Upload
aayush-agarwal
View
221
Download
0
Embed Size (px)
Citation preview
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
1/31
REPORT REGARDING STUDIES
CONDUCTED WITH THE OWNERS'VALIDATED DATA FOR THE
NEW WECC THERMAL TURBINE-
GOVERNOR MODELING
Les Pereira (Chair, GMTF)
Donald Davies (Chair, MDTF)
Shawn Patterson (Chair, M&VWG)
Dmitry Kosterev, BPA
Mark Willis, CAISO
Governor Modeling Task Force
WECC Modeling & Validation Work Group
February 28, 2003
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
2/31
2
Report Regarding Studies Conducted With the Owners' Validated Data for the
New WECC Thermal Turbine-Governor Modeling
Executive Summary and Recommendations
This report includes details of simulations performed with validated governor datasubmitted by generator owners for the new thermal governor model developed by the
Governor Modeling Task Force (GMTF). The Modeling & Validation Work Group
(M&VWG) and the Technical Studies Subcommittee (TSS) have previously approved thenew thermal governor model, which was developed using approximated data.
The studies reported herein were conducted using the new dynamic database populated
with validated governor data from the owners. Study results clearly indicate that the newthermal governor model is more accurate than the existing thermal governor models. It is
not intended that these studies reproduce in exact detail the events themselves1. Rather it
is the intent of these studies to demonstrate that the new thermal governor model is
comparatively more accurate than the existing model as demonstrated by simulations forrandom and staged major generator trip disturbances. In these simulations, the existing
governor model has been seen to be consistently optimistic. The new model exhibits abetter match to frequency response, flows, and oscillations than with the existing
governor model. Most of the events studied occurred at WECC system loads of 90000 to
110000 MW. With higher load levels and flows, it is reasonable to expect that therelative improvement in results with the new model as compared to the old model will
become even more apparent.
While the new governor modeling is clearly more accurate than the existing modeling,the GMTF will continue its work to refine the governor modeling in the simulation of
responses after 20 to 30 seconds when other effects such as AGC need to be addressed.
Generator owners will likely refine their governor models as more disturbance data isobtained. Also, the introduction of Kaplan hydro turbine models and other modeling
improvements for both governors and exciters will improve simulation results. The need
for longer time simulations greater than 20 seconds has to be first established by theWECC. (An example would be the NERC requirements for frequency-responsive
reserves.) Modeling work will continue with criteria that includes more accurate
frequency response, generator pickup, oscillations and intertie flows.
Recommendations
Based on studies performed with validated governor data submitted by generator ownersfor the new thermal governor model, the GMTF recommends the use of the new thermal
governor model with generator owners new data in lieu of the existing model and
existing data for WECC studies for simulations up to 20 seconds.
1 This can only be possible if every generating unit and every load is accurately modeled dynamically, and
system voltages and flows are accurately initialized.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
3/31
3
Background
The new thermal governor model was developed using assumed data based on theMay18, 2001 trip test. The GMTF presented the model to WECC in July 2002 after
extensive studies and a validation effort that included the May 18, 2001 Northwest and
Hoover generator trip tests, the June 7, 2000 trip test, and verification simulations ofthree other major system disturbances. A comprehensive report titled New Thermal
Turbine-Governor Modeling for the WECC (Report) was issued by the GMTF and is
available on the WECC web-site2.
The model was approved by the MVWG at Roseville on July 16, 2002 and was approved
by the TSS at Estes Park on August 28, 2002. These approvals were essentially for the
model, i.e. the ggov1 model and the load controller lcfb1 for the ieeeg1 thermal governormodel, with the understanding that validated data would be obtained from the generator
owners before use of the model by the WECC members for studies. Additionally,
presentations were made at the PCC, RITF and OSS at meetings between June and
October 2002. There was a wide distribution of the Report and the presentations at thevarious meetings.
Current WECC policy requires that all generation owners submit appropriate computer
model data to represent their machines and associated equipment along with recorded
data that validates the accuracy of the computer models. It was therefore required thatthe data for the new models be validated by comparing actual measured electrical power
output response data of each unit to the computer modeled simulation response.
