete cable run. Installation of DC power cable with fixing accessories (cable ties), labels and connectors (shoes) up to the defined length if applicable including testing of the complete cable runs. Installation of alarm cable with fixing accessories (cable ties), labels and connectors up to the defined length including testing of the complete cable run. Installation of labels for DC breakers, AIB and ADM. Terminating of FlexBus cable, fiber optic or PCM cables to the integrated transmission plug-in unit (only for existing cables). Installation testing of the Base Station system unit and integrated transmission plug-in unit. Installation of DC Circuit Breaker and DCDB if required.

    Excludes Installation and Commissioning of an external DC Power Supply System. Supply, installation and testing of transmission connections and links. Installation and commissioning of transmission indoor unit (other than integrated).

    Special cases and other requirements

    Bill of Quantities Pos Category Occ. Qnt Unit Compo

    nent Remark

    1 Installation of Flexi BS system module

    100 % As required

    pcs Incl. fixing, casing, front and back covers

    2 Installation of Int. TRS PIU 100 % As reuired

    pcs Incl label, TRM vable termination term.

    3 Installation of Grounding Cable 100 % As required

    site Incl. testing

    4 Installation of DC Power Cable 100 % As required

    site Incl. labeling & testing

    5 Installation of Ext. Al. Cable 100 % As required

    site Incl. labeling & testing

    6 Installation testing of Flexi BS system module

    100 % As required

    pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 10 of 67 Issue 2013-02-08 printed: December 11, 2013

    6. 00001357 I panel antenna up to 3m Installation of RF panel antenna higher than 0.5 and up to max. 3m

    Service Installation of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length. Installation of labels for the antenna. Installation of panel antenna bigger than 0.5m and up to 3m with its own mounting brackets and tilting kits. Termination of the grounding cable to the grounding termination point (port of a grounding bus bar). Termination of the feeder line to the antenna (only if RF feeder exists). Adjustment of the panel antenna azimuth and tilt. Installation and commissioning of RET (2 per antenna) including the installation of RET control cable.

    Excludes Installation of antenna holder pole or mast. Installation of omni or panel antenna smaller than 0.5m or bigger than 2m. Antenna line testing.

    Special cases and other requirements

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Grounding Cable Installation 100 % 7 m Incl. labeling 2 RF Antenna Installation 100 % 1 pcs Inc. fixing & labeling 3 Adjustment of RF Antenna 100 % 1 pcs Azimuth, tilting 4 RET Installation 100% 2 pcs 5 RET Control cable installation 100% 2 pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 11 of 67 Issue 2013-02-08 printed: December 11, 2013

    7. 00038290 IC FO cable basic Installation and testing/commissioning of specified length of fiber optic cable or patch cord

    Service Installation of up to specified length of fiber optic cable or patch cord with fixing accessories, labels and connectors (if needed). Installation of protection tube or conduit for the fiber optic cable. Cleaning of FO connectors and plugging on both ends according installation manual Testing of the fiber optic cable run in its complete length. Terminating of the fiber optic cable run to the equipment or the ODF.

    Excludes Installation of fiber optic cable and its protection above specified length.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Installation of FO Pigtail Cable 100 % 1 pcs Incl. fixing and labelling 100 % 2 pcs Pigtail splicing

    2 Installation of FO Cable 100 % 20 m Incl. Protection, label, term, test 3 Cleaning of FO connector 100 % 2 pcs Standard cleaning process 4 Commissioning of FO Cable 100 % 20 m Incl. Documentation

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 12 of 67 Issue 2013-02-08 printed: December 11, 2013

    8. 00001382 IC IP hub type device Installation and commissioning of IP LAN hub, switch or router

    Service Installation of AC/DC power cable with fixing accessories (cable ties), labels and connectors (cable shoes) up to the defined length. Installation of labels for the AC/DC breaker. Installation of IP LAN hub, switch or router and its mounting into a 19-inch cabinet including the installation of fixing material. Commissioning of the IP LAN hub, switch or router if applicable.

    Excludes Installation and testing of interface cables, such as LAN. Installation of additional cable lengths for cables delivered under this Service Item.

    Special cases and other requirements The supply of cable ties, labels and rack fixing materials (bolts and clips) is also included in this Service Item.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 AC/DC Power Cable Installation 100 % 4 m Incl. labeling & testing 2 IP LAN Device Installation 100 % 1 pcs 3 IP LAN Device Commissioning 100 % 1 pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 13 of 67 Issue 2013-02-08 printed: December 11, 2013

    9. 00038297 IC LAN cable basic Installation and testing/commissioning of basic length of LAN cable

    Service Installation of LAN cable with fixing accessories, labels and connectors. Testing of the LAN cable run in its complete length (if applicable). Terminating of the LAN cable to an existing patch panel at each end.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 LAN Cable Installation 100 % 10 m Incl label, term, test

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 14 of 67 Issue 2013-02-08 printed: December 11, 2013

    10. 00045202 IC remote RF module feed basic (Per site) Installation of remote RF module feed

    Service Installation and fixing of the OVP boxes if applicable. Installation of grounding cable for the OVP boxes with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length including testing of the complete cable run if applicable. Installation of AC or DC power cable with fixing accessories (cable ties), labels and connectors (shoes) up to the defined length if applicable including testing of the complete cable runs if applicable. Installation of labels for AC or DC breakers if applicable Installation of fibre optic cable with fixing accessories (cable ties), labels and connectors up to the defined length, including cleaning of connector and testing of the complete cable runs. Installation of protection tube or conduit for the fiber optic cable if required Testing of the fiber optic cable run in its complete length.

    Excludes Installation of Flexi WCDMA base station system module(s) or/and RF module(s) Installation of 19" rack, Flexi plinth, indoor FCIA cabinet or outdoor FCOA cabinet. Installation and commissioning of base station antenna line. Installation and commissioning of an external DC power supply system. Transportation of the equipment to the site.

    Bill of Quantities Pos Category Occ. Qnt Unit Comp

    onent Remark

    1 Installation of OVP box 100 % As required on site

    pcs Incl. fixing or pole mounting

    2 Installation of grounding cable 100 % As required pcs Incl. labeling & testing, length 3m 3 Installation of DC power cable 100 % As required m Incl. labeling & testing 4 Installation of FO Cables 100 % As required m Incl. labeling & testing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 15 of 67 Issue 2013-02-08 printed: December 11, 2013

    11. 00039294 InstM Flexi BS Installation materials for Flexi base station

    Material

    Bill of Quantities Pos Category Occurrence Qnt Unit Remark

    1 Grounding cable complete 100% 3 m MK 16 GND CABLE Y/G (reel) 100% 2 pcs RS Cable shoe 16mm2 / M8

    2 DC Power Cable Complete 100% 10 m DC cable 2x16mm2 100% 4 pcs Cable lug, 16mm2

    3 LAN Cable Complete 100% 10 m Pre-made LAN cable 4 Label 100% 2 pcs Label as per Mobily Standard 100% 0.04 pcs Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 16 of 67 Issue 2013-02-08 printed: December 11, 2013

