Current Geothermal Projects in Taiwan

Sheng-Rong Song

Geothermal team of NTU

GRC Annual Meeting & Expo

14-17 October, 2018

Status of power structure in Taiwan Gross Electricity Productions: 225.8 billions kWh

Renewable energy Nuclear energy

Gases & Coals

Hydro

2017 Power generation of Taiwan

http://www.taipower.com.tw/content/new_info/new_info-b31.aspx?LinkID=8

To find clean, renewable and sustainable energy

Nature

2011

311 (2011) Japan Earthquake and Tsunami – Nuclear disaster Taiwan has three the most dangerous nuclear power plants

Conclusions of 2015 National Energy Forum: Promote and

push the geothermal power plants commercially ASAP.

Years of decommissioning nuclear power plants:

No. 1: 2018-2019; No. 2: 2021-2023; No.3: 2024-2025

Items Installed Capacity

(MW)

Gross Electricity

Production (B- kWh)

2017 2020 2025 2017 2020 2025

Solar 1,210 6,500 20,000 1.1 8.1 25

Wind (land) 682 814 1,200 1.5 1.9 2.9

Wind

(offshore)

0 520 3,000 0 1.9 11.1

Geothermal 0 150 200 0 1 1.3

Bioenergy 727 768 813 3.6 5.6 5.9

Hydropower 2,089 2,100 2,150 6.6 4.7 4.8

Fuel Cells 0 22.5 60 0 0.2 0.5

Total 4,708 10,875 27,423 12.7 23.4 51.5

Goals of Renewable Energy in Taiwan

Energy portfolio standard (2025):

20%(renewable) + 30% (coals) + 50% (gases)

Taichung City

Potentials: 26 MW

Target: 0 MW

Ilan County

Potentials: 141 MW

Target: 29 MW

Nantou County

Potentials: 77 MW

Target: 3 MW

Chiayi County

Potentials: 11 MW

Target: 0 MW

Tainan City

Potentials: 11 MW

Target: 0 MW

Kaoshung City

Potentials: 14 MW

Target: 0 MW

New Taipei City

Potentials: 527 MW

Target: 100 MW

Hualien County

Potentials: 25 MW

Target: 3 MW

Taitung County

Potentials: 133 MW

Target: 15 MW

Taiwan Geothermal Promotion projects in 2020

BOE, 2018

Promotion and Financial supports from

government

Renewable Energy Development Act -- 2009

< 10 MW, Not necessary for environmental

assessments

Feed-in-Tariff (FIT): NT$ 5.20/kWh (17.3 cents

USD) for 20 years (Ave. NT$ 2.5/kWh)

Government’s subsidies for geothermal exploration

(drilling): ~ NT$ 100 millions (~3.2 millions USD)

R&D funds – National Energy Program

Eurasian Plate Philippine Sea Plate Ryukyu Arc

Taiwan

Luz

on

Luzon Arc

谷關

馬槽

寶來 廬山

關子嶺

知本 金崙

泰安

北投

礁溪

金山

1960-1980’s

exploration works 蘇澳

東埔

仁澤

奧萬大

四重溪

烏來 清

Tutan Volcano

Group Ilan

Area

Hua-Tung

Area

Geothermal Formosa

Recoverable Resources: 33,640 MW Altitude: <1,000 m,Depth: < 4Km,T >175℃

Lushan Area

6,170MW 2,886MW 170MW 25,754MW

N S

Geothermal play types based on geologic controls

Tatun Volcano Group Ilan Plain

Mountain Range

Magmatic-Volcanic field type

Extensional domain

type

Orogenic belt/foreland basin type

Moeck, 2014

Magmatic-volcanic field type Tatun Volcano Group

Wang et al., 1999

TVG Turtle Island

Lutao Island

Thermal manifestation

SUMMARY OF INPUT PARAMENTERS

Minumum Most Likely Maximum

km² 17.8 30.4 40

m 1200 1400 1600

0.05 0.1

℃ 250 260 280

0.1 0.2

Fixed Parameters

Seperator Temperature 145 ℃

Rock Volumetric Heat Capacity 2475 kJ/m³ ℃

Fluid Volumetric Heat Capacity 3958 kJ/m³ ℃

Condeser Temperature 50 ℃

Dead-state Temperature 20 ℃

Plant Capacity Factor 0.95

Power Plant Life 30 years

Results

MW MW/km² Utilization Fac.

425 14.45 36.16%

88 0.28%

292 35.72%

417 36.15%

375-400

Recovery Factor

Variable Parameters

Reservoir Area

Reservoir Thickness

Rock Porosity

Reservoir Temperature

Most-likely (Modal)

Statistics

Mean

Std. Deviation

Minimum(90% prob.)

Median (50% prob.)

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

Freq

uenc

y

MW

Histogram of Recoverable Geothermal Energy Reserves

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

Cum

ulat

ive

Prob

abili

ty

MW

Cumulative Probability of Recoverable Energy Reserves

SUMMARY OF INPUT PARAMENTERS

Minumum Most Likely Maximum

km² 17.8 30.4 40

m 1200 1400 1600

0.05 0.1

℃ 250 260 280

0.1 0.2

Fixed Parameters

Seperator Temperature 145 ℃

Rock Volumetric Heat Capacity 2475 kJ/m³ ℃

Fluid Volumetric Heat Capacity 3958 kJ/m³ ℃

Condeser Temperature 50 ℃

Dead-state Temperature 20 ℃

Plant Capacity Factor 0.95

Power Plant Life 30 years

Results

MW MW/km² Utilization Fac.

