Ridgeway Community Building Study Report
Village of Ridgeway
June 2020
Prepared by Hailey Roessler
Community Building Feasibility Village of Ridgeway, WI
2 | P a g e 2020‐06‐19
Table of Contents
I. Introduction
II. Ridgeway Community Building
A. Physical Condition Assessment
B. Site
C. Existing Building and current floor plans
D. Deficiency Summary
III. Village Revitalization
A. Site
B. Building Use
C. Building Code Implications
D. Conceptual Design and Potential Floor Plan
IV. Potential Partners
V. Grant Options
VI. Pro forma budget
VII. Potential Timeline
VIII. Analysis of Alternatives
IX. Potential Revenue Sources and Benefits of the Community Space
X. Further Study Needed
Appendices
Appendix A ‐ Brickkicker Property Inspection Report completed 04/22/2020
Appendix B ‐ Dodgeville School District Prior Year Inspection Reports
Appendix C ‐ February 2018 Survey Results as applicable from the 2018 Comprehensive Plan
Community Building Feasibility Village of Ridgeway, WI
3 | P a g e 2020‐06‐19
I. Introduction The Village of Ridgeway is considering the acquisition of the Ridgeway Elementary School
located at 208 Jarvis Street, currently owned by the Dodgeville School District. Negotiations are
currently in progress.
The purpose of this review is to determine the effectiveness and costs associated with facility
acquisition, rehabilitation, and repurposing for a community space. This paper will review the
general condition of the facility, general expected alterations, potential phasing, and
preliminary construction cost projections for the needed work. The following potential uses are
only options and are dependent on what the Village Board and Residents determine the best
utilization for the space. The Village could potentially acquire it for adaptive repurposing or
other uses determined to be a good use of village resources.
Primary Physical Deficiencies of the building are:
HVAC/Boiler systems
General exterior repairs
Ceiling and floor tile repair and asbestos abatement
The general proposed uses of the space are:
Village Hall with Board/Meeting Room
Police Office with classroom remodel into a garage
Public Library, Reading Room, Media Center (utilizing existing library)
Multi‐purpose community room (utilizing gymnasium,
Senior and social services use areas
Public Food Pantry
Business Office rental space, business incubation facility, including potential daycare
facility
Alterations as needed to isolate the varied uses for functional, security, and code
reasons
The preliminary data in this report are provided from various sources as follows:
Building Inspection Report by on April 20, 2020
Plan Commission Meeting April 28, 2020
Dodgeville School District reports and documents
Physical assessment for square footage areas May 8, 2020
The comments listed in this report are based on observations, various professional meetings
with multiple area stakeholders, Municipal Clerk surveys/various accounts from other villages
and case histories, the Southwestern Wisconsin Regional Planning Commission, and the Village
of Ridgeway Comprehensive Plan. There is a range of use and phasing alternatives to address
the Village’s physical and space use needs. There may be code‐related mandatory
Community Building Feasibility Village of Ridgeway, WI
4 | P a g e 2020‐06‐19
improvements before the Village may use the building. This is an initial planning document,
general in nature, to identify some ideas and preliminary strategies.
II. Ridgeway Elementary School Community Building Study A. Physical Condition Assessment
Physical needs are items associated with the condition of the buildings and grounds.
B. Site: Site actually consists of four tax parcels. The two field parcels (1.218 acres) are listed under the
Dodg Joint Dist #1 and the two parcels with buildings (1.82 acres) are listed to the School JT
Dist#1 Ridgeway Elementary. The total site area consists of approximately 3 acres and includes
a 25 stall parking lot, an accessible driveway with 2 handicap accessible parking stalls, pea
gravel playground, two half basketball courts, and open field area.
Community Building Feasibility Village of Ridgeway, WI
5 | P a g e 2020‐06‐19
Community Building Feasibility Village of Ridgeway, WI
6 | P a g e 2020‐06‐19
C. Existing Building The main structure of the school consists of the original building built in 1939 and an addition in
1965. This structure consists of 26,291 square feet among three multi‐levels. There is no
elevator in the building. Portable units were added in 1992 and 2008. The portable added in
2008 served as the Village of Ridgeway Marshal Office/Police Department for approximately 4
years until it was closed down and slated for removal in March of 2020 due to gas line leaks.
The portable added in 1992 is currently utilized by the Village Marshal Office at the same price
of $400/month for office and evidence room space. The squad car is currently exposed and has
no garage.
