Upload
ambrose-robinson
View
217
Download
3
Embed Size (px)
Citation preview
February, 2012
ERCOT Public
ERCOT CRR Update
Matt MerenessERCOT Manager Day-Ahead Market and CRR Auction
2
Agenda
Recap of Annual CRR Auction and Lessons Learned
CRR Next Steps in 2012ERCOT Tactical / Short-termERCOT/Market Strategic Discussions (and consider priority)
Appendix of detailed PCRR/CRR examples
Deferred- 2012 CRR Market Notice discussion
February, 2012 ERCOT Public
3
Recap of Annual CRR Auction for 2012/2013
February, 2012 ERCOT Public
4
Recap of Annual CRR Auction for 2012/2013
Execution times of Annual CRR Auction
2012 Annual Auction (55% of system capacity)• 60 hours for final run of Peak WD
• 14 hours for final run of Peak WE
• 7.5 hours for final run of Peak Off-Peak
2013 Annual Auction (15% of system capacity)• 194 hours for final run of Peak WD*
• 50 hours for final run of Peak WE
• 36 hours for final run of Peak Off-Peak
Issue/Risk– Execution time took 8-days for one component of auction
February, 2012 ERCOT Public
5
Recap of Annual CRR Auction for 2012/2013
NOMCR and Outage Metrics
Posted 72 models for auction (3TOU x 12 months x 2 years)
2012 Annual Auction (55% of system capacity)• Snapshot taken 8/17/2011• NOMCRs:
• 526 NOMCRs part of model build• 490 Approved status (for Testing or Production) • 36 Other status (Received, Resubmitted, Submitted, Add’l data required)
• Outages- 18 Outages part of model build• Used 8 in model build
2013 Annual Auction (15% of system capacity)• Snapshot taken 6/28/2011• NOMCRs:
• 725 NOMCRs part of model build• 674 Approved status (for Testing or Production) • 51 Other status (Received, Resubmitted, Submitted, Add’l data required)
• Outages- 8 Outages part of model build• Used 1 in model build
Question, how were long-term planned changes in model build, such as CREZ lines in annual model?
February, 2012 ERCOT Public
6
Annual CRR Auction for 2012/2013
Lessons Learned :– Both years of Auction published on time (completed execution between Oct31- Nov16)– Lessons learned:
• Credit- Significant market credit hold of $1.6 billion for 3 weeks, so team looking for feedback to propose changes to timing and sequence to alleviate coinciding credit collateral posting (next bullet).
• Sequence/timing- Considering with market changes to execute 2-year auction in separate bid and credit windows for each year to relieve market credit and improve analysis of results.
• Technical- 2013 PeakWeekDay auction executed for 194 hours, so evaluating performance improvement options for next year’s auction (software, servers, configuration).
• Bid Limit of 200,000- Market was oversubscribed for 2012 so looking at options whether to consider no changes, or to consider alternative minimum bids prices, reduce maximum bids per CRRAH in first round, or curtailment of least value bids prior to running auctions.
