Page 2: Sample Project Works
Page 3: Sample Project Works

March 21, 2016 Attention: C: O: F: E: Dear Sir/Madam: ____________ Construction is pleased to have the opportunity to submit to you our quotation for your present project. ____________ Construction is prepared to do your job for the price stated. Thank you for the opportunity to submit this quotation. We would be pleased to meet with you at your convenience to review our proposal in more detail. We look forward to hearing from you Yours truly, ____________ Construction

RE: DEMOLITION, EARTH & OTHER WORKS AT: (___________ Main Street, Welland) Dear Sir/Madam: ____________ Construction is pleased to have the opportunity to submit to you our quotation for your present project. ____________ Construction is prepared to do your job for the price stated. SCOPE OF WORK: DEMOLITION $________ SCHEDULE A

Demolition of the existing one story brick building of Approx. 6850 SQ FT area including basement level, foundation & footing.

Demolition of the existing two story brick building of Approx. 7250 SQ FT area including basement level, foundation & footing.

Demolition of existing asphalt area of Approx. 35000 SQ FT including removal of 3 existing basketball pole, foundation & net.

Demolition of existing concrete side walks of Approx. 3920 SQ FT area. Demolition of existing SOD area of Approx. 37300 SQ FT including salvage & relocate existing sign,

existing shrub & its roots, existing catch basin & dispose off site, existing chain link fence, posts & foundation, existing benches, existing manhole, its inlet & outlet pipes & to be filled with compacted sand, existing hydro pole, foundation pier & guy wires.

Demolitions of existing play area of Approx. 1100 SQ FT including playground equipment & benches. Load and Transport demolition debris off site from scope of work. Supply labor, equipment and material to complete scope of work.

SCOPE OF WORK: EXCAVATION $________ SCHEDULE B

Excavation for proposed building of Approx. 2670 SQ FT @ average of 4.9LF Depth to U/S footing. Supply of all Ontario One Locates within job envelope. Stockpile excavated earth material on site for reusable back-fill. Load and transport remainder of extra-excavated earth material off site. Supply all labor and equipment for completing scope of work.

Page 4: Sample Project Works

SCOPE OF WORK: FORMWORK $_________ SCHEDULE C

Supply and Install 1050 Linear Feet footings & Concrete block pier as per foundation details. Supply and Install 1050 Linear Feet foundation wall @ 4.8FT height 14in thick. Supply and Install rebar and dowels as per structural drawings. Supply and Install waterproofing system. (Liquid rubber, Delta Membrane, 4inch Weeping tile, Sump

Pump) Supply all labor and equipment and material for completing scope of work.

SCOPE OF WORK: BACK-FILL $________ SCHEDULE D Back-fill exterior wall foundations to existing grade. Back-fill of foundation walls using stockpiled excavated earth material.

SCOPE OF WORK: SLAB $_________ SCHEDULE E Supply and Install 4” compacted granular base for Approx. 18630 SQ FT for grade slab. Supply and Install 125 mm concrete grade slab. of Approx. 18630 SQ FT.

NOTES:

Note 1: Work is to be continuous and completed in one mobilization. Additional mobilization is $1850. This includes (1) removal (1) delivery of machine. Any delays or work stoppages in the work described above, caused by no fault of ____________, will be back charged at a rate of $500.00/crew hour (partial hour delays will be accumulated daily). All payments must be paid in full to validate warranty and drawings can be released.

GENERAL EXCLUSIONS Any work not shown as a scope, drawings or agreed upon before commencing of work. Supply of all permits, road closures, road housekeeping, air rights etc. Placement of hording or fencing unless listed on above scope of work. ____________ construction will not be responsible for delays in completion of work arising from

strikes, walkouts, lockouts, material shortages, fires any acts of god or any other causes beyond the control of ____________ Construction.

____________ will not do any shoring or earth retention system unless listed in our scope of work. Any winter housekeeping such as: cleaning snow, heating footings, breaking frost, defrost ice or dirt

etc, unless listed above on scope of work.

DEPOSIT/PAYMENT SCHEDULE

Complete: Scope of Work: SCHEDULE A- $_________ plus HST SCHEDULE B- $_________plus HST

SCHEDULE C- $_________ plus HST SCHEDULE D- $________ plus HST SCHEDULE E- $________ plus HST

TOTAL $____________ plus HST

Page 5: Sample Project Works

Client agrees to pay ____________ Construction $________________ (_________________) plus HST upon commencing of SCHEDULE A, and the remaining shall be paid upon completion of SCHEDULE A. Client agrees to pay ____________ Construction $________________ (_________________) plus HST upon commencing of SCHEDULE B, and the remaining shall be paid upon completion of SCHEDULE B. Client agrees to pay ____________ Construction $________________ (_________________) plus HST upon commencing of SCHEDULE C and the remaining shall be paid upon completion of SCHEDULE C. Client agrees to pay ____________ Construction $________________ (_________________) plus HST upon commencing of SCHEDULE D and the remaining shall be paid upon completion of SCHEDULE D. Client agrees to pay ____________ Construction $________________ (_________________) plus HST upon commencing of SCHEDULE E and the remaining shall be paid upon completion of SCHEDULE E.

