Community Forum 12 December 2013
Resort Management Update
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 - Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Board Appointments
Continuing Board Members
Dean Belle, Deputy Chairman
Jennifer Hutchison, Chairman
Bryce Moore, RAFC Chairman
Dr Kate Brooks, Governance Committee Chairman
Board Appointments
New Appointments to Mt Buller & Mt Stirling Alpine Resort Management Board announced 4 June 2013.
Andrew Evans • Founder and joint Managing Director of Real Estate Development Corporation Pty
Ltd and Canopi Homes. • Founder and Director of Global Pipe Pty. Ltd. • Background and knowledge inthe property industry spanning urban renewal,
residential and industrial subdivision, development of commercial, industrial and retail projects, as well as medium and high-density residential development.
• Member of the Victorian Planning and Environmental Law Association. • Former World Cup Freestyle competitor and Mt Buller Resident.
John Lithgow • Current Chairman of the Mansfield & Mt Buller Cycling Club Criterium and Mt
Buller Road Race Committee. • Former owner/operator of the Yarra Glen Grand Hotel, Yarra Glen • Background in tourism promotion • Keen skier and cyclist
Board Appointments
New Appointments to Mt Buller & Mt Stirling Alpine Resort Management Board announced 16 August 2013.
Elaine Farrelly • A Chartered Accountant with more than 20 years’ experience, • Executive level experience across the telecommunications, media, property
development, manufacturing and not for profit sectors. • She has worked with national and international corporations including KPMG,
Optus, ICI (now Orica) and Fairfax. • Currently the Chairman of the global Movember organisation. • She holds a Bachelor of Commerce, a Master of Arts and is a graduate member of
the Australian Institute of Company Directors
Board Appointments
Departing Board Members
Richard Brooks
Lea Corbett
Michael (Mick) Harding
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 - Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Winter Visitor Statistics
Winter Visitor Statistics
Week 16
Vehicle Multiplier
Day Cars 36,826 3.15 116,002
Buses 1686 40 67,440
Total Day Visitors 183,442 72%
ON Cars 26,999 2.6 70,197
Total ON Visitors 70,197 28%
TOTAL 253,639 100%
ARCC 253,647
Winter Visitor Statistics
Woolcott Research - Net Promoter Score
• This is an index indicating the overall level of promotion a ski resort would likely receive from its visitors.
• The Net Promoter Score is calculated by subtracting the amount of net detractors from the amount of net promoters.
• Promoters are respondents who gave a score of 9 or 10, i.e. extremely likely to recommend the resort.
• Detractors are respondents who gave a score of 0 to 6.
2008 2009 2010 2011 2012 2013
Mt
Buller
2008
%
Mt
Buller
2009
%
Mt
Bulle
r
2010
%
Mt
Buller
2011
%
Mt
Buller
2012 %
Week
1
n=111
%
Week
2
n=98
%
Week
3
n=101
%
Week
4
n=97
%
Week
5
n=102
%
Week
6
n=94
%
Week
7
n=98
%
Week
8
n=99
%
Week
9
n=95
%
Week
10
n=100
%
Promoter 47 53 60 57 51 60 59 64 65 47 49 52 59 40 41
Detractor 14 15 12 13 15 12 6 11 7 23 15 14 13 27 24
Net
Promoter
Score
33 38 48 44 36 48 53 53 58 24 34 38 46 13 17
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 - Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
DATE EVENT
25 -31 Oct Peak Pics Exhibition – High Country Festival
2 - 5 Nov Opening of MTB Trails
2 Nov Sunset Mountain Challenge & Film Festival
8 - 10 Nov Targa High Country
24 Nov Mirabella Running Club – Run Buller
30 Nov Mirimbah Park “ Rides and Reels”
30 Nov Mountain Bike Season Opening Weekend
Summer Events & Activities
DATE EVENT
7-8 Dec Elevation Gravity Enduro MTB Series
14 Dec Sculpture Walk Launch
26 – 27 Dec – Jan Northside Express Chairlift Opens
26-27 Dec-Jan Downhill Mountain Bike Trails Open
Summer Events & Activities
DATE EVENT
24 - 26 Jan Mt Buller Chamber Music Summer School
1-2 Feb Mt Buller Sky Run
7 - 9 Feb MTBA National Series Round - XC & DH
15 Feb Alpine Assault Solo & Team Marathon Challenge
22 Feb 7 Peaks Domestique Series
Summer Events & Activities
DATE EVENT
8-10 Mar Bike Buller MTB Festival
9 Mar Picnic in the Park
22 Mar Scody High Country Challenge
23 Mar Mansfield Mount Buller Cycle Race
18 – 21 Apr Easter Celebrations
19 Apr Mountain High Fun Run
Summer Events & Activities
Summer Clinics and Courses
DATE Clinic / Camps
1-5 Nov MTB Skills – Mt Buller Ride Retreat
16 - 17 Nov Gravity OZ - Women’s Trail Master Skills Clinic
23 -24 Nov Blue Dirt - MTB Ride Weekend
10-12 Jan Gravity OZ - Summer Gravity Camp
1-2 Feb Blue Dirt – MTB Ride Weekend
1-2 March Gravity OZ – Women’s Trail Master Skills Clinic
TBC Jan- April MTB Skills – Women’s Clinics (4 planned)
TBC Feb MTB Skills – Bike Buller MTB Festival Training Camp
26 Dec 8 April Summit Nature Walk • Self Guided
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Water Storage Project
Tirol Flat
Control & Upper Boggy
Koflers
Water Storage Project
Project Scope – What is to be delivered
Size: 100ML off-stream storage with potential provision
for future expansion
Supply: Minimum of 10ML per 24hrs
Location: Assessment of identified sites to determine best
location: (Assessment criteria; construction cost, planning approval, environmental, construction risk, supply, ski area impact, etc)