Community Building Feasibility Village of Ridgeway, WI
7 | P a g e 2020‐06‐19
Current floor plans:
Community Building Feasibility Village of Ridgeway, WI
8 | P a g e 2020‐06‐19
Current square footage breakdown:
Community Building Feasibility Village of Ridgeway, WI
9 | P a g e 2020‐06‐19
The current structure is in good shape for its age and is comprised of concrete foundation and
masonry load bearing walls.
The building is centrally located and an anchor to the village, providing a sense of place to the
community. While functioning as a school, it was a central service and a source of identity in
the area.
This need in the community for services and a sense of place would be well served by a
municipal community center whose character and improvements could be directed by the
Village Board, Plan Commission, and area residents. Allowing a large central building to become
a vacant area or failed development project would add to ongoing Village concerns regarding
public nuisances and zoning deficiencies. Ownership of the property allows the village to
control the space and its uses.
D. Deficiency Summary of the current building: There are a number of cosmetic deficiencies to the outside of the building, and some windows
need replacement.
Of primary concern:
The boiler and HVAC systems need replacement
o Only a split system fan coil conditions the office areas, there is no other cooling
in the building
Ceiling and floor tiles contain asbestos and need to be sealed or replaced
o Floor tile is showing wear and peeling from the concrete substrate – exposing
the asbestos
o Areas affected: Art and storage areas, cafeteria, kitchen, main hallway, stair
landing, back service hall, library area
o Potential areas of contamination in the old boiler, pipe insulation, furnace area,
and materials beneath the gym floor
o Area of concern is roughly 8,300 square feet
o Prior to any major renovation an inspection, design and project management
would need to be completed by certified contractors
The main entrance and restroom facilities are not ADA compliant, there is no elevator,
and building layout makes installation impossible for access to all three floors. There is
an accessible entrance on the north side of the building by the handicap stalls with ramp
access available to the gym (could serve as a polling place)
Fire walls and/or sprinkler systems would likely need to be installed prior to village uses
Roof and drainage will likely require ongoing repairs and maintenance
See Appendix A for a complete inspection report done in 2020 for additional commentary on
the current building conditions.
Community Building Feasibility Village of Ridgeway, WI
10 | P a g e 2020‐06‐19
III. Village Revitalization
A. Site The site as configured can generally serve the Village’s uses. An environmental site assessment
does not exist, and is to be provided by the Dodgeville School District as a matter of
contingency in the purchase.
The 2008 Portable was to be removed March 24, 2020 but to date (May 5, 2020) is standing
due to the School District’s contractor request for extension. It is still slated to be removed by
the Dodgeville School District.
The 1992 Portable currently serves as the Marshal Office. It could be auctioned for a Village set
amount or razed as needed by the Village or School District depending on the offer negotiated.
The existence of the playground and playing field areas offer opportunities to serve ongoing
community use of the building as well as an auxiliary outdoor park and recreation uses by
village residents. The playground does need improvements and the Ridgeway Home and School
organization was working to fund those improvements as recently as January 2020. The
conversation leading up to closure, the global pandemic, and closure on April 13, 2020 stalled
those efforts.
If a police garage is added, garage doors will be needed as well as general repurposing of the
classroom to serve as evidence storage and garage space for the squad car. The lower level
would have easy access to the parking area and could facilitate garage doors.
B. Building Use The facility offers ample space and can accommodate many intended uses. Alterations would
be needed to satisfy Building Code requirements and physical condition deficiencies that
contribute to potential health concerns (asbestos).
A physical separation of uses with doors for security and fire prevention, would be
recommended to allow for independent usage of different areas of the building by different
entities.
Community Building Feasibility Village of Ridgeway, WI
11 | P a g e 2020‐06‐19
Community Municipal Building Center Potential Space Use Summary:
Area Name Area
Village Office Space and Board/Meeting Room 2,415 ft2
Marshal Office 840 ft2
Marshal Garage 812ft2
Library 1,680ft2
Gym 3,600ft2
Childcare/Senior Center 1,848ft2
Boys & Girls locker rooms 494ft2
Kitchen
Leased Space/Incubator (5 rooms) 3,270ft2
Total 14,959 ft2
Non‐village use (leased space) 9,212 ft2
Village Use – Police, library, village area 5,747 ft2
Remaining areas not measured: all bathrooms, two storage areas (one with utility sink) on the
second floor, storage areas on the first floor, hallways, and stairways. Taking the total square
footage of the building minus the above leaves these spaces with 11,332 square feet.