425 14.45 36.16%

88 0.28%

292 35.72%

417 36.15%

375-400

Recovery Factor

Variable Parameters

Reservoir Area

Reservoir Thickness

Rock Porosity

Reservoir Temperature

Most-likely (Modal)

Statistics

Mean

Std. Deviation

Minimum(90% prob.)

Median (50% prob.)

0.00%

2.00%

4.00%

6.00%

8.00%

10.00%

Freq

uenc

y

MW

Histogram of Recoverable Geothermal Energy Reserves

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

Cum

ulat

ive

Prob

abili

ty

MW

Cumulative Probability of Recoverable Energy Reserves

Potentials – volume method & Monte Carlo simulation

Reserves of TVG ~425 MW

Tseng, 2014

Reserves of TVG ~514 MW

ITRI, 2011

Depth of slice, km

Power available for slice, MW

Amount at 240-280oC, MW

Amount at 280-320oC, MW

Amount at 320-360oC, MW

Amount over 360oC, MW

3 to 4 269.66 131.2 74.0 51.2 13.3

4 to 5 390.41 192.4 98.0 68.1 32.0

5 to 6 533.21 239.9 144.5 81.9 66.9

Total 1193.29

Potentials-deep geothermal energy (EGS)

Tatun Volcano Group

Potentials of 0-4 km ~2,886 MW

LF

RTTHVE V

e

)( 0

USGS Circular 790

Chiang et al., 2011

Tseng, 2014

Challenges of TVG

Geothermal area

National Park

1 20kilometers

2796000

314000

2780000

295000

擎天崗

馬槽

磺嘴山

七星山

小油坑

頂北投紗帽山

Challanges:

Acidic corrosion

National Park

Current geothermal project in TVG

Private Company – dry steam; > 3MW (2020)

43471

43567

43609

43643

43669

43688

43706

43721

43733

43745

43756

43774

43791

43810

43831

43857

43883

43923

43982

mgal

磁測資料

電阻資料(深度400m)

Current geothermal project in Lutao

Well Depth: 150 m; T:94℃

Taipower: Two production wells with depth 1,000 m

for 2 MW

Extensional domain type

The Chingshui Geothermal field Toucheng Geothermal field

High T (~230℃ at 3,000 m deep)

Had pilot power plant

> 60 MW

With deep reservoir

Chingshui geothermal field (ROT+BOT)

ITRI, 2011

Lu et al., 2017

Current geothermal project in Chingshui

0 200 200

Meters

IC-04 IC-21 IC-19

IC-13 IC-16

IC-9

IC-01

IC-02

IC-03 IC-14

IC-18

IC-15

IC-5

IC-12

IC-06

IC-07

IC-08

IC-11

IC-10

IC-17

IC-20

C-1 C-2

Well

Hot Spring

Private Company – Binary system 300 KW

(2018); 4MW (2020)

More production wells with depths > 1,000

m will be drilled soon

More explorations will be done in the future.

More than 10 exploring wells

High T (> 180℃ at 2,000 m

deep)

> 30 MW

High thermal fluid

productions ITRI, 2011

The Toucheng Geothermal Field

Current geothermal project in Touchang

200℃, ~140 tons/hour

Taipower and Taiwan CPC: Binary system or Flashing; > 8MW

2 wells with depths > 1,500 m will be drilled in 2019

More explorations will be done in the future.

Potentials-deep geothermal energy (EGS)

Ilan area:

Potentials of 0-4 km ~6,170 MW

LF

RTTHVE V

e

)( 0

USGS Circular 790

Chiang et al., 2011

Challenges of Ilan area

Challanges:

Carbonate scaling

Poor infrastructures

Land uses

Orogenic belt/foreland basin type

Central Range 1960-1980’s exploration

Zhiben = 26 MW Chinlun = 48 MW Lushan = 41 MW

Koukuan = 15 MW

Totals:

387 MW ITRI, 2011

Potentials-deep geothermal energy (EGS)

Hua-Tung areas:

Potentials of 0-4 km ~25,754 MW

LF

RTTHVE V

e

)( 0

USGS Circular 790

Regional Silica Surface heat flow

Volume by 3-D visuslization

Chiang et al., 2011

Challanges:

Carbonate scaling

Poor infrastructures

Land uses

National Park

Challenges of Hua-Tung areas

Yushan NP

Taroko NP

Current geothermal project in Lushan and Ruisui

Private company: Binary system ~ 3MW

More explorations will be done in the future.

T: 140-180℃, ~160℃

Current geothermal project in Hongye & Jinfeng

T: 130-190℃, ~160℃; Potentials: 12 MW; Current: no; 1 MW (2020) 3MW (2025)

T: 150-210℃, ~180℃; Potentials: 18 MW; Current: no; 1 MW (2020) 3MW (2025)

Current geothermal project in Jihben & Jinlun

T: 140-200℃, ~170℃; Potentials: 25 MW;

Current: 30KW, 3MW (2020)

T: 140-180℃, ~160℃; Potentials: 48 MW;

Current: no; 2 MW (2020); MW, 10 MW (2025)

Three geothermal play types can be distinguished based on

tectonic settings in Taiwan.

They are the magmatic-volcanic field type, extensional domain

type and orogenic belt/foreland basin type.

Geothermal potentials of install capacity for those three types are

2,886 MW, 6,170 MW and 25,754 MW, respectively in Taiwan.

The major challenges for developing geothermal energy are acidic

corrosion for Tatun volcano area and scaling for others.

The geothermal energy for electricity just kicks off.

Taiwan government will speed up for the geothermal

developments in near future.

Conclusions