Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Central North Sea
Relinquishment report
Relinquishment Report for Licence P1818Block 30/1a
Date: June 2016
Document last updated 05-10-2016 16:28 BST
Relinquishment Report - Licence P1818 Block 30/1a
Relinquishment Report - Licence P1818 Block 30/1a
1 Licence Information: 12 Licence Synopsis: 23 Work programme summary 34 Database: 8
4.1 Seismic Database 84.2 Key Wells 10
5 Prospectivity Update: 115.1 Reservoir 135.2 Trap 165.3 Seal 195.4 Source 215.5 Further Technical work undertaken 22
6 Resource and Risk Summary 237 Conclusions: 298 Clearance 30
List of figures
2.1 P1818 Location Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 3.1 Faraday Pre-Drill Location Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3 3.2 Faraday Seismic Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 3.3 30/1a-11 CPI . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 3.4 Fulmar C & B Petrophysics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 3.5 Faraday Post Well Seismic Interpretation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 4.1 Seimic Coverage of 30/1a . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 4.2 Veritas 2007 Reprocessing area. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 4.3 Comparison of CGG 2007 PrSDM vs Legacy data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.4 CGGVeritas 2012 PreSDM Reprocessing area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 5.1 Triassic Lead A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 5.2 Top Sele Lead B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 5.3 Upper Jurassic Well Correlation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 5.4 Near Top Pentland Time Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 5.5 Inline 11500 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 5.6 Crossline 33800 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17 5.7 Near Top Triassic Time Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 5.8 Top Sele Time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 5.9 Faraday HPHT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
5.10 Farady MDT pressure Plot . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 5.11 Lower Heather Well Correlation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 6.1 Faraday Post Well Seismic Interpretation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 6.2 Marlowe Depth Map . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 6.3 Triassic Lead A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 6.4 Top Sele Lead B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
List of tables
1.1 C o n s o r t i u m d e t a i l s : . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 3.1 P r e - D r i l l U n r i s k e d I n - p l a c e v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 3.2 3 0 / 1 a - 1 1 P e t r o p h y s i c a l A v e r a g e s - C u t o f f s a p p l i e d V s h a l e = 1 0 % ( * i n t e r v a l w i t h . . . . . . . 6 5.1 A v e r a g e R e s e r v o i r P r o p e r t i e s f o r F u l m a r . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 6.1 F a r a d a y H e a t h e r T u r b i d i t e s I n p u t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 6.2 F a r a d a y H e a t h e r T u r b i d i t e s v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 6.3 F a r a d a y F u l m a r I n p u t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 6.4 F a r a d a y F u l m a r v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 6.5 M a r l o w e H e a t h e r T u r b i d i t e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 6.6 M a r l o w e W e s t H e a t h e r T u r b i d i t e s v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 6.7 M a r l o w e E a s t H e a t h e r T u r b i d i t e s v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 6.8 M a r l o w e F u l m a r i n p u t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 6.9 M a r l o w e W e s t F u l m a r v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
6.10 M a r l o w e E a s t F u l m a r v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 6.11 T r i a s s i c L e a d A I n p u t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 6.12 T r i a s s i c L e a d A v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 6.13 F o r t i e s L e a d B I n p u t s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 6.14 F o r t i e s L e a d B v o l u m e s . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
1 Licence Information:
Licence Number: P1818
Licence Round: 26th Round
Licence Type: Traditional
Block(s): 30/1a
Table 1.1: Consortium details:
Companies Equities
ENGIE E&P UK Ltd (Operator) 30%
Maersk Oil North Sea UK Ltd 30%
INEOS (RWE Dea UK SNS Ltd) 25%
Nippon Oil Expl. & Prod. U.K. Limited 15%
1 Licence Information:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 1
2 Licence Synopsis:
This report is in support for an early relinquishment of Licence P1818, block 30/1a, which is currently in it's second term. The
License was originally awarded in the 26th Licensing round as a 'Traditional' License (4+4+18 years), with a start date of 10th
January 2011. The original award group comprised of GDF SUEZ E&P UK Ltd (now ENGIE E&P UK Limited) 30%, Maersk Oil
North Sea UK Ltd 30%, RWE Dea UK SNS Ltd (now INEOS) 25% & JX Nippon Exploration and Production (UK) Limited 15%.