    12. 00073261 BTS INST. MATERIALS Installation materials for Flexi base station

    Material

    Bill of Quantities Pos Category Occurrence Qnt Unit Remark

    1 Grounding cable complete 100% 3 m MK 16 GND CABLE Y/G (reel) 100% 2 pcs RS Cable shoe 16mm2 / M8

    2 DC Power Cable Complete 100% 10 m DC cable 2x16mm2 100% 4 pcs Cable lug, 16mm2

    3 LAN Cable Complete 100% 10 m Pre-made LAN cable 4 Label 100% 2 pcs Label as per Mobily Standard 100% 0.04 pcs Cable tie, 100pcs

    5 DC Circuit Breaker 63 Amps

    100% 1 pcs As per Mobily required Brand

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 17 of 67 Issue 2013-02-08 printed: December 11, 2013

    13. 00007502 M LAN cable basic Material for basic length of LAN cable

    Material Supply of LAN cable with fixing accessories, labels and connectors.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 LAN Cable Complete 100 % 1 pcs CS73099.15 pre-made 15m LAN c 2 Label 100 % 2 pcs CS73331.10 LAN cable label (Brady 511) 100 % 0.04 pcs CS73320.04 Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 18 of 67 Issue 2013-02-08 printed: December 11, 2013

    14. 00045205 M remote RF module feed add (2x5m) Additional Installation materials for remote RF module feed

    Material Supply of additional DC power cable if applicable with fixing accessories depending on the type and configuration of the cable basic length.

    Excludes Supply of basic length of the AC or DC cable. Supply of basic length of the fiber optic cable. Supply of basic length of the protection tube or conduit.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    2 DC Power Cable

    100% 10 m CSxxx 2x6mm2 with rubber insulation for Outdoor Installation

    3 Clamps 100% 5 pcs CSxxx Clamps for DC cable and FO

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 19 of 67 Issue 2013-02-08 printed: December 11, 2013

    15. 00045204 M remote RF module feed basic (2x20m) Installation materials for remote RF module feed

    Material Supply of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length. Supply of DC power cable with fixing accessories (cable ties), labels and connectors (shoes) up to the defined length.

    Bill of Quantities Pos Category Occurr

    ence Qnt Uni

    t Component Remark

    1 Grounding cable complete

    100% 2 pcs CS73178 MKEM-LSZH 16 y/g inst. cable (reel), length 3m

    100% 4 pcs CS73226.06 RS Cable shoe 16mm2 / M8

    100% 0.4 m CS73327.12 Shrink sleeve

    100% 0.24

    pcs CS73320.01 Cable tie, 100pcs

    2 DC Power Cable Complete

    100% 40 m CSxxx 2x6mm2 with rubber insulation for Outdoor Installation

    100% 4 pcs CSxxx Cable lugs

    100% 0.2 m CS73327.12 Shrink sleeve

    100% 0.8 pcs CS73320.01 Cable tie, 100pcs

    3 Clamps 100% 20 pcs CSxxx Clamps for DC cable and FO

    4 Labels 100% 2 pcs CSxxx DC cable label

    100% 0.04

    pcs CS73320.01 Cable tie, 100pcs

    100% 2 pcs CSxxx FO cable label

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 20 of 67 Issue 2013-02-08 printed: December 11, 2013

    16. 00038731 M singlemode FO cable basic Material of singlemode fiber optic cable

    Material Supply of up to specified length of singlemode fiber optic cable with fixing accessories, labels and connectors. Supply of protection tube or conduit for the fiber optic cable.(if needed)

    Excludes Supply of fiber optic cable and its protection above specified length.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Singlemode FO Cable Complete 100 % 1 pcs CS73505.20 Premade Rugged duplex jumper cable 20m

    100 % 0.4 pcs CS73320.04 Cable tie, 100pcs 2 Label 100 % 2 pcs Indoor cable label

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 21 of 67 Issue 2013-02-08 printed: December 11, 2013

    17. 00000890 Multiple travel Travel of multiple persons to the site

    Service All travel related to carry out the tasks in the sales package by one or multiple persons. Travel by car (station wagon, MPV, or off-road SUV), or train or other means needed for the work team to get to the site. Travel by ferry for the person(s) and the car if needed. Travel time cost of the person or persons including accommodation if overnight stay is needed as long as required for completing the agreed tasks in the sales package. Transportation of tools, materials or equipment in the same car up to the capacity of the trunk or carrying capacity of the persons and moving of the transported tools, materials or equipment onto and from the site (equipment room, battery room, rooftop, any other part of the site). Insurance of the persons, vehicles, tools, materials and equipment within the scope of this Service Item.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Travel 100 % 1 pcs All travel related to the sales package

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 22 of 67 Issue 2013-02-08 printed: December 11, 2013

    18. 00056303 On site BS integration On site activities to integrate a BTS as a part of the network

    Service Transmission verification including physical connections (E1/T1, FlexBus, optical fiber) Setting site specific parameters Downloading Site Configuration File (SCF) Initiate communication with remote engineer to support remote functional verification

    Excludes Installation of a DDF/ODF block Installation of transmission cable Manual commissioning

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 On site BS integration 100 % 1

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 23 of 67 Issue 2013-02-08 printed: December 11, 2013

    19. 00001513 Rem BTS/BSC/TCSM modules Removal of BTS/BSC/TCSM modules

    Service Decommissioning of modules. Disconnection and removal of internal cabling (if applicable). Removal of labels from the modules. Removal and packaging of the modules. Installing dummy panels instead of the removed plug-in units (if applicable). Collecting of the removed items in a designated area at the site. Transport of the removed modules back to the WH.

    Bill of Quantities Pos Category Occ. Qnt Unit Compone

    nt Remark

    1 PIU Decommissioning 100 % As require on site

    pcs

    2 PIU Removal and transport

    100 % As require on site

    pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 24 of 67 Issue 2013-02-08 printed: December 11, 2013

    20. 00001485 Site survey BS site

    Service Conduct of a site survey on a base station site and preparation of related documents including photographs (if applicable) and the relevant site survey check list.

    Excludes

    Special cases and other requirements This Service Item may include multiple network elements, which are implemented at the same phase at the same site.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Site Survey 100 % 1 pcs Per survey

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 25 of 67 Issue 2013-02-08 printed: December 11, 2013

    21. 00001487 Transport DOP/Site to Site 0-3,5t regulr Transportation of low-volume cargo

    Service Carrying or moving cargo from the storage area, or in case of removal, from a designated area at the site, and loading of the cargo onto the vehicle as described below. Transportation of tools, materials or equipment in a truck/lorry with the payload capacity up to 3.5 tons for an initial distance from the storage area to site. (or return travel of the vehicle). Transportation of the same volume of cargo by train. Travel by ferry for the passangers and the vehicle in both directions if needed. Carrying or moving the cargo from the vehicle into the equipment room, battery room, rooftop or other designated area at the site, or in case of removal, into the storage area. Accommodation of the or passangers and secure parking of the vehicle if overnight stay is needed. Insurance of the persons, vehicle, tools, materials and equipment within the scope of this Service Items.

