175
SCHEDULE -C BASIC RATE AVG.lead 25% FINAL RATE AVERAGE LABOURE RATE CONSIDERED FOR RATE ANALYSIS GF TO 6F 1 Excavation upto 6' 0" depth CFT 4.00 1.00 4.00 2 Excavation upto 6' 0"- to - 8' 0" depth CFT 5.50 1.00 5.50 3 Pro.& filling yellow soil brought from outside. CFT 2.00 1.00 2.00 4 Pro.& filling quarry spoil brought from outside. CFT 2.00 1.00 2.00 5 Sand filling CFT 2.00 1.00 2.00 6 Rubble soaling 9" thk. SFT 4.00 1.00 4.00 7 Rubble soaling thk. Above 9" CFT 6.00 1.00 6.00 8 Pcc 2" thk. SFT 3.00 1.00 3.00 9 Pcc 3" thk. SFT 4.00 1.00 4.00 10 Pcc 4" thk. SFT 4.00 1.00 4.00 11 Pcc 6" thk. SFT 5.00 1.00 5.00 12 9" Auger RFT 18.00 1.00 18.00 13 Extra for bulb NO 35.00 1.00 35.00 14 Footing CFT 20.00 1.00 20.00 15 9"x 9" beam/column RFT 35.00 1.1667 40.83 16 9"x12" beam/column RFT 35.00 1.1667 40.83 17 9"x15" beam/column RFT 35.00 1.1667 40.83 18 12"x 12" col/beam & section > 1 sft CFT 35.00 1.1667 40.83 19 4.5" thk.slab SFT 16.00 1.1667 18.67 20 5" thk. Slab SFT 17.00 1.1667 19.83 21 6" thk. Slab SFT 18.00 1.1667 21.00 27 9"x 4" lintel RFT 16.00 1.1667 18.67 28 9"x 6" lintel RFT 16.00 1.1667 18.67 29 4.5"x 4" lintel RFT 14.00 1.1667 16.33 30 4.5"x6" lintel RFT 14.00 1.1667 16.33 31 Upto 4" thick chajja/ loft SFT 20.00 1.1667 23.33 32 Sloping slab 5" SFT 24.00 1.1667 28.00 33 Stair tappa WITH waist slab RFT 100.00 1.1667 116.67 34 4" thick Floor slab with nominal reinforcement SFT 6.00 1.00 6.00 6" RCC WALL / PARDI SFT 21.00 1.1667 24.50 9" RCC WALL / PARDI SFT 24.00 1.1667 28.00 35 9" Brick masonary SFT 6.00 1.1667 7.00 36 4.5" brick masonary SFT 5.00 1.1667 5.83 37 14" brick masonary SFT 9.50 1.1667 11.08 38 4.5" brick mas. Cornice rft 8.00 1.1667 9.33

Rate Analysis

  • Upload
    rinpal

  • View
    32

  • Download
    12

Embed Size (px)

Citation preview

Page 1: Rate Analysis

SCHEDULE -C BASIC RATE AVG.lead 25% FINAL RATEAVERAGE LABOURE RATE CONSIDERED FOR RATE ANALYSIS GF TO 6F

1 Excavation upto 6' 0" depth CFT 4.00 1.00 4.002 Excavation upto 6' 0"- to - 8' 0" depth CFT 5.50 1.00 5.503 Pro.& filling yellow soil brought from outside. CFT 2.00 1.00 2.004 Pro.& filling quarry spoil brought from outside. CFT 2.00 1.00 2.005 Sand filling CFT 2.00 1.00 2.006 Rubble soaling 9" thk. SFT 4.00 1.00 4.007 Rubble soaling thk. Above 9" CFT 6.00 1.00 6.008 Pcc 2" thk. SFT 3.00 1.00 3.009 Pcc 3" thk. SFT 4.00 1.00 4.00

10 Pcc 4" thk. SFT 4.00 1.00 4.0011 Pcc 6" thk. SFT 5.00 1.00 5.0012 9" Auger RFT 18.00 1.00 18.0013 Extra for bulb NO 35.00 1.00 35.0014 Footing CFT 20.00 1.00 20.0015 9"x 9" beam/column RFT 35.00 1.1667 40.8316 9"x12" beam/column RFT 35.00 1.1667 40.8317 9"x15" beam/column RFT 35.00 1.1667 40.8318 12"x 12" col/beam & section > 1 sft CFT 35.00 1.1667 40.8319 4.5" thk.slab SFT 16.00 1.1667 18.6720 5" thk. Slab SFT 17.00 1.1667 19.8321 6" thk. Slab SFT 18.00 1.1667 21.0027 9"x 4" lintel RFT 16.00 1.1667 18.6728 9"x 6" lintel RFT 16.00 1.1667 18.6729 4.5"x 4" lintel RFT 14.00 1.1667 16.3330 4.5"x6" lintel RFT 14.00 1.1667 16.3331 Upto 4" thick chajja/ loft SFT 20.00 1.1667 23.3332 Sloping slab 5" SFT 24.00 1.1667 28.0033 Stair tappa WITH waist slab RFT 100.00 1.1667 116.6734 4" thick Floor slab with nominal reinforcement SFT 6.00 1.00 6.00

6" RCC WALL / PARDI SFT 21.00 1.1667 24.509" RCC WALL / PARDI SFT 24.00 1.1667 28.00

35 9" Brick masonary SFT 6.00 1.1667 7.0036 4.5" brick masonary SFT 5.00 1.1667 5.8337 14" brick masonary SFT 9.50 1.1667 11.0838 4.5" brick mas. Cornice rft 8.00 1.1667 9.33

Page 2: Rate Analysis

SCHEDULE -C BASIC RATE AVG.lead 25% FINAL RATEAVERAGE LABOURE RATE CONSIDERED FOR RATE ANALYSIS GF TO 6F

39 Mass masonary CFT 8.00 1.1667 9.3340 9"x 9" Masonary Pillar RFT 11.50 1.1667 13.4241 9"x 12" Masonary Pillar RFT 11.50 1.1667 13.4242 9"x 15" Masonary Pillar RFT 14.00 1.1667 16.3343 9"x 18" Masonary Pillar RFT 14.00 1.1667 16.3344 12"x 12" Masonary Pillar RFT 14.00 1.1667 16.3345 Internal mala plaster SFT 5.00 1.1667 5.8346 Extra over for neeru & cement slurry finishing. SFT 0.50 1.00 0.5047 External Single coat plaster (s.f ) SFT 6.00 1.1667 7.0048 External Double coat plaster (s.f /mala) SFT 8.00 1.1667 9.3349 Vata, patta, tapak RFT 6.00 1.00 6.0050 Stonecrete / Malad with base coat SFT 14.00 1.1667 16.3351 Vata, patta, tapak in Gutka plaster/stonecrete/malad RFT 6.00 1.00 6.0052 Double coat of Gutka Plaster / roller SFT 10.00 1.1667 11.6753 IPS floor finish SFT 7.00 1.1667 8.1754 U.c.r masonary CFT 10.00 1.00 10.0055 Plum concrete CFT 10.00 1.00 10.0056 Flush pointing in rubble masonary SFT 2.00 1.00 2.0057 Exposed pointing in rubble masonary SFT 4.00 1.00 4.0058 Mala plaster on ucr masonary SFT 5.00 1.00 5.0059 KOTA Flooring with ordinary Polish & cutting SFT 8.50 1.1667 9.9260 MARBLE Flooring with ordinary Polish & cutting SFT 12.00 1.1667 14.0061 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishin RFT 8.50 1.1667 9.9262 P.MARBLE for sill / james / skirting / tappa / riser / shelves with cutting & jari finis RFT 12.00 1.1667 14.0063 Ceramic tiles dado / flooring SFT 7.00 1.1667 8.1764 Granamite tiles dado SFT 9.00 1.1667 10.5065 GRANAMITE tile skirting with cutting & jari finishing RFT 8.50 1.1667 9.9266 GRANAMITE tile flooring SFT 8.50 1.1667 9.9267 Granite stone flooring SFT 14.00 1.1667 16.3368 GRANITE for sill / james / skirting / tappa / riser / shelves with cutting & jari finishRFT 14.00 1.1667 16.33

69 MOULDING Of KOTA / MARBLE /GRANITE with with cutting & polishing70 dhar RFT 6.00 1.00 6.0071 dhar+champher - Dc RFT 8.00 1.00 8.0072 champher+dhar+champher - Dcc RFT 11.00 1.00 11.00

Page 3: Rate Analysis

SCHEDULE -C BASIC RATE AVG.lead 25% FINAL RATEAVERAGE LABOURE RATE CONSIDERED FOR RATE ANALYSIS GF TO 6F

73 Half round RFT 15.00 1.00 15.0074 Full round RFT 25.00 1.00 25.0075 Extra over on simple polishing for Mirror polish76 Marble SFT 10.00 1.00 7.5077 Kota SFT 8.50 1.00 6.0078 Waterproof in terrace with brick bats SFT 9.00 1.1667 10.5079 Waterproof vata RFT 9.00 1.1667 10.5080 Waterproof toilet sunk with brick bats concrete and base plaster SFT 13.00 1.1667 15.1781 China mosaic SFT 12.00 1.1667 14.0082 Kolshi filling CFT 2.00 1.00 2.0083 Manglore tile SFT 9.90 1.00 9.9084 Flush door with frame-beading patti- laminate- hardware-fixing comp. SFT 30.00 1.00 30.0085 Window shutter with frame-glass- hardware-fixing comp. SFT 35.00 1.00 35.0086 Architave patti making & fixing RFT 5.00 1.00 5.00

NOTE: ABOVE LABOUR RATE WITH AVERAGE LEAD FOR G+6 STOREY BUILDING WITH STAIR CABIN / L-M ROOM CONSIDERED FOR RATE ANALYSIS

