Role of Account Management at ERCOTNodal Training ProjectDebrief for TPTF
September 12, 2006
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Agenda
I. Readiness Discussion
II. Course Availability and Schedule
III. Nodal Training Communications
IV. Standard Course Development Process
V. Project Planning and Budgeting Assumptions
VI. Suggestions for Restructuring the Course Curriculum
VII. LMS Update
VIII. Nodal 101 Course Update
VII. LMP 201 Update
VIII. Work in Progress
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTReadiness Discussion
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Discussion
• Materials have all been distributed– Summarized TAC comments– Market Readiness Requirements
• Validate comments and discuss
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTCourse Availability and Schedule
Market Education
September 12, 2006 TPTF Nodal Training Debrief
TPTF Curriculum – Proposed Availability Schedule
Group / Course
Pro
po
sed C
ou
rse H
ou
rs
So
urce o
f SM
E
No
dal T
rainin
g
Su
pp
ort
Delivered
By
NE
RC
Certified
Test R
equ
ired
Visu
al Pro
cess Map
Face to
Face
Availab
le
Web
-Ex A
vailable
Web
-based
A
vailable
Basic Training Program QSE 40 Nodal Training Standard Process Nodal Training Yes Yes Yes June, 2007 June, 2007 Aug, 2007CRRs, PCRRs, and Supply Hedging 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Nov, 2007 Nov, 2007 Dec, 2007ERCOT 101 for Wind Generation 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Jan, 2008 Feb, 2008 Mar, 2008ERCOT LMP 201 (Economics) 8 Prof. Baldick TBD Prof. Baldick No TBD No Oct, 2007 NA NAERCOT Nodal 101: The Basics 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Available Dec, 2006 Dec, 2006Extended Training - System Dynamics 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Sep, 2009 NA NAGeneration 101 16 Nodal Training Standard Process Nodal Training Yes Yes Yes Dec, 2007 Jan, 2008 Feb, 2008Generation 201 16 Nodal Training Standard Process Nodal Training Yes Yes Yes Dec, 2007 Jan, 2008 Feb, 2008Generation 301 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Dec, 2007 NA NALoad Serving Entity 201 20 Nodal Training Standard Process Nodal Training Yes Yes Yes May, 2007 May, 2007 July, 2007Market Settlements 301 16 Nodal Training Standard Process Nodal Training Yes Yes Yes Sep, 2007 Oct, 2007 NAMIS 101: Market Information Systems 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Dec, 2007 Jan, 2008 NANetwork Model Management 16 Nodal Training Standard Process Nodal Training Yes Yes Yes Nov, 2007 Nov, 2007 NANOIE QSE Operations 8 Nodal Training Standard Process Nodal Training Yes Yes Yes May, 2007 July, 2007 NAScenario-based Training for Generators 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Oct, 2008 NA NAScenario-based Training for LSEs 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Oct, 2008 NA NAScenario-based Training for TSPs and DSPs 8 Nodal Training Standard Process Nodal Training Yes Yes Yes Oct, 2008 NA NASystem Operator Seminar (Support for) 24 Nodal Training Standard Process Nodal Training Yes Yes Yes 2009 NA NATransition to Nodal Markets & Start-up Testing 16 Nodal Training Standard Process Nodal Training Yes Yes Yes April, 2007 May, 2007 NATransmission 101 20 Nodal Training Standard Process Nodal Training Yes Yes Yes Nov, 2007 Nov, 2007 Jan, 2008
Available dates are based on current information, staffing and plan assumptions.