Invoiced prior to work completed and materials supplied. Payment upon completion of work and/or materials. No Holdback. An interest charge of 2% per month (24% annually) will be assessed to overdue accounts. Nonpayment could be considered to be grounds for us to stop work, delay project and/or termination of contract. Purchaser ____________ Construction Signature: ________________ Signature: ________________ (I have authority to bind the Company) (I have authority to bind the Company) Name: Name: Title: Title: Date: Date: Witness Witness Signature: ____________________ Signature: ____________________ Name (Please Print):__________________ Name (Please Print):__________________ This quotation becomes effective as a contract when signed by duly authorized representative of each party. Any changes to this quotation must, however be signed by a representative ____________ Construction. Instructions in writing or verbally will serve as an irrevocable agreement from Owner or General Contractor, to proceed with the contract work.

Please sign and return to email: info@____________construction.com This quote expires in 14 days

Page 6: Sample Project Works
Page 7: Sample Project Works
Page 8: Sample Project Works

ID Task Name Duration Start Finish1 DEMOLITION, EARTH & OTHER WORKS AT: (___________ 

Main Street, Welland)67 days Sun 2/7/16 Tue 5/10/16

2 Demolition  23 days Sun 2/7/16 Wed 3/9/16

3 Mobilization of Equipments on Site 0 days Sun 2/7/16 Sun 2/7/16

4 Demolition of the existing one story brick building 5 days Mon 2/8/16 Fri 2/12/16

5 Demolition of the existing two story brick building 9 days Mon 2/15/16 Thu 2/25/16

6 Demolition of existing asphalt area 3 days Fri 2/26/16 Tue 3/1/16

7 Demolition of existing concrete side walks 1 day Fri 2/26/16 Fri 2/26/16

8 Demolition of existing SOD area 4 days Wed 3/2/16 Mon 3/7/16

9 Demolitions of existing play area 1 day Wed 3/2/16 Wed 3/2/16

10 Load and Transport demolition debris 10 days Thu 2/25/16 Wed 3/9/16

11 Excavation 5 days Thu 3/10/16Wed 3/16/16

12 Excavation of Footings 3 days Thu 3/10/16 Mon 3/14/16

13 Stockpile excavated earth material on site for back‐fill 1 day Mon 3/14/16 Mon 3/14/16

14 Load and transport remaining extra‐excavated earth material from site

2 days Tue 3/15/16 Wed 3/16/16

2/7

January FebruarMarch April May June J

Task

Milestone

Summary

Project Summary

Manual Task

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Sample Construction Schedule

Page 1

Project: Project3Date: Wed 3/30/16

Page 9: Sample Project Works

ID Task Name Duration Start Finish15 Foundation  31 daysWed 3/16/16Wed 4/27/16

16 Mobilization of Rebar material on site 0 days Wed 3/16/16 Wed 3/16/16

17 Mobilization of Shuttering material on site 0 days Wed 3/16/16 Wed 3/16/16

18 Rebar Fixing for Part I Footings 3 days Thu 3/17/16 Mon 3/21/16

19 Shuttering for Part I Footings 4 days Mon 3/21/16 Thu 3/24/16

20 Casting of Part I Footings 1 day Tue 3/29/16 Tue 3/29/16

21 Rebar Fixing for Part I Footings 3 days Wed 3/30/16 Fri 4/1/16

22 Shuttering for Part I Footings 4 days Fri 4/1/16 Wed 4/6/16

23 Casting of Part I Footings 1 day Thu 4/7/16 Thu 4/7/16

24 Rebar Fixing for Concrete Pier 2 days Tue 4/12/16 Wed 4/13/16

25 Shuttering for Concrete Pier 2 days Wed 4/13/16 Thu 4/14/16

26 Casting of Concrete Pier 1 day Fri 4/15/16 Fri 4/15/16

27 Rebar Fixing for Foundation Wall 4 days Mon 4/18/16 Thu 4/21/16

28 Shuttering for Foundation Wall 5 days Wed 4/20/16 Tue 4/26/16

3/16

3/16

January FebruarMarch April May June J

Task

Milestone

Summary

Project Summary

Manual Task

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Sample Construction Schedule

Page 2

Project: Project3Date: Wed 3/30/16

Page 10: Sample Project Works

ID Task Name Duration Start Finish29 Casting for Foundation Wall 1 day Wed 4/27/16 Wed 4/27/16

30 Backfill 2 days Thu 4/28/16 Fri 4/29/16

31 Back‐fill for foundations & Wall to existing grade 2 days Thu 4/28/16 Fri 4/29/16

32 Grade Slab 8 days Fri 4/29/16 Tue 5/10/16

33 Preparation of ground for slab 1 day Mon 5/2/16 Mon 5/2/16

34 Availability of granular base material 0 days Fri 4/29/16 Fri 4/29/16

35 Laying of granular base material 2 days Tue 5/3/16 Wed 5/4/16

36 Rebar fixing for grade slab 2 days Thu 5/5/16 Fri 5/6/16

37 Shuttering for grade slab 2 days Fri 5/6/16 Mon 5/9/16

38 Casting of grade slab 1 day Tue 5/10/16 Tue 5/10/16

4/29

January FebruarMarch April May June J

Task

Milestone

Summary

Project Summary

Manual Task

Manual Summary Rollup

Manual Summary

Start‐only

Finish‐only

Deadline

Progress

Sample Construction Schedule

Page 3

Project: Project3Date: Wed 3/30/16