Report Regarding Studies Conducted With Owner's Validated Data

Embed Size (px)

Citation preview

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    1/31

    REPORT REGARDING STUDIES

    CONDUCTED WITH THE OWNERS'VALIDATED DATA FOR THE

    NEW WECC THERMAL TURBINE-

    GOVERNOR MODELING

    Les Pereira (Chair, GMTF)

    Donald Davies (Chair, MDTF)

    Shawn Patterson (Chair, M&VWG)

    Dmitry Kosterev, BPA

    Mark Willis, CAISO

    Governor Modeling Task Force

    WECC Modeling & Validation Work Group

    February 28, 2003

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    2/31

    2

    Report Regarding Studies Conducted With the Owners' Validated Data for the

    New WECC Thermal Turbine-Governor Modeling

    Executive Summary and Recommendations

    This report includes details of simulations performed with validated governor datasubmitted by generator owners for the new thermal governor model developed by the

    Governor Modeling Task Force (GMTF). The Modeling & Validation Work Group

    (M&VWG) and the Technical Studies Subcommittee (TSS) have previously approved thenew thermal governor model, which was developed using approximated data.

    The studies reported herein were conducted using the new dynamic database populated

    with validated governor data from the owners. Study results clearly indicate that the newthermal governor model is more accurate than the existing thermal governor models. It is

    not intended that these studies reproduce in exact detail the events themselves1. Rather it

    is the intent of these studies to demonstrate that the new thermal governor model is

    comparatively more accurate than the existing model as demonstrated by simulations forrandom and staged major generator trip disturbances. In these simulations, the existing

    governor model has been seen to be consistently optimistic. The new model exhibits abetter match to frequency response, flows, and oscillations than with the existing

    governor model. Most of the events studied occurred at WECC system loads of 90000 to

    110000 MW. With higher load levels and flows, it is reasonable to expect that therelative improvement in results with the new model as compared to the old model will

    become even more apparent.

    While the new governor modeling is clearly more accurate than the existing modeling,the GMTF will continue its work to refine the governor modeling in the simulation of

    responses after 20 to 30 seconds when other effects such as AGC need to be addressed.

    Generator owners will likely refine their governor models as more disturbance data isobtained. Also, the introduction of Kaplan hydro turbine models and other modeling

    improvements for both governors and exciters will improve simulation results. The need

    for longer time simulations greater than 20 seconds has to be first established by theWECC. (An example would be the NERC requirements for frequency-responsive

    reserves.) Modeling work will continue with criteria that includes more accurate

    frequency response, generator pickup, oscillations and intertie flows.

    Recommendations

    Based on studies performed with validated governor data submitted by generator ownersfor the new thermal governor model, the GMTF recommends the use of the new thermal

    governor model with generator owners new data in lieu of the existing model and

    existing data for WECC studies for simulations up to 20 seconds.

    1 This can only be possible if every generating unit and every load is accurately modeled dynamically, and

    system voltages and flows are accurately initialized.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    3/31

    3

    Background

    The new thermal governor model was developed using assumed data based on theMay18, 2001 trip test. The GMTF presented the model to WECC in July 2002 after

    extensive studies and a validation effort that included the May 18, 2001 Northwest and

    Hoover generator trip tests, the June 7, 2000 trip test, and verification simulations ofthree other major system disturbances. A comprehensive report titled New Thermal

    Turbine-Governor Modeling for the WECC (Report) was issued by the GMTF and is

    available on the WECC web-site2.

    The model was approved by the MVWG at Roseville on July 16, 2002 and was approved

    by the TSS at Estes Park on August 28, 2002. These approvals were essentially for the

    model, i.e. the ggov1 model and the load controller lcfb1 for the ieeeg1 thermal governormodel, with the understanding that validated data would be obtained from the generator

    owners before use of the model by the WECC members for studies. Additionally,

    presentations were made at the PCC, RITF and OSS at meetings between June and

    October 2002. There was a wide distribution of the Report and the presentations at thevarious meetings.

    Current WECC policy requires that all generation owners submit appropriate computer

    model data to represent their machines and associated equipment along with recorded

    data that validates the accuracy of the computer models. It was therefore required thatthe data for the new models be validated by comparing actual measured electrical power

    output response data of each unit to the computer modeled simulation response.

    To introduce the new governor model to owners and describe the requirements forobtaining validated data, a workshop was conducted by the GMTF at Salt Lake City on

    August 19-20, 2002. To facilitate obtaining validated data for the new model from the

    owners, the GMTF proposed the formation of a Model Data Task Force (MDTF) at thePCC meeting on October 25, 2002. The MDTF was formed with members comprising

    generator owners, and control area and interconnection service provider representatives 3.