Community Building Feasibility Village of Ridgeway, WI
12 | P a g e 2020‐06‐19
C. Possible Building Code Implications: Commercial Wisconsin Building Code and
the International Building Code
A change in use from a school to a mixed‐use building may require:
Sprinkler system and smoke/fire isolation in assembly occupancy – gym
Accessibility issues will need to be addressed
Electrical wiring and services will need to be studied and evaluated by a licensed
professional
o Current service is 120/240 volt single phase three wire system and due to the
type of construction future electrical upgrades would likely require surface
mount conduit and raceway
o Modifications needed are unknown at this time and will warrant further
determination if the project were to proceed
o See page 41 of Appendix A for further details on current electrical installations
and photos, minor repairs noted for age of building
D. Conceptual Design and Potential Floor Plan
For the Village to minimize costs the focus would be:
Limited remodeling to accommodate proposed uses
Initial replacement or sealing‐off of interior finishes in asbestos affected areas
Code required alterations
Boiler and HVAC service replacement and/or ductless mini split unit installation
and/or installation of new high‐efficiency gas furnaces throughout the various zones
of the building
The proposal on the next page indicates a Board Room, and village office space on the first
floor. The Village could potentially utilize the second floor, but doorbells or some notification
for alerting village staff would be required for accessibility compliance for individuals not able
to use the stairs to the second floor of the building.
Senior citizen support areas are an identified need of our aging population, will serve the
community well, and allow for an opportunity for partial Community Development Block Grant
(CDBG) funding.
Child care services are an additional identified community need. Child care areas would need to
have a private entrance to the outside and a fenced outdoor area.
Community Building Feasibility Village of Ridgeway, WI
13 | P a g e 2020‐06‐19
Potential Layout Options:
Community Building Feasibility Village of Ridgeway, WI
14 | P a g e 2020‐06‐19
IV. Potential Partners
Southwestern Wisconsin Regional Planning Commission (SWRPC)
Wisconsin Economic Development Authority (WEDA)/EDA
US Department of Agriculture
US Department of Commerce
Ridgeway Advancement
Ridgeway Home and School Organization
Southwest Wisconsin Community Action Program (SWCAP)
Iowa County Aging and Disability Resource Center (ADRC)/ Greater Agency on Aging Resources (GWAAR)
HeaART Coalition
SUN Program
Southwest Wisconsin Library System (Dodgeville & Barneveld libraries)
Southwest Wisconsin Technical College
WPPI/Focus on Energy
Alliant Energy – Green Energy/Renewable Energy Initiatives
V. Grant Options
Department of Natural Resources/Environmental Protection Agency
DNR Stewardship Grant (May 1 deadline) offers assistance for playgrounds, parks, and urban
green spaces.
EPA/DNR Brownfield Grants assist in asbestos abatement and the redevelopment of properties
that would otherwise be vacant or “brown fields”.
US Department of Housing and Urban Development/Wisconsin Department of Administration –
Community Development Block Grants (end of May deadline)
Delta 3 is currently working on our 2021 Project application. 2019 Infrastructure improvements
were funded through CDBG. In this circumstance the CDBG funding would assist with eligible portions of
the building conversion project. The senior center space, food pantry, and a percentage of the gym and
common area improvements are eligible for CDBG funding.
The Village can include a percentage of the gym space as CDBG eligible per approval of DOA. A
percentage (typically based on sq. footage, determining the percentage of sq. footage the senior center
is in relation to the total building sq. footage) would be eligible. A portion of costs (applying senior
Community Building Feasibility Village of Ridgeway, WI
15 | P a g e 2020‐06‐19
center and food pantry percentage) for other common/shared areas such as the entryway, hallway,
kitchen, mechanical room, and bathrooms could also be eligible.
Economic Development Authority (EDA)/US Department of Commerce/Wisconsin Economic
Development
COVID‐19 Response Stimulus Package – parameters yet to be determined
Both Iowa County and Southwest Wisconsin Regional Planning Commission attest to the timing
of this project and the rollout of a new grant opportunity from EDA. We could join with SWRPC in a
regional application that would focus on the study, planning, and design of the business incubation
portion, and the potential for providing a space for remote workers and distance learning students.