Page 4: Rate Analysis

CONCRETE GRADES

GRADE PROPN MAT. COST PROFIT TOTAL TOTAL L&T SNS mixCFT CM with vat with vat

M8 `1:04:08 39.54 4.61 44.15 1559.14 0 0.00

M10 `1:03:06 45.65 5.04 50.69 1790.10 2600 0.00

M15 `1:02:04 55.28 6.58 61.86 2184.57 2700 0.00

M20 `1:1.5:03 68.31 7.85 76.16 2689.57 2825 2903.00

M25 `1:1:2 79.46 8.88 88.34 3119.70 2925 3018.00

M30 NIL 95.47 10.42 105.89 3739.47 3050 3150.00

cement cement fly ashM8 `1:04:08 kg kg

M10 `1:03:06 185 0 100

M15 `1:02:04 200 0 100

M20 `1:1.5:03 225 245 95

M25 `1:1:2 245 270 105

M30 NIL 280 300 110

Page 5: Rate Analysis

Page 5

SCHEDULE -BBASIC RATES CONSIDERED FOR RATE ANALYSIS

NO ITEM RATE1 UNIT REMARK

1 CEMENT OPC 230.00 BAG

2 CEMENT PPC 230.00 BAG

3 STEEL 35000.00 TON GALLET /BURN

4 KAPCHI 1900.00 BRASS

5 BLACK SAND 1600.00 BRASS

6 YELLOW SAND 1600.00 BRASS

7 BRICKS 3.00 NO

8 YELLOW SOIL 500.00 BRASS

9 QUARRY SPOIL 900.00 BRASS

10 9" RUBBLE 1100.00 BRASS

11 LIME (5KG BAG) 19.00 BAG

12 MARBLE SLAB (GREEN) 40.00 SFT

13 MARBLE SLAB (WHITE , RAJNAGAR) 35.00 SFT

14 BLACK GRANITE - SOUTH 115.00 SFT

15 BLACK GRANITE - COMERTIAL 85.00 SFT

16 COLOR GRANITE 125.00 SFT ONWARDS

17 KOTA (22" X 16") 22.00 SFT 1/2" -3/4" THICK

18 KOTA SLAB 27.50 SFT

19 GRANITE TILE (2' X 1') 45.00 SFT

20 VETRIFIED ( 24 X 24 ) 32.00 SFT ONWARDS

21 VETRIFIED ( 32 X 32 ) 42.00 SFT ONWARDS

22 VETRIFIED ( 36 X 36 ) 65.00 SFT ONWARDS

23 VETRIFIED ( 39 X 39 ) 70.00 SFT ONWARDS

24 GLAZE TILES ( 6 X 8 ) 120.00 PER BOX REGULAR TILE

25 GLAZE TILES ( 8 X 8 ) 160.00 PER BOX

26 GLAZE TILES ( 8 X 12 ) 110.00 PER BOX

27 GLAZE TILES ( 12 X 12 ) 165.00 PER BOX

28 GLAZE TILES ( 12 X 18 ) 230.00 PER BOX

29 GLAZE TILES ( 12 X 24 ) 330.00 PER BOX

30 GLAZE TILES ( 13 X 10 ) 230.00 PER BOX

31 RUSTIK TILES ( 12 X 12 )Nitco ceramic 25.50 SFT

32 PARSOLINA TILES (24 X 24) 25.50 SFT

33 SAL WOOD 651.00 CFT

34 TEAK WOOD (GHANA) 1200.00 CFT

35 4MM PLAIN GLASS 24.00 SFT

36 FLUSH DOOR MR GRADE 45.00 SFT

37 FLUSH DOOR PF GRADE 50.00 SFT

38 LAMINATE 0.8 MM THICK 12.00 SFT

39 LAMINATE 1MM THICK 24.00 SFT

40 VINEER LAMINATE 40.00 SFT

41 WOODEN MOULDING 2 X 1/2 12.00 RFT

42 MAIN DOOR LATCH LOCK 650.00 NO

43 MORTICE LOCK WITH KEY 350.00 NO

44 MORTICE LOCK WITHOUT KEY 350.00 NO

45 3" CP BRASS STOPPER 22.00 NO

46 4" CP BRASS STOPPER 25.00 NO

47 6" CP BRASS STOPPER 35.00 NO

48 4" CP BRASS HANDLE 18.00 NO

49 6" CP BRASS HANDLE 26.00 NO

Page 6: Rate Analysis

Page 650 10" CP BRASS HANDLE 175.00 NO

51 8" S.S WIN.HOOK 14.00 NO

52 3" S.S HINGES 9.50 NO

53 4" S.S HINGES 17.00 NO

54 5" S.S HINGES 26.00 NO

55 DOOR STOPPER CP BRASS 130.00 NO

56 DOOR EYE S.S. 80.00 NO

57 DOOR HOLDER MAGNET PVC 50.00 NO

FOLLOWING ITEMS ARE PRO / APPLYING

58 CEMENT PRIMER (Asian/Narolac) 1.10 SFT

59 ACRYLIC WALL PUTTY 2.65 SFT

60 OIL PAINT 5.25 SFT

61 LUSTER PAINT 7.50 SFT

62 PLASTICK PAINT 7.00 SFT

63 WEATHER SHIELD 7.50 SFT

64 APEX EXTERIOR COLOR 6.50 SFT

65 TEXTURE PLASTER WITH APEX COLOR 18.50 SFT

66 POP PUNNING 12.00 SFT

67 POP CEILLING 35.00 SFT

68 GYPSUM CEILLING 45.00 SFT

69 ANODISED ALUMINIUM VENTILATION with Bajari glass 165.00 SFT

70 ANODISED ALUMINIUM WINDOW with Bajari glass 150.00 SFT

71 M.S GRILL 40.00 KG

72 FRENCH POLISH 6.00 SFT

73 MELAMINE POLISH 22.00 SFT

Page 7: Rate Analysis

Page 7SCHEDULE -DBASIC ITEM RATE ANALYSIS

SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

1 Pro.& filling black sand brought from outside.

black sand 1.00 1600.00 1600.00

shrinkage 15 % 0.20 320.00

mat. Cost 1920.00 19.20

labor cost 100.00 2.00 200 2.00

2120.00

5% ohd/.supervision+ water + el.power 5.00 106.00 1.06

profit on material 15.00 288.00 2.88

profit ON LABOUR 15.00 30.00 0.30

total cost 2544.00

25.44

2 Pro.& filling yellow soil brought from outside.

yellow soil 1.00 500.00 500.00

shrinkage 35 % 0.35 175.00

mat. Cost 675.00 6.75

labor cost 100.00 2.00 200 2.00

875.00

5% ohd/.supervision+ water + el.power 5.00 43.75 0.44

profit on material sup. By owner

profit 15.00 875.00 131.25 1.31

total cost 1050.00

10.50

Page 8: Rate Analysis

Page 8SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

3 Pro.& filling quarry spoil brought from outside.

quarry spoil 1.00 900.00 900.00

shrinkage 20% 0.20 180.00

mat. Cost 1080.00 10.80

labor cost 100.00 2.00 200 2.00

1280.00

5% ohd/.supervision+ water + el.power 5.00 64.00 0.64

profit on material sup. By owner

profit ON LABOUR PART 15.00 1280.00 192.00 1.92

total cost 1536.00

15.36

4 Rubble soaling 9" thk.

Ruble 1.00 1100.00 1100.00

mat. Cost 1100.00 11.00

labor cost 100.00 4.00 400 4.00

1500.00

5% ohd/.supervision+ water + el.power 5.00 75.00 0.75

profit 15.00 1500.00 225.00 2.25

total cost 1800.00

18.00

Page 9: Rate Analysis

Page 9SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

5 Rubble soaling thk. Above 9"

Ruble 1.00 1100.00 1100.00

mat. Cost 1100.00 11.00

labor cost 100.00 6.00 600 6.00

1700.00

5% ohd/.supervision+ water + el.power 5.00 85.00 0.85

profit 15.00 1700.00 255.00 2.55

total cost 2040.00

20.40

6 2" THK PCC (1:4:8)

total concrete 100.00 0.17 16.67

cement 8.11 1.35 230.00 310.88 3.11

sand 0.63 0.10 1600.00 166.99 1.67

metal 0.84 0.14 1900.00 264.42 2.64

mat. Cost 742.29

labor cost 100.00 3.00 300.00 3.00

1042.29

5% ohd/.supervision+ water + el.power 5.00 52.11 0.52

10% profit on cement supply by owner 10.00 310.88 31.09 0.31

15% profit on other material 15.00 431.40 64.71 0.65

profit on labor part 15.00 300.00 45.00 0.45

total cost 1235.20

12.35

7 3" THK PCC (1:4:8)

total concrete 100.00 0.25 25.00

cement 8.11 2.03 230.00 466.33 4.66

sand 0.63 0.16 1600.00 250.48 2.50

metal 0.84 0.21 1900.00 396.63 3.97

mat. Cost 1113.43

labor cost 100.00 4.00 400.00 4.00

1513.43

5% ohd/.supervision+ water + el.power 5.00 75.67 0.76

10% profit on cement supply by owner 10.00 466.33 46.63 0.47

15% profit on other material 15.00 647.11 97.07 0.97

profit on labor part 15.00 400.00 60.00 0.60

total cost 1792.80

17.93

8 3" THK PCC (1:3:6)

total concrete 100.00 0.25 25.00

cement 11.39 2.85 230.00 654.93 6.55

sand 0.57 0.14 1600.00 227.72 2.28

metal 0.85 0.21 1900.00 405.65 4.06

mat. Cost 1288.30

labor cost 100.00 4.00 400.00 4.00

1688.30

5% ohd/.supervision+ water + el.power 5.00 84.41 0.84

10% profit on cement supply by owner 10.00 654.93 65.49 0.65

15% profit on other material 15.00 633.37 95.01 0.95

profit on labor part 15.00 400.00 60.00 0.60

total cost 1993.21

Page 10: Rate Analysis

Page 10SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

19.93

Page 11: Rate Analysis

Page 11SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

9 4" THK PCC (1:4:8)

total concrete 100.00 0.33 33.33

cement 8.11 2.70 230.00 621.77 6.22

sand 0.63 0.21 1600.00 333.97 3.34

metal 0.84 0.28 1900.00 528.83 5.29

mat. Cost 1484.57

labor cost 100.00 4.00 400.00 4.00

1884.57

5% ohd/.supervision+ water + el.power 5.00 94.23 0.94

10% profit on cement supply by owner 10.00 621.77 62.18 0.62

15% profit on other material 15.00 862.81 129.42 1.29

profit on labor part 15.00 400.00 60.00 0.60

total cost 2230.40

22.30

10 4" THK PCC (1:3:6)

total concrete 100.00 0.33 33.33

cement 11.39 3.80 230.00 873.23 8.73

sand 0.57 0.19 1600.00 303.63 3.04

metal 0.85 0.28 1900.00 540.87 5.41

mat. Cost 1717.73

labor cost 100.00 4.00 400.00 4.00

2117.73

5% ohd/.supervision+ water + el.power 5.00 105.89 1.06

10% profit on cement supply by owner 10.00 873.23 87.32 0.87

15% profit on other material 15.00 844.49 126.67 1.27

profit on labor part 15.00 400.00 60.00 0.60

total cost 2497.61

24.98

11 6" THK PCC (1:4:8)

total concrete 100.00 0.50 50.00

cement 8.11 4.06 230.00 932.65 9.33

sand 0.63 0.31 1600.00 500.96 5.01

metal 0.84 0.42 1900.00 793.25 7.93

mat. Cost 2226.86

labor cost 100.00 5.00 500.00 5.00

2726.86

5% ohd/.supervision+ water + el.power 5.00 136.34 1.36

10% profit on cement supply by owner 10.00 932.65 93.27 0.93

15% profit on other material 15.00 1294.21 194.13 1.94

profit on labor part 15.00 500.00 75.00 0.75

total cost 3225.60

32.26

12 6" THK PCC (1:3:6)