    Guidelines for the selection and validation of the owner's governor model were published

    by the GMTF and have been included in the Report. To assist in the selection of the

    parameters of the new model, computer programs were developed that simulated the

    governor performance for a frequency profile input of the May 18, 2001 test, and otherevents. These computer programs were available for use with the GE stability program.

    Additionally, for those owners who did not have the GE program or access to it, a

    spreadsheet simulation tool, based on a linearized version of a Matlab-Simulink programof the ggov1 model, was developed using the modeling technique of frequency profile

    input of the May 18, 2001 test and the October 8, 2002 event. A PTI version of the

    ggov1 model was also developed.

    2 The reference url is http://www.wecc.biz/committees/PCC/TSS/MVWG/thermalgovernor.html3 A list of the MDTF members is given in Appendix 1.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    4/31

    4

    The MDTF conducted an intensive program of assistance, including workshop meetings

    and conference calls, to assist owners to select and validate their governor models by

    January 15th 2003. Over 90% of generator owners responded with data for over 800generators. The MDTF has already released the 2003 Spring & Summer Operating cases

    to WECC members with the new data.

    MDTF Details of Validated Data Submittal from the Owners

    The new governor modeling data were compiled from submittals by generator ownersand the Model Data Task Force members. The following statistics demonstrate the

    significant effort that occurred. There are 828 thermal units generating at least 10 MW in

    the 2003 HS4 operating case. Generator owners or control area/interconnection service

    providers submitted information regarding new governor modeling for 765 of thosethermal units. The dynamic data collected by the MDTF includes 132 units with load

    controllers (that are not base loaded) and 590 base-loaded units. For governors and

    exciters that were not previously modeled, there are 400 new governor models and 100

    new exciter models. The new governor models include 50 new hydro governor models.

    The MDTF was formed by a November 7, 2002 letter from the PCC chair. There wasparticipation from Control Area Operators, Transmission Interconnection Service

    Providers, Generator Owners, and the Governor Modeling Task Force members.

    Although generator owners are responsible to provide model data for their generators, thetask force provides experts to assist generator owners in understanding what is needed for

    simulation models and how to obtain and provide the needed information. The purpose

    of the task force is to assist the generator owners as necessary so they can succeed in

    providing the needed model data. The initial focus of the task force was to assist ownersto provide data for the new governor model. In the future, focus will be placed upon

    improving data for other models such as the generator overexcitation limiters, adding

    governor and exciter data for unmodeled generators, and improving load modeling data.

    To complete the initial focus on populating data for new governor model by January 15,

    2003 the task force conducted two meetings and several conference calls. The purpose ofthese meetings and calls was to train MDTF members regarding new governor model

    data needs and to provide support to MDTF members so they could provide assistance to

    the generator owners. Another important function of the MDTF task force is to provide

    an avenue for identification of and communication with the generator ownersinterconnected to their systems.

    Governor Model Studies of Generator Disturbances

    Recordings of system frequency for the following underfrequency events were made

    available from the WECC website and were used for governor data validation by theowners.

    May 18, 2001 tests (NW and Hoover trips) - 1250 MW and 750 MW

    respectively (10:40 and 10:20 PDT)

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    5/31

    5

    July 27, 2002 (19:19 PDT), Four Corners trip (2065 MW)

    July 15, 2002 (13:04 and 15:12 PDT), NW RAS trip (2350 MW)

    July 17, 2002 (15:41 PDT), NW RAS trip (2350 MW)

    June 6, 2002 (13:47 PDT), PDCI loss (2800 MW)

    October 8, 2002 (15.21 PDT), NW RAS (2900 MW)

    Simulation studies of some of these events have been included in this report.

    Results Comparison

    The following sections of the report includes plots depicting a comparison in resultsbetween:

    1) the present data files,2) the data files with the base load flag, load controller, and other changes submitted to

    the MDTF, and

    3) the actual system performance.

    Note that the results with the new data files are significantly closer to the system

    performance than are those with the old data files. Plots of flow changes on paths,frequency levels, and voltages were reviewed. Representative plots are included in the

    following discussion.

