Upload
gabriel-henry
View
212
Download
0
Tags:
Embed Size (px)
Citation preview
Robert Hoffman/Polar Project ScientistBarbara Giles/Polar Deputy Project Scientist
Polar Project Status October,
2002
PWG Project Status / 23 October 2002 Pg 2
State of the Spacecraft
• The Polar spacecraft and instruments are healthy. Only the plasma wave instrument and the MICS sensor portion of CAMMICE have suffered major faults; PWI now operates only during eclipse.
• Polar has initiated semi-annual attitude maneuvers to extend orbit normal operations for auroral imaging and optimize fuel usage.
• At ecliptic normal, despun platform control and auroral viewing is limited to an ~4.5 hour segment of each 17 hour orbit.
CAMMICE, CEPPAD, EFI, HYDRA, MFE, PIXIE, PWI, SEPS,TIDE, TIMAS, UVI, VIS
March 18, 2002 – half flip to ecliptic normalFall 2002 – half flip to orbit normalSpring 2003 – full flip to orbit normal for southern winter auroral viewingFall 2003 – half flip to ecliptic normal (permanent)
PWG Project Status / 23 October 2002 Pg 3
Status of the Science
• Polar completed a prolonged observation campaign through the dayside equatorial magnetopause region with unprecedented high-temporal and spatial resolution. Now conducting a similar campaign across the nightside equatorial magnetosphere.
• Polar, IMAGE, Cluster, Wind and Geotail will hold a collaborative workshop on the dayside magnetopause and cusp at Yosemite in Feb. 2003.
• Polar’s auroral science progressed to studies of the conjugate aurora. Some initial findings:
– Onset brightening first seen in southern hemisphere with northern hemisphere onset detected ~1 min. later
– Expansive phase brighter in southern hemisphere but located ~45min earlier in local time in the north.
• A JGR special section on "Causes of the Aurora" will appear soon.
More than ten "great" conjugate events have been captured including this substorm onset on 1 Nov 2001
thermal plasma, accelerated by circularly polarized waves, is regularly seen in the dayside boundary layers
PWG Project Status / 23 October 2002 Pg 4
Mission Operation and Ground Data Processing: Then and
Now
~7.625$M
4.144$M
<4.172$M
Polar, Wind and Geotail mission operations and ground data processing combined
PWG Project Status / 23 October 2002 Pg 5
Status of the Mission Operation and Ground Data Processing Re-engineering
1. Unattended spacecraft contacts for data playbacks
2. Cross-training of flight operations personnel
3. Re-hosting the CMS for security and obsolescence issues
4. Re-hosting of NRT data service
5. Automation and re-hosting of KP processing
6. Simplifying online distribution of LZ and ancillary data
7. Automation of CD production
8. Re-hosting of the project web site
9. Streamlining NRT to include LZ processing and QL
FOT costReduction
CHDF and SPOF cost reduction
Future of Wind
9 re-engineering tasks were originally identified:
Completed, in “ring-out” phaseIn acceptance testingStartedIn planning phase, initial testing complete
PWG Project Status / 23 October 2002 Pg 6
Ground Data Processing:What was Lost? What was
Gained?
• ISTP services no longer provided: – systematic collection of data products from associated missions– KP CD distribution (impact is to Russian and South American data repositories)– dedicated program assistance center – off-hours data processing or problem response– automated data pushing to clients– quality control services of the ISTP/CDHF– problem response and quality control services of the ISTP/SPOF
• Services improved: – open ftp access to the full data set– HTR data produced in addition to KP, software easily updated – automated processing brings faster turn around of products
With respect to Polar, Wind and Geotail, all data services previously required from the ISTP/CDHF and ISTP/SPOF have been retained.
PWG Project Status / 23 October 2002 Pg 7
Who Gets the Credit: The Ground Data Processing Re-
engineering team
The success of the re-engineering effort is due to the cooperative efforts of several groups at GSFC who provided full- and part-time programming, system admin, design and management expertise.