To introduce the new governor model to owners and describe the requirements forobtaining validated data, a workshop was conducted by the GMTF at Salt Lake City on
August 19-20, 2002. To facilitate obtaining validated data for the new model from the
owners, the GMTF proposed the formation of a Model Data Task Force (MDTF) at thePCC meeting on October 25, 2002. The MDTF was formed with members comprising
generator owners, and control area and interconnection service provider representatives 3.
Guidelines for the selection and validation of the owner's governor model were published
by the GMTF and have been included in the Report. To assist in the selection of the
parameters of the new model, computer programs were developed that simulated the
governor performance for a frequency profile input of the May 18, 2001 test, and otherevents. These computer programs were available for use with the GE stability program.
Additionally, for those owners who did not have the GE program or access to it, a
spreadsheet simulation tool, based on a linearized version of a Matlab-Simulink programof the ggov1 model, was developed using the modeling technique of frequency profile
input of the May 18, 2001 test and the October 8, 2002 event. A PTI version of the
ggov1 model was also developed.
2 The reference url is http://www.wecc.biz/committees/PCC/TSS/MVWG/thermalgovernor.html3 A list of the MDTF members is given in Appendix 1.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
4/31
4
The MDTF conducted an intensive program of assistance, including workshop meetings
and conference calls, to assist owners to select and validate their governor models by
January 15th 2003. Over 90% of generator owners responded with data for over 800generators. The MDTF has already released the 2003 Spring & Summer Operating cases
to WECC members with the new data.
MDTF Details of Validated Data Submittal from the Owners
The new governor modeling data were compiled from submittals by generator ownersand the Model Data Task Force members. The following statistics demonstrate the
significant effort that occurred. There are 828 thermal units generating at least 10 MW in
the 2003 HS4 operating case. Generator owners or control area/interconnection service
providers submitted information regarding new governor modeling for 765 of thosethermal units. The dynamic data collected by the MDTF includes 132 units with load
controllers (that are not base loaded) and 590 base-loaded units. For governors and
exciters that were not previously modeled, there are 400 new governor models and 100
new exciter models. The new governor models include 50 new hydro governor models.
The MDTF was formed by a November 7, 2002 letter from the PCC chair. There wasparticipation from Control Area Operators, Transmission Interconnection Service
Providers, Generator Owners, and the Governor Modeling Task Force members.
Although generator owners are responsible to provide model data for their generators, thetask force provides experts to assist generator owners in understanding what is needed for
simulation models and how to obtain and provide the needed information. The purpose
of the task force is to assist the generator owners as necessary so they can succeed in
providing the needed model data. The initial focus of the task force was to assist ownersto provide data for the new governor model. In the future, focus will be placed upon
improving data for other models such as the generator overexcitation limiters, adding
governor and exciter data for unmodeled generators, and improving load modeling data.
To complete the initial focus on populating data for new governor model by January 15,
2003 the task force conducted two meetings and several conference calls. The purpose ofthese meetings and calls was to train MDTF members regarding new governor model
data needs and to provide support to MDTF members so they could provide assistance to
the generator owners. Another important function of the MDTF task force is to provide
an avenue for identification of and communication with the generator ownersinterconnected to their systems.
Governor Model Studies of Generator Disturbances
Recordings of system frequency for the following underfrequency events were made
available from the WECC website and were used for governor data validation by theowners.
May 18, 2001 tests (NW and Hoover trips) - 1250 MW and 750 MW
respectively (10:40 and 10:20 PDT)
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
5/31
5
July 27, 2002 (19:19 PDT), Four Corners trip (2065 MW)
July 15, 2002 (13:04 and 15:12 PDT), NW RAS trip (2350 MW)
July 17, 2002 (15:41 PDT), NW RAS trip (2350 MW)
June 6, 2002 (13:47 PDT), PDCI loss (2800 MW)
October 8, 2002 (15.21 PDT), NW RAS (2900 MW)
Simulation studies of some of these events have been included in this report.
Results Comparison
The following sections of the report includes plots depicting a comparison in resultsbetween:
1) the present data files,2) the data files with the base load flag, load controller, and other changes submitted to
the MDTF, and
3) the actual system performance.
Note that the results with the new data files are significantly closer to the system
performance than are those with the old data files. Plots of flow changes on paths,frequency levels, and voltages were reviewed. Representative plots are included in the
following discussion.
