HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential www.huawei.com 3 May 2011 Samar Tahir ID:707649 Part I : Project Scope Part II : Project Swap Scenarios Part III: Key points of Installation

Huawei Mobily WiMAX LTE [Samar 707649] Ppt

Embed Size (px)

Citation preview

Page 1: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

www.huawei.com

3 May 2011

Samar Tahir ID:707649Part I : Project ScopePart II : Project Swap ScenariosPart III: Key points of Installation

Page 2: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

www.huawei.com

3 May 2011

Part - I Project Scope

Page 3: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Objectives and Scope - I

• Project Name : Saudi Mobily WiMAX & LTE Project 5508500

• In order to meet the requirement of Mobily multiple networks deployment, Huawei presents multi-

mode BTS solution which is applicable for WiMAX/TDLTE multi-mode deployment and smooth

evolution from WiMAX to LTE

• Scope :

• 1)Huawei 265 WIMAX sites upgrade, and 150 new sites based on Huawei WIMAX coverage cities.

• 2) 99 new TDL and WIMAX co-sites will be built in the New cities.

• 3) 477 new TDL and WIMAX co-sites will be built in Easten, Madinah and Yanbo area.

• Huawei will introduce a new LTE network with two SAE geographically separated in location

within the same access network using single ran solution which will put up with the exceeding

data demands of end users.

Page 3

Huawei Existing City 415

New City 99

Easten&Madinah,Yanbo 477

Page 4: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Objectives and Scope - II

• Two new ASN-GW’s will be added to the existing network and will be installed in GOSI–Dammam and Silver-Khobar. Huawei is proposing two possible scenarios for the Target Network Topology. The distribution is done based on geographic location of cities keeping in mind the transmission delay consideration. Both scenarios are as following:

Page 4

Page 5: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

www.huawei.com

3 May 2011

Part - II Project Swap Scenarios

Page 6: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Page 6

Contents

Swap Scenario analysis

Swap Process

2

3

Swap Strategy1

Rollback Process4

Proposed Solution

6

Risk Analysis5

Page 7: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 7

1) Swap Strategy for WiMAX

Cluster swap

Low HighMedium

Swap a complete network

Cluster-based Swap

Swap site by site

Cluster-based Swap is the most practical strategy

Project complexity and risk

Number of sites to be Swapped (i.e. sites per cut-over night)

Low

High

� Cluster scale: 7~10 sites

�Based on RF proposed Clusters : An efficient Solution

Page 8: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

1) Swap Strategy for MW (Transmission)

Page 8

Cluster swap

Low HighMedium

Swap a complete network

Link-based Swap

Swap site by site

Link-based Swap is the most practical

strategy

Project complexity and risk

Number of sites to be Swapped (i.e. sites per cut-over night)

Low

High

� Cluster scale: 6~10 sites

�Swapping a complete MW Link : An efficient Solution

Page 9: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 9

Cluster 1

Existing ASN_GW

Cluster N

CSN

Huawei ASN_GW

• Step 1: Install and commission Huawei ASN_GW/ DBS3900

• Step 2: During MDT : power off existing sites in Cluster (n)

• Step 3: power on new sites in the cluster (n)

• Step 4: Drive test the cluster (n)

• Step 5: Remove existing equipment

Existing BTS

Existing BTS

New DBS3900

New DBS3900New DBS3900

New DBS3900 Existing BTS

Existing BTS

Swap Strategy----Cluster Mode

2) WiMAX Swap Strategy

Cluster ModeStrategy

Easy Project Management and Schedule Control.Cut-over risk can be controlled easily.Have a chance to roll back.

Advantages

Some modification to existing network for cooperating with new system (different network planning schemeSignal may face interference on boundary region

Risk

Page 10: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 10

2) Microwave Swap Strategy• Depending on the Site Scenario

aGW

BTS/eNB

BTS/eNB

BTS/eNB

BTS/eNB

BTS/eNB

BTS/eNB

100Mbps, 1+0

150Mbps, 1+0

Configuration:1 pcs CSHA card1 pcs IFU2 card

RTN910RTN910

Configuration:1 pcs CSH card3 pcs IFU2 card1 pcs EM6F card

RTN950RTN950

Page 11: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 11

Contents

Swap Scenario analysis

Swap Process

2

3

Swap Principles and Strategy1

Rollback Process4

Proposed Solution

9

Risk Analysis5

Page 12: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 12

Scenario Analysis for WiMAX site SwapBased on the experience of Huawei Swap Project, 4 scenarios for the BTS Swap are provided as follows: Easy swap mean that There is extra space, power and accessibility for new DBS3900. The reverse is hard swap