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Requested Supported Courses and Capabilities
Group / Course
Pro
po
sed C
ou
rse H
ou
rs
So
urce o
f SM
E
No
dal T
rainin
g
Su
pp
ort
Delivered
By
NE
RC
Certified
Test R
equ
ired
Visu
al Pro
cess Map
Face to
Face
Availab
le
Web
-Ex A
vailable
Web
-based
A
vailable
EMS Product Training 16 Vendor Templates, LMS Upload Vendor Yes Yes No TBD NA NA
MMS Product Training 16 Vendor Templates, LMS Upload Vendor Yes Yes No TBD NA NA
OTS Product Training 16 Vendor Templates, LMS Upload Vendor Yes Yes No TBD NA NA
NMMS Prodcut Training 16 Vendor Templates, LMS Upload Vendor Yes Yes No TBD NA NA
CRR Product Training 32 Vendor Templates, LMS Upload Vendor Yes Yes No TBD NA NA
ROME Product Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NANodal Operating Guide Training 16 Collen - IRT Standard Process Nodal Training Yes Yes No May, 2007 NA NAControl Room Desk Procedure Training 20 OTS Trainer Standard Process OTS Trainer Yes Yes Yes Dec, 2007 NA NA
EMS Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
MMS Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
OTS Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
NMMS Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
CRR Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
ROME Application Support Training 24 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NA
Outage Scheduler Application Support Training 40 Vendor Templates, LMS Upload Vendor No Yes No TBD NA NAMIS Application Support Training 16 ERCOT team 25% Support ERCOT team No Yes No TBD NA NAEDW Application Support Training 16 ERCOT team 25% Support ERCOT team No Yes No TBD NA NAMP Registration Application Support Training 16 ERCOT team 25% Support ERCOT team No Yes No TBD NA NATIBCO / EAI Application Support Training 24 ERCOT team 25% Support ERCOT team No Yes No TBD NA NA
September 12, 2006 TPTF Nodal Training Debrief
Scheduling Assumptions
• The available dates are based on the current EDS delivery schedule and phasing
(prior to Sept, 2006) and the Curriculum descriptions regarding Training Readiness.
• ERCOT Team refers to ERCOT staff and contractors who are developing an
application.
• Vendor assumes that the vendor developing the software is contracted to create
and deliver the courses (including tests) in approved format.
• Individual course delivery schedules are not currently scheduled other than for 101
The Basics (Typically delivery schedules are finalized 30 days before date
available, rooms are preliminarily assigned at the beginning of course
development).
• WebEx productions are currently not scheduled.
• All courses (other than LMP 201 which replaced LMP 101) will be hosted on LMS.
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTNodal Training Communication
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Proposed Nodal Training Site
http://nodal.ercot.com/training/index.html
September 12, 2006 TPTF Nodal Training Debrief
Proposed Course Pages
September 12, 2006 TPTF Nodal Training Debrief
Communication Plan
For course updates and other nodal training information there are
several ways is which information will be communicated.• Nodal training website• Nodal project news letter• Word of mouth• E-mail exploder lists – actual lists to be determined• During course delivery• TPTF presentations
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTCourse Development Process
Market Education
September 12, 2006 TPTF Nodal Training Debrief
8 Hour Course Development Cycle – One Day Course
4 Days
12 Days
12 Days
24 Days
5 Days
12 Days
12 Days
54 Days
TPTF subgroup review of
abstract and outline
Publish Course
TPTF subgroup review of
preliminary module
BetaTPTF workshop
Interactive Visual
Training Map
Schedule Course
Design Course
Develop Preliminary
ModuleDevelop Course
Structure F.A.Q.
Document
Develop Quick
Guides
Compose WebEx
Materials
Migrate Materials to Web-Based Training
Deliver Courses
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTCurrent Nodal Training Budget and Plan Assumptions
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Nodal Training Planning and Budgeting Assumptions
• The training plan does not include the current ERCOT payments for WebEx sessions. ERCOT
departments are allowed to use WebEx sessions without specifying the actual charge in
budgets. WebEx sessions will not exceed 125 students per class session.
• The training plan assumes the use of the current LMS with the purchase of Lectora to provide a
testing platform.
• Any required self-study presenters are provided from resources already allocated to the
project.
• For budgeting purposes we have used the lowest estimated cost ($6 per booklet) for
production of the course booklets. This is not the current preferred ERCOT vendor for printing -
Document Engine – which has estimated three times this much. Printing is black & white only.