February, 2012 ERCOT Public
7
Agenda
Recap of Annual CRR Auction and Lessons Learned
CRR Next Steps in 2012ERCOT Tactical / Short-termERCOT/Market Strategic Discussions (and consider priority)
Appendix of Examples
February, 2012 ERCOT Public
8
CRR Next Steps in 2012
ERCOT Tactical / Short-term– Implementation of NPRR395 (credit posting), NPRR357/430 (credit screening)– Market requests such as CRR Model Build paper, PCRR and CRR Offers in Auction– Consider CRR Calendar and Protocol changes to separate 2-year Annual Auction– Improve system performance of 2013 PeakWeekDay Auction
ERCOT/Market Strategic Discussions (and consider priority)– Options around 200,000 Bid Limit – CRR Payment Schedule options– Rolling Auction options and approaches
February, 2012 ERCOT Public
9
Agenda
Recap of Annual CRR Auction and Lessons Learned
CRR Next Steps in 2012ERCOT Tactical / Short-term Model Build Process (slides + whitepaper) PCRR and CRR Offers in Auction (slides + Appendix) Separate 2-year Annual Auction Improve system performance for Annual Auction
ERCOT/Market Strategic Discussions (and consider priority) Next Steps for 2012 Market Notices
February, 2012 ERCOT Public
10
CRR Model Build Process
CRR Team will support the CRR Model Build Process as an “Other Binding Document”
Current draft for market consideration posted with this presentation
Summary of processCIM snapshot from current production model
Apply NOMCRs to create model for Outage Evaluation
Perform Study to determine most constraining day of month (outages)
That day of month becomes model build date to build:
Using current CIM model
Applying all approved NOMCRs leading up to that date (future model)
Applying Outages
Topology Processor creates model file to pre-process for CRR
CRR Engineer applies all other supporting data- Forecasted Temps, LDF, etc
Model uploaded into CRR system and posted to market
Multi-month models are same as monthly methods repeated into future months
February, 2012 ERCOT Public
11 ERCOT PublicFebruary, 2012
2013 Annual Auction (15% of system capacity)• Operations Model = 6/28/2011 (18 months before Jan 1, 2013)• NOMCRs = 725 in-flight (most future NOMCR = 6/1/2012)• Outages = 8 Outages in model build study, used 1 in model build across months
2012 Annual Auction (55% of system capacity)• Operations Model = 8/17/2011 (4 months before Jan 1, 2012)• NOMCRs = 526 in-flight (most future NOMCR = 7/11/2012) • Outages = 18 Outages in model build study, used 8 in model build
Question- Were long-term planned changes in model build, such as CREZ lines?
Answer is “No”, but there was at least one CREZ line with a NOMCR that was accepted (Scurry South – Dermott 345 kv double circuit).
ERCOT has studied amount of change in accuracy of dates of future improvements and excluded them from consideration in 1-2 years in future (see next slide for example)
CRR Model Build for Annual Auctions
12 ERCOT PublicFebruary, 2012
CRR Model Build- Sample of Changes in Energization Dates
13
PCRR and CRR Offer Explanation
Reminder that Network Model is scaled for auction at:
Year 2 – Scaled to 15% of ratings/capacity
Year 1 – Scaled to 55% of ratings/capacity
Monthly – Scaled to 90% of ratings/capacity
For any PCRRs or previously awarded CRRs:
For Year2 and Year1 the ownership is scaled-down to represent the “base CRR” capacity on the scaled-down model that affects how much more capacity can be sold. No scaling down in monthly auction.
For Allocated PCRRs, the CRRAH has the option to:
- Hold the PCRRs and pay for their value in the CRR Auction (at discount)
or
- Offer their PCRRs into the market
These offers can be up to 100% of their MW value, even if it exceeds the scaled-down model, and potentially be fully cleared and transferred to another CRRAH (since this is a transfer of ownership, not incremental capacity on the network model).
February, 2012 ERCOT Public
14
PCRR and CRR Offer Explanation
Detailed examples in the appendix, but a high level annual auction example:
100MW line with 80MW PCRR ownership for Year1- 55% Auction
Offer from CRRAH NOIE to sell 80MW PCRR
Bid from CRRAHX at high price to buy 100MW
February, 2012 ERCOT Public
Bus A Bus B
55MW capacity = 100 MW rating (100x55%) less 44MW CRR baseload (80x55%)11 MW for sale from ERCOT
100 MW bid 100MW line
80 MW offer
Assuming high bid price from CRRAHX:CRRAHX = Clears the 80MW (offer) + 11MW (system) = 91MWCRRAHNOIE = Sells all 80MW, 0 Remaining
Note in monthly auction, the 91MW ownership is scaled down to 90% to become CRR baseload, just as PCRR was.
15
Separate 2-year Annual Auction
Annual Auction processes and systems are already separated in terms of:
Credit lock, Modeling, Bid window, Auction solutions
ERCOT proposal to consider separating credit/bid/auction windows for each year to relieve market credit and improve analysis of results.