The License covers an area of 50.78 sq km Fig. 2.1
23/26c No op
30/1b ENI
30/7c CnPh
23/27b BGI
29/5d Tot
30/2a BGI
30/7b CnPh
30/2b BGI29/5b Tot
30/1c BP
22/30b Sh
30/1a ENGIE
29/5e Itha30/1f
ENGIE
29/10b Itha
23/26a BP
29/5a Sh
23/26b ChTx
29/5c Tot
30/2c CnPh
29/4d Tot
29/10a Sh
29/4a Sh
22/30c Tot
29/10c Sh
30/6c CnPh
30/1g Maer
22/30e Sh
22/29b Tot
Jade
Judy
Machar
Erskine
Jasmine
Elgin
GlenelgWest
Franklin
Franklin
Puffin
Julia
Jill
Shearwater
Commander
Stella
Kessog
Hurricane
MarconiJackdaw
Courageous
Ockley
Faraday
Faraday(Heather)
Thunderer 1
Thunderer 2
JadeSouth
Capercalie
Endeavour
CordeliaLear
Crathes
8
9
2
5
2
1
W1
9
2
4
3
2
H1
12
B1Z
9
H3
2B2Z
4
3
13A
1R01
3
11
8
1
12
10Z
7
10
2A
4
12Z
8
A3Z
15
H2
3Z
5Z
19
W4
6Y
5A
12Z16
13
10
2
K1Z
1
W1Z
4Z
7
B1Y
5Z
2R01
5A
A3
H1Z
1
K1
J7
14
3Z
4
3R0113Z
3
5
19Z
8Z
14
3
7
11
4Z 17
1
F4
7
J12
A13Z
5
1
B1Z
5AR01
6 1
3R01
A713Z 1R01
4
8
4
11
9Z
10
6
4Y
21
18
6 A2Z
3
5Y
B1X
9
5
A1Z
15
8
5
10Z
2Z
F5Z
9
6
2F10Y
12
A8
2
1A
13Y
B1
5Y
F6Z
7
19Y
G8Y
6Z A6
3
4R01
B1
A12
11
A5
5
2°12'0"E
2°12'0"E
2°0'0"E
2°0'0"E
1°48'0"E
1°48'0"E
57°0'
0"N
57°0'
0"N
56°50
'0"N
56°50
'0"N
0 6 123Kilometers
Key:Faraday DiscoveryENGIE Licence P1818ENGIE Non-OpENGIE Operator
Document Path: X:\ArcGIS\Corporate\Regions\UKCS\MXD\LICENCE SUMMARY MAPs_Current.mxd Date: 01/06/2016Fig. 2.1 P1818 Location Map
The License is approaching the end of the 2nd term. ENGIE E&P UK Limited and it's partners are electing to fully relinquish the
licence, having fulfilled all work commitments which led to the discovery of the Faraday hydrocarbon accumulation (well
30/1a-11). Faraday is uneconomic; furthermore, the partnership do not see any remaining economically viable prospectivity
within the license.
2 Licence Synopsis:
Relinquishment Report Licence P1818 Block 30/1a
Page 2 GDF SUEZ E&P UK Ltd
3 Work programme summary
The original work programme required the Licensees to drill one well on the Faraday Prospect to a depth of 5,569m or 100m
into the Jurassic Pentland Formation, whichever was the shallower.
The 30/1a-11 well spudded on the 31st July 2011 and reached a TD of 18,382ft MD, -18,203ft TVDSS (5,602m MD, -5,548m
TVDSS) on the 22nd December 2011. The primary target reservoir for this HPHT exploration well was the Upper Jurassic Late
Oxfordian Fulmar Sandstone Formation. The prospect was located on the western flank of a rotated fault block, where the
Fulmar appeared to onlap onto the Middle Jurassic Pentland Formation Fig. 3.1 Fig. 3.2.
30/1a
Fig. 3.1 Faraday Pre-Drill Location Map. Sub-Regional Depth map at Top Fulmar
3 Work programme summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 3
Fig. 3.2 Faraday Seismic Section. Predrill Cross section. Data courtesy of CGG
The key pre-drill geological uncertainty was the base/lateral seal. There was a concern that the Fulmar sands may be deposited
directly onto the underlying Pentland, which the updip 30/1f-8 well had proven to be water wet with only minor shows.
However, analysis of offset wells had indicated that there should be a basal seal of Lower Heather Shale approximately 100-
150ft thick separating the Fulmar from the Pentland and pressure analysis indicated that there was a ~30Bar (435psi) pressure
difference between the Fulmar and Pentland gas gradients in the Franklin wells. The overall pre-drill geological risk was
estimated at 26%, while the in-place volume estimate ranged from 145 to 1,124bcf (see table below).
Table 3.1: Pre-Drill Unrisked In-place volumes
P90 P50 P10 Mean
GIIP Faraday (bcf) 145.0 467.5 1,124.8 574.3
Whilst drilling through the Heather section, the well encountered ~89 ft of hydrocarbon bearing Intra Heather Turbidite sands
between 16,756-16,845ft MD, with good gas shows and resistivities in the 30-60 ohm-m range. The well was deepened to
17,359ft MD, encountering loss, gain and differential sticking issues whilst drilling from 17,038 and 17,359ft MD. Hole
problems led to the running of a 7" liner at the top of the Fulmar (shoe at 17,356ft MD), which in turn meant that data
acquisition had to be limited to acquiring LWD GR & Resisitivity data over the Heather Sands and wireline Density and Porosity
data through casing.