The following table summarizes generation represented on line and frequency responsivefor the simulations (not base loaded, with active governors):
Event date PGEN TotalFrequencyresponsive PGEN
May 18, 2001 92168 MW 51149 MW
June 6, 2002 110202 MW 63325 MW
July 17, 2002 119713 MW 68415 MW
July 27, 2002 102174 MW 51705 MW
October 8, 2002 103435 MW 54712 MW
May 18, 2001 System Test NW RAS (1250 MW) Trip
On May 18, 2001, a WECC system test was performed. Separate tests were conductedincluding 1) Chief Joseph Brake insertion, 2) tripping of Hoover units (750 MW), and 3)
tripping of Northwest units (1250 MW). Notably, AGC was turned off during the tests tocapture the effect of the governors. Plots are included here for tripping of the Northwestgenerator units.
The switch deck used to perform the simulation with the alldyns.p epcl included thefollowing records. The switching code is in the first column, the second column contains
the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
6/31
6
Switching Codes -
TG - Trip generator
TG 0.0 "CHIEF J5" 13.8 "I "
TG 0.0 "CHIEF J5" 13.8 "J "
TG 0.0 "CHIEF J5" 13.8 "K "TG 0.0 "CHIEF J5" 13.8 "M "
TG 0.0 "COULEE20" 15.0 "1 "
TG 0.0 "GMS G10 " 13.8 "1 "
Plots depicting frequency at Malin and flow on Malin-Round Mountain 500 kV line 1 are
included below. In every plot, blue depicts the present model, red the new, and green
provides actual traces from system monitors during the disturbance.
Effect of Governor Blocking
The M&VWG recommendation for the last several years has been to represent all
thermal generators larger than 150 MW that are loaded more than 90% with blockedgovernors for simulations. The new governor modeling replaces that approximation with
a more accurate representation of the individual generators. The following plots compareresults for the May 18 northwest generator trip between a representation with the old
M&VWG recommendation and the new representation. The turquoise plot provides
results for the simulation with no governor blocking.
-10 0 10 20 30 40 50 60
59.84
59.86
59.88
59.9
59.92
59.94
59.96
59.98
60
60.02MAY 18, 2001 1250 MW NW TRIP Malin Frequency
Time in Seconds
Frequency(Hz)
May 18th test recording
New thermal governor model
Existing governor model- without OCSG "blocking'- with OCSG 'blocking'
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
7/31
7
-10 0 10 20 30 40 50 60
100
150
200
250
300
350
400
Time in secs
Malin-RdMt#1Lineflow,
MW
May 18th 2001 NW 1250 MW Trip Test
New thermal governor model
May 18th test recording
Existing governor model- without OCSG "blocking'- with OCSG 'blocking'
-10 0 10 20 30 40 50 60
1.085
1.09
1.095
1.1MAY 18, 2001 NWTRIP Malin Voltage dip
Time in Seconds
MalinVoltage(pu)
Note: The simulated voltage is offset by +.01
to match initial actual voltage. Initial time is alsooffset to facilitate comparison
New thermal governor model
May 18th test recording
Existing governor model
- without blocking- with recommended blocking
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
8/31
8
-10 0 10 20 30 40 50 60
995
1000
1005
1010
1015
1020
1025
1030
1035MAY 18, 2001 NWTRIP Cols-Brdvw flow
Time in Seconds
Cols-BrdvwFlow(MW)
Note: The simulated flow is offset by +40 to matchinitial actual flow. Initial time is also offset to facilitate
comparison.
Esisting governor model- without blocking
- with recommended blocking
New thermal governor model
May 18 test record
May 18, 2001 System Test Hoover (750 MW) Trip
On May 18, 2001, a WECC system test was performed. Separate tests were conductedincluding 1) Chief Joseph Brake insertion, 2) tripping of Hoover (750 MW) units, and 3)
tripping of Northwest (1250 MW) units. Plots are included here for tripping of the
Hoover generator units.