• Based on the Curriculum seven courses need to be transcribed for narration for web-based.
• The number of students trained per active course per month by face to face is estimated at 50.
• There are no charges included for ERCOT provided facility, software & supplies or for
internally printed material.
September 12, 2006 TPTF Nodal Training Debrief
Nodal Training Planning and Budgeting Assumptions
• The level of effort is based on market-focused courses identified by the Market
Participants in the “Curriculum" document, and those identified by the IRT group
as required for ERCOT Readiness. Any additional training at ERCOT would be
the responsibility of the particular department, though it is suggested that the
standard formats and process being used by the Nodal Training Project may be
of value. The market-focused course schedule and scope is to support the
requirements dictated by the TPTF as documented in the Curriculum documents.
Scaling of development effort is based on the course creation section of the
process.
September 12, 2006 TPTF Nodal Training Debrief
Nodal Training Planning and Budgeting Assumptions
• PJM training is not being purchased.
• Contractor travel expenses are included in vendor rates.
• Other than LMP 201, all courses are presented by ERCOT staff or Training contractors.
• The LMS contract is good for two years there is no guarantee of the same price from the
vendor – OnLine Training – for the 3rd year. The cost of software licenses includes est. 10%
sales tax.
• All scenario based training is one day.
• Nodal Program Office will provide a mechanism to monitor budget & time.
• Training external to Texas can be provided at time and material reimbursement.
• The cost of course delivery through 2009 is included in the Nodal Training budget with the
assumption of using internal ERCOT resources. No assumption is made as to the provision of
these resources. Approximately 14,000 hours have been budgeted using these internal
resources at $65 hour. Should these resources not be available cost of contractors for training
delivery could be as high as $165 an hour (including expenses). The current assumption is that
each course, once available, will be presented once a month through market opening.
September 12, 2006 TPTF Nodal Training Debrief
Nodal Training Planning and Budgeting Assumptions
• The Annual ERCOT Operations Training Seminar will include at least 2 Hours of nodal
material in the 2007 Seminar. The Seminar Working Group is expected to include more in
the Seminar to be held in the fall of 2008; how much is yet to be determined. Since the
2009 Seminar is to be held in the fall of 2009, post Nodal implementation, operational
implementation issues will be considered by the Seminar Working Group. Nodal Training
will provide support and material to the Seminar as required. The current Early Delivery
System (EDS) development timelines must consider all available options to prepare target
populations for Nodal implementation.
• The Extended Training – System Dynamics course is budgeted for development but not
delivery as delivery (according to the Curriculum) occurs after 1/1/09.
• The Nodal Training Budget does not include any activity or expenses after 1/1/09.
September 12, 2006 TPTF Nodal Training Debrief
Training Travel Discussion
• Training external to Texas can be provided at time and material reimbursement.
• Training has currently budgeted for in-Texas training at four separate locations (North, South, East and West) at an ERCOT approved facility.– Market Participant support & travel is not included.
– Budget assumes course travel for three people per month in Texas, with two nights out (three days) at one of the four locations.
– Out-of-Austin facilities are assumed free and include projection and sound capability supporting an audience from 25-50 people.
• Laptop is purchased for training use in out-of-Austin facilities, includes tax, support, and warranty.
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTSuggestions for Reorganization of Nodal Training Curriculum for Budget Reduction
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Nodal Training Budgeting
Background• Can the scope be reduced
• Can we simplify the process
• Can the scale be reduced
• Can we reorganize the schedule
• Must maintain the quality and content
Perspective• Nodal 101 Training in production
• Development of five day Basic Training Course outline/abstract for QSEs
• Familiarity with other components of the Nodal Project
September 12, 2006 TPTF Nodal Training Debrief
Courses with no suggestions for curriculum changes
• NOIE QSE Operations
• Basic Training Program
• Extended Training System Operations
• ERCOT LMP 201
• Market Settlements 301
• CRRs, PCRRs etc
• Support for Annual System Operations Seminar
September 12, 2006 TPTF Nodal Training Debrief
Reduction of Face to Face Course Delivery
Rationale: The provision of Web-Based Training with electronic testing capability could provide the necessary coverage. Nodal Training will host a once-a-month question and answer conference-call for questions. In addition several of the course durations could be reduced.