    The following table summarizes generation represented on line and frequency responsivefor the simulations (not base loaded, with active governors):

    Event date PGEN TotalFrequencyresponsive PGEN

    May 18, 2001 92168 MW 51149 MW

    June 6, 2002 110202 MW 63325 MW

    July 17, 2002 119713 MW 68415 MW

    July 27, 2002 102174 MW 51705 MW

    October 8, 2002 103435 MW 54712 MW

    May 18, 2001 System Test NW RAS (1250 MW) Trip

    On May 18, 2001, a WECC system test was performed. Separate tests were conductedincluding 1) Chief Joseph Brake insertion, 2) tripping of Hoover units (750 MW), and 3)

    tripping of Northwest units (1250 MW). Notably, AGC was turned off during the tests tocapture the effect of the governors. Plots are included here for tripping of the Northwestgenerator units.

    The switch deck used to perform the simulation with the alldyns.p epcl included thefollowing records. The switching code is in the first column, the second column contains

    the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    6/31

    6

    Switching Codes -

    TG - Trip generator

    TG 0.0 "CHIEF J5" 13.8 "I "

    TG 0.0 "CHIEF J5" 13.8 "J "

    TG 0.0 "CHIEF J5" 13.8 "K "TG 0.0 "CHIEF J5" 13.8 "M "

    TG 0.0 "COULEE20" 15.0 "1 "

    TG 0.0 "GMS G10 " 13.8 "1 "

    Plots depicting frequency at Malin and flow on Malin-Round Mountain 500 kV line 1 are

    included below. In every plot, blue depicts the present model, red the new, and green

    provides actual traces from system monitors during the disturbance.

    Effect of Governor Blocking

    The M&VWG recommendation for the last several years has been to represent all

    thermal generators larger than 150 MW that are loaded more than 90% with blockedgovernors for simulations. The new governor modeling replaces that approximation with

    a more accurate representation of the individual generators. The following plots compareresults for the May 18 northwest generator trip between a representation with the old

    M&VWG recommendation and the new representation. The turquoise plot provides

    results for the simulation with no governor blocking.

    -10 0 10 20 30 40 50 60

    59.84

    59.86

    59.88

    59.9

    59.92

    59.94

    59.96

    59.98

    60

    60.02MAY 18, 2001 1250 MW NW TRIP Malin Frequency

    Time in Seconds

    Frequency(Hz)

    May 18th test recording

    New thermal governor model

    Existing governor model- without OCSG "blocking'- with OCSG 'blocking'

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    7/31

    7

    -10 0 10 20 30 40 50 60

    100

    150

    200

    250

    300

    350

    400

    Time in secs

    Malin-RdMt#1Lineflow,

    MW

    May 18th 2001 NW 1250 MW Trip Test

    New thermal governor model

    May 18th test recording

    Existing governor model- without OCSG "blocking'- with OCSG 'blocking'

    -10 0 10 20 30 40 50 60

    1.085

    1.09

    1.095

    1.1MAY 18, 2001 NWTRIP Malin Voltage dip

    Time in Seconds

    MalinVoltage(pu)

    Note: The simulated voltage is offset by +.01

    to match initial actual voltage. Initial time is alsooffset to facilitate comparison

    New thermal governor model

    May 18th test recording

    Existing governor model

    - without blocking- with recommended blocking

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    8/31

    8

    -10 0 10 20 30 40 50 60

    995

    1000

    1005

    1010

    1015

    1020

    1025

    1030

    1035MAY 18, 2001 NWTRIP Cols-Brdvw flow

    Time in Seconds

    Cols-BrdvwFlow(MW)

    Note: The simulated flow is offset by +40 to matchinitial actual flow. Initial time is also offset to facilitate

    comparison.

    Esisting governor model- without blocking

    - with recommended blocking

    New thermal governor model

    May 18 test record

    May 18, 2001 System Test Hoover (750 MW) Trip

    On May 18, 2001, a WECC system test was performed. Separate tests were conductedincluding 1) Chief Joseph Brake insertion, 2) tripping of Hoover (750 MW) units, and 3)

    tripping of Northwest (1250 MW) units. Plots are included here for tripping of the

    Hoover generator units.

    The switch deck used to perform the simulation with the alldyns.p epcl included the

    following records. The switching code is in the first column, the second column containsthe time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

    Switching Codes -TG - Trip generator

    TG 0.0 "HOVRA1A2" 16.5 "A1"

    TG 0.0 "HOOVERA6" 16.5 "1 "TG 0.0 "HOOVERA7" 16.5 "1 "

    TG 0.0 "HOVRN1N2" 16.5 "N2"TG 0.0 "HOVRN3N4" 16.5 "N3"TG 0.0 "HOVRN3N4" 16.5 "N4"

    TG 0.0 "HOVRN5N6" 16.5 "N5"

    Plots depicting frequency at Malin and flow on Malin-Round Mountain 500 kV line 1 are

    included below. In every plot, blue depicts the present model, red the new, and green

    provides actual traces from system monitors during the disturbance.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    9/31

    9

    -10 0 10 20 30 40 50 60

    59.9

    59.92

    59.94

    59.96

    59.98

    60

    60.02MAY 18, 2001 Hoover trip Malin Frequency dip

    Time in Seconds

    Frequency(Hz)

    Note: The simulated frequency is offset

    by +0.01 to match initial actual frequency.Initial time is also offset to facilitate comparison.

