Upload
ayik-abdillah
View
104
Download
4
Tags:
Embed Size (px)
DESCRIPTION
universitas indonesia
Citation preview
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 1
1
Chapter 2: Physical Treatment Units; Design of Sedimentation Tanks
Wastewater Engineering and Design
2
Outline
n Physical Treatment Unit
n Types of Sedimentationn Principle of Sedimentation
n Primary Sedimentation Tank
n Settling Thickener
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 2
3Figure 2-1: Physical Unit Treatment (Metcalf and Eddy, 1991)
4
Operation Applicationn Flow metering Process control, process monitoring
and discharge reports
n Screening Removal of coarse and settleablesolids by interception
n Flow equalization Equalization of flow and mass loading of BOD and suspended solids
n Mixing Mixing chemicals and gases with wastewater, and maintaining solids in suspension
n Flocculation Promotes the aggregation of small particles into larger particles to enhance their removal by gravity sedimentation
Physical Treatment Unit
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 3
5
Operation Applicationn Sedimentation Removal of settleable solids
and thickening of sludges
n Flotation Removal of finely divided suspended solids and particles biological sludges
n Filtration Removal of fine resudualsuspended solids remaining after biological or chemical treatment
n Microscreening Same as filtration
n Gas transfer Addition and removal of gases
n Volatilization Emission of volatile and semi-volatile and gas stripping
organic compounds from WW
Physical Treatment Unit
6
Types of Sedimentation
Bar Screening
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 4
7
Four Types of Settling
Type I: Discrete Settling
1. Particles settle out individually and do not interact with one another.
2. Suspension of low solids concentration.
Types of Sedimentation
8
3. Occur in:a) Grit chambers
and some primary clarifiers used in wastewater treatment plants.
b) Some presedimentationbasins in water treatment.
Type I: Discrete Settling
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 5
9
Type II: Flocculants Settling
1. As particles flocculate (due to velocity differences), they increase in mass and velocity:
a) Mixing due to hydraulic gradients in clarifier produces particle collisions:
10
b) Larger particles overtakes smaller ones and flocculate:
Type II: Flocculants Settling
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 6
11
2. Suspension of low solids concentration3. Occurs in:
a. Most primary and all secondary clarifiers in wastewater treatment.
b. Most sedimentation basins in water treatment.
Type II: Flocculants Settling
12
Type II: Flocculants Settling
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 7
13
Type III: Zone Settling or Hindered Settling
1. Formation of dense mat of particles that settle out as a unit:
Settling of different size particles will eventually form thick settling blanket that settles at a constant velocity.
14
2. Suspension of intermediate concentration.3. Intraparticle forces are sufficient enough to affect adjacent particles.4. Occurs in:
a. Thickeners (sludge disposal)b. Bottom of clarifiers and sometimes
sedimentation basins.
Type III: Zone Settling or Hindered Settling
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 8
15
Type IV: Compression Settling
1. Settling occurs by compression where water is forced out of the interstitial voids between particles.
In order to settle, water must pass through particles arranged like porous media. Furthermore, there is a high head loss due to a large surface to volume ratio. Therefore, settling occurs slowly.
16
2. Suspension by very high concentration.3. All particles are influenced by the presence of other particles.4. Occurs in drying beds and some filtration process.
Type IV: Compression Settling
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 9
17
Grit Materials
Sand, gravel, egg shells, coffee grounds, fruit rinds, seeds, bones (whos)
18
Principles of Sedimentation
Vp = Volume of particles = 1/6 Dp3 (cm3)Ap = Projected surface area of particle = /4Dp2 (cm2) Fp = Drag force = friction factor * inertial force (g-cm/s2)Fb = Bouyant force (g-cm/s2)Fg = Force due to gravity (g-cm/s2)Vs = Velocity of particle (cm/s)mp = Mass of particle (g)g = Acceleration due to gravity (cm/s2)rl = Density of water (g/cm3)rp = Density of particle (g/cm3)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 10
19
Momentum Balance
( )dbg
sp FFFFdt
Vmd--==
( )2
2s
pldplppsp VACgVgV
dt
Vmdrrr --=
Determination of the Drag Coefficient in water
Cd = f(NR) & Particle Shape
Cd can be determined if the pressure and shear stress characteristics surrounding an object are known. However, Cd can also be determined if the total drag is measured by a force dynamometer.