The switch deck used to perform the simulation with the alldyns.p epcl included the
following records. The switching code is in the first column, the second column containsthe time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
Switching Codes -TG - Trip generator
TG 0.0 "HOVRA1A2" 16.5 "A1"
TG 0.0 "HOOVERA6" 16.5 "1 "TG 0.0 "HOOVERA7" 16.5 "1 "
TG 0.0 "HOVRN1N2" 16.5 "N2"TG 0.0 "HOVRN3N4" 16.5 "N3"TG 0.0 "HOVRN3N4" 16.5 "N4"
TG 0.0 "HOVRN5N6" 16.5 "N5"
Plots depicting frequency at Malin and flow on Malin-Round Mountain 500 kV line 1 are
included below. In every plot, blue depicts the present model, red the new, and green
provides actual traces from system monitors during the disturbance.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
9/31
9
-10 0 10 20 30 40 50 60
59.9
59.92
59.94
59.96
59.98
60
60.02MAY 18, 2001 Hoover trip Malin Frequency dip
Time in Seconds
Frequency(Hz)
Note: The simulated frequency is offset
by +0.01 to match initial actual frequency.Initial time is also offset to facilitate comparison.
May 18 test recording
Present governor model
New governor model
-10 0 10 20 30 40 50 60
300
320
340
360
380
400
420
440
460
480
500MAY 18, 2001 Hoover trip Mln-RM flow
Time in Seconds
Malin-RM
Flow(MW)
Note: The simulated flow is offset by +20 tomatch initial actual flow. Initial time is also offset
to facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
10/31
10
-10 0 10 20 30 40 50 60
1.09
1.091
1.092
1.093
1.094
1.095
1.096
1.097
1.098
1.099
1.1MAY 18, 2001 Hoover trip Malin Voltage
Time in Seconds
MalinVoltage(pu)
-10 0 10 20 30 40 50 60
950
960
970
980
990
1000
1010
1020
1030
1040
1050MAY 18, 2001 Hoover trip Clstp-Brdvw flow
Time in Seconds
Clstp-BrdvwFlow(MW)
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
11/31
11
June 6, 2002 NW RAS operation
On June 6, 2002, the PDCI tripped, first one pole and then the other followed by
operation of the NW generator tripping RAS.
The switch deck used to perform the simulation with the alldyns.p epcl included the
following records. The switching code is in the first column, the second column containsthe time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
Switching Codes -DB - Delete bus
DL - Delete line
DDC - Delete DC line
TG - Trip generator
FL - Fault line
CC - comment
MBS - Modify shunt
CC DROP PDCI POLE 3
CCDDC 0.0 "CELILO3P" 500. "SYLMAR3P" 500.
DB 0.0 "CELILO1 " 500.
DB 0.0 "CELILO3 " 230.
DB 0.0 "SYLMAR1 " 230.
DB 0.0 "SYLMAR3 " 230.
CCCC AT 12.0 CYCLES INSERT FORT ROCK SERIES CAPS
CC
RC 12.0 "CAPTJACK" 500. "GRIZZLY " 500. "1 " 4
RC 12.0 "GRIZZLY " 500. "MALIN " 500. "1 " 4
RC 12.0 "PONDROSA" 500. "SUMMER L" 500. "1 " 4
CC
CC AT 90.0 CYCLES INSERT BOTH SHUNT CAPS AT MALIN 500CC
MBS 90.0 "MALIN " 500. "c1" "R"
MBS 90.0 "MALIN " 500. "c2" "R"CC
CC AT 12.45 SECONDS (747 CYCLES) DROP PDCI POLE 4
CC
DDC 747.0 "CELILO4P" 500. "SYLMAR4P" 500.
DB 747.0 "CELILO2 " 500.
DB 747.0 "CELILO4 " 230.
DB 747.0 "SYLMAR2 " 230.
