Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Presented By:Utility Manager
Action Taken:YesNo2
Abstain_tL
CITY OF NOME, ALASKA
RESOLUTION NO. R-15-ol-o3
A RESOLUTION APPROVING & ACCEPTING A LOAN FROM THE ALASKA DEPT. OFENVIRONMENTAL CONSERVATION ALASKA DRINKING WATER FUND TO
PROVIDE FINANCING FOR IMPROVEMENTS TO COMMUNITY WATERINFRASTRUCTURE
WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,
WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to 20 years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,
WHEREAS, by Resolution R-14-lo-o2, which amended Resolution R-13-o5-o2, a loanamendment was authorized for Project #627161, to provide additional match funding for SclaircoreReplacement Phase ; and,
WHEREAS, Sclaircore Replacement Phase i requires funding to match municipal matchinggrants for East 5th Avenue construction, and ADEC recommended combining the initial loanamendment with the additional required match, for a total of $1,563,6oo; and,
NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan ADEC Drinking Water Fund Loan for the construction of water system improvements for a newtotal of $1,563,600, with a 20-year payback at i.% interest, as recommended by Nome Joint UtilityBoard Resolution ‘4-17, and authorizes the Utility Manager as Chief Operating Officer of the Utilityto execute any and all documents that may be required by the Department to reflect theindebtedness, the terms of its repayment, and any security thereof, including but not limited to anagreement for the loan and a promissory note.
APPROVED and SIGNED this 12th day ofJanuary, 2015.
DENISE MICHELS,
ATTEST:
TOM MORAN, Clerk
NOME JOINT UTILITY SYSTEM
NOME JOINT UTILITY BOARD
RESOLUTION 14-17
A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTA LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKADRINKING WATER FUND TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TO
COMMUNITY WATER INFRASTRUCTURE
WHEREAS, The Utility Board determined application should be submitted to the AlaskaDepartment of Environmental Conservation Drinking Water Fund Program tofinance various infrastructure improvements constructed to the water and sewersystems, including replacements, extensions and enhancements; and,
WHEREAS, the Alaska Department of Environmental Conservation Alaska Clean Water &Alaska Drinking Water Fund loan programs offers terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems; and
WHEREAS, NJUS submitted annual questionnaires to be included on the Amended IntendedUse Plans for the ADEC Drinking Water Loan program. ADEC has completed thepublic notice process and has included funding for East Nome Water Replacement— $2,690,000, and intends to offer NJUS a loan of up to that amount; and,
WHEREAS, initial loan applications made to provide partial funding for Sclaircore ReplacementPhase 2A, additional federal funding was awarded, and the existing loan onlypartially matches state grants for Phase 2B, and Sclaircore Replacement Phase I(East 5 Avenue) requires funding to match municipal matching grants forcompletion of Phase 28 and Phase I (East 5th Avenue) — for a total of $1,563,600;
NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and authorize acceptance of a loan for $1,563,600 through the ADECDrinking Water Fund Loan Program for construction of water system improvements with a 20 yearpayback at 1.5% interest, and authorize the Utility Manager as Chief Operating Officer of the Utilityto execute any and all documents that may be required by the Department to reflect theindebtedness, the terms of its repayment, and an security thereof, including but not limited to anagreement for the loan and a promissory note.
SIGNED THIS I DAY OF &vY bel , 2014 AT NOME, ALASKA.
Berda Wilison, ChairmanATTEST: NOME JOINT UTILITY BOARD
David Barron, SecretaryNOME JOINT UTILITY BOARD
‘7
:
ill
ALASKA DRINKING WATER FUND
STATE WATER LOAN PROGRAM
INTENDED USE PLAN - AmendedFINAL
FFYI4 Grant Allotment
State Fiscal Year 2015
IIIi‘[I
III
J
llSubmitted to the U.S. Environmental Protection Agency
ByAlaska Department of Environmental Conservation
Division of WaterDecember 2014
I
AL
ASK
AD
RIN
KIN
GW
AT
ER
FUN
DF
undi
ngP
rior
ity
Lis
t-
Am
ende
dF
isca
lY
ear
2015
Ráñ
ksá
árC
rnrn
unit
::o
m.:
iibn
cW
ater
$te
flID
#.:
.:$
àt1
6fl
)
.........................................................
-.•
.••
...
Gre
en...
.A
ssIs
tnce
Frn
anc
term
Pro
ject
Pro
Ject
Co
nst
ruct
ion
Sust
aInab
hty
_______
__
__
__
__
__
__
Pfo
ject
Des
crip
t,on
Am
ountZ
Rat
e(Y
rsS
ub
s1d
yA
mount
Sta
rtP
OI,
C9
AK
2211
229
Tre
atm
ent
Plan
tU
pgra
deT
he
proj
ect w
illre
habi
litat
eth
efa
iling
Cre
eIoo
odPa
rksu
rfac
ew
ater
(35Q
\&
Res
ervo
irtr
eatm
ent
syst
emne
arW
asill
a.W
ork
incl
udes
impr
ovem
ents
and
purc
hase
of$5
05,5
771.
50%
20$3
79,1
838/5
/2014.
Fix
itFi
rst
‘I
Con
stru
ctio
n[t
hesy
stem
,an
dco
nstr
uctio
nof
are
serv
oir.
A23
4001
0R
epla
cefa
ihng
wa
erse
airi
ppin
gal
ong
Dpo
riSt
i’ee
tK
ing
Plac
eW
arre
nN
ome
ircor
eP
Iae
and
Spo
kane
Stre
etw
thne
wdi
fect
hwy
arct
icpi
pe.
Ela
mna
tloil
ofpi
pe$2
92,3
0G1
50%
20*1
,389
,817
$2,9
20,3
00EN
G-E
C5/1
5/2
504.
FIx
itFi
rst
ePla
cem
efa
ilure
l&1
will
prov
ide
ener
gysa
ving
s.
AK
2211
821
Spen
ard
Hei
ghts
Des
ign
and
cons
truc
tion
offi
hrat
ion
impr
ovem
ents
tore
duce
arse
nic
leve
ls,
$312
800
01.
50%
20$3
128
000
ENG
-BC
5/15
/201
5Fi
xit
Firs
t(1
00)
lDls
trlb
utlo
nSy
stem
and
repl
acin
gen
dof
life
galv
aniz
edw
ater
lines
with
new
lines
.
AX
2110
643
Salm
onC
reek
.Sec
onda
The
asse
ssm
ent
ofle
vee
0di
sinf
ectio
nre
quir
edfa
cilit
ype
miit
bng
and
the
desi
gean
dco
nstru
ctio
nof
asec
orid
ary
disi
nfec
tion
proc
ess
atth
eSa
lmon
$4t)
0O00
150%
2G3/
1]20
15ft
xit
Frs
tC
reek
Wat
erT
reat
men
tFa
cilit
y
AK
2213
001
Res
urre
ctio
nD
rive
Wat
erR
ehab
ilita
teor
repl
ace
appr
oxim
atel
y53
1lin
ear
feet
of8-
inch
duct
ileiro
npi
pe75
000
01
50%
205
914.
