22
Presented By: Utility Manager Action Taken: Yes No2 Abstain_tL CITY OF NOME, ALASKA RESOLUTION NO. R-15-ol-o3 A RESOLUTION APPROVING & ACCEPTING A LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKA DRINKING WATER FUND TO PROVIDE FINANCING FOR IMPROVEMENTS TO COMMUNITY WATER INFRASTRUCTURE WHEREAS, the Nome Joint Utility Board determined application should be submitted to the Alaska Department of Environmental Conservation Drinking Water Fund Program to finance various infrastructure improvements to water and sewer systems, including replacements, extensions and enhancements; and, WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water & Alaska Drinking Water Fund loan programs with terms up to 20 years with no prepayment penalties to provide low interest (1.5%) financing to communities for water and sewer systems and NJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADEC programs; and, WHEREAS, by Resolution R-1 4 -lo-o2, which amended Resolution R-1 3 -o 5 -o2, a loan amendment was authorized for Project #627161, to provide additional match funding for Sclaircore Replacement Phase ; and, WHEREAS, Sclaircore Replacement Phase i requires funding to match municipal matching grants for East 5 th Avenue construction, and ADEC recommended combining the initial loan amendment with the additional required match, for a total of $1,563,6oo; and, NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and accepts an ADEC Drinking Water Fund Loan for the construction of water system improvements for a new total of $1,563,600, with a 20-year payback at i.% interest, as recommended by Nome Joint Utility Board Resolution ‘4-17, and authorizes the Utility Manager as Chief Operating Officer of the Utility to execute any and all documents that may be required by the Department to reflect the indebtedness, the terms of its repayment, and any security thereof, including but not limited to an agreement for the loan and a promissory note. APPROVED and SIGNED this 12 th day of January, 2015. DENISE MICHELS,

RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

Presented By:Utility Manager

Action Taken:YesNo2

Abstain_tL

CITY OF NOME, ALASKA

RESOLUTION NO. R-15-ol-o3

A RESOLUTION APPROVING & ACCEPTING A LOAN FROM THE ALASKA DEPT. OFENVIRONMENTAL CONSERVATION ALASKA DRINKING WATER FUND TO

PROVIDE FINANCING FOR IMPROVEMENTS TO COMMUNITY WATERINFRASTRUCTURE

WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,

WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to 20 years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,

WHEREAS, by Resolution R-14-lo-o2, which amended Resolution R-13-o5-o2, a loanamendment was authorized for Project #627161, to provide additional match funding for SclaircoreReplacement Phase ; and,

WHEREAS, Sclaircore Replacement Phase i requires funding to match municipal matchinggrants for East 5th Avenue construction, and ADEC recommended combining the initial loanamendment with the additional required match, for a total of $1,563,6oo; and,

NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan ADEC Drinking Water Fund Loan for the construction of water system improvements for a newtotal of $1,563,600, with a 20-year payback at i.% interest, as recommended by Nome Joint UtilityBoard Resolution ‘4-17, and authorizes the Utility Manager as Chief Operating Officer of the Utilityto execute any and all documents that may be required by the Department to reflect theindebtedness, the terms of its repayment, and any security thereof, including but not limited to anagreement for the loan and a promissory note.

APPROVED and SIGNED this 12th day ofJanuary, 2015.

DENISE MICHELS,

Page 2: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

ATTEST:

TOM MORAN, Clerk

Page 3: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY SYSTEM

NOME JOINT UTILITY BOARD

RESOLUTION 14-17

A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTA LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKADRINKING WATER FUND TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TO

COMMUNITY WATER INFRASTRUCTURE

WHEREAS, The Utility Board determined application should be submitted to the AlaskaDepartment of Environmental Conservation Drinking Water Fund Program tofinance various infrastructure improvements constructed to the water and sewersystems, including replacements, extensions and enhancements; and,

WHEREAS, the Alaska Department of Environmental Conservation Alaska Clean Water &Alaska Drinking Water Fund loan programs offers terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems; and

WHEREAS, NJUS submitted annual questionnaires to be included on the Amended IntendedUse Plans for the ADEC Drinking Water Loan program. ADEC has completed thepublic notice process and has included funding for East Nome Water Replacement— $2,690,000, and intends to offer NJUS a loan of up to that amount; and,

WHEREAS, initial loan applications made to provide partial funding for Sclaircore ReplacementPhase 2A, additional federal funding was awarded, and the existing loan onlypartially matches state grants for Phase 2B, and Sclaircore Replacement Phase I(East 5 Avenue) requires funding to match municipal matching grants forcompletion of Phase 28 and Phase I (East 5th Avenue) — for a total of $1,563,600;

NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and authorize acceptance of a loan for $1,563,600 through the ADECDrinking Water Fund Loan Program for construction of water system improvements with a 20 yearpayback at 1.5% interest, and authorize the Utility Manager as Chief Operating Officer of the Utilityto execute any and all documents that may be required by the Department to reflect theindebtedness, the terms of its repayment, and an security thereof, including but not limited to anagreement for the loan and a promissory note.

SIGNED THIS I DAY OF &vY bel , 2014 AT NOME, ALASKA.

Berda Wilison, ChairmanATTEST: NOME JOINT UTILITY BOARD

David Barron, SecretaryNOME JOINT UTILITY BOARD

Page 4: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

‘7

:

ill

ALASKA DRINKING WATER FUND

STATE WATER LOAN PROGRAM

INTENDED USE PLAN - AmendedFINAL

FFYI4 Grant Allotment

State Fiscal Year 2015

IIIi‘[I

III

J

llSubmitted to the U.S. Environmental Protection Agency

ByAlaska Department of Environmental Conservation

Division of WaterDecember 2014

I

Page 5: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

AL

ASK

AD

RIN

KIN

GW

AT

ER

FUN

DF

undi

ngP

rior

ity

Lis

t-

Am

ende

dF

isca

lY

ear

2015

Ráñ

ksá

árC

rnrn

unit

::o

m.:

iibn

cW

ater

$te

flID

#.:

.:$

àt1

6fl

)

.........................................................

-.•

.••

...

Gre

en...

.A

ssIs

tnce

Frn

anc

term

Pro

ject

Pro

Ject

Co

nst

ruct

ion

Sust

aInab

hty

_______

__

__

__

__

__

__

Pfo

ject

Des

crip

t,on

Am

ountZ

Rat

e(Y

rsS

ub

s1d

yA

mount

Sta

rtP

OI,

C9

AK

2211

229

Tre

atm

ent

Plan

tU

pgra

deT

he

proj

ect w

illre

habi

litat

eth

efa

iling

Cre

eIoo

odPa

rksu

rfac

ew

ater

(35Q

\&

Res

ervo

irtr

eatm

ent

syst

emne

arW

asill

a.W

ork

incl

udes

impr

ovem

ents

and

purc

hase

of$5

05,5

771.

50%

20$3

79,1

838/5

/2014.

Fix

itFi

rst

‘I

Con

stru

ctio

n[t

hesy

stem

,an

dco

nstr

uctio

nof

are

serv

oir.

A23

4001

0R

epla

cefa

ihng

wa

erse

airi

ppin

gal

ong

Dpo

riSt

i’ee

tK

ing

Plac

eW

arre

nN

ome

ircor

eP

Iae

and

Spo

kane

Stre

etw

thne

wdi

fect

hwy

arct

icpi

pe.

Ela

mna

tloil

ofpi

pe$2

92,3

0G1

50%

20*1

,389

,817

$2,9

20,3

00EN

G-E

C5/1

5/2

504.

FIx

itFi

rst

ePla

cem

efa

ilure

l&1

will

prov

ide

ener

gysa

ving

s.

