Sanmarg Assists & Participates in Emergency Gas
Pipeline Leak Mockdrill
A message was received in client’s control room at 6:00 am in morning that
there was a suspected leak in a gas pipeline. Consequently the Operation
In-charge of the concerned pipeline, Operation & Maintenance team, HSE
Department and the local Government Authorities of that area were
immediately informed and mobilized. The operation & maintenance team
reached in less than the 4 hours with the fully equipped emergency
response vehicle. The fire tender and Ambulance were also on standby at
the affected site.
The affected area was cordoned at a radius of 30 meter and information
was conveyed to the control room to isolate the leakage area by closing
the nearest upstream/ downstream remote operated valves. The line was
depressurized. Once the valves were closed, explosive limit (LPG has the
lower explosive limit of 5 and upper explosive limit of 15) of the gas was
checked with the help of LEL meter. The excavation work was only
performed when the LEL became zero and manual excavation had been
done, exposing the pipeline. When proper clearance for inserting the leak
clamp was given, pinhole area was identified and needle was inserted in
that area to arrest the leak. It was ensured that the needle was of the same
material of the pipeline to avoid the occurrence of localized corrosion.
After inserting the needle, leak clamp was placed and clamp screws were
tightened with the help of appropriate tools and tackles (non-sparking tools
were used). To check the integrity of tightened leak Clamp, pressure
testing was done in consultation with the control room and gas content was
continuously checked with the help of LEL meter. When all activities were
completed at the leakage location, the manual backfilling, compaction,
leveling and restoration were done as per the site condition. Control room
was informed to restart the transportation of gas. Manpower & equipment
were demobilized and a final report was generated.
SANMARG NEW PROJECT UPDATES
• Apr, 14: Reliance Gas
Pipeline Ltd. awards 21
months PMC contract for
construction supervision,
QA/QC, maintaining
pipeline spread, and
warehouse management.
• Mar, 14: Cairn India
awards three year contract
for Electrical Maintenance
services for their Above
Ground Installations in
Mangala Development
Pipeline Operations.
• Feb, 14: Reliance Gas
Transportation
Infrastructure Limited
(RGTIL) awards two
month contract for Laying
of 12″ and 4″
Interconnecting Pipeline
for Fire Water and
Instrument Air between
RGTIL’s Compressor
Stations.
Quarterly Newsletter
Apr - Jun2014 /Volume 1 / Issue 1
www.sanmargprojects.com
SANMARG’s Role in the Mock Drill
• Provided Manpower for Excavation, Backfilling, Compaction, leveling and restoration.
• Provided Welders, Fitters, Grinders etc. • Supplied heavy equipment like JCB, Hydra and Cranes. • Supplied Welding Machines, all consumables, tools and tackles,
DG Set, Spanners etc. • Supplied All PPE’s • Supplied Site Vehicle.
The Safety Checklist
• All Personnel on site were in Proper Protective Equipment. • Fire tender and Ambulance were available at site and reached
in time. • Client’s control room Team and the Site Team were in full
coordination • Adequate number of Portable fire extinguishers of type DCP
and CO2 were available. • 5 Kg DCP powder refills were available in spare. • The Leakage location was properly barricaded and the
warning signs were installed. • No mobile phones were used for communication in the
barricaded area. • First Aid box with appropriate medicines were also available.
Learnings...
• Various awareness programs should be conducted for the Villagers close to the pipeline areas, educating them about causes of leak in a pipeline and action to be taken in case a leak is noticed.
• Dedicated vehicle for emergency transportation with Proper communication system and equipment should be made available round the clock.
• Mutual Assistance protocol should be maintained with neighboring industries and villages/towns. We are very grateful to our reputed client for giving us such a great opportunity to assist and participate in the Mockdrill.
By-Ranjeet Srivastava
Fitting of leak clamp in progress
Mobile Maintenance Vehicle (MMV).
Epoxy Painting on Leak Clamp
www.sanmargprojects.com
Sanmarg Organizes a Four Day ISO
9001:2008 Internal Audit Training in
Collaboration With DNV.GL
SANMARG Employees have successfully completed an
intensive four day Internal Auditor’s training on ISO
9001:2008 standard which covered Quality Management
System, Root Cause Analysis and Corrective/
Preventive Action from 21 April 2014 to 24th April 2014.
Shri B.S. Negi Delivers a Talk on the Future
of Gas Pipelines in INDIA
Mr. B.S. Negi, Ex Member of the Petroleum & Natural
Gas Regulatory Board (PNGRB), visited SANMARG on
25th April 2014 and presented the current snapshot and
the future scenario of Natural Gas sector.