Water Storage Project
Project Scope – How is it to be delivered
Stage 1
1. Finalise location 2. Draft and submit Planning Permit Application 3. Develop a Design & Construct Package for:
a) Construction of 100ML Dam b) Location (As per 1)
4. Investigation and resolution of ancillary items: a) Amendments to water drafting licenses b) Alternative water supplies c) Integration into current infrastructure
5. Develop Business Case
Stage 2
1. Construct & Commission
Water Storage Project Update
x 2013 2014 2015 2016
Jan Feb Mar May Jun Jul August September Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
29-4 5-11 12-18
19-25
26-1 2-8 9-15 16-22
23-29
Winter Winter Winter Winter
Steering Committee Meetings s
EOI Administered
Tender Documents Issued
Tender Information Session
Tender Response Period
Top 2 Tender Interview
Tender Appointment
Desk Top Review of Sites
Location Determined X
Planning Permit Submission X
Planning Permit Approval
X
Design & Construct Package Creation
D & C Tender Release X
QS Price Estimate
D&C Tender Submitted
D&C Tender Appointment X
Ancillary Investigation Works
Business Case / Funding
Government Budget Submission X
Start Constrcution - Scratching X
Full Construction
Fill
Use x X
May-July: EOI Administered
30 Aug: Appoint Tender
Feb 14: Submit Planning Permit
Mar: D&C Tender Released
Apr 14: D&C Tender Appointed
April 14: Planning Permit Approved
Apr 14: Start Construction (Prelim)
Jan-May 15: Finish Construction
Jun 15 / Jun 16: First Use
Dec: Determine Location
Water Storage Project
Site Location
• Site location was determined through the use of a Multi Criteria Assessment process based upon 35 criteria taken from the Alpine Planning Scheme, the RMB Strategic Plan and other project specific objectives.
• Key project criteria are: Geotechnical Suitability/Risk Resort Recreation Utility/Impact Environmental Impact Construction Costs
• Preliminary Geotech and flora and fauna assessments of the site have been undertaken.
• Detailed Geotech and flora and fauna assessments are being commenced
which will influence the final design, Planning Permit Application and Business Case.
Water Storage Project
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Capital Works Program 2013-14
PROJECT WATER & SEWERAGE
Water for Snow Making System Sun Valley Repairs
Water Other
Water Supply System (5 yr Plan) Additional Water Storage Facility
Sewerage
Sewerage Treatment Plant Upgrades (5 yr Plan) ASSET ENHANCMENT
Energy Saving Efficiencies (Annual Action Plan) Website rebuild Hard Waste Bunkers - Boggy Corner IT Systems
COMMUNITY FACILITIES / ARMB BUILDINGS
Alpine Central Renovations (5 yr Plan) RMB Buildings (5 yr Plan) Cow Camp Extension Mirimbah Park - Precinct Design Level 4 Conference Equipment
PRODUCT AND ACTIVITIES
Signage EPIC MTB Trail Development Mt Buller Cinema Technology Upgrade Automated Guided Walks Snow Play Area Development
ACCESS / TRANSPORT
Vehicle Access System (5 year Plan) MT STIRLING
Mt Stirling Hydro ROADS AND CAR PARKS
Road & Car parks (5 yr Plan) Link Road Culvert Replacements Spoon Drains, Sheeting, Windrows and Outflows Water Flow Redirection & Earth Works Roadside Slumping Stabilisation Works
Sun Valley Reservoir Liner
Cow Camp Refurbishment
Ground Level Current Floor Plan
Ground Level New Plan
New Mezzanine level
Cow Camp Refurbishment
EPIC Mountain Bike Trail
• 40km cross country descending trail from Buller-Stirling, through Mansfield State Forest (DEPI) and Mt Russell Education Area (PV)
• Will be the first EPIC mountain bike trail in Australia endorsed by IMBA (International Mountain Biking Association)
• Attracted both State and Federal funding with Resort Management as lead Agency and Project Manager
• After 4 years of planning, construction commenced on December 2
Snow Play – Additional Area
Mt Buller - Mt Stirling Link Road
Mt Stirling
Mt Buller
Project Objectives:
• Primary: All weather, all vehicle alternative access for public and emergency management, access and egress.
• Secondary: Better link the two resorts: • Complementary activities & facilities, • Efficiencies, • Touring opportunities
Current Status: • Route Alignment finalised • Planning Application and Documentation lodged and following the
planning course • In Process of Appointing Tender for Civil Engineering Consultant • Construction to commence early 2014 subject to planning approval. • Construction duration - two summer seasons.
Mt Buller - Mt Stirling Link Road
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Environmental Update
Mountain Pygmy-possums
Environmental Update
Mt Stirling
Topics
• Board Appointments
• Winter 2013 Visitor Statistics
• Summer 2013/14 Update
• Water Storage Project - Update
• 2013/14 Capital Works Program - Overview
• Environmental Update
• Mt Stirling Update
• Questions
Questions
?
Thank you
Water Supply
• Sun Valley • Overview of the System
• Development of the Snowmaking & Water Supply Systems • How they work and parameters
• Additional Water Storage Project & Timeline
• Additional Snowmaking Infrastructure Plan & Timeline
Snowmaking & Water Supply
Overview of the Water Supply System
Snowmaking & Water Supply
• Additional Snowmaking Infrastructure Plan & Timeline