    2013-14 BUDGETBOE Meeting4/10/13

  • 7/28/2019 Schenectady Budget April 10

    2/32

    Budget Target2013-14 Appropriations $ 165,736,055

    2013-14 Revenue $ 155,685,598

    The Gap $ 10,050,457

    Add 1% Levy increase $ 522,034Fund Balance $ 2,000,000

    Amount to Reduce = $ 7,528,423

    Add 1% Levy increase = $522,034

    2013-14 Target Budget = $158,207,632

    Increase = $ 2,171,977

    % Increase = 1.39%

  • 7/28/2019 Schenectady Budget April 10

    3/32

    Aid Category 2012-13 GF

    Budget

    2012-13 GF

    Actual

    2013-14

    Budget

    Change

    From Budget

    General Purpose Aid $65,986,724 $65,990,973 $69,221,667 $3,230,694

    Foundation Aid 72,990,701 72,994,950 73,213,934 218,984Gap Elimination Adjustment ($7,003,977) ($7,003,977) (3,992,267) 3,011,710

    Expense-Based Aids 25,410,677 25,997,223 $25,787,019 376,342

    Building Aid 8,391,482 8,672,727 8,628,574 237,092

    Transportation Aid 6,740,558 6,763,064 6,763,064 22,506

    BOCES Aid 2,698,728 3,103,942 2,685,614 (13,114)

    Private Excess Cost Aid 4,380,700 4,128,423 4,380,700 0

    Public Excess Cost Aid 3,199,209 3,329,067 3,329,067 129,858

    Instructional Materials Aid 1,054,260 1,056,009 $1,050,845 (3,415)

    Computer Software Aid 144,439 155,867 155,387 10,948Library Materials Aid 66,380 65,031 64,831 (1,549)

    Textbook Aid 636,964 628,634 627,295 (9,669)

    Hardware & Technology Aid 206,477 206,477 203,332 (3,145)

    Total $92,451,661 $93,044,205 $96,059,531 3,607,870

    Spec Ed Student deduct ($200,000) ($200,000) 3,407,870

  • 7/28/2019 Schenectady Budget April 10

    4/32

    Revenue 2012-13 GF

    Budget

    2013-14

    Budget

    Change

    From 12-13

    Tax Levy $52,203,479 $52,203,479 $0

    PILOTS 2,275,815 2,364,436 88,621Interest/Penalty on Taxes 910,000 $730,000 ($180,000)

    Utility Tax 2,560,000 $2,370,000 ($190,000)

    Local revenue 465,000 385,414 ($79,586)

    Refund Prior Year Expense 400,000 400,000 $0

    ERATE reimbursement 300,000 383,000 83,000

    Gifts & Donations 135,000 25,000 $(110,000)

    Other Revenue 550,000 606,461 56,461

    Transfer Grants 300,000 300,000 0

    Federal Aid 509,700 792,700 283,000

    Total Non-State Aid $60,608,994 60,560,490 ($48,504)

    Fund Balance $3,175,00 $2,000,000

    Total Revenue $156,035,655 $158,420,021 $3,559,366

  • 7/28/2019 Schenectady Budget April 10

    5/32

    Special Education ShiftsCost Savings $700,000

    What does this mean?

    Approximately 42 students currently placed in out-of-districtprograms will return to district (six classrooms)

    Implications Reduction in tuition payments to out-of-district placements

    Increase in district staffing

    Training required for staff Classroom Management

    Functional Behavior Assessments

    Behavior Intervention Plans

    Monitoring progress

    Crisis management

    Habilitative Services

    Transition planning for students and families

  • 7/28/2019 Schenectady Budget April 10

    6/32

    Special Education ShiftsCost Savings

    $900,000

    What does this mean?

    Reduction of 97 paras district-wide and 2.5 CSE Chairs

    Implications

    Reduction of both individual and shared paras Reduction of program paras

    Reorganization of the Special Education office toward buildingbased services

    Increase in specialist staff (Reading Specialists, Behavior

    Specialists, School Psychologists) Training for staff providing specialized services

    Training for teachers and paras in classroom management andintervention skills

    Training for building staff in CSE processes

  • 7/28/2019 Schenectady Budget April 10

    7/32

    Superintendent Hearings

    Cost Savings

    $30,000

    What does this mean?