Sanmarg Projects Exhibits in the Tenth
Annual Get Energy Exhibition, London
SANMARG Projects participated in the Tenth Annual Get
Energy Exhibition which provides a networking and
information exchange platform for International E&P
companies, Engineering Services Providers,supporting
Industries and the Education sector (Universities and
Training Institutes). This Exhibition took place at
Business Design Center, London from 2nd till 4th of
June.
Internal Auditor’s Training
Session by Shri BS Negi
Mr. Subhadeep Tarat, Mr. Subbarao Cherukuri
NACE Level II NACE Level I
Congratulations!
Mr. Subhadeep Tarat (Assistant Manager, SANMARG)
and Mr. Subbarao Cherukuri (Site Incharge, SANMARG)
have successfully completed NACE Level II and NACE
Level I training respectively.
www.sanmargprojects.com
Top Oil and Gas Headlines Around the World
Upcoming Projects
Russia and India are planning
to construct a $30 Billion Oil
Pipeline through Xinjiang in
China whose groundwork has
been started on 21 October
2013 after the visit of ex
Indian Prime Minister Dr
Manmohan Singh to Moscow
for 14th India-Russia Annual
Summit.
Almost 30 new port projects
worth INR 21,000 Cr have
been awarded by the Ministry
of Union Shipping in FY 13-14
in India, meansan additional
217 MT of capacity.
In December 2013, Iran and
India agreed to construct deep
water gas pipeline of 1400
km,31 Million cubic meters
capacity across the Sea of
Oman as India keen to boost
Energy ties with Iran
Indian Oil will begin Marketing
of Refinery Catalysts to
Domestic and International
markets which is formulated
and developed by its internal
R&D division to improve
refinery margins.
AEGIS announced early
commissioning of its 70,120 KL
bulk liquid terminal at Pipava port
in Gujarat, almost six months
ahead of scheduled time. With new
capacity, Aegis Group will be able
to handle liquid volumes of over 3
to 4 Million MT and Gas Volumes
of over 750000 MT.
Northern Gateway Pipeline (1177
Km) in Canada has been approved
which transfer 5,25,000 barrels
crude from Alberta oil sands to
country’s Pacific coast.
Mergers& Acquisitions
PETRONET has invited bids to
lease out their underutilized LNG
storage tanks at Kochi, Kerala.
The underutilization occurs due to
a delay in laying of pipelines
connecting the port to consumption
centers in Karnataka and Tamil
Nadu.
Cairn Energy Plc is seeking
shareholder approval to sell its
9.65% stake in Cairn India after
restrictions imposed by Income Tax
department were lifted. Cairn
energy is expected to receive over
INR 6665.35 crore for its 9.65%
stake at the current market price.
Adani Ports and Special
Economic Zone acquired the
strategic Dhamra Port on the east
coast of India for INR 5500 Crore
from a 50:50 JV between Tata
Steel and L&T. This deal is the
largest in Indian Port sector since
the Pipava Port.
ESSAR OIL gets nod to acquire
73.99% stake in group company
Vadinar Power to make it its fully
owned subsidiary after Essar Oil’s
shareholders accepted the
proposal.
HPCL to acquire 11-15% STAKE in
Petronet’s East Coast Terminal.
HPCL is expanding its Vizag
Refinery to 15 million tones pa
from its current capacity of 8.33
MT leading to increase the gas
requirement for HPCL is huge.
New Appointments
CAIRN India ‘s interim CEO Mr. P
Elango has quit. Mr Sudhir Mathur,
CAIRN’s CFO has assumed
additional responsibilities.
Mr. NK Verma, Director
(Exploration) ONGC have been
recommended by Public
Enterprises Selection Board to
head ONGC Videsh Ltd. His
appointment is yet to be approved
by the Government.
Message from Editorial Board….
Dear Readers, Hope you like the very first edition of SANMARG Quarterly Newsletter. We invite you to share your Experience, thoughts, ideas and any meaningful feedback regarding the Newsletter. E-mail your thoughts at [email protected]
Best Wishes
Ranjeet Srivastava
Shweta Singhal Jigyasa Kaul
SANMARG PROJECTS PVT LTD
5TH FLOOR, ATS TOWER, PLOT 16, SECTOR 135, NOIDA, INDIA-201305 PH: +91 120 3127156, 120 3126486