At the top of the Fulmar Formation 17,357ft MD (-17,191ft TVDSS), some thin sands were encountered with total
hydrocarbon gas levels of 15%. The main body of sand within the Fulmar (17,357.5ft, (-17,191.5ft TVDSS) to 17,666ft MDRT
(-17,500ft TVDSS), 309ft TVT), comprised variable quality sandstone ranging from well sorted, moderately porous with good
hydrocarbon shows, to very fine and silty with shows; two cores were cut within the main sand body (47.6ft in total). Two
further sand bodies were developed in the Lower Heather unit and a series of thinner sand developments within the Pentland
Formation Fig. 3.3. Petrophysical analysis indicates that the Heather Turbidites have good Hydrocarbon Saturations of ~83%.
The Fulmar C interval was found to be poorly developed at Faraday, whereas in offset fields this is often extensive and
3 Work programme summary
Relinquishment Report Licence P1818 Block 30/1a
Page 4 GDF SUEZ E&P UK Ltd
Fig. 3.3 30/1a-11 CPI. Petrophysical evaluation of Jurassic Section
amalgamated with the underlying B sands. The petrophysical estimation of the C sands is problomatic as they straddle the 7
5/8" casing shoe, but it was noted that whilst drilling these sands, losses were encountered followed by a gas kick of >14.5%
total gas. The Fulmar B sand petrophysics suggest very high porosities in the 20-30% range, unlike these sands in any of the
offset wells. Hydrocarbon saturations are estimated to be low at ~27%. For such good quality sands the transition zone
would be expected to be sharp; the core over this section had oil fluorescence suggesting either the very base of a
hydrocarbon column or possibly a palaeo-contact. For volumetric analysis, a contact of -5,317m TVDSS has ben assumedFig.
3.4.
3 Work programme summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 5
Fulmar C
Fulmar B
Fig. 3.4 Fulmar C & B Petrophysics
Table 3.2: 30/1a-11 Petrophysical Averages- Cut offs applied Vshale =<50% and Porosity =>10% (*interval with poorly
defined properties due to poor logs)
Zone Name Top
ft MD
Base
ft MD
Gross ft
Net ft
N:G Av Por
%bv
Av Sw
%pv
Heather Turbidites
16756.0 16845.0 89.0 53.5 0.60 15.8 17
Fulmar csg shoe*
17357.5 17400.0 42.5 30.0 0.71 13.9
Fulmar 17400.0 17666.0 266.0 94.5 0.36 23.5
Lower Heather Unit
17666.0 17934.5 268.5 44.0 0.16 12.6
Lower Heather
Shale
17934.5 18045.5 111.0 0.0 0.0 na
Pentland 18045.5 18310.0 264.5 73.3 0.28 12.0
Eight runs of the RCX tool were attempted in the 6 3/4" hole section, which achieved moderate pressure data and recovered
four fluid samples from the Fulmar sands at 17,580 ft MD. All four were gas condensate samples but they were heavily
contaminated with mud filtrate.
The well was not tested due to higher than anticipated temperatures and pressures. The well was plugged and abandoned as a
Gas Condensate discovery in accordance with Oil & Gas UK guidelines.
Post well analysis indicates that the Heather sands are J56 in age, older than the J62 Turbidites seen in both Erskine and
Shearwater. The Fulmar sands are J54b and J52 in age, similar to those in Shearwater and Elgin Franklin (for full correlation
see GFB012391|Fig. 3.4]).
3 Work programme summary
Relinquishment Report Licence P1818 Block 30/1a
Page 6 GDF SUEZ E&P UK Ltd
The post well seismic interpretation on reprocessed seismic data has mapped an Intra Heather Sandstone structure, with
stratigraphic pinch out to the east and either independent down dip closure to the west, or a larger downthrown fault closure
to the north and south. At Fulmar level, a similar stratigraphic pinch out structure is seen with independent closure to the
west using the 17,444ft TVDSS water up-to as seen in the 30/1a-11 Lower Fulmar Sst. Fig. 3.5
Top Heather Sandstone Depth (m) Top Fulmar Depth (m)
WUT 5317m
Max 5600m 600m column
Independent Spill 5475m
475m column
GDT 5085m 85m column
Faraday
Faraday East
Fig. 3.5 Faraday Post Well Seismic Interpretation.. On 2012 PrSDM Final TMA Stack volume
3 Work programme summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 7
4 Database:
4 Database:
Relinquishment Report Licence P1818 Block 30/1a
Page 8 GDF SUEZ E&P UK Ltd
4.1 Seismic Database
The P.1818 License is covered by a patchwork of proprietary and non-proprietary seismic, including the PGS Megamerge and
the CGGVertias 2001 Q30 Phase 1 Long Offset data Fig. 4.1.
