Upload
kallie-goldsby
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
Risk Management Overview
Week 2
Review of Project Life Cycle PhasesPhase 1: Initiating Defines and authorizes the project or a
project phasePhase 2: Planning Defines and refines objectives, and plans
the course of action required to attain the objectives and scope that the project was undertaken to address
Phase 3: Executing Integrates people and other resources to carry out the project management plan for the project
Phase 4: Monitoring/Controlling Regularly measures progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives
Phase 5: Closing Formalizes acceptance of the product, service, or result and brings the project or a project phase to an orderly end
PMBOK® p. 41
Project Risk
• “A project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one of the project’s objectives”– Threat risk has a negative impact on the project’s
objective(s).– Opportunity risk has a positive impact on the
project’s objective(s) such as allowing the project to finish early, with less cost, and with more scope (functionality) than originally planned.
PMBOK® p. 238
Project Risk Management
• “Project risk management includes the processes concerned with conducting risk management planning, identification, analysis, responses, and monitoring and control on a project; most of these processes are updated throughout the project. ”
PMBOK® p. 237
Project Risk Management Objective
• “The objectives of Project Risk Management are to increase the probability and impact of positive events, and decrease the probability and impact of events adverse to the project.”
PMBOK® p. 237
Risk Management AreasRisk
Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
PMBOK® p. 239
Risk Management AreasRisk management planning Decide how to approach, plan, and execute the
risk management activities for the project. Standard templates, checklists, etc..
Risk identification Determine which risks might affect the project and document their characteristics. Identify at a high-level – about 80% are identified here.
Qualitative risk analysis Prioritize risks by evaluating and combining their probability and impacts. Subjective analysis.
Quantitative risk analysis Analyze numerically (expected monetary value) the effect of identified risks on overall project objectives. Objective analysis.
Risk response planning Develop courses of action to reduce threats and increase opportunities to project objectives. Note – this is not the same as risk mitigation.
Risk monitoring and control Track identified risks, monitor residual risks, identify new risks, execute risk response plans, and evaluate their effectiveness throughout the execution of the project.
PMBOK® p. 340
Knowledge Areas – Risk Centered
Risk
Integration
Communication
HumanResources
Procurement
Cost
Time
Quality
Scope
Adapted from Wideman, 1992
Project Life Cycle and Risk Management
Initiating PlanningExecuting/Controlling
Closing
Risk Management Planning
Risk Management PlanningRisk IdentificationQualitative Risk AnalysisQuantitative Risk AnalysisRisk Response Planning
Risk Monitor/ControlIterate risk identification, analysis and response planning
Risk lessons learned
When is risk management performed?
Stakeholders
• “individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion. They may also exert influence over the project’s objectives and outcomes”
PMBOK® p. 24
Risk StakeholdersProject manager The person responsible for managing the project.
Ultimately responsible for the risk management process. Participates in risk management activities throughout the project.
Project sponsor Person, or group, that provides financial resources for the project. Sets the risk threshold and tolerance for the project. Signs off on the risk management plan.
Project team members The group performing the work on the project. Participates in all risk management activities throughout the project.
Customers Person or organization that will use the project’s product.
Others People or groups not directly related to the project’s product, but can influence, positively or negatively, the course of the project.
PMBOK® p. 26
Risk Tolerance
• Propensity (individual or organization) to operate in an uncertain environment.
• Risk…– Seeker – embraces risk to realize gains– Tolerant – tolerates risk to ensure success– Averse – avoids risk to avoid failure
http://articles.techrepublic.com.com/5100-10878_11-6035405.html
http://articles.directorym.net/Know_Your_Risk_Tolerance_First-a881332.html
Risk tolerance may change throughout the project depending on problems, crises, regulatory changes, and changes in
stakeholders.