DB 747.0 "SYLMAR4 " 230.CC
CC AT 16.85 SECONDS (1011 CYCLES) DROP FOLLOWING GEN
CC AT CHIEF JOSEPH, GRAND COULEE AND MCNARY
CC (CHIEF JO = 1735 MW, COULEE = 500 MW, MCNARY = 300 MW)
CC
TG 1011.0 "CHIEF J5" 13.8 "I "
TG 1011.0 "CHIEF J5" 13.8 "J "
TG 1011.0 "CHIEF J5" 13.8 "K "TG 1011.0 "CHIEF J5" 13.8 "M "
TG 1011.0 "CHIEF J5" 13.8 "N "
TG 1011.0 "CHIEF J5" 13.8 "O "
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
12/31
12
TG 1011.0 "CHIEF J5" 13.8 "P "
TG 1011.0 "CHIEF J5" 13.8 "Q "
TG 1011.0 "CHIEF J5" 13.8 "R "
TG 1011.0 "CHIEF J5" 13.8 "S "
TG 1011.0 "CHIEF J5" 13.8 "T "TG 1011.0 "CHIEF JO" 13.8 "1 "
TG 1011.0 "CHIEF JO" 13.8 "2 "TG 1011.0 "CHIEF JO" 13.8 "3 "
TG 1011.0 "CHIEF JO" 13.8 "D "
TG 1011.0 "CHIEF JO" 13.8 "E "
TG 1011.0 "CHIEF JO" 13.8 "F "
TG 1011.0 "CHIEF JO" 13.8 "G "
TG 1011.0 "COULEE14" 13.8 "1 "TG 1011.0 "COULEE15" 13.8 "1 "
TG 1011.0 "COULEE16" 13.8 "1 "
TG 1011.0 "COULEE17" 13.8 "1 "
TG 1011.0 "COULEE18" 13.8 "1 "
TG 1011.0 "MCNARY07" 13.8 "7 "
TG 1011.0 "MCNARY08" 13.8 "8 "
TG 1011.0 "MCNARY09" 13.8 "9 "
TG 1011.0 "MCNARY10" 13.8 "A "TG 1011.0 "MCNARY11" 13.8 "B "
Plots depicting frequency and voltage at Malin and flows on several significant paths are
included below. In every plot, blue depicts the present model, red the new, and green
provides traces from system monitors during the disturbance.
-10 0 10 20 30 40 50 60
59.65
59.7
59.75
59.8
59.85
59.9
59.95
60
60.05
06 June 2002 PDCI Trip Malin Freq dip
Time in Seconds
MalinFrequency(Hz)
Note: The simulated frequency isoffset by -0.03 Hz to match initialactual frequency. Initial time is also
offset to facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
13/31
13
-10 0 10 20 30 40 50 60
0.9
0.95
1
1.05
1.1
1.15
06 June 2002 PDCI Trip Malin Volt dip
Time in Seconds
MalinVoltage(pu)
Note: The simulated voltage is offset by+0.02 pu to match actual initial voltages.Initial time is also offset to facilitate
comparison.
-10 0 10 20 30 40 50 60
1000
1200
1400
1600
1800
2000
220006 June 2002 PDCI Trip Mln-RM Flow
Time in Seconds
MW
FlowonMalin-RM
Line1
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
14/31
14
-10 0 10 20 30 40 50 60
400
600
800
1000
1200
1400
06 June 2002 PDCI Trip Midway-Vincent Flow
Time in Seconds
MW
FlowonMidway-VincentLine1
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
15/31
15
-10 0 10 20 30 40 50 60
750
800
850
900
950
1000
105006 June 2002 PDCI Trip Palo Verde-Devers Flow
Time in Seconds
MW
FlowonPV-DeversLine
Note: The simulated flow is offset by +50 MWto match initial actual flow. Initial time is alsooffset t o facilitate comparison.
-10 0 10 20 30 40 50 60
0.99
1
1.01
1.02
1.03
1.04
1.05
1.06
1.07
1.0806 June 2002 PDCI Trip Vincent Volt dip
Time in Seconds
VincentVoltage(pu)
Note: The simulated voltage is offsetby -0.02 pu to match initial actual voltage.
Initial time is also offset to facilitatecomparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
16/31
16
July 17, 2002 NW RAS operation
On July 17, 2002 the Northwest RAS operated tripping northwest generation.