Fit
F(2
91,8
26)
Reh
abil
itat
ion.
with
inR
esur
rect
ion
Driv
efr
omT
ikis
hla
Str
eett
o79
41R
esur
rect
ion
Driv
e.$
‘.
/2/
ixirs
AK
2213
001
Rep
lace
exis
ting
faih
nwat
erm
ain
riO
erra
hS
tree
t fro
mFi
rew
eed
l.as
eto
7115
114e
Fix
itFi
rst
Fir
ewee
d.
AK
2226
020
Palm
erSt
eel
Wat
erM
ain
Rep
lace
old
stee
lw
ater
pipe
inth
eno
rthe
aste
rnar
eaof
the
City
ofPa
lmer
.28
571
41
202
50
000
ENG
-BC
61
2015
F(5
937)
Rep
lace
men
t1
know
nas
the
“She
rrod
”ar
ea.
.0
//
lxi
1Su
bsid
yfu
ndin
gfo
rth
eN
ome-
Nom
eSc
lair
coro
Rep
lace
men
t-Ph
IIIpr
ojec
tis
limite
dto
avai
labl
esu
bsid
yfu
nds.
Add
ition
ally
,fu
llpr
ojec
tfun
ding
ofth
ePa
lmer
-Pa
lmer
Stee
lWat
erM
ain
Rep
lace
men
tpr
ojec
twill
bede
pend
ent
upon
rem
aini
ngav
aila
ble
loan
fund
s.T
heD
epar
tmen
twi
llne
gotia
tew
ithPa
lmer
topr
ovid
ead
ditio
nalf
unds
asth
eybe
com
eav
aila
ble
late
rin
the
year
.2T
ota
lav
aila
ble
proj
ect
loan
fund
ing
and
subs
idy
unde
rth
isA
men
ded
IUP
is$1
3062
573
and
$1,7
69,0
00,
resp
ectiv
ely.
3Cri
teri
afo
rbe
ing
elig
ible
for
alo
ansu
bsid
ym
aybe
refe
renc
edon
page
13un
der
the
narr
ativ
ese
ctio
nof
the
PUP.
Proj
ects
whi
chde
mon
stra
tead
equa
tecr
iteri
afo
rm
eetin
ga
Gre
enpr
ojec
tcom
pone
ntwi
llbe
elig
ible
tore
ceiv
ean
addi
tiona
l25
poin
ts.
Gre
enPr
ojec
tR
eser
veC
ateg
ory
Typ
e:G
IF-
Gre
enIn
fras
truc
ture
,W
rR-
Wat
erEf
ficie
ncy,
EN
G-
Ene
rgy
Effic
ienc
y&
LIN
-E
nvir
onm
enta
llyIn
nova
tive.
Gre
enPr
ojec
tJus
tific
atio
nTy
pe:
BC
-B
usin
ess
Cas
e!C
AT
-C
ateg
oric
al.
6Pr
ior
tofu
ndin
gan
ypr
ojec
tsho
wn
toha
vea
fund
ing
subs
idy
for
Gre
en,
aB
usin
ess
Cas
efo
rpr
ojec
tG
reen
elig
ibili
tym
ust
befo
und
just
ifie
d.
Sus
tain
abil
ity
Pol
icy.
“Fix
itF
irst
-fix
exis
ting
criti
cal
infr
astr
uctu
re;
“Im
prov
eTF
M”
-im
prov
ete
chni
cal,
finan
cial
and
man
ager
ial
capa
city
ofth
esy
stem
;an
d,“P
lann
ing
-pl
anni
ngan
dde
velo
pmen
tof
alte
rnat
ive
proj
ects
that
refl
ectt
hefu
lllif
ecy
cle
cost
ofin
fras
truc
ture
.65
poin
tsar
eon
lyaw
arde
dif
afe
asib
ility
orde
sign
stud
yha
sbe
enco
mpl
eted
for
the
pre
ct
byth
een
dof
the
ofqu
estio
nnai
reso
licita
tion
perio
d.
3 4 5
.6
.
7
216
ALP
AT+
201
No
nie
•
200
Spen
ard
Hei
ghts
Wat
er
•jneau
176
Anc
hora
ge
‘171
:..
Aii
chtl
taei
156
Pal
mer
•
•D
isad
vant
age
Com
mun
ity(c
rite
ria
may
bere
fere
nced
onpa
ge13
)
•E
quiv
alen
cyPr
ojec
t(c
rite
ria
may
bere
fere
nced
onpa
ge12
)
•E
xtra
50po
ints
for
cons
truc
tion
star
tby
Sep
tem
ber
15,
2014
8
Tot
alR
eque
sted
Am
ount:
I$t4
08959t:
]
Tot
alSu
bsid
ized
Am
ount
3:I$
1,76
9i..:
.:IT
otal
Equ
ival
ency
Am
ount
: [*
:9,6
75,8
TzI
Tot
alG
reen
Am
ount
:$:
.:6,2
98
DW
Prio
rity
List
App
endi
xV
aA
men
ded
IUP
-FI
NA
L
AL
ASK
AD
RIN
KIN
GW
AT
ER
FUN
DF
undi
ngP
rior
ity
Pla
nnin
gL
ist
-A
men
ded
Fis
cal
Yea
r20
15
Wat
erM
ain
Rep
iace
men
d
AK
2120
323
Cha
tham
Ave
nue
Wat
er(8
,050
)M
ain
Rep
lace
men
t
AK
2120
3231S
ctio
enba
rR
oad
Wat
er
AK
2110
643
Las
tC
hanc
eB
asin
Wel
l
(31,
275)
Fiel
dC
apac
ity:Im
PrO
Ver
Tief
lts•
0347
Zon
eC
onve
rsio
n•
(291
843
0Z
one
Con
vers
ion.
‘eda
ceap
prox
.330
0oA
CptO
(YofD
Ppip
ew
1th
C-9
00(V
Con
gnaI
lTra
cts
Psi
Vie
wSt
Firs
tAve
Nor
thar
idFr
ontS
t.
epla
cem
ent
ofth
eex
istin
gag
ing/
faili
ngw
ater
syst
emw
ithin
DeG
roff
Str
eet
)etw
een
Saes
nill
Cre
ekR
oad
and
Lake
Stre
et.
epla
cern
ent
ofap
pro
xra
tely
4000
feet
ofw
ater
pipi
ngw
itlur
ith
eEg
ari
rrye
corr
idor
betw
een
Ten
thS
tree
tan
dM
ain
Str
eet,
eev
alu
ate
wat
erpr
ojec
tsrs
tthan
upda
ted
mas
ter
plan
:co
nduc
thy
drol
ogic
rtud
ies;
deve
lop
new
wat
erso
urce
sdo
wnt
own
and
atth
ela
ndfil
l;an
dup
grad
eN
ater
dist
ribu
tion
pipi
ngin
clud
ing
met
ers
and
leak
dete
ctio
n.
epla
cen
ien
tof
feti
ngdu
ctil
eIr
onI-
lOPE
pip
ing
incn
tlcal
area
shr
ough
out t
hew
ater
syst
em
Inst
all4
91-l
inea
lfee
tof
8”H
OPE
wat
erm
ains
,(2
)fir
ehy
dran
ts,
and
(14)
rerv
ices
inst
alle
dto
the
edge
ofth
erig
ht-o
f-w
ay,
inap
prox
imat
ely
5.40
feet
ofro
adw
ay.
inst
al1,9
’ier
eiet
iiee
tofl
rklO
PE
wti
tem
a1rt
sfte
m;.
tfli
eSeh
ndfi
ieT
rad::
;:in
ters
ectio
nto
Val
ley
Forg
ef8
oad
200-
knea
tlee
tof4
”-1G
’H
OPE
wat
erm
ates
thtQ
hO
i4:t
ndP
tOeeh2flt
5ali
dffiU
le:g
at:
:.:
Inst
all
and
deve
lop
two
wel
lsat
the
Last
Cha
nce
Bas
inW
ell
Fiel
dto
impr
ove
:apa
city
,an
ddr
illan
dde
velo
pfiv
ew
ells
aacen
tto
exis
ting
wel
lsut
ilizi
ngsx
istin
gin
fras
truc
ture
.