Scenario No.Scenario Definition

Swap Type TX Antenna Space Indoor (space, power)Down Time

Person RemarksGF RT

1 A YES YES YES 2h 1-

2 B YES No YES 5h 3h 3-

3 C No No YES 5h 4h 3

4 D No No No 6h 6h 3-

Note:“A” means “classification A, Easy Swap & high priority”;“B” means “classification B, Hard Swap & Second priority”;MDT will apply by cluster, and Down time of cluster should consider by maximum down time of site

Click hereFor more information

Click hereFor more information

Click hereFor more information

Click hereFor more information

Please click here to go to WiMAX and MW Combined Scenarios

Page 13: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 13

DBS3900 site Swap Scenario A�Easy Swap-A, with Extra Transmission, Space & Power:� Definition.

� There is extra space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.

� There have transmission for Huawei DBS3900 to commissioning (use existing IDU or Mobily switch)

� Key point•Completing civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance.•Completing the hardware installation and commissioning (integration) of Huawei DBS3900 in advance(DBS3900, RRU, DC-Box & Antenna), and block huawei’s cells•Downtime•Site downtime ≈2 hour•deactivate all sectors of sumsung’s wimax site remotely•Active Huawei’s blocked sectors remotely•Drive test, confirm service is normal and put site on air.•Power off Samsung BTS

Go back Main menu

Page 14: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 14

DBS3900 site Swap Scenario B�Hard Swap, with Extra Transmission, indoor space, power:� Definition.

• There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.• There have No Extra space for Huawei antennas•Key point•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance •Completing the hardware installation and commissioning (integration) of Huawei DS3900 in advance(DBS3900, RRU, DC-Box),and block huawei’s cells•Downtime•site downtime ≈5 & 3 hour•Power off Samsung BTS•Remove sumsung’s antennas and install huawei’s antennas •Unblock huawei’s cells remotely and do the drive test•Confirm service is normal and put site on air

Go back Main menu

Page 15: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 15

DBS3900 site Swap Scenario C�Hard Swap, with Extra indoor space, power:� Definition.

• There have extra indoor space, power and accessibility to allow Installation of the Huawei DBS3900 parallel to the existing BTS.• There have No Extra transmission for Huawei DBS3900 to commissioning & No Extra space for Huawei antennas

� Key point•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Completing the hardware installation and commissioning of Huawei DS3900 locally in advance(DBS3900, RRU, DC-Box)

•Lay out jumper, Feeder, fiber cables & power cables in advance � Downtime

•site downtime ≈5 & 4 hour•Power off sumsung’s BTS •Remove sumsung’s antennas and install Huawei’s antennas•Cutover transmission from Samsung BTS to Huawei DBS3900•integrate this site locally and unblock cells•Do Drive Test and confirm service is normal, then put site on air

Go back Main menu

Page 16: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 16

DBS3900 site Swap Scenario D�Hard Swap:� Definition.

• There is no extra footprint for Huawei DBS3900 installation. � Key point

•Completing Civil work in advance (Outdoor RRU rack, Minor civil work)•Lay out jumper, Feeder, fiber cables & power cables in advance•Completing the hardware installation (BBU and DCDU within MDT time)

� Downtime•site downtime ≈6 hour•Sumsung’s team Power off sumsung’s BTS and remove their equipment•Remove sumsung’s antennas and install Huawei’s antennas•Install huawei’s BBU and DCDU in space position and power on huawei’s DBS3900•Do commissioning and integration locally•unblock cells•Do Drive Test and confirm service is normal, then put site on air

Go back Main menu

Page 17: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 17

ScenarioScenarioScenarioScenario DescriptionDescriptionDescriptionDescription Advantage Risks Remarks

Scenario 1Install and then dismantle(Temp

frequency available)

This solutions is available . All the Installation and alignment can be done without MDT. It can be roll back

Small risk when MDT

Scenario 2Install and then dismantle(Temp

frequency unavailable)

This solutions is available when there is no Temp frequency. It can be roll back

Alignment time depending on the size of new antenna . Medium risk.