    Excludes Transportation of cargo in a vehicle with the payload capacity above 3.5 tons. Transportation by helicopter. Hoisting of the cargo by crane. Travel of personnel other than the driver and the aids for cargo loading and unloading.

    Special cases and other requirements This Service Item also covers the cases where one aditional stop is made on the route to and on the route back from the destination for the purpose of loading or unloading additional cargo up to the capacity of the vehicle, which is used especially for microwave links. In case of shipping the cargo by airplane, this Service Item shall be ordered in such a quantity so that the price of the air-ticket and handling or storing of the cargo at the airport is compensated.

    Bill of Quantities Pos Category Occ. Qnt Unit Component Remark

    1 Transport DOP/Site to Site 0+3,5t regulr 100 % 200 km 100km in 2 dirs, accom.

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 26 of 67 Issue 2013-02-08 printed: December 11, 2013

    22. 00001344 I BSC Installation of BSC

    Service Installation of rack mounting rails with fixing materials up to the defined length per rail (if applicable).

    Installation of grounding cable with fixing accessories (cable ties), labels and connectors (cable lugs) up to the defined length.

    Installation of power cables with fixing accessories (cable ties), labels and connectors (cable lugs) up to the defined length.

    Installation of an external alarms cable with fixing accessories (cable ties), labels and connectors up to the defined length.

    Installation of an analogue X.25 cable with fixing accessories (cable ties), labels and connectors up to the defined length.

    Installation of labels for the grounding termination point (port of a grounding bus bar), DC power breakers, DDF block, AIB or ADM.

    Installation and testing of clock synchronization cable with fixing accessories (cable ties), labels and connectors up to the defined length. (if applicable)

    Cutting of computer floor tiles and dressing cut edges with suitable edging material or/and installing cable flanges (if applicable).

    Installation of the BSC cabinet and its fixing to the rails (if applicable) or floor including the fixing material.

    Installation (insertion) of plug-in units as delivered for the BSC up to the maximum configuration.

    Excludes Installation of subsequent BSC extensions.

    Installation and testing of interface cables, such as PCMs or LAN.

    Installation of additional cable lengths for cables delivered under this Service Item.

    Special cases and other requirements Cross connection of external alarms in Alarm Distribution Module is not considered as it is assumed that the incoming alarms and the external alarms cable share the same ADM block.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Rack Mount Rail Installation 100% 2 pcs

    2 Cable Flange Installation 100% 1 pcs Incl. floor cutting

    3 Grounding Cable Installation 100% 50 m Incl. labeling & testing

    4 DC Power Cable Installation 100% 200 m Incl. labeling & testing

    5 Ext. Alarms Cable Installation 100% 50 m Incl. labeling & testing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 27 of 67 Issue 2013-02-08 printed: December 11, 2013

    6 An. X.25 Cable Installation 0% 18 m Incl. labeling & testing

    7 Cabinet Installation 100% 1 pcs Incl. fixing, voltage ch.

    8 PIU Installation 100% 1 pcs Includes all the delivered PIUs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 28 of 67 Issue 2013-02-08 printed: December 11, 2013

    23. 00001383 IC lamp panel Installation and commissioning of alarm panel or alarm interface box (TIF)

    Service Installation of alarm panel or TIF(telemetry interface) signaling cable up to the defined length including fixing accessories (cable ties), labels and connectors.

    Installation of multi-core DC power cable for the alarm panel up to the defined length including fixing accessories (cable ties), labels and connectors (cable shoes).

    Installation of label for the alarm panel or TIF signalling.

    Installation and commissioning of alarm panel or TIF signalling.

    Excludes Installation of additional power or interface cable.

    Special cases and other requirements The supply of cable ties and labels is also included in this Service Item.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Cable Installation 100% 3 pcs Connector fitting

    2 Power Cable Installation 100% 4 pcs Connector fitting

    3 alarm panel Installation 100% 1 pcs

    4 alarm panel Commissioning 100% 1 pcs

    5 TIF Installation and Commissioning 0% 1 pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 29 of 67 Issue 2013-02-08 printed: December 11, 2013

    24. 00001390 I MHA-TMA Installation and commissioning of Mast Head Amplifier

    Service Installation of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to defined length.

    Termination of the grounding cable to the grounding termination point (port of a grounding bus bar).

    Installation of additional fixing material for the MHA, such as steel bands, etc.

    Installation of MHA with its own mounting brackets, clamps or additional fixing material including connection to the antenna line (only if RF feeder exists) with installation of waterproofing. Installation of additional jumper with fixing materials and abels including installation of waterproofing.

    Installation of label for the MHA.

    Excludes Commisioning of antenna line and antenna

    Installation of Bias Tee.

    Installation of antenna line including other active and passive components.

    Special cases and other requirements If the antenna line is installed in the same time like the MHA, installation of waterproofing for the RF feeder-MHA connector as well as termination of the RF feeder to the MHA are part of the antenna line installation.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Jumper cable installation 100% 1 lot DNxxx incl, labeling

    2 Grounding Cable Installation 100% 7 m DNxxx Incl. labeling

    4 MHA Installation 100% 1 pcs DNxxx Inc. fixing & labeling

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 30 of 67 Issue 2013-02-08 printed: December 11, 2013

    25. 00001413 ICIntg PIU ext Installation, Commissioning and Integration of Plug-in unit extension

    Service Installation (insertion) of the extended plug-in unit/s in question

    Installation of intercabinet cabling (if applicable)

    Commissioning of extended plug-in unit/s

    Integration of extended plug-in unit/s

    Excludes Testing of interface cables, such as PCMs, external alarm cable, X.25 cable, clock synchronization cable, etc.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Core PIU Installation 100% 8 pcs DNxxx

    2 Core PIU Commissioning 100% 8 pcs DNxxx Incl. ext cable term.

    3 Core PIU Integration 100% 8 pcs DNxxx

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 31 of 67 Issue 2013-02-08 printed: December 11, 2013

    26. 00001515 Rem proprietary PCM Removal of proprietary PCM

    Service Deinstallation of one DDF block.

    Deinstallation of PCM cable, including jumper cables and fixing material up to the defined length per cable.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Removal of cables 100% 1 pcs DNxxx As required on site

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 32 of 67 Issue 2013-02-08 printed: December 11, 2013

    27. 00001516 Rem subrack server or IP hub device Removal of subrack mounted/housed server or IP LAN device

    Service Disconnection and removal of AC power cable of the cabinet including fixing in the defined length (if applicable).

    Removal of labels from the AC breakers and 19-inch frame.

    Removal of fixing materials of the server/LAN device or its shelf.

    Removal and packaging of the server/LAN device.

    Collecting of the removed items in a designated area at the site.

    Excludes Removal of 19-inch frame or cabinet.

    Removal of plug-in units, batteries or subracks.

    Removal of additional cables.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Cable Removal 100% As required on site

    m DNxxx Incl. remov of fixing

    2 Server/LAN Device Removal 100% 1 pcs DNxxx Incl. packaging

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 33 of 67 Issue 2013-02-08 printed: December 11, 2013

    28. 00003379 I blade server chassis Installation blade server chassis hardware (Juniper or Megamon)

    Service Installation of the blade server chassis and plug-in units into a rack.