    Elimination of use of consultants acting as HearingOfficers for Superintendent Hearings

    Implications

    Increased time commitment for DLT to conduct Hearings

    Better follow through with building level staff toimplement systemic changes

  • 7/28/2019 Schenectady Budget April 10

    8/32

    Increase Class Size

    Cost savings

    $1,224,000

    What does this mean?

    Reduction of 17 FTE elementary classroom teachers K-2 maximum class size will be 25 students

    3-6 maximum class size will be 30 students

    Implications

    Increase in grade level splits (ex. split)

    Larger class sizes at the elementary level

  • 7/28/2019 Schenectady Budget April 10

    9/32

    Change to ESL Centers

    Cost Savings

    $220,000

    What does this mean?

    Decrease in travel stipends Reduction of 3 teacher FTEs (including BOCES)

    Implications

    Students will not attend their neighborhood school

    Siblings of ESL students do not attend ESL Center if theydo not qualify for ESL Services

    Once a student tests out of ESL, the student returns tohis/her home school.

  • 7/28/2019 Schenectady Budget April 10

    10/32

    Increase Medicaid Billing / ComplianceCost Savings

    $300,000

    What does this mean?

    Increase in accountability for service providers

    All prescriptions must be in place by September 1st

    All service providers must have caseloads in place by the start of the school year

    Initial observations for all students on caseload must take place within the first week ofschool

    Implications

    Processes and procedures must be monitored and enforced

    All IEPs must be entered and uploaded to Cleartrack for providers review on or before thefirst day of school

    Session notes must be signed within four working days after the service has been rendered

    Transportation for eligible Students with Disabilities must be sent to transportation providersprior to the first day of school

    Nursing services for classified students during the school day must be clearly stated on theIEP in order for Medicaid reimbursement

    Out of district service providers must follow Medicaid compliant processes and procedures

    Train newly hired staff prior to the start of the school year

  • 7/28/2019 Schenectady Budget April 10

    11/32

    UPK TransportationCost Savings

    $125,000

    What does this mean?

    144 students served at SCSD sites

    231 students served at Community-based sites

    1 full day class and 1-A.M and 1-P.M. class at Early ChildhoodCenters

    1- A.M. and 1-P.M. class at Lincoln Elementary School tocompliment the full-service grant

    Implications

    Reduction of 2.5 teacher FTEs

    Reduction of 2.5 paraprofessional FTEs

    Fewer students receiving full day pre-k (36 )

  • 7/28/2019 Schenectady Budget April 10

    12/32

    End Small Lease @ EllisCost Savings

    $8,500

    What does this mean?

    Central Registration will be relocated to an in-district location

    Will remain on a public transportation route

    Implications

    Families first experience with the district will be in a districtlocation

    A district location is more accessible for families.

    Health Services will be referred to Ellis; however, the NurseNavigator will not be on site.

  • 7/28/2019 Schenectady Budget April 10

    13/32

    Increase GrantsCost Savings

    $25,000 (already committed)What does this mean?

    Development officer will have the ability to effectively andaggressively pursue all eligible grants for the SCSD

    Additional revenue for the SCSD will likely exceed the costsavings if grants are aggressively pursued

    Increase in programming for students which would otherwisenot be possible

    Implications

    Sustainability of programs funded by grants once the grantends

    Increase Development Officer to full-time status to pursueadditional grant funding. This is an increase of .20 FTE.

  • 7/28/2019 Schenectady Budget April 10

    14/32

    Supplemental Funds(Magnet Schools)Cost Savings

    $36,000

    What does this mean?

    There will be a reduction in supplemental funds for the two city-wide magnet schools.

    There will be no supplemental funds for the two neighborhoodmagnet schools.

    Implications

    Fewer enrichment opportunities for our students attending city-wide and neighborhood magnet schools.

