SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
4) Sample Test Package System ID & Status Report (Database). This is mandatory on large projects. Procedures shall detail Organizational C
responsibilities for test packages & have provisions for "lost packages" & other system controls for test packages from package design through
system completion (MCC) and the QC certification process including turnover of records.
6) Test Package Format (Organization of Sections) shall be in the most effic ient manner possible to eliminate package size and yet contain all
applicable/important test information and documents needed for safe and correct system pressure testing. Copies of any procedures (Pressure
Leak Test, Reinstatement) shall only be provided with test packages on review for initial approval by Company. Procedure copies (Pressure Te
GI-2.102, etc) shall be kept at test sites (test manifolds) with associated Safe Work Permits. Combining QC forms is encouraged. SATR use is
required or alternatively, QC test reports shall contain SATR elements. Increase efficiency & eliminate waste.
5) Pressure Test Matrix is a modified line list showing all systems and proposed pressure test design for SA approval. Reduce review time
significantly & improve efficiency by performing a close review of Pressure Test Matrix & associated system information early on in major proje
"Critical Path" to MCC is nearly always Test Package Completion. Delays are often due to inefficiency, poor organization and planning, a lack o
dedicated manpower solely for Pressure Test Package development, coordination, clearance, & inadequate test planning based on a system
approach.
A2
A4
ACCEPTANCE CRITERIA REFERENCE PASS
A Test Package Database & Format (Minimum Requirements)
Features of the database shall be compatible (linked = preference) with
other SAEP-1160 required databases such as Welding & NDT to allow
efficient test package clearance control practices on a system or line
designation basis.
Note: NDT & other special processes (PWHT, PMI, Coatings, etc)
frequently hold up test package issuance. To improve efficiency, link
databases to improve package coordination, prevent rework andretesting, and identify/target outstanding special process work
SAEP-1160,
Para. 5.1,
Para. 5.2
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
NOTES: 1) SAEP-1160 Section 8 details Minimum Test Package Requirements for Projects (Plant Piping, Pipelines, Equipment). Usage of SA
1160 is mandatory when referenced by Sch Q for contracts with December 2005 cut-off dates and later.
Pressure Test Matrix (Design) uses a modified system line list and
contains specific proposed test information such as system names, line
numbers, testing design data (system class, design/test pressures
proposed), proposed test medium, test type (Hydrostatic or Pneumatic
strength test, Service Test, Bubble Leak Test, flushing requirements,
proposed Lay-up, special considerations/treatments, Chemical cleaning,
mechanical cleaning, internal FBE coating, and other pressure testdesign considerations within Remarks section. Submit this Matrix
along with a Sample Package
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER
MECH-
FAIL N/A RE-INSP
EQPT CODE SYSTEM ID. PLANT NO.
TRAVEL
EQUIPMENT DESCRIPTION
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06
LAYOUT DRAWING NUMBER
EQUIPMENT ID NUMBER(S)
SCHEDULED INSPECTION DATE & TIME MH's SPENTQUANTITY INSP.ACTUAL INSPECTION DATE & TIME
SAUDI ARAMCO USE ONLYSAUDI ARAMCO ACTIVITY NUMBER
EC / PMCC / MCC NO.REV. NO. PURCHASE ORDER NUMBER
WORK PERMIT RE
CONTRACTOR INSPECTION LEVELSAUDI ARAMCO INSPECTION LEVEL
SAUDI ARAMCO TIP NUMBER
2) Pressure Test Packages are (an integral part of) Test Procedures (See SAES-A-004 definition). Both Contract Sch Q & SAEP-1160 require
Pressure Testing Procedure, along with other procedures & a Test Package for effective/safe pressure testing work control.
3) Submit a single multiple document package as follows (30 days before the start of work per Sch Q) for Company approval:
a) Three mandatory Pressure Test Procedures (as applicable) can be combined into one (Hydrotest, Pneumatic Test, Bubble Leak Test).
b) Sample Test package with applicable QC records, Forms (per Attachment 1 of the Checklist and as listed below).
c) A Re-instatement Procedure and Checklist (Utilize SAIC-A-2006 & SATR-A-2011 or QC forms meeting SATR minimum content).
d) Pressure Test System Matrix (Modified Piping Design Line Index) per checklist as listed below.
e) Pressure Test Package Database - Sample Status Report (per checklist as l isted below).
A1
ITEM
No.
A3
Test Package Data Tracking System (Database) utilizes an elecronic
format acceptable to Company and demonstates effective Test package
tracking (system/line basis). Database is maintained & kept current &
available at all times for Saudi Aramco review.