    Connecting of the chassis grounding cable to the rack.

    Installation of chassis alarm cable with connector to DDF.

    Installation of DC or AC power cable with fixing accessories (cable ties), labels and connectors.

    Connecting of internal cablings.

    Installation of labels for the DC breaker(s).

    Excludes Installation of a 19 inch rack.

    Installation and testing of interface cables, such as STM1 or LAN.

    Installation of additional cable lengths for cables delivered under this Service Item.

    Installation of plug-in units, which are not part of the delivery of the blade server.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Chassis installation 100% 1 pcs DNxxx

    2 Ground cable installation 100% 1 pcs DNxxx

    3 Alarm cable installation 100% 1 pcs DNxxx Incl. labeling & testing

    4 AC or DC Power Cable Installation 100% As required

    m DNxxx Incl. labeling & testing

    5 Plug-in unit installation 100% As required

    pcs DNxxx

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 34 of 67 Issue 2013-02-08 printed: December 11, 2013

    29. 00003934 Site survey core Site survey of a BSC-TCSM-RNC-Core site

    Service Conduct of a site survey and preparation of related documents including photographs (if applicable) and the relevant site survey check list.

    Agreement of site details with customer representative, if applicable.

    Confirmation of site access.

    Excludes Special cases and other requirements

    This Service Item may include multiple network elements, which are implemented at the same phase at the same site.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Site Survey BSC-TCSM-RNC-core 100% 1 pcs Site Survey template document

    per Survey

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 35 of 67 Issue 2013-02-08 printed: December 11, 2013

    30. 00003957 Rem cabinet BSC-RNC Removal of BSC or -RNC cabinet

    Service Decommissioning and physical switch off of the cabinet.

    Disconnection and removal of AC power cable of the cabinet including fixing (if applicable).

    Disconnection and removal of of DC cable of the cabinet including fixing (if applicable).

    Disconnection and removal of grounding cable of the cabinet including fixing .

    Disconnection and removal of Q1 cable of the cabinet including fixing in the length (if applicable).

    Disconnection and removal of external alarms cable of the cabinet including fixing in the length (if applicable).

    Disconnection and removal of analogue X.25 cable of the cabinet including fixing in the length (if applicable).

    Disconnection and removal of clock synchronization cable of the cabinet including fixing (if applicable). Removal of labels from the AC or DC breakers, DDF blocks, cable termination points.

    Removal of fixing materials of the cabinet.

    Dismantling and packaging of enclosures of the cabinet, such as doors, if applicable.

    Removal and packaging of the cabinet.

    Collecting of the removed items in a designated area at the site.

    Excludes Cabinet de-integration support in NSS or NMS.

    Removal of 19-inch frame or cabinet.

    Removal of plug-in units, batteries or subracks.

    Removal of upgrade kits.

    Removal of power cabinet.

    Removal of additional cables.

    Removal of more than one BSC or RNC cabinet.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 De-commissioning 100% 1 pcs DNxxx Data clean up in cabinet

    100% 1 pcs DNxxx Physical switch off cabinet

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 36 of 67 Issue 2013-02-08 printed: December 11, 2013

    2 Cable Removal 100% As required

    m DNxxx Incl. remov of fixing - 2 x pair of power feeds for 1 cabinet

    100% As required

    m DNxxx Removal of ground cable

    3 Door Set Removal 100% 1 pcs DNxxx incl. packaging

    4 Cabinet Removal 100% 1 pcs DNxxx Incl. Packaging and inter cabling

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 37 of 67 Issue 2013-02-08 printed: December 11, 2013

    31. 00033865 Travel low Travel low

    Service All travel related to carry out the tasks in the sales package by one or more people, which normally only takes part of a day to implement.

    Travel by car (station wagon, MPV, or off-road SUV), or train or other means needed for the work team to get to the site. Travel by ferry for the person(s) and the car if needed.

    Travel time cost of the person or persons including accommodation if overnight stay is needed as long as required for completing the agreed tasks in the sales package.

    Transportation of tools, materials or equipment in the same car up to the capacity of the trunk or carrying capacity of the persons and moving of the transported tools, materials or equipment onto and from the site (equipment room, battery room, rooftop, any other part of the site).

    Insurance of the persons, vehicles, tools, materials and equipment within the scope of this service item.

    Excludes Transportation of goods above the capacity of the car or the persons.

    Travel by helicopter.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Travel low 100% 1 pcs N/A All travel related to the sales package

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 38 of 67 Issue 2013-02-08 printed: December 11, 2013

    32. 00033872 Travel TRS Travel transmission

    Service All travel related to carry out the tasks in the sales package by one or more people on a MWR end or similar task, which normally only takes part of a day to implement.

    Travel by car (station wagon, MPV, or off-road SUV), or train or other means needed for the team to get to the site. Travel by ferry for the person(s) and the car if needed.

    Travel time cost of the person or persons including accommodation if overnight stay is needed as long as required for completing the agreed tasks in the sales package.

    Transportation of tools, materials or equipment in the same car up to the capacity of the trunk or carrying capacity of the persons and moving of the transported tools, materials or equipment onto and from the site (equipment room, battery room, rooftop, any other part of the site).

    Insurance of the persons, vehicles, tools, materials and equipment within the scope of this service item.

    Excludes Travel by helicopter.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Travel Transmission 100% 1 pcs N/A All travel related to the sales package

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 39 of 67 Issue 2013-02-08 printed: December 11, 2013

    33. 00033875 Rem cabinet BSC-RNC add Removal of an additional BSC-RNC cabinet

    Service Decommissioning and physical switch off of the cabinet.

    Disconnection and removal of AC power cable of the cabinet including fixing (if applicable).

    Disconnection and removal of up to four runs of DC cable of the cabinet including fixing (if applicable).

    Disconnection and removal of grounding cable of the cabinet including fixing .

    Disconnection and removal of Q1 cable of the cabinet including fixing in the defined length (if applicable). Disconnection and removal of external alarms cable of the cabinet including fixing in the defined length (if applicable).

    Disconnection and removal of analogue X.25 cable of the cabinet including fixing in the defined length if applicable).

    Disconnection and removal of clock synchronization cable of the cabinet including fixing (if applicable).

    Removal of labels from the AC or DC breakers, DDF blocks, cable termination points.

    Removal of fixing materials of the cabinet.

    Dismantling and packaging of enclosures of the cabinet, such as doors, if applicable.

    Removal and packaging of the cabinet.

    Collecting of the removed items in a designated area at the site.

    Excludes Cabinet de-integration support in NSS or NMS.

    Removal of 19-inch frame or cabinet.

    Removal of additional cables.