The switch deck used to perform the simulation with the alldyns.p epcl included the
following records. The switching code is in the first column, the second column contains
the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
Switching Codes -DL - Delete line
TG - Trip generator
FL - Fault line
CC - comment
MBS - Modify shunt
DL 0.0 "MIN287 " 287 "KIT287 " 287 "1 "TG 0.0 "KMO G1 " 13.8 "1 "
TG 0.0 "KMO G2 " 13.8 "1 "
TG 0.0 "KMO G3 " 13.8 "1 "
CC fault p.u. clear clearCC imp. dist from to
CC time bus1_name bkv bus2_name bkv ckt sec r x from cl1 cl2
FL 276 "GRIZZLY " 500. "MALIN" 500. "1 " 1 0 0 1 279 280
CC 615 MW at Chief Joseph
TG 293 "CHIEF J5" 13.8 "O "
TG 293 "CHIEF J5" 13.8 "P "TG 293 "CHIEF J5" 13.8 "Q "
TG 293 "CHIEF J5" 13.8 "R "
TG 293 "CHIEF J5" 13.8 "S "
TG 293 "CHIEF J5" 13.8 "T "
CC 324 MW at Chief Joseph */
TG 293 "CHIEF J2" 13.8 "5 "
TG 293 "CHIEF J2" 13.8 "6 "TG 293 "CHIEF J2" 13.8 "7 "TG 293 "CHIEF J2" 13.8 "8 "
CC 386 MW at Chief Joseph */
TG 293 "CHIEF JO" 13.8 "1 "
TG 293 "CHIEF JO" 13.8 "2 "
TG 293 "CHIEF JO" 13.8 "3 "
TG 293 "CHIEF JO" 13.8 "D "
TG 293 "CHIEF JO" 13.8 "E "
CC 605 MW at Grand Coulee PH3 */TG 293 "COULEE21" 15.0 "1 "
CC 397 MW at Grand Coulee */TG 293 "COULEE06" 13.8 "1 "
TG 293 "COULEE07" 13.8 "1 "TG 293 "COULEE08" 13.8 "1 "
TG 293 "COULEE09" 13.8 "1 "
CC 170 MW at Wanapum */
TG 293 "WANAPUM2" 13.8 "7 "
TG 293 "WANAPUM2" 13.8 "9 "
CC 230 MW at Rocky Reach */TG 293 "ROCKY RH" 15.0 "7 "
TG 293 "RRCH8-11" 15.0 "A "
CC Insert Chief Joseph braking resistor */
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
17/31
17
MBS 293 "CHIEF JO" 230 "bB" "A" 14. 0.0
MBS 323 "CHIEF JO" 230 "bB" "D"
C
Plots depicting frequency and voltage at Malin and flows on several significant paths areincluded below. In every plot, blue depicts the present model, red the new, and green
provides traces from system monitors during the disturbance.
-10 0 10 20 30 40 50 60
59.65
59.7
59.75
59.8
59.85
59.9
59.95
60
17July2002 NWRAS Malin Frequency dip
Time in Seconds
Frequency
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
18/31
18
-10 0 10 20 30 40 50 60
1.06
1.07
1.08
1.09
1.1
1.11
1.1217July2002 NWRAS Malin Voltage dip
Time in Seconds
Voltage
Note: The simulated voltage is offset by 0.003to match initial actual voltage. Initial time is also
offset to facilitate comparison.
-10 0 10 20 30 40 50 60
-100
0
100
200
300
400
500
600
700
80017July2002 NWRAS Malin-Round Mountain Line 1 Flow
Time in Seconds
MW
Flow
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
19/31
19
-10 0 10 20 30 40 50 60
0
50
100
150
200
250
300
350
40017July2002 NWRAS Midway-Vincent Line 1 Flow
Time in Seconds
MW
Flow
Note: The simulated flow is offset by -100 MWto match initial actual flow. Initial time is also
offset to facilitate comparison
-10 0 10 20 30 40 50 60
600
650
700
750
800
850
900
950
100017July2002 NWRAS PV-Devers Line Flow
Time in Seconds
MW
Flow
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
20/31
20
-10 0 10 20 30 40 50 60
460
470
480
490
500
510
520
530
540
550
56017July2002 NWRAS Colstrip-Broadview Line 1 Flow
Time in Seconds
MW
Flow
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
21/31
21
July 27, 2002 Four Corners Plant trip
On July 27, 2002 all five units at the Four Corners generating station tripped.
The switch deck used to perform the simulation with the alldyns.p epcl included the
following records. The switching code is in the first column, the second column contains
the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
Switching Codes -
TG - Trip generator
TG 0.0 "FCNGEN 1" 20.0 "1 "
TG 0.0 "FCNGEN 2" 20.0 "1 "TG 870. "FCNGEN 3" 20.0 "1 "
TG 870. "FCNGN4CC" 22.0 "4 "
TG 870. "FCNGN5CC" 22.0 "5 "
Plots depicting frequency and voltage at Malin and flows on several significant paths areincluded below. In every plot, blue depicts the old model, red the new, and green
provides traces from system monitors during the disturbance.