total concrete 100.00 0.50 50.00

cement 11.39 5.70 230.00 1309.85 13.10

sand 0.57 0.28 1600.00 455.44 4.55

metal 0.85 0.43 1900.00 811.30 8.11

mat. Cost 2576.59

labor cost 100.00 5.00 500.00 5.00

3076.59

5% ohd/.supervision+ water + el.power 5.00 153.83 1.54

10% profit on cement supply by owner 10.00 1309.85 130.99 1.31

Page 12: Rate Analysis

Page 12SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 1266.74 190.01 1.90

profit on labor part 15.00 500.00 75.00 0.75

total cost 3626.42

36.26

Page 13: Rate Analysis

Page 13SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

13 9" AUGER (M-20)

total concrete 100.00 0.44 44.16

cement 22.00 9.71 230.00 2234.31 22.34

sand 0.5219 0.23 1600.00 368.72 3.69

metal 0.7828 0.35 1900.00 656.74 6.57

mat. Cost 3259.77

labor cost 100.00 18.00 1800.00 18.00

5059.77

5% ohd/.supervision+ water + el.power 5.00 252.99 2.53

10% profit on cement supply by owner 10.00 2234.31 223.43 2.23

15% profit on other material 15.00 1025.47 153.82 1.54

profit on labor part 15.00 1800.00 270.00 2.70

total cost 5960.01

59.60

14 FOUNDATION (M-20)

total concrete 100.00 1.00 100.00

cement 22.00 22.00 230.00 5060.00 50.60

sand 0.5219 0.52 1600.00 835.04 8.35

metal 0.7828 0.78 1900.00 1487.32 14.87

mat. Cost 7382.36

labor cost 100.00 20.00 2000.00 20.00

9382.36

5% ohd/.supervision+ water + el.power 5.00 469.12 4.69

10% profit on cement supply by owner 10.00 5060.00 506.00 5.06

15% profit on other material 15.00 2322.36 348.35 3.48

profit on labor part 15.00 2000.00 300.00 3.00

total cost 11005.83

110.06

15 6"x 9" BEAM ( M-20)

total concrete 100.00 0.38 37.50

cement 22.00 8.25 230.00 1897.50 18.98

sand 0.5219 0.20 1600.00 313.14 3.13

metal 0.7828 0.29 1900.00 557.75 5.58

mat. Cost 2768.39

labor cost 100.00 40.83 4083.33 40.83

6851.72

5% ohd/.supervision+ water + el.power 5.00 342.59 3.43

10% profit on cement supply by owner 10.00 1897.50 189.75 1.90

15% profit on other material 15.00 870.89 130.63 1.31

profit on labor part 15.00 4083.33 612.50 6.13

total cost 8127.19

81.27

16 6"x 12" BEAM / ( M-20)

total concrete 100.00 0.50 50.00

cement 22.00 11.00 230.00 2530.00 25.30

sand 0.5219 0.26 1600.00 417.52 4.18

metal 0.7828 0.39 1900.00 743.66 7.44

mat. Cost 3691.18

labor cost 100.00 40.83 4083.33 40.83

7774.51

5% ohd/.supervision+ water + el.power 5.00 388.73 3.89

10% profit on cement supply by owner 10.00 2530.00 253.00 2.53

Page 14: Rate Analysis

Page 14SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 1161.18 174.18 1.74

profit on labor part 15.00 4083.33 612.50 6.13

total cost 9202.92

92.03

Page 15: Rate Analysis

Page 15SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

17 9"x 9" BEAM / COLUMN ( M-20)

total concrete 100.00 0.56 56.25

cement 22.00 12.38 230.00 2846.25 28.46

sand 0.5219 0.29 1600.00 469.71 4.70

metal 0.7828 0.44 1900.00 836.62 8.37

mat. Cost 4152.58

labor cost 100.00 40.83 4083.33 40.83

8235.91

5% ohd/.supervision+ water + el.power 5.00 411.80 4.12

10% profit on cement supply by owner 10.00 2846.25 284.63 2.85

15% profit on other material 15.00 1306.33 195.95 1.96

profit on labor part 15.00 4083.33 612.50 6.13

total cost 9740.78

97.41

18 9"x 12" BEAM / COLIMN ( M-20)

total concrete 100.00 0.75 75.00

cement 22.00 16.50 230.00 3795.00 37.95

sand 0.5219 0.39 1600.00 626.28 6.26

metal 0.7828 0.59 1900.00 1115.49 11.15

mat. Cost 5536.77

labor cost 100.00 40.83 4083.33 40.83

9620.10

5% ohd/.supervision+ water + el.power 5.00 481.01 4.81

10% profit on cement supply by owner 10.00 3795.00 379.50 3.80

15% profit on other material 15.00 1741.77 261.27 2.61

profit on labor part 15.00 4083.33 612.50 6.13

total cost 11354.37

113.54

19 9"x 15" BEAM / COLIMN ( M-20)

total concrete 100.00 0.94 93.75

cement 22.00 20.63 230.00 4743.75 47.44

sand 0.5219 0.49 1600.00 782.85 7.83

metal 0.7828 0.73 1900.00 1394.36 13.94

mat. Cost 6920.96

labor cost 100.00 40.83 4083.33 40.83

11004.30

5% ohd/.supervision+ water + el.power 5.00 550.21 5.50

10% profit on cement supply by owner 10.00 4743.75 474.38 4.74

15% profit on other material 15.00 2177.21 326.58 3.27

profit on labor part 15.00 4083.33 612.50 6.13

total cost 12967.97

129.68

20 COLUMN /BEAM S/C >=1CFT (M-20)

total concrete 100.00 1.00 100.00

cement 22.00 22.00 230.00 5060.00 50.60

sand 0.5219 0.52 1600.00 835.04 8.35

metal 0.7828 0.78 1900.00 1487.32 14.87

mat. Cost 7382.36

labor cost 100.00 40.83 4083.33 40.83

11465.69

5% ohd/.supervision+ water + el.power 5.00 573.28 5.73

10% profit on cement supply by owner 10.00 5060.00 506.00 5.06

Page 16: Rate Analysis

Page 16SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 2322.36 348.35 3.48

profit on labor part 15.00 4083.33 612.50 6.13

total cost 13505.83

135.06

Page 17: Rate Analysis

Page 17SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

21 4.5" thick SLAB (M-20)

total concrete 100.00 0.38 37.50

cement 22.00 8.25 230.00 1897.50 18.98

sand 0.5219 0.20 1600.00 313.14 3.13

metal 0.7828 0.29 1900.00 557.75 5.58

mat. Cost 2768.39

labor cost 100.00 18.67 1866.67 18.67

4635.05

5% ohd/.supervision+ water + el.power 5.00 231.75 2.32

10% profit on cement supply by owner 10.00 1897.50 189.75 1.90

15% profit on other material 15.00 870.89 130.63 1.31

profit on labor part 15.00 1866.67 280.00 2.80

total cost 5467.19

54.67

22 5" THICK SLAB ( M-20 )

total concrete 100.00 0.42 41.67

cement 22.00 9.17 230.00 2108.33 21.08

sand 0.5219 0.22 1600.00 347.93 3.48

metal 0.7828 0.33 1900.00 619.72 6.20

mat. Cost 3075.98

labor cost 100.00 19.83 1983.33 19.83

5059.32

5% ohd/.supervision+ water + el.power 5.00 252.97 2.53

10% profit on cement supply by owner 10.00 2108.33 210.83 2.11

15% profit on other material 15.00 967.65 145.15 1.45

profit on labor part 15.00 1983.33 297.50 2.98

total cost 5965.76

59.66

23 6" THICK SLAB ( M-20 )

total concrete 100.00 0.50 50.00

cement 22.00 11.00 230.00 2530.00 25.30

sand 0.5219 0.26 1600.00 417.52 4.18

metal 0.7828 0.39 1900.00 743.66 7.44

mat. Cost 3691.18

labor cost 100.00 21.00 2100.00 21.00

5791.18

5% ohd/.supervision+ water + el.power 5.00 289.56 2.90

10% profit on cement supply by owner 10.00 2530.00 253.00 2.53

15% profit on other material 15.00 1161.18 174.18 1.74

profit on labor part 15.00 2100.00 315.00 3.15

total cost 6822.92

68.23

24 4.5" THICK SLOPING SLAB ( M-20 )

total concrete 100.00 0.38 37.50

cement 22.00 8.25 230.00 1897.50 18.98

sand 0.5219 0.20 1600.00 313.14 3.13

metal 0.7828 0.29 1900.00 557.75 5.58

mat. Cost 2768.39

labor cost 100.00 28.00 2800.00 28.00

5568.39

5% ohd/.supervision+ water + el.power 5.00 278.42 2.78

10% profit on cement supply by owner 10.00 1897.50 189.75 1.90

Page 18: Rate Analysis

Page 18SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 870.89 130.63 1.31

profit on labor part 15.00 2800.00 420.00 4.20

total cost 6587.19

65.87

Page 19: Rate Analysis

Page 19SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

25 5" THICK SLOPING SLAB ( M-20 )

total concrete 100.00 0.42 41.67

cement 22.00 9.17 230.00 2108.33 21.08

sand 0.5219 0.22 1600.00 347.93 3.48

metal 0.7828 0.33 1900.00 619.72 6.20

mat. Cost 3075.98

labor cost 100.00 28.00 2800.00 28.00

5875.98

5% ohd/.supervision+ water + el.power 5.00 293.80 2.94

10% profit on cement supply by owner 10.00 2108.33 210.83 2.11

15% profit on other material 15.00 967.65 145.15 1.45

profit on labor part 15.00 2800.00 420.00 4.20

total cost 6945.76

69.46

26 6" THICK SLAB ( M-25 )

total concrete 100.00 0.50 50.00

cement 27.83 13.92 230.00 3200.45 32.00

sand 0.52 0.26 1600.00 417.52 4.18

metal 0.70 0.35 1900.00 661.01 6.61

mat. Cost 4278.98

labor cost 100.00 21.00 2100.00 21.00

6378.98

5% ohd/.supervision+ water + el.power 5.00 318.95 3.19

10% profit on cement supply by owner 10.00 3200.45 320.05 3.20

15% profit on other material 15.00 1078.53 161.78 1.62

profit on labor part 15.00 2100.00 315.00 3.15

total cost 7494.75

74.95

27 9"x 4" LINTEL / COPING ( M-20)

