Upload
franz
View
18
Download
1
Embed Size (px)
DESCRIPTION
SECONDARY PARTICLE SHOWERS AND ENERGY DEPOSITION. Francesco Cerutti team (EN-STI). HL-LHC Kick off Internal Meeting 2011 Apr 15 th. WP10 SCOPE [I]. radiation sources i. collision debris (~ luminosity) - PowerPoint PPT Presentation
Citation preview
1
SECONDARY PARTICLE SHOWERSAND ENERGY DEPOSITION
Francesco Cerutti
team (EN-STI)
HL-LHC Kick off Internal Meeting
2011 Apr 15th
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition
radiation sources i. collision debris(~ luminosity)
ii. beam losses on the tertiary collimators [ ] iii. beam – residual gas interaction
(~ beam intensity) (~ beam intensity and gas density)
2
WP10 SCOPE [I]
(synergic) overlap with other
WP/activity
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 3
issues
• quench
• cooling
• material damage (coils, sensitive equipment ...)
• radiation to electronics (SEE) [ ]
• working conditions of instrumentation [ ]
• background to experiments [ ]
• activation [ ]
warm (TAS, TAN) and cold absorber design
in the following
an overview of the scenario as presently pinned
down
through a lot of work by A. Mereghetti
(past EN-STI fellow)
in fruitful collaboration with TE-MSC
(in particular E. Todesco and E. Wildner)
and thanks to many LIUWG colleagues
WP10 SCOPE [II]
(synergic) overlap with other
WP/activity
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 4
THE COLLISION DEBRIS [I]
7 TeV p + 7 TeV p
beyond the present TAS (absorbing ~150W at
L=L0=1034cm-2s-1)
about 2.5% of the interaction products
and 35% of 14TeV, i.e. 630W at L=L0
with a 50mm aperture TAS
about 3.5% of the interaction products
and almost 40% of 14TeV, i.e. 3.5kW at
L=5L0
FLUKA (DPMJET)
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 5
THE COLLISION DEBRIS [II]
FLUKA model of the present triplet in P1
spectra evolution through the triplet
striking capturing by the quadrupole magnetic field
LHC Project Report 1167 (2008)
204 T/m
Q1 Q2b Q3Q2a
The TAS provides a significant protection for Q1 only
(and reduces the background to the experiments)
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 6
IMPACT ON THE TAS-D2 REGIONmW/cm3 for
L=2.5L0
vertical plane
horizontal plane
peak of 840 mW/cm3
(i.e. 6 GGy/3000fb-1)
1.1kW
1kW
TAN at L=5L0
x=2.5mm x y=2.5mm
x z=5cm scoring grid
neutral
charged
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 7
(NOT) QUENCHING THE TRIPLET
Total lengt
h (m)
Gradient(T/m)
Aperture(mm)
36.2 156 90
40.7 125 115
43.6 112 130
45.7 104 140
the longer, the better
0
5
10
15
20
25
20 30 40 50 60Distance from IP [m]
Pea
k P
ower
[m
W/c
m3]
130 mm Phase II
90 mm Phase I
0
5
10
15
20
25
20 25 30 35 40 45 50 55 60 65 70
Peak
pow
er [m
W/c
m3 ]
Distance to IP (m)
90 mm
115 mm
130 mm
140 mm
idea and numbers by E. Todesco
(L=2.5L0)
55mm TAS aperture225 urad half crossing angle vertical crossing
same gradient, larger aperture(“Phase II”)
results and plotsby E. Wildner
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 8
SHIELDING OPTIONS•ideally a continuous liner (here 3mm tungsten, green curve) is quite effective
• the role of the interconnections! jump at the Q2a front face with liner
limited to the first element, blue curve
• as an alternative, a thick liner in Q1 (here 13mm stainless steel, purple curve) casting a shadow over Q2a
• end plates of limited help
assumed as totally absorbing! blue curve
L=2.5L0130mm coil aperture
Q1
Q1
Q2a
Q2a
Q2b Q3
Q2b Q3
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 9
110mm coil aperture
Q1 Q2a
Q2b
Q3
10mm thick additional liner
75mm residual aperture
mW cm-
3
8.05 m from the IP face 0.25 m from the IP face
1.25 m from the IP face 9.55 m from the IP face
FDDF
L=2.5L0
CROSSING SCHEME & TRIPLET CONFIGURATION
total power at L=5L0: 800W @ 1.9 K + 200W in the absorber & beam screen
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition
CROSSING ANGLE/PLANE
vertical crossing
L=2.5L0
10
x
y
z
0 vs 142.5 vs 220 urad (half)
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 11
USE OF INCREASING APERTURES
45 120 140 180(coil) aperture [mm]
(peak values depend on the coil azimuthal position!)
worse case
increasing aperture effect
10mm Cu liner effect
L=2.5L0
sextupole
skew quadrupo
le
horizontal dipole
corrector
vertical dipole corrector
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 12
MATERIAL DAMAGE [I]
r=2.5mm x =2o x z=10cm scoring grid
r=2.5mm x =60o x z=10cm scoring grid
MGy per
100 fb-1
coil insulatormW/cm3 for
L=2.5L0
dose radial profile
150 MGy per 3000 fb-1
vacuum gaskets
1.5 MGy per 3000 fb-
1
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 13
MATERIAL DAMAGE [II]
tracklength fraction [%]
photons 88
electrons/positrons 7
neutrons 4.5
pions 0.45
protons 0.15
1 MeV
particle fluence over the inner cable
200mm coil aperture
photons
positive pions
neutrons
[cm-2 per 1000 fb-1]
peak of1017 neutrons cm-2/3000
fb-1
DPA calculation
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 14
RADIATION TO ELECTRONICSpredicted high energy hadron fluence from 7 TeV p + 7 TeV p collisions in
Point 1
[units of 106 cm-2 per 100 fb-
1]
UL16 (14): 109 – 1010 UJ16 (14): 1010 – 5 1011 RR17 (13): 109 – 1011 per 3000 fb-1
beam – gas contribution(H2 equivalent density of 1015
molecules/m3,nominal beam intensity along 100 days per
year)of the same order as
the one from beam-beam collisions
RR17: ratio between beam - gas and beam - beam contributions
TCL
HL-LHC Kick off Internal Meeting 2011 Apr 15th F.Cerutti Secondary particle showers and energy deposition 15
CONCLUDING REMARKS
on the basis of the iterative evolution of the HL-LHC layout and optics (magnetic strengths,
crossing angle), a major effort will be required for setting up a suitable geometry model,
extending from the experimental vacuum chamber up to the Dispersion Suppressor, in order
to assess energy deposition / fluence values and investigate the effectiveness of possible
design solutions
estimates – especially for point quantities – are affected by systematic uncertainties (due to
the machine description and the critical dependence on few collision products emitted
inside a tiny solid angle). Therefore reasonable margins should never be forgotten, and
relative comparisons between different configurations have to be considered as inherently
carrying a stronger reliability than absolute predictions, provided that a consistent
simulation framework is constantly used
in parallel, following the underway LHC operation, simulation benchmarking is happily
ongoing