Prov
Ide
syst
emte
dund
ancy
mth
eti
rwer
sity
Med
ical
Dis
tric
tare
ade
com
mis
siar
sele
ctPR
Vs
redu
cing
oper
atin
gco
sts
max
eniz
epr
oduc
tion
rom
Wel
t4an
dre
duce
tran
sien
tpre
ssur
ewav
esin
syst
em
onve
rtth
e43
0H
GL
zone
near
Abb
ott
and
Elm
ore
and
cons
olid
ate
diff
eren
tpo
rtio
nsin
toei
ther
the
475
HGL
zone
orth
e41
1H
zone
.The
conv
ersi
onNi
llin
crea
setr
ansm
issi
onca
paci
tyan
dre
duci
ngpr
essu
refl
uctu
atio
ns.
Gre
enre
en
Est
tmat
edA
sste
tance
Fin
ante
TeFe
nP
roje
ctP
roje
ctC
onsf
ruct
lon
Sus
ta1n
abil
it,
Am
ount’
Rat
e(Y
rs)
Subsi
dy’
Am
ount
3‘t
ype”
Sta
rtfo
1icy
e
1Tot
alav
aila
ble
prce
ctlo
anfu
ndin
gan
dsu
bsid
yun
dert
his
Am
ende
dIU
Pis
$13,
06Z
573
and
$1,7
69,0
00,
resp
ectiv
ely.
2Cri
teri
afo
rbe
ing
elig
ible
for
alo
ansu
bsid
ym
aybe
refe
renc
edon
page
13un
der
the
narr
ativ
ese
ctio
nof
the
IUP.
Proj
ects
whi
chde
mon
stra
tead
equa
tecr
iteri
afo
rm
eetin
ga
Gre
enpr
ojec
tcom
pone
ntwi
llbe
elig
ible
tore
ceiv
ean
addi
tiona
l25
poin
ts.
Gre
enPr
ojec
tR
eser
veC
ateg
ory
Typ
e:G
IF-
Gre
enIn
fras
truc
ture
,W
TR
-W
ater
Effic
ienc
y,EN
G-
Ene
rgy
Effic
ienc
y&
EIN
-E
nvir
onm
enta
llyIn
nova
tive.
Gre
enPr
ojec
tJus
tific
atio
nTy
pe:
BC
-B
usin
ess
Cas
e!C
AT
-C
ateg
oric
al.
Prio
rto
fund
ing
any
proj
ects
how
nto
have
afu
ndin
gsu
bsid
yfo
rG
reen
,a
Bus
ines
sC
ase
for
proj
ect
Gre
enel
igib
ility
mus
tbe
foun
dju
stif
ied.
Sust
airr
abili
tyPo
licy
-“F
tcit
Firs
t”-
fixex
istin
gcr
itica
lin
fras
truc
ture
;“I
mpr
ove
TFM
”-
impr
ove
tech
nica
l,fi
nanc
ial
and
man
ager
ial
capa
city
ofth
esy
stem
;an
d,“P
lann
ing”
-pl
anni
ngan
dde
velo
pmen
tof
alte
rnat
ive
50po
ints
are
only
awar
ded
ifa
feas
ibili
tyor
desi
gnst
udy
has
been
com
plet
edfo
rth
epr
ojec
tby
the
end
ofth
eof
ques
tionn
aire
solic
itatio
npe
riod
.
8A
K23
4001
0lE
ast
Nom
eW
ater
(3,5
98)
Rep
lace
men
t
.:k’,fl.’,rr
Phas
edpr
ojec
tto
repl
ace
faile
dan
dfa
iling
dire
ctbu
ried
“Scl
airc
ore”
wat
eran
dse
wer
pipi
ngth
atw
asin
stal
led
inth
e19
80s.
156
Nom
e•
146
Sitk
a
143
3trn
eau
141
Dill
ingh
am+
9. 10 :1.1
::::
12 14
AK
2130
075
DeG
roff
Str
eet
Wat
er(8
,881
)ll
mpr
ovem
ents
AK
ZI1O
8fl
lEga
nD
r/IO
thlo
ltaIr
f
AK
2260
197
Drin
king
Wat
er(9
62)
Impr
ovem
ents
131
Ket
chik
an•
$2,6
90,0
00
$2,0
0000
0
$162
,000
$1.8
000ô
ô*
36.
16 18
13t
Ket
ctilk
an•
128
June
au
12 126
Anc
hora
ge
$2,6
90,0
00
$2,0
00,0
00
$1,3
52,1
00
$180
001
0
$1,0
00,0
00
$542
249
$864
,829
$2,0
00,0
00
$750,0
0
$450
,000
1.50
%
180%
1.50
%
1.50
%
1.50
%
1.50
%.
1.50
%
1.50
%.
1.50
%
1.50
%
20 20 20 20 20 20 20
2G.
20 20 20
ENS-
BC
WTR
-BC
wrR
•ec
ENG
-BC
ENS-
BC
3/1/
2014
s/1/2
o1s.
;.;
5/15
/201
6
8/1/
2014
1/1/
2015
10/1
/201
4
Fix
itFi
rst
Fix
itj
Fix
itFi
rst
Fix
itFi
rst
Fix
itF
irst
FIt
itFf
rSt::
&.
Fix
itFi
rst
•D
isad
vant
age
Com
mun
ity(c
riter
iam
aybe
refe
renc
edon
page
13)
•E
quiv
alen
cyPr
ojec
t(c
rite
ria
may
bere
fere
nced
onpa
ge12
)
•E
xtra
50po
ints
for
cons
truc
tion
star
tby
Sep
tem
ber
15,
20
14
$200
,000
$2,0
00,0
00
9/i
5/2
4•
j*oveF
M
Tot
alR
eque
sted
Am
ount
1$t6
,it5
,713
1
9/15
/201
4
Tot
alSu
bsid
ized
Am
ount
3:[$
:::::
..
