9
Shielding of Route Goward Status – 25 June 2013 • Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) • Finishing works: Metalworks – in july 2013 –2 nd layer of blacktop and parking – after Septum 16 works

Shielding of Route Goward Status – 25 June 2013

  • Upload
    elia

  • View
    18

  • Download
    0

Embed Size (px)

DESCRIPTION

Shielding of Route Goward Status – 25 June 2013. Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) Finishing works : Metalworks – in july 2013 2 nd layer of blacktop and parking – after Septum 16 works. - PowerPoint PPT Presentation

Citation preview

Page 1: Shielding  of Route  Goward Status  – 25  June  2013

Shielding of Route Goward Status – 25 June 2013

• Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th)

• Finishing works: – Metalworks – in july 2013– 2nd layer of blacktop and parking – after Septum 16 works

Page 2: Shielding  of Route  Goward Status  – 25  June  2013

Temporary road

Retaining wallPiling works

Some pictures of the works:

Page 3: Shielding  of Route  Goward Status  – 25  June  2013

Slab reinforcement

Formwork for the slab

Biocofra

Page 4: Shielding  of Route  Goward Status  – 25  June  2013

Concreting

Road works

Backfilling

Page 5: Shielding  of Route  Goward Status  – 25  June  2013

Shielding of Septum 16 Status – 25 June 2013

• Adjudication of the works on 19 June 2013

• June-July 2013 - Preparatory works

– « Sondages » – Felling of trees– Removal of the barrier closing access to the PS – Removal of the street lighting– Setting out of the works– Worksite installation– Information campaign for users and TSO

• July 2013 – Earthworks

• September 2013 - Piling works

Page 6: Shielding  of Route  Goward Status  – 25  June  2013

«Sondages»

Page 7: Shielding  of Route  Goward Status  – 25  June  2013

Worksite installations:

Parking route Gowardshared with CV

Concrete batching plant(to be confirmed)

Temporary spoil dump

Access to building 561 (RP)

«Passage pieton» closed

Page 8: Shielding  of Route  Goward Status  – 25  June  2013

Provisional ScheduleExpected in July 2013!

Page 9: Shielding  of Route  Goward Status  – 25  June  2013

Thank you for your attentionAny questions?