total concrete 100.00 0.25 25.00

cement 22.00 5.50 230.00 1265.00 12.65

sand 0.5219 0.13 1600.00 208.76 2.09

metal 0.7828 0.20 1900.00 371.83 3.72

mat. Cost 1845.59

labor cost 100.00 18.67 1866.67 18.67

3712.26

5% ohd/.supervision+ water + el.power 5.00 185.61 1.86

10% profit on cement supply by owner 10.00 1265.00 126.50 1.27

15% profit on other material 15.00 580.59 87.09 0.87

profit on labor part 15.00 1866.67 280.00 2.80

total cost 4391.46

43.91

28 9"x 6" LINTEL / COPING ( M-20)

total concrete 100.00 0.38 37.50

cement 22.00 8.25 230.00 1897.50 18.98

sand 0.5219 0.20 1600.00 313.14 3.13

metal 0.7828 0.29 1900.00 557.75 5.58

mat. Cost 2768.39

labor cost 100.00 18.67 1866.67 18.67

4635.05

5% ohd/.supervision+ water + el.power 5.00 231.75 2.32

10% profit on cement supply by owner 10.00 1897.50 189.75 1.90

Page 20: Rate Analysis

Page 20SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 870.89 130.63 1.31

profit on labor part 15.00 1866.67 280.00 2.80

total cost 5467.19

54.67

Page 21: Rate Analysis

Page 21SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

29 9"x 7" LINTEL / COPING / RUNNER BEAM ( M-20)

total concrete 100.00 0.44 43.75

cement 22.00 9.63 230.00 2213.75 22.14

sand 0.5219 0.23 1600.00 365.33 3.65

metal 0.7828 0.34 1900.00 650.70 6.51

mat. Cost 3229.78

labor cost 100.00 18.67 1866.67 18.67

5096.45

5% ohd/.supervision+ water + el.power 5.00 254.82 2.55

10% profit on cement supply by owner 10.00 2213.75 221.38 2.21

15% profit on other material 15.00 1016.03 152.40 1.52

profit on labor part 15.00 1866.67 280.00 2.80

total cost 6005.05

60.05

30 6"x 6" LINTEL / COPING ( M-20)

total concrete 100.00 0.25 25.00

cement 22.00 5.50 230.00 1265.00 12.65

sand 0.5219 0.13 1600.00 208.76 2.09

metal 0.7828 0.20 1900.00 371.83 3.72

mat. Cost 1845.59

labor cost 100.00 18.67 1866.67 18.67

3712.26

5% ohd/.supervision+ water + el.power 5.00 185.61 1.86

10% profit on cement supply by owner 10.00 1265.00 126.50 1.27

15% profit on other material 15.00 580.59 87.09 0.87

profit on labor part 15.00 1866.67 280.00 2.80

total cost 4391.46

43.91

31 6"x 4" Chajja STRIPS ( M-20)

total concrete 100.00 0.17 16.50

cement 22.00 3.63 230.00 834.90 8.35

sand 0.5219 0.09 1600.00 137.78 1.38

metal 0.7828 0.13 1900.00 245.41 2.45

mat. Cost 1218.09

labor cost 100.00 RFT 23.33 2333.33 23.33

3551.42

5% ohd/.supervision+ water + el.power 5.00 177.57 1.78

10% profit on cement supply by owner 10.00 834.90 83.49 0.83

15% profit on other material 15.00 383.19 57.48 0.57

profit on labor part 15.00 2333.33 350.00 3.50

total cost 4219.96

42.20

32 6"x 7" Chajja STRIPS ( M-20)

total concrete 100.00 0.29 29.00

cement 22.00 6.38 230.00 1467.40 14.67

sand 0.5219 0.15 1600.00 242.16 2.42

metal 0.7828 0.23 1900.00 431.32 4.31

mat. Cost 2140.88

labor cost 100.00 RFT 23.33 2333.33 23.33

4474.22

5% ohd/.supervision+ water + el.power 5.00 223.71 2.24

10% profit on cement supply by owner 10.00 1467.40 146.74 1.47

Page 22: Rate Analysis

Page 22SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 673.48 101.02 1.01

profit on labor part 15.00 2333.33 350.00 3.50

total cost 5295.69

52.96

Page 23: Rate Analysis

Page 23SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

33 4.5"x 4" LINTEL / COPING ( M-20)

total concrete 100.00 0.125 12.50

cement 22.00 2.75 230.00 632.50 6.33

sand 0.5219 0.07 1600.00 104.38 1.04

metal 0.7828 0.10 1900.00 185.92 1.86

mat. Cost 922.80

labor cost 100.00 rft 16.33 1633.33 16.33

2556.13

5% ohd/.supervision+ water + el.power 5.00 127.81 1.28

10% profit on cement supply by owner 10.00 632.50 63.25 0.63

15% profit on other material 15.00 290.30 43.54 0.44

profit on labor part 15.00 1633.33 245.00 2.45

total cost 3035.73

30.36

34 4.5"x 6" LINTEL / COPING ( M-20)

total concrete 100.00 0.188 18.75

cement 22.00 4.13 230.00 948.75 9.49

sand 0.5219 0.10 1600.00 156.57 1.57

metal 0.7828 0.15 1900.00 278.87 2.79

mat. Cost 1384.19

labor cost 100.00 rft 16.33 1633.33 16.33

3017.53

5% ohd/.supervision+ water + el.power 5.00 150.88 1.51

10% profit on cement supply by owner 10.00 948.75 94.88 0.95

15% profit on other material 15.00 435.44 65.32 0.65

profit on labor part 15.00 1633.33 245.00 2.45

total cost 3573.59

35.74

35 4" THICK CHHAJA / LOFT (M-20)

total concrete 100.00 0.333 33.33

cement 22.00 7.33 230.00 1686.67 16.87

sand 0.5219 0.17 1600.00 278.35 2.78

metal 0.7828 0.26 1900.00 495.77 4.96

mat. Cost 2460.79

labor cost 100.00 sft 23.33 2333.33 23.33

4794.12

5% ohd/.supervision+ water + el.power 5.00 239.71 2.40

10% profit on cement supply by owner 10.00 1686.67 168.67 1.69

15% profit on other material 15.00 774.12 116.12 1.16

profit on labor part 15.00 2333.33 350.00 3.50

total cost 5668.61

56.69

36 5" THICK CHHAJA / LOFT (M-20)

total concrete 100.00 0.417 41.67

cement 22.00 9.17 230.00 2108.33 21.08

sand 0.5219 0.22 1600.00 347.93 3.48

metal 0.7828 0.33 1900.00 619.72 6.20

mat. Cost 3075.98

labor cost 100.00 sft 23.33 2333.33 23.33

5409.32

5% ohd/.supervision+ water + el.power 5.00 270.47 2.70

10% profit on cement supply by owner 10.00 2108.33 210.83 2.11

15% profit on other material 15.00 967.65 145.15 1.45

Page 24: Rate Analysis

Page 24SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

profit on labor part 15.00 2333.33 350.00 3.50

total cost 6385.76

63.86

Page 25: Rate Analysis

Page 25SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

37 7" THICK CHHAJA / LOFT (M-20)

total concrete 100.00 0.580 58.00

cement 22.00 12.76 230.00 2934.80 29.35

sand 0.5219 0.30 1600.00 484.32 4.84

metal 0.7828 0.45 1900.00 862.65 8.63

mat. Cost 4281.77

labor cost 100.00 sft 23.33 2333.33 23.33

6615.10

5% ohd/.supervision+ water + el.power 5.00 330.76 3.31

10% profit on cement supply by owner 10.00 2934.80 293.48 2.93

15% profit on other material 15.00 1346.97 202.05 2.02

profit on labor part 15.00 2333.33 350.00 3.50

total cost 7791.38

77.91

38 STAIR STEPS WITH WAIST SLAB (M-20)

Quantity for 1 rft 0.50 12.5"+5.5" 10"

step rft 10" x 7" T/R with waist slab 0.63

total concrete 100.00 0.625 62.50

cement 22.00 13.75 230.00 3162.50 31.63

sand 0.5219 0.33 1600.00 521.90 5.22

metal 0.7828 0.49 1900.00 929.58 9.30

mat. Cost 4613.98

labor cost 100.00 rft 116.67 11666.67 116.67

16280.64

5% ohd/.supervision+ water + el.power 5.00 814.03 8.14

10% profit on cement supply by owner 10.00 3162.50 316.25 3.16

15% profit on other material 15.00 1451.48 217.72 2.18

profit on labor part 15.00 11666.67 1750.00 17.50

total cost 19378.65

193.79

39 4" THICK FLOOR SLAB (M-15) with steel

total concrete 100.00 0.333 33.33

cement 15.66 5.22 230.00 1200.60 12.01

sand 0.59 0.20 1600.00 313.12 3.13

metal 0.78 0.26 1900.00 495.77 4.96

mat. Cost 2009.49

labor cost 100.00 sft 6.00 600.00 6.00

2609.49

5% ohd/.supervision+ water + el.power 5.00 130.47 1.30

10% profit on cement supply by owner 10.00 1200.60 120.06 1.20

15% profit on other material 15.00 808.89 121.33 1.21

profit on labor part 15.00 600.00 90.00 0.90

total cost 3071.36

30.71

Page 26: Rate Analysis

Page 26SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

40 6" THICK FLOOR SLAB (M-15) with steel

total concrete 100.00 0.500 50.00

cement 15.66 7.83 230.00 1800.90 18.01

sand 0.59 0.29 1600.00 469.68 4.70

metal 0.78 0.39 1900.00 743.66 7.44

mat. Cost 3014.24

labor cost 100.00 sft 6.00 600.00 6.00

3614.24

5% ohd/.supervision+ water + el.power 5.00 180.71 1.81

10% profit on cement supply by owner 10.00 1800.90 180.09 1.80

15% profit on other material 15.00 1213.34 182.00 1.82

profit on labor part 15.00 600.00 90.00 0.90

total cost 4247.04

42.47

BRICK MASONARY

41 9" THICK BRICK MASONARY ( 1 :6 )

cement 2.65 230.00 609.50 6.10

sand 0.2672 1600.00 427.52 4.28

bricks 1006.00 3.00 3018.00 30.18

mat. Cost 4055.02

labor cost 100.00 7.00 700.00 7.00

4755.02

5% ohd/.supervision+ water + el.power 5.00 237.75 2.38

10% profit on cement supply by owner 10.00 609.50 60.95 0.61

15% profit on other material 15.00 3445.52 516.83 5.17

profit on labor part 15.00 700.00 105.00 1.05

total cost 5675.55

56.76

42 4.5" THICK BRICK MASONARY ( 1 :4 )

cement 1.43 230.00 328.90 3.29

sand 0.086 1600.00 137.60 1.38

bricks 478.00 3.00 1434.00 14.34

mat. Cost 1900.50

labor cost 100.00 5.83 583.33 5.83

2483.83

5% ohd/.supervision+ water + el.power 5.00 124.19 1.24

10% profit on cement supply by owner 10.00 328.90 32.89 0.33

15% profit on other material 15.00 1571.60 235.74 2.36

profit on labor part 15.00 583.33 87.50 0.88

total cost 2964.16

29.64

43 14" THICK BRICK MASONARY ( 1 :6 )