.:
Tot
alG
reen
Am
ount
I$9.3
94:24
9:1
Impr
ove
TFM
OW
Plan
ning
List
App
endi
xlV
bA
men
ded
IUP
-FI
NA
L
NOME JOINT UTILITY BOARDMeeting Date: December 18, 2014
Sclaircore Replacement Phase I & II; ADEC Drinking Water & Clean Water LoansResolutions 144w & 140&
NJUS applied for two municipal matching grants (MMGs) for Sclaircore Replacement Phase 2,for two phases to replace water-sewer utilities in the east quadrant of town, from Front to 6th
between N and K streets. The State awarded funding for Phase 2A in the amount of $3.OMMand Phase 2B in the amount of $4.557MM, the total of which represented 57% of the project.(Nome is eligible for up to 70% match, but in our initial application DEC limited the award to$3.0MMtypicalIy their grant limit (only 45%), although we were successful in making the casefor 70% funding in the second application.
Concurrent with the initial MMG application, the Utility submitted loan questionnairesequivalent to the amount of Phase 2A to be considered for funding under the Alaska DrinkingWater and Clean Water Loan Programs. These questionnaires successfully rated and wereincluded in the respective program’s Intended Use Plans (IUP). The Drinking Water Fund loanof $1,990,000 included a 50% subsidy (loan forgiveness) component. The Clean Water Fundloan of $1,740,000 included approximately 10% subsidy.
NJUS continued to seek out additional potential funding from federal sources to provideadditional matching funds for Phase 2B. We were not successful in our quest with USDA duringthis round, but did capture $769,800 in EPA funding for the project. This left a residual fundingneed of $1.2MM to fully match the state grants.
NJUS also applied for a MMG for Sclaircore Replacement Phase I (East 5th Avenue) and wasawarded $1,058,000 for the project. Concurrently, application was made to USDA for matchfunds. USDA accepted an application for a $308,000 loan and a $1,075,000 grant for furtherprocessing to provide additional funding for the project. We continued discussions with USDAas the terms being offered were onerous, requiring significant reserves to be funded on anannual basis, but the project had already been started. While other requirements to secure thefunding were not completed as we believed we were still in negotiation, USDA now advises thatbeing the project was started before all items had been resolved, they cannot provide fundingfor the project. (In a prior project, USDA did award funding subsequent, but based on their owninternal reviews, were directed they could not do so again — something that was not sharedwith NJUS until recently.)
ADEC was contacted and agreed that NJUS could include the Phase I (East 5th Avenue) in arevised application, and that the amendment requests for additional funding for Phase 2 shouldbe included in the same application, as opposed to amending an existing loan.
Recommended action:
That Resolutions 14-17 and 14-18 be adopted, to provide additional Phase 2 and include Phase Imatching funds in new loans applications, and that the prior amendments contained for Phase2 in Resolutions 14-07 and 14-08 be rescinded.
J. Handeland12/15/14
NOME JOINT UTILITY SYSTEMa component unit of
P.O. Box 70 Nome, Alaska 99762 (907) 443-NJUS Fax (907) 443-6336
December 10, 2014
RE: USDA Anticipated FundingEast 5th Avenue Sclaircore Replacement
In 2010, NJUS submitted an application for funding to USDA for funding assistance with theconstruction of East 5th Avenue Sclaircore Replacement. After meeting with USDA personnel,additional updates were required to the Preliminary Engineering Report (PER) and EnvironmentalReport (ER), which were done and submitted. On May 25, 2011, USDA issued an Initial Letter ofConditions (LOC) advising funding application ($308,000 loan and $1,075,000 grant) had beenselected for further processing.
The LOC included numerous provisions, including the requirement to establish operating (annual$377,196) nd short lived asset replacement (annual $290,833) reserves, NIUS transmitted toUSDA concern relative to these requirements and requested a review and revision, as theserequirements in themselves would require additional revenue of approximately $43 percustomer per month before considering debt service.
A pre-construction meeting was scheduled for July 2011, but USDA advised they could notparticipate due to short notice and the emergency family leave of one of their personnel. Workcommenced on the project and the USDA Engineer came to Nome later in the month for whatwe believed was a follow-up for the pre-construction meeting, hut USDA considered it only aninspection, noting work had commenced.
USDA considered the request relating to the reserve requirements and revised them in anAmended LOC issued in February 2012. In May 2012 the Utility Board passed resolutions on thefinancing and submitted a request to USDA relative to the financing, as the standard forms hadbeen previously found unworkable (due to their requirement of placing USDA in “first position”,and other USDA loans and the Alaska Municipal Bond Bank issue already had superior position).We find no response was received.
NJUS considered the financing secured and reflected same as outstanding receivables. In March2014 as we were working to resolve all outstanding grant/loan matters, NJUS met with the USDAengineer to review the status and were advised to contact the Community Programs Director(CPD) to determine outstanding matters required to finalize the funding. In response to ourrequest, the CPD telephoned to advise of her impending retirement and that this file would needto wait until later in the year when new personnel were in place.
Pr’ovicling reliable utility services to system rate payers efficiently and econoinkally by
RE: USDA Anticipated Funding — East 5th Avenue Sclaircore ReplacementDecember 10, 2014Page 2.
On November 10, the Utility Manager met with the City Manager and Finance Director expressingconcern that the funding could fall through. A call was placed to USDA and they confirmed thefunding had not been deobligated and a file review would commence. A telephonic meetingwas scheduled for November 26, but was changed several times by USDA as they continued toreview their files.
On November 25, we were advised by phone that delays were due to file review and internalconsultation. We were advised that because the project had been started and completed beforeresolving all matters, based on a prior determination by USDA National Office, funding would notbe provided and that there was a process of appeal. We met with the City Manager and FinanceDirector to advise of this, and that we would likely have to go through the appeals process.
As we had not received a response to our May 2012 inquiry on the loan documents, and USDAhad amended the LOC in February 2012, after construction was completed, we did not completethe process of submitting other USDA LOC documents, pending the request to further amend theLOC.
Subsequently, on December 8, USDA advised based on their internal handling of a loan to Nomein 2006, there were specific requirements that the loan and companion grant could not be closeduntil all LOC items were met and that construction could not begin until Rural Development gaveauthorization to proceed. Based on construction being complete and other documentation/procedures in the LOC not having been met, they could not fund the project.
With an inclination this funding could be in jeopardy, in November NJUS submittedquestionnaires to the ADEC clean water and drinking water program to seek potential loanfunding under their open period for amending the current year Intended Use Plan (IUP), abovethat which had been already approved as amendment requests ($1.3MM)to the loans for currentyear sclaircore replacement. These questionnaires were scored and included in the IUP, withadditional funding of $3.7MM available above the amendment amount,
Under the USDA funding, the Utility would have had required annual loan payments ofapproximately $60,000 plus the requirement to deposit $173,017 into a SLA reserve, orapproximately $15 per water/sewer customer per month for 40 years. Under the alternatefunding through ADEC, the annual requirement for 20 years would result in a requirement ofbetween $4.50 and $6.81 depending on whether additional project costs not included in theUSDA funding may also be loan eligible. Should ADEC amend their loan program to extend theterms to 30 years, the annual requirement comparative would be between $3.00 and $4.54.
it is unfortunate USDA funding will not materialize. However, having now had an opportunity toreview in greater detail the ADEC loan option. Utility customers actually will benefit to a greaterdegree by utilizing ADEC (debt service and reserve requirements are $10/month less percustomer under AIEC than USDA>. Utilizing additional ADEC loan funding to “refinance” the 5th
Avenue project paid with operating funds is the only option available and with authorizingresolutions, can be applied for and reimbursements received in January 2015.