Courses Impacted Savings
ERCOT Nodal 101 After 2006 $ 75,000
Transition to Nodal Markets $250,000• Reduce to 4 hours (from 16 hours) as content is largely project information that might
be provided in updates to TPTF and circulated on a regular basis. Course content still includes a description of the plans, major components and anticipated interaction points of the Market.
Transmission 101 $300,000• Reduce to 10 hours (from 20 hours) as content is very specific to TSPs and DSPs
and they are already required to attend the Basic Training QSE course per the Readiness discussions.
September 12, 2006 TPTF Nodal Training Debrief
Consolidation of Generation Courses
Rationale: There are currently four courses that are generation focused for a total duration of 48 hours of classroom time. Based on the fact that this material will build on the Basic Training QSE course generation specific material could be provided over 16 hours of training (vastly reducing development and delivery time) with one possible format as follows:Day 1, Morning Generation 101
Day 1, Afternoon Generation 101, test 101
Day 1, Afternoon Generation 201
Day 2, Morning Generation 201, test 201
Day 2, Afternoon Generation 301, test 301
Day 2, Afternoon Wind Generation, test wind generation
Courses Impacted Savings
Generation 101,201,301 $910,000
Wind Generation 101 $290,000
September 12, 2006 TPTF Nodal Training Debrief
Reduction of Course Duration
Rationale: Based on the current anticipated depth of material being created for the
5 Day Basic Training Program, the following courses could have their duration
reduced.
Courses Impacted Savings
Load Service Entity 201 $142,000
(Reduce from 20 to 16 hours)
Network Model Management $ 76,000
(Reduce from 16 to 8 hours)
September 12, 2006 TPTF Nodal Training Debrief
Removal of courses from Nodal Training Plan and Budget
Rationale: This course can be scheduled for production and delivery after the
1/1/2009 date used for the Texas Nodal Training budget and plan.
Course Impacted Savings
Scenario-Based Training $737,000
Rationale: This course will be provided by the ERCOT Software Development
Team in the form of presentations.
Course Impacted Savings
MIS 101 $292,000
September 12, 2006 TPTF Nodal Training Debrief
Additional Potential Savings
Item Impacted Savings
Remove WebEx $ 78,000
Remove Off-site Texas Training $ 90,000
Remove support for vendor supplied training $100,000
Drop Interactive Visual Training (Quality Impact) $100,000
Drop Process Maps (Quality Impact) $429,000
Drop Quick Guides (Quality Impact) $273,000
Drop FAQ (Quality Impact) $ 55,000
September 12, 2006 TPTF Nodal Training Debrief
Budget Saving Summary
Items Savings
Curriculum Restructuring $3,072,000
No off-site Texas training $ 90,000
Drop WebEx $ 78,000
Drop Vendor Training Support $ 100,000
Reduce Training Quality $ 857,000
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTLMS Update
Market Education
September 12, 2006 TPTF Nodal Training Debrief
• Tracking and reporting on Nodal Market Readiness
• Automation of as many processes as possible
• Support for distance learning
• MPs need to be able to manage their own students
• Mapping Market Protocols to learning objectives
• Support for NERC Certification and CEH
• Flexible and secure system
Business Drivers
September 12, 2006 TPTF Nodal Training Debrief
Technology
Functional Requirement Categories
• User Accounts
• Publishing & Scheduling
• Student Enrollment
• Attendance & Tracking
• Reporting
• Certification
• Protocol Mapping
Prospective software
• WBT Manager (LMS), hosted by external vendor
• Lectora courseware and exam creation tools, hosted by external vendor
• Requisite Pro for protocol mapping
September 12, 2006 TPTF Nodal Training Debrief
LMS Readiness Schedule
9/15 – Complete Requirements / UI Design
9/22 – Licensing & Software Procurement (dependency)
10/20 – Requirements, UI, & Template Design Approval (dependency)
10/20 – LMS Configuration Completed
11/10 – UI & Templates Completed
11/22 – System Testing & Data Migration Completed
12/22 – Flight Testing Completed
12/26 – Go Live
September 12, 2006 TPTF Nodal Training Debrief
Proposed Features
Reporting:
• Reporting access provided at the overall system and business domain (MP) levels.