Fig. 4.1 Seimic Coverage of 30/1a
In 2006-7, GDF Suez and its partners contracted CGGVeritas to conduct a proprietary PSDM reprocessing project over 30/1a
and its neighbouring blocks Fig. 4.2. The reprocessing comprised of six input surveys with varying bin and cable length, giving
a total of 827 sqkm input area and a 432 sqkm output area. This resulted in significant improvement to the imaging of the
Pre-Cretaceous section (note the 30/1a-11 well was drilled on this seismic volume) Fig. 4.3.
Fig. 4.2 Veritas 2007 Reprocessing area.
Megamerge PSTM
GDF Suez 2007 PrSDM
Fig. 4.3 Comparison of CGG 2007 PrSDM vs Legacy data. Data courtesy of CGG
Following the drilling of the Faraday well and the acquisition by CGGVeritas of further Long offset data, CGGVeritas were
contracted in 2012 to conduct further PrSDM reprocessing over the area. The input surveys included four from CGGVeritas'
Central North sea multi-client database - Q30 Ph I, Q30 Ph IV, Q22 Ph III and Q22 Ph VI, the CNS Cornerstone 3D, and infill
data from three other surveys - Erskine 1986, Shearwater 1996 and Shearwater 2001. The migration input area was 893km²
and the output area was 475.7km² Fig. 4.4
Fig. 4.4 CGGVeritas 2012 PreSDM Reprocessing area
4 Database:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 9
The block is also covered by the CGG Cornerstone Q30 Phase 8 BroadSeis 3D which ENGIE and its partners purchased in
2013.
4 Database:
Relinquishment Report Licence P1818 Block 30/1a
Page 10 GDF SUEZ E&P UK Ltd
4.2 Key Wells
The P1818 License lies within a prolific HPHT area with a number of wells drilled in and around the Elgin, Franklin,
Shearwater, Erskine and Kessog discoveries.
Within the license itself is the 30/1f-8 well, drilled by Enterprise in 1991, on the western margins of the J ridge, which
targeted Jurassic and Triassic prospectivity. The well TD'd at 5,010m MD (16,435ft MD) within the Middle Jurassic Pentland
Formation. Oil and Gas shows were seen throughout the Pentland Formation. On the operators comp log a 52ft sand is
present at the top of the Pentland section and has been labelled Puffin Formation (Equivalent to the U. Jurassic Fulmar).
Proprietary chemostartigarphic analysis conducted for ENGIE E&P UK Limited indicates this is most likely to be a thick Pentland
channel sst, suggesting that this well was drilled updip from the Fulmar pinch out edge. Three cores were cut in the Pentland
but the well was not tested. Minor oil shows were also seen in the Tertiary Forties Sandstone.
Other Key offset wells include all the exploration/appraisal and development wells from the Elgin Franklin Fields, which have
producing sections in the Jurassic Fulmar, Pentland and Triassic. Further wells include:
the Shearwater 22/30c-15 & 15z and 22/30b-11 wells drilled by Shell as appraisal wells, which encountered thick
hydrocarbon bearing Upper Jurassic Fulmar sections topped by Heather turbidite sequences;
the Erskine 23/26b-14 and 15 wells which encountered Fulmar sections; and
the Kessog 30/1c -4, 5 & 6 wells which have important Pentland and Triassic sections.
5 Prospectivity Update:
In the original 26th Round application document, in addition to the Faraday prospect, two other leads were identified on the
awarded license. Lead A was at Triassic level and comprised two fault blocks. The westerly block had dip closure to the west,
north and south and fault closure to the east. The eastern fault block was a down thrown graben feature with fault closure to
the north, east and west and dip closure to the south. The eastern fault block is down thrown relative to the high drilled and
tested by the dry 30/1c- 2A well. The crest of the structure occurred at approximately 4,800m (15,750ft) TVDSS with a
maximum closing contour at 5,120m (16,800ft) TVDSS. The estimated in place volumes were Mean 212bcf gas, with the key
risks identified as top and lateral seal. Fig. 5.1
Fig. 5.1 Triassic Lead A. As mapped in the 26th Round application.
Lead B was a small 4-way dip closed structure at top Sele level with its crest at approximately 3,068m (10,064ft) TVDSS and a
closing contour at 3,086m (10,125ft) TVDSS, giving total closure of 18m (65ft).The lead was located some 1.5km to the east
of the 30/1f-8 well, which encountered minor shows in the Forties sandstone. The most likely reservoir was expected to be
the Forties, which is present over the area. The estimated in place volumes were Mean 5bcf gas, with the key risk being
reservoir presence and quality. Fig. 5.2
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 11
Fig. 5.2 Top Sele Lead B. As mapped in the 26th Round Application.
