32
E. PICHOT EUROnu-CERN 09/06/2011 Page 1 Safety at SPIRAL2

Safety at SPIRAL2

  • Upload
    manju

  • View
    32

  • Download
    0

Embed Size (px)

DESCRIPTION

Safety at SPIRAL2. Summary. Administrative procedure SPIRAL2 Presentation Safety approach Releases authorization. Administrative procedure. French regulation – significant evolutions. - PowerPoint PPT Presentation

Citation preview

Page 1: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 1

Safety at SPIRAL2

Page 2: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 2

Summary

Administrative procedure

SPIRAL2 Presentation

Safety approach

Releases authorization

Page 3: Safety at SPIRAL2

Page 3E. PICHOT CERN 09/06/2011

Administrative procedure

Page 4: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 4

French regulation – significant evolutions

Main text : Law dedicated to transparency and safety in nuclear field (« loi TSN » in French), 13/06/2006

Change in national organization :

IRSN

GANIL ASN (Nuclear Safety Authority)

MSNR (under Ministry)

And the New Environmental Authority (linked with MSNR)

Administrative

Technical

Page 5: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 5

Application decree of TSN law : decree 2007-1557, 02/11/2007

describes all the steps to produce a creation/modification authorization demand (DAM) for a nuclear facility, and the content of the different documents

French regulation – significant evolutions

+Releases authorization demand for SPIRAL2 and for the existing

facility

SPIRAL2 : modification of the perimeter of the nuclear facility

SPIRAL2 is one of the first facilities following this new procedure.

Page 6: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 6

Administrative procedure : 2009 - 2010

19/05/10

Official acceptation (by MSNR) to launch the public enquiries (all other points OK)

Public enquiries

14/06/10 15/07/10

27/07/10 Questions of

the public enquiry

commission

05/09/2010

Favourable opinion of

PEC

Administrative Authorization

to start buildings

construction

11/10/10

GANIL answers

13/08/10

Technical Safety Validation (buildings

conception)

02/12/10

Page 7: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 7

Technical Instruction of Impact Study

Technical prescriptions for releases

Administrative procedure : In progress …

Administrative Authorization

Compliance Test for all Satefy equipments

SPIRAL 2 Decree

Preliminary safety report Phase 2

Page 8: Safety at SPIRAL2

Page 8E. PICHOT CERN 09/06/2011

SPIRAL2 Presentation

Phase 1 Phase 2

Page 9: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 9

Existing GANIL

Page 10: Safety at SPIRAL2

Page 10E. PICHOT CERN 09/06/2011

Phase 1

SPIRAL2 Project

Ions (>C) : 15 MeV/A, 1 mA

Deuteron : 40 MeV, 50 µA

Deuteron : 40 MeV, 5 mA

Dedicated for Deuteron

Phase 2

C Converter and UCx Target 1014 fissions/s

HEB : Deuteron (40 MeV, 5 mA)

Page 11: Safety at SPIRAL2

Page 11E. PICHOT CERN 09/06/2011

133 m

Level : - 9.50 m

Free room for (Q/A 1/6) SuperconductingLINAC

Neutrons for Science Area (NFS)

Beam to the PRODUCTION target

S3 Exp hall

Reserved space for+ Exp Area / + LINAC

Phase 1 : Beam level

Injector area (Q/A 1/3 and deuterons)

Page 12: Safety at SPIRAL2

Page 12E. PICHOT CERN 09/06/2011

Filling up layer (using the limestone extracted during the excavation)

Phase 1 : Cross section View

Page 13: Safety at SPIRAL2

Page 13E. PICHOT CERN 09/06/2011

DESIR

Ganil

HE Beam

Phase 2 : Beam level

Page 14: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 15

Currently …

Page 15: Safety at SPIRAL2

Page 16E. PICHOT CERN 09/06/2011

Safety Approach

Page 16: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 17

Different sources of ionizing radiation :Neutrons produced by nuclear reaction between beam and :

Vacuum chamber in case of diffuse loose (1 W/m)

Target and/or beam dump

Prompt Gamma produced by nuclear reactions due to :Beam (in target and beam dump)

Neutrons (in concrete)