• Report generation on student performance:
– By student
– By Market Participant and Market Participant Division
– By Market Segment (QSE, LSE, etc.)
• For the market at large with a wide range of additional reports
Publishing & Scheduling:
• Organization of content by course and module
• Class schedule, instructor, and facility management tools
• Support for launching self-directed, electronic deliverables (courseware, exams, and
other course aids)
• Publicly accessible via the Internet
September 12, 2006 TPTF Nodal Training Debrief
Proposed Features
User Account:
• MP-centric student hierarchy
• Local MP administrator support at both the company and division level
• Mandatory student account creation
• Self-service, managed, and bulk creation of accounts
• Self-service and managed account maintenance
• Self-service support for transition between Market Participants
Certification:
• Tracking of certification programs to facilitate NERC requirements
• Support for organizing curricula to meet certification program needs
• Application of training time towards student Continuing Educational Hours (CEH)
September 12, 2006 TPTF Nodal Training Debrief
Proposed Features
Student Enrollment:
• Access to all course curricula via a global course catalog
• Self-service and managed student class enrollment
• Alerts to facilitate communication between Training and students
Attendance and Tracking Features:
• Manual attendance management for class sessions
• Automatic attendance management for self-service, distance learning
• Tracking of all AICC- or SCORM-compliant electronic courseware
• Exam data gathering, by question and learning objective
• Optional support for pre-requisite constraints on certain curricula
• Optional support for “testing out” of certain curricula
September 12, 2006 TPTF Nodal Training Debrief
Proposed Features
Protocol Mapping:• Mapping of Market Protocols and derived Nodal system application features to
applicable learning objectives
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTNodal 101 Update
Market Education
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Evaluation Results
Four MP classes held (150 attendees, 90 surveys completed – 60%)
• July 26 – 37 attendees, 20 surveys completed
• July 27 – 33 attendees, 21 surveys completed
• Aug 8 – 35 attendees, 26 surveys completed
• Aug 23 – 45 attendees, 23 surveys completed
Survey asked attendees:
• Name (optional)
• Participant Type– QSE, LSE/REP, TDSP, Generation, PUCT, Other
• Role– Accounting/Settlements, Power Operations, Engineering, Management, Consultant,
Other
• Nodal Market Knowledge– Beginner, Intermediate, Advanced
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Surveys by Type
0% 5% 10% 15% 20% 25% 30% 35% 40% 45%
QSE
LSE/REP
TDSP
GEN
Other
26-Jul 27-Jul 8-Aug 23-Aug
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Surveys by Role
0% 5% 10% 15% 20% 25% 30% 35%
Acct/Settlements
PowerOp
Engineer
Management
Consultant
Other
26-Jul 27-Jul 8-Aug 23-Aug
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Prior Nodal Knowledge
0% 10% 20% 30% 40% 50% 60% 70%
Beginner
Intermediate
Advanced
26-Jul 27-Jul 8-Aug 23-Aug
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Topic Importance
Topics
• Market Overview• LMP• Adjustment Period and Real-
Time Operations• Day-Ahead Operations• Congestion Revenue Rights• Settlements
Participants asked to rate each topic using the following scale:
• No Opinion (0 – Not Counted)• Very Unimportant (1)• Unimportant (2)• Important (3)• Very Important (4)
All topics received ratings between 3.02 and 3.44
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Content/Presentation Ratings
Adapted to reflect generic NERC survey
• Met learning objectives• Prerequisites were appropriate• Materials were accurate and
relevant• Instructional method was
appropriate• Time allotted was appropriate• Instructor(s) were effective• Facilities and/or tech equipment
were appropriate• Materials issued before/during
training were appropriate• A/V used were effective• Recommend course to others
Participants asked to rate each item using the following scale:
• No Opinion (0 – Not Counted)• Strongly Disagree (1)• Disagree (2)• Agree (3)• Strongly Agree (4)
All categories received ratings between 3.16 and 3.48 except
Time Allotted - 2.86 (Large amount of new material)
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Test Procedures
• Attendees were told that they need to take the test, this is now documented on the web site and in the course materials.
