Upload
tamera
View
25
Download
0
Embed Size (px)
DESCRIPTION
2011 MAR 17. Reserve and Congestion Management Using Wind Power Probabilistic Forecast: A Real Case-Study. Ricardo Bessa 1 ( [email protected] ) Leonardo Bremermann 1 , Manuel Matos 1 Rui Pestana 2 , Nélio Machado 2 Hans-Peter Waldl 3 , Christian Wichmann 3 - PowerPoint PPT Presentation
Citation preview
© 2011
Reserve and Congestion Management Using Wind Power
Probabilistic Forecast: A Real Case-Study
Ricardo Bessa1 ([email protected])Leonardo Bremermann1, Manuel Matos1
Rui Pestana2, Nélio Machado2 Hans-Peter Waldl3, Christian Wichmann3
1 INESC Porto, Portugal2 REN, Portugal
3 Overspeed GmbH & Co. KG, Germany
2011 MAR 17
+
© 2011
Introduction
• In the ANEMOS.plus European project power system management tools were developed, and are now being demonstrated at several end-users
• Two of these management tools will be presented (on-going demonstration for REN)
• Robust Reserve Setting (RRS) tool
– Objectives: estimation of the operational reserve needs to account for units outages, wind power and load uncertainty
– Output: reserve levels for each hour of a predefined period (i.e. day-ahead, intraday) obtained with different decision-aid methods
• Fuzzy Power Flow (FPF) tool
– Objectives: identify possible voltage violations and branch congestions
– Output: list of nodes with possible voltage limits violations and branches with possible congestions
2EWEA Annual Conference, 14-17 March 2011
© 2011 3EWEA Annual Conference, 14-17 March 2011
Robust Reserve Setting Tool
© 2011
Robust Reserve Setting (RRS) Tool
4EWEA Annual Conference, 14-17 March 2011
G: Uncertain Generation
L: Uncertain Load
Decision Methods
Preferred Operating
Reserve Level
Evaluation
Decision Maker(REN)
Probabilistic Model
Decision-aid Phase
Demonstration at the Portuguese SO
(REN)
(risk vs reserve cost)
Deterministic Multicriteria
Problem
System Gen. Margin Model
SM=G-L
Risk Indices
© 2011
Uncertainty Modeling
• Conventional generation: discrete probability distribution of the possible capacity states (capacity outage probability table, COPT)
• Load: Gaussian distribution with a given standard deviation and zero mean
• Wind generation: set of quantiles forecasted by the ANEMOS platform
5EWEA Annual Conference, 14-17 March 2011
© 2011
System Generation Margin Distribution (Probabilistic Model)
6EWEA Annual Conference, 14-17 March 2011
risk of loss of load
LOLP=0.49EPNS=157.1 MW
PWRE=0.037EWRE=4.13 MW
upward reserve
+ 700 MW
LOLP=0.036EPNS=5.4 MW
risk of generation surplus
PWRE=0.51EWRE=129.1 MW
downward reserve
- 600 MW
© 2011
Risk/(Reserve or Cost) Curves and Decision-aid
7EWEA Annual Conference, 14-17 March 2011
max accepted
LOLP
Recommended upward reserve
max accepted
PWRE
Recommended downward
reserve
© 2011
Demonstration Case Design
8EWEA Annual Conference, 14-17 March 2011
RRS(ANEMOS.plus)
Upscaled Probabilistic WPF
Load and Special Regime Generation
(e.g. mini-hydro, CHP) Forecasts
4 GW4 times per day
(ANEMOS)
7 times per day
Market Dispatch andInterconnection Levels
7 times per dayDaily, 6 Intraday Markets
Hourly Upward and Downward Reserve Needs
7 times per dayDaily, 6 Intraday Markets
Running since 28 Sept 2010
Sequential Market
© 2011
0
500
1000
1500
2000
2500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MW
h
Intra1 Intra2 Intra3 Intra4 Intra5
Intra6 Intra7 Mob. Reserve Benchmark Rule
Output Results (Upward Reserve)
9EWEA Annual Conference, 14-17 March 2011
LOLP=0.1%
© 2011
Upward Reserve Results (Oct-Feb, 4 Months)
10EWEA Annual Conference, 14-17 March 2011
Market Session
LOLP=0.1%
LOLP=0.5%
LOLP=1%
Benchmark Rule
Daily 1.44 % 2.25 % 2.76 % 4.34 %
Intraday 1 0.83 % 1.39 % 1.79 % 3.13 %