Scenario 3Direct swap then

install new link

This solution is available when there is no space available on the original infrastructure and no space to erect a new structure on the tower.

Link outage vary from case to case, depending on the size of the newly install antenna and path distance. And it can not be roll back. High risk.

Scenario 4 Re-rout

The outage downtime is short in solution. The link only stays down during the cutover. After re-routing, it can release some spaces on the congested infrastructure for future swap.

Need new licensed frequency and LOS risk .

MW Swap Scenario: Please click here to go to WiMAX and MW Combined Scenarios

Click hereFor more information

Click hereFor more information

Click hereFor more information

Click hereFor more information

Page 18: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 1:To have enough space to install new Microwave antenna and use temp frequency

Swap Solution:� Swap Process (in daytime, First times)

① To Install a new MW link, It is including IDU, ODU, antenna, all of used cable;

② Power on the new link and mute the ODU, then configure the frequency with temp frequency and make the alignment.

③ Configuration the service after finish the alignment .④ Power off the new link.

New antenna candidate place: another side →

up↗

down↘

existing antenna

Go back Main menu Next Page

Page 19: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 1 To have enough space to install new Microwave antenna

and use temp frequency

●●●●Swap Process (in midnight MDT time.)

① Power off the original microwave equipment link

② Power on the new microwave link and configure the

frequency as perdesign again;

③ After finish step 2, connect Lan cable(fiber) to Winmax

and

monitor it.

Go back Main menu Previous Page

Page 20: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 2:To have enough space to install new Microwave antenna and use existing link frequency, namely have no temp frequency

Swap Solution:� Swap Process (in daytime, First times)

① To Install a new MW link, It is including IDU, ODU, antenna, all of used cable;

② Power on the new link and mute the ODU, then configure the frequency with original frequency and service.

③ Power off the new link.

New antenna candidate place: another side →

up↗

down↘

existing antenna

Go back Main menu Next Page

Page 21: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 2 To have enough space to install new Microwave antenna

and use existing link frequency, namely have no temp

frequency

●●●●Swap Process (in daytime MDT time, the second times,

Downtime is from 5 hours to more than 8 hours, It depends

on the antenna size.)

① Power off the original microwave equipment link

② Power on the new microwave link and make alignment;

③ After finish step 2, connect Lan cable(fiber) to Winmax

and

monitor it.

Go back Main menu Previous Page

Page 22: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 3

No enough space to install new Microwave antenna and mounting pole

Swap Solution:

� Swap Process (in daytime, First times)

① To install a new IDU and other indoor equipment and used cable. And prepare ODU&antenna.

② Test hardware and finish site configuration of IDU separately in each site.

Go back Main menu Next Page

Page 23: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

MW Swap Scenario 3

No enough space to install new Microwave antenna and

mounting pole on tower.

� Swap Process (in midnight, the second times, Downtime is

from 5 hours to more than 8 hours, It depends on the

antenna size. )

①Power off the original microwave equipments and

dismantle existing link. Then install new antenna&ODU

rapidly;

②Power on new microwave equipments and make

alignment;

③Configure the service and connect lan(fiber) cable to

Wimax, especially check new MW link status.Go back Main menu Previous Page

Page 24: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Site Swap Scenario 4No enough space to install new Microwave antenna on the existing radio’s tower leg to the existing far-end site, but has spaces on other tower legs which can be utilized to divert the traffic to adjacent chains.

Swap Solution:

� Swap Process (in daytime, First times)① To install a new mounting pole for microwave antenna on other tower

legs.② To install a new MW link including IDU, ODU, antenna, all of used

cable;③ MW pre-commissioning with new frequency to ensure operation

availability;④ To Configure the Ethernet service and ping each other between Near

site and far-site.

Go back Main menu Next Page

Page 25: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 25

Site Swap Scenario 4

No enough space to install new Microwave antenna on the

existing radio’s tower leg to the existing far-end site, but

has spaces on other tower legs which can be utilized to

divert the traffic to adjacent chains.

� Swap Process (in midnight, the second times)

①Power off the original microwave equipments;

②Power on new microwave equipments;

③Configure the existing frequency to Huawei microwave

equipment.