20
Principles of Sedimentation
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 11
21
Larminar region: viscous forces control the drag forceTurbulent region: inertial forces of displaced fluid are controlling the drag force
For laminar flow: (NR < 1)
l
splR
VDN
mr
=
Rd N
C24
=
splspl
spl
lspldd VD
VD
VDV
ACF pmpr
rmr 3
2*424
2
222
=
==
Principles of Sedimentation
22
Remembering the general equation:
( )splplpp
sp VDgVgVdt
Vdm pmrr 3--=
( )p
spl
p
pl
p
pps
m
VD
m
gV
m
gV
dt
Vd pmrr 3--=
Substituting for mp and Vp:
( )
pp
spl
pp
pl
pp
pps
D
VD
V
gV
V
gV
dt
Vd
rppm
rr
rr
6
33
--=
( )pp
sl
p
lps
D
Vg
dt
Vd
rm
rrr
2
18-
-=
Principles of Sedimentation
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 12
23
Let l
ppD
mr
t18
2
=
( )tr
r sp
ls Vgdt
Vd-
-= 1
Using the integration factor method and the initial conditions: Vs = 0 @ t = 0
( )t /lsp
V g 1 1 e- t r
= t - - r Where the relative measure of the fractional approach to SS is:
( )t /1 e- t-
Principles of Sedimentation
24
l
ppDtimerelaxationmr
t18
2
==
When t then VsVtl
tp
V g 1 r
= t - r
( )t /s tV V 1 e- t= -ornow (1-e-3) = 0.95 (it takes 3t to attain 0.95Vt)
Principles of Sedimentation
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 13
25
Example 2-1: Typical grit particle (sand)
Dp = 100 mm = 0.01 cmrp = 2.65 g/cm3
Since the typical retention time for a particle may be on the order of hours or more, we are not concerned about non-steady state.
26
Therefore, we can assume steady-state:
( ) p ls l s2
p p p
d V 18 V0 g
dt D
r -r m= = - r r
Solve for Vs: (Stokes law for settling)2
p l ps R
l
g( )DV for N 1
18
r -r=
m
Example 2-1: Typical grit particle (sand)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 14
27
Example 2-2: Bio floc particle
ml = 0.01185 g/(cm-s) rp = 1.05 g/cm3 rl = 1.0 g/cm3Dp = 100 mm T = 25 oC
Check NR
Since NR < 1, laminar flow exists and Stokes Law is Valid
28
What about a large particle size (sand)?
rp = 2.65 g/cm3 Dp = 200 mm T = 25 oC
Since the Reynolds number is greater than 1.0, Stokes law is not valid because the drag coefficient of the particle in water does not vary as 24/NR, but as:
Example 2-2: Bio floc particle
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 15
29
Rearrange the original force balance:
( ) 2p s sp p l p d l p
d m V VV g V g C A 0
dt 2= r -r - r =
Solving for Vs yield the following equation for Newtons law for settling particles:
Example 2-2: Bio floc particle
30
Using NR = 5.11 from above:
d
24 3C 0.34 6.36
5.11 5.11= + + =
recalculate NR NR = 4.38
Example 2-2: Bio floc particle
Since we cannot solve explicitly for Vs as in Stokess Law expression, we must now use a trial and error solution as demonstrated below:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 16
31
The procedure for calculating the settling velocity of a particle when NR > 1 is:
1. Use Stokes Law to obtain the initial guess for VS.
2. Use this Vs to obtain NR, if NR > 1, then go to next step.
3. Use the following iteration process:
a) Use NR to get Cd
dR R
24 3C 0.34
N N= + +
32
c) Use Vs to find new NRd) Repeat until convergence is met.
b) Use Cd to get new Vs
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 17
33
Brownian Motion
In water and WW, colloidal particles are usually present and are hard to remove by settling. A colloidal particle may be thought as a giant molecule and its Brownian motion is really a diffusion process, where diffusion results from the random thermal motion (due to thermal gradients within the fluid).
34
The above particle motion was first observed for water molecules by Dr. Robert Brown. In 1905, Einstein used Stokess relationship and developed the following equation to describe the motion.
Brownian Motion
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 18
35
Bp
1 2kTV
X 3 D
= D pm
Where: k = Boltzman constant = 1.38*10-16 (g-cm2)/(s2-K)
T = temperature (K) DX = net x component distance of travel (cm)m= kinematic fluid viscosity (g/cm-s)Dp = mean particle diameter (cm)VB = particle velocity due to Brownian Motion (cm/s)
When VB > Vs (stokes), particles will not settle out of solution because the motion of the particle is governed by collision withthe water molecules.