632 Bobby Candey
696/583 David Berger
587 Ryan Boller
587 Marlo Maddox
587 Jim Byrnes
587 Chris Howard
423 Jeff Lubelczyk
632 Rick Burley
632 Tami Kovalick
632 Natalie Jaquith
690 Sandy Kramer
contr. Jim Legg
The core team:
With specific tasks & consulting by:
PWG Project Status / 23 October 2002 Pg 8
Long Term Funding Profile
• The PWG infrastructure held within CSOC has decreased dramatically over the past year. Some CSOC cost estimates for FY03 do not reflect this decrease.
• Conducting future mission operations under the current contracting mechanism does not appear to be economically feasible under the current long term funding profile.
PWG Project Status / 23 October 2002 Pg 9
Contracting for Future Mission Services
Option Roadblock Issues Status
Direct contract with Honeywell
Waiver of requirement for transfer to educational or research related location
1.Direct contract not permissible w/o extended competition cycle
2.ID/IQ, permission to add task to MIDEX ID/IQ or start new ID/IQ
Preferred method: currently pursuing ID/IQ and waiver.
Contract with educational or research location
May want waiver on 6-month “pull-out” requirement
Contractual and management layer between NASA and MO team
USRA and Capital College are willing
Remain with CSOC
1.$$$2.Uncertainty regarding post-
CSOC3.Operations reliability and safety4.Changes remain costly and slow
Negotiations continue with regard to cost and staffing levels
A six-month NOI to remove mission operations services from the CSOC contract was submitted. Arrangements for continued operations are being actively pursued.
PWG Project Status / 23 October 2002 Pg 10
Regarding Data Availability
• ISTP required special event archiving, rather than the full data set, as has become common with recent missions. Data accessibility was the responsibility of the project.
• Many Polar instrument teams have adjusted their data archiving and accessibility as is possible within their IT infrastructure and funding.
– Continuous HTR data from PWI, TIMAS, and TIDE. CAMMICE and CEPPAD soon.
– TIDE, PWI and MFE provide interactive data processing via the web.
• Additional progress can be made over the next year:
– HYDRA has HTR data software, needs to convert format to CDF.
– UVI, VIS and PIXIE could archive continuous HTR rather than events.
– MFE should update IT infrastructure and/or PWG project should produce MFE KP.
– PWG project should create and host software library for access to LZ
– PWG project could encourage and/or host additional interactive data processing.
• Progress depends on:– MO&DA contract mechanism that allows appropriate control over PWG re-engineering.
– Small augmentations to team funding for specific data processing/accessibility tasks.
PWG Project Status / 23 October 2002 Pg 11
Summary
• The Polar spacecraft and instruments are healthy.
• Science progress over the past two years has been particularly robust. Prospects for further breakthroughs with respect to substorm and reconnection physics appears very strong.
• Science funding has been relatively stable. FY02 funding was, on average, 90% of FY01 levels. Funding profiles for FY03 are budgeted at FY02 levels.
• The new mission operations and ground data processing systems are operating and serving the science community well. Several important re-engineering tasks remain to be completed by the end of December 02.
• Conducting future mission operations under the current contracting mechanism does not appear to be economically feasible under the current long term funding profile.
• A six-month notice, effective Sept. 30, for discontinuation of CSOC services was submitted.
• Arranging for an alternate contracting mechanism for mission operations remains difficult. Several avenues are being pursued.
• A plan to implement additional data accessibility improvements is under development.
Robert Hoffman/Polar Project ScientistBarbara Giles/Polar Deputy Project Scientist
Backup Slides
PWG Project Status / 23 October 2002 Pg 13
Summary: Then and Now
~7.625$M2.6$M
Polar, Wind and Geotail mission operations and ground data processing combined
PWG Project Status / 23 October 2002 Pg 14
Review of the ISTP Data System(an independent entity to serve the worldwide SEC
community)
In addition to • data processing and distribution services for GGS (Polar, Wind, Geotail) & IMP-8,• data distribution services for SOHO and Cluster,• operations and science coordination,
ISTP served as a one-stop data source by • consolidating and distributing data for 15 additional spacecraft, observatories and T&M programs• providing extensive data and media integrity and quality services.