February, 2012 ERCOT Public
Year 1
Year 2Oct/Nov
All credit/bids/auctions in flight simultaneously
Year 1
Year 2
Oct/Nov
Year 2 credit/ bids/auctions
Nov/Dec
Year 1 credit/ bids/auctions
Current
Proposed
16
Improve System Performance
2013 Annual Auction (15% of system capacity)• 194 hours for final run of Peak WD
Risk– Execution time took 8-days for one Time-of-Use auction segment, and thus time for a re-execution due to credit or solution issue is limited.
Mitigation plan- ERCOT in process of re-executing 194 hr run on upgraded platform to benchmark Linux technology and newer Nexant code. Testing progress.
February, 2012 ERCOT Public
17
Agenda
Recap of Annual CRR Auction and Lessons Learned
CRR Next Steps in 2012ERCOT Tactical / Short-termERCOT/Market Strategic Discussions (and consider priority)– Options around 200,000 Bid Limit – CRR Payment Schedule options– Rolling Auction options and approaches
Appendix of Examples
February, 2012 ERCOT Public
18
Options around 200,000 Bid Limit
Bid trending of all auctions since go live
Exceeded 200,000 bid limit two times resulting in Round 2
February, 2012 ERCOT Public
19 ERCOT PublicFebruary, 2012
Options for consideration
Auction for the auction- ERCOT to conduct an auction/allocation for the bid capacity
Questions to consider regarding timing, involvement of money
Complexity of more people, processes, timing
Additional chance for “self-reduction of bids”
If 200k exceeded, introduce an additional day for self-reduction by CRRAHs of known over-subscribed amount before invoking the low bid limit quantity
Increase minimum Option bid price
Reserve bid capacity for higher value bids, but no guarantee of <200k limit
Remove credit constraint in CRR Clearing engine
Allows P-Q Curves (example up to 10 segments)
Curve counts as single bid, estimate would consolidate 30-50% of bids
Forced ranking of 200,000 bids
Take all option bids, rank by price, and curtail down to 200,000 limit
ERCOT and Vendor will continue to test 200,000 threshold
Options around 200,000 Bid Limit
20 ERCOT PublicFebruary, 2012
Options for consideration
Part of NPRR357 was concept of paying for CRRs only in the prompt month
Revisiting of collateral requirements of CRR ownership
No comments from CRR team on payment schedule or collateral
Could be considered in context of current annual auction
Could be considered with rolling auction
In response to some questions about credit default processes during auction, Protocols 7.5.5.3 (1)(b) ERCOT may review preliminary CRR Auction results to ensure that post auction collateral
requirements are satisfied for all CRR Account Holders participating in the CRR Auction. If it is practicable to rerun the applicable CRR Auction, and the post CRR Auction collateral requirements for a Counter-Party are not satisfied, ERCOT:(i) Shall promptly notify the Counter-Party of the amount by which its Financial Security must be increased and allow it until 1500 on the next Bank Business Day from the date on which ERCOT delivered Notification to increase the Financial Security. (ii) If sufficient Financial Security is not received by 1500 on the next Bank Business Day, ERCOT shall void all of the Counter-Party’s bids and offers in the CRR Auction and rerun the CRR Auction without that Counter-Party’s activity.
CRR Payment Schedule
21 ERCOT PublicFebruary, 2012
Open discussion to gather options and priorities for market rolling auction
Tenor/horizon of auctions (shorter/longer)
Percentage of capacity auctioned each annual, month, or other period
Potentially minimize model builds with transition from monthly to seasonal periods
Example, utilize seasons for Annual and Quarterly
Monthly would only be offered at granularity in prompt month
Is there a target to sell every period in year at monthly frequency, or quarterly?
CRR Rolling Auction Concepts
Execute monthly for each month (once)?Execute 3 future quarters/seasons, on quarterly basis?Release up to X% per season?