    May 18 test recording

    Present governor model

    New governor model

    -10 0 10 20 30 40 50 60

    300

    320

    340

    360

    380

    400

    420

    440

    460

    480

    500MAY 18, 2001 Hoover trip Mln-RM flow

    Time in Seconds

    Malin-RM

    Flow(MW)

    Note: The simulated flow is offset by +20 tomatch initial actual flow. Initial time is also offset

    to facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    10/31

    10

    -10 0 10 20 30 40 50 60

    1.09

    1.091

    1.092

    1.093

    1.094

    1.095

    1.096

    1.097

    1.098

    1.099

    1.1MAY 18, 2001 Hoover trip Malin Voltage

    Time in Seconds

    MalinVoltage(pu)

    -10 0 10 20 30 40 50 60

    950

    960

    970

    980

    990

    1000

    1010

    1020

    1030

    1040

    1050MAY 18, 2001 Hoover trip Clstp-Brdvw flow

    Time in Seconds

    Clstp-BrdvwFlow(MW)

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    11/31

    11

    June 6, 2002 NW RAS operation

    On June 6, 2002, the PDCI tripped, first one pole and then the other followed by

    operation of the NW generator tripping RAS.

    The switch deck used to perform the simulation with the alldyns.p epcl included the

    following records. The switching code is in the first column, the second column containsthe time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

    Switching Codes -DB - Delete bus

    DL - Delete line

    DDC - Delete DC line

    TG - Trip generator

    FL - Fault line

    CC - comment

    MBS - Modify shunt

    CC DROP PDCI POLE 3

    CCDDC 0.0 "CELILO3P" 500. "SYLMAR3P" 500.

    DB 0.0 "CELILO1 " 500.

    DB 0.0 "CELILO3 " 230.

    DB 0.0 "SYLMAR1 " 230.

    DB 0.0 "SYLMAR3 " 230.

    CCCC AT 12.0 CYCLES INSERT FORT ROCK SERIES CAPS

    CC

    RC 12.0 "CAPTJACK" 500. "GRIZZLY " 500. "1 " 4

    RC 12.0 "GRIZZLY " 500. "MALIN " 500. "1 " 4

    RC 12.0 "PONDROSA" 500. "SUMMER L" 500. "1 " 4

    CC

    CC AT 90.0 CYCLES INSERT BOTH SHUNT CAPS AT MALIN 500CC

    MBS 90.0 "MALIN " 500. "c1" "R"

    MBS 90.0 "MALIN " 500. "c2" "R"CC

    CC AT 12.45 SECONDS (747 CYCLES) DROP PDCI POLE 4

    CC

    DDC 747.0 "CELILO4P" 500. "SYLMAR4P" 500.

    DB 747.0 "CELILO2 " 500.

    DB 747.0 "CELILO4 " 230.

    DB 747.0 "SYLMAR2 " 230.

    DB 747.0 "SYLMAR4 " 230.CC

    CC AT 16.85 SECONDS (1011 CYCLES) DROP FOLLOWING GEN

    CC AT CHIEF JOSEPH, GRAND COULEE AND MCNARY

    CC (CHIEF JO = 1735 MW, COULEE = 500 MW, MCNARY = 300 MW)

    CC

    TG 1011.0 "CHIEF J5" 13.8 "I "

    TG 1011.0 "CHIEF J5" 13.8 "J "

    TG 1011.0 "CHIEF J5" 13.8 "K "TG 1011.0 "CHIEF J5" 13.8 "M "

    TG 1011.0 "CHIEF J5" 13.8 "N "

    TG 1011.0 "CHIEF J5" 13.8 "O "

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    12/31

    12

    TG 1011.0 "CHIEF J5" 13.8 "P "

    TG 1011.0 "CHIEF J5" 13.8 "Q "

    TG 1011.0 "CHIEF J5" 13.8 "R "

    TG 1011.0 "CHIEF J5" 13.8 "S "

    TG 1011.0 "CHIEF J5" 13.8 "T "TG 1011.0 "CHIEF JO" 13.8 "1 "