ISTP Real-time System(IRTS)
Telemetry Processor(LZPR)
ISTP CDHF/IDDS
ISTPCentral Data
Handling Facility(CDHF)
Key ParameterIntegration and Testing
(KITT)
ISTP Data Distribution
System(IDDS)
US ClusterScience Data Center
(USCSDC)
NSSDCCDAWeb
DPS
Heritage IMP-8System
Wind
Polar
Geotail
SOHO
IMP-8
LZ
data
data
LZ &data
LZ &data
Ancillary Computationsof Ephemerides Real Time
Key Parameters &High Resolution Data
electronic transfers
CD-ROMS12k/yr
computed for Polar, Wind and Geotail
for health & safety
Wind/KONUSgamma ray burstearly warning
Wind real time KP
Science Planning and
Operations Facility (SPOF)
Instrument and science teams
ingestion of data for 12 collaborative programs
PWG Project Status / 23 October 2002 Pg 15
Initial Courses of Action
• The ISTP project office was disbanded and reduction of past ISTP activities occurred during October and November of 2001.
• ISTP ground system services immediately reduced were: – QuickLook data processing for special requests only, – key parameter CD distribution reduced from ~12,300 to 156 per year, – no key parameter re-processing, – no key parameter software updates, – no ground based or collaborative mission data processing or ingestion, – no dedicated program assistance center, – no system software updates excepting security patches, – no test or development environment, and – no off-hours data processing or problem response– services of the ISTP SPOF and Command Management System were
consolidated with the MOC and the project scientist's office.
Note: Items in blue have been restored within the new PWG data processing environment
PWG Project Status / 23 October 2002 Pg 16
Initial Courses of Action
• Contacted instrument teams regarding requirements for various operations and data services.
• Produced prioritized requirements document for Polar, Wind and Geotail. (available at http://tide.gsfc.nasa.gov/studies/POLAR/Polar_Ops_specs_25Jun02.pdf)
• Conducted six feasibility studies for alternative approaches 1) the present ground system management under CSOC (2 studies) 2) SPDF at GSFC under the direction of Bob McGuire 3) LASP at U Colorado under the direction of Bill Peterson4) UC Berkeley under the direction of Bob Lin 5) the NSSTC under the direction of Dennis Gallagher
PWG Project Status / 23 October 2002 Pg 17
Results of Feasibility Studies
The following conclusions and actions resulted from the review of the studies:
• More software and system re-engineering needed to be pursued than provided for by the CSOC/CDHF study and CSOC estimates for flight operations.
• Eight re-engineering projects were identified to reduce the number of FTEs by three-quarters.
• The re-engineering work should be performed under local control.
• The UC Berkeley capabilities for hosting mission operations remain of interest.
It was determined that a consolidation of all systems under the PWG Mission Operations Center (MOC) under an ID/IQ contract, as suggested by the SPDF study, offered the most cost effective solution with the least disruption to flight operations and the least risk to spacecraft health and safety.
PWG Project Status / 23 October 2002 Pg 18
Plan for Re-engineering
Project Office
PWG Data Processing
Real Time decommutationPlayback decommutation into Quick Look
Level Zero file generation
Key Parameter processing
Online Data distribution and archive Key Parameter (KP) ingestion
Level Zero CD production
KP CD production
Receipt of instrument commands
Web server maintenance
E/PO
Despun Platform Operations PlanningScience Planning
LZ quality control
KP quality control
Web page maintenance
Mission Operations Center (MOC)
Flight Operations Team (FOT)
Command Management System (CMS)
Flight Dynamics Facility (FDF)
Deep Space Network (DSN) Scheduling
Spacecraft & Instrument Engineering
IT security and network operations
Instrument Teams
NSSDC/Code 630
Level Zero deep archive
CDAWeb KP access and archive
Science, science, science
Science Management
Instrument commanding
Ancillary data processing
25 EP reduced to 13 EP
41 EP reduced to 3 EP
5 EP reduced to 1.5 EP
2 EP
PWG Project Status / 23 October 2002 Pg 19
Re-engineering tasks with greatest short term
payoff
1. Unattended spacecraft contacts for data playbacks
2. Cross-training of flight operations personnel
3. Re-hosting the CMS for security and obsolescence issues
4. Re-hosting of NRT data service
5. Automation and re-hosting of KP processing
6. Simplifying online distribution of LZ and ancillary data
7. Automation of CD production
8. Streamlining NRT to include LZ processing and QL
Reduction of FOT
Elimination of CHDF
For the future of Wind
PWG Project Status / 23 October 2002 Pg 20
Cross-training of FOT Personnel
6-7 console operators
2 CMS operators
2 spacecraft engineers
1 flight ops lead
1 DSN scheduler
4-5 console operators
GroundSystem
Engineer
Instrument Engineer
Flight opslead
DSN scheduler
Current After
1 instrument engineer
1 ground system engineer Spacecraft Engineers
still to be implemented
PWG Project Status / 23 October 2002 Pg 21
Re-hosting the CMS for Security and Obsolescence
Issues
Notes:• Core CMS software remains the same.