    Removal of more than one BSC or RNC cabinet.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 De-commissioning 100% 1 pcs DNxxx Data clean up in cabinet

    100% 1 pcs DNxxx Physical switch off cabinet

    2 Cable Removal 100% As required

    m DNxxx Incl. remov of fixing - 2 x pair of power feeds for 1 cabinet

    100% As m DNxxx Removal of ground cable

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 40 of 67 Issue 2013-02-08 printed: December 11, 2013

    required

    3 Door Set Removal 100% 1 pcs DNxxx DX200, incl. packaging

    4 Cabinet Removal 100% 1 pcs DNxxx DX200 Incl. Packaging and inter cabling

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 41 of 67 Issue 2013-02-08 printed: December 11, 2013

    34. 00038266 I 1 5-8 antenna line basic (1 run upto any length) Installation of a 1 5/8" antenna line in required length

    Service Dismantling and reassembly of the cable entry or gland.

    Installation of 1 5/8" feeder cable in the required length with fixing accessories (clamps, cable ties), grounding kits and waterproofing materials, labels and connectors.

    Installation of jumper cables with fixing accessories, waterproofing materials and labels,.

    Termination of the antenna line to the Base Station.

    Termination of the antenna line to the antenna including waterproofing of the outdoor connector (if antenna exists).

    Excludes Installation of antenna.

    Installation of active and passive antenna line components, such as Bias Tee, MHA, diplexer, triplexer, combiner, etc.

    Installation of cable support structures.

    Installation of any other type of RF feeder cable.

    Commissioning of antenna line and antenna

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Feeder Cable Installation 100% As required at site

    m DNxxx Incl. Grounding and waterpr.

    2 Jumper Installation 100% 1 lot DNxxx Incl. Sealing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 42 of 67 Issue 2013-02-08 printed: December 11, 2013

    35. 00038268 I RDSA Cables (For Diversity Sharing) Installation of RDSA cables for Diversity Sharing between 2G and UMTS900

    Service Installation of RDSA cables and FO cables between 2G and UMTS900 modules as per site configuration

    Re-configuration / Re-commissioning of existing 2G BTS if required

    Azimuth and Tilt Adjustment of antennas if required on site

    Any other work required to complete the work on site

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 43 of 67 Issue 2013-02-08 printed: December 11, 2013

    36. 00038285 I floor mount 19-23 cab Installation of floor mount 19-23 inch cabinet

    Service Installation of a floor-standing 19 or 23 inch cabinet with floor fixing material and label.

    Installation of an AC power distribution strip for the 19 or 23 inch cabinet with mounting material.

    Installation of AC power cable with fixing material and labels up to the defined length.

    Installation of DC power cable with fixing material, labels and connectors (lugs) up to the defined length.

    Installation labels for AC power breaker and ground termination point (bus bar port).

    Installation of the grounding cable up to the defined length including labeling of the ground termination point

    Excludes Installation of DC power distribution frame.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 19-23 inch Cabinet Installation 100% 1 pcs DNxxx Floor-standing

    2 19-23 inch Cabinet AC Strip Install. 100% 1 pcs DNxxx

    3 Grounding Cable Installation 100% 7 m DNxxx Incl. labeling & testing

    4 AC Power Cable Installation 100% 7 m DNxxx Incl. labeling & testing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 44 of 67 Issue 2013-02-08 printed: December 11, 2013

    37. 00038559 InstM BSC Installation material for BSC, 1 cabinet

    Material Supply of rack mounting rails with fixing materials up to the defined length per rail (if applicable).

    Supply of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length.

    Supply of power cable with fixing accessories (cable ties), labels and connectors (cable shoes) up to the defined length.

    Supply of an external alarms cable with fixing accessories (cable ties), labels and connectors up to the defined length..

    Supply of labels for the grounding termination point (port of a grounding bus bar), DC power breakers, DDF block, AIB or ADM.

    Supply of clock synchronization cable with fixing accessories (cable ties), labels and connectors up to the defined length.

    Supply of suitable edging material or/and supplying cable flanges (if applicable). Supply of fixing material.

    Excludes Installation material for subsequent BSC extensions.

    Supply of interface cables, such as PCM, LAN or STM-1

    Supply of additional cable lengths for cables delivered under this Service Item.

    Special cases and other requirements Cross connection material for external alarms in Alarm Distribution Module is not considered as it is assumed that the incoming alarms and the external alarms cable share the same ADM block.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Rack Mount Rail Complete 100% 2 pcs CS73349.02 Floor Rails 895mm

    100% 1 pcs CS73217.04 Fasteners for rails, 1PCS per cabinet

    100% 1 pcs CS73222.20 Floor rail Installation det, 1PCS per cabinet, includes two cabinet support bars for each cabinet, their attachment parts.

    2 Ground Cable Complete 100% 50 m CS73179 Grounding cable, 25mm2

    100% 1 pcs CS73226.08 Gnd cable lug, 25mm2

    3 DC Power Cable Complete 100% 100 m CS73180.01 DC cable black 35mm2,

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 45 of 67 Issue 2013-02-08 printed: December 11, 2013

    100% 100 m CS73180.02 DC cable blue 35mm2,

    100% 8 pcs CS73226.09 DC cable ferrule, 35mm2

    100% 1 m CS73327.12 Shrink sleeve black

    100% 1 m CS73327.10 Shrink sleeve blue

    4 Ext. Alarms Cable Complete 100% 1 pcs CS73131.50 Ext. al. cable, pre-made, 50m

    5 Comp. Floor Cable Flange 100% 1 pcs CS73339.20 Insulation tape 19*18 black

    6 Label 100% 1 pcs CS73331.10 Cable label set

    7 Fixing accessories 100% 1 pcs CS73320.01 Cable tie, 100pcs

    100% 1 pcs CS73320.05 Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 46 of 67 Issue 2013-02-08 printed: December 11, 2013

    38. 00038637 InstM packaging for cables Packaging material for cables

    Material Supply of packaging material.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Packaging Material 100% 1 pcs Reel for cables

    0% 1 pcs Box for fixing materials and grounding kits (50pcs)

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 47 of 67 Issue 2013-02-08 printed: December 11, 2013

    39. 00038638 InstM packaging for PIUs Packaging material for plug in units

    Material Supply of packaging material.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Packaging Material 100% 1 pcs box type Box for PIUs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 48 of 67 Issue 2013-02-08 printed: December 11, 2013

    40. 00038640 InstM packaging for cabinet Packaging material for cabinet

    Material Supply of packaging material.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Packaging Material 100% 1 pcs Box for cabinet

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 49 of 67 Issue 2013-02-08 printed: December 11, 2013

    41. 00039295 I indoor Flexi BS cab Installation of indoor Flexi base station cabinet

    Service Installation and fixing of indoor Flexi base station cabinet.

    Installation of grounding cable for the indoor Flexi base station cabinet with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length including testing of the complete cable run.

    Excludes Installation of more than one indoor Flexi base station cabinet.

    Installation of 19" rack, outdoor FCOA cabinet or Flexi base station plinth

    Transportation of the equipment to the site.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Installation of indoor Flexi BS cabinet 100% 1 pcs DNxxx Incl. fixing

    2 Installation of Grounding Cable 100% 3 m DNxxx Incl. labeling & testing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 50 of 67 Issue 2013-02-08 printed: December 11, 2013

    42. 00040307 I ODF block or module Installation of ODF block or module.

    Service Installation of ODF block or module into existing frame (e.g.: patch module, splice module, FO splitter module) including

    labeling and fixing accessories. Excludes

    Installation of ODF frame.