Go back Main menu Previous Page

Page 26: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Combined Scenarios for WiMAX and MW

SerialNo.

Swap Type

WiMAX Scenario Definition MW Scenario Definition

Scenario TX AntennaSpace

Indoor(space,power)

Scenario

Temp Freq AntennaSpace

Re-Routing Required

1 A1 A YES YES YES 1 YES YES No2 A2 A YES YES YES 2 No YES No3 A3 A YES YES YES 3 N/A No No4 A4 A YES YES YES 4 N/A No Yes5 B1 B YES No YES 1 YES YES No6 B2 B YES No YES 2 No YES No7 B3 B YES No YES 3 N/A No No8 B4 B YES No YES 4 N/A No Yes9 C1 C No No YES 1 No YES No

10 C2 C No No YES 2 No YES No11 C3 C No No YES 3 N/A No No12 C4 C No No YES 4 N/A No Yes13 D1 D No No No 1 No YES No14 D2 D No No No 2 No YES No15 D3 D No No No 3 N/A No No16 D4 D No No No 4 N/A No Yes

Page 27: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

1. Scenario A1• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. Also for MW the temp freq is available as well as the space on tower for installation of antennas before MDT.

• Key points: – 1) Install WiMAX BTS and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS for MW before MDT using Temp frequency.– 4) Install WiMAX antennas and out door equipment before MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario A1 , please click here.– For Details on MW Equipment Handling in Scenario A1 , please click here.

Page 28: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

2. Scenario A2• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.

• Key points: – 1) Install WiMAX BTS and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Finish LOS during MDT using the existing frequency.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario A2 , please click here.– For Details on MW Equipment Handling in Scenario A2 , please click here.

Page 29: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

3. Scenario A3• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.

• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Finish LOS during MDT using the existing frequency.– 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario A3 , please click here.– For Details on MW Equipment Handling in Scenario A3 , please click here.

Page 30: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

4. Scenario A4• Definition: There is extra indoor space, power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.

• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Install WiMAX antennas and out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due

to capacity planning or have losses in the link. Need Re-Routing.– 6) Finish Re-Routing.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8) Test Service.– 9) Dismantle the existing WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario A4 , please click here.– For Details on MW Equipment Handling in Scenario A4 , please click here.

Page 31: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

5. Scenario B1• Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.

• Key points: – 1) Install WiMAX BTS (indoor + RRU) and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS for MW before MDT using Temp frequency.– 4) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario B1 , please click here.– For Details on MW Equipment Handling in Scenario B1 , please click here.

Page 32: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

6. Scenario B2• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.

• Key points: – 1) Install WiMAX BTS (excluding antennas) and MW before MDT.– 2) Commission WiMAX BTS before MDT.– 3) Finish LOS during MDT using the existing frequency.– 4) Install WiMAX antennas during MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario B2 , please click here.– For Details on MW Equipment Handling in Scenario B2 , please click here.

Page 33: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

7. Scenario B3• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.

• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT using existing transmission.– 3) Install WiMAX out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW).– 5) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 6) Finish LOS during MDT using the existing frequency.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8)Test Service.– 9) Dismantle the existing WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario B3 , please click here.– For Details on MW Equipment Handling in Scenario B3 , please click here.

Page 34: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

8. Scenario B4• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.

• Key points: – 1) Install WiMAX BTS before MDT.– 2) Commission WiMAX BTS before MDT using existing transmission.– 3) Install WiMAX out door equipment before MDT.– 4) Install MW during MDT. (Replacing existing MW)– 5) Install WiMAX antennas during MDT. (Replacing existing antennas)– 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due

to capacity planning or have losses in the link. Need Re-Routing– 7)Finish Re-Routing.– 8) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 9) Test Service.– 10) Dismantle the existing WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario B4 , please click here.– For Details on MW Equipment Handling in Scenario B4 , please click here.

Page 35: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

9. Scenario C1• Definition: There is extra indoor space , power and accessibility to allow Installation of the Huawei

DBS3900 parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. Also for MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.

• Key points: – 1) Install WiMAX BTS (indoor + RRU) and MW before MDT.– 2) Finish LOS for MW before MDT using Temp frequency.– 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 4) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6)Test Service.– 7) Dismantle the existing MW and BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario C1 , please click here.– For Details on MW Equipment Handling in Scenario C1 , please click here.