spof1.gsfc.nasa.govoutside firewall, receives/relays
commands & verifications
Current After
CMSinside firewall, verifies
command sequences, etc.,on older VMS machine
Decnet “push”,identified as security risk
spof7.gsfc.nasa.govoutside firewall, receives/relays
commands & verifications
CMSinside firewall, verifies
command sequences, etc.,re-hosted on new PC
TCP/IP FORMATSsecure relay across firewall
Bldg. 2 Bldg. 3
Bldg. 3Bldg. 3
PWG Project Status / 23 October 2002 Pg 22
Unattended Spacecraft Contacts for Data Playbacks
Notes:• Fewer attended contacts/fewer “double” attended contacts may mean less convenient or
delayed command scheduling.• Errors at DSN sites will mean result in several hours of data loss for Polar and several days of
data loss for Wind.
6-8 console operators,covering 24x7, typically 4 shifts of two operators,Wind: 1 contact/3 days,Polar: 4 contacts/day,All attended contacts
4 console operators,covering 16x5,
Wind: 1 contact/3 days,Polar: 3-4 contacts/day,
TBD number of unattended contacts
Current Proposed
still to be implemented
PWG Project Status / 23 October 2002 Pg 23
New Science Data System Overview
The following Polar, Wind and Geotail services provided by ISTP were retained:• Near Real Time (NRT) data, open line access• Quicklook (spacecraft playback) data, online access • Level Zero data processing, online and CD distribution• Geotail Sirius data processing, online access• Key Parameter data processing, online and limited CD distribution• Ancillary data processing, online access
ISTP Real-time System(IRTS)
Telemetry Processor(LZPR)
Polar/Wind/Geotail Data Processing
CDAWeb
Wind
Polar
Geotail
LZ
LZ
LZ &data
Instrument and science teamsLZ &
data
Ancillary Computationsof Emphemerides
Real Time datafor health & safety
Key Parameters &High Resolution Data
Project Scientist's OfficePolar platform operationsScience coordinationPWG web site
Quality control of data products
KP Ingested:CanopusSuperDARNSonderstromSESAMEGOES seriesLANL series
FASTSAMPEXACESOHOClusterIMAGEPolar HTR
electronic transfers
CD-ROMS4k/yr
PWG Project Status / 23 October 2002 Pg 24
Automation of KP Processing
Before Now
Notes :• Routine quality checking of KP file production will reside with instrument teams.• New high time resolution and Key Parameter software routines can be readily added by the
instrument teams to the software library.