Brownian Motion
36
The following characteristics are typical for water and wastewater colloids:
Table 2-1: Characteristics of water and wastewater colloids (Metcalf & Eddy, 1991)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 19
37
Example 2-3:
Calculate the smallest settleable sand particle in water at 25 oC.
Assume DX = 1.0 cm
Solution
38
Setting VB = Vs
Coagulation and flocculation can be used to bring particles together to form larger ones that will settle out of solution by gravitational forces.
Example 2-3:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 20
39
Characteristics of Colloidal Particles in Water
1) Size-Very Small
1-1000 nm10-10,000 Angstroms10-4 10-7 cm
2) Surface Area Very Large
Diameter of Spheres Surface Area1 cm 0.0487 in2
10-4 cm 33.8 ft2
10-8 cm 3.8 yd2
10-6 cm 0.7 acres10-7 cm 7.0 acres
3) Charge Colloidal particles are usually NEGATIVELY charge causing repulsion of similar charge and colloidal stability.
40
Design of Type I Sedimentation Basins
Assumptions:1. Plug flow exists in settling zone where fluid
moves across the settling zone with a constant velocity.
2. Designed to remove discrete particle (settling zone only considered)
3. Particles uniformly distributed at inlet.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 21
41
Key Process Variables
1. Hydraulic retention time = t = V/Q = Vol. tank/Flowrate2. Overflow rate = Vo =Q/Atop
Vs = Flowrate/Top cross sectional area = h0/t
Vf = horizontal fluid velocity ho = height of settling zoneL = Length of settling zone
If VsVo, all particle of that diameter are removed.If Vs
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 22
43
Say Dp = 200 mm, Vs = 0.0235 m/s
Will all the particles be removed?
Example 2-4:
44
Say Dp = 100 mm, Vs = 0.0076 m/s
l
l
Example 2-4:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 23
45
Removal efficiency is independent of depth (ho) and retention time (t)
Vs = f(g,ml,rl, rp,Dp) Vo = f(Q, Atop)How can we use this information to determine the R.E. of a sedimentation tank with many sizes of particles?
(Metcalf & Eddy, 1991)
46
Break the problem into two parts.
1. For particles which have Vs Vo all particles are removed or (1-Xo) is removed.
2. For Vs Vo a fraction of the particles with such velocities are removed.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 24
47
Break down the curve for all particles with settling velocities Vs
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 25
49
How do we obtain the necessary information to make this calculation?
Two ways:1. Use Stokes equation or Newtons equation
depending on NR2. Use a column settling test (most common)
1. Put a suspension in column.
2. Mix well and sample to determine Co.
3. Stop mixing and begin timing.
4. Take samples from same depth.
50
Example 2-5:For the following data and an overflow rate of 2.0 m/hr, what is the R.E.?
Solution1. Plot x vs. Vs2. Determine Xo from overflow rate (Vo) 3. Determine R.E. from
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 26
51
ox
o so o
1R .E. (1 X ) V dx
V= - +
Example 2-5:
52
Now suppose youre given R.E. and you need to calculate Vo.
Solution: 1. Plot x vs. Vs2. Assume an Xo3. Go to curve and get Vo4. Calculate:
Example 2-5:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 27
53
5. Calculate R.E.
6. Plot R.E. vs. Vo7. Use graph to get overflow for the R.E. of interest.
Example 2-5:
54
Example 2-6:
For the following data, calculate the overflow rate for a R.E. of 75%.