    Fewer resources available to support the magnet theme.

  • 7/28/2019 Schenectady Budget April 10

    15/32

    Middle School 7 Period Day

    Cost Savings $640,800What does this mean? Advanced and Enrichment level courses will be offered at MPMS

    adding rigor, depth, and complexity in order to nurture and developadvanced academic potential.

    Academic Intervention Services will be redefined. There will be a shiftfrom a scheduled course to a push-in model. Music and art will be reduced to mandated levels. Health instruction will move from 7th grade to 6th grade. Studio in Art will be offered after school. World Language will be offered to all 7th and 8th grade students.Implications Reduction of 8.9 FTEs

  • 7/28/2019 Schenectady Budget April 10

    16/32

    Non-Mandated Program Cuts(Initially)

    Cost Savings $1,510,000

    What does this mean?

    Change music and art to one time per week for 30 minutes at the

    K-6 level

    Implement scheduling efficiencies for instrumental lessons

    Instructional programs stay intact at a reduced level, including theTIE program at the elementary level and instructional support forSHS classes.

    Implications Reduction of 8 FTE music teachers

    Reduction of 6.5 FTE art teachers

    Reduction of 6 FTE librarians

  • 7/28/2019 Schenectady Budget April 10

    17/32

    Non-Mandated Program Cuts(Last Time)Cost Savings $1,120,000

    What does this mean?

    Reduce music at K-6 to 40 minutes one time per week

    Reduce art at K-6 to 40 minutes one time per week

    Implement scheduling efficiencies for instrumental lessons

    Instructional programs stay intact at a reduced level, including theTIE program at the elementary level and instructional support forSHS classes.

    Implications Reduction of 4.5 FTE music teachers

    Reduction of 2.2 FTE art teachers

    Reduction of 6 FTE librarians

  • 7/28/2019 Schenectady Budget April 10

    18/32

    Non-Mandated Program Cuts(Current Proposal)Cost Savings

    $620,000

    What does this mean?

    Eliminate art and music at the kindergarten leveI

    Implement scheduling efficiencies for instrumental lessons

    Instructional programs stay intact at a reduced level

    Implications

    Reduction of 3 FTE librarians

    Reduction of 1.8 FTE for art

    Reduction of 1.8 FTE for music for K level

    Reduction of 1.5 FTE for music efficiencies for instrumentallessons

  • 7/28/2019 Schenectady Budget April 10

    19/32

    Share Fine Arts Coordinationwith ProctorsCost Savings

    $35,000

    What does this mean? Partnership with SCSD and Proctors

    Shared responsibility for Fine Arts coordination

    Implications Reduction in dedicated services to the district

  • 7/28/2019 Schenectady Budget April 10

    20/32

    Reductions in Athletics

    Cost Savings

    $12,654

    What does this mean?

    Reduction in payment (rate) for turf supervisionImplications

    Track will remain supervised and open to the community

  • 7/28/2019 Schenectady Budget April 10

    21/32

    Elimination of Plato Credit RecoveryProgramCost Savings

    $171,500

    What does this mean?

    Students will receive intervention and/or credit recoverythrough other strategies and courses.

    Implications

    Reduction of 1.0 FTE @ SHS

    One less option for students needing credit recovery forgraduation

    Currently used with students at SAMSS

  • 7/28/2019 Schenectady Budget April 10

    22/32

    Reductions in Instructional SupportCost Savings

    $600,000

    What does this mean?

    Elimination of 3 in-resident positions

    Elimination of 3 district instructional coaches

    Elimination of .5 TLC at FDR

    Reduce Supply Budgets by 25%

    Implications

    Decrease in support for elementary principals

    Decrease in instructional and curricular support

    Decrease in supplies and materials

  • 7/28/2019 Schenectady Budget April 10

    23/32

    SHS - Zero Hour and Program and SupportReductions

    Cost Savings

    $480,000

    What does this mean?