14" B.m ( 1:6 c.m )

cement 5.30 230.00 1219.00 12.19

sand 0.477 1600.00 763.84 7.64

bricks 1485.00 3.00 4455.00 44.55

mat. Cost 6437.84

labor cost 100.00 sft 11.08 1108.33 11.08

7546.17

5% ohd/.supervision+ water + el.power 5.00 377.31 3.77

10% profit on cement supply by owner 10.00 1219.00 121.90 1.22

Page 27: Rate Analysis

Page 27SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 5218.84 782.83 7.83

profit on labor part 15.00 1108.33 166.25 1.66

total cost 8994.46

89.94

Page 28: Rate Analysis

Page 28SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

44 4.5" brick mas. Cornice

for 100rft single brick

cement 1.19 230.00 273.70 2.74

sand 0.072 1600.00 114.40 1.14

bricks 294.00 3.00 882.00 8.82

mat. Cost 1270.10

labor cost 100.00 rft 9.33 933.33 9.33

2203.43

5% ohd/.supervision+ water + el.power 5.00 110.17 1.10

10% profit on cement supply by owner 10.00 273.70 27.37 0.27

15% profit on other material 15.00 996.40 149.46 1.49

profit on labor part 15.00 933.33 140.00 1.40

total cost 2630.44

26.30

45 MASS MASONARY (1:6)

cement 4.55 230.00 1046.50 10.47

sand 0.409 1600.00 654.72 6.55

bricks 1271.00 3.00 3813.00 38.13

mat. Cost 5514.22

labor cost 100.00 cft 9.33 933.33 9.33

6447.55

5% ohd/.supervision+ water + el.power 5.00 322.38 3.22

10% profit on cement supply by owner 10.00 1046.50 104.65 1.05

15% profit on other material 15.00 4467.72 670.16 6.70

profit on labor part 15.00 933.33 140.00 1.40

total cost 7684.74

76.85

46 9"x 9" PILLAR

cement 2.19 230.00 503.70 5.04

sand 0.197 1600.00 315.20 3.15

bricks 755.00 3.00 2265.00 22.65

mat. Cost 3083.90

labor cost 100.00 rft 13.42 1341.67 13.42

4425.57

5% ohd/.supervision+ water + el.power 5.00 221.28 2.21

10% profit on cement supply by owner 10.00 503.70 50.37 0.50

15% profit on other material 15.00 2580.20 387.03 3.87

profit on labor part 15.00 1341.67 201.25 2.01

total cost 5285.50

52.85

Page 29: Rate Analysis

Page 29SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

47 9"x 12" PILLAR

cement 3.05 230.00 701.50 7.02

sand 0.275 1600.00 439.36 4.39

bricks 1125.00 3.00 3375.00 33.75

mat. Cost 4515.86

labor cost 100.00 rft 13.42 1341.67 13.42

5857.53

5% ohd/.supervision+ water + el.power 5.00 292.88 2.93

10% profit on cement supply by owner 10.00 701.50 70.15 0.70

15% profit on other material 15.00 3814.36 572.15 5.72

profit on labor part 15.00 1341.67 201.25 2.01

total cost 6993.96

69.94

48 9"x 15" PILLAR

cement 3.75 230.00 862.50 8.63

sand 0.343 1600.00 549.12 5.49

bricks 1260.00 3.00 3780.00 37.80

mat. Cost 5191.62

labor cost 100.00 rft 16.33 1633.33 16.33

6824.95

5% ohd/.supervision+ water + el.power 5.00 341.25 3.41

10% profit on cement supply by owner 10.00 862.50 86.25 0.86

15% profit on other material 15.00 4329.12 649.37 6.49

profit on labor part 15.00 1633.33 245.00 2.45

total cost 8146.82

81.47

49 9"x 18" PILLAR

cement 4.38 230.00 1007.40 10.07

sand 0.400 1600.00 640.00 6.40

bricks 1510.00 3.00 4530.00 45.30

mat. Cost 6177.40

labor cost 100.00 rft 16.33 1633.33 16.33

7810.73

5% ohd/.supervision+ water + el.power 5.00 390.54 3.91

10% profit on cement supply by owner 10.00 1007.40 100.74 1.01

15% profit on other material 15.00 5170.00 775.50 7.76

profit on labor part 15.00 1633.33 245.00 2.45

total cost 9322.51

93.23

50 9"x 24" PILLAR

cement 5.30 230.00 1219.00 12.19

sand 0.534 1600.00 855.04 8.55

bricks 2012.00 3.00 6036.00 60.36

mat. Cost 8110.04

labor cost 100.00 rft 11.00 1100.00 11.00

9210.04

5% ohd/.supervision+ water + el.power 5.00 460.50 4.61

10% profit on cement supply by owner 10.00 1219.00 121.90 1.22

15% profit on other material 15.00 6891.04 1033.66 10.34

profit on labor part 15.00 1100.00 165.00 1.65

Page 30: Rate Analysis

Page 30SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

total cost 10991.10

109.91

Page 31: Rate Analysis

Page 31SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

51 SMALL PADESTALS/WALLS.

cement 2.65 230.00 609.50 6.10

sand 0.2672 1600.00 427.52 4.28

bricks 1006.00 3.00 3018.00 30.18

mat. Cost 4055.02

labor cost 100.00 RFT/SFT 7.00 700.00 7.00

4755.02

5% ohd/.supervision+ water + el.power 5.00 237.75 2.38

10% profit on cement supply by owner 10.00 609.50 60.95 0.61

15% profit on other material 15.00 3445.52 516.83 5.17

profit on labor part 15.00 700.00 105.00 1.05

total cost 5675.55

56.76

52 12"x 12" PILLAR

cement 4.75 230.00 1092.50 10.93

sand 0.428 1600.00 684.48 6.84

bricks 1270.00 3.00 3810.00 38.10

mat. Cost 5586.98

labor cost 100.00 rft 16.33 1633.33 16.33

7220.31

5% ohd/.supervision+ water + el.power 5.00 361.02 3.61

10% profit on cement supply by owner 10.00 1092.50 109.25 1.09

15% profit on other material 15.00 4494.48 674.17 6.74

profit on labor part 15.00 1633.33 245.00 2.45

total cost 8609.75

86.10

53 INTERNAL MALA PLASTER

cement 1.49 230.00 342.70 3.43

yellow sand 0.090 1600.00 144.00 1.44

mat. Cost 486.70

labor cost 100.00 sft 5.83 583.33 5.83

1070.03

5% ohd/.supervision+ water + el.power 5.00 53.50 0.54

10% profit on cement supply by owner 10.00 342.70 34.27 0.34

15% profit on other material 15.00 144.00 21.60 0.22

profit on labor part 15.00 583.33 87.50 0.88

total cost 1266.91

12.67

54 EXTRA OVER MALA PLASTER FOR NEERU PLASTER

cement 0.25 230.00 57.50 0.58

LIME 5KG BAG 2.000 19.00 38.00 0.38

mat. Cost 95.50

labor cost 100.00 sft 0.50 50.00 0.50

145.50

5% ohd/.supervision+ water + el.power 5.00 7.28 0.07

10% profit on cement supply by owner 10.00 57.50 5.75 0.06

15% profit on other material 15.00 38.00 5.70 0.06

profit on labor part 15.00 50.00 7.50 0.08

Page 32: Rate Analysis

Page 32SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

total cost 171.73

1.72

Page 33: Rate Analysis

Page 33SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

55 EXTERNAL SINGLE COAT SANDFACE PLASTER

cement 1.49 230.00 342.70 3.43

black sand 0.111 1600.00 178.24 1.78

mat. Cost 520.94

labor cost 100.00 sft 7.00 700.00 7.00

1220.94

5% ohd/.supervision+ water + el.power 5.00 61.05 0.61

10% profit on cement supply by owner 10.00 342.70 34.27 0.34

15% profit on other material 15.00 178.24 26.74 0.27

profit on labor part 15.00 700.00 105.00 1.05

total cost 1447.99

14.48

56 EXTERNAL DOUBLE COAT SANDFACE PLASTER

cement 2.78 230.00 639.40 6.39

black sand for first coat 0.111 1600.00 178.24 1.78

yellow sand for second coat 0.062 1600.00 99.68 1.00

mat. Cost 917.32

labor cost 100.00 sft 9.33 933.33 9.33

1850.65

5% ohd/.supervision+ water + el.power 5.00 92.53 0.93

10% profit on cement supply by owner 10.00 639.40 63.94 0.64

15% profit on other material 15.00 277.92 41.69 0.42

profit on labor part 15.00 933.33 140.00 1.40

total cost 2188.81

21.89

57 EXTERNAL DOUBLE COAT OF GUTKA /MALA/ROLLER PLASTER

cement 3.53 230.00 811.90 8.12

black sand for first coat 0.111 1600.00 178.24 1.78

yellow sand for second coat 0.062 1600.00 99.68 1.00

mat. Cost 1089.82

labor cost 100.00 sft 11.67 1166.67 11.67

2256.49

5% ohd/.supervision+ water + el.power 5.00 112.82 1.13

10% profit on cement supply by owner 10.00 811.90 81.19 0.81

15% profit on other material 15.00 277.92 41.69 0.42

profit on labor part 15.00 1166.67 175.00 1.75

total cost 2667.19

26.67

Page 34: Rate Analysis

Page 34SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

58 PATTA/TAPAK IN GUTKA /MALA PLASTER

cement 3.53 0.5 230.00 405.95 4.06

black sand for first coat 0.111 0.5 1600.00 89.12 0.89

yellow sand for second coat 0.062 0.5 1600.00 49.84 0.50

mat. Cost 544.91

labor cost(6 rs for single by other agency 100.00 RFT 6.00 600.00 6.00

+ 12 rs for second coat by other agency) 1144.91

5% ohd/.supervision+ water + el.power 5.00 57.25 0.57

10% profit on cement supply by owner 10.00 405.95 40.60 0.41

15% profit on other material 15.00 138.96 20.84 0.21

profit on labor part 15.00 600.00 90.00 0.90

total cost 1353.59

13.54

59 STONECRETE /MALAD PLASTER

cement 3.65 230.00 839.50 8.40

black sand for first coat 0.111 1600.00 178.24 1.78

yellow sand for mixing with chips 0.000 1600.00 0.00 0.00

stone chips 166.110 kg 7.00 1162.77 11.63

mat. Cost 2180.51

labor cost 100.00 sft 16.33 1633.33 16.33

3813.84

5% ohd/.supervision+ water + el.power 5.00 190.69 1.91

10% profit on cement supply by owner 10.00 839.50 83.95 0.84

15% profit on other material 15.00 1341.01 201.15 2.01

profit on labor part 15.00 1633.33 245.00 2.45

total cost 4534.64

45.35

60 PATTA IN STONECRETE /MALAD PLASTER

cement 3.65 0.5 230.00 419.75 4.20

black sand for first coat 0.111 0.5 1600.00 89.12 0.89

yellow sand for mixing with chips 0.000 0.5 1600.00 0.00 0.00

stone chips 166.110 0.5 7.00 581.39 5.81

mat. Cost 1090.26

labor cost 100.00 sft 6.00 600.00 6.00

1690.26

5% ohd/.supervision+ water + el.power 5.00 84.51 0.85

10% profit on cement supply by owner 10.00 419.75 41.98 0.42

15% profit on other material 15.00 670.51 100.58 1.01

profit on labor part 15.00 600.00 90.00 0.90

total cost 2007.32

20.07

61 vata plaster work (1:4)