Which trait(s) describe your style? Taking risks makes good sense only in the absence of acceptable
alternatives. I generally prefer stimulation over security I have confidence in my ability to recover from my mistakes, no
matter how big. I believe opportunity generally knocks only once. It is better to ask for permission than to beg for forgiveness. Success in management is as much as a matter of luck as ability. I can handle big losses and disappointment with little difficulty Given a choice, I would choose a $3,000 annual raise over a $10,000
bonus that I have a one-in-three chance of winning. I am willing to try anything once. I seek adventure. I stick to the rules.
Risk Tolerance Game
Successful project management is spotting the projects that will succeed and shouting "mine" and for the rest ducking and shouting "yours".
http://www.project-training-uk.freeserve.co.uk/page2.htm
The Cost of Uncertainty
• Uncertainty decreases as the project progresses
• The cost (amount at stake) of making changes (to address risks) increases as the project progresses
• Addressing risks later in the project is more expensive than earlier action
• Goal is to reduce uncertainty early in the project by effective risk management
Risk Management Should be Adapted Based on
• Project size, importance, and complexity• Risk tolerance (organizational and
stakeholders)• Organizational policies and culture• External regulatory environment• There is no “one size fits all” in project risk
management
Risk Management Implementation
• Resistance to risk management– Some companies want to avoid talking about risks– Tendency to deal with risks when they occur– Fear that talking about a risk will make it happen
• Requires commitment, discipline and participation
• Many companies stop after identifying and qualifying risks instead of integrating all risk processes into the entire project life cycle.
Risk Management Excuses
A lack of planning by you does not constitute an emergency for me.
http://www.project-training-uk.freeserve.co.uk/page2.htm
Risk Management Planning
Planning without action is futile, action without planning is fatal.
http://www.project-training-uk.freeserve.co.uk/page1.htm
Risk Management ProcessesRisk
Management Planning
Risk Identification
Qualitative Risk Analysis
Quantitative Risk Analysis
Risk Response Planning
Risk Monitoring and Control
PMBOK® p. 239
“Risk Management Planning is the process of deciding how to approach and conduct the risk
management activities for a project”
The risk management plan is a subset of your overall project plan and should be completed early during project planning
PMBOK® p. 242
Risk Management Planning
Inputs• Organization assets
(policies, lessons learned, etc..)
• Stakeholder risk tolerance
• Project Charter• Project Scope• Risk Management Plan
template
Tools/Techniques• Risk Planning
Meetings
Outputs• Risk
Management Plan
• Updates to project management plan
PMBOK® p. 242
Risk Management Planning• Set overall goals and objectives
• Determine tolerance level
• Decide how much money, time, and other resources will need to be allocated for risk management activities
• Establish templates, checklists, and other tools to be used in risk management for your project
• Create probably and impact scales
• Establish importance of risk management
• Decide basis for evaluating project risk PMBOK® p.243 - 246
Risk Planning Inputs• Project Management Plan– Project Charter– Project Scope
• Stakeholder risk tolerance– Used as an input for defining impact scales– Determines formality of your risk plan and processes– Factored in to developing risk responses– May differ from project manager and/or team risk
tolerance• Risk management plan template
What do you do if..
• Your customer is not a risk taker, but you (the project manager) believes some risk will always be present and needs to be managed?
• You (the project manager) thinks the customer is wanting to take too many risks?