Submit a sample "Database Status Report for Test Pkgs"
Test Package Minimum Content is per Attachment 1
Note: This checklist details SAEP-1160 specific requirements
SAEP-1160,
Section 8
SAEP-1160,
Para. 5.1,
Para. 5.2
SAEP-1160,
Para. 5.1,
Para. 5.2
Page 1 of 9
7/22/2019 SAIC-A-2003 Rev 2
2/9
DATE APPROVED QR NUMBER
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER
FAIL N/A
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH-
ITEM
No.ACCEPTANCE CRITERIA REFERENCE PASS
SAEP-1160,
Section 8
RE-INSP D
A5
Individual Test Packages consist of multiple sections:A) Flow Chart per Attachment 2 with an Index Page (Pkg Contents)
B) Pre-Pressure Test (Punch List) Section with Checklists & Forms
C) QC/NDE/Special Process Documentation (SAEP-1160 Database)
D) Pressure Test Section (SIS, system info, test/calibration reports)
E) System Cleanliness & Lay-Up & associated documentation
F) Re-Instatement Procedure with Final Inspection (QC Certified)
Six sections above can be broken down into additional sections as
outlined in Pressure Testing Procedure & Sample Test Pkg.
SAEP-1160,
Section 8
A7Index Page denotes Package Content and has specific signoffs for
Quality Control/Assurance. This can be indexed by Section.
SAEP-1160,
Section 8
A6Test Package Flow Chart (Attachment 2) denotes responsible
agencies for tracking & confirmation of various inspection reqmts.
B Pre-Pressure Test Checklist (or Punchlist) Section contains the following:
B1
Pre-Pressure Test Checklist (Punchlist) Section meets the following
requirements for specific content and field instruction:
A) Specific SAIC-A-2010 - Pre-Pressure Test Checklist (Punchlist) for
On-Plot Piping
B) SATR-A-2007 - Pre-Pressure Test Check List (QC Form)
Checklist shall cover all anticipated workscope items & provide
adequate field instruction. Spec Check usage is recommended.
SAEP-1160,
Section 8
B2
P&ID & Isometric Drawings including a bill of materials/specs.
An Index of applicable drawings is included in the test package.
Reference all Line List numbers & corresponding dwg numbers
SAEP-1160,
Section 8
C QA/QC Documentation Section contains the following (as applicable)
C1
Weld Inspection Summary Sheet (Elements per SATR-W-2008)
Note 1: This can be a single Sheet Database including all special
process work in strict accordance with SAEP-1160 Sect. 6 Tables
Note 2: Limited scopes (500 or less welds/project) are exempt and can
use a Company approved hard copy tracking system.
SAEP-1160,Section 5.1
C2Detailed Weld Map (Isos for Plant Piping, pipelines use isos or sketch
with detailed notes and legend as approved by Company)
SAEP-1160,
Section 8
SAEP-1160,
Section 8
C3NDE Records (MT, PT, RT, UT) showing extent, sequence on NDE and
selection meeting project specifications
SAEP-1160,
Section 8
C5Isolation Valve Test Certificates are available & utilize a uniqueIdentification number whenever valves are field tested before their
installation into the line for pressure testing.
SAEP-1160,
Section 8
C4
As-Built drawings as applicable to the workscope.
Note 1: Test package SHALL show the actual system under test. Ensure
piping modifications/revisions/dimensional changes are corrected by
hand (red ink is preferable) on isos/sketches. Note 2:
Corrections made by hand are acceptable (Initial & date).
Note 3: "Provide As-Built drawings" can be listed as a "B" item
C6 Flange Joint Assembly Inspection Report (SATR-L-2001).SAEP-1160,
Section 8
SAEP-1160,
Section 8
C7 Internal Cleanliness / Flushing Report (SATR-A-2008)SAEP-1160,
Section 8
C8Checklists for test preparation and Test Equipment verification
(SAIC-A-2009)
SAEP-1160,
Section 8
C8 Verification of System Readiness for Testing (SAIC-A-2004)
C9 Pressure Test Report Form (SATR-A-2001)SAEP-1160,
Section 8
Page 2 of 9
7/22/2019 SAIC-A-2003 Rev 2
3/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2
SAEP-1160,
Section 8
C10
Calibration or Test certificates for the following test instruments as
applicable: (Equivalent approved test reports are acceptable)
a. Pressure gage and recorders (SATR-A-2002/2004)
b. Temperature gage and recorders (SATR-A-2003/2005)
c. Test Relief Valve/s (SATR-A-2006)
d. Test Manifold (SATR-A-2001)
e. Water Analysis (test medium) - (SATR-A-2014)
SAEP-1160,
Section 8
E System Lay-up
C11 Reinstatement Procedure QC form & Instructions.