    TG 1011.0 "CHIEF JO" 13.8 "2 "TG 1011.0 "CHIEF JO" 13.8 "3 "

    TG 1011.0 "CHIEF JO" 13.8 "D "

    TG 1011.0 "CHIEF JO" 13.8 "E "

    TG 1011.0 "CHIEF JO" 13.8 "F "

    TG 1011.0 "CHIEF JO" 13.8 "G "

    TG 1011.0 "COULEE14" 13.8 "1 "TG 1011.0 "COULEE15" 13.8 "1 "

    TG 1011.0 "COULEE16" 13.8 "1 "

    TG 1011.0 "COULEE17" 13.8 "1 "

    TG 1011.0 "COULEE18" 13.8 "1 "

    TG 1011.0 "MCNARY07" 13.8 "7 "

    TG 1011.0 "MCNARY08" 13.8 "8 "

    TG 1011.0 "MCNARY09" 13.8 "9 "

    TG 1011.0 "MCNARY10" 13.8 "A "TG 1011.0 "MCNARY11" 13.8 "B "

    Plots depicting frequency and voltage at Malin and flows on several significant paths are

    included below. In every plot, blue depicts the present model, red the new, and green

    provides traces from system monitors during the disturbance.

    -10 0 10 20 30 40 50 60

    59.65

    59.7

    59.75

    59.8

    59.85

    59.9

    59.95

    60

    60.05

    06 June 2002 PDCI Trip Malin Freq dip

    Time in Seconds

    MalinFrequency(Hz)

    Note: The simulated frequency isoffset by -0.03 Hz to match initialactual frequency. Initial time is also

    offset to facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    13/31

    13

    -10 0 10 20 30 40 50 60

    0.9

    0.95

    1

    1.05

    1.1

    1.15

    06 June 2002 PDCI Trip Malin Volt dip

    Time in Seconds

    MalinVoltage(pu)

    Note: The simulated voltage is offset by+0.02 pu to match actual initial voltages.Initial time is also offset to facilitate

    comparison.

    -10 0 10 20 30 40 50 60

    1000

    1200

    1400

    1600

    1800

    2000

    220006 June 2002 PDCI Trip Mln-RM Flow

    Time in Seconds

    MW

    FlowonMalin-RM

    Line1

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    14/31

    14

    -10 0 10 20 30 40 50 60

    400

    600

    800

    1000

    1200

    1400

    06 June 2002 PDCI Trip Midway-Vincent Flow

    Time in Seconds

    MW

    FlowonMidway-VincentLine1

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    15/31

    15

    -10 0 10 20 30 40 50 60

    750

    800

    850

    900

    950

    1000

    105006 June 2002 PDCI Trip Palo Verde-Devers Flow

    Time in Seconds

    MW

    FlowonPV-DeversLine

    Note: The simulated flow is offset by +50 MWto match initial actual flow. Initial time is alsooffset t o facilitate comparison.

    -10 0 10 20 30 40 50 60

    0.99

    1

    1.01

    1.02

    1.03

    1.04

    1.05

    1.06

    1.07

    1.0806 June 2002 PDCI Trip Vincent Volt dip

    Time in Seconds

    VincentVoltage(pu)

    Note: The simulated voltage is offsetby -0.02 pu to match initial actual voltage.

    Initial time is also offset to facilitatecomparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    16/31

    16

    July 17, 2002 NW RAS operation

    On July 17, 2002 the Northwest RAS operated tripping northwest generation.

    The switch deck used to perform the simulation with the alldyns.p epcl included the

    following records. The switching code is in the first column, the second column contains

    the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

    Switching Codes -DL - Delete line

    TG - Trip generator

    FL - Fault line

    CC - comment

    MBS - Modify shunt

    DL 0.0 "MIN287 " 287 "KIT287 " 287 "1 "TG 0.0 "KMO G1 " 13.8 "1 "

    TG 0.0 "KMO G2 " 13.8 "1 "

    TG 0.0 "KMO G3 " 13.8 "1 "

    CC fault p.u. clear clearCC imp. dist from to

    CC time bus1_name bkv bus2_name bkv ckt sec r x from cl1 cl2

    FL 276 "GRIZZLY " 500. "MALIN" 500. "1 " 1 0 0 1 279 280

    CC 615 MW at Chief Joseph

    TG 293 "CHIEF J5" 13.8 "O "

    TG 293 "CHIEF J5" 13.8 "P "TG 293 "CHIEF J5" 13.8 "Q "