Risk Management Planning Outputs
• Risk management plan– Probably and impact scales
• Changes/updates to the project management plan
Define Probability and Impact• Define significant ranges for probability scores• Define impact definitions for each of the 4
competing demands– Scope, time, cost, quality
• Base these definitions on:– Historical data– Expert judgment– Risk tolerance – Organizational culture/policies
Probability Score ExampleProbably of Risk
Range of Probability Probability Score
81% - 99% 5
61% - 80% 4
41% - 60% 3
21% - 40% 2
1% - 20% 1
(red)
(red)
(yellow)
(green)
(green)
Scope Impact ExampleImpact of Risk on Scope Objective
Description of Potential Scope Impact ImpactScope reduction renders deliverable useless 5More than 20% of major functionality is affected 4Major areas of the scope are affected 3No more than 15% of the scope is affected (minor areas of functionality only)
2Minor functionality affected 1
(red)
(red)
(yellow)
(green)
(green)
Time Impact ExampleImpact of Risk on Time Objective
Description of Potential Time Impact Impact> 20% schedule delay 511 – 20% schedule delay 46 – 10% schedule delay 31 – 5% schedule delay 2Delays are insignificant (less than 1% schedule delay) 1
(red)
(red)
(yellow)
(green)
(green)
Cost Impact ExampleImpact of Risk on Cost Objective
Description of Potential Cost Impact Impact> 25% cost increase 516 – 25% cost increase 46 – 15% cost increase 31 – 5% cost increase 2Cost increase is insignificant (less than 1% increase) 1
(red)
(red)
(yellow)
(green)
(green)
Cost Impact ExampleImpact of Risk on Cost Objective
Description of Potential Cost Impact Impact> 25% cost increase 516 – 25% cost increase 46 – 15% cost increase 31 – 5% cost increase 2Cost increase is insignificant (less than 1% increase) 1
(red)
(red)
(yellow)
(green)
(green)
Quality Impact ExampleImpact of Risk on Quality Objective
Description of Potential Quality Impact ImpactProject deliverable is rendered unusable 5Quality reduction affects major functionality, less than 90% functionality meets quality standards
4Quality reduction affects major functionality – require customer approval
3Major functionality not affected, 90 – 96% functionality meets quality standards
2Major functionality is not affected, at least 97% functionality meets quality standards
1
(red)
(red)
(yellow)
(green)
(green)
Create Probability and Impact Scales
Some things that don't count are counted, many things that count
aren't counted.
http://www.project-training-uk.freeserve.co.uk/page1.htm
Tailor Risk Management to Your Project
• Do we need a risk management officer?• Do we advisors or risk experts from outside
the project?• Do we need a formal quantitative risk
assessment?• How often do we need formal risk meetings?• Risk management processes are determined
by the size, complexity, and organizational impact of the project.
The Risk Management Plan (RMP)
• The RMP does not address individual risks• The RMP does address the processes for how
risks will be identified, analyzed, responded to, and monitored throughout the project life cycle.
• Include risk management activities in the project WBS, schedule, and budget.
• Establish risk objectives for the team.• Risk communication plan.• How frequently will risks be addressed.
Create a Risk Management Plan
People make a plan work, a plan alone seldom makes people work
(Confucius).
Project Charter ExampleTable 5-2
Schwalbe, 2007 p. 185
Project Charter Example
Schwalbe, 2006 pp. 86 - 87
Project Charter Example
Schwalbe, 2006 pp. 86 - 87
Project Scope Statement
Schwalbe, 2007 p. 187
Sample Scope Management Plan Example
Schwalbe, 2007 p.184
Work Breakdown Structure (WBS) Example
Schwalbe, 2006 p. 185
Work Breakdown Structure (WBS) Example
Schwalbe, 2006 p. 176
Work Breakdown Structure (WBS) Example – Tabular Format
1.0 Concept1.1 Evaluate current systems1.2 Define Requirements
1.2.1 Define user requirements1.2.2 Define content requirements1.2.3 Define system requirements1.2.4 Define server owner requirements
1.3 Define specific functionality1.4 Define risks and risk management approach1.5 Develop project plan1.6 Brief Web development team
2.0 Web Site Design3.0 Web Site Development4.0 Roll Out5.0 Support
Schwalbe, 2006 p. 177
Project Schedule Example – Gantt Chart
Schwalbe, 2006 p. 179
Project Cost Budget Estimates ExampleBudget Category Estimated Costs Explanation
Headcount (FTE) 13 Included are 9 programmer/analysts, 2database analysts, 2 infrastructuretechnicians.
Compensation $1,008,500 Calculated by employee change notices(ECNs) and assumed a 4% pay increase inJune. Overload support was planned at$10,000.