-10 0 10 20 30 40 50 60
59.8
59.82
59.84
59.86
59.88
59.9
59.92
59.94
59.96
59.98
60
27 July 2002 FCorn Trip Malin Freq dip
Time in Seconds
MalinFrequency(Hz)
Note: The simulated frequency is offset by -.015
to match initial actual frequency. Initial timeis also offset to facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
22/31
22
-10 0 10 20 30 40 50 60
1.03
1.04
1.05
1.06
1.07
1.08
1.09
1.1
1.1127 July 2002 FCorn Trip Malin Volt dip
Time in Seconds
MalinVoltage(pu)
Note: The simulated voltage is offset by +.03 to matchinitial actual voltage. Initial time is also offset to facilitatecomparison.
-10 0 10 20 30 40 50 60
950
1000
1050
1100
1150
1200
1250
130027 July 2002 FCorn Trip Mln-RM Flow
Time in Seconds
MW
FlowonMalin-RMLine1
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
23/31
23
-10 0 10 20 30 40 50 60
200
250
300
350
400
45027 July 2002 FCorn Trip Midway-Vincent Flow
Time in Seconds
MW
FlowonMidway-VincentLine1
-10 0 10 20 30 40 50 60
400
450
500
550
600
650
700
750
80027 July 2002 FCorn Trip Palo Verde-Devers Flow
Time in Seconds
MW
FlowonPV-DeversLine
Note: The simulated flow is offset by -60 MW
to match initial actual flow. Initial time is alsooffset to facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
24/31
24
-10 0 10 20 30 40 50 60
850
855
860
865
870
875
880
885
890
895
90027 July 2002 FCorn Trip Colstrip-Broadview Line 1 Flow
Time in Seconds
MW
FlowonColstrip-BroadviewLine1
-10 0 10 20 30 40 50 60
1.04
1.045
1.05
1.055
1.06
1.065
1.0727 July 2002 FCorn Trip Vincent Volt dip
Time in Seconds
VincentVoltage(pu)
Note: The simulated voltage is offset by -0.04to match initial actual voltage. Initial time is also offsetto facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
25/31
25
Oct 8, 2002 Line trip and NW RAS operation
On October 8, 2002 the Northwest RAS operated tripping northwest generation.
The switch deck used to perform the simulation with the alldyns.p epcl included the
following records. The switching code is in the first column, the second column contains
the time the switching occurred in cycles, and bus names, kV, unit ids, etc follow:
Switching Codes -
DL - Delete lineTG - Trip generator
CC - comment
DL 0.0 "PONDROSA" 500 "SUMMER L" 500 "1 "
DL 0.0 "MALIN " 500 "SUMMER L" 500 "1 "
DL 0.0 "BURNS " 500 "SUMMER L" 500 "1 "CC /* 677 MW at Chief Joseph */
TG 17 "CHIEF J5" 13.8 "N "
TG 17 "CHIEF J5" 13.8 "O "TG 17 "CHIEF J5" 13.8 "P "
TG 17 "CHIEF J5" 13.8 "Q "
TG 17 "CHIEF J5" 13.8 "R "
TG 17 "CHIEF J5" 13.8 "S "
TG 17 "CHIEF J5" 13.8 "T "CC /* 520 MW at Grand Coulee */
TG 17 "COULEE01" 13.8 "1 "TG 17 "COULEE02" 13.8 "1 "
TG 17 "COULEE03" 13.8 "1 "
TG 17 "COULEE04" 13.8 "1 "
TG 17 "COULEE05" 13.8 "1 "
CC /* 307 MW at Grand Coulee */
TG 17 "COULEE06" 13.8 "1 "
TG 17 "COULEE07" 13.8 "1 "
TG 17 "COULEE08" 13.8 "1 "CC /* 490 MW at Grand Coulee #20 */
TG 17 "COULEE20" 15.0 "1 "
CC /* 551 MW at Grand Coulee #24 */
TG 17 "COULEE24" 15.0 "1 "
CC /* 167 MW at Wanapum */
TG 17 "WANAPUM2" 13.8 "7 "
TG 17 "WANAPUM2" 13.8 "A "
CC /* 196 MW at Rocky Reach */TG 17 "ROCKY RH" 15.0 "7 "
TG 17 "RRCH8-11" 15.0 "B "
Plots depicting frequency and voltage at Malin and flows on several significant paths are
included below. In every plot, blue depicts the present model, red the new, and greenprovides traces from system monitors during the disturbance. Some of the plots below
also include a turquoise trace with PPSM monitor data. The other actual data (green) in
this report is from the PMU monitors.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
26/31
26
-10 0 10 20 30 40 50 60
59.6
59.65
59.7
59.75
59.8
59.85
59.9
59.95
60
8 Oct 2002 NWRas Malin Freq dip
Time in Seconds
MalinFrequency(Hz)
-10 0 10 20 30 40 50 60
1.06
1.08
1.1
1.12
1.14
1.16
8 Oct 2002 NWRas Malin Volt dip
Time in Seconds
MalinVoltage(pu)
Note: The simulated voltage is offset by +.01 t omatch initial actual voltage. Initial time is also offsetto facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
27/31
27
-10 0 10 20 30 40 50 60
300
400
500
600
700
800
900
1000
11008 Oct 2002 NWRas Mln-RM Flow
Time in Seconds
MW
FlowonMalin-RMLine1
Note: The simulated flow is offset by -20 to matchinitial actual flow. Initial time is also offset to facilitate
comparison.