    TG 293 "CHIEF J5" 13.8 "R "

    TG 293 "CHIEF J5" 13.8 "S "

    TG 293 "CHIEF J5" 13.8 "T "

    CC 324 MW at Chief Joseph */

    TG 293 "CHIEF J2" 13.8 "5 "

    TG 293 "CHIEF J2" 13.8 "6 "TG 293 "CHIEF J2" 13.8 "7 "TG 293 "CHIEF J2" 13.8 "8 "

    CC 386 MW at Chief Joseph */

    TG 293 "CHIEF JO" 13.8 "1 "

    TG 293 "CHIEF JO" 13.8 "2 "

    TG 293 "CHIEF JO" 13.8 "3 "

    TG 293 "CHIEF JO" 13.8 "D "

    TG 293 "CHIEF JO" 13.8 "E "

    CC 605 MW at Grand Coulee PH3 */TG 293 "COULEE21" 15.0 "1 "

    CC 397 MW at Grand Coulee */TG 293 "COULEE06" 13.8 "1 "

    TG 293 "COULEE07" 13.8 "1 "TG 293 "COULEE08" 13.8 "1 "

    TG 293 "COULEE09" 13.8 "1 "

    CC 170 MW at Wanapum */

    TG 293 "WANAPUM2" 13.8 "7 "

    TG 293 "WANAPUM2" 13.8 "9 "

    CC 230 MW at Rocky Reach */TG 293 "ROCKY RH" 15.0 "7 "

    TG 293 "RRCH8-11" 15.0 "A "

    CC Insert Chief Joseph braking resistor */

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    17/31

    17

    MBS 293 "CHIEF JO" 230 "bB" "A" 14. 0.0

    MBS 323 "CHIEF JO" 230 "bB" "D"

    C

    Plots depicting frequency and voltage at Malin and flows on several significant paths areincluded below. In every plot, blue depicts the present model, red the new, and green

    provides traces from system monitors during the disturbance.

    -10 0 10 20 30 40 50 60

    59.65

    59.7

    59.75

    59.8

    59.85

    59.9

    59.95

    60

    17July2002 NWRAS Malin Frequency dip

    Time in Seconds

    Frequency

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    18/31

    18

    -10 0 10 20 30 40 50 60

    1.06

    1.07

    1.08

    1.09

    1.1

    1.11

    1.1217July2002 NWRAS Malin Voltage dip

    Time in Seconds

    Voltage

    Note: The simulated voltage is offset by 0.003to match initial actual voltage. Initial time is also

    offset to facilitate comparison.

    -10 0 10 20 30 40 50 60

    -100

    0

    100

    200

    300

    400

    500

    600

    700

    80017July2002 NWRAS Malin-Round Mountain Line 1 Flow

    Time in Seconds

    MW

    Flow

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    19/31

    19

    -10 0 10 20 30 40 50 60

    0

    50

    100

    150

    200

    250

    300

    350

    40017July2002 NWRAS Midway-Vincent Line 1 Flow

    Time in Seconds

    MW

    Flow

    Note: The simulated flow is offset by -100 MWto match initial actual flow. Initial time is also

    offset to facilitate comparison

    -10 0 10 20 30 40 50 60

    600

    650

    700

    750

    800

    850

    900

    950

    100017July2002 NWRAS PV-Devers Line Flow

    Time in Seconds

    MW

    Flow

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    20/31

    20

    -10 0 10 20 30 40 50 60

    460

    470

    480

    490

    500

    510

    520

    530

    540

    550

    56017July2002 NWRAS Colstrip-Broadview Line 1 Flow

    Time in Seconds

    MW

    Flow

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    21/31

    21

    July 27, 2002 Four Corners Plant trip

    On July 27, 2002 all five units at the Four Corners generating station tripped.

    The switch deck used to perform the simulation with the alldyns.p epcl included the

    following records. The switching code is in the first column, the second column contains

    the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

    Switching Codes -

    TG - Trip generator

    TG 0.0 "FCNGEN 1" 20.0 "1 "

    TG 0.0 "FCNGEN 2" 20.0 "1 "TG 870. "FCNGEN 3" 20.0 "1 "

    TG 870. "FCNGN4CC" 22.0 "4 "

    TG 870. "FCNGN5CC" 22.0 "5 "

    Plots depicting frequency and voltage at Malin and flows on several significant paths areincluded below. In every plot, blue depicts the old model, red the new, and green

    provides traces from system monitors during the disturbance.