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 12 GDF SUEZ E&P UK Ltd
5.1 Reservoir
The principle reservoir in the area is the Upper Jurassic Fulmar Fm. together with the Upper Heather Turbidite sands. The
Fulmar sands form the main reservoir at the on trend 22/30c Shearwater field, as well as the nearby 22/30b & 29/5b
Elgin/Franklin and 23/26b Erkine fields. In the Late Oxfordian, the Fulmar and Heather Formations were deposited as a
progradational / aggradational shoreline or barrier shoreline to shelf succession that was ultimately transgressed, being
overlain by retrogradational sandy shoreface successions (Early-Middle Kimmeridgian) and then by shelfal mudstones and
sandstones of the Heather Formation (Late Kimmeridgian) Fig. 5.3.
The reservoir quality of the Fulmar is primarily controlled by grain size and the degree of sorting. The best quality reservoir
occurs in the higher energy, coarser grained upper shoreface sands. This is largely to do with the higher energy environment
winnowing away the fines that reduce porosity and permeability. The more distal the facies the greater the clay content and
the greater the degree of bioturbation, both of which result in reduced reservoir quality. Even though primary reservoir facies
is one of the key determining factors for reservoir quality, there are a number of other factors within the HP/HT environment
that can help to preserve porosity. These include:
early hydrocarbon migration as an inhibitor to the cementation process, restricting diagenesis;
overpressure which helps to arrest the effects of compaction; and
the presence and dissolution of sponge spicules in certain facies, helping to create secondary porosity.
Average petrophysicaly derived reservoir properties from offset wells are tabulated below.
Well Field Net Reservoir Net Pay
Gross Net N/G Av Phi Av Sw Gross Net N/G Av Phi Av Sw
TVDSS m TVDSS m TVDSS m TVDSS m
22/30c-8 Elgin 346.1 274.8 0.794 0.158 0.453 346.1 159.3 0.460 0.186 0.237
22/30c-10 Elgin 304.0 235.5 0.774 0.146 0.618 304.0 125.1 0.411 0.160 0.392
22/30c-11 Shearwater 269.0 211.0 0.784 0.171 0.560 269.0 124.8 0.464 0.190 0.380
22/30c-13 Elgin 312.0 241.6 0.753 0.159 0.410 312.0 188.2 0.586 0.171 0.311
23/26b-8 Erskine 118.5 75.4 0.636 0.160 0.338 118.5 74.52 0.629 0.163 0.334
23/26b-14 Erskine 123.4 79.2 0.642 0.187 0.300 123.4 76.35 0.619 0.190 0.288
23/26b-15 Erskine 115.5 48.2 0.418 0.123 0.990 115.5 0.000 0.000 0.000 0.000
23/26a-21 Endeavour 95.0 87.0 0.917 0.170 1.000 95.0 0.000 0.000 0.000 0.000
29/4b-4 Glenelg 411.5 325.0 0.790 0.134 0.597 411.5 158.7 0.386 0.145 0.350
29/5b-4 Franklin 279.7 155.0 0.554 0.152 0.380 279.7 142.9 0.511 0.155 0.359
29/5b-6 Franklin 282.3 188.7 0.668 0.171 0.233 282.3 188.1 0.666 0.171 0.222
29/5b6z Franklin 282.3 196.3 0.695 0.165 0.240 282.3 194.6 0.689 0.166 0.238
29/5b-8 Franklin 438.6 138.7 0.316 0.143 0.710 438.6 49.9 0.114 0.153 0.474
AVERAGE 259.8 173.6 0.672 0.157 0.525 259.8 114.1 0.426 0.142 0.276
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 13
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 14 GDF SUEZ E&P UK Ltd
29
/5b
-8
22
/30
c-1
3
22
/30
b-1
1
23
/26
b-1
5
30
/1a-
11
3
0/1
c-3
J7
J6
J5
J4
J3
J2
J1
CH
EMO
STR
AT
J62
J56
J54
b
J54
a
J52
J46
J44
BIO
STR
AT
He
ath
er
Sst
Fulm
ar S
st
LITH
OST
RA
T
LEG
END
Fig
. 5.3
Up
per
Ju
rass
ic W
ell C
orr
elat
ion
.
Table 5.1: Average Reservoir Properties for Fulmar
Other reservoirs that are important in surrounding blocks but as yet unproven in this license include the Tertiary Rogaland
Sands as proven by the 30/1f-13 Marconi well, the Forties Sst as proven in the 30/2-1 Courageous well and its subsequent
appraisals, the Cretaceous Hod Chalk Formation as proven in the Ockley 30/1d-10, 301d-12 and the original 30/1c-2A well,
the Middle Jurassic Pentland Fm. as proven in the 30/1c-4 Kessog wells and finally the Triassic as proven in the 30/2c Jade
Field and the 30/2a-10 Thunderer well.