Page 36: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

10. Scenario C2• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.

• Key points: – 1) Install WiMAX BTS (excluding antennas) and MW before MDT.– 2) Finish LOS during MDT using the existing frequency.– 3) Commission WiMAX BTS during MDT by swpping transmission with existing BTS.– 4) Install WiMAX antennas during MDT.– 5) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 6) Test Service.– 7) Dismantle the existing MW and WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario C2 , please click here.– For Details on MW Equipment Handling in Scenario C2 , please click here.

Page 37: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

11. Scenario C3• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.

• Key points: – 1) Install WiMAX BTS (excluding antennas) before MDT.– 2) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 3) Install MW during MDT. (Replacing existing MW).– 4) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 5) Finish LOS during MDT using the existing frequency.– 6) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 7)Test Service.– 8) Dismantle the existing WiMAX BTS during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario C3 , please click here.– For Details on MW Equipment Handling in Scenario C3 , please click here.

Page 38: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

12. Scenario C4• Definition: There is extra space, power and accessibility to allow Installation of the Huawei DBS3900

parallel to the existing BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.

• Key points: – 1) Install WiMAX BTS (excluding antennas) before MDT.– 2) Commission WiMAX BTS during MDT by swapping transmission of existing BTS.– 3) Install MW during MDT. (Replacing existing MW)– 4) Install WiMAX antennas during MDT. (Replacing existing antennas)– 5) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due

to capacity planning or have losses in the link. Need Re-Routing.– 6) Finish Re-Routing.– 7) Switch off existing WiMAX and MW equipment during MDT and Switch On Huawei Equipment.– 8) Test Service.– 9) Dismantle the existing WiMAX BTS and MW during MDT.

• Details:– For Details on WiMAX Equipment Handling in Scenario C4 , please click here.– For Details on MW Equipment Handling in Scenario C4 , please click here.

Page 39: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

13. Scenario D1• Definition: There is no extra indoor space to allow Installation of the Huawei DBS3900 parallel to the

existing BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. For MW the temp freq is available as well as the space on tower for installation of MW antennas before MDT.

• Key points: – 1) Install WiMAX BTS (outdoor excluding antenna) and MW before MDT. – 2) Finish LOS for MW before MDT using Temp frequency.– 3) Install WiMAX BTS during MDT by first dismantling existing BTS.– 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 5) Install WiMAX antennas during MDT after dismantling existing antenna’s.– 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing MW.

• Details:– For Details on WiMAX Equipment Handling in Scenario D1 , please click here.– For Details on MW Equipment Handling in Scenario D1 , please click here.

Page 40: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

14. Scenario D2• Definition: There is not extra space to allow Installation of the Huawei DBS3900 parallel to the existing

BTS. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available but the space on tower for installation of MW antennas is available.

• Key points: – 1) Install WiMAX BTS (outdoor excluding antennas) and MW before MDT.– 2) Finish LOS during MDT using the existing frequency.– 3) Install WiMAX BTS during MDT by first dismantling existing BTS.– 4) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 5) Install WiMAX antennas during MDT. (Replacing Existing Antennas).– 6) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 7) Test Service.– 8) Dismantle the existing MW.

• Details:– For Details on WiMAX Equipment Handling in Scenario D2 , please click here.– For Details on MW Equipment Handling in Scenario D2 , please click here.

Page 41: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

15. Scenario D3• Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing

BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT. MW Temp freq is not available and the space on tower for installation of MW antennas is also not available.

• Key points: – 1) Install WiMAX BTS (out door excluding antennas) before MDT.– 2) Install WiMAX BTS during MDT by dismantling existing equipment.– 3) Commission WiMAX BTS during MDT by swapping transmission with existing BTS.– 4) Install MW during MDT. (Replacing existing MW).– 5) Install WiMAX antennas during MDT (Replacing Existing Antennas).– 6) Finish LOS during MDT using the existing frequency.– 7) Switch off existing MW equipment during MDT and Switch On Huawei Equipment.– 8)Test Service.

• Details:– For Details on WiMAX Equipment Handling in Scenario D3 , please click here.– For Details on MW Equipment Handling in Scenario D3 , please click here.