    -10 0 10 20 30 40 50 60

    59.8

    59.82

    59.84

    59.86

    59.88

    59.9

    59.92

    59.94

    59.96

    59.98

    60

    27 July 2002 FCorn Trip Malin Freq dip

    Time in Seconds

    MalinFrequency(Hz)

    Note: The simulated frequency is offset by -.015

    to match initial actual frequency. Initial timeis also offset to facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    22/31

    22

    -10 0 10 20 30 40 50 60

    1.03

    1.04

    1.05

    1.06

    1.07

    1.08

    1.09

    1.1

    1.1127 July 2002 FCorn Trip Malin Volt dip

    Time in Seconds

    MalinVoltage(pu)

    Note: The simulated voltage is offset by +.03 to matchinitial actual voltage. Initial time is also offset to facilitatecomparison.

    -10 0 10 20 30 40 50 60

    950

    1000

    1050

    1100

    1150

    1200

    1250

    130027 July 2002 FCorn Trip Mln-RM Flow

    Time in Seconds

    MW

    FlowonMalin-RMLine1

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    23/31

    23

    -10 0 10 20 30 40 50 60

    200

    250

    300

    350

    400

    45027 July 2002 FCorn Trip Midway-Vincent Flow

    Time in Seconds

    MW

    FlowonMidway-VincentLine1

    -10 0 10 20 30 40 50 60

    400

    450

    500

    550

    600

    650

    700

    750

    80027 July 2002 FCorn Trip Palo Verde-Devers Flow

    Time in Seconds

    MW

    FlowonPV-DeversLine

    Note: The simulated flow is offset by -60 MW

    to match initial actual flow. Initial time is alsooffset to facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    24/31

    24

    -10 0 10 20 30 40 50 60

    850

    855

    860

    865

    870

    875

    880

    885

    890

    895

    90027 July 2002 FCorn Trip Colstrip-Broadview Line 1 Flow

    Time in Seconds

    MW

    FlowonColstrip-BroadviewLine1

    -10 0 10 20 30 40 50 60

    1.04

    1.045

    1.05

    1.055

    1.06

    1.065

    1.0727 July 2002 FCorn Trip Vincent Volt dip

    Time in Seconds

    VincentVoltage(pu)

    Note: The simulated voltage is offset by -0.04to match initial actual voltage. Initial time is also offsetto facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    25/31

    25

    Oct 8, 2002 Line trip and NW RAS operation

    On October 8, 2002 the Northwest RAS operated tripping northwest generation.

    The switch deck used to perform the simulation with the alldyns.p epcl included the

    following records. The switching code is in the first column, the second column contains

    the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:

    Switching Codes -

    DL - Delete lineTG - Trip generator

    CC - comment

    DL 0.0 "PONDROSA" 500 "SUMMER L" 500 "1 "

    DL 0.0 "MALIN " 500 "SUMMER L" 500 "1 "

    DL 0.0 "BURNS " 500 "SUMMER L" 500 "1 "CC /* 677 MW at Chief Joseph */

    TG 17 "CHIEF J5" 13.8 "N "

    TG 17 "CHIEF J5" 13.8 "O "TG 17 "CHIEF J5" 13.8 "P "

    TG 17 "CHIEF J5" 13.8 "Q "

    TG 17 "CHIEF J5" 13.8 "R "

    TG 17 "CHIEF J5" 13.8 "S "

    TG 17 "CHIEF J5" 13.8 "T "CC /* 520 MW at Grand Coulee */

    TG 17 "COULEE01" 13.8 "1 "TG 17 "COULEE02" 13.8 "1 "

    TG 17 "COULEE03" 13.8 "1 "

    TG 17 "COULEE04" 13.8 "1 "

    TG 17 "COULEE05" 13.8 "1 "

    CC /* 307 MW at Grand Coulee */

    TG 17 "COULEE06" 13.8 "1 "

    TG 17 "COULEE07" 13.8 "1 "

    TG 17 "COULEE08" 13.8 "1 "CC /* 490 MW at Grand Coulee #20 */

    TG 17 "COULEE20" 15.0 "1 "

    CC /* 551 MW at Grand Coulee #24 */

    TG 17 "COULEE24" 15.0 "1 "

    CC /* 167 MW at Wanapum */

    TG 17 "WANAPUM2" 13.8 "7 "

    TG 17 "WANAPUM2" 13.8 "A "

    CC /* 196 MW at Rocky Reach */TG 17 "ROCKY RH" 15.0 "7 "

    TG 17 "RRCH8-11" 15.0 "B "

