Upload
nathan-robinson
View
216
Download
3
Embed Size (px)
Citation preview
Recommendations of the Initial Environmental
Assessment (IEE)• According to the SIEE, the project is
identified as a category of B under the ADB environmental assessment requirements, and stated that full EIA is not required.
• According the ADB Environmental Assessment Guideline (2003), if EIA is not needed the IEE is regarded as the final environmental assessment report. (para. 131)
• Based on the IEE and its EMP and the country’s environmental legislations , the flowcharts was developed by the project.
Assessment of Compliance with
conditions & requirements by
Aimag ETD
End
Survey result evaluation by Project Environmental
Team
Start implementation
GOM Category I &ADB Category CNo need of EIA
GOM Category IISet conditions & requirements by
Aimag ETDADB requires
Report of (IEE)
GOM Category III &ADB Category A Needs EIA by
licensed firms
Approval of Environment Management and
Monitoring Plans by MNET
Inspection by LGUs
Yes
No
No
EIA FlowchartPasture & water field
surveys by Project Environmental Team
Acceptance by Soum
Government Unit
End Review on proposed locations by AAC
Investment proposal by Project Environmental
Team (IA/EA)
GOM Environmental Categorization by Aimag ETD
Review of EIA Report by MNET
Yes
Approval by ADB
Yes No
Yes
No
Yes
No
End
Approval (no-
objection base) by MOFALI
Monitoring by PMU/PIU
ADB Category BReport of Initial Environmental
Examination (IEE)
ADB Environmental Categorization by Project
Environmental Team
Yes
No
Yes
No
Notes of Steps
• STEP 1: Pasture & water field surveys– Project experts expect to conduct field surveys for pasture and hydrology assessments at herder
groups.– The field surveys are to be conducted with participation of those herders who will use and be
responsible for maintenance of future water points.– Social facts are also to be collected during identification processes of project target herder groups.
• STEP 2: Survey result evaluation– Summary tables on findings of the field surveys will be prepared and evaluated. It will be included in
project reports.– The project will check if proposed locations meet to the project requirements.
• STEP3: Soum governor’s acceptance– Survey findings will be introduced to Soum Government Units and Environmental Inspector, which
results in decisions on acceptance of proposed water point sites and herder groups.
• STEP4: Investment Proposal or Sub-Project– The term “investment proposal” is applied in the project documents, meanwhile, the term “sub-
project” is applied in ADB Environmental Guideline. In this document, an investment proposal is used.
– The project will prepare an investment proposal that should be submitted to the Environmental and Tourism Department of Ovorkhangai Aimag together with environmental assessment checklists (EAC).
– The investment proposal contains descriptions, technical justifications, drawings and maps.
• STEP5: Environmental Categorization– The project will prepare categorize the selected water point and extension centre sites according to
ADB environmental requirements , and submit Environmental Assessment Checklist (EAC) to the Environmental and Tourism Department of Ovorkhangai Aimag for its review and approval.
– The environmental assessment checklist will be prepared for each water point and submitted together with the investment proposal.
• STEP4: AAC review of locations – The Aimag Advisory Committee (AAC) of the project will review proposed locations where water
points will be established or rehabilitated.
• STEP7: Aimag Environmental Inspection– An environmental inspector, who are a head of the Environmental and Tourism Department of
Ovorkhangai Aimag, reviews and makes one of following four conclusions: (i) implement the investment proposal without detailed EIA, (ii) implement the proposal if the project meets set conditions and requirements ; (iii) conduct EIA prior implementing; or (iv) reject the proposal according to conditions stipulated in the environmental guideline.
Notes of Steps (cont.)
• STEP8.1: GOM Category I– If impacts of the proposal are below than the levels stipulated by standards, norms, normative,
procedure, guidelines, and legislations, start implementing the proposal without detailed EIA after ADB approval.
– This category of GOM is similar to ADB Category C. ADB Environment Specialist advised to submit very brief paper with attachment of environmental monitoring plan
• STEP8.2: ADB Category B– As required by project document report of initial environmental examination is to be delivered.
• STEP8.3: GOM Category II– Set conditions and requirements. When meets set conditions and requirements, implement the
proposal (after ADB approval), if not reject the proposal.– The environmental inspector at the Environmental and Tourism Department of Ovorkhangai Aimag
will identify a deadline for meeting such requirements and instruct additional measures on mitigating or minimizing those impacts that should be brought down to appropriate levels in accordance with standards, norms, normative, and legislations.