cement 1.13 230.00 259.90 2.60

yellow sand 0.110 1600.00 176.00 1.76

mat. Cost 435.90

labor cost 100.00 rft 6.00 600.00 6.00

1035.90

5% ohd/.supervision+ water + el.power 5.00 51.80 0.52

10% profit on cement supply by owner 10.00 259.90 25.99 0.26

15% profit on other material 15.00 176.00 26.40 0.26

Page 35: Rate Analysis

Page 35SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

profit on labor part 15.00 600.00 90.00 0.90

total cost 1230.09

12.30

Page 36: Rate Analysis

Page 36SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

62 tapak plaster work (1:4)

cement 1.00 230.00 230.00 2.30

yellow sand 0.032 1600.00 50.72 0.51

mat. Cost 280.72

labor cost 100.00 rft 6.00 600.00 6.00

880.72

5% ohd/.supervision+ water + el.power 5.00 44.04 0.44

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 50.72 7.61 0.08

profit on labor part 15.00 600.00 90.00 0.90

total cost 1045.36

10.45

63 Patta plaster work (1:4)

cement 1.00 230.00 230.00 2.30

yellow sand 0.051 1600.00 81.28 0.81

mat. Cost 311.28

labor cost 100.00 rft 6.00 600.00 6.00

911.28

5% ohd/.supervision+ water + el.power 5.00 45.56 0.46

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 81.28 12.19 0.12

profit on labor part 15.00 600.00 90.00 0.90

total cost 1082.04

10.82

64 Stonecrete tapak plaster work (1:4)

cement 1.20 230.00 276.00 2.76

black sand for first coat 0.030 1600.00 48.00 0.48

yellow sand for mixing with chips 0.000 1600.00 0.00 0.00

stone chips 19.500 kg 7.00 136.50 1.37

mat. Cost 460.50

labor cost 100.00 rft 6.00 600.00 6.00

1060.50

5% ohd/.supervision+ water + el.power 5.00 53.03 0.53

10% profit on cement supply by owner 10.00 276.00 27.60 0.28

15% profit on other material 15.00 184.50 27.68 0.28

profit on labor part 15.00 600.00 90.00 0.90

total cost 1258.80

12.59

Page 37: Rate Analysis

Page 37SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

65 REINFORCEMENT

STEEL with 2.5% wastage 0.001025 ton 29000.00 29.72

BINDING WIRE 0.02 kg/ton 40.00 0.80

mat. Cost 30.53

5% ohd/.supervision+ el.power 5.00 1.53

10% profit on steel supply by owner 10.00 30.53 3.05

total cost 35.10

35.10

66 Ips floor finish 2" thick

total concrete 100.00 0.167 16.67

cement+ toping 15.66 3.11 230.00 715.30 7.15

sand 0.59 0.10 1600.00 156.56 1.57

metal 0.78 0.13 1900.00 247.89 2.48

mat. Cost 1119.75

labor cost 100.00 rft 8.17 816.67 8.17

1936.41

5% ohd/.supervision+ water + el.power 5.00 96.82 0.97

10% profit on cement supply by owner 10.00 715.30 71.53 0.72

15% profit on other material 15.00 404.45 60.67 0.61

profit on labor part 15.00 816.67 122.50 1.23

total cost 2287.93

22.88

67 U.C.R masonary in c.m 1:6 without pointing.

mortar 40% 40.00 1.000 40.00

cement 15.00 6.00 230.00 1380.00 13.80

sand 1.30 0.52 1600.00 832.00 8.32

rubble stone 1.25 0.75 1100.00 825.00 8.25

mat. Cost 3037.00

labor cost 100.00 cft 10.00 1000.00 10.00

4037.00

5% ohd/.supervision+ water + el.power 5.00 201.85 2.02

10% profit on cement supply by owner 10.00 1380.00 138.00 1.38

15% profit on other material 15.00 1657.00 248.55 2.49

profit on labor part 15.00 1000.00 150.00 1.50

total cost 4775.40

47.75

68 Plum concrete

60% ruble + 40% concrete(1:3:6) 40.00 1.000 40.00

cement 11.05 4.42 230.00 1016.60 10.17

sand 0.55 0.22 1600.00 352.00 3.52

metal 0.83 0.33 1900.00 630.80

rubble stone 1.25 0.75 1100.00 825.00 8.25

mat. Cost 2824.40

labor cost 100.00 cft 10.00 1000.00 10.00

3824.40

5% ohd/.supervision+ water + el.power 5.00 191.22 1.91

10% profit on cement supply by owner 10.00 1016.60 101.66 1.02

15% profit on other material 15.00 1807.80 271.17 2.71

Page 38: Rate Analysis

Page 38SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

profit on labor part 15.00 1000.00 150.00 1.50

total cost 4538.45

45.38

Page 39: Rate Analysis

Page 39SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

69 Flush pointing on rubble masonary

cement 0.80 230.00 184.00 1.84

sand 0.090 1600.00 144.00 1.44

mat. Cost 328.00

labor cost 100.00 sft 2.00 200.00 2.00

528.00

5% ohd/.supervision+ water + el.power 5.00 26.40 0.26

10% profit on cement supply by owner 10.00 184.00 18.40 0.18

15% profit on other material 15.00 144.00 21.60 0.22

profit on labor part 15.00 200.00 30.00 0.30

total cost 624.40

6.24

70 Exposed pointing on rubble masonary

cement 2.00 230.00 460.00 4.60

sand 0.150 1600.00 240.00 2.40

mat. Cost 700.00

labor cost 100.00 sft 4.00 400.00 4.00

1100.00

5% ohd/.supervision+ water + el.power 5.00 55.00 0.55

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 240.00 36.00 0.36

profit on labor part 15.00 400.00 60.00 0.60

total cost 1297.00

12.97

71 Mala plaster on rubble masonary (1:4)

100.00 0.125 12.50

cement 22.88 2.86 230.00 657.80 6.58

sand 132.00 0.165 1600.00 264.00 2.64

mat. Cost 921.80

labor cost 100.00 sft 5.00 500.00 5.00

1421.80

5% ohd/.supervision+ water + el.power 5.00 71.09 0.71

10% profit on cement supply by owner 10.00 657.80 65.78 0.66

15% profit on other material 15.00 264.00 39.60 0.40

profit on labor part 15.00 500.00 75.00 0.75

total cost 1673.27

16.73

72 KOTA Flooring with ordinary Polish & cutting(22 x 16,18 x 18, 24 x 24)

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

kota with wastage 121.00 121.00 22.00 2662.00 26.62

mat. Cost 3388.67

labor cost 100.00 sft 9.92 991.67 9.92

4380.33

5% ohd/.supervision+ water + el.power 5.00 219.02 2.19

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 2928.67 439.30 4.39

profit on labor part 15.00 991.67 148.75 1.49

Page 40: Rate Analysis

Page 40SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

total cost 5233.40

52.33

Page 41: Rate Analysis

Page 41SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

73 KOTA slab Flooring with ordinary Polish & cutting

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

kota with wastage 121.00 121.00 27.50 3327.50 33.28

mat. Cost 4054.17

labor cost 100.00 sft 9.92 991.67 9.92

5045.83

5% ohd/.supervision+ water + el.power 5.00 252.29 2.52

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 3594.17 539.13 5.39

profit on labor part 15.00 991.67 148.75 1.49

total cost 6032.00

60.32

74 GreenMarble Flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

white cement for joint filling 2.00 2.000 12.00 24.00

marble with wastage 110.00 110.00 40.00 4400.00 44.00

mat. Cost 5150.67

labor cost 100.00 sft 14.00 1400.00 14.00

6550.67

5% ohd/.supervision+ water + el.power 5.00 327.53 3.28

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 4690.67 703.60 7.04

profit on labor part 15.00 1400.00 210.00 2.10

total cost 7837.80

78.38

75 White Marble slab (rajnagar) Flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

white cement for joint filling 2.00 2.000 12.00 24.00 0.24

marble with wastage 110.00 110.00 35.00 3850.00 38.50

mat. Cost 4600.67

labor cost 100.00 sft 14.00 1400.00 14.00

6000.67

5% ohd/.supervision+ water + el.power 5.00 300.03 3.00

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 4140.67 621.10 6.21

profit on labor part 15.00 1400.00 210.00 2.10

total cost 7177.80

71.78

Page 42: Rate Analysis

Page 42SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

76 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 2.75" width)

100.00 0.250 25.00

cement 2.00 0.50 230.00 115.00 1.15

sand 0.17 0.042 1600.00 66.67 0.67

kota with wastage 110.00 27.50 22.00 605.00 6.05

mat. Cost 786.67

labor cost 100.00 rft 9.92 991.67 9.92

1778.33

5% ohd/.supervision+ water + el.power 5.00 88.92 0.89

10% profit on cement supply by owner 10.00 115.00 11.50 0.12

15% profit on other material 15.00 671.67 100.75 1.01

profit on labor part 15.00 991.67 148.75 1.49

total cost 2128.25

21.28

77 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" to 5.75" width)

100.00 0.500 50.00

cement 2.00 1.00 230.00 230.00 2.30

sand 0.17 0.083 1600.00 133.33 1.33

kota with wastage 105.00 52.50 22.00 1155.00 11.55

mat. Cost 1518.33

labor cost 100.00 rft 9.92 991.67 9.92

2510.00

5% ohd/.supervision+ water + el.power 5.00 125.50 1.26

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 1288.33 193.25 1.93

profit on labor part 15.00 991.67 148.75 1.49

total cost 3000.50

30.01

78 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 6" to 11.75" width)