    Installation of ODF chassis or shelf.

    Special cases and other requirements NOTE: In some countries the installation standards may require special license or permissions from Local Telecom Company and authorities. When localizing this generic item check the country specific legislation. Installation manuals and tools have to be used.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 ODF block or module installation 100% 1 pcs DNxxx Incl. labeling and fixing accessories

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 51 of 67 Issue 2013-02-08 printed: December 11, 2013

    43. 00040308 M ODF block (48 ports) Material for an ODF block 48 ports Tyco type as per Mobily specifications.

    Material Supply of an ODF block including mounting materials.

    Supply of labels for the ODF block

    Excludes Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 ODF block 100% 1 pcs CSxxx

    2 Block Mount Material 100% 4 pcs CSxxx Bolt

    100% 4 pcs CSxxx 19" rail clip w/ nut

    3 Label 100% 1 pcs CSxxx Block label

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 52 of 67 Issue 2013-02-08 printed: December 11, 2013

    44. 00038565 InstM TCSM Installation material for TCSM, 1 cabinet

    Service Material

    Supply of rack mounting rails with fixing materials.

    Supply of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to the defined cable length.

    Supply of power cable with fixing accessories (cable ties), labels and connectors (cable lugs) up to the defined cable length.

    Supply of labels for the TMGB and DC power breakers.

    Supply of suitable edging material or/and supplying cable flanges (if applicable).

    Supply of fixing material.

    Excludes Supply of interface cables, such as PCMs or LAN

    Installation material for subsequent TCSM extensions.

    Special cases and other requirements Bill of Quantities Pos Category Qnt Unit Component Remark

    1 Rack Mount Rail Complete

    2 pcs CS 73349.03

    Floor Rails 1190mm

    1 pcs CS 73217.04

    Fasteners for rails, 1PCS per cabinet

    1 pcs CS 73222.20

    Floor rail Installation det, 1PCS per cabinet, includes two cabinet support bars for each cabinet, their attachment parts.

    2 Ground Cable Complete

    50 m CS73179 y/g 25mm2

    2 pcs CS73226.08 Cable lug, 25mm2 3 DC Power Cable

    Complete 50 m CS73180.01 DC cable black 35mm2, 2x

    50 m CS73180.02 DC cable blue 35mm2, 2x 4 pcs CS73226.09 DC cable shoe 1 m CS73327.12 Shrink sleeve black 1 m CS73327.10 Shrink sleeve blue

    4 Comp. Floor Cable Flange

    2 pcs CS73339.20 Insulation tape 19*18 black

    5 Label set 1 pcs CS73331.10 Cable label set 6 Fixing accessories 1 pcs CS73320.01 Cable tie, 100pcs

    1 pcs CS73320.05 Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 53 of 67 Issue 2013-02-08 printed: December 11, 2013

    45. 00001361 I TCSM Installation of TCSM

    Service Installation of rack mounting rails with fixing materials.

    Installation of grounding cable with fixing accessories (cable ties), labels and connectors (lugs) up to the defined cable length.

    Installation of power cable with fixing accessories (cable ties), labels and connectors (cable lugs) up to the defined cable length.

    Installation of labels for the TMGB and DC power breakers.

    Cutting of computer floor tiles and dressing cut edges with suitable edging material or/and installing cable flanges (if applicable).

    Installation of the TCSM cabinet on the floor or fixing to the rails.

    Installation (insertion) of plug-in units as delivered for the TCSM up to the maximum configuration.

    Material Excludes

    Installation of subsequent TCSM extensions.

    Installation of additional cable lengths.

    Special cases and other requirements Bill of Quantities Pos Category Qnt Unit Component Remark

    1 Rack Mount Rail Installation

    2 pcs

    2 Cable Flange Installation

    1 pcs Incl. floor cutting

    3 Grounding Cable Installation

    50 m Incl. labeling & testing

    4 DC Power Cable Installation

    200 m Incl. labeling & testing

    5 DX200 Cabinet Installation

    1 pcs Incl. fixing, PIUs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 54 of 67 Issue 2013-02-08 printed: December 11, 2013

    46. 00073251 Implementation BTS 2G and UMTS900 for swap Installation, Commissioning & Integration of 2G Flexi MR BTS to Swap existing 2G BTS and Installation, Commissioning and Integration of UMTS900 at the same time with Diversity sharing using RDSA cable.

    Service Collection of the equipment and materials from the DoP/WH and its transportation / delivery to the site including loading unloading etc.

    Travel of Implementation teams to the site

    Preparation for swap of 2G including alarm checking etc

    Installation and fixing Base Station cabinet/rack if applicable.

    Installation of Base Station modules including casing, fixing of earthquake protection screws, front and back covers if applicable.

    Installation of grounding cable for the Base Station with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length including testing of the complete cable run.

    Installation of Circuit Breakers including labeling

    Installation of power cable with fixing accessories (cable ties), labels and connectors (shoes) up to the defined length including testing of the complete cable runs.

    Installation of alarm cable with fixing accessories (cable ties), labels and connectors up to the defined length including testing of the complete cable run if applicable

    Installation of transmission cable(s) with fixing accessories (cable ties), labels and connectors up to the defined length including testing of the complete cable run if applicable

    Installation of internal cabling not limited to DC Power cable(s), grounding cable(s) and databus cable(s) if applicable

    Connecting RF antenna lines and jumpers to the BTS including installation of new jumpers and RDSA cable.

    Installation of labels for DC breakers, AIB and ADM.

    Powering-up, Commissioning and integration of the 2G and 3G Base Stations.

    Cut-over from existing 2G BTS to the new Flexi 2G BTS

    Antenna Azimuth and Tilt adjustment if required

    Clear all the HW snags from the Punch List

    Create Site HW documentation for Site HW Acceptance and submit to NSN in hard and soft format as agreed.

    Fall-back to the old 2G BTS, in case of swap failure

    Any other related work required on site for complete Implementation

    All the coordination with NSN and Mobily staff to complete the Implementation work

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 55 of 67 Issue 2013-02-08 printed: December 11, 2013

    Excludes Supply, Installation and Commissioning of an external DC Power Supply System, MW or IP Transmission. Removal of Existing 2G BTS.

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 56 of 67 Issue 2013-02-08 printed: December 11, 2013

    47. 00073252 BTS Implementation TDD LTE for Swap sites Installation, Commissioning & Integration of Flexi MR TDD LTE BTS Feeder-less to Swap existing TDD LTE BTS Feeder-less

    Service Collection of the equipment and materials from the DoP/WH and its transportation / delivery to the site including loading unloading etc.

    Travel of Implementation teams to the site

    Preparation for swap of TDD LTE including alarm checking etc

    Installation and fixing Base Station cabinet/rack if applicable.

    Installation of Base Station modules (System Modules in the Shelter and RF Modules on the Tower Top) including casing, fixing of earthquake protection screws, front and back covers if applicable.

    Installation of grounding cable for the Base Station with fixing accessories (cable ties), labels and connectors (lugs) up to the defined length including testing of the complete cable run.