ox
o so o
1R.E. (1 X ) V dx
V= - +
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 28
55
Solution1. Assume Xo = 0.207
2. Assume Xo = 0. 417
Example 2-6:
56
3. Assume Xo = 0. 65
Example 2-6:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 29
57
58Figure 2-1: Two approaches to determining minimum particle size removed in a nonturbulent chamber (Mihelcic, 1999)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 30
59
Type I Sedimentation for a Circular Clarifier
60
But Vf = Q/SA = Q/2prH = area of a cylinder with height H
All particles with Vs > Vo will be 100% removed. The analysis is the same for both circular and rectangular tanks employing type I sedimentation.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 31
61Figure 2-2: Typical rectangular primary sedimentation tank (Metcalf & Eddy, 1991)
62
Horizontal Flow Grit Chambers
Flow control weirs typically require free discharge and hence a relatively high head loss (typically 30 40% of flow depth)
Proportional weirs may cause higher velocities at the bottom leading to bottom scour
Where effective flow control is not achieved, channels will remove significant quantities of organic material requiring grit washing and classifying
With effective flow control, removal of grit not requiring further classification is possible
Excessive wear on submerged chain and flight equipment and bearings
No unusual construction is required
Difficulty in maintaining a 0.3 m/s velocity over a wide range of flows
Flexibility to alter performance is possible by adjusting outlet control device
DisadvantagesAdvantages
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 32
63
Aerated Grit Chambers
Flexibility to remove grit can adapt to varying field conditions
Significant quantities of potentially harmful volatile organic and odors may be released from wastewaters containing these constituents
Pre-aeration may alleviate septic conditions in the incoming wastewater to improve performance of downstream treatment units
Aerated grit chambers ca also be used for chemical addition, mixing, pre-aeration, and flocculation ahead of primary treatment
Some confusion exits about design criteria necessary to achieve a good spiral roll pattern removal system
By controlling the rate of aeration, a grit of relatively low putrescible organic content can be removed
Additional labor is required for maintenance and control of the aeration system
Head loss through the grit chamber is minimal
Power consumption is higher than other grit removal processes
The same efficiency of grit removal is possible over wide flow range
DisadvantagesAdvantages
64
Optimum velocity is 3 m/s0.15-0.4Horizontal velocity, m/s
Function of velocity and channel length
15-90Detention time at peak flow, s
Based on theoretical length20-50Allowance for inlet and outlet turbulence, %
Function of channel depth and grit velocity
3-25Length, m
Depend on channel area and flow rate
0.6-1.5Water depth, m
Dimension
CommentRangeItem
Table 2-2: Horizontal Flow Grit Chambers Typical Design Criteria (Metcalf& Eddy, 1999)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 33
65
Table 2-3: Aerated Grit Chambers Typical Design Criteria (Metcalf & Eddy, 1999)
Provide valves and flow meters to allow proper adjustment
0.6 0.75Transverse roll velocity, m/s
0.45 typical0.27 0.74
Medium to coarse bubble
Air supply m3/min-m
Type of diffuser
3 typical2 5 Minimum detention time (at peak flow), min
Varies widely
4: 1 typical
1.5:1 typical
0.2-5
3:1 5:1
1.1 5.1
Dimensions
Depth, m
L: W ratio
W: D ratio
CommentRangeItem
66
Type II: Primary Sedimentation Tanks
Primary sedimentation tanks are designed to:1. Reduce solids loading to minimize operational
problems in downstream treatment processes.2. Lower the oxygen demand.3. Decrease the rate of energy consumption for
oxidation of particulate matter.
These effects enhance soluble substrate removal during aeration and reduce the volume of waste activated sludge that is generated. Also removes floating material, thereby minimizing operational problems in downstream treatment processes (scum build-up in secondary treatment processes. If efficiently designed, removal rates of 50 to 70% of suspended solids and 25 to 40% of BOD5 can be realized.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 34
67
Flocculent Settling
Depends Upon:1. Overflow Rate2. Depth of Basin3. Velocity Gradients in the Basin4. Concentration of Particles5. Range of Particle Sizes6. Settling Column Analysis of
Flocculating Particles.
68
Example 2-7:
A column analysis of flocculating suspension is performed in the settling column shown below. The initial solids concentration is 250 mg/L. The data is also shown below. What will be the overall removal efficiency of a settling basin that is 3 meters in depth with a retention time of 1 hour and 45 minutes
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 35
69
Solution:1) Determine the removal rate at each depth and time.
70
2) Plot iso-concentration lines as shown is the accompanying figure.3) Construct vertical line at to = 105 min.4) Calculate the percentage removal using the following equation:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 36
71
72
This procedure is very cumbersome and time consuming. Another easier method is to calculate the removal efficiency from the average concentration in the column. For a given retention time, t, the average concentration in the column can be calculated using the following equation:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 37
73
74
Now add 1 to both side of the last equation in the previous slide.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 38
75
76
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 39
77
Type III Settling - Thickening
Definition: a process for removing water from sludge which produces a more concentrated slurry (i.e. end product is a liquid).
This process is not dewatering which produces end product with the properties of solid.
Importance of Thickening:1. Produce a greater volume of product water.2. Produce a smaller volume of sludge.3. Reduces the size of a sludge treatment facility,
(e.g. digester).