-10 0 10 20 30 40 50 60
1100
1150
1200
1250
1300
1350
14008 Oct 2002 NWRas Palo Verde-Devers Flow
Time in Seconds
MW
FlowonPV-DeversLine
Note: The simulated flow is offset by -20 to match initial
actual flow. Initial time is also offset to facilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
28/31
28
-10 0 10 20 30 40 50 60
880
900
920
940
960
980
1000
1020
1040
1060
10808 Oct 2002 NWRas Colstrip-Broadview Line 1 Flow
Time in Seconds
MW
FlowonColstrip-BroadviewLine1
Note: The simulated flow is offset by +30 to matchinitial actual flow. Initial time is also offset to
facilitate comparison.
-10 0 10 20 30 40 50 60
1.025
1.03
1.035
1.04
1.045
1.05
1.055
1.06
1.065
1.078 Oct 2002 NWRas Vincent Volt dip
Time in Seconds
VincentVoltage(pu)
Note: The simulated voltage is offset by -0.015 to match
initial actual voltage. Initial time is also offset to facilitate
comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
29/31
29
-10 0 10 20 30 40 50 60
200
300
400
500
600
700
800
900
10008 Oct 2002 NWRas Custer-Ingledow Line Flow
Time in Seconds
MW
FlowonCuster-IngledowLine
Note: The simulated flow is offset by -40 to matchinitial actual flow. Initial time is also offset tofacilitate comparison.
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
30/31
30
APPENDIX 1
MODEL DATA TASK FORCE (MDTF) PARTICIPANTS
Baj Agrawal APS
Jeffrey Scott AVAKai C Lee BCHA
Barry Francis BEPC
Dmitry Kosterev BPATXavier Baldwin BURB
Alan Roth CALP
Mario Lara CFE
Bert E. Hoffman CHPDMark Willis CISO
Romulo F Barreno DENA
Ben Supremo DENA
Jerry Kyle DOPDDavid Tovar EPE
Wayne Kunkel GCPDDavid Barrajas IID
Mark Hanson IPC
John (Gang-Kung) Hu LDWPMike Kramer MID
Robert Jenkins MIR
Les Pereira NCPA
Helena Ho NEVPMarc A. Kodis NRG
John Cummings NWMT
Craig Quist PACBill Hall PAC
Mike Okapal PAC
Ashok Agarwal PASASherman Chen PG&E
Jon Eric Thalman PG&E
Richard J. Goddard PGE
Kenneth Dillon PGEGeorge Nail PNM
Bob Johnson PSC
Tom Green PSCJoe Seabrook PSE
John Phillips PSE
Joseph W. Milton REINam Nguyen SCE
Fred Ojima SCL
Abbas Abed SDGE
Dilip Mahendra SMUD
7/27/2019 Report Regarding Studies Conducted With Owner's Validated Data
31/31
31
Zeina Randall SPP
John Hernandez SRP
John Kehler TAAKenneth Peck TEP
Chris Shultz TPWR
Vince Leung TSGTShawn Patterson USBR
John Greenlaw WACM
Doug Smith WAPADonald Davies (Chair) WECC
Andy Schuetzinger