    Plots depicting frequency and voltage at Malin and flows on several significant paths are

    included below. In every plot, blue depicts the present model, red the new, and greenprovides traces from system monitors during the disturbance. Some of the plots below

    also include a turquoise trace with PPSM monitor data. The other actual data (green) in

    this report is from the PMU monitors.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    26/31

    26

    -10 0 10 20 30 40 50 60

    59.6

    59.65

    59.7

    59.75

    59.8

    59.85

    59.9

    59.95

    60

    8 Oct 2002 NWRas Malin Freq dip

    Time in Seconds

    MalinFrequency(Hz)

    -10 0 10 20 30 40 50 60

    1.06

    1.08

    1.1

    1.12

    1.14

    1.16

    8 Oct 2002 NWRas Malin Volt dip

    Time in Seconds

    MalinVoltage(pu)

    Note: The simulated voltage is offset by +.01 t omatch initial actual voltage. Initial time is also offsetto facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    27/31

    27

    -10 0 10 20 30 40 50 60

    300

    400

    500

    600

    700

    800

    900

    1000

    11008 Oct 2002 NWRas Mln-RM Flow

    Time in Seconds

    MW

    FlowonMalin-RMLine1

    Note: The simulated flow is offset by -20 to matchinitial actual flow. Initial time is also offset to facilitate

    comparison.

    -10 0 10 20 30 40 50 60

    1100

    1150

    1200

    1250

    1300

    1350

    14008 Oct 2002 NWRas Palo Verde-Devers Flow

    Time in Seconds

    MW

    FlowonPV-DeversLine

    Note: The simulated flow is offset by -20 to match initial

    actual flow. Initial time is also offset to facilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    28/31

    28

    -10 0 10 20 30 40 50 60

    880

    900

    920

    940

    960

    980

    1000

    1020

    1040

    1060

    10808 Oct 2002 NWRas Colstrip-Broadview Line 1 Flow

    Time in Seconds

    MW

    FlowonColstrip-BroadviewLine1

    Note: The simulated flow is offset by +30 to matchinitial actual flow. Initial time is also offset to

    facilitate comparison.

    -10 0 10 20 30 40 50 60

    1.025

    1.03

    1.035

    1.04

    1.045

    1.05

    1.055

    1.06

    1.065

    1.078 Oct 2002 NWRas Vincent Volt dip

    Time in Seconds

    VincentVoltage(pu)

    Note: The simulated voltage is offset by -0.015 to match

    initial actual voltage. Initial time is also offset to facilitate

    comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    29/31

    29

    -10 0 10 20 30 40 50 60

    200

    300

    400

    500

    600

    700

    800

    900

    10008 Oct 2002 NWRas Custer-Ingledow Line Flow

    Time in Seconds

    MW

    FlowonCuster-IngledowLine

    Note: The simulated flow is offset by -40 to matchinitial actual flow. Initial time is also offset tofacilitate comparison.

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    30/31

    30

    APPENDIX 1

    MODEL DATA TASK FORCE (MDTF) PARTICIPANTS

    Baj Agrawal APS

    Jeffrey Scott AVAKai C Lee BCHA

    Barry Francis BEPC

    Dmitry Kosterev BPATXavier Baldwin BURB

    Alan Roth CALP

    Mario Lara CFE

    Bert E. Hoffman CHPDMark Willis CISO

    Romulo F Barreno DENA

    Ben Supremo DENA

    Jerry Kyle DOPDDavid Tovar EPE

    Wayne Kunkel GCPDDavid Barrajas IID

    Mark Hanson IPC

    John (Gang-Kung) Hu LDWPMike Kramer MID

    Robert Jenkins MIR

    Les Pereira NCPA

    Helena Ho NEVPMarc A. Kodis NRG

    John Cummings NWMT

    Craig Quist PACBill Hall PAC

    Mike Okapal PAC

    Ashok Agarwal PASASherman Chen PG&E

    Jon Eric Thalman PG&E

    Richard J. Goddard PGE

    Kenneth Dillon PGEGeorge Nail PNM

    Bob Johnson PSC

    Tom Green PSCJoe Seabrook PSE

    John Phillips PSE

    Joseph W. Milton REINam Nguyen SCE

    Fred Ojima SCL

    Abbas Abed SDGE

    Dilip Mahendra SMUD

  • 7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data

    31/31

    31

    Zeina Randall SPP

    John Hernandez SRP

    John Kehler TAAKenneth Peck TEP

    Chris Shultz TPWR

    Vince Leung TSGTShawn Patterson USBR

    John Greenlaw WACM

    Doug Smith WAPADonald Davies (Chair) WECC

    Andy Schuetzinger