Page 42: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

16. Scenario D4• Definition: There is no extra space to allow Installation of the Huawei DBS3900 parallel to the existing

BTS and existing transmission has enough resources to commission the WiMAX Site before MDT. There is not enough space on tower to install WiMAX antennas before MDT and there is no existing transmission available that could be used for commissioning before MDT MW Temp freq is not available and the space on tower for installation of MW antennas is also not available. MW LOS during MDT is not successful.

• Key points: – 1) Install WiMAX BTS (out door excluding antennas) before MDT.– 2) Install WiMAX BTS during MDT by dismantling existing equipment.– 3) Commission WiMAX BTS during MDT by swapping transmission of existing BTS.– 4) Install MW during MDT. (Replacing existing MW)– 5) Install WiMAX antennas during MDT. (Replacing existing antennas)– 6) Cannot Finish LOS during MDT using the existing frequency or MW Design has been changed due

to capacity planning or have losses in the link. Need Re-Routing.– 7) Finish Re-Routing.– 8) Switch Off existing MW equipment during MDT and Switch On Huawei Equipment.– 9)Test Service.

• Details:– For Details on WiMAX Equipment Handling in Scenario D4 , please click here.– For Details on MW Equipment Handling in Scenario D4 , please click here.

Page 43: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 43

Contents

Swap Scenario analysis

Swap Process

2

3

Swap Principles and Strategy1

Rollback Process4

Proposed Solution

9

Risk Analysis5

Page 44: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 44

End-to-End Swap Work Process

Driver test and Statistical counters

Network optimization

Customer Acceptance test

Design Review & Benchmarking

Survey & Design

Swap Solution Review

Swap Implementation

Optimization & Acceptance

Develop Swap strategy

Critical Review of existing network design and parameter mapping

Performance benchmarking

Site Survey

Site Audit and related design

Site RF design approval

Complete end-to-end solution

Solution Analysis/Review

Swap solution and approval

Swap preparation

Swap Demo &Training (Sub-Urban)

Implementation

0 3 6 9

12 15 18 21 24 27 30 33 36 39 42 45 48

010

20

30

40

50

60

70

80

90

100

Number of Sites

• Network information collection & assessment

•Radio network survey & engineering survey

•Network swap planning •Swap implementation •Network Monitor and Optimization

Page 45: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

End-to-End Swap Work Process for WIMAX

WIMAX SWAP SOP V1.1

Cutover Flowchart for SWAP

• Standard Operation Procedure For WIMAX Swap :

• Cutover Flowchart For WIMAX Swap :

Page 46: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 46

Contents

Swap Scenario analysis

Swap Process

2

3

Swap Principles and Strategy1

Rollback Process4

Proposed Solution

9

Risk Analysis5

Page 47: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 47

Rollback PrinciplesWiMAX Rollback criteria:

•Base on number of sites unsuccessfull in SWAP cluster

WiMAX Rollback Actions:•Troubleshooting unsuccessfull sites during MDT•Request support to rollback to samsung.

MW Rollback criteria:• Base on number of sites unsuccessfull in SWAP cluster

MW Rollback Actions:

• Troubleshooting unsuccessfull sites during MDT• Request support from Trx team if required.

Page 48: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 48

Contents

Swap Scenario analysis2

Swap Principles and Strategy1

Rollback Process4

Risk Analysis5

Swap Process3

Proposed Solution6

Page 49: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Risks Analysis

• WiMAX Risks Involved:– On time support required to dismantle existing equipment and incase of rollback.

• MW Risks Involved:• 1. Some Fiber sites are not confirmed. This will affect the LOS &site survey. This still affect our implement

design.• 2. Swap risk:

– Customer request use the existing link’s frequency. It means we will face 2 scenarios: • Enough space to install. Can roll back but can not forecast how long the downtime it will be .• No space to install: first dismantle existing link, then install new link and alignment. This can not roll

back, high risk. And all the work on the tower need to be done in the day time.

• RNP Risks Involved:• In the swap period, everyday the network will have new provisional boundary with Samsung sites.

Because of this the HO KPI may be bad.But for that the wimax service is fixed wireless service so there is not some real heavy affection to the users.

• About the detail performance risk considering and solution preparation, Huawei need to first collect the Samsung current network information then do the analyse and report to Mobily.