• STEP8.4: GOM Category III– For those proposals, which are needs EIA, the environmental inspector at the Environmental and
Tourism Department of Ovorkhangai Aimag submits the proposal together with a reference letter to central environmental authority, which is MNET.
– After reviewing the aimag inspector’s conclusion, as it is shown in STEP12, EIA is conducted by licensed firms.
– STEP12: MNET makes a review on EIA report through the Independent Experts’ Committee. – Based on recommendations made by the committee, MNET approves on implementing the project as
well as approves the Environmental Management Plan, Monitoring Plan and their budgets.– This category of GOM is similar to ADB category of A.
• STEP9: Approval by MOFALI– Soum refer its proposal to the Agriculture Land Relations Division (former Pasture and Crop Division)
of MOFALI for initial assessment and verification that proposed water point complies with Government requirements, in parallel with preparation of the detailed proposal.
• STEP10: Detailed environmental assessment/ Initial Environmental Examination– This step is a continuation of the STEP2.
• STEP11: MOFALI Approval– After reviewing official letter by ETD, MOFALI issues and submits appropriate letter to ADB together
with Report of IEE to ADB.
• STEP12: ADB Approval– ADB reviews and approves the environmental checklists and or IEE report.
Notes of Steps (cont.)
• STEP15: Implement Environmental Management and Monitoring Plans– Monitoring is to be conducted by the Specialized Inspection Agency and Local Government Unit
during implementation period.
• STEP16: Start Implementation– Pasture use agreements and plans at each herder group– Construction of water points by the selected contractor(s).– Capacity of herders on pasture and water use management.
• STEP17: Inspection by the LGUs– Construction works will be Inspected by LGU and the Project.
EIA Flowchart
Review and verification of
location of water points
STARTPasture & water
field surveys
1. Pasture assessment survey data2. Hydrological survey data
Any one decision: 1. Acceptance without detailed
environmental impact assessment OR
1. Acceptance if meeting certain conditions & requirements
OR
1. Conduct detailed environmental impact assessment
OR
1. Reject investment proposal
1. Pasture assessment survey results2. Hydrological survey results
Data evaluation of pasture & water
surveys
Project pasture and water
experts with participation of
herders and responsible
officer of LGUs
Review of surveys results
1. Soum Environmental Officer Conclusion2. Soum Governor’s Acceptance Letter Soum
Governor
1. List of project location of water points (herder groups) by AAC
Decision alternatives
Project Advisory
Committee
Environmental assessment
1. Environmental assessment checklist2. Investment proposal (content is the same
as IEE report)
Project Environmental
Officer
Aimag Environmental
Department
Submission
1. MOFALI Approval (no-objection base)2. IEE report 3. ADB Approval
MOFALI and ADB Responsible
Officials
Processes Documents Responsibility
MonitoringLGUs, Project
Environmental Team
Preparatory Stage
Identification of Target Soums through
Inception Workshop
Nomination of Target Soums
by Aimag Advisory Committee (AAC)
Advised Target Soum Names
by AAC
MOU between MOFALI,
Ovorkhangai Aimag
Government and VSO
Invitation to Herders & Herder
Groups (HG) in Target Soums
Invitation letter through Agriculture Tomorrow
Newspaper; Soum Governments
HG Identification Participatory Workshops in Target Soums
Preliminary Identification of Target HGs
Conduct Field Surveys
Pasture Study through Participatory Monitoring
Workshopspasture type; season of use; edificatory species; coverage; phytomass; general
conditionsBy Project Environmental Team
Hydrogeology Study Ensuring Participation by Herders and LGUsassessment on water needs; identification
of conditions in terms of geology, hydrogeology, geomorphology, and geo-
botany features; geophysical survey selected points; study recharge potential
By Project Environmental Team
Social Survey: HG formation; share of poor families; herder numbers; livestock number;
previous experience; interest of cooperation
By Project Environmental Team
Establishment of Tripartite cooperation agreement between LGU, MOFALI and
Project
End of Preparation Stage
Compliance with the Project
Final Identification of HG by the Project(areas of cooperation with HG:
pasture or pasture & water)
Pasture Use Planning and Agreement by LGU and HG selected
Cooperate with selected HGs in
pasture management
Cooperate with selected HGs in pasture & water management
Yes
No
Approval By LGU &
AAC
Yes
Yes
Yes
Yes
No