AK

2211

821

Spen

ard

Hei

ghts

Des

ign

and

cons

truc

tion

offi

hrat

ion

impr

ovem

ents

tore

duce

arse

nic

leve

ls,

$312

800

01.

50%

20$3

128

000

ENG

-BC

5/15

/201

5Fi

xit

Firs

t(1

00)

lDls

trlb

utlo

nSy

stem

and

repl

acin

gen

dof

life

galv

aniz

edw

ater

lines

with

new

lines

.

AX

2110

643

Salm

onC

reek

.Sec

onda

The

asse

ssm

ent

ofle

vee

0di

sinf

ectio

nre

quir

edfa

cilit

ype

miit

bng

and

the

desi

gean

dco

nstru

ctio

nof

asec

orid

ary

disi

nfec

tion

proc

ess

atth

eSa

lmon

$4t)

0O00

150%

2G3/

1]20

15ft

xit

Frs

tC

reek

Wat

erT

reat

men

tFa

cilit

y

AK

2213

001

Res

urre

ctio

nD

rive

Wat

erR

ehab

ilita

teor

repl

ace

appr

oxim

atel

y53

1lin

ear

feet

of8-

inch

duct

ileiro

npi

pe75

000

01

50%

205

914.

Fit

F(2

91,8

26)

Reh

abil

itat

ion.

with

inR

esur

rect

ion

Driv

efr

omT

ikis

hla

Str

eett

o79

41R

esur

rect

ion

Driv

e.$

‘.

/2/

ixirs

AK

2213

001

Rep

lace

exis

ting

faih

nwat

erm

ain

riO

erra

hS

tree

t fro

mFi

rew

eed

l.as

eto

7115

114e

Fix

itFi

rst

Fir

ewee

d.

AK

2226

020

Palm

erSt

eel

Wat

erM

ain

Rep

lace

old

stee

lw

ater

pipe

inth

eno

rthe

aste

rnar

eaof

the

City

ofPa

lmer

.28

571

41

202

50

000

ENG

-BC

61

2015

F(5

937)

Rep

lace

men

t1

know

nas

the

“She

rrod

”ar

ea.

.0

//

lxi

1Su

bsid

yfu

ndin

gfo

rth

eN

ome-

Nom

eSc

lair

coro

Rep

lace

men

t-Ph

IIIpr

ojec

tis

limite

dto

avai

labl

esu

bsid

yfu

nds.

Add

ition

ally

,fu

llpr

ojec

tfun

ding

ofth

ePa

lmer

-Pa

lmer

Stee

lWat

erM

ain

Rep

lace

men

tpr

ojec

twill

bede

pend

ent

upon

rem

aini

ngav

aila

ble

loan

fund

s.T

heD

epar

tmen

twi

llne

gotia

tew

ithPa

lmer

topr

ovid

ead

ditio

nalf

unds

asth

eybe

com

eav

aila

ble

late

rin

the

year

.2T

ota

lav

aila

ble

proj

ect

loan

fund

ing

and

subs

idy

unde

rth

isA

men

ded

IUP

is$1

3062

573

and

$1,7

69,0

00,

resp

ectiv

ely.

3Cri

teri

afo

rbe

ing

elig

ible

for

alo

ansu

bsid

ym

aybe

refe

renc

edon

page

13un

der

the

narr

ativ

ese

ctio

nof

the

PUP.

Proj

ects

whi

chde

mon

stra

tead

equa

tecr

iteri

afo

rm

eetin

ga

Gre

enpr

ojec

tcom

pone

ntwi

llbe

elig

ible

tore

ceiv

ean

addi

tiona

l25

poin

ts.

Gre

enPr

ojec

tR

eser

veC

ateg

ory

Typ

e:G

IF-

Gre

enIn

fras

truc

ture

,W

rR-

Wat

erEf

ficie

ncy,

EN

G-

Ene

rgy

Effic

ienc

y&

LIN

-E

nvir

onm

enta

llyIn

nova

tive.

Gre

enPr

ojec

tJus

tific

atio

nTy

pe:

BC

-B

usin

ess

Cas

e!C

AT

-C

ateg

oric

al.

6Pr

ior

tofu

ndin

gan

ypr

ojec

tsho

wn

toha

vea

fund

ing

subs

idy

for

Gre

en,

aB

usin

ess

Cas

efo

rpr

ojec

tG

reen

elig

ibili

tym

ust

befo

und

just

ifie

d.

Sus

tain

abil

ity

Pol

icy.

“Fix

itF

irst

-fix

exis

ting

criti

cal

infr

astr

uctu

re;

“Im

prov

eTF

M”

-im

prov

ete

chni

cal,

finan

cial

and

man

ager

ial

capa

city

ofth

esy

stem

;an

d,“P

lann

ing

-pl

anni

ngan

dde

velo

pmen

tof

alte

rnat

ive

proj

ects

that

refl

ectt

hefu

lllif

ecy

cle

cost

ofin

fras

truc

ture

.65

poin

tsar

eon

lyaw

arde

dif

afe

asib

ility

orde

sign

stud

yha

sbe

enco

mpl

eted

for

the

pre

ct

byth

een

dof

the

ofqu

estio

nnai

reso

licita

tion

perio

d.

3 4 5

.6

.

7

216

ALP

AT+

201

No

nie

200

Spen

ard

Hei

ghts

Wat

er

•jneau

176

Anc

hora

ge

‘171

:..

Aii

chtl

taei

156

Pal

mer

•D

isad

vant

age

Com

mun

ity(c

rite

ria

may

bere

fere

nced

onpa

ge13

)

•E

quiv

alen

cyPr

ojec

t(c

rite

ria

may

bere

fere

nced

onpa

ge12

)

•E

xtra

50po

ints

for

cons

truc

tion

star

tby

Sep

tem

ber

15,

2014

8

Tot

alR

eque

sted

Am

ount:

I$t4

08959t:

]

Tot

alSu

bsid

ized

Am

ount

3:I$

1,76

9i..:

.:IT

otal

Equ

ival

ency

Am

ount

: [*

:9,6

75,8

TzI

Tot

alG

reen

Am

ount

:$:

.:6,2

98

DW

Prio

rity

List

App

endi

xV

aA

men

ded

IUP

-FI

NA

L

Page 6: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

AL

ASK

AD

RIN

KIN

GW

AT

ER

FUN

DF

undi

ngP

rior

ity

Pla

nnin

gL

ist

-A

men

ded

Fis

cal

Yea

r20

15

Wat

erM

ain

Rep

iace

men

d

AK

2120

323

Cha

tham

Ave

nue

Wat

er(8

,050

)M

ain

Rep

lace

men

t

AK

2120

3231S

ctio

enba

rR

oad

Wat

er

AK

2110

643

Las

tC

hanc

eB

asin

Wel

l

(31,

275)

Fiel

dC

apac

ity:Im

PrO

Ver

Tief

lts•

0347

Zon

eC

onve

rsio

n•

(291

843

0Z

one

Con

vers

ion.