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 15
5.2 Trap
Following the drilling of the 30/1a-11 Faraday well, a number of interpretations have been concluded, initially on the 2012
PSDM volume, Fig. 3.5, and more recently on the CGG Q30 Phase 8 BroadSeis PSTM, over the whole of 30/1a.
On the BroadSeis data Time structure maps have been generated for the following key horizons:
Top Sele Formation
Top Forties Sandstone
Top Ekofisk
Base Cretaceous Unconformity
Near Top Pentland Formation
Near Top Triassic
Near Top Julius Mudstone
Near Top Judy Sandstone
Near Top Smith Bank Formation
Top Rotliegendes
Faraday at both Heather Turbidite and Fulmar level, is a combined stratigraphic and dip closed structure. Fig. 5.4 Fig. 5.5
Fig. 5.6 The up dip closure is related to an intra-Heather unconformity which is linked to gravity slumping of the Fulmar and
Heather sequences. There is dip closure to the west and possible fault closure to the North and South.
Time CI = 0.050 secs
5 km
Cro
ssli
ne
33800
Inline
11550
Block 30/1a
Salt Diapir
Limit of BroadSeis
3D Seismic Data
Faraday
Marlowe
East & West
Fig. 5.4 Near Top Pentland Time Structure. On CGG BroadSeis PrSTM volume
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 16 GDF SUEZ E&P UK Ltd
Fig. 5.5 Inline 11500. Dip line through the Faraday prospect, from Q30PH PrSTM TMA BroadSeis (Time). Data courtesy of CGG
TWT msecs
BCU
NS
Near Top Pentland
Near Top Triassic
Near Top Smith Bank Fm
Top Rotliegendes
Near Top Julius Mudstone Near Top Judy
Sandstone
Top Forties
Top Ekofisk
2.5 km
Top Sele
Top Salt
Potential for Heather and
Fulmar in Lead Marlowe
Lead Marlowe
Fig. 5.6 Crossline 33800. Data courtesy of CGG
Marlowe East and West are two fault-bounded fault blocks to the east of Faraday between Faraday and the 30/1d-12
Oakwood Fulmar discovery in the adjacent block. There is the potential for a similar reservoir combination of Heather
turbidites and Fulmar sands in Marlowe, however, the presence of Fulmar is then very dependent on how the Top Pentland is
tied across the faults and if a higher pick is believed this then reduces the potential reservoir thickness.
As a comparison with the original 26th Round application, a copy of the Near Top Triassic and Top Sele time map is also
included to show the similarity between the two vintages of interpretation Fig. 5.7 Fig. 5.8
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 17
Cro
ssli
ne
33800
Inline
11550
Block 30/1a
Limit of BroadSeis
3D Seismic Data
Fig. 5.7 Near Top Triassic Time Map
Cro
ssli
ne
33800
Inline
11550
Block 30/1a
Limit of BroadSeis
3D Seismic Data
Lead B
Fig. 5.8 Top Sele Time. Q30 Ph8 PrSTM TMA BroadSeis (Time)
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 18 GDF SUEZ E&P UK Ltd
5.3 Seal
For the prime Upper Jurassic Reservoirs, the top seal is provided by the overlying Heather and Kimmeridge Clay Fms, which
are prevalent across the area and provide the regional seal to most of the offset fields. A key consideration in all HPHT
prospects/fields is the impact of overpressure on top seal failure. A cross plot of the CNS HPHT fields temperature vs pressures
demonstrates that Faraday is similar to Elgin and Franklin, with a top reservoir pressure of 15,750psig (1,086 bar) and
temperature of 375 Deg F (190.5 Deg C) Fig. 5.9.
Faraday
FARADAYEstimated Max. From RCX Pre Tests & Samples:BHP = 15750 psig BHT = 375 Deg F
Fig. 5.9 Faraday HPHT
A more detailed plot of the sub-regional RFT/MDT data reveals that the Faraday Fulmar B sands are in a similar but not exact
overpressure (6,000-8,000psi) regime to Shearwater Fig. 5.10. However the depth of the crest of the Faraday structure at
Fulmar level is below (-5,100m) the fracture gradient .
Another key factor for the Faraday discovery is the requirement for a base seal to separate the Fulmar sands from the
underlying Pentland Fm. and help explain why the updip 30/1f-8 well only had shows in the Pentland. Pre-drill it had been
recognised that there was a correlatable Lower Heather Shale in all offset wells that separated the Fulmar from the Pentland
Fig. 5.11. Pressure analysis indicated there was often a pressure difference between these two zones thus confirming a
potential barrier. The 30/1a-11 well actually encountered 105ft (32m) of Lower Heather Shale. A number of MDT pressure
points were attempted in the Pentland sands but unfortunately they were all tight.