    Installation of Circuit Breakers including labeling

    Installation of power cable with fixing accessories (cable ties), labels and connectors (shoes) up to the defined length including testing of the complete cable runs.

    Installation of alarm cable with fixing accessories (cable ties), labels and connectors up to the defined length including testing of the complete cable run if applicable

    Installation of transmission cable(s) with fixing accessories (cable ties), labels and connectors up to the defined length including testing of the complete cable run if applicable

    Installation of internal cabling not limited to DC Power cable(s), grounding cable(s) and databus cable(s) if applicable

    Connecting RF antenna lines and jumpers to the BTS including installation of new jumpers.

    VSWR and Return Loss measurement for jumpers if required

    Installation of labels for DC breakers, AIB and ADM.

    Powering-up, Commissioning and integration of the Base Station.

    Cut-over from existing LTE BTS to the new Flexi MR LTE BTS

    Remove existing LTE BTS RRHs and accessories such as FO and Power cables etc. from the tower and place them inside the shelter

    Antenna Azimuth and Tilt adjustment if required

    Clear all the HW snags from the Punch List

    Create Site HW documentation for Site HW Acceptance and submit to NSN in hard and soft format as agreed.

    Fall-back to the old LTE BTS, in case of swap failure

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 57 of 67 Issue 2013-02-08 printed: December 11, 2013

    Any other related work required on site for complete Implementation

    All the coordination with NSN and Mobily staff to complete the Implementation work

    Excludes Supply, Installation and Commissioning of an external DC Power Supply System, MW or IP Transmission. Removal of Existing LTE BTS except RRHs,

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 58 of 67 Issue 2013-02-08 printed: December 11, 2013

    48. 00001347 I diplexer Installation of one diplexer on the antenna line

    Service Installation of additional fixing material for the diplexer (in case of pole mounting), such as steel bands, etc.

    Installation of diplexer with additional fixing material including connection to the antenna line (only if RF feeder exists) with waterproofing.

    Installation of one additional jumper with fixing materials, and labels including installation of waterproofing (only if diplexer placed close to the antenna).

    Installation of two additional jumper with fixing materials and labels including installation of waterproofing (only if diplexer placed close to the Base Stetion).

    Installation of label for the diplexer.

    Material Excludes

    Commisioning of antenna line and antenna

    Installation of more than one diplexer.

    Installation of antenna line including other active and passive components.

    Special cases and other requirements If the antenna line is installed in the same time like the diplexer, the installation of waterproofing for the RF feeder-diplexer connector as well as termination of the RF feeder to the diplexer are part of the antenna line installation.

    Bill of Quantities

    Pos Category Occurrence Qnt Unit Component Remark

    1 Jumper Installation

    100% 2 pcs DNxxx Incl. Labeling

    2 Diplexer Installation

    100% 1 pcs DNxxx Inc. fixing & labeling

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 59 of 67 Issue 2013-02-08 printed: December 11, 2013

    49. 00001504 Rem MHA-TMA Removal and packing of one Mast Head Amplifier / Tower Mounted Amplifier

    Service Blocking of the affected sector in the Base Station.

    Reconfiguration of Base Station.

    Disconnection and removal of the grounding cable including fixing in the defined length.

    Removal of waterproofing from connectors.

    Removal of one jumper cable between MHA/TMA and antenna including cable fixing.

    Disconnection of feeder cables from MHA/TMA.

    Installation of connector covers (caps) to the antenna connector and the feeder connectors, or termination of feeder cables to the antenna and installation of new waterproofing.

    Removal and packaging of MHA/TMA including mounting brackets, accessories and applying of MHA/TMA connector covering (caps).

    Re-commissioning of the antenna line (if applicable).

    Collecting of the removed items in a designated area at the site.

    Material Excludes

    Removal of any other active or passive components of the antenna line.

    Removal of more than one MHA/TMA.

    Removal of Bias Tee.

    Special cases and other requirements The supply of connector covers (caps) to the antenna connector and the feeder connectors, or termination of feeder cables to the antenna and supply of new waterproofing is also included in this Service Item.

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 BS Reconfiguration

    100% 1 pcs DNxxx Incl. sector block, reconf.

    2 Removal of Cable 100% 7 m DNxxx MHA gnd cable

    3 Removal of Jumper

    100% 0.5 m DNxxx Incl. fixing, labels

    100% 1.5 m DNxxx Incl. fixing, labels 4 Removal of MHA 100% 1 pcs DNxxx Incl. pack,

    waterproofing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 60 of 67 Issue 2013-02-08 printed: December 11, 2013

    50. 00001509 Rem omni or panel antenna up to 2m Removal of omni or panel RF antenna of the size up to 2 meters

    Service Blocking of the affected antenna (sector) in the Base Station.

    Disconnection and removal of the grounding cable (if applicable).

    Removal of waterproofing from connectors antenna connectors.

    Disconnection of feeder cables.

    Installation of waterproofing materials for temporary sealing of feeder connectors (if applicable).

    Removal and packaging of antenna including mounting brackets and tilting kits

    Collecting of the removed items in a designated area at the site.

    Material Excludes

    Removal of any other type of antenna bigger than 2m.

    Removal of jumper or antenna line.

    Special cases and other requirements The supply of waterproofing materials for temporary sealing of feeder connectors (if applicable) is also included in this Service Item (if applicable).

    Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 Antenna (Sector) Blocking

    100% 1 pcs DNxxx

    2 Cable Removal 100% 7 m DNxxx Ant. gnd cable 3 RF Ant.

    Deinstallation 100% 1 pcs DNxxx > 2m incl pack, temp

    waterp.

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 61 of 67 Issue 2013-02-08 printed: December 11, 2013

    51. 00007508 M floor mount 19-23 open frame Material for floor-standing 19-23 inch open frame

    Service Material

    Supply of a floor-standing open 19 or 23 inch frame with floor fixing material and label.

    Supply of an AC power distribution strip for the 19 or 23 inch frame with mounting material.

    Supply of AC power cable with fixing material and labels up to the defined length.

    Supply of DC power cable with fixing material, labels and connectors (lugs) up to the defined length.

    Supply labels for AC power breaker and ground termination point (bus bar port). Supply of the grounding cable up to the defined length including labeling of the ground termination point.

    Excludes Installation material for DC power distribution or frame enclosures.