Gamma from decay of radionuclides produced by :Beam activation

Neutron activation

Radioactive targets

Decay of radioactive beam

External exposure

Page 17: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 18

Safety ApproachShielding (concrete + limestone)

Radioprotection (french regulation rules)

limestone activation (lower than 1/10 of specific activities from french regulation (same values as those of the 96/29 european directive))

Safety access systemUGA : Prevent Beam and Workers in the same room at the same time

UGB : Radiation measurement

ALARA approachMonitoring of diffuse beam losses (BLM, …)

Estimation of worker dose due to maintenance (hypothesis of process availability)

Concrete, limestone and safety access system are safety classified

External exposition

Page 18: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 19

Shielding

Calculation chain : MCNPX – FISPACT2007 – MCNPX Transport - Activation - Transport

Neutrons Dose rate (Sv/h)

(0,0)

X

Y

220

210-3217

212

210-4

210-4

210-1

P06

P08

P01

239

218

217 210-4

247209214215

Y

Z

P08 P06

P09

P12

P16

Surépaisseur à évaluer

Page 19: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 20

Safety Access system

UGAs (S7-300F)CPU – CPU317F

UGAn (S7-300)CPU – CPU315

Entrées sécurisées –

SM326

Sorties – SM322

Sorties sécurisées –

SM326

Entrées – SM321

Sorties – SM322

Entrées – SM321

SAS- unicité de passage :

SYS A et B- présence personne :

SYS A et B- portes automatiques- clé passage matériel- BP entrée et sortie

SUPERVISIONUGAs

Porte manuelle- capteurs porte fermée

- capteur porte verrouillée- synthèse portes

fermées/verrouillées

Porte automatique

- verrou- capteurs porte fermée

- capteur porte verrouillée

Porte bouchon- actionneur fermeture- actionneur ouverture

- capteurs porte fermée- capteur porte ouverte

Système d’aide à la

ronde : Type 2

SAAFs (S7-300F)

Sorties sécurisées –

SM326

Entrées sécurisées –

SM326

AFP

AFPS

SFAP5

Communication profisafe

Communication profisafe

Communication profibus

UGB (S7-300)

Sorties – SM322

Entrées – SM321

Communication profibus

UGBd (S7-200)

CPU – CPU224

Sorties – EM223

Entrées – EM223

2

1

6

4

2

2

1

2

18

2

9

2

2

4

1

SAAFc

AFR AFRS SFAP6

- Bloc AF- Dipôle standard

- Dipôle AP

Communication Ethernet

Communication Ethernet

1

1

1

Communication Profibus

Communication EthernetCommunication

Ethernet

Réseau Profibus

Réseau Ethernet

2

4

1

1 1 1

1

BP

1

BP

2

BP

1

4

2

2

2

2

2

2

2

1

1

1

6

3

1 à 3

2

23 2 2 2 2 2 2

2

2

1

1

4

1

1

1

Système d’aide à la

ronde : Type 1

2

1

2

1

1

CPU – CPU315

CPU – CPU317F

3

3

4

4

SSE

Eclairage salle Réseau / Liaison série

Entrée / sortie ToR

SUPERVISION UGAn

PCA

2

4

4

SRSA

1

1

2

Porte automatique

Porte BouchonBEAM ON

1

SUPERVISIONUGB

Signalisation lumineuse

2

2

Seuils Balises (SHBF, S2, Sa)

PCB

4

4

1

1

Page 20: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 21

Safety Access system :

Autorisation UGAn

0s 1min 2min

Temporisation 2 min

SSE discontinu SSE fixe

Réduction éclairage 2/3

Sécurité Faisceau locale

SRSA

PCA

Autorisation UGAs

x2

Autorisation SRSA

Sortie SRSA UGAn

UGAAccès interdit

autorisé

Sortie SRSA UGAs x2

Interdiction ouverture porte bouchon

Information PCP clignotante Information PCP fixe

UGA

Demande accès

interdit UGAs

x2

Verrouillage portes automatiques

Demande accès

interdit UGAn

BEAM ON

Page 21: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 22

Collect of input for all the process equipments :duration of maintenance (based on GANIL experience or on first test operations)

dose rate in situ or in isolated place for each equipment

identification of different kinds of workers (mechanic, vacuum specialist …)