    Limited reduction of Zero Hour as it directly impacts electives of highly

    desirable programsElimination of 2 High School Guidance Counselors

    Adjust Lab Offerings to required time reduce 3.0 science FTE

    Reduce 3 Non-mandated paraprofessionals

    Implications

    Continues to Support Options for students

    Increased Caseload

    Decrease in instructional, curricular and building time and support

  • 7/28/2019 Schenectady Budget April 10

    24/32

    Medical Insurance

    Projected Savings $360,000

    District currently uses a commission based fee structurefor its Medical Insurance broker services. Savings will beachieved by moving to a flat fee structure and other planadministrative changes, with no change to plan design.

  • 7/28/2019 Schenectady Budget April 10

    25/32

    TransportationCost Savings$125,000

    What does this mean? All in-district bus contracts were included in a RFP this spring The change is the bus contractor only - no bus route impact A current bus contractor will expand their role in the district so now only 1 bus

    contractor will handle all in-district big bus runs No change in service or routes from this RFP

    Implications This will be pure savings and will lower expenses for future contracts All in-district big buses will be handled by one vendor This allows us to leverage economies of scale by using one vendor We will still have 3 bus vendors for district runs so redundancy is in place

  • 7/28/2019 Schenectady Budget April 10

    26/32

    Operations & Maintenance Overtime

    Cost Savings

    $15,000

    What does this mean? Fewer funds available for overtime or special projects

    Implications

    Criteria for overtime approval will become more stringent Special projects may take longer to schedule and

    complete

    Summer work schedule will become tighter

  • 7/28/2019 Schenectady Budget April 10

    27/32

    Energy Savings

    Cost Savings

    $600,000

    What does this mean?

    Reduction in the district-wide utility budget 3 year agreement was signed after a new cooperative bid

    We are locked in at this lower rate until April 30, 2015

    Implications Energy conservation and reduction plans need to be developed and

    implemented to ensure usage does not increase

  • 7/28/2019 Schenectady Budget April 10

    28/32

    Copiers

    Cost Savings$25,000

    What does this mean? Numerous contracts have been re-negotiated to more favorable terms

    Reduced contract lease costs Eliminated copy overage costs in new leases Reduced the number of copiers in the district

    Implications

    Some copiers have been re-deployed to replace expiring copierleases Fewer copiers in the district Increased use of the Copy Center where our cost per copy is lowest Increased potential for Copy Center Revenue from other

    organizations

  • 7/28/2019 Schenectady Budget April 10

    29/32

    Close one School

    Cost savings

    $233,000

    What does this mean?

    Reduction of 1 administrator Reduction of 1 custodian, 1 cleaner, and 1 secretary

    Reduction of .5 nurse

    Implications

    Increase in students in neighborhood elementary schools Larger class sizes at the elementary level in

    neighborhood schools

  • 7/28/2019 Schenectady Budget April 10

    30/32

    Reorganization of District Office

    Cost savings

    $160,000

    What does this mean?

    All District Offices will be relocated to one building in orderto share more services.

    Reduction of 4 staff positions

    Implications

    Increase in shared roles

  • 7/28/2019 Schenectady Budget April 10

    31/32

    Area of Reduction Amount

    Special Education Shifts $1,600,000

    Reduce non-mandated programs $620,000

    Increase Class Size $1,224,000

    MS 7 Period Day $640,800

    Reduce Instructional Supports $600,000

    Reduce Zero Period HS Supports $480,000

    Change Management of Health Insurance $360,000

    Change to ESL Centers $220,000

    Increase Medicaid Billing / Compliance $300,000

    Superintendent Hearings $30,000

    UPK Transportation $125,000

    Reduce Energy Usage $600,000

    End Small Lease $8,500

    Share Fine Arts Coordination with Proctors $35,000

  • 7/28/2019 Schenectady Budget April 10

    32/32

    Area of Reduction Amount

    Increase Grants $25,000

    Transportation $125,000

    Reorganize Central Office $160,000

    Close one school $233,000

    Athletics $12,654O&M $15,000

    PLATO $171,500

    Copiers $25,000

    Supplemental Funds (Magnets) $36,000

    Increased Revenue $212,352

    Total $7,858,806