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

kota slab 100.00 100.00 27.50 2750.00 27.50

mat. Cost 3476.67

labor cost 100.00 rft 9.92 991.67 9.92

4468.33

5% ohd/.supervision+ water + el.power 5.00 223.42 2.23

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 3016.67 452.50 4.53

profit on labor part 15.00 991.67 148.75 1.49

total cost 5339.00

53.39

79 P.KOTA for sill / james / tappa / riser / shelves with cutting & jari finishing ( up to 12" to 17.75" width)

100.00 1.500 150.00

cement 2.00 3.00 230.00 690.00 6.90

sand 0.17 0.250 1600.00 400.00 4.00

kota slab 100.00 150.00 27.50 4125.00 41.25

mat. Cost 5215.00

labor cost 150.00 rft 9.92 1487.50 14.88

6702.50

5% ohd/.supervision+ water + el.power 5.00 335.13 3.35

10% profit on cement supply by owner 10.00 690.00 69.00 0.69

15% profit on other material 15.00 4525.00 678.75 6.79

Page 43: Rate Analysis

Page 43SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

profit on labor part 15.00 1487.50 223.13 2.23

total cost 8008.50

80.09

Page 44: Rate Analysis

Page 44SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

80 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" width)

100.00 0.250 25.00

cement 2.00 0.50 230.00 115.00 1.15

sand 0.17 0.042 1600.00 66.67 0.67

white marble with wastage 105.00 26.25 35.00 918.75 9.19

white cement 2.00 0.50 12.00 6.00 0.06

mat. Cost 1106.42

labor cost 100.00 rft 14.00 1400.00 14.00

2506.42

5% ohd/.supervision+ water + el.power 5.00 125.32 1.25

10% profit on cement supply by owner 10.00 115.00 11.50 0.12

15% profit on other material 15.00 991.42 148.71 1.49

profit on labor part 15.00 1400.00 210.00 2.10

total cost 3001.95

30.02

81 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" to 6" width)

100.00 0.500 50.00

cement 2.00 1.00 230.00 230.00 2.30

sand 0.17 0.083 1600.00 133.33 1.33

white marble with wastage 105.00 52.50 35.00 1837.50 18.38

white cement 2.00 1.00 12.00 12.00 0.12

mat. Cost 2212.83

labor cost 100.00 rft 14.00 1400.00 14.00

3612.83

5% ohd/.supervision+ water + el.power 5.00 180.64 1.81

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 1982.83 297.43 2.97

profit on labor part 15.00 1400.00 210.00 2.10

total cost 4323.90

43.24

82 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 6" to 9" width)

100.00 0.750 75.00

cement 2.00 1.50 230.00 345.00 3.45

sand 0.17 0.125 1600.00 200.00 2.00

white marble 100.00 75.00 35.00 2625.00 26.25

white cement 2.00 1.50 12.00 18.00 0.18

mat. Cost 3188.00

labor cost 100.00 rft 14.00 1400.00 14.00

4588.00

5% ohd/.supervision+ water + el.power 5.00 229.40 2.29

10% profit on cement supply by owner 10.00 345.00 34.50 0.35

15% profit on other material 15.00 2843.00 426.45 4.26

profit on labor part 15.00 1400.00 210.00 2.10

total cost 5488.35

54.88

Page 45: Rate Analysis

Page 45SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

83 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing( up to 9" to 12" width)