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 19
Pressure regression between Faraday Fulmar and Pentland
Shearwater GWC -5151 m
30/1a-11 Logs HCWC -5317 m
Faraday Crest -5100 m
Fulmar Fm
Pentland Fm
Lower Heather Shale
Heather Turbidites
Fig. 5.10 Farady MDT pressure Plot
30/1a‐11Faraday
22/30b‐11Shearwater
23/26b‐15Erskine
Turbidites
22/30b‐15zShearwater
29/5b‐8Franklin
L. Heather Shale
Fig. 5.11 Lower Heather Well Correlation
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 20 GDF SUEZ E&P UK Ltd
5.4 Source
The primary source rock in the Central North Sea is the Kimmeridge Clay Fm with the Heather FM providing a secondary
source. Seismic mapping indicates that the primary hydrocarbon kitchen in the area lies to the west in a structural low
between 29/5b and 30/1a. This also acts as one of the local sources for both the Elgin - Franklin and Shearwater fields.
Furthermore, the presence of proven hydrocarbons in the 30/1a-11 Faraday well confirms the presence of a working
petroleum system. Regional Vitrinite reflectance mapping indicates that the Kimmeridge Clay is locally expected to be in the
Ro 0.7 to 1.0 range Late Oil to Gas phase. The 30/1a-11 well was not tested, however, four RCX samples were acquired at
17,580ft MD in the Fulmar Sandstone. All four were confirmed as Gas Condensate samples but with heavy mud
contamination. No samples were acquired in the upper Heather Turbidite sands but fluid inclusion analysis did identify light oil
to gas condensate inclusions at 16,780ft MD.
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 21
5.5 Further Technical work undertaken
Post the 30/01a-11 well a number of geological studies were undertaken, including:
Riley Geoscience Ltd - Biostratigraphy
Ichron - Biostratigraphy
Chemostrat - Chemostratigraphy Analysis
Ichron - Core Sedimentology and Petrography
Core Labs - Routine Core analysis
Core Lab - SCAL
Core Lab - Compositional and Water Analysis of RCX samples
FIT - Fluid Inclusion Analysis
Following the drilling of the Faraday well, the partnership initiated a 2012 PSDM Reprocessing of the CGGV Long cable data
over the Faraday Discovery (see Section 4 Database for more information).
5 Prospectivity Update:
Relinquishment Report Licence P1818 Block 30/1a
Page 22 GDF SUEZ E&P UK Ltd
6 Resource and Risk Summary
FARADAY
The Faraday field was discovered by the 30/1a-11 well and encountered hydrocarbons in the Heather turbidites and Fulmar
sands Fig. 6.1
Top Heather Sandstone Depth (m) Top Fulmar Depth (m)
WUT 5317m
Max 5600m 600m column
Independent Spill 5475m
475m column
GDT 5085m 85m column
Faraday
Faraday East
Fig. 6.1 Faraday Post Well Seismic Interpretation.. On 2012 PrSDM Final TMA Stack volume
Table 6.1: Faraday Heather Turbidites Inputs
Parameter P90 P50 P10
Net to Gross 0.36 0.6 0.84
Porosity 0.13 0.18 0.24
Sg 0.73 0.83 0.93
GWC (m) 5315 5475 5564
CEF (1 scf) 300 315 330
Recovery Factor Gas 0.5 0.6 0.7
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 23
Table 6.2: Faraday Heather Turbidites volumes
Volumes Units P90 P50 P10
GIIP bcf 51 141 305
HIIP mmboe 19 53 116
Recoverable mmboe 11 31 68.5
Table 6.3: Faraday Fulmar Inputs
Parameter P90 P50 P10
Net to Gross 0.28 0.52 0.81
Porosity 0.16 0.21 0.25
Sg 0.58 0.70 0.80
GWC (m) 5315 5475 5564
CEF (1 scf) 300 315 330
Recovery Factor Gas 0.5 0.6 0.7
Table 6.4: Faraday Fulmar volumes
Volumes Units P90 P50 P10
GIIP bcf 27 59 104
HIIP mmboe 10 22 40
Recoverable mmboe 6 13 23
MARLOWE Prospect The Marlowe prospect is split into an Eastern and western fault block, with potential reservoirs at both Heather Turbidite and
Fulmar level. The key risks are reservoir presence and effectiveness, followed by seal risk, and side seal in particular Fig. 6.2
Fig. 6.2 Marlowe Depth Map. On 2012 PrSDM Final TMA Stack volume
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
Page 24 GDF SUEZ E&P UK Ltd
Table 6.5: Marlowe Heather Turbidites
Parameter P90 P50 P10
Net to Gross 0.36 0.60 0.84
