Sedimentation Pond PENYALIRAN TAMBANG 1

Settling Pond

Embed Size (px)

DESCRIPTION

tambang

Citation preview

PowerPoint Presentation

Sedimentation PondPENYALIRAN TAMBANG111

Prosedur Rancangan Sedimentation PondHitung Surface Runoff Volume Hitung peak inflow dischargeHitung storage volumeRetention BasinDepth of storageProsedur Rancangan Sedimentation PondHitung Surface Run off Volume:

V = C x CH x ADengan:V = volumeC = runoff coefficientCH= curah hujan untuk design storm duration tertentuA = luas catchment.Prosedur Rancangan Sedimentation PondProsedur Rancangan Sedimentation PondHitung storage volume :

S= max. storage volume in the reservior (m3)

Prosedur Rancangan Sedimentation PondRetention Basin(Mengenal hukum Stokes dahulu)Stokes Law

www.swac.umn.eduStokes Law

WDrag/Frictional Force = FdBuoyancy Force = UGravity Force = W

Fd +U = WFd = W UFd = FgU11Prosedur Rancangan Sedimentation PondProsedur Rancangan Sedimentation Pond

MaintenanceMaintenance