Page 50: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 50

Contents

Swap Scenario analysis2

Swap Principles and Strategy1

Rollback Process4

Swap Process3

Proposed Solution6

Risk Analysis5

Page 51: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Recommended Proposal:

1. Proposal One: – First Swap Wimax Sites– Then Swap MW transmission

2. Proposal Two: (Recommended)– Start Swap Wimax in Region A and SWAP MW in Region B simultaneously .

3. Proposal Three:– Precondition: Match RF cluster with MW link design

• 3.A: First Swap WiMAX according to RF clusters, Once all Wimax sites are Swapped in a particular MW link, then Swap MW for that Link.

• 3.B: Swap Both MW and WiMAX Simultaneously in same RF cluster. (Some sites might be require two or even more MDT’s depending on MW link design)

Page 52: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Benefits Of Recommended Proposal:

Page 53: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES CO., LTD.

www.huawei.com

Huawei Confidential

Security Level:2011-5-3

Part Part Part Part ---- IIIIIIIIIIIIInstallation Key PointInstallation Key PointInstallation Key PointInstallation Key Point

Page 54: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

INDOOR EQUIPMENT [Key points]

• Types of indoor equipment include:

– DCDU [DC-Power Distribution Unit]

– BBU [Base Band Unit for WiMAX]

• Transmission Rack in Block-8 Should be utilized for installation unless

specified otherwise. [Block 8 is the right most 60 cm*60cm block when

entering the shelter ]

• 63A fuses should be used to connect DCDU with exist ing DC-

Distribution BOX [DCDB] installed usually on wall i n block 7 of the

shelter.

• If DCDB is full then the direct connection with rec tifier can be made but

power team approval is required from Mobily.

– DCDB uses round fuses while rectifier uses fuse with pins on top and

bottom.

Page 54

Page 55: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

DCDU

Page 55

•Has 9 power outputs = Load 0- Load 5 for RRU , Load 6,7 for BBU power1&2Leave the last one blank•Should leave 1U gap between Equipments for cable routing and heat dissipation•Proper Labeling required as shown in picture

Page 56: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

BBU 1/2

Page 56

FAN

UPEU0

Slot7 BMPT

Slot6 reserved

Slot4 USCU

UPEU1

Slot5

Slot0 BBBI

Slot1

Slot2 BBBI

Slot3

BMPT = Main Processing and transmitting UnitBBBI = Base Band Processing and Radio interface UnitUPEU = Universal power and Environmental Interface Unit

Page 57: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

BBU 2/2

Page 57

BBBI CPRI0 for fiber connections to RRU

BMPT FE/GE0 for transmission [Mw IDU or Cisco Switch]GPS for GPS signal cableETH for Local commissioning

UPEUPWR for power connection with DCDUMON1/2 Input and output of environment alarm signals.EXT-ALM Boolean-value signals and monitoring the ext environment.

Page 58: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

OUTDOOR EQUIPMENT [Key points]

• Outdoor Equipments Include:

– RRU

– GPS Antenna

– Antenna RF

– Combiner

• GPS should be connected to BBU through antenna arre stor.

• Color Coding for feeder Antenna – Combiner , and CPR I for RRU – BBU is

extremely important to get rid of any cross connect ions.

• Swap Sites = RF Antenna azimuth for Existing [Samsu ng] Antennas should be

noted before installation of Huawei RF antennas.

• Three RRU power cables should be routed in one PVC pipe.

• Three RRU CPRI cables should be routed in one PVC p ipe.

• Its important to note RRU type Wimax/LTE , before i nstalling on pole/rack.

Page 58

Page 59: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU

Page 59

WiMAX RRU:

2614MHz~2624

MHz

TD-LTE RRU:

2582MHz~2602

MHz

Page 60: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential Page 60

1.RRU Rack overview - 1

Page 61: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

1.RRU Rack overview - 2

Page 61

Page 62: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU Installation 1/3

Page 62

Main bracket

Auxiliary bracket Main bracket

2

Auxiliary bracket

Main bracket 1

LTE RRU

Wimax RRU

Page 63: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU Installation 2/3

Page 63

LTE TDD RRU

WiMAX TDD RRU

Same direction

WiMAX TDD RRU

1 2

3 4

Page 64: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU Installation 3/3

Page 64

Page 65: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Combiner

Page 65

Page 66: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU- Combiner Connection

Page 66

LTE TDD RRU

BD

CA

ANTA_TX/RXANTB_TX/RX

BD C A

AD D A

BC C B

WiMAX RRU

Bottom View of LTE RRU

Top View of Combiner

ANTA_TX/RX

BD C A

AD D A

BC C B

Bottom View of WiMAX RRU

Top View of Combiner

NOTE :

COMBINER ALWAYS TO BE INSTALLED ON LTE SIDE OF THE POLE !!!