E1 System Lay-Up Certificate Form (SATR-A-2009)SAEP-1160,
Section 8
F Re-instatement and/or Final Assembly
REMARKS:
REFERENCE DOCUMENTS:
1. SAEP-1160 - Process Controls for Capital Projects (June 7, 2006)
F1
Final Punch List (By the Contractor)
a. SAIC-L-2022 &
b. SATR-A-2011
SAEP-1160,
Section 8
2. Schedule Q Pro Forma Contract (Contract Edition)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Name, Initials and Date:
Work is Complete and Ready for Inspection:
Name, Initials and Date:
T&I Witnessed QC Record Reviewed W or
QC Inspector PID Representative
Name, Initials and Date:
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
T&I Witnessed QC Record Reviewed W or
QC Supervisor Proponent and Others
Name, Sign and Date:
Quality Record Approved:Name, Organization,
Initials and Date:
T&I Witnessed QC Record Reviewed W or
*Person Responsible for Completion of Quality Work / Test Y = YES N =
31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER
N/A
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
REITEM
No.ACCEPTANCE CRITERIA REFERENCE PASS FAIL
7/22/2019 SAIC-A-2003 Rev 2
4/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH-
Attachment 1 -- SAEP-1160 Section 8 (Test Pkg Minimum Content)
Attachment 2 -- NEMA TC 2 (Type EPC-40-PVC)
Page 4 of 9
7/22/2019 SAIC-A-2003 Rev 2
5/9
Attachment 2 -- TEST PACKAGE FLOW CHART
Test Package (or Test System) No
Test Pack
Preparation Engineering Contractor QC
31-Dec-05
Pre-Test
Punch
Listing
(NOTE: Use form SATR-A-2007)
Construction Contractor QC
S. Aramco
Pre-Test
Punch
ListingSAPMT PID Proponent
(By Request)
Clear 'A'
Items Construction Contractor QC
Clear
S. Aramco
'A' ItemsConstruction Contractor QC SAPMT PID
Flushing &
Cleanliness Construction Contractor QC SAPMT PID Proponent
(By Request)
Proponent
(By Request)
Pressure
Testing Construction Contractor QC SAPMT PID Proponent
Construction Contractor QC SAPMT
System
Lay-Up Construction Contractor QC SAPMT PID
S. Aramco
Final Insp
for MCCSAPMT PID Proponent
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED
Reinstate
System
Final Insp
(Contractor)
QR NUMBER
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH-
Page 5 of 9
7/22/2019 SAIC-A-2003 Rev 2
6/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
C6 Flange Joint Assembly Inspection Report (SATR-L-2001).SAEP-1160,
Section 8
C5Isolation Valve Test Certificates are available & utilize a uniqueIdentification number whenever valves are field tested before their
installation into the line for pressure testing.
SAEP-1160,
Section 8
QA/QC Documentation Section contains the following (as applicable)C
C1
Weld Inspection Summary Sheet (Elements per SATR-W-2008)
Note 1: This can be a single Sheet Database including all special
process work in strict accordance with SAEP-1160 Sect. 6 Tables
Note 2: Limited scopes (500 or less welds/project) are exempt and can
use a Company approved hard copy tracking system.
SAEP-1160,Section 5.1
C2Detailed Weld Map (Isos for Plant Piping, pipelines use isos or sketch
with detailed notes and legend as approved by Company)
SAEP-1160,
Section 8
C3NDE Records (MT, PT, RT, UT) showing extent, sequence on NDE and
selection meeting project specifications
SAEP-1160,
Section 8
C4
As-Built drawings as applicable to the workscope.
Note 1: Test package SHALL show the actual system under test. Ensure
piping modifications/revisions/dimensional changes are corrected by
hand (red ink is preferable) on isos/sketches. Note 2:
Corrections made by hand are acceptable (Initial & date).
Note 3: "Provide As-Built drawings" can be listed as a "B" item
SAEP-1160,
Section 8
B2
P&ID & Isometric Drawings including a bill of materials/specs.
An Index of applicable drawings is included in the test package.
Reference all Line List numbers & corresponding dwg numbers
SAEP-1160,
Section 8
C9 Pressure Test Report Form (SATR-A-2001)SAEP-1160,
Section 8
A7Index Page denotes Package Content and has specific signoffs for
Quality Control/Assurance. This can be indexed by Section.
SAEP-1160,
Section 8
B1
Pre-Pressure Test Checklist (Punchlist) Section meets the following
requirements for specific content and field instruction:
A) Specific SAIC-A-2010 - Pre-Pressure Test Checklist (Punchlist) for
On-Plot Piping
B) SATR-A-2007 - Pre-Pressure Test Check List (QC Form)
Checklist shall cover all anticipated workscope items & provide
adequate field instruction. Spec Check usage is recommended.
SAEP-1160,
Section 8
B Pre-Pressure Test Checklist (or Punchlist) Section contains the following:
A6Test Package Flow Chart (Attachment 2) denotes responsible
agencies for tracking & confirmation of various inspection reqmts.
