Shielding of Route Goward Status – 25 June 2013. Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th) Finishing works : Metalworks – in july 2013 2 nd layer of blacktop and parking – after Septum 16 works. - PowerPoint PPT Presentation
Citation preview
Shielding of Route Goward Status – 25 June 2013
• Main works of Route Goward will be completed end of June 2013 (1st layer blacktop on june 28th)
• Finishing works: – Metalworks – in july 2013– 2nd layer of blacktop and parking – after Septum 16 works
Temporary road
Retaining wallPiling works
Some pictures of the works:
Slab reinforcement
Formwork for the slab
Biocofra
Concreting
Road works
Backfilling
Shielding of Septum 16 Status – 25 June 2013
• Adjudication of the works on 19 June 2013
• June-July 2013 - Preparatory works
– « Sondages » – Felling of trees– Removal of the barrier closing access to the PS – Removal of the street lighting– Setting out of the works– Worksite installation– Information campaign for users and TSO
• July 2013 – Earthworks
• September 2013 - Piling works
«Sondages»
Worksite installations:
Parking route Gowardshared with CV
Concrete batching plant(to be confirmed)
Temporary spoil dump
Access to building 561 (RP)
«Passage pieton» closed
Provisional ScheduleExpected in July 2013!
Thank you for your attentionAny questions?