‘eda

ceap

prox

.330

0oA

CptO

(YofD

Ppip

ew

1th

C-9

00(V

Con

gnaI

lTra

cts

Psi

Vie

wSt

Firs

tAve

Nor

thar

idFr

ontS

t.

epla

cem

ent

ofth

eex

istin

gag

ing/

faili

ngw

ater

syst

emw

ithin

DeG

roff

Str

eet

)etw

een

Saes

nill

Cre

ekR

oad

and

Lake

Stre

et.

epla

cern

ent

ofap

pro

xra

tely

4000

feet

ofw

ater

pipi

ngw

itlur

ith

eEg

ari

rrye

corr

idor

betw

een

Ten

thS

tree

tan

dM

ain

Str

eet,

eev

alu

ate

wat

erpr

ojec

tsrs

tthan

upda

ted

mas

ter

plan

:co

nduc

thy

drol

ogic

rtud

ies;

deve

lop

new

wat

erso

urce

sdo

wnt

own

and

atth

ela

ndfil

l;an

dup

grad

eN

ater

dist

ribu

tion

pipi

ngin

clud

ing

met

ers

and

leak

dete

ctio

n.

epla

cen

ien

tof

feti

ngdu

ctil

eIr

onI-

lOPE

pip

ing

incn

tlcal

area

shr

ough

out t

hew

ater

syst

em

Inst

all4

91-l

inea

lfee

tof

8”H

OPE

wat

erm

ains

,(2

)fir

ehy

dran

ts,

and

(14)

rerv

ices

inst

alle

dto

the

edge

ofth

erig

ht-o

f-w

ay,

inap

prox

imat

ely

5.40

feet

ofro

adw

ay.

inst

al1,9

’ier

eiet

iiee

tofl

rklO

PE

wti

tem

a1rt

sfte

m;.

tfli

eSeh

ndfi

ieT

rad::

;:in

ters

ectio

nto

Val

ley

Forg

ef8

oad

200-

knea

tlee

tof4

”-1G

’H

OPE

wat

erm

ates

thtQ

hO

i4:t

ndP

tOeeh2flt

5ali

dffiU

le:g

at:

:.:

Inst

all

and

deve

lop

two

wel

lsat

the

Last

Cha

nce

Bas

inW

ell

Fiel

dto

impr

ove

:apa

city

,an

ddr

illan

dde

velo

pfiv

ew

ells

aacen

tto

exis

ting

wel

lsut

ilizi

ngsx

istin

gin

fras

truc

ture

.

Prov

Ide

syst

emte

dund

ancy

mth

eti

rwer

sity

Med

ical

Dis

tric

tare

ade

com

mis

siar

sele

ctPR

Vs

redu

cing

oper

atin

gco

sts

max

eniz

epr

oduc

tion

rom

Wel

t4an

dre

duce

tran

sien

tpre

ssur

ewav

esin

syst

em

onve

rtth

e43

0H

GL

zone

near

Abb

ott

and

Elm

ore

and

cons

olid

ate

diff

eren

tpo

rtio

nsin

toei

ther

the

475

HGL

zone

orth

e41

1H

zone

.The

conv

ersi

onNi

llin

crea

setr

ansm

issi

onca

paci

tyan

dre

duci

ngpr

essu

refl

uctu

atio

ns.

Gre

enre

en

Est

tmat

edA

sste

tance

Fin

ante

TeFe

nP

roje

ctP

roje

ctC

onsf

ruct

lon

Sus

ta1n

abil

it,

Am

ount’

Rat

e(Y

rs)

Subsi

dy’

Am

ount

3‘t

ype”

Sta

rtfo

1icy

e

1Tot

alav

aila

ble

prce

ctlo

anfu

ndin

gan

dsu

bsid

yun

dert

his

Am

ende

dIU

Pis

$13,

06Z

573

and

$1,7

69,0

00,

resp

ectiv

ely.

2Cri

teri

afo

rbe

ing

elig

ible

for

alo

ansu

bsid

ym

aybe

refe

renc

edon

page

13un

der

the

narr

ativ

ese

ctio

nof

the

IUP.

Proj

ects

whi

chde

mon

stra

tead

equa

tecr

iteri

afo

rm

eetin

ga

Gre

enpr

ojec

tcom

pone

ntwi

llbe

elig

ible

tore

ceiv

ean

addi

tiona

l25

poin

ts.

Gre

enPr

ojec

tR

eser

veC

ateg

ory

Typ

e:G

IF-

Gre

enIn

fras

truc

ture

,W

TR

-W

ater

Effic

ienc

y,EN

G-

Ene

rgy

Effic

ienc

y&

EIN

-E

nvir

onm

enta

llyIn

nova

tive.

Gre

enPr

ojec

tJus

tific

atio

nTy

pe:

BC

-B

usin

ess

Cas

e!C

AT

-C

ateg

oric

al.

Prio

rto

fund

ing

any

proj

ects

how

nto

have

afu

ndin

gsu

bsid

yfo

rG

reen

,a

Bus

ines

sC

ase

for

proj

ect

Gre

enel

igib

ility

mus

tbe

foun

dju

stif

ied.

Sust

airr

abili

tyPo

licy

-“F

tcit

Firs

t”-

fixex

istin

gcr

itica

lin

fras

truc

ture

;“I

mpr

ove

TFM

”-

impr

ove

tech

nica

l,fi

nanc

ial

and

man

ager

ial

capa

city

ofth

esy

stem

;an

d,“P

lann

ing”

-pl

anni

ngan

dde

velo

pmen

tof

alte

rnat

ive

50po

ints

are

only

awar

ded

ifa

feas

ibili

tyor

desi

gnst

udy

has

been

com

plet

edfo

rth

epr

ojec

tby

the

end

ofth

eof

ques

tionn

aire

solic

itatio

npe

riod

.

8A

K23

4001

0lE

ast

Nom

eW

ater

(3,5

98)

Rep

lace

men

t

.:k’,fl.’,rr

Phas

edpr

ojec

tto

repl

ace

faile

dan

dfa

iling

dire

ctbu

ried

“Scl

airc

ore”

wat

eran

dse

wer

pipi

ngth

atw

asin

stal

led

inth

e19

80s.

156

Nom

e•

146

Sitk

a

143

3trn

eau

141

Dill

ingh

am+

9. 10 :1.1

::::

12 14

AK

2130

075

DeG

roff

Str

eet

Wat

er(8

,881

)ll

mpr

ovem

ents

AK

ZI1O

8fl

lEga

nD

r/IO

thlo

ltaIr

f

AK

2260

197

Drin

king

Wat

er(9

62)

Impr

ovem

ents

131

Ket

chik

an•

$2,6

90,0

00

$2,0

0000

0

$162

,000

$1.8

000ô

ô*

36.

16 18

13t

Ket

ctilk

an•

128

June

au

12 126

Anc

hora

ge

$2,6

90,0

00

$2,0

00,0

00

$1,3

52,1

00

$180

001

0

$1,0

00,0

00

$542

249

$864

,829

$2,0

00,0

00

$750,0

0

$450

,000

1.50

%

180%

1.50

%

1.50

%

1.50

%

1.50

%.

1.50

%

1.50

%.

1.50

%

1.50

%

20 20 20 20 20 20 20

2G.

20 20 20

ENS-

BC

WTR

-BC

wrR

•ec

ENG

-BC

ENS-

BC

3/1/

2014

s/1/2

o1s.

;.;

5/15

/201

6

8/1/

2014

1/1/

2015

10/1

/201

4

Fix

itFi

rst

Fix

itj

Fix

itFi

rst

Fix

itFi

rst

Fix

itF

irst

FIt

itFf

rSt::

&.

Fix

itFi

rst

•D

isad

vant

age

Com

mun

ity(c

riter

iam

aybe

refe

renc

edon

page

13)

•E

quiv

alen

cyPr

ojec

t(c

rite

ria

may

bere

fere

nced

onpa

ge12

)

•E

xtra

50po

ints

for

cons

truc

tion

star

tby

Sep

tem

ber

15,

20

14

$200

,000

$2,0

00,0

00

9/i

5/2

4•

j*oveF

M

Tot

alR

eque

sted

Am

ount

1$t6

,it5

,713

1

9/15

/201

4

Tot

alSu

bsid

ized

Am

ount

3:[$

:::::

..