– 150 attendees– 87 took test (58% of those who attended)– 69 passed (79% of those who took the test)
• ERCOT Attendees– 26 attendees– 10 (38%) took test and all passed
• Test was open book/notes
• Multiple choice questions– Some questions removed as a result of 7/26 and 7/27 classes
• Passing score = 70%
• “Test out” option to be in place Q4 2006 when LMS is operational
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Intro Slide on Testing
• Market Participant – An Entity that engages in any activity that is in whole or in part the subject of the Nodal Protocols, regardless of whether that Entity has signed an Agreement with ERCOT.
• Market Participants are required as part of the Nodal Transition Plan to demonstrate Market Readiness. – Training is considered one component of Market Readiness.
– As such each Market Participant, as defined above, will be expected to take the test for a given course.
– ERCOT will maintain such information and report to the Market as required on the status of Training Readiness.
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – Test Performance, all Attendees
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
Passed
Failed
26-Jul 27-Jul 8-Aug 23-Aug
September 12, 2006 TPTF Nodal Training Debrief
ERCOT Nodal 101: The Basics – 2006 Face to Face Schedule
• September 21, 2006 in Austin• October 11, 2006 in Taylor• October 25, 2006 in Austin• November 7, 2006 in Austin• November 29, 2006 in Taylor
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTLMP 201 Update
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Summary of comments
• Very strong content that was broader than LMP, include a lot of basic supply and demand theory.
• Had some material that was commentary on other markets that could be removed.
• Material delivered as if in a university – Professor Baldick presents the information without facilitating the learning of the information.
• Professor Baldick is highly knowledgeable about the subject matter.• Professor Baldick has certain opinions that are not necessarily those of
ERCOT and is not afraid to voice them.• Audience did not perceive this as a 200 level course.• Material was in Professor Baldick’s own format.• Recommendation from an audience member was that the course
should be mandatory.
September 12, 2006 TPTF Nodal Training Debrief
Decisions required for LMP 201
• Should this course be included in the “Nodal Training” Curriculum in standard format with or without test as a replacement for LMP 101?– Professor Baldick owns the material completely.
• Should this course be mandatory and a prerequisite to Nodal Basics 101?
• Should this course be called “The Economics of LMP”?
Market Education
Nodal Education:(Course Title)
(Presenter Name)(Presenter Title)ERCOT
July 17, 2006
Role of Account Management at ERCOTWork in Progress
Market Education
September 12, 2006 TPTF Nodal Training Debrief
Accomplishments and On-going Work
Recent Accomplishments• Finalization of ERCOT Nodal 101 Development including quick guides• Transition of delivery of Nodal 101 to Wholesale Client Services• Completion of initial budget and plans• Beta Run of LMP 201 • Training development standards• Completion of Protocol Mapping
On-going Work• Finalization of LMP 201 • Development of 5-Day Basics Training Program
– Release of abstract and outline to TPTF Sub-Group 9/15/2006
• Development of Interactive Visual Process Map has commenced• Completion of LMS requirements validation• Development of Transition to Nodal Testing
– Release of abstract and outline to TPTF Sub-Group 10/14/2006