L”v
USDA — 5th Avenue
Submitted project application, Preliminary Engineering Report (PER), Environmental Report (ER>—summer 2010
Met with Misty on application — Nov/Dec 2010
USDA review of PER/ER previously submitted required updates; done with Lloyd Persson, CE2
Initial Letter of Conditions — May 2011
Pre-Construction meeting scheduled 7/6/11 — Advised USDA could not participate due tonotice/Misty out on emergency family leave.
Work commenced summer 2011
(rug and Persson in town to meet on project status— July 2011
Transition engineer from Persson to Erdman — fall 2011
Erdrnan met with HuH on SL revisions. Utility submitted requested changes to short livedassets schedule/reserve requirements — February 2012
Received amended letter of conditions — February 2012
Utility Board passed resolutions on financing— May 2012
Transmitted resolutions to Kruse, requesting clarification on loan documents/securityagreement — June 2012
Project review by Krug in Norne — March 2014
Requested meeting with Kruse to resolve outstanding issues; she was retiring and said it wouldhave to wait until later in year — April 2014
City Manager, Finance Director, Utility Manager contacted Hull — confirmed funds had not beende-obligated and she would review file — November 2014
Meeting scheduled with Hull to review outstanding issue on loan documents-securityagreement, and requested additional change to short lived asset schedule/reserve requirement—November 2014. Meeting times moved a couple of times as she had not been able tocomplete file review. Meeting scheduled for 11/26, but changed to 12/3 due to holiday.Requested that if there was another opening prior to 12/3, that we would like to meet as soonas possible.
Advised by phone 11/25 that delays were due to file review and internal consultation. Statedbeing work had been completed prior to resolving all matters, funding would not be provided,and that there was an appeals process. Delay had been while she reviewed file and workedwith National Office to determine what their response was going to be. To expect a letter.
Met with city manager & finance officer to advise of above.
Brief synopsis 12/2/14 /1 hand eland
EAST 5TH AVENUEPROJECT COSTING TOTAL
LaborMate na IsFreightEquip Rent-OthersEquip Rent-NJUSServicesLegalPermitsInspectionSuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew
DEC 62766 - PAY REQUEST00-0 L’bor02-0 Freight03-0 Equip Rent-Others04-0 Equip Reni-NJUS
RESIDUAL (portion USDA planned)00-0 Labor01-0 Materials02-0 Freight03-0 Equip Rent-Others04-0 Equip Rent-NJUS05-0 Services06-0 Legal07-0 Permits
SuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew
PORTION UNMATCHED IN DEC00-0 Labor02-0 Freight03-0 Equip Rent-Others
20,866.1153,106.40 1,263.50
53,731.951,962.40 79,023.18
115,001.74 1,082,264.12
2,2 50 .006,317.02 25,439.45
TOTAL821,029.49708,660.07113,567.82511,759.30249,346.15137,316.43
78.00506.12
2,250.00175,582.82
2,600.0020,866.1154,369.90
1S9,258.41194,540.21
3,151,730.83
GENJN. WATER70-0651 70-065212,347.92 322,364.19
177,635.6658.48 13,919.57
1,620.00 237,958.96112,313.83
14,810.09 11,648.3478.00
00-001-002-003-004-005-006-007-008-009-015-020-050-052-054-0
FIRE I-{YD70-0654
55,728.7822,154.71
2,263.9916,494.154,265.461,500.00
SVC LINES70-0655120,315.43174,370.8454,285.6617,392.2627,183.74
101,575.00
506.12
7,821.221,825.00
SEWER70-0653310,273.17334,498,8643,040.12
238,293.93105,583.12
7,783.00
63,987.69387.50
60,562.9661,799.43
1,226,209.78
72,017.44387.50
4,967.0012,288.83
125,979.94
39,996.5039,466.37
602,275.25
Inspection08-009-015-020-050-052-0
54-0
70-0651 70-0652 70-0653 70-06548,295.21 303,965.53 292,109.27 33,539.89 84,343.53 722,253.43
4,636.19 14,959.53 2,208.31 53,413.00 75,217.03783.00 218,908.13 219,243.10 2,905.37 15,102.73 456,942.33
117,222.87 110,421.94 2,521.20 26,850.26 257,016.279,078.21 644,732.72 636,733.84 41,174.77 179,709.52 1511,429.06
(1,058,000.00)
453,429.06
70-0651 70-0652 70-0653 70-0654 70-0655 IQIAI.4,052.71 18,398.66 18,163.90 22,188.89 35,971.90 98776.06
.- 177,635.66 334,498.86 22,154.71 174,370.84 708,660.0758.48 9,283.38 28,080.59 55.68 872.66 38,350.79
837.00 19,050.83 19,050.83 13,588.78 2,289.53 54,816.97- (4,909.04) (4,838.82) 1,744.26 333.48 (7,670.12)
14,810.09 11,648.34 7,783.00 1,500.00 101,575.00 137,316.4378.00
--
- - 78.00506.12
- -- - 506.12
--
- 2,250.00 2,250.007,821.22 72,017.44 63,987.69 6,317.02 25,439.45 175,582.821,825.00 387.50 387.50
- - 2,600.0020,866.11 - -
- - 20,866.1153,106.40 1,263.50
-- - 54,369.90
- 53,731.95 60,562.96 4,967.00 39,996.50 159,258.411,962.40 79,023.18 61,799.43 12,288.83 39,466.37 194,540.21
105,923.53 437,531.40 589,475.94 84,805.17 422,565.73 1,640,301.77
70-0651 70-0652 70-0653 70-0654 70-0655 IQIJ.291,589.27 84,343.53 375,932.80
4,636.19 14,959.53 2,208.31 53,413.00 75,217.031,045.00 1,045.00 189.35 2,279.35
- 5,681.19 307,593.80 2,397.66 137,756.53 453,429.18
TOTAL FOR LOAN CONSIDERATION 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL00-0 Labor 4,052.71 18,398.66 309,753.17 22,188.89 120,315.43 474,708.8601-0 Materials - 177,635.66 334,498.86 22,154.71 174,370.84 708,660.0702-0 Freight 58.48 13,919.57 43,040.12 2,263.99 54,285.66 113,567.82
03-004-005-006-007-008-009-015-020-050-052-054-0
Equip Rent-OthersEquip Rent-NJUSServicesLegalPermitsInspectionSuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew
GEN/ENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655
837.00 20,095.83 20,095.83 13,778.13 2,289.53- (4,909.04) (4,838.82) 1,744.26 333.48
14,810.09 11,648.34 7,783.00 1,500.00 101,575.0078.00 -
- -
506.12 - - - -
--
- 2,250.007,821.22 72,017.44 63,987.69 6,317.02 25,439.451,825.00 387.50 387.50 - -
20,866.11-
53,106.40 1,263.50 - -
- 53,731.95 60,562.96 4,967.001,962.40 79,023.18 61,799.43 12,288.83
105,923.53 443,212.59 897.069,74 87,202.83
DRiNKING WATERCLEAN WATER
TOTAL57,096.32(7,670.12)
137,316.4378.00
506.122,250.00
175,582.822,600.00
20,866.1154,369.90
159,258.41194,540.21
2,093.730.95
39,996.5039,466.37
560.322,26
52,961.77 443,212.59 87,202.83 280,161.13 863,538.3252,961.76 897,069.74 280,161.13 1,230,192.63
105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95
GEN/ENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL
GEN/ENG WATER SEWER FIRE HYD SVC LINESSORTED BY DEC LOAN CLASS 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL DEC LOAI\j C20-0 Interest 1 20,866.11 - - -
- 20,866.11 23856
50-0 CE2 Engineering 2 53,106.40 1,263.50 - - - 54,369.90 54,359
06-0 Legal 3 78.00 --
- 78.0007-0 Permits 3 506.12
-
- 506.1208-0 Inspection 3
- 2,250.00 2,250.0015-0 Surveying 3 1,825.00 387.50 387.50 - 2,600.0052-0 CE2 Const Mgmt 3 - 53,731.95 60,562.96 4,967.00 39,996.50 159,258.4154-0 CE2 Core Crew 3 1,962.40 79,023.18 61,799.43 12,288.83 39,466.37 194,540.21 359232
01-0 Materials 4 - 177,535.66 334,498.86 22,154.71 174,370.84 708,660.0702-0 Freight 4 58.48 13,919.57 43,040.12 2,263.99 54,285.66 113,567.8203-0 Equip Rent-Others 4 837.00 20,095.83 20,095.83 13,778.13 2,289.53 57,096.3204-0 Equip Rent-NJUS 4 - (4,909.04) (4,838.82) 1,744.26 333.48 (7,670.12)05-0 Services 4 14,810.09 11,648.34 7,783.00 1,500.00 101,575.00 137,316.4309-0 Supplies 4 7,821.22 72,017.44 63,987.69 6,317.02 25,439.45 175,582.8200-0 Labor 4 4,052.71 18,398.66 309,753.17 22,188.89 120,315.43 474,709.86 1,659,262
105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95 2,093,730
GEN/ENG WATER SEWER FIRE HYD SVC LINESDRINKING WATER 70-0651 70-0652 70-0654 70-0655 IPL DEC LO i C20-0 Interest 1 10,433.05 -
-- 10,433.05 10,33
50-0 CE2 Engineering 2 26,553.20 1,263.50-
- 27,816.70 27,816
06-0 Legal 3 39.00 --
- 39.0007-0 Permits 3 253.06
-- 253.06
08-0 Inspection 3 --
- 1,125.00 1,125.0015-0 Surveying 3 912.50 387.50
-- 1,300.00
52-0 CE2 Const Mgmt 3 - 53,731.95 4,967.00 19,998.25 78,697.2054-0 CE2 Core Crew 3 981.20 79,023.18 12,288.83 19,733.18 112,026.39 193,440.
01-0 Materials 4 - 177,635.66 22,154.71 87,185.42 286,975.7902-0 Freight 4 29.24 13,919.57 2,263.99 27,142.82 43,355.6203-0 Equip Rent-Others 4 418.50 20,095.83 13,778.13 1,144.77 35,437.2304-0 Equip Rent-NJUS 4 - (4,909.04) 1,744.26 166.74 (2998.04)05-0 Services 4 7,405.05 11,648.34 1,500.00 50,787.50 71,340.8909-0 Supplies 4 3,910.61 72,017.44 6,317.02 12,719.73 94,964.8000-0 Labor 4 2,026.36 18,398.66 22,188.89 60,157.72 102,771.63 631,847.
52,961.77 443,212.59 - 87,202.83 280,161.13 863,538.32 863,538.
GEN/ENG WATER SEWER FIRE HYD SVC LINESCLEAN VLAT 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL DEC LOAN Ci20-0 Interest 1 10,433.06
-
- 10,433.06 10,433.
50-0 CE2 Engineering 2 26,553.20-
- 26,553.20 26,553.
06-0 Legal 3 39.00-
- 39.0007-0 Permits 3 253.06
- 253.0608-0 Inspection 3 - 1,125.00 1,125.0015-0 Surveying 3 912.50 387.50
- 1,300.0052-0 CE2 Const Mgmt 3 - 60,562.96 19,998.25 80,561.2154-0 CE2 Core Crew 3 981.20 61,799.43 19,733.19 82,513.82 165,792.
01-0 Materials 4 - 334,498.86 87,185.42 421,684.28
GENJENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL02-0 Freight 4 29.24 43,040.12 27,142.84 70,212.2003-0 Equip Rent-Others 4 418.50 20,095.83 1,144,76 21,659.0904-0 Equip Rent-NJUS 4 - <4,838.82) 166.74 (4,672.08)05-0 Services 4 7,405.04 7,783.00 50,787.50 65,975.5409-0 Supplies 4 3,910.61 63,987.69 12,719.72 80,618.0200-0 Labor 4 2,026.35 309,733.17 60,157.71 371,937.23 1,02741
52,961.76 - 897,069.74 - 280,161.13 1,230,192.63 i9
DRINKING WATER 52,961.77 443,212.59 87,202.83 280,161.13 863,538.32CLEAN WATER 52,961.76 897,069.74 280,161.13 1,230,192.63105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95
Application Amend Available Add 5th Qv rINTENDED USE PLAN PROJECTS LISTEDDrinking Water 2,690,000 700,000 1,990,000 863,538.32 i,1)6t 6:Clean Water 2,340,000 600,000 1,740,000 1,230,192.63 509g0
5,030,000 1,300,000 3,730,000 2,093,730,95 1636,:Gc
Amend Add 5th Intal LoanDrinking Water 2,690,000 200,000 863,538.32 ] 563,53832 (1,126,461.68)Clean Water 2,340,000 600,000 J.,230,192.63 ,830,192.63 (509,807.37)
5,030,000 1,300,000 2,093 730.95 3,393,73095 (1,636,269.05)
20 yrs 65,000.00 [‘i04,686.55 169,686.55 2,093,730.951230 customers 50.78 81.79 132.57Per Month 4.23 6.82 11.05
30 yrs 43,333.33 69,791.03 113,124.371280 customers 33.85 54.52 88.38Per Month 2.82 4.54 7.36
USDA EXPECTED Grant 1,075,000.00Loan 308,000.00 Pay x 40 yrs 59,242.40 includes interest @ 3.75%
1,383,000.00 SLA Asset Require 173,017.00232,259.40
ST
5TH
AV
E-2
011
PR
INPR
#1A
Pin
PR#1
Mat
chT
otal
USD
A+
DE
C62
766
DE
C62
766.
US
DA
-li
USD
A-1
2A
bove
Ava
ilM
atch
(USD
A)
(USD
A)
Abo
vA
vail
PR
#i
Net
ofM
atch
07.6
51E
ng/G
en12
,293
.60
942.
0093
.00
13,3
28.6
09,
078.
219,
078.
2107
.652
Wtr
mai
n15
0,51
8.06
52,7
27.9
399
,889
.20
5,68
1.1
930
8,81
6.38
644,
732.
7263
9,05
1.53
07.6
53S
wrm
ain
333,
000.