Intraday 2 1.23 % 1.76 % 2.14 % 3.18 %
Intraday 3 1.15 % 1.77 % 2.33 % 2.47 %
Intraday 4 1.28 % 2.02 % 2.51 % 2.08 %
Intraday 5 1.18 % 1.72 % 2.37 % 2.35 %
Intraday 6 0.70 % 0.70 % 1.10 % 2.47 %
Reliability (or calibration) of probabilistic forecasts is the key requirement
Sharpness is important, but it is not the critical factor
© 2011 11EWEA Annual Conference, 14-17 March 2011
Fuzzy Power Flow Tool
© 2011
Fuzzy Power Flow (FPF)
• Fuzzy numbers for generation and load (active and reactive)
• The midpoint is computed by the deterministic AC power flow
• The FPF consists of a linearization step and a non-iterative algorithm to deal with uncertainties
• Output data
– e.g. fuzzy node voltages’ magnitudes and angles; fuzzy active and reactive power flows; fuzzy active and reactive losses and currents
12EWEA Annual Conference, 14-17 March 2011
00.10.20.30.40.50.60.70.80.9
1
30 40 50 60 70
u(x)
MW
00.10.20.30.40.50.60.70.80.9
1
10 20 30 40 50u(
x)MW
00.10.20.30.40.50.60.70.80.9
1
10 15 20 25 30 35 40
u(x)
MW
Load about 50 MW Load more or less between 30 and 40 MW Load between 15 and 30 MW
© 2011
Demonstration Case Design
13EWEA Annual Conference, 14-17 March 2011
Deterministic AC PowerFlow
AC Fuzzy PowerFlow (ANEMOS.plus)
Network physical data
Conventional generation and load for day D+1
Deterministic andprobabilistic WPF for D+1
(ANEMOS)
Transformation of WPF uncertainty
into fuzzy sets
Running since 25 Oct 2010
1 time per day and for 24 hours of the next day
Fuzzy setsVoltage module and phase
P and Q power flowsActive losses
Q5%
Point Forecast
Q95%
Transmission Network of Portugal 1 time per day and for 24 hours
1 time per day and for 24 hours
forecast launched at 6AM38 Wind farms
6 network nodes~2 GW
© 2011
Output Information
• List of possible bus voltage violations and branch congestion
• Voltage violation: >1.05 pu and <0.95 pu
• Congestion: greater than line limit power
• Severity index of the congestion and voltage violation (in %)
14EWEA Annual Conference, 14-17 March 2011
0 10 20 30 40 50 60 700
0.2
0.4
0.6
0.8
1
apparent Power Flow (MVA)
Severity of the congestion
© 2011
Output Results
15EWEA Annual Conference, 14-17 March 2011
• Possibility of overvoltage situations in two nodes at 9PM 31 Oct
• Possibility of network congestions in two lines on 31 Oct at 9PM
1.03 1.035 1.04 1.045 1.05 1.0550
0.2
0.4
0.6
0.8
1
1.2Node 102911
Voltage (pu) Voltage limit (pu)
1.03 1.035 1.04 1.045 1.05 1.0550
0.2
0.4
0.6
0.8
1
1.2 Node 102662
Voltage (pu) Voltage limit (pu)
700.
00
800.
00
900.
00
1000
.00
1100
.00
1200
.00
1300
.00
1400
.00
1500
.00
0.00
0.20
0.40
0.60
0.80
1.00
1.20line 0399
Apparent Fuzzy Power Flow (MVA)Line Capacity (MVA)
100.00 120.00 140.00 160.00 180.00 200.000
0.2
0.4
0.6
0.8
1
1.2 line 0090
Apparent Fuzzy Power Flow (MVA)Line limit
© 2011
Output Results
16EWEA Annual Conference, 14-17 March 2011
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
3
1 1 1 1 1
3
1
3
2
1
3 3 3
2 2
Number of network congestions
31 Oct 2010
31 network congestion along this day
27 Oct 2010
0 network congestion along this day
© 2011
Conclusions
• The tools were developed according to the end-users prerequisites and necessities
• Robust reserve setting tool
– avoids making assumptions on the errors distributions
– defines the reserve dynamically
– models different attitudes and values of the decision-maker
• Fuzzy power flow tool
– allows the inclusion of probabilistic WPF in day-ahead security evaluation
– contribute to identify weak points of the transmission network during operational phases
• Next step: quantitative and qualitative evaluation results for the whole demonstration period (until June 2011)
17EWEA Annual Conference, 14-17 March 2011