    Special cases and other requirements Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 19/23inch Frame 100% 1 pcs CS75064.00 Floor-standing

    2 19/23inch Frame Fixing 100% 4 pcs CSxxx Bolt

    100% 4 pcs CSxxx Washer

    100% 4 pcs CSxxx Anchor

    3 19/23inch Frame AC Strip 100% 1 pcs CSxxx AC strip, 6 sockets

    4 19/23inch AC Strip Mount Material

    100% 4 pcs CSxxx Bolt

    100% 4 pcs CSxxx Washer

    100% 4 pcs CSxxx Nut

    5 Power Cable Complete 100% 7 m CSxxx AC/DC power cable

    100% 0.1 m CS73327.12 Shrink sleeve

    100% 1 pcs CSxxx AC plug

    100% 0.3 pcs CS73320.01 Cable tie, 100pcs

    6 Ground Cable Complete 100% 7 m CSxxx Grounding cable max. 3m

    100% 2 pcs CSxxx Gnd cable lug

    100% 0.2 m CS73327.12 Shrink sleeve

    100% 0.3 pcs CS73320.01 Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 62 of 67 Issue 2013-02-08 printed: December 11, 2013

    7 Label 100% 2 pcs CSxxx AC/DC cable label

    100% 0 pcs CS73320.01 Cable tie, 100pcs

    100% 2 pcs CSxxx Grounding cable label

    100% 0 pcs CS73320.01 Cable tie, 100pcs

    100% 1 pcs CSxxx Circuit braker label

    100% 1 pcs CSxxx Gnd point lable

    100% 1 pcs CSxxx 19-frame label

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 63 of 67 Issue 2013-02-08 printed: December 11, 2013

    52. 00038286 I floor mount 19-23 open frame Installation of floor-standing 19-23 inch open frame

    Service Installation of a floor-standing open 19 or 23 inch frame with floor fixing material and label.

    Installation of an AC power distribution strip for the 19 or 23 inch frame with mounting material.

    Installation of AC power cable with fixing material and labels up to the defined length.

    Installation of DC power cable with fixing material, labels and connectors (lugs) up to the defined length.

    Installation labels for AC power breaker and ground termination point (bus bar port).

    Installation of the grounding cable up to the defined length including labeling of the ground termination point.

    Material Excludes

    Installation of DC power distribution or frame enclosures.

    Special cases and other requirements Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 19/23inch Frame Installation 100% 1 pcs DNxxx Floor-standing 2 19/23inch Frame AC Strip

    Install. 100% 1 pcs DNxxx

    3 Grounding Cable Installation 100% 10 m DNxxx Incl. labeling & testing 4 AC/DC Power Cable

    Installation 100% 20 m DNxxx Incl. labeling & testing

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 64 of 67 Issue 2013-02-08 printed: December 11, 2013

    53. 00007509 M floor mount 19-23 cab Material for floor mount 19-23 inch cabinet

    Service Material

    Supply of a floor-standing 19 or 23 inch cabinet with floor fixing material and label.

    Supply of an AC power distribution strip for the 19 or 23 inch cabinet with mounting material.

    Supply of AC power cable with fixing material and labels up to the defined length.

    Supply of DC power cable with fixing material, labels and connectors (lugs) up to the defined length.

    Supply labels for AC power breaker and ground termination point (bus bar port). Supply of the grounding cable up to the defined length including labeling of the ground termination point.

    Excludes Supply of DC power distribution frame.

    Special cases and other requirements Bill of Quantities Pos Category Occurrence Qnt Unit Component Remark

    1 19-23 inch Cabinet 100% 1 pcs CS75054.50 Floor-standing 2 19-23 inch Cabinet Fixing 100% 4 pcs CSxxx Bolt

    100% 4 pcs CSxxx Washer 100% 4 pcs CSxxx Anchor

    3 19-23 inch Cabinet AC Strip 100% 1 pcs CSxxx AC strip, 6 sockets 4 19-23 inch Cabinet AC Strip

    Mount Material 100% 4 pcs CSxxx Bolt

    100% 4 pcs CSxxx Washer 100% 4 pcs CSxxx Nut

    5 Power Cable Complete 100% 20 m CSxxx AC power cable 100% 0.1 m CS73327.12 Shrink sleeve 100% 1 pcs CSxxx AC plug 100% 0.3 pcs CS73320.01 Cable tie, 100pcs

    6 Ground Cable Complete 100% 10 m CSxxx Grounding cable max. 3m

    100% 2 pcs CSxxx Gnd cable lug 100% 0.2 m CS73327.12 Shrink sleeve 100% 0.3 pcs CS73320.01 Cable tie, 100pcs

    7 Label 100% 2 pcs CSxxx AC cable label 100% 0 pcs CS73320.01 Cable tie, 100pcs

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 65 of 67 Issue 2013-02-08 printed: December 11, 2013

    100% 2 pcs CSxxx Grounding cable label 100% 0 pcs CS73320.01 Cable tie, 100pcs 100% 1 pcs CSxxx Circuit braker label 100% 1 pcs CSxxx Gnd point lable 100% 1 pcs CSxxx Cabinet label

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 66 of 67 Issue 2013-02-08 printed: December 11, 2013

    54. 00073254 Implementation BTS Modules Re-arrangement Re-arrangement of existing Flexi BTS modules within the existing cabinet

    Service Travel of Implementation teams to the site

    Preparation for re-arrangement of modules including planning for MDT,BTS shut-down or sector blockage etc.

    Removal and re-installation of modules along with all the cabling, labeling work

    Re-arrangement of all the internal cable on site

    Re-arrangement and replacement of all the jumpers if required .

    VSWR and Return Loss measurement for jumpers if required

    Powering-up of the Base Station or un-block the sector if required.

    Clear all the HW snags from the Punch List

    Any other related work required on site for complete Implementation

    All the coordination with NSN and Mobily staff to complete the Implementation work

    Excludes Any new HW installation

  • Copyright 2009 , Nokia Siemens Networks All rights reserved.

    Service Item Appendix Page 67 of 67 Issue 2013-02-08 printed: December 11, 2013

    55. 00073255 BTS Modules Removal and Installation Removal for BTS RF modules from one site and Re-installation on another site

    Service Travel of Implementation teams to both the sites

    Site survey of sites and preparation of all the related documents for the sites as part of site folder for site acceptance.

    Preparation for Removal and Re-installation of modules including planning for MDT,BTS shut-down or sector blockage etc.

    Removal of spare RF modules from 2G sites which have been downgraded by re-farming

    Transport of modules from site to WH or new site

    Re-installation of RF modules at new site where UMTS900 is to be installed

    Installation and fixing of Flexi base station plinth on floor if required.

    Installation of grounding cable for the Flexi base station plinth with fixing accessories (cable ties), labels and connectors (lugs) up to the required length including testing of the complete cable run.

    Installation of Flexi base station RF modules including casing, fixing of earthquake protection screws, front and back covers if applicable.

    Installation of grounding cable between Flexi base station RF module and Flexi base station plinth or the nearest grounding point with fixing accessories (cable ties) including testing of the complete cable run if applicable.

    Installation of delivered internal power cabling between Flexi base station RF modules and system module, including fixing accessories (cable ties).

    Installation of delivered internal databus cabling between Flexi base station RF module and system module, including cleaning of optical connectors and fixing accessories (cable ties).

    Preparation and Installation of Jumpers (including clamps and Weather proofing) as required on site from the RF module to the Antenna.

    Testing of the Jumpers (VSWR etc) if required and attach test report. Installation of RDSA cables and FO cables between 2G and 3G modules as per given site configuration

    Re-configuration / Re-commissioning of existing 2G BTS if required

    Azimuth and Tilt Adjustment for antennas if required on site.

    Conduct PAT, prepare and submit all PAT documents and Clear all the HW snags from the Punch List

    Any other related work required on site for complete Implementation

    All the coordination with NSN and Mobily staff to complete the Implementation work