.:

Tot

alG

reen

Am

ount

I$9.3

94:24

9:1

Impr

ove

TFM

OW

Plan

ning

List

App

endi

xlV

bA

men

ded

IUP

-FI

NA

L

Page 7: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY BOARDMeeting Date: December 18, 2014

Sclaircore Replacement Phase I & II; ADEC Drinking Water & Clean Water LoansResolutions 144w & 140&

NJUS applied for two municipal matching grants (MMGs) for Sclaircore Replacement Phase 2,for two phases to replace water-sewer utilities in the east quadrant of town, from Front to 6th

between N and K streets. The State awarded funding for Phase 2A in the amount of $3.OMMand Phase 2B in the amount of $4.557MM, the total of which represented 57% of the project.(Nome is eligible for up to 70% match, but in our initial application DEC limited the award to$3.0MMtypicalIy their grant limit (only 45%), although we were successful in making the casefor 70% funding in the second application.

Concurrent with the initial MMG application, the Utility submitted loan questionnairesequivalent to the amount of Phase 2A to be considered for funding under the Alaska DrinkingWater and Clean Water Loan Programs. These questionnaires successfully rated and wereincluded in the respective program’s Intended Use Plans (IUP). The Drinking Water Fund loanof $1,990,000 included a 50% subsidy (loan forgiveness) component. The Clean Water Fundloan of $1,740,000 included approximately 10% subsidy.

NJUS continued to seek out additional potential funding from federal sources to provideadditional matching funds for Phase 2B. We were not successful in our quest with USDA duringthis round, but did capture $769,800 in EPA funding for the project. This left a residual fundingneed of $1.2MM to fully match the state grants.

NJUS also applied for a MMG for Sclaircore Replacement Phase I (East 5th Avenue) and wasawarded $1,058,000 for the project. Concurrently, application was made to USDA for matchfunds. USDA accepted an application for a $308,000 loan and a $1,075,000 grant for furtherprocessing to provide additional funding for the project. We continued discussions with USDAas the terms being offered were onerous, requiring significant reserves to be funded on anannual basis, but the project had already been started. While other requirements to secure thefunding were not completed as we believed we were still in negotiation, USDA now advises thatbeing the project was started before all items had been resolved, they cannot provide fundingfor the project. (In a prior project, USDA did award funding subsequent, but based on their owninternal reviews, were directed they could not do so again — something that was not sharedwith NJUS until recently.)

ADEC was contacted and agreed that NJUS could include the Phase I (East 5th Avenue) in arevised application, and that the amendment requests for additional funding for Phase 2 shouldbe included in the same application, as opposed to amending an existing loan.

Recommended action:

That Resolutions 14-17 and 14-18 be adopted, to provide additional Phase 2 and include Phase Imatching funds in new loans applications, and that the prior amendments contained for Phase2 in Resolutions 14-07 and 14-08 be rescinded.

J. Handeland12/15/14

Page 8: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY SYSTEMa component unit of

P.O. Box 70 Nome, Alaska 99762 (907) 443-NJUS Fax (907) 443-6336

December 10, 2014

RE: USDA Anticipated FundingEast 5th Avenue Sclaircore Replacement

In 2010, NJUS submitted an application for funding to USDA for funding assistance with theconstruction of East 5th Avenue Sclaircore Replacement. After meeting with USDA personnel,additional updates were required to the Preliminary Engineering Report (PER) and EnvironmentalReport (ER), which were done and submitted. On May 25, 2011, USDA issued an Initial Letter ofConditions (LOC) advising funding application ($308,000 loan and $1,075,000 grant) had beenselected for further processing.

The LOC included numerous provisions, including the requirement to establish operating (annual$377,196) nd short lived asset replacement (annual $290,833) reserves, NIUS transmitted toUSDA concern relative to these requirements and requested a review and revision, as theserequirements in themselves would require additional revenue of approximately $43 percustomer per month before considering debt service.

A pre-construction meeting was scheduled for July 2011, but USDA advised they could notparticipate due to short notice and the emergency family leave of one of their personnel. Workcommenced on the project and the USDA Engineer came to Nome later in the month for whatwe believed was a follow-up for the pre-construction meeting, hut USDA considered it only aninspection, noting work had commenced.

USDA considered the request relating to the reserve requirements and revised them in anAmended LOC issued in February 2012. In May 2012 the Utility Board passed resolutions on thefinancing and submitted a request to USDA relative to the financing, as the standard forms hadbeen previously found unworkable (due to their requirement of placing USDA in “first position”,and other USDA loans and the Alaska Municipal Bond Bank issue already had superior position).We find no response was received.

NJUS considered the financing secured and reflected same as outstanding receivables. In March2014 as we were working to resolve all outstanding grant/loan matters, NJUS met with the USDAengineer to review the status and were advised to contact the Community Programs Director(CPD) to determine outstanding matters required to finalize the funding. In response to ourrequest, the CPD telephoned to advise of her impending retirement and that this file would needto wait until later in the year when new personnel were in place.

Pr’ovicling reliable utility services to system rate payers efficiently and econoinkally by

Page 9: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

RE: USDA Anticipated Funding — East 5th Avenue Sclaircore ReplacementDecember 10, 2014Page 2.

On November 10, the Utility Manager met with the City Manager and Finance Director expressingconcern that the funding could fall through. A call was placed to USDA and they confirmed thefunding had not been deobligated and a file review would commence. A telephonic meetingwas scheduled for November 26, but was changed several times by USDA as they continued toreview their files.

On November 25, we were advised by phone that delays were due to file review and internalconsultation. We were advised that because the project had been started and completed beforeresolving all matters, based on a prior determination by USDA National Office, funding would notbe provided and that there was a process of appeal. We met with the City Manager and FinanceDirector to advise of this, and that we would likely have to go through the appeals process.

As we had not received a response to our May 2012 inquiry on the loan documents, and USDAhad amended the LOC in February 2012, after construction was completed, we did not completethe process of submitting other USDA LOC documents, pending the request to further amend theLOC.

Subsequently, on December 8, USDA advised based on their internal handling of a loan to Nomein 2006, there were specific requirements that the loan and companion grant could not be closeduntil all LOC items were met and that construction could not begin until Rural Development gaveauthorization to proceed. Based on construction being complete and other documentation/procedures in the LOC not having been met, they could not fund the project.

With an inclination this funding could be in jeopardy, in November NJUS submittedquestionnaires to the ADEC clean water and drinking water program to seek potential loanfunding under their open period for amending the current year Intended Use Plan (IUP), abovethat which had been already approved as amendment requests ($1.3MM)to the loans for currentyear sclaircore replacement. These questionnaires were scored and included in the IUP, withadditional funding of $3.7MM available above the amendment amount,

Under the USDA funding, the Utility would have had required annual loan payments ofapproximately $60,000 plus the requirement to deposit $173,017 into a SLA reserve, orapproximately $15 per water/sewer customer per month for 40 years. Under the alternatefunding through ADEC, the annual requirement for 20 years would result in a requirement ofbetween $4.50 and $6.81 depending on whether additional project costs not included in theUSDA funding may also be loan eligible. Should ADEC amend their loan program to extend theterms to 30 years, the annual requirement comparative would be between $3.00 and $4.54.

it is unfortunate USDA funding will not materialize. However, having now had an opportunity toreview in greater detail the ADEC loan option. Utility customers actually will benefit to a greaterdegree by utilizing ADEC (debt service and reserve requirements are $10/month less percustomer under AIEC than USDA>. Utilizing additional ADEC loan funding to “refinance” the 5th

Avenue project paid with operating funds is the only option available and with authorizingresolutions, can be applied for and reimbursements received in January 2015.