SAEP-1160,
Section 8
C8 Verification of System Readiness for Testing (SAIC-A-2004)SAEP-1160,
Section 8
C7
SAEP-1160,
Section 8
ITEM
No.ACCEPTANCE CRITERIA FAIL N/AREFERENCE PASS RE-INSP D
A5
C8Checklists for test preparation and Test Equipment verification
(SAIC-A-2009)
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH-
Individual Test Packages consist of multiple sections:A) Flow Chart per Attachment 2 with an Index Page (Pkg Contents)
B) Pre-Pressure Test (Punch List) Section with Checklists & Forms
C) QC/NDE/Special Process Documentation (SAEP-1160 Database)
D) Pressure Test Section (SIS, system info, test/calibration reports)
E) System Cleanliness & Lay-Up & associated documentation
F) Re-Instatement Procedure with Final Inspection (QC Certified)
Six sections above can be broken down into additional sections as
outlined in Pressure Testing Procedure & Sample Test Pkg.
SAEP-1160,
Section 8
Internal Cleanliness / Flushing Report (SATR-A-2008)SAEP-1160,
Section 8
Page 6 of 9
7/22/2019 SAIC-A-2003 Rev 2
7/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
ITEM
No.ACCEPTANCE CRITERIA FAIL N/AREFERENCE PASS RE
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
SAUDI ARAMCO INSPECTION CHECKLISTSAIC NUMBER DATE APPROVED QR NUMBER
Review of Test Package Preparation
(Content, Format & Database)SAIC-A-2003 1-Dec-06 MECH
C10
Calibration or Test certificates for the following test instruments as
applicable: (Equivalent approved test reports are acceptable)
a. Pressure gage and recorders (SATR-A-2002/2004)
b. Temperature gage and recorders (SATR-A-2003/2005)
c. Test Relief Valve/s (SATR-A-2006)
d. Test Manifold (SATR-A-2001)
e. Water Analysis (test medium) - (SATR-A-2014)
SAEP-1160,
Section 8
SAEP-1160,
Section 8
F1
Final Punch List (By the Contractor)
a. SAIC-L-2022 &
b. SATR-A-2011
SAEP-1160,
Section 8
System Lay-Up Certificate Form (SATR-A-2009)SAEP-1160,
Section 8
C11 Reinstatement Procedure QC form & Instructions.
REFERENCE DOCUMENTS:
1. SAEP-1160 - Process Controls for Capital Projects (June 7, 2006)
2. Schedule Q Pro Forma Contract (Contract Edition)
E1
T&I Witnessed QC Record Reviewed W or
QC Record Reviewed Wor
*Person Responsible for Completion of Quality Work / Test Y = YES N =
QC Supervisor Proponent and Others
Name, Sign and Date:
Quality Record Approved:Name, Organization,
Initials and Date:
T&I Witnessed QC Record Reviewed W or
Name, Initials and Date:
Performed Inspection Work / Rework May Proceed
Name, Initials and Date:
QC Inspector PID Representative
Name, Initials and Date:
Work is Complete and Ready for Inspection:
Name, Initials and Date:
T&I Witnessed
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
E System Lay-up
REMARKS:
F Re-instatement and/or Final Assembly
7/22/2019 SAIC-A-2003 Rev 2
8/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Attachment 1 -- SAEP-1160 Section 8 (Test Pkg Minimum Content)
Attachment 2 -- NEMA TC 2 (Type EPC-40-PVC)
Review of Test Package Preparation
(Content, Format & Database)MECH-SAIC-A-2003 1-Dec-06
Page 8 of 9
7/22/2019 SAIC-A-2003 Rev 2
9/9
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - December 2005) Rev 2 31-Dec-05
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Review of Test Package Preparation
(Content, Format & Database)MECH-SAIC-A-2003 1-Dec-06
Attachment 2 -- TEST PACKAGE FLOW CHART
Test Package (or Test System) No
Flushing &
Cleanliness PID Proponent
(By Request)
PID
Test Pack
Preparation Engineering Contractor QC
Pre-Test
Punch
ListingConstruction Contractor QC
Construction Contractor QC SAPMT
PIDContractor QC SAPMT Proponent
System
Lay-Up Construction Contractor QC SAPMT PID Proponent
(By Request)
Pressure
Testing Construction
S. Aramco
Final Insp
for MCCSAPMT PID
Reinstate
System
Final Insp
(Contractor)Construction Contractor QC SAPMT
Proponent
Clear
S. Aramco
'A' ItemsConstruction Contractor QC SAPMT
Clear 'A'
Items Construction Contractor QC
S. Aramco
Pre-Test
Punch
ListingSAPMT PID Proponent
(By Request)
(NOTE: Use form SATR-A-2007)
Page 9 of 9