Verification of the individual worker’s dose objective of

2 mSv per year

ALARA approach

Page 22: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 23

Very large difference between the two phases of SPIRAL2 :Phase 1 :

Actinides targets with a maximum activity of 1 GBq for the thin targets and 10 GBq for sealed targets

Human handling

Accidental impact for the public lower than 1 µSv

Phase 2 :UCx target up to 1014 fissions/s with radioactive inventory up to 6.1014 Bq

Maintenance in hot cell

Accidental impact for the public in the order of 1 mSv

Under vacuum, the first static barrier is continuous from production (red zone) to experiment area (green zone)

Confinement

Page 23: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 24

First barrier :

Sealed Target capsule :Designed to resist in case of fall

Wall of the chamber and Vacuum valves :Diaphragma (before and after the thin target)

Survey of pressure and quick valves automatism

Second barrier :

Nuclear ventilation

Calculated to Earthquake (walls and filters)

Automatic fire extinction (foam)

Confinement : Phase 1

Page 24: Safety at SPIRAL2

Page 25E. PICHOT CERN 09/06/2011

UCx Characteristics :

UC + 7/3 O2 = 1/3 U3O8 + CO2 ΔHR = -1488 kJ mol-1

UC + 2 H2O = UO2 + CH2 + hydrocarbures supérieursUC + 2 H2O = UO2 + 2H2 + C

ECS

Extraction

Converter

Pumping System

Confinement : Phase 2

Zone de transfert

Chambre source

Cible de production

Page 25: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 26

The concentration of oxygen in the production cave is controlled below 1 % :Walls and filters of the production cave are calculated to earthquake

Survey of pressure and quick valves automatism

Vacuum valves can be closed if an earthquake occurs

Water cooling system (oven, source, converter) :Double Layer between water and UCx

If not achievable to realize, single layer could be acceptable :with specific calculation

the equipment need to be changed each time

Confinement : Phase 2

Page 26: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 27

Confinement : Phase 2

Page 27: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 28

External risks :Air plane crash :

The production building is calculated to a plane crash

(LEARJET 23)

Propane and Butane transport Truck :Production cave and gaseous storage are located under the ground level

The parts of the building which contain significant radioactive inventories are built to resist to an overpressure of 50 mbar

Earthquake :The production building is calculated to Safety earthquake

Risks analysis are under progress to define requirements on the equipments

Confinement : Phase 2

Page 28: Safety at SPIRAL2

Page 29E. PICHOT CERN 09/06/2011

Releases authorization

Page 29: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 30

Releases

Limits for radioactive releases (on activity flow, on volumetric activity) :

tritium

iodine

rare gasses ;

others bêta et gamma emitters ;

alpha emitters.

Limits for chemical releases (on concentration, on flow - kg/year, kg/day, kg/hour…)

Decree of 26/11/1999 :As low as possible

Uncontroled radioactive releases : not allowed

Collected at the origin, filtered, treated if necessary, released only by smockestack with minimal flow and suitable height

Page 30: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 31

Releases

Category Activity for 1 year Existing GANIL (Bq)

Activity for 1 year SPIRAL2 Phase 1

(Bq)

Activity for 1 year SPIRAL2 Phase 2

(Bq)

Tritium 2.1.1096,5.109 8,6.1011

Rare gasses 3.35.1010

2,2.1012 1,6.1012

Iodin 1.94.108

0,5.106 6,2.106

Carbone 14 5.6.1044,3.107 1.4.109

Other emitters 1.2.1013

1.4.1012 3,3.1012

Page 31: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 32

Gamma emitters : permanent registration on 4 points near the site limit, one situated under prevailing wind, Systematic measure at site limits once a month, Permanent and systematic measure outside of the site and on several points,

On 4 points : air sampling system for the measure of the radioactive elements having a release limit,

On the same points : dust sampling system and filter, analysed once a day for radioactivity,

Rain sampling during a month around the site,

Ground sampling once a year,

Grass and milk sampling once a month,

Main agricultural products sampling once a year.

Environment control

Page 32: Safety at SPIRAL2

E. PICHOT EUROnu-CERN 09/06/2011 Page 33

Suggestion of implementation for GANIL