78
Purposes of Sedimentation Basins:
1. Clarification
2. Thickening
With respect to design of sedimentation basins (or clarifiers) it is essential to consider both of these functions.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 40
79(Metcalf & Eddy, 1991)
80(Metcalf & Eddy, 1991)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 41
81
Batch Settling Test
(Metcalf & Eddy, 1991)
82
Design Considerations for Thickening of Sludge
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 42
83
In which,Q = influent flow rate to the clarifier/thickener, (L3/t)Co = influent suspended solids concentration, (M/L3)Ce = effluent suspended solids concentration, (M/L3)Ac = area available for clarification, (L2)AT = area available for thickening, (L2)Qu = flow rate leaving bottom of the
clarifier/thickener, (L3/t)Cu = suspended solids concentration leaving the
bottom of the clarifier/thickener, (M/L3)Vi = settling velocity of the suspended solids, (L/t)Ci = suspended solids concentration of the blanket,
(M/L3)Ub = velocity of the solids in the underflow due to
pumping (L/t)
84
Assume: Ce
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 43
85
In which,GT = total solids flux in the clarifier (M/L2-t)Gg = settling flux in the clarifier due to gravity (M/L2-t)Gb = bulk flux due to under flow pumping (M/L2-t)
2) Sizing a clarifier for thickening based on solids flux method.
( ).T
masssolidsG Totalflux
area time=
In which, area is equal to the cross sectional area of the sludge blanket
GT = Gg + Gb
86
At the bottom of the clarifier, Ci = Cu so the expression for Gb can be written as:
u ub b u
T
Q CG U C
A= =
Since the product of QuCu is usually unknown, it can be replaced by QCo from the above mass balance, QCo = QuCu.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 44
87
In addition, at the bottom of the clarifier, Gg = 0, therefore, the area for thickening can be rewritten as:
u u o oT
L L L L b
Q C QC QCA
G G C (V U )= = =
+
88(Metcalf & Eddy, 1991)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 45
89
(Metcalf & Eddy, 1991)
90
(Metcalf & Eddy, 1991)
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 46
91
(Metcalf & Eddy, 1991)
92
Alternative definition sketch for the analysis of settling data using the solids-flux method of analysis (Metcalf & Eddy, 1991).
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 47
93
Example 2-8:
Given the treatment scheme, estimate the maximum concentration of the aerator mixed-liquor biological suspended solids concentration that can be maintained if the sedimentation tank application rate is fixed at 600 gal/ft2-d and the sludge recycle rate, Qr, is 40% of Q. The following settling data was obtained from operation of a pilot plant.
94
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 48
95
Solution1. Develop the gravity solids-flux curve from the given data.
96
2. Determine the underflow bulk velocity and plot the curve on the same graph as the gravity solids flux curve.
b 2
3
0.4Q gal 1 ftU 600 0.95
gal hQ 0.4Q ft d h7.48 24ft d
= = + -
Ub is the slope of the curve for the underflow solids flux. The underflow flux curve can be plotted using the following equation:
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 49
97
b i bG kC U=
In which,
98
3. Develop the total flux curve for the system by summing the gravity flux curve with the underflow flux curve, and determine the value of the limiting flux and the maximum underflow concentration.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 50
99
21,800 /R uC C mg L= =
100
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 51
101
Example 2-9:
102
Given the settling data in the following table derived from an activated sludge pilot plant, determine the limiting solids flux values when the concentration of the recycled solids concentration is 10,500 and 15,000 mg/L, respectively. Determine the recycle rate to the sedimentation tank required for thickening in conjunction with the aeration tank, if the MLSS in the aeration tank is to be maintained at 5,000 mg/L and the underflow concentration from the sedimentation tank is 12,000 mg/L. Neglect the effect of biological growth in the sedimentation tank and assume the flow is equal to 1.0 MGD.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 52
103
104
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 53
105
106
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 54
107
10,500
108For an underflow concentration of 12,000 mg/L the limiting solidflux, SFL, = 1.8 lb/ft2-h
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 55
109
110
22
(1 0.71)(1.0 )(5,000 )8.34 1,650
(1.8 / )(24 / )
lbmgMGD
MGLA ftmglb ft hr hr dL
+= =
-
The corresponding surface hydraulic loading rate is 606 gal/ft2-d.
Wastewater Engineering and Design
By Assist. Prof. Dr. Wipada Sanongraj 56
111
Table 2-4: Typical Design Information for Secondary Clarifiers(Metcalf & Eddy, 1999)