Shared Services Contract for

Residual Waste Treatment

Ian Telford

Clyde Valley Residual Waste

Project

1

Page 2: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

• Integrated Waste Management

• Integrated Health & Social Care

• Social Transport & Fleet Management

• Property Sharing & Management

• Back Office

• Common Charging Framework

• Joint Economic Strategy

2

Sir John Arbuthnott

Page 3: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Waste Management

• North Lanarkshire Lead Authority

• Core Team established September 2010

• Outline BC produced in November 2010

– Identify cost savings

– Treatment and Disposal Entity

Page 4: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Clyde

Valley

Waste

Arisings

Page 5: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Waste Management Project

DeliverablesDelivered were:

• Detailed Business Case

– Delivery Vehicle Options• Business plan, service review, benchmarking

• Collections Best Practice

Page 6: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Entity Options

As Is

Administrative/

Contractual Joint Working

Contractual Joint Working

Joint Committee & Joint Contractual

Working

New Entity with Contractual Powers

Joint Board

Corporate Model

Inc

rea

sin

g a

bility

to d

ele

ga

te P

ow

ers

Page 7: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Cost Avoidance - Joint Treatment & Disposal

0

1

2

3

4

5

6

7

8

9

2009/10

2010/11

2011/12

2012/13

2013/14

2014/15

2015/16

2016/17

2017/18

2018/19

2019/20

2020/21

2021/22

2022/23

2023/24

2024/25

Co

st A

void

ance

M N

om

inal

)

Residual treatment & diposal

Management & staffing

Dry recyclate

Organic treatment

Procurement activities

Page 8: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Challenges• Councils at various stages for development of their own

plans

• Zero Waste Plan and Carbon Metric Implications

• Composition of Waste (collection systems)

• Flexibility to develop and enhance recycling to fit Government policy

• Interdependency of all Projects being progressed under Waste Management

• Timelines (internal and legislative)

• Resources and Funding

• Commitment of Partner Councils

Page 9: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

9

Page 10: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Background

Four of the Eight Authorities signed up

Outline Business Case.

Inter Authority Agreement

Legally Binding Document

North Ayrshire asked to join

Re run Business case

10

Page 11: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Background

• Five Partner Councils

• 25 year Residual Waste treatment contract for

190,000 tpa from December 2019

• £700m contract

11

Page 12: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

12

Partner Councils

Page 13: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Policy Context

• - Zero Waste Plan

– Recycling Targets (70%)

– Landfill Diversion Target

(95%)

– Landfill Ban biodegradable

material (2020)

• SEPA

– Thermal Treatment

Guidelines

13

Page 14: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Main Drivers

• Sir John Arbuthnott report (2009)

• Waste (Scotland) Regulations

(2012) – ban on landfill of biodegradable municipal waste by 2020

14

Page 15: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

15

Governance

• Inter Authority Agreement

• Clyde Valley Chief Exec. and Leaders forum

• Steering group

– Chair Gavin Whitefield

– Project Sponsors

• Dedicated Project Team

• Project Group

– Financial, Legal, Technical and Planning sub groups

Page 16: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

16

Advisers

• Technical SLR Consulting

• Legal Pinsent Masons

• Financial Grant Thornton

• Insurance Willis

Page 17: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

17

Market Testing

• Meet the Buyer

• PIN released to ensure there was a market

• Survey Monkey Questionnaire

• Industry Day held over 2 days

– 31 companies came along

– 21 one to one sessions

KEY OUTCOMES

• Useful data gathering for IDD and ITPD

production

• Market Awareness (on both sides)

Page 18: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Project Concept

• No Site offered to Bidders

– Evaluation favours bidders with sites

which have planning consent

• Transfer station offered by each authority

• Primary treatment should be local

• No restriction on secondary treatment

location

18

Page 19: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Form of Contract

• Standard Contract based on WIDP

– Waste Industry Delivery Programme

– PFI based (SoPC4)

• Amended for Scots Law by

Scottish Futures Trust (kilted WIPD)

• Procured using the Competitive Dialogue

Process

19

Page 20: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Procurement Strategy

OJEU Contract Notice

PQQPre Qualification Questionnaire

ISOSOutline Solutions

ISDS Detailed Solutions

ISFTFinal Tenders

Page 21: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

21

Project Timetable

• OJEU notice January 2013

• Issued ISOS to six bidders June 2013

• Issued ITPDD to four bidders Oct 2014

• Final tenders invited June 2015

• Preferred Bidder appointed October 2015

• Financial Close 11 May 2016.

• Service Commencement December 2019

Page 22: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Viridor’s Solution

• Viridor manage Transfer Station sites

(exception NL)

• Transport to Primary Treatment Facility at

Bargeddie

• Extract Recyclate at Bargeddie

• Transport RDF to Dunbar

• Energy Recovery at Dunbar

Page 23: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

23

Budget Issues

• Tonnage related

• Guaranteed minimum tonnage– All Scottish Councils Associated Councils

• Recycling initiatives funded separately

• Other Waste initiatives funded separately

• 25 year contract

• Opex index linked – Percentage index linked is bid specific

Page 24: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Contractual Risks

• Inflation (basket of indices)

• Qualifying Change in Law

• Foreign Exchange rates (FC)

Page 25: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Benefits

• Low GMT and no exclusivity

• Guaranteed additional recycling

• Guaranteed diversion from landfill

• Composition risk with Viridor

• Year on year carbon reduction

• Community benefits

• Carbon Impact

• Economies of scale (procurement and CM

costs)

Page 26: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Contract Management

• Dedicated Contract Management Team

• Project Agreement, Authority’s Requirements,

Payment Mechanism,

• Post Contract IAA

• KPI Model (92 KPIs), Payment Mechanism

Model, IAA Model

• Annual and Monthly reports, review of KPIs,

monitoring Waste Law list, forecasting

tonnages,

• Relationship Management

Page 27: Shared Services Contract for Residual Waste Treatmentapse.org.uk/apse/assets/File/Ian Telford.pdf · Challenges • Councils at various stages for development of their own plans •

Success Factors for Shared

Services

• High Level Commitment (All Levels)

• Strong Business case

• Binding Agreement

• Build good relationships with Partners

• Project Champion

• Enthusiastic Project Team

• Effective information sharing

• Open and honest communication

27