Generated by Jive on 2015-02-16+01:00 1 real time project NTR NTR 101 posts since Sep 20, 2007 real time project Oct 12, 2007 7:09 AM hi guru, what is life cycle of project for sap-abap and how to move from developsystem to quality system Kishore Kumar Varma 87 posts since Aug 22, 2007 Re: real time project Oct 12, 2007 8:09 AM Hi, A. Cycle fo sap -ABAP 1. Functional specs 2. Issue log 3. Technical Specs 4. Technical Spec review 5. Coding 6. Testing and Test Cases 7. Delivery of object B. Based on transport number the request can be moved from development system to quality system. Hope the above info will help you. Rewards points if useful With Regards, K K V Re: real time project Oct 12, 2007 8:18 AM Hi http://www.ondemandgk.com/content/docs/whitepapers/ OnDemand_Personal_Navigator_and_Solution_Manager.pdf

SAP Real Live SAP Implementation

  • Upload
    dfw2030

  • View
    14

  • Download
    4

Embed Size (px)

DESCRIPTION

SAP Real Live SAP ImplementationSAP Real Live SAP Implementation

Citation preview

  • Generated by Jive on 2015-02-16+01:001

    real time project

    NTR NTR 101 posts since Sep 20, 2007real time project Oct 12, 2007 7:09 AMhi guru,

    what is life cycle of project for sap-abapand how to move from developsystem to quality system

    Kishore Kumar Varma 87 posts since Aug 22, 2007Re: real time project Oct 12, 2007 8:09 AMHi,

    A. Cycle fo sap -ABAP

    1. Functional specs2. Issue log3. Technical Specs4. Technical Spec review5. Coding6. Testing and Test Cases7. Delivery of object

    B. Based on transport number the request can be moved from development system to quality system.

    Hope the above info will help you. Rewards points if useful

    With Regards,K K V

    Re: real time project Oct 12, 2007 8:18 AMHi

    http://www.ondemandgk.com/content/docs/whitepapers/OnDemand_Personal_Navigator_and_Solution_Manager.pdf

  • real time project

    Generated by Jive on 2015-02-16+01:002

    If you are working on new implementation then life cycle is same for all ..

    Implementation steps:1. AS IS process2. To be process mapping3. customizaiton in SAP + devepment4. Unit testing5. Full testing6. End-user training7. Go-live8. Support for initial month-ends.9. Ongoing support....

    Basically full life cycle is ised in the context of full implementation of the project which involves - Business BluePrint, Realization, Testing, Go live and post go live support.

    End to End can be related to a particular business process. For example, we can consider Order to Cash asend to end cycle. This will involve - creation of a Sales Order, Delivery, Billing , Customer Payment.

    SAP full life cycle starts with Reqirements gathering to go-live.

    1. Requirement gathering.2. Project initiation3. Blue print Analysis4. Dev. Phase5.Testing6.Go-live.

    Reward if usefull

    Suresh Thirumanan 9 posts since Sep 26, 2007Re: real time project Oct 12, 2007 11:09 AMHi

    I hope you are refering to the Project assignment when you create Transport requests.The assignment to a Project is just for grouping Transport requests .

    This would help to group all the development objects created for a specific purpose under many Transportrequests .

    Now this grouping of such requests can be transported together to another system for example.

  • real time project

    Generated by Jive on 2015-02-16+01:003