4219
,575
.46
96,8
13.4
316
,004
.53
292,
109.
2775
7,50
3.11
636,
733.
8432
8,62
0.04
07.6
54F
ire
Hyd
24,4
39.9
112
,317
.50
10,9
11.8
32,
397.
6650
,066
.90
41,1
74.7
738
,777
.11
07.6
55S
vcL
ines
303,
107.
6021
,830
.26
56,2
39.6
153
,413
.00
84,3
43.5
351
8,93
4.00
179,
709.
5341
,953
.00
823,
359.
5910
7,39
3.15
263,
947.
0777
,496
.38
376,
452.
801,
648,
648.
991,
511,
429.
071,
057,
479.
8993
0,75
2.74
453,
949.
1813
84,7
01.9
2(5
20
0)
520.
0045
3,42
9.18
1,05
7,99
1,38
3,00
0.00
(1,7
01.9
2)(1
,181
.92)
(520
.00)
3DA
anti
cipa
ted
part
icip
atio
nbo
oked
rece
ivab
le1,
383,
000.
00ov
eA
vail
able
263,
947.
071
,646
,94
77
(1,7
01.9
2)st
saf
ter
7/16
/12
reco
ncil
e46
,284
.14
1,69
3,23
1.21
)nst
ruct
ion
Loa
nIn
tere
st20
,866
.11
‘anc
eth
roug
hD
EC
Loa
ns1,
714,
097.
32
____
____
____
____
____
____
____
____
____
___
USD
AO
rigi
nal
OW
CW
SLA
Res
erve
290,
833
37.6
51E
ng/G
en13
,328
.60
1,95
7.00
20,8
66.1
136
,151
.71
18,0
75.8
618
,075
.85
Ope
rati
ngR
eser
ve
377,
196
37.6
52W
trm
ain
308,
816.
3830
8,81
6.38
308,
816.
3866
8,02
937
.653
Sw
rmai
n75
7,50
3.11
757,
503.
1175
7,50
3.11
Per
Cus
tom
er51
5.45
37.6
54Fi
reH
yd50
,066
.90
21,0
68.2
171
,135
.11
71,1
35.1
1P
erC
ustl
Mo
42.9
5)7
,655
Svc
Lin
es51
8,93
4.00
23,2
58.9
354
2,19
2.93
271
,096
.47
271,
096A
61,
648,
648.
9946
,284
.14
20,8
66.1
11,
715,
799.
2466
9,12
3.82
1,04
6,67
5.42
1,70
1.92
USD
AR
evis
edA
nnua
lE
stC
usto
mer
s1,
296
Mon
thU
SDA
SLA
Res
erve
Req
uire
173,
017
Tot
al1,
715,
000
1,32
3P
erC
usto
mer
133.
5020
yrs
85,7
5066
5.51
Per
Cus
tlM
o11
.13
3oyrs
57,1
6744
3.68
USD
A30
8KL
oan
-40
yrs
15,0
63E
st@
DE
Cgr
t2,
302,
000
(mt
288K
)11
.62
Est
@U
SDA
2,44
1,00
00.
97E
st@
Con
st2,
989,
000
alC
ost
3,15
1,73
1-G
rant
EngI
Mtls
2A
6,73
0,00
0
28T
otat
6,51
0,00
013
,240
,000
MM
G
Mat
ch
45%
3,00
0,00
0
55%
3,73
0,00
0
6,73
0,00
0
70%
4,55
7,00
0
30%
1,95
3,00
0
6,51
0,00
0
7,55
7,00
057
%
5,68
3,00
0
13,2
40,0
00
DW
Cw
Tot
at
1,99
0,00
0
1,74
0,00
0
3,73
0,00
0
Sub
%D
raw
50%
1,99
0,00
0
10%
1,74
0,00
0
3,73
0,00
0
EPA
769,
800
4,49
9,80
0
1,18
3,20
0
5,68
3,00
0(7
69,8
00)
4,91
3,20
0
(1,1
75,0
00)
3,73
8,20
0
28%
995,
000
180,
000
8,73
2,00
0
769,
800
9,50
1,80
0
9,50
1,80
013
,240
,000
72%
336,
500
247
Mat
ch
DEC
Loa
nsEP
AG
rant
Add
edM
atch
Req
uire
d
5,68
3,00
0(3
,730
,000
)(7
69,8
00)
1,18
3,20
0
325,
500
239
662,
000
486
EAST
SCLA
IRC
OR
ER
EPLA
CEM
ENT
-PH
ASE
2
2014
IUP
43%
7,55
7,00
0
Sub
sidy
Net
995,
000
995,
000
180,
000
1,56
0,00
0
1,17
5,00
02,
555,
000
Add
itio
nal
Mat
ch EPA
1361
2018
6,91
0
137
11.4
4 7R
es
NOME JOINT UTILITY SYSTEMEAST SCLA)RCORE REPLACEMENT
PHASE 2
Phase 2A 28 TotalProject Total Estimate 6,730,000 6,510,000 13,240,000
MMG 3,000,000 45% 4,557,000 70% 7,557,000 57%Match 3,730,000 55% 1,953,000 30% 5,683,000 43%
6,730,000 6,510,000 13,240,000
Total Match Required 5,683,000
Funding Sources:
Loan TotalEXISTING LOANS
SFY 2014 Amendwith
IUP Request
________________________________ ___________ ____________
Amendment
Drinking Water #627161 1,990,000 700,000 2,690,000
Clean Water p627141 1,740,000 600,000 2,340,000
3,730,000 1,300,000 5,030,000
EPA STAG 769,800
4,499,800
Additional Unmet Match Requirement 1,183,200Contingency 10% 118,320
1,301,520
/jkh08/12/14
NOME JOINT UTILITY BOARDMeeting Date: September 16, 2014
NJUS
Sclaircore Replacement — Phase II; ADEC Drinking Water & Clean Water Loan AmendmentsResolutions 14-07 & 14-08
NJUS applied for two municipal matching grants (MMGs) for Sclaircore Replacement Phase 2,for two phases to replace water-sewer utilities in the east quadrant of town, from Front to 6Ibetween N and K streets. The State awarded funding for Phase 2A in the amount of $3.OMMand Phase 2B in the amount of $4.557MM, the total of which represented 57% of the project.(Nome is eligible for up to 70% match, but in our initial application DEC limited the award to$3.OMM-typically their grant limit (only 45%), although we were successful in making the casefor 70% funding in the second application.
Concurrent with the initial MMG application, the Utility submitted loan questionnairesequivalent to the amount of Phase 2A to be considered for funding under the Alaska DrinkingWater and Clean Water Loan Programs. These questionnaires successfully rated and wereincluded in the respective program’s Intended Use Plans (IUP). The Drinking Water Fund loanof $1,990,000 included a 50% subsidy (loan forgiveness) component. The Clean Water Fundloan of $1,740,000 included approximately 10% subsidy.
NJUS continued to seek out additional potential funding from federal sources to provideadditional matching funds for Phase 2B. We were not successful in our quest with USDA duringthis round, but did capture $769,800 in EPA funding for the project. This left a residual fundingneed of $1.2MM to fully match the state grants.