TAE GUI interfaces on VAXto shift of operators
Custom software & Oracle on Dec Alpha control processing
Frozen software library
Extensive quality checking
Automated file processing
Consolidation to single machine with ready access to data
Software library converted tocollection of individual processes
Limited quality checking
PWG Project Status / 23 October 2002 Pg 25
Simplifying Online Data Distribution
Before Now
Notes:• Data access by open ftp• LZ data older than 2-3 months is gzip compressed• All data is public including NRT, QL, LZ, KP, ancillary
More Data:Magneto Optical Disks in cabinet
More Data:Magneto Optical Disks in jukebox
~2TB
Most Recent Data:magnetic disk
~.3TB
AMASS
workstation on open network - open ftp access
SCSI RAID w/ enough magnetic disk spacefor 3 months uncompressed LZ and ancillarydata plus older PWG LZ and ancillary data
in compressed format~2.5TB
Directory structure to mirror that ofISTP LZ CDroms
Polar-Wind-Geotail on-line data access
workstation on open network - controlled access
PWG Project Status / 23 October 2002 Pg 26
Automation of CD Production
Notes:• DVDs for Polar_all, Wind_all and Geotail_all distribution• Quality control of CD product to be performed by receiver; limited replacements possible
Before Now
several older control
machineswith Oracledatabase
several olderCD duplicators
several older CD writers
ISTP/IDDS
Custom and proprietary software for control , extensive cataloguing and quality control
New PCto control CDproduction equipment
New DVD/CD writer comboauto-loader for DVDauto-loader for CD
Automatic labeling of platter
Polar-Wind-Geotail DVD/CD Production
Simple scripting, less quality controlDVD for archiving, CDs to instrument teams
PWG Project Status / 23 October 2002 Pg 27
Streamlining NRT Processing to Include LZ and QL
Notes:• Software port process should be transparent to instrument teams.• File types and formats would remain identical..• Routine quality checking of LZ data files will reside with instrument teams.• Reprocessing/replacement of LZ data may be limited to 1-2 months after receipt of files.• There will be some data loss.
Wind/PolarNRT on older
microVaxs
Wind/Geotail QL & LZ
Bldg. 23
Bldg. 3
Before After
NRT for Wind & Polar rehosted to Dec Alpha
LZ for Wind & Polar rehosted to Dec Alpha
Wind/PolarNRT on older
microVaxs
Wind/PolarNRT on older
microVaxsWind/Polar NRT
(on older microVaxs)
Unix using LabView & OraclePolar QL & LZ
Bldg. 3Geotail QL & LZ
PWG Project Status / 23 October 2002 Pg 28
Schedule for Remaining Re-engineering Activities
Oct Nov Dec Jan Feb Mar Apr
2002
unattended spacecraft contacts for data playbacks
cross-training of flight operations personnel
transition to new CMS
CD system
streamlining NRT to include LZ and QL
burning in of new PWG data system
2003
PWG Project Status / 23 October 2002 Pg 29
Concerns on the Project Side
With Respect to Mission Operations:
• Can we find a contractual environment for operations that is affordable and legal?
• Can the re-engineered system collapse to an affordable Wind-only environment after Polar and Geotail end of missions.
• What is the minimum data recovery percentage acceptable in light of fiscal constraints imposed on extended mission programs.
PWG Project Status / 23 October 2002 Pg 30
Mass and energy coverage of the Polar particle
instrumentation packages
Polar remains the best instrumented spacecraft in the magnetosphere.
PWG Project Status / 23 October 2002 Pg 31
Exploring the Sun-Earth
SystemAn alliance of solar, heliospheric and geospace missions for the coordinated study of Sun-Earth system dynamics.
PWG Project Status / 23 October 2002 Pg 32
Alliance Objectives
The SEC Alliance of spacecraft will expand the scientific productivity of the individual missions by fostering joint scientific analyses of phenomena that originate at the sun, propagate through interplanetary space, and impact the Earth's magnetosphere and upper atmosphere.
Targeted objectives include:
• Understand the coronal causes of heliospheric disturbances
• Determine the evolution of disturbances within the heliosphere
• Understand the coupling of solar wind energy to geospace
• Understand the coupling of energy from the magnetosphere into the atmosphere
PWG Project Status / 23 October 2002 Pg 33
Alliance Activities
Sponsor analysis campaigns focused on specific science problems that bridge mission objectives. To date:• Energy transfer across the dayside magnetopause and through the cusp• Propagation of disturbances through interplanetary space
Sponsor opportunities for collaboration: • Yosemite 2002: Magnetospheric imaging workshop• Geospace Workshop - Feb 2002• Joint SOHO-ACE workshop - Mar 2002• Spring AGU 2002: special sessions sponsored by Alliance members• Tentative Fall 2002: Interplanetary disturbance propagation workshop• Yosemite 2003: The cusp and dayside magnetopause
Joint E/PO Activities• EOS Alliance article• Web home page• Aurora poster
• Flyers/pamphlets on popular SEC science topics• Updating/re-issuing popular ISTP products
PWG Project Status / 23 October 2002 Pg 34
PWG Project Status / 23 October 2002 Pg 35
PWG Project Status / 23 October 2002 Pg 36