L”v

Page 10: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

USDA — 5th Avenue

Submitted project application, Preliminary Engineering Report (PER), Environmental Report (ER>—summer 2010

Met with Misty on application — Nov/Dec 2010

USDA review of PER/ER previously submitted required updates; done with Lloyd Persson, CE2

Initial Letter of Conditions — May 2011

Pre-Construction meeting scheduled 7/6/11 — Advised USDA could not participate due tonotice/Misty out on emergency family leave.

Work commenced summer 2011

(rug and Persson in town to meet on project status— July 2011

Transition engineer from Persson to Erdman — fall 2011

Erdrnan met with HuH on SL revisions. Utility submitted requested changes to short livedassets schedule/reserve requirements — February 2012

Received amended letter of conditions — February 2012

Utility Board passed resolutions on financing— May 2012

Transmitted resolutions to Kruse, requesting clarification on loan documents/securityagreement — June 2012

Project review by Krug in Norne — March 2014

Requested meeting with Kruse to resolve outstanding issues; she was retiring and said it wouldhave to wait until later in year — April 2014

City Manager, Finance Director, Utility Manager contacted Hull — confirmed funds had not beende-obligated and she would review file — November 2014

Meeting scheduled with Hull to review outstanding issue on loan documents-securityagreement, and requested additional change to short lived asset schedule/reserve requirement—November 2014. Meeting times moved a couple of times as she had not been able tocomplete file review. Meeting scheduled for 11/26, but changed to 12/3 due to holiday.Requested that if there was another opening prior to 12/3, that we would like to meet as soonas possible.

Advised by phone 11/25 that delays were due to file review and internal consultation. Statedbeing work had been completed prior to resolving all matters, funding would not be provided,and that there was an appeals process. Delay had been while she reviewed file and workedwith National Office to determine what their response was going to be. To expect a letter.

Met with city manager & finance officer to advise of above.

Brief synopsis 12/2/14 /1 hand eland

Page 11: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

EAST 5TH AVENUEPROJECT COSTING TOTAL

LaborMate na IsFreightEquip Rent-OthersEquip Rent-NJUSServicesLegalPermitsInspectionSuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew

DEC 62766 - PAY REQUEST00-0 L’bor02-0 Freight03-0 Equip Rent-Others04-0 Equip Reni-NJUS

RESIDUAL (portion USDA planned)00-0 Labor01-0 Materials02-0 Freight03-0 Equip Rent-Others04-0 Equip Rent-NJUS05-0 Services06-0 Legal07-0 Permits

SuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew

PORTION UNMATCHED IN DEC00-0 Labor02-0 Freight03-0 Equip Rent-Others

20,866.1153,106.40 1,263.50

53,731.951,962.40 79,023.18

115,001.74 1,082,264.12

2,2 50 .006,317.02 25,439.45

TOTAL821,029.49708,660.07113,567.82511,759.30249,346.15137,316.43

78.00506.12

2,250.00175,582.82

2,600.0020,866.1154,369.90

1S9,258.41194,540.21

3,151,730.83

GENJN. WATER70-0651 70-065212,347.92 322,364.19

177,635.6658.48 13,919.57

1,620.00 237,958.96112,313.83

14,810.09 11,648.3478.00

00-001-002-003-004-005-006-007-008-009-015-020-050-052-054-0

FIRE I-{YD70-0654

55,728.7822,154.71

2,263.9916,494.154,265.461,500.00

SVC LINES70-0655120,315.43174,370.8454,285.6617,392.2627,183.74

101,575.00

506.12

7,821.221,825.00

SEWER70-0653310,273.17334,498,8643,040.12

238,293.93105,583.12

7,783.00

63,987.69387.50

60,562.9661,799.43

1,226,209.78

72,017.44387.50

4,967.0012,288.83

125,979.94

39,996.5039,466.37

602,275.25

Inspection08-009-015-020-050-052-0

54-0

70-0651 70-0652 70-0653 70-06548,295.21 303,965.53 292,109.27 33,539.89 84,343.53 722,253.43

4,636.19 14,959.53 2,208.31 53,413.00 75,217.03783.00 218,908.13 219,243.10 2,905.37 15,102.73 456,942.33

117,222.87 110,421.94 2,521.20 26,850.26 257,016.279,078.21 644,732.72 636,733.84 41,174.77 179,709.52 1511,429.06

(1,058,000.00)

453,429.06

70-0651 70-0652 70-0653 70-0654 70-0655 IQIAI.4,052.71 18,398.66 18,163.90 22,188.89 35,971.90 98776.06

.- 177,635.66 334,498.86 22,154.71 174,370.84 708,660.0758.48 9,283.38 28,080.59 55.68 872.66 38,350.79

837.00 19,050.83 19,050.83 13,588.78 2,289.53 54,816.97- (4,909.04) (4,838.82) 1,744.26 333.48 (7,670.12)

14,810.09 11,648.34 7,783.00 1,500.00 101,575.00 137,316.4378.00

--

- - 78.00506.12

- -- - 506.12

--

- 2,250.00 2,250.007,821.22 72,017.44 63,987.69 6,317.02 25,439.45 175,582.821,825.00 387.50 387.50

- - 2,600.0020,866.11 - -

- - 20,866.1153,106.40 1,263.50

-- - 54,369.90

- 53,731.95 60,562.96 4,967.00 39,996.50 159,258.411,962.40 79,023.18 61,799.43 12,288.83 39,466.37 194,540.21

105,923.53 437,531.40 589,475.94 84,805.17 422,565.73 1,640,301.77

70-0651 70-0652 70-0653 70-0654 70-0655 IQIJ.291,589.27 84,343.53 375,932.80

4,636.19 14,959.53 2,208.31 53,413.00 75,217.031,045.00 1,045.00 189.35 2,279.35

- 5,681.19 307,593.80 2,397.66 137,756.53 453,429.18

TOTAL FOR LOAN CONSIDERATION 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL00-0 Labor 4,052.71 18,398.66 309,753.17 22,188.89 120,315.43 474,708.8601-0 Materials - 177,635.66 334,498.86 22,154.71 174,370.84 708,660.0702-0 Freight 58.48 13,919.57 43,040.12 2,263.99 54,285.66 113,567.82

Page 12: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

03-004-005-006-007-008-009-015-020-050-052-054-0

Equip Rent-OthersEquip Rent-NJUSServicesLegalPermitsInspectionSuppliesSurveyingInterestCE2 EngineeringCE2 Const MgmtCE2 Core Crew

GEN/ENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655

837.00 20,095.83 20,095.83 13,778.13 2,289.53- (4,909.04) (4,838.82) 1,744.26 333.48

14,810.09 11,648.34 7,783.00 1,500.00 101,575.0078.00 -

- -

506.12 - - - -

--

- 2,250.007,821.22 72,017.44 63,987.69 6,317.02 25,439.451,825.00 387.50 387.50 - -

20,866.11-

53,106.40 1,263.50 - -

- 53,731.95 60,562.96 4,967.001,962.40 79,023.18 61,799.43 12,288.83

105,923.53 443,212.59 897.069,74 87,202.83

DRiNKING WATERCLEAN WATER

TOTAL57,096.32(7,670.12)

137,316.4378.00

506.122,250.00

175,582.822,600.00

20,866.1154,369.90

159,258.41194,540.21

2,093.730.95

39,996.5039,466.37

560.322,26

52,961.77 443,212.59 87,202.83 280,161.13 863,538.3252,961.76 897,069.74 280,161.13 1,230,192.63