Page 67: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Antenna

Page 67

Bottom View of Antenna and Combiner

A B DC

Page 68: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Antenna Installation [Color Coding]

Page 68

Sector 2 Yellow Sector 3 BlueSector 1 RedSector 2 Yellow Sector 3 BlueSector 1 Red

Page 69: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

GPS Antenna Installation

• The location requirements for installing the GPS antenna are as follows:– Install the GPS antenna in open

air. The installation place should have no obstacles at the angle of 10° above the horizon.

– Keep the antenna away from high buildings and accessory construction on the roof.

– Install the GPS antenna on a platform as large as possible. The antenna must have an upright visual angle greater than 90°.

Huawei Technologies

LTE BMPT

WIAMX BMPT

Note :In phase 1 we just leave this cable there because we don’t insert the LTE board yet.In phase 2 we can do the connection

Page 70: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

1) Total RRU’s = 6 [3 for Wimax, 3 for LTE ]2) Total CPRI’s required = 9 [3 for Wimax , 6 for L TE ] which means each WiMAX RRU will use only 1 CPRI and each LTE RRU will us e 2 CPRI’s.3) For Project Phase 1 [Wimax 30MHZ]CPRI connection will be as follows:WiMAX RRU Sector 0 : no connection WiMAX RRU Sector 1 : no connectionWiMAX RRU Sector 2 : ConnectionLTE RRU Sector 0 : Connection [CPRI 0 only]LTE RRU Sector 1 : Connection [CPRI 0 only]LTE RRU Sector 2 : no Connection4) For Project Phase 2 [Wimax 10MHZ, LTE 20 MHZ]WiMAX RRU Sector 0 : ConnectionWiMAX RRU Sector 1 : ConnectionWiMAX RRU Sector 2 : ConnectionLTE RRU Sector 0 : ConnectionLTE RRU Sector 1 : ConnectionLTE RRU Sector 2 : Connection

Page 70

RRU-BBU Connection 1/2

WiMAX RRU:

2614MHz~2624MHz

TD-LTE RRU:

2582MHz~2602MHz

RRU Phase-1

[Wimax 30 MHZ]

Wimax Sector

0

Wimax Sector

1

Wimax Sector

2

LTE Sector

0

LTE Sector

1

LTE Sector

2

BBU Slot 3

BBBI CPRI 0 X X X Yes X XBBBI CPRI 1 X X X X Yes XBBBI CPRI 2 X X Yes X X X

Page 71: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU-BBU Connection 2/2

Page 71

From LTE CPRI_0From LTE CPRI_1 From WiMAX CPRI_0

Please put the remaining cable under BBU rack orderly!

Page 72: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU-BBU Connection Phase-1[Wimax 30MHz]

Page 72

Page 73: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

RRU-BBU Connection Final

Page 73

Page 74: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Optical Cables – CPRI color coding

Page 74

LTE CPRI fiber sector1(0,1) sector 2(0,1)

sector 3(0,1)

CPRI_0

CPRI_1

1

0

WiMAX CPRI fiber sector1, sector 2, sector 3

Page 75: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Connect the TX cable to MW IDU

Page 75

WiMAX BMPT Board:

Huawei MW IDU Service Board:

Nera MW IDU:

Note :The reserved IDU port will be finalized after confirm with Mobily

ETH-PortOptical-Port

Page 76: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Inserting LTE boards to BBU

Page 76

Page 77: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

Changing Cable Connection for LTE

Page 77

LTE CPRI_0LTE CPRI_1

Original connection:

Target connection:

Page 78: Huawei Mobily WiMAX LTE [Samar 707649] Ppt

HUAWEI TECHNOLOGIES Co., Ltd. HUAWEI Confidential

www.huawei.com

3 May 2011

Thank You

www.huawei.com