22 ERCOT PublicFebruary, 2012
Questions?
Any comments on tactical or strategic issues and priorities?
23 ERCOT PublicFebruary, 2012
APPENDIX of EXAMPLES
Treatment of Baseload in the CRR Allocations & Auctions
24
CRR Allocation/Auction Process
Annual PCRR Allocation Annual PCRR Allocation (For Year 2012 and (For Year 2012 and
2013)2013)
Monthly True-up Monthly True-up Allocation (In Year 2012)Allocation (In Year 2012)
Annual Auction Annual Auction (For Year 2012 and (For Year 2012 and
2013)2013)
Monthly Auction Monthly Auction (In Year 2012)(In Year 2012)
Annual PCRR Allocation Annual PCRR Allocation (For Year (For Year 20142014))
Annual Auction Annual Auction (For Year 2013 and (For Year 2013 and
2014)2014)
Monthly True-up Monthly True-up Allocation (In Year 2013)Allocation (In Year 2013)
Monthly Auction Monthly Auction (In Year 2013)(In Year 2013)
February, 2012 ERCOT Public
25
Constraint Factor & Baseloading Factor
Annual/MonthlyAnnual/Monthly Allocation/AuctionAllocation/Auction Constraint Constraint FactorFactor
Baseloading Baseloading FactorFactor
AnnualAnnual
Allocation
Year 1
100% 100%
Year 2
100% 100%
Auction
Year 1
55% 55%
Year 2
15% 15%
MonthlyMonthlyAllocation 100% 100%
Auction 90% 100%
February, 2012 ERCOT Public
26
PCRR Treatment in Annual Auction for Year 2012
In the Annual PCRR Allocation for year 2012, Market Participant MP1 requested 20 MW obligation with the path A->B, PeakWeekDay, for January 2012 and was fully allocated.
In the Annual Auction, MP1 is holding 20 MW obligation and offering 5 MW for sale @$0.1/MWh
Market Participant MP2 is bidding 90 MW obligation to buy with the path A->B @$0.25/MWh.
The base load held by MP1 is scaled to 55%*20=11 MW, and the transmission capacity of A->B is scaled down to 55%*100=55 MW.
Bus A Bus B
100 MW rating
20 MW
February, 2012 ERCOT Public
27
PCRR Treatment in Annual Auction for Year 2012 (continued)
Bus A Bus B
55 MW rating
11 MW
The auction is to sell the 55% of remaining transmission capacity, which is 55%*(100-20) = 44 MW.
After the auction is run, 5 MW is sold by MP1 49 MW is awarded to MP2
The final CRR ownership: CRR1: 15 MW owned by MP1 CRR2: 49 MW owned by MP2
February, 2012 ERCOT Public
28
PCRR Treatment in Annual Auction for Year 2012 (continued)
Bus A Bus B
55 MW rating
11 MW
The power flow on line A->B is ScaledPCRRMW+ AwardedBidMW- SoldOfferMW=55%*20 + 49 – 5 = 55 MW. Therefore A->B is binding. Clearing price of path A->B is $0.25/MWh
February, 2012 ERCOT Public
29
Monthly (True-up) Allocation in Year 2012
Bus A Bus B
100 MW rating
15 MW
The base load is 15+49=64MW and the basdloading factor is 100% (no scaling).
The line rating is 100 MW and the constraint factor is 100% (no scaling).
The power flow on the line A->B is 64 MW.
49 MW
The baseloading factor is 100% (no scaling), and therefore the base load is 15+49=64MW.
The constraint factor is 100% (no scaling), and therefore the line rating is 100*100%=100 MW.
The initial power flow on the line A->B is 64 MW.
February, 2012 ERCOT Public
30
Monthly Auction in Year 2012
Bus A Bus B
90 MW rating
15 MW
The baseloading factor is 100% (no scaling), and therefore the base load is 15+49 = 64 MW.