105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95

Page 13: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

GEN/ENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL

GEN/ENG WATER SEWER FIRE HYD SVC LINESSORTED BY DEC LOAN CLASS 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL DEC LOAI\j C20-0 Interest 1 20,866.11 - - -

- 20,866.11 23856

50-0 CE2 Engineering 2 53,106.40 1,263.50 - - - 54,369.90 54,359

06-0 Legal 3 78.00 --

- 78.0007-0 Permits 3 506.12

-

- 506.1208-0 Inspection 3

- 2,250.00 2,250.0015-0 Surveying 3 1,825.00 387.50 387.50 - 2,600.0052-0 CE2 Const Mgmt 3 - 53,731.95 60,562.96 4,967.00 39,996.50 159,258.4154-0 CE2 Core Crew 3 1,962.40 79,023.18 61,799.43 12,288.83 39,466.37 194,540.21 359232

01-0 Materials 4 - 177,535.66 334,498.86 22,154.71 174,370.84 708,660.0702-0 Freight 4 58.48 13,919.57 43,040.12 2,263.99 54,285.66 113,567.8203-0 Equip Rent-Others 4 837.00 20,095.83 20,095.83 13,778.13 2,289.53 57,096.3204-0 Equip Rent-NJUS 4 - (4,909.04) (4,838.82) 1,744.26 333.48 (7,670.12)05-0 Services 4 14,810.09 11,648.34 7,783.00 1,500.00 101,575.00 137,316.4309-0 Supplies 4 7,821.22 72,017.44 63,987.69 6,317.02 25,439.45 175,582.8200-0 Labor 4 4,052.71 18,398.66 309,753.17 22,188.89 120,315.43 474,709.86 1,659,262

105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95 2,093,730

GEN/ENG WATER SEWER FIRE HYD SVC LINESDRINKING WATER 70-0651 70-0652 70-0654 70-0655 IPL DEC LO i C20-0 Interest 1 10,433.05 -

-- 10,433.05 10,33

50-0 CE2 Engineering 2 26,553.20 1,263.50-

- 27,816.70 27,816

06-0 Legal 3 39.00 --

- 39.0007-0 Permits 3 253.06

-- 253.06

08-0 Inspection 3 --

- 1,125.00 1,125.0015-0 Surveying 3 912.50 387.50

-- 1,300.00

52-0 CE2 Const Mgmt 3 - 53,731.95 4,967.00 19,998.25 78,697.2054-0 CE2 Core Crew 3 981.20 79,023.18 12,288.83 19,733.18 112,026.39 193,440.

01-0 Materials 4 - 177,635.66 22,154.71 87,185.42 286,975.7902-0 Freight 4 29.24 13,919.57 2,263.99 27,142.82 43,355.6203-0 Equip Rent-Others 4 418.50 20,095.83 13,778.13 1,144.77 35,437.2304-0 Equip Rent-NJUS 4 - (4,909.04) 1,744.26 166.74 (2998.04)05-0 Services 4 7,405.05 11,648.34 1,500.00 50,787.50 71,340.8909-0 Supplies 4 3,910.61 72,017.44 6,317.02 12,719.73 94,964.8000-0 Labor 4 2,026.36 18,398.66 22,188.89 60,157.72 102,771.63 631,847.

52,961.77 443,212.59 - 87,202.83 280,161.13 863,538.32 863,538.

GEN/ENG WATER SEWER FIRE HYD SVC LINESCLEAN VLAT 70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL DEC LOAN Ci20-0 Interest 1 10,433.06

-

- 10,433.06 10,433.

50-0 CE2 Engineering 2 26,553.20-

- 26,553.20 26,553.

06-0 Legal 3 39.00-

- 39.0007-0 Permits 3 253.06

- 253.0608-0 Inspection 3 - 1,125.00 1,125.0015-0 Surveying 3 912.50 387.50

- 1,300.0052-0 CE2 Const Mgmt 3 - 60,562.96 19,998.25 80,561.2154-0 CE2 Core Crew 3 981.20 61,799.43 19,733.19 82,513.82 165,792.

01-0 Materials 4 - 334,498.86 87,185.42 421,684.28

Page 14: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

GENJENG WATER SEWER FIRE HYD SVC LINES70-0651 70-0652 70-0653 70-0654 70-0655 TOTAL02-0 Freight 4 29.24 43,040.12 27,142.84 70,212.2003-0 Equip Rent-Others 4 418.50 20,095.83 1,144,76 21,659.0904-0 Equip Rent-NJUS 4 - <4,838.82) 166.74 (4,672.08)05-0 Services 4 7,405.04 7,783.00 50,787.50 65,975.5409-0 Supplies 4 3,910.61 63,987.69 12,719.72 80,618.0200-0 Labor 4 2,026.35 309,733.17 60,157.71 371,937.23 1,02741

52,961.76 - 897,069.74 - 280,161.13 1,230,192.63 i9

DRINKING WATER 52,961.77 443,212.59 87,202.83 280,161.13 863,538.32CLEAN WATER 52,961.76 897,069.74 280,161.13 1,230,192.63105,923.53 443,212.59 897,069.74 87,202.83 560,322.26 2,093,730.95

Application Amend Available Add 5th Qv rINTENDED USE PLAN PROJECTS LISTEDDrinking Water 2,690,000 700,000 1,990,000 863,538.32 i,1)6t 6:Clean Water 2,340,000 600,000 1,740,000 1,230,192.63 509g0

5,030,000 1,300,000 3,730,000 2,093,730,95 1636,:Gc

Amend Add 5th Intal LoanDrinking Water 2,690,000 200,000 863,538.32 ] 563,53832 (1,126,461.68)Clean Water 2,340,000 600,000 J.,230,192.63 ,830,192.63 (509,807.37)

5,030,000 1,300,000 2,093 730.95 3,393,73095 (1,636,269.05)

20 yrs 65,000.00 [‘i04,686.55 169,686.55 2,093,730.951230 customers 50.78 81.79 132.57Per Month 4.23 6.82 11.05

30 yrs 43,333.33 69,791.03 113,124.371280 customers 33.85 54.52 88.38Per Month 2.82 4.54 7.36

USDA EXPECTED Grant 1,075,000.00Loan 308,000.00 Pay x 40 yrs 59,242.40 includes interest @ 3.75%

1,383,000.00 SLA Asset Require 173,017.00232,259.40

Page 15: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

ST

5TH

AV

E-2

011

PR

INPR

#1A

Pin

PR#1

Mat

chT

otal

USD

A+

DE

C62

766

DE

C62

766.

US

DA

-li

USD

A-1

2A

bove

Ava

ilM

atch

(USD

A)

(USD

A)

Abo

vA

vail

PR

#i

Net

ofM

atch

07.6

51E

ng/G

en12

,293

.60

942.

0093

.00

13,3

28.6

09,

078.

219,

078.

2107

.652

Wtr

mai

n15

0,51

8.06

52,7

27.9

399

,889

.20

5,68

1.1

930

8,81

6.38

644,

732.

7263

9,05

1.53

07.6

53S

wrm

ain

333,

000.

4219

,575

.46

96,8

13.4

316

,004

.53

292,

109.

2775

7,50

3.11

636,

733.

8432

8,62

0.04

07.6

54F

ire

Hyd

24,4

39.9

112

,317

.50

10,9

11.8

32,

397.

6650

,066

.90

41,1

74.7

738

,777

.11

07.6

55S

vcL

ines

303,

107.

6021

,830

.26

56,2

39.6

153

,413

.00

84,3

43.5

351

8,93

4.00

179,

709.

