Civil engineering for LIU – PS Shielding of route Goward

Civil engineering for LIU – PS Shielding of route Goward

Embed Size (px)

Citation preview

Page 1: Civil engineering for LIU – PS Shielding of route Goward

Civil engineering forLIU – PS

Shielding of route Goward

Page 2: Civil engineering for LIU – PS Shielding of route Goward

Status – 22 may 2012

• Document « Civil engineering for increasing the radiation shielding on the route Goward. Passage over the PS » completed → EDMS approval procedure ongoing (25 may 2012)

• CE execution drawings completed → EDMS approval procedure ongoing (22 may 2012)• Tender documents completed → EDMS approval procedure completed (16 may 2012)• Market survey completed → list of firms to be finalized ( translation in english of the tender

documents to be confirmed depending on the nationality of the selected firms)

NEXT STEPS • Launch call of tender• Organize an information campaign to the attention of the occupants of the center of the ring

NEW ! • Two “sondages” requested by RP to determine if the ground around the PS is contaminated →

potential impacts on the method of execution and the cost / delay of work Reminder: the assumption for this project was that there was no RP constraints for materials and/or workers

Page 3: Civil engineering for LIU – PS Shielding of route Goward

Installation de chantier

Page 4: Civil engineering for LIU – PS Shielding of route Goward

Démolition et démontage

Page 5: Civil engineering for LIU – PS Shielding of route Goward

Terrassement et accès provisoire

Page 6: Civil engineering for LIU – PS Shielding of route Goward

Pieux

Page 7: Civil engineering for LIU – PS Shielding of route Goward

Dalle

Page 8: Civil engineering for LIU – PS Shielding of route Goward

Mur bâtiment 365

Page 9: Civil engineering for LIU – PS Shielding of route Goward

Mur de soutènement du parking

Page 10: Civil engineering for LIU – PS Shielding of route Goward

Mur de soutènement sud-est

Page 11: Civil engineering for LIU – PS Shielding of route Goward

Situation finale

Page 12: Civil engineering for LIU – PS Shielding of route Goward

Profil en long de la route

Page 13: Civil engineering for LIU – PS Shielding of route Goward

Marquage et signalisation

Page 14: Civil engineering for LIU – PS Shielding of route Goward

Provisional Schedule

Travaux préparatoires avant chantier de génie civil:

-Evacuation des transformateurs –EN/EL-Abattage des arbres GS/IS-Dépose des candélabres – GS/SE-Dépose des moniteurs RP - DGS/RP- Autres??