The constraint factor is 90% , and therefore The line rating is 100*90% = 90 MW.
The power flow on the line A->B is 64 MW. The remaining transmission capacity is 90-64 = 26
MW.
49 MW
February, 2012 ERCOT Public
31
In the Annual PCRR Allocation for 2013 as the year 2, Market Participant MP1 is requesting 100 MW obligation with the path A->B, PeakWeekDay, in January 2013 and gets fully awarded.
Bus A Bus B
100 MW rating
100 MW
PCRR Treatment in Annual Auction for Year 2013 as Y2
February, 2012 ERCOT Public
32
In the Annual Auction, MP1 is holding 100 MW obligation and offering 80 MW for sale @$0.1/MWh
Market Participant MP2 is bidding 190 MW obligation to buy with the path A->B @$0.25/MWh.
The base load held by MP1 is scaled to 15%*100 = 15 MW, and the transmission capacity of A->B is scaled down to 15%*100 =15 MW.
PCRR Treatment in Annual Auction for Year 2013 as Y2 (continued)
February, 2012 ERCOT Public
33
Bus A Bus B
15 MW rating
15MW
The auction is to sell the 15% of remaining transmission capacity, which is 15%*(100-100) = 0 MW.
After the auction is run, 80 MW is sold by MP1 80 MW is awarded to MP2
The final CRR ownership: CRR1: 20 MW owned by MP1 CRR2: 80 MW owned by MP2
PCRR Treatment in Annual Auction for Year 2013 as Y2 (continued)
February, 2012 ERCOT Public
34
Bus A Bus B
15 MW rating
15 MW
The power flow on line A->B isScaledPCRR+AwardedBidMW-SoldOfferMW=15%*100 + 80 – 80 = 15 MW. Therefore A->B is binding. Clearing price of path A->B is $0.25/MWh
PCRR Treatment in Annual Auction for Year 2013 as Y2 (continued)
February, 2012 ERCOT Public
35
Bus A Bus B
55 MW rating
11 MW
The base load is 15+49=64MW and the basdloading factor is 100% (no scaling).
The line rating is 100 MW and the constraint factor is 100% (no scaling).
The power flow on the line A->B is 64 MW.
In September 2012, the Annual PCRR Allocation is to only allocate PCRR for year 2014, and there is NO annual PCRR allocation for year 2013.
In the Annual Auction for year 2013 as the year 1, the baseloading factor is 55% (scaling), and therefore the base load is 20*55%+80*55%=11+44=55 MW.
The constraint factor is 55%, and therefore the line rating is 55*100%=55 MW.
PCRR Treatment in Annual Auction for Year 2013 as Y2 (continued)
44 MW
February, 2012 ERCOT Public
36
The base load is 15+49=64MW and the basdloading factor is 100% (no scaling).
The line rating is 100 MW and the constraint factor is 100% (no scaling).
The power flow on the line A->B is 64 MW.
Suppose MP3 is willing to buy obligation bid 120 MW @ $0.8/MWh. Suppose MP1 and MP2 are offering 20 MW @0.1$/MWh and 80 MW@
0.25$/MWh for sale respectively. The final solution:
MP1 sold 20 MW MP2 sold 80 MW MP3 bought 100 MW
The final CRR ownership: CRR1: 20 - 20 = 0 MW CRR2: 80 - 80 = 0 MW CRR3: 100 MW
Bus A Bus B
55 MW rating
11 MW
44 MW
PCRR Treatment in Annual Auction for Year 2013 as Y2 (continued)
February, 2012 ERCOT Public
37
Bus A Bus B
90 MW rating
The baseloading factor is 100% (no scaling), and therefore the base load (from MP3) is 100 MW.
The constraint factor is 90% , and therefore the line rating is 100*90% = 90 MW.
The initial power flow on the line A->B is 100 MW, and the line’s rating will be extended to 100 MW in order to achieve the feasible solution.
100 MW
Monthly Auction in Year 2013
February, 2012 ERCOT Public