5341

,953

.00

823,

359.

5910

7,39

3.15

263,

947.

0777

,496

.38

376,

452.

801,

648,

648.

991,

511,

429.

071,

057,

479.

8993

0,75

2.74

453,

949.

1813

84,7

01.9

2(5

20

0)

520.

0045

3,42

9.18

1,05

7,99

1,38

3,00

0.00

(1,7

01.9

2)(1

,181

.92)

(520

.00)

3DA

anti

cipa

ted

part

icip

atio

nbo

oked

rece

ivab

le1,

383,

000.

00ov

eA

vail

able

263,

947.

071

,646

,94

77

(1,7

01.9

2)st

saf

ter

7/16

/12

reco

ncil

e46

,284

.14

1,69

3,23

1.21

)nst

ruct

ion

Loa

nIn

tere

st20

,866

.11

‘anc

eth

roug

hD

EC

Loa

ns1,

714,

097.

32

____

____

____

____

____

____

____

____

____

___

USD

AO

rigi

nal

OW

CW

SLA

Res

erve

290,

833

37.6

51E

ng/G

en13

,328

.60

1,95

7.00

20,8

66.1

136

,151

.71

18,0

75.8

618

,075

.85

Ope

rati

ngR

eser

ve

377,

196

37.6

52W

trm

ain

308,

816.

3830

8,81

6.38

308,

816.

3866

8,02

937

.653

Sw

rmai

n75

7,50

3.11

757,

503.

1175

7,50

3.11

Per

Cus

tom

er51

5.45

37.6

54Fi

reH

yd50

,066

.90

21,0

68.2

171

,135

.11

71,1

35.1

1P

erC

ustl

Mo

42.9

5)7

,655

Svc

Lin

es51

8,93

4.00

23,2

58.9

354

2,19

2.93

271

,096

.47

271,

096A

61,

648,

648.

9946

,284

.14

20,8

66.1

11,

715,

799.

2466

9,12

3.82

1,04

6,67

5.42

1,70

1.92

USD

AR

evis

edA

nnua

lE

stC

usto

mer

s1,

296

Mon

thU

SDA

SLA

Res

erve

Req

uire

173,

017

Tot

al1,

715,

000

1,32

3P

erC

usto

mer

133.

5020

yrs

85,7

5066

5.51

Per

Cus

tlM

o11

.13

3oyrs

57,1

6744

3.68

USD

A30

8KL

oan

-40

yrs

15,0

63E

st@

DE

Cgr

t2,

302,

000

(mt

288K

)11

.62

Est

@U

SDA

2,44

1,00

00.

97E

st@

Con

st2,

989,

000

alC

ost

3,15

1,73

1-G

rant

EngI

Mtls

Page 16: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

2A

6,73

0,00

0

28T

otat

6,51

0,00

013

,240

,000

MM

G

Mat

ch

45%

3,00

0,00

0

55%

3,73

0,00

0

6,73

0,00

0

70%

4,55

7,00

0

30%

1,95

3,00

0

6,51

0,00

0

7,55

7,00

057

%

5,68

3,00

0

13,2

40,0

00

DW

Cw

Tot

at

1,99

0,00

0

1,74

0,00

0

3,73

0,00

0

Sub

%D

raw

50%

1,99

0,00

0

10%

1,74

0,00

0

3,73

0,00

0

EPA

769,

800

4,49

9,80

0

1,18

3,20

0

5,68

3,00

0(7

69,8

00)

4,91

3,20

0

(1,1

75,0

00)

3,73

8,20

0

28%

995,

000

180,

000

8,73

2,00

0

769,

800

9,50

1,80

0

9,50

1,80

013

,240

,000

72%

336,

500

247

Mat

ch

DEC

Loa

nsEP

AG

rant

Add

edM

atch

Req

uire

d

5,68

3,00

0(3

,730

,000

)(7

69,8

00)

1,18

3,20

0

325,

500

239

662,

000

486

EAST

SCLA

IRC

OR

ER

EPLA

CEM

ENT

-PH

ASE

2

2014

IUP

43%

7,55

7,00

0

Sub

sidy

Net

995,

000

995,

000

180,

000

1,56

0,00

0

1,17

5,00

02,

555,

000

Add

itio

nal

Mat

ch EPA

1361

2018

6,91

0

137

11.4

4 7R

es

Page 17: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY SYSTEMEAST SCLA)RCORE REPLACEMENT

PHASE 2

Phase 2A 28 TotalProject Total Estimate 6,730,000 6,510,000 13,240,000

MMG 3,000,000 45% 4,557,000 70% 7,557,000 57%Match 3,730,000 55% 1,953,000 30% 5,683,000 43%

6,730,000 6,510,000 13,240,000

Total Match Required 5,683,000

Funding Sources:

Loan TotalEXISTING LOANS

SFY 2014 Amendwith

IUP Request

________________________________ ___________ ____________

Amendment

Drinking Water #627161 1,990,000 700,000 2,690,000

Clean Water p627141 1,740,000 600,000 2,340,000

3,730,000 1,300,000 5,030,000

EPA STAG 769,800

4,499,800

Additional Unmet Match Requirement 1,183,200Contingency 10% 118,320

1,301,520

/jkh08/12/14

Page 18: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY BOARDMeeting Date: September 16, 2014

NJUS

Sclaircore Replacement — Phase II; ADEC Drinking Water & Clean Water Loan AmendmentsResolutions 14-07 & 14-08

NJUS applied for two municipal matching grants (MMGs) for Sclaircore Replacement Phase 2,for two phases to replace water-sewer utilities in the east quadrant of town, from Front to 6Ibetween N and K streets. The State awarded funding for Phase 2A in the amount of $3.OMMand Phase 2B in the amount of $4.557MM, the total of which represented 57% of the project.(Nome is eligible for up to 70% match, but in our initial application DEC limited the award to$3.OMM-typically their grant limit (only 45%), although we were successful in making the casefor 70% funding in the second application.

Concurrent with the initial MMG application, the Utility submitted loan questionnairesequivalent to the amount of Phase 2A to be considered for funding under the Alaska DrinkingWater and Clean Water Loan Programs. These questionnaires successfully rated and wereincluded in the respective program’s Intended Use Plans (IUP). The Drinking Water Fund loanof $1,990,000 included a 50% subsidy (loan forgiveness) component. The Clean Water Fundloan of $1,740,000 included approximately 10% subsidy.

NJUS continued to seek out additional potential funding from federal sources to provideadditional matching funds for Phase 2B. We were not successful in our quest with USDA duringthis round, but did capture $769,800 in EPA funding for the project. This left a residual fundingneed of $1.2MM to fully match the state grants.

ADEC was contacted and will amend the existing drinking water and clean water loans for Phase2 to provide the additional match funding required.

When considering the amount of subsidy (loan forgiveness) and the EPA funding used, the netresult raises the grant percentage from 57% to 72% of the projects.

Recommended action:

That Resolutions 14-07 and 14-08 be adopted, amending the Phase 2 ADEC Drinking Water andClean Water Loans to provide the additional matching funds required as match to awardedmunicipal matching grants. This funding mechanism was discussed previously and the addeddebt service requirement was considered during the rates adjustment implemented earlier thisyear.

i. Handeland09/15/14

Page 19: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

Presented By:Utility ManagerAction Taken:

No°Abstain.