Consultant/PurchasedServices
$424,500 Expected consulting needs in support of theProject Accounting and Cascadeimplementation efforts; maintenanceexpenses associated with the Hewlett-Packard (HP) computing platforms;maintenance expenses associated with thesoftware purchased in support of the BSRproject.
Travel $25,000 Incidental travel expenses incurred insupport of the BSR project, most associatedwith attendance of user conferences andoff-site training.
Depreciation $91,000 Included is the per head share ofworkstation depreciation, the Cascade HPplatform depreciation, and the depreciationexpense associated with capitalizedsoftware purchases.
Rents/Leases $98,000 Expenses associated with the Mach1computing platforms.
Other Suppliesand Expenses
$153,000 Incidental expenses associated with thingssuch as training, reward and recognition,long distance phone charges, miscellaneousoffice supplies.
Total Costs $1,800,000 Schwalbe, 2006 presentation slide
Return on Investment Example
Schwalbe, 2006 p. 126
Stakeholder Analysis ExampleKey Stakeholders
Ahmed Susan Erik Mark DavidOrganization Internal
seniormanagement
Project team Project team Hardwarevendor
Projectmanager forotherinternalproject
Role onproject
Sponsor ofproject andone of thecompany'sfounders
DNAsequencingexpert
Leadprogrammer
Suppliessomeinstrumenthardware
Competingfor companyresources
Unique facts Demanding,likes details,businessfocus,StanfordMBA
Very smart,Ph.D. inbiology,easy to workwith, has atoddler
BestprogrammerI know,weird senseof humor
Start-upcompany, heknows wecan makehim rich ifthis works
Nice guy,one of oldestpeople atcompany,has 3 kids incollege
Level ofinterest
Very high Very high High Very high Low tomedium
Level ofinfluence
Very high;can call theshots
Subjectmatterexpert;critical tosuccess
High; hardto replace
Low; othervendorsavailable
Low tomedium
Suggestionson managingrelationship
Keepinformed, lethim leadconversations ,do as hesays andquickly
Make sureshe reviewsspecifications and leadstesting; cando somework fromhome
Keep himhappy so hestays;emphasizestockoptions;likesMexicanfood
Give himenough leadtime todeliverhardware
He knowshis projecttakes a backseat to thisone, but Ican learnfrom him
Schwalbe, 2006
Stakeholder Analysis ExampleKey Stakeholders
Ahmed Susan Erik Mark DavidOrganization Internal
seniormanagement
Project team Project team Hardwarevendor
Projectmanager forotherinternalproject
Role onproject
Sponsor ofproject andone of thecompany'sfounders
DNAsequencingexpert
Leadprogrammer
Suppliessomeinstrumenthardware
Competingfor companyresources
Unique facts Demanding,likes details,businessfocus,StanfordMBA
Very smart,Ph.D. inbiology,easy to workwith, has atoddler
BestprogrammerI know,weird senseof humor
Start-upcompany, heknows wecan makehim rich ifthis works
Nice guy,one of oldestpeople atcompany,has 3 kids incollege
Level ofinterest
Very high Very high High Very high Low tomedium
Level ofinfluence
Very high;can call theshots
Subjectmatterexpert;critical tosuccess
High; hardto replace
Low; othervendorsavailable
Low tomedium
Suggestionson managingrelationship
Keepinformed, lethim leadconversations ,do as hesays andquickly
Make sureshe reviewsspecifications and leadstesting; cando somework fromhome
Keep himhappy so hestays;emphasizestockoptions;likesMexicanfood
Give himenough leadtime todeliverhardware
He knowshis projecttakes a backseat to thisone, but Ican learnfrom him
Schwalbe, 2006
References
• Information Technology Project Management, Fourth Edition (2006) and Fifth Edition (2007) by Kathy Schwalbe
• Risk Management Handbook, Project Management Institute, Newtown Square, PA, 1992, by R.M. Wideman
• Management Concepts