Wisconsin Department of Commerce’s Blight Elimination and Brownfields Redevelopment (BEBR) grant
program, grants between $5‐$7 million dollars annually to Wisconsin redevelopment projects. (Note:
BEBR grants have a year‐round open application period.) – changed to WEDC Brownfield Program
US Department of Agriculture
Community Facilities Direct Grant provides funding to:
Public facilities such as town halls, courthouses, airport hangars or street improvements
Community support services such as child care centers, community centers, fairgrounds or
transitional housing
Public safety services such as fire departments, police stations, prisons, police vehicles, fire
trucks, public works vehicles or equipment
Educational services such as museums, libraries or private schools
Utility services such as telemedicine or distance learning equipment
Local food systems such as community gardens, food pantries, community kitchens, food banks,
food hubs or greenhouses
Private Development
The offer should include all four tax parcels (by name) and the two parcels south of village
owned and covered East Street could be developed into lots and sold.
Tax Incremental District Options
The Ridgeway Elementary School building and all tax parcels currently owned by the Dodgeville
School District are within the Village’s current TID that expires in 2027.
Private Sector Partnerships and Community Grants from Private Corporations
Area businesses, larger businesses offer community programs
Older Americans Act (OAA) Funding – Area Agency on Aging or State Unit on Aging/Wisconsin
Association of Senior Center Directors
The Older Americans Act (OAA) specifically authorizes funding for the operation, “acquisition,
alteration, or renovation of existing facilities” of multipurpose senior centers. Resources are also
available for senior centers and other community organizations to deliver services such as meals,
Community Building Feasibility Village of Ridgeway, WI
16 | P a g e 2020‐06‐19
transportation, information and referral, health promotion and disease prevention, and caregiver
support.
State and Area Plans determine how the OAA funding is used at the local level.
Fundraising and Donations
Private donations from residents, stakeholders, and other organizations not mentioned that are
interested in supporting the project
VI. Pro forma budget
Items Projected Costs
Boiler and Furnace Replacement
TBD
Electrical Misc. Upgrades TBD Code Required Upgrades TBD Marshal Office Renovation and Upgrades TBD
Asbestos abatement TBD
Childcare/Senior Center miscellaneous upgrades TBD
Leased Space/Incubator space miscellaneous upgrades minimal
Soft Costs
Full feasibility study by architect/engineer
TBD
Grant application and administration $30,000
Architectural and engineering services, construction administration TBD
Total Less approximate grant funding (20%) Approximate net village cost
Community Building Feasibility Village of Ridgeway, WI
17 | P a g e 2020‐06‐19
VII. Potential timeline
Phase I – preliminary design and grant application Time
Offer written for purchase For four tax parcels and buildings with contingencies including the removal of the 2008 portable
May 2020
Community Survey and Involvement June/July 2020 Architectural/Engineering Design August 2020 Grant Application August 2020 – May 2021 Village Matching Fund Commitment April 2021
Awards of grants August 2021
Phase 2 – final design and implementation Time
Final design September 2021 Bidding/Award November 2021 Start Construction Complete Construction
2022
2022
Community Building Feasibility Village of Ridgeway, WI
18 | P a g e 2020‐06‐19
VIII. Analysis of Alternatives
Case studies across the state attest that municipalities have horror stories and costs in managing vacant
school buildings and potential developers of those properties.
Alternatives Associated Costs
New Village Hall (requires land acquisition) $1 to $5 million Marshal Office and Garage $35,000 – $55,000 Detached, simple one‐car garage‐various options
Razing of Building 26,291ft2 of building National avg. for commercial demo is $4‐$8
$105,164 ‐ $210,328
Soft Costs or Costs not otherwise identified Private development problems Zoning and CUP
Ongoing Meetings, Reviews, Letters, Citations
Varies depending on project
IX. Potential Revenue Sources and Benefits of the Community Space There is a potential for revenue to be generated from the second‐floor office space areas or the meeting
room. The kitchen could potentially be rented as commercial kitchen space to area
businesses/entrepreneurs preparing products for sale. The gym and/or cafeteria could also function as
rental halls.
Senior Centers serve as a focal point in a community, connect older adults to vital community services
and facilitate the health and independence of the population. Most Senior centers are not what they
used to be. Today’s senior center is a vibrant, action‐packed combination of local fitness center, job and
volunteering headquarters, transportation hub, or tasty dining locale.
If green‐energy options are explored, the electricity account of the village could potentially see credits
and therefore not have to pay for its electricity usage.
X. Further Study Needed
Architectural/Design Review of Marshal Office and Garage Upgrade
Use of the building as a Village Hall
Grant applications in first floor repurposing including green energy options
Incubator Space Exploration
Complete Budget and Timeline for Repurposing