ADEC was contacted and will amend the existing drinking water and clean water loans for Phase2 to provide the additional match funding required.
When considering the amount of subsidy (loan forgiveness) and the EPA funding used, the netresult raises the grant percentage from 57% to 72% of the projects.
Recommended action:
That Resolutions 14-07 and 14-08 be adopted, amending the Phase 2 ADEC Drinking Water andClean Water Loans to provide the additional matching funds required as match to awardedmunicipal matching grants. This funding mechanism was discussed previously and the addeddebt service requirement was considered during the rates adjustment implemented earlier thisyear.
i. Handeland09/15/14
Presented By:Utility ManagerAction Taken:
No°Abstain.
CITY OF NOME, ALASKA
RESOLUTION NO. R-14-lo-oz
A RESOLUTION APPROVING & ACCEPTING AN AMENDED LOAN FROM THEALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKA
DRINKING WATER FUND TO PROVIDE FINANCING FOR IMPROVEMENTS TOCOMMUNITY WATER INFRASTRUCTURE
WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,
WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to 20 years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,
WHEREAS, by Resolution R-13-o5-oz, as recommended by Nome Joint Utility BoardResolution 12-04, a loan was authorized for Project #6z7161 — East Nome Water Replacement —
$1,990,000, ofwhich $995,000 was subsidized (converted to a grant); and,
WHEREAS, the initial loan was made to provide partial funding for Sclaircore ReplacementPhase iA, additional federal funds were awarded, and the existing loan only partially matches stategrants for Phase 2B, and the State is willing to amend the loan to provide additional funding to fullymatch the existing municipal matching grant for completion of Phase 2B;
NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan amended ADEC Drinking Water Fund Loan for the construction of water system improvementsfor a new total of $2,690,000 (of which $995,000 has been subsidized) with a 20 year payback at 1.5%interest, as recommended by Nome Joint Utility Board Resolution i-o7, and authorizes the UtilityManager as Chief Operating Officer of the Utility to execute any and all documents that may berequired by the Department to reflect the indebtedness, the terms of its repayment, and any securitythereof, including but not limited to an agreement for the loan and a promissory note.
APPROVED and SIGNED this j3t1 day of
ATTEST: .
TOM M RAN, Clerkf/If
DENISE MICHELS,
NOME JOINT UTILITY SYSTEM
NOME JOINT UTILITY BOARD
RESOLUTION 14-07
A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTAN AMENDMENT TO A LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL
CONSERVATION ALASKA DRINKING WATER FUND TO PROVIDE LOAN FINANCING FORIMPROVEMENTS TO COMMUNITY WATER INFRASTRUCTURE
WHEREAS, The Utility Board determined application should be submitted toDepartment of Environmental Conservation Drinking Water Fundfinance various infrastructure improvements constructed to the watersystems, including replacements, extensions and enhancements; and,
the AlaskaProgram toand sewer
WHEREAS,
WHEREAS,
WHEREAS,
the Alaska Department of Environmental Conservation Alaska Clean Water &Alaska Drinking Water Fund loan programs offers terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems; and
NJUS submitted annual questionnaires to be included on the Intended Use Plansfor these ADEC programs, application was made, and ADEC provided an initialloan Project #627161 — East Nome Water Replacement — $1,990,000. Of thisamount, $995,000 was eligible for subsidy (repayment assistance) and convertedto a grant); and,
the initial loan application was made to provide partial funding for SclaircoreReplacement Phase 2A, additional federal funding was awarded, and the existingloan only partially matches state grants for Phase 2B, and the State is willing toamend the loan to provide additional funding to fully match the existing municipalmatching grant for completion of Phase 28;
NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and authorize acceptance of additional $700,000, amending the existingADEC Drinking Water Fund Loan #627161, for the construction of water system improvements for anew total of $2,690,000 (of which $995,000 has been subsidized) with a 20 year payback at 1.5%interest, and authorize the Utility Manager as Chief Operating Officer of the Utility to execute anyand all documents that may be required by the Department to reflect the indebtedness, the terms ofits repayment, and an security thereof, including but not limited to an agreement for the loan and apromissory note.
SIGNEDTHIS JL DAYOF
___________
2014 AT NOME, ALASKA.
I1,-oVBerda Willson, ChairmanNOME JOINT UTILITY BOARD
avid Barron, ryNOME JOINT UTILITY BOARD
Presented By:Utility ManagerAction Taken:
YesNo
Abstain
CITY OF NOME, ALASKA
RESOLUTION NO. R-13-o5-02
A RESOLUTION APPROVING & ACCEPTING A LOAN FROM THE ALASKADEPT. OF ENVIRONMENTAL CONSERVATION ALASKA DRINKING WATER FUND
TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TOCOMMUNITY WATER INFRASTRUCTURE
WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,
WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to zo years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,
WHEREAS, application was made and ADEC is prepared to enter in to an Agreement forProject #627161 — East Nome Water Replacement — $1,990,000, of which up to $995,000 15 eligible forsubsidy (repayment-conversion to a grant), and by Resolution 12-04 the Nome Joint Utility Systemrecommends the loan be accepted; and,
NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan ADEC Drinking Water Fund Loan for the construction of water system improvements in theamount of $1,990,000 with a 20 year payback at 1.5% interest, and authorizes the Utility Manager asChief Operating Officer of the Utility to execute any and all documents that may be required by theDepartment to reflect the indebtedness, the terms of its repayment, and any security thereof,including but not limited to an agreement for the loan and a promissory note.
APPROVED and SIGNED this 13th day of May,
__
LDISE MICHft. yIayor
fl//_Z:—)\J\__
TOM MORAN, Clerk
NOME JOINT UTILITY SYSTEM
NOME JOINT UTILITY BOARD
RESOLUTION 12-04
A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTA LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKADRINKING WATER FUND TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TO
COMMUNITY WATER INFRASTRUCTURE
WHEREAS, The Utility Board determined application should be submitted to the AlaskaDepartment of Environmental Conservation Drinking Water Fund Program torefinance various infrastructure improvements constructed to the water and sewersystems, including replacements, extensions and enhancements; and,
WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water &Alaska Drinking Water Fund loan programs with terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems and NJUS submitted annual questionnaires to beincluded on the Intended Use Plans for these ADEC programs; and,
WHEREAS, Application was made and ADEC is prepared to enter in to an Agreement forProject #627161 — East Nome Water Replacement — $1,990,000. Of this amount,up to $995,000 is eligible for subsidy (repayment-conversion to a grant).
NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and accept an ADEC Drinking Water Fund Loan for the construction ofwater system improvements in the amount of $1,990,000 with a 20 year payback at 1.5% interest,and authorize the Utility Manager as Chief Operating Officer of the Utility to execute any and aHdocuments that may be required by the Department to reflect the indebtedness, the terms of itsrepayment, and an security thereof, including but not limited to an agreement for the loan and apromissory note.
SIGNED THIS DAY OF I , 2012 AT NOME, ALASKA.
4(‘. /
‘— /: tdBerda J. WiIIson ChairmanNOME JOINT UTILITY BOARD
ATTET— ;;—
David Barron, SecretaryNOME JOINT UTILITY BOARD