Porosity 0.13 0.18 0.24
Sg 0.73 0.83 0.93
Marlowe West GWC (m) 4900 4900 4900
Marlowe East GWC (m) 5200 5200 5200
CEF (1 scf) 300 315 330
Recovery Factor Gas 0.5 0.6 0.7
Table 6.6: Marlowe West Heather Turbidites volumes
Volumes Units P90 P50 P10
GIIP bcf 38.1 68.8 119.7
HIIP mmboe 14.2 25.9 44.9
Recoverable mmboe 8.17 15.2 26.7
Table 6.7: Marlowe East Heather Turbidites volumes
Volumes Units P90 P50 P10
GIIP bcf 30.6 55.4 96.3
HIIP mmboe 11.5 20.8 36.1
Recoverable mmboe 6.6 12.2 21.5
Table 6.8: Marlowe Fulmar inputs
Parameter P90 P50 P10
Net to Gross 0.28 0.52 0.81
Porosity 0.16 0.21 0.25
Sg 0.58 0.70 0.80
Marlowe West GWC (m) 4285 5075 5175
Marlowe East GWC (m) 4285 5175 5425
CEF (1 scf) 300 315 330
Recovery Factor Gas 0.5 0.6 0.7
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 25
Table 6.9: Marlowe West Fulmar volumes
Volumes Units P90 P50 P10
GIIP bcf 34 142 376
HIIP mmboe 13 53 144
Recoverable mmboe 7 30.6 83
Table 6.10: Marlowe East Fulmar volumes
Volumes Units P90 P50 P10
GIIP bcf 35 112 249
HIIP mmboe 13 42 95
Recoverable mmboe 7 24 55
Lead A & Lead B The Triassic Lead A and the Tertiary Sele/Forties Lead B volumes remain as calculated in the 26th Rnd application.
Lead A reservoir is anticipated to be either Triassic fluvial Josephine or Joanne Sandstones, similar to those encountered in
Kessog to the east. Top seal is likely to be provided by intra-formational shales within the Skagerrak Formation such as the
Jonathan or Joshua Mudstones Members. The key risks are charge and migration and more particularly how the overlying
Kimmeridge and Heather charge the Triassic. The lateral seal is a concern particularly to the east. A further concern is how
Lead A is isolated from the dry updip 30/2a-1C well which tested a Triassic section. Fig. 6.3
Fig. 6.3 Triassic Lead A. As mapped in the 26th Round application.
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
Page 26 GDF SUEZ E&P UK Ltd
Table 6.11: Triassic Lead A Inputs
Parameter P90 P50 P10
GRV 676 676 676
Net to Gross 0.3 0.4 0.5
Porosity 0.11 0.13 0.154
Sg 0.45 0.511 0.59
CEF (1 scf) 251 300 349
Condensate Yield stb/1e6scf 176 200 224
Recovery Factor Gas 0.32 0.42 0.58
Table 6.12: Triassic Lead A volumes
Volumes Units P90 P50 P10
GIIP bcf 120 200 317
HIIP mmboe
Recoverable mmboe 17.5 29 48
The most likely reservoir in Lead B is anticipated to be the Forties Sandstone. For volumetric purposes, reservoir properties
were derived from the offset Courageous field (30/2a) and a Gas Condensate similar to Courageous was also assumed Fig.
6.4.
Fig. 6.4 Top Sele Lead B. As mapped in the 26th Round Application.
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 27
Table 6.13: Forties Lead B Inputs
Parameter P90 P50 P10
Net to Gross 0.4 0.56 0.74
Porosity 0.16 0.21 0.27
Sg 0.45 0.511 0.59
CEF (1 scf) 225 231 239
Condensate Yield stb/1e6scf 145 150 154
Recovery Factor Gas 0.45 0.51 0.59
Table 6.14: Forties Lead B volumes
Volumes Units P90 P50 P10
GIIP bcf 2.8 4.7 7.9
HIIP mmboe 40
Recoverable mmboe 6 13 23
6 Resource and Risk Summary
Relinquishment Report Licence P1818 Block 30/1a
Page 28 GDF SUEZ E&P UK Ltd
7 Conclusions:
There are a significant number of hydrocarbon discoveries at many different stratigraphic levels in this area of the HPHT
Central North Sea. The 30/1a-11 Faraday discovery is, however, too small and currently uneconomic. Other undrilled
prospectivity on the P.1818 license in the Fulmar and Heather Turbidites are also uneconomic. These include the Marlowe
Prospect, Triassic Lead A and very small Lead B in the Tertiary.
7 Conclusions:
Relinquishment Report Licence P1818 Block 30/1a
ENGIE E&P UK Limited Page 29
8 Clearance
The operator has obtained confirmation from all partners and CGG that this document and all information contained within
can be published.
8 Clearance
Relinquishment Report Licence P1818 Block 30/1a
Page 30 GDF SUEZ E&P UK Ltd
ENGIE E&P UK LTD40 Holborn ViaductLondon EC1N 2PBTel: 020 3122 1400
engie-ep.co.uk