CITY OF NOME, ALASKA

RESOLUTION NO. R-14-lo-oz

A RESOLUTION APPROVING & ACCEPTING AN AMENDED LOAN FROM THEALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKA

DRINKING WATER FUND TO PROVIDE FINANCING FOR IMPROVEMENTS TOCOMMUNITY WATER INFRASTRUCTURE

WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,

WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to 20 years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,

WHEREAS, by Resolution R-13-o5-oz, as recommended by Nome Joint Utility BoardResolution 12-04, a loan was authorized for Project #6z7161 — East Nome Water Replacement —

$1,990,000, ofwhich $995,000 was subsidized (converted to a grant); and,

WHEREAS, the initial loan was made to provide partial funding for Sclaircore ReplacementPhase iA, additional federal funds were awarded, and the existing loan only partially matches stategrants for Phase 2B, and the State is willing to amend the loan to provide additional funding to fullymatch the existing municipal matching grant for completion of Phase 2B;

NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan amended ADEC Drinking Water Fund Loan for the construction of water system improvementsfor a new total of $2,690,000 (of which $995,000 has been subsidized) with a 20 year payback at 1.5%interest, as recommended by Nome Joint Utility Board Resolution i-o7, and authorizes the UtilityManager as Chief Operating Officer of the Utility to execute any and all documents that may berequired by the Department to reflect the indebtedness, the terms of its repayment, and any securitythereof, including but not limited to an agreement for the loan and a promissory note.

APPROVED and SIGNED this j3t1 day of

ATTEST: .

TOM M RAN, Clerkf/If

DENISE MICHELS,

Page 20: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY SYSTEM

NOME JOINT UTILITY BOARD

RESOLUTION 14-07

A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTAN AMENDMENT TO A LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL

CONSERVATION ALASKA DRINKING WATER FUND TO PROVIDE LOAN FINANCING FORIMPROVEMENTS TO COMMUNITY WATER INFRASTRUCTURE

WHEREAS, The Utility Board determined application should be submitted toDepartment of Environmental Conservation Drinking Water Fundfinance various infrastructure improvements constructed to the watersystems, including replacements, extensions and enhancements; and,

the AlaskaProgram toand sewer

WHEREAS,

WHEREAS,

WHEREAS,

the Alaska Department of Environmental Conservation Alaska Clean Water &Alaska Drinking Water Fund loan programs offers terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems; and

NJUS submitted annual questionnaires to be included on the Intended Use Plansfor these ADEC programs, application was made, and ADEC provided an initialloan Project #627161 — East Nome Water Replacement — $1,990,000. Of thisamount, $995,000 was eligible for subsidy (repayment assistance) and convertedto a grant); and,

the initial loan application was made to provide partial funding for SclaircoreReplacement Phase 2A, additional federal funding was awarded, and the existingloan only partially matches state grants for Phase 2B, and the State is willing toamend the loan to provide additional funding to fully match the existing municipalmatching grant for completion of Phase 28;

NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and authorize acceptance of additional $700,000, amending the existingADEC Drinking Water Fund Loan #627161, for the construction of water system improvements for anew total of $2,690,000 (of which $995,000 has been subsidized) with a 20 year payback at 1.5%interest, and authorize the Utility Manager as Chief Operating Officer of the Utility to execute anyand all documents that may be required by the Department to reflect the indebtedness, the terms ofits repayment, and an security thereof, including but not limited to an agreement for the loan and apromissory note.

SIGNEDTHIS JL DAYOF

___________

2014 AT NOME, ALASKA.

I1,-oVBerda Willson, ChairmanNOME JOINT UTILITY BOARD

avid Barron, ryNOME JOINT UTILITY BOARD

Page 21: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

Presented By:Utility ManagerAction Taken:

YesNo

Abstain

CITY OF NOME, ALASKA

RESOLUTION NO. R-13-o5-02

A RESOLUTION APPROVING & ACCEPTING A LOAN FROM THE ALASKADEPT. OF ENVIRONMENTAL CONSERVATION ALASKA DRINKING WATER FUND

TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TOCOMMUNITY WATER INFRASTRUCTURE

WHEREAS, the Nome Joint Utility Board determined application should be submitted to theAlaska Department of Environmental Conservation Drinking Water Fund Program to finance variousinfrastructure improvements to water and sewer systems, including replacements, extensions andenhancements; and,

WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water& Alaska Drinking Water Fund loan programs with terms up to zo years with no prepaymentpenalties to provide low interest (1.5%) financing to communities for water and sewer systems andNJUS submitted annual questionnaires to be included on the Intended Use Plans for these ADECprograms; and,

WHEREAS, application was made and ADEC is prepared to enter in to an Agreement forProject #627161 — East Nome Water Replacement — $1,990,000, of which up to $995,000 15 eligible forsubsidy (repayment-conversion to a grant), and by Resolution 12-04 the Nome Joint Utility Systemrecommends the loan be accepted; and,

NOW, THEREFORE, BE IT RESOLVED that the Nome City Council approves and acceptsan ADEC Drinking Water Fund Loan for the construction of water system improvements in theamount of $1,990,000 with a 20 year payback at 1.5% interest, and authorizes the Utility Manager asChief Operating Officer of the Utility to execute any and all documents that may be required by theDepartment to reflect the indebtedness, the terms of its repayment, and any security thereof,including but not limited to an agreement for the loan and a promissory note.

APPROVED and SIGNED this 13th day of May,

__

LDISE MICHft. yIayor

fl//_Z:—)\J\__

TOM MORAN, Clerk

Page 22: RESOLUTION NO. R-15-ol-o3 ALASKA CITY OF NOME, A ... · Pfoject Descript,on AmountZ Rate (Yrs Subs1dy Amount Start POI,C9 AK2211229 Treatment Plant Upgrade The project will rehabilitate

NOME JOINT UTILITY SYSTEM

NOME JOINT UTILITY BOARD

RESOLUTION 12-04

A RESOLUTION REQUESTING THE NOME COMMON COUNCIL APPROVE & ACCEPTA LOAN FROM THE ALASKA DEPT. OF ENVIRONMENTAL CONSERVATION ALASKADRINKING WATER FUND TO PROVIDE LOAN FINANCING FOR IMPROVEMENTS TO

COMMUNITY WATER INFRASTRUCTURE

WHEREAS, The Utility Board determined application should be submitted to the AlaskaDepartment of Environmental Conservation Drinking Water Fund Program torefinance various infrastructure improvements constructed to the water and sewersystems, including replacements, extensions and enhancements; and,

WHEREAS, the Alaska Department of Environmental Conservation has Alaska Clean Water &Alaska Drinking Water Fund loan programs with terms up to 20 years with noprepayment penalties to provide low interest (1.5%) financing to communities forwater and sewer systems and NJUS submitted annual questionnaires to beincluded on the Intended Use Plans for these ADEC programs; and,

WHEREAS, Application was made and ADEC is prepared to enter in to an Agreement forProject #627161 — East Nome Water Replacement — $1,990,000. Of this amount,up to $995,000 is eligible for subsidy (repayment-conversion to a grant).

NOW THEREFORE BE IT RESOLVED that the Nome Joint Utility Board requests the NomeCommon Council approve and accept an ADEC Drinking Water Fund Loan for the construction ofwater system improvements in the amount of $1,990,000 with a 20 year payback at 1.5% interest,and authorize the Utility Manager as Chief Operating Officer of the Utility to execute any and aHdocuments that may be required by the Department to reflect the indebtedness, the terms of itsrepayment, and an security thereof, including but not limited to an agreement for the loan and apromissory note.

SIGNED THIS DAY OF I , 2012 AT NOME, ALASKA.

4(‘. /

‘— /: tdBerda J. WiIIson ChairmanNOME JOINT UTILITY BOARD

ATTET— ;;—

David Barron, SecretaryNOME JOINT UTILITY BOARD