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

white marble 100.00 100.00 35.00 3500.00 35.00

white cement 2.00 2.00 12.00 24.00 0.24

mat. Cost 4250.67

labor cost 100.00 rft 14.00 1400.00 14.00

5650.67

5% ohd/.supervision+ water + el.power 5.00 282.53 2.83

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 3790.67 568.60 5.69

profit on labor part 15.00 1400.00 210.00 2.10

total cost 6757.80

67.58

84 P.Marble for tappa / riser / shelves with cutting & jari finishing ( up to 12" to 18" width)

100.00 1.500 150.00

cement 2.00 3.00 230.00 690.00 6.90

sand 0.17 0.250 1600.00 400.00 4.00

white marble 100.00 150.00 35.00 5250.00 52.50

white cement 2.00 3.00 12.00 36.00 0.36

mat. Cost 6376.00

labor cost 150.00 rft 14.00 2100.00 21.00

8476.00

5% ohd/.supervision+ water + el.power 5.00 423.80 4.24

10% profit on cement supply by owner 10.00 690.00 69.00 0.69

15% profit on other material 15.00 5686.00 852.90 8.53

profit on labor part 15.00 2100.00 315.00 3.15

total cost 10136.70

101.37

85 Parsolina Ceramic tiles Flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

tiles 24" x 24" with wastage 105.00 105.00 25.50 2677.50 26.78

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 3428.17

labor cost 100.00 sft 8.17 816.67 8.17

4244.83

5% ohd/.supervision+ water + el.power 5.00 212.24 2.12

10% profit on cement & tiles supply by owner 10.00 3137.50 313.75 3.14

15% profit on other material 15.00 290.67 43.60 0.44

profit on labor part 15.00 816.67 122.50 1.23

total cost 4936.93

49.37

Page 46: Rate Analysis

Page 46SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

86 Parsolina Ceramic tiles skirting (3" width)

100.00 0.250 25.00

cement 2.00 0.50 230.00 115.00 1.15

sand 0.17 0.042 1600.00 66.67 0.67

tiles 24" x 24" with wastage 105.00 26.25 25.50 669.38 6.69

white cement for joints 2.00 0.50 12.00 6.00 0.06

mat. Cost 857.04

labor cost 100.00 rft 8.17 816.67 8.17

1673.71

5% ohd/.supervision+ water + el.power 5.00 83.69 0.84

10% profit on cement & tiles supply by owner 10.00 784.38 78.44 0.78

15% profit on other material 15.00 72.67 10.90 0.11

profit on labor part 15.00 816.67 122.50 1.23

total cost 1969.23

19.69

87 Granamite(Vitrified) tiles Flooring 24" x 24"

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

virified tiles 24" x 24" with wastage 105.00 105.00 32.00 3360.00 33.60

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 4110.67

labor cost 100.00 sft 9.92 991.67 9.92

5102.33

5% ohd/.supervision+ water + el.power 5.00 255.12 2.55

10% profit on cement & tiles supply by owner 10.00 3820.00 382.00 3.82

15% profit on other material 15.00 290.67 43.60 0.44

profit on labor part 15.00 991.67 148.75 1.49

total cost 5931.80

59.32

88 Granamite(Vitrified) tiles Flooring 32" x 32"

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

tiles 32" x 32" with wastage 105.00 105.00 42.00 4410.00 44.10

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 5160.67

labor cost 100.00 sft 9.92 991.67 9.92

6152.33

5% ohd/.supervision+ water + el.power 5.00 307.62 3.08

10% profit on cement & tiles supply by owner 10.00 4870.00 487.00 4.87

15% profit on other material 15.00 290.67 43.60 0.44

profit on labor part 15.00 991.67 148.75 1.49

total cost 7139.30

71.39

Page 47: Rate Analysis

Page 47SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

89 Granamite(Vitrified) tiles Flooring 36" x 36"

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

tiles 36" x 36" with wastage 105.00 105.00 65.00 6825.00 68.25

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 7575.67

labor cost 100.00 sft 9.92 991.67 9.92

8567.33

5% ohd/.supervision+ water + el.power 5.00 428.37 4.28

10% profit on cement & tiles supply by owner 10.00 7285.00 728.50 7.29

15% profit on other material 15.00 290.67 43.60 0.44

profit on labor part 15.00 991.67 148.75 1.49

total cost 9916.55 99.17

90 Granamite(Vitrified) tiles Flooring 39" x 39"

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

tiles 39" x 39" with wastage 105.00 105.00 70.00 7350.00 73.50

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 8100.67

labor cost 100.00 sft 9.92 991.67 9.92

9092.33

5% ohd/.supervision+ water + el.power 5.00 454.62 4.55

10% profit on cement & tiles supply by owner 10.00 7810.00 781.00 7.81

15% profit on other material 15.00 290.67 43.60 0.44

profit on labor part 15.00 991.67 148.75 1.49

total cost 10520.30

105.20

91 Granamite(Vitrified) tiles Dado 24" x 24"

100.00 1.000 100.00

cement 3.00 3.00 230.00 690.00 6.90

virified tiles 24" x 24" with wastage 105.00 105.00 32.00 3360.00 33.60

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 4074.00

labor cost 100.00 sft 10.50 1050.00 10.50

5124.00

5% ohd/.supervision+ water + el.power 5.00 256.20 2.56

10% profit on cement & tiles supply by owner 10.00 4050.00 405.00 4.05

15% profit on other material 15.00 24.00 3.60 0.04

profit on labor part 15.00 1050.00 157.50 1.58

total cost 5946.30

59.46

92 Granamite(Vitrified) tiles Dado 32" x 32"

100.00 1.000 100.00

cement 3.00 3.00 230.00 690.00 6.90

tiles 32" x 32" with wastage 105.00 105.00 42.00 4410.00 44.10

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 5124.00

labor cost 100.00 sft 10.50 1050.00 10.50

6174.00

5% ohd/.supervision+ water + el.power 5.00 308.70 3.09

10% profit on cement & tiles supply by owner 10.00 5100.00 510.00 5.10

Page 48: Rate Analysis

Page 48SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 24.00 3.60 0.04

profit on labor part 15.00 1050.00 157.50 1.58

total cost 7153.80

71.54

Page 49: Rate Analysis

Page 49SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

93 Granamite(Vitrified) tiles Dado 36" x 36"

100.00 1.000 100.00

cement 3.00 3.00 230.00 690.00 6.90

tiles 36" x 36" with wastage 105.00 105.00 65.00 6825.00 68.25

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 7539.00

labor cost 100.00 sft 10.50 1050.00 10.50

8589.00

5% ohd/.supervision+ water + el.power 5.00 429.45 4.29

10% profit on cement & tiles supply by owner 10.00 7515.00 751.50 7.52

15% profit on other material 15.00 24.00 3.60 0.04

profit on labor part 15.00 1050.00 157.50 1.58

total cost 9931.05

99.31

94 Granamite(Vitrified) tiles Dado 39" x 39"

100.00 1.000 100.00

cement 3.00 3.00 230.00 690.00 6.90

tiles 39" x 39" with wastage 105.00 105.00 70.00 7350.00 73.50

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 8064.00

labor cost 100.00 sft 10.50 1050.00 10.50

9114.00

5% ohd/.supervision+ water + el.power 5.00 455.70 4.56

10% profit on cement & tiles supply by owner 10.00 8040.00 804.00 8.04

15% profit on other material 15.00 24.00 3.60 0.04

profit on labor part 15.00 1050.00 157.50 1.58

total cost 10534.80

105.35

95 Granamite(Vitrified) tiles Skirting 24" x 24" (2" width)

100.00 0.167 16.67

cement 2.00 0.33 230.00 76.67 0.77

sand 0.17 0.028 1600.00 44.44 0.44

virified tiles 24" x 24" with wastage 105.00 17.50 32.00 560.00 5.60

white cement for joints 2.00 0.33 12.00 4.00 0.04

mat. Cost 685.11

labor cost 100.00 rft 9.92 991.67 9.92

1676.78

5% ohd/.supervision+ water + el.power 5.00 83.84 0.84

10% profit on cement & tiles supply by owner 10.00 636.67 63.67 0.64

15% profit on other material 15.00 48.44 7.27 0.07

profit on labor part 15.00 991.67 148.75 1.49

total cost 1980.30

19.80

Page 50: Rate Analysis

Page 50SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

96 Granamite(Vitrified) tiles Skirting 32" x 32" (2" width)

100.00 0.167 16.67

cement 2.00 0.33 230.00 76.67 0.77

sand 0.17 0.028 1600.00 44.44 0.44

tiles 32" x 32" with wastage 105.00 17.50 42.00 735.00 7.35

white cement for joints 2.00 0.33 12.00 4.00 0.04

mat. Cost 860.11

labor cost 100.00 rft 9.92 991.67 9.92

1851.78

5% ohd/.supervision+ water + el.power 5.00 92.59 0.93

10% profit on cement & tiles supply by owner 10.00 811.67 81.17 0.81

15% profit on other material 15.00 48.44 7.27 0.07

profit on labor part 15.00 991.67 148.75 1.49

total cost 2181.55

21.82

97 Granamite(Vitrified) tiles Skirting 36" x 36" (2" width)

100.00 0.167 16.67

cement 2.00 0.33 230.00 76.67 0.77

sand 0.17 0.028 1600.00 44.44 0.44

tiles 36" x 36" with wastage 105.00 17.50 65.00 1137.50 11.37

white cement for joints 2.00 0.33 12.00 4.00 0.04

mat. Cost 1262.61

labor cost 100.00 rft 9.92 991.67 9.92

2254.28

5% ohd/.supervision+ water + el.power 5.00 112.71 1.13

10% profit on cement & tiles supply by owner 10.00 1214.17 121.42 1.21

15% profit on other material 15.00 48.44 7.27 0.07

profit on labor part 15.00 991.67 148.75 1.49

total cost 2644.43

26.44

98 Granamite(Vitrified) tiles Skirting 39" x 39" (2" width)

100.00 0.167 16.67

cement 2.00 0.33 230.00 76.67 0.77

sand 0.17 0.028 1600.00 44.44 0.44

tiles 39" x 39" with wastage 105.00 17.50 70.00 1225.00 12.25

white cement for joints 2.00 0.33 12.00 4.00 0.04

mat. Cost 1350.11

labor cost 100.00 sft 9.92 991.67 9.92

2341.78

5% ohd/.supervision+ water + el.power 5.00 117.09 1.17

10% profit on cement & tiles supply by owner 10.00 1301.67 130.17 1.30

15% profit on other material 15.00 48.44 7.27 0.07

profit on labor part 15.00 991.67 148.75 1.49

total cost 2745.05

27.45

Page 51: Rate Analysis

Page 51SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

99 Black Granite (south) stone Flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

Granite stone 105.00 105.00 115.00 12075.00 120.75

color cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 12825.67

labor cost 100.00 sft 16.33 1633.33 16.33

14459.00

5% ohd/.supervision+ water + el.power 5.00 722.95 7.23

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 12365.67 1854.85 18.55

profit on labor part 15.00 1633.33 245.00 2.45

total cost 17327.80

173.28

100 GRANITE for sill / james / skirting cutting & jari finishing (up to 3" wide)

100.00 0.250 25.00

cement 2.00 0.50 230.00 115.00 1.15

sand 0.17 0.042 1600.00 66.67 0.67

Granite stone 105.00 26.25 115.00 3018.75 30.19

color cement for joints 2.00 0.50 12.00 6.00 0.06

mat. Cost 3206.42

labor cost 100.00 rft 16.33 1633.33 16.33

4839.75

5% ohd/.supervision+ water + el.power 5.00 241.99 2.42

10% profit on cement supply by owner 10.00 115.00 11.50 0.12

15% profit on other material 15.00 3091.42 463.71 4.64

profit on labor part 15.00 1633.33 245.00 2.45

total cost 5801.95

58.02

101 GRANITE for sill / james / skirting / riser cutting & jari finishing (up to 3" to 6" wide)

100.00 0.500 50.00

cement 2.00 1.00 230.00 230.00 2.30

sand 0.17 0.083 1600.00 133.33 1.33

Granite stone 105.00 52.50 115.00 6037.50 60.38

color cement for joints 2.00 1.00 12.00 12.00 0.12

mat. Cost 6412.83

labor cost 100.00 rft 16.33 1633.33 16.33

8046.17

5% ohd/.supervision+ water + el.power 5.00 402.31 4.02

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 6182.83 927.43 9.27

profit on labor part 15.00 1633.33 245.00 2.45

total cost 9643.90

96.44

Page 52: Rate Analysis

Page 52SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

102 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 6" to 9" wide)

100.00 0.750 75.00

cement 2.00 1.50 230.00 345.00 3.45

sand 0.17 0.125 1600.00 200.00 2.00

Granite stone 105.00 78.75 115.00 9056.25 90.56

color cement for joints 2.00 1.50 12.00 18.00 0.18

mat. Cost 9619.25

labor cost 100.00 rft 16.33 1633.33 16.33

11252.58

5% ohd/.supervision+ water + el.power 5.00 562.63 5.63

10% profit on cement supply by owner 10.00 345.00 34.50 0.35

15% profit on other material 15.00 9274.25 1391.14 13.91

profit on labor part 15.00 1633.33 245.00 2.45

total cost 13485.85

134.86

103 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 9" to 12" wide)

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

Granite stone 105.00 105.00 115.00 12075.00 120.75

color cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 12825.67

labor cost 100.00 rft 16.33 1633.33 16.33

14459.00

5% ohd/.supervision+ water + el.power 5.00 722.95 7.23

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 12365.67 1854.85 18.55

profit on labor part 15.00 1633.33 245.00 2.45

total cost 17327.80

173.28

104 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 12" to 15" wide)

100.00 1.250 125.00

cement 2.00 2.50 230.00 575.00 5.75

sand 0.17 0.208 1600.00 333.33 3.33

Granite stone 105.00 131.25 115.00 15093.75 150.94

color cement for joints 2.00 2.50 12.00 30.00 0.30

mat. Cost 16032.08

labor cost 100.00 rft 16.33 1633.33 16.33

17665.42

5% ohd/.supervision+ water + el.power 5.00 883.27 8.83

10% profit on cement supply by owner 10.00 575.00 57.50 0.58

15% profit on other material 15.00 15457.08 2318.56 23.19

profit on labor part 15.00 1633.33 245.00 2.45

total cost 21169.75

211.70

Page 53: Rate Analysis

Page 53SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

105 COLOR GRANITE (SOUTH) STONE FLOORING

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

Granite stone 105.00 105.00 125.00 13125.00 131.25

color cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 13875.67

labor cost 100.00 rft 16.33 1633.33 16.33

15509.00

5% ohd/.supervision+ water + el.power 5.00 775.45 7.75

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 13415.67 2012.35 20.12

profit on labor part 15.00 1633.33 245.00 2.45

total cost 18587.80

185.88

106 COLOR GRANITE for skirting cutting & jari finishing( up to 2" wide)

100.00 0.250 25.00

cement 2.00 0.50 230.00 115.00 1.15

sand 0.17 0.042 1600.00 66.67 0.67

Granite stone 105.00 26.25 125.00 3281.25 32.81

color cement for joints 2.00 0.50 12.00 6.00 0.06

mat. Cost 3468.92

labor cost 100.00 rft 16.33 1633.33 16.33

5102.25

5% ohd/.supervision+ water + el.power 5.00 255.11 2.55

10% profit on cement supply by owner 10.00 115.00 11.50 0.12

15% profit on other material 15.00 3353.92 503.09 5.03

profit on labor part 15.00 1633.33 245.00 2.45

total cost 6116.95

61.17

107 COLOR GRANITE for skirting cutting & jari finishing( up to 3" to 6" wide)

100.00 0.500 50.00

cement 2.00 1.00 230.00 230.00 2.30

sand 0.17 0.083 1600.00 133.33 1.33

Granite stone 105.00 52.50 125.00 6562.50 65.63

color cement for joints 2.00 1.00 12.00 12.00 0.12

mat. Cost 6937.83

labor cost 100.00 rft 16.33 1633.33 16.33

8571.17

5% ohd/.supervision+ water + el.power 5.00 428.56 4.29

10% profit on cement supply by owner 10.00 230.00 23.00 0.23

15% profit on other material 15.00 6707.83 1006.18 10.06

profit on labor part 15.00 1633.33 245.00 2.45

total cost 10273.90

102.74

Page 54: Rate Analysis

Page 54SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

108 COLOR GRANITE for skirting cutting & jari finishing( up to 6" to 9" wide)

100.00 0.750 75.00

cement 2.00 1.50 230.00 345.00 3.45

sand 0.17 0.125 1600.00 200.00 2.00

Granite stone 105.00 78.75 125.00 9843.75 98.44

color cement for joints 2.00 1.50 12.00 18.00 0.18

mat. Cost 10406.75

labor cost 100.00 rft 16.33 1633.33 16.33

12040.08

5% ohd/.supervision+ water + el.power 5.00 602.00 6.02

10% profit on cement supply by owner 10.00 345.00 34.50 0.35

15% profit on other material 15.00 10061.75 1509.26 15.09

profit on labor part 15.00 1633.33 245.00 2.45

total cost 14430.85

144.31

109 COLOR GRANITE for skirting cutting & jari finishing( up to 9" to 12" wide)

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.17 0.167 1600.00 266.67 2.67

Granite stone 105.00 105.00 125.00 13125.00 131.25

color cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 13875.67

labor cost 100.00 rft 16.33 1633.33 16.33

15509.00

5% ohd/.supervision+ water + el.power 5.00 775.45 7.75

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 13415.67 2012.35 20.12

profit on labor part 15.00 1633.33 245.00 2.45

total cost 18587.80

185.88

110 COLOR GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 12" to 15" wide)

100.00 1.250 125.00

cement 2.00 2.50 230.00 575.00 5.75

sand 0.17 0.208 1600.00 333.33 3.33

Granite stone 105.00 131.25 125.00 16406.25 164.06

color cement for joints 2.00 2.50 12.00 30.00 0.30

mat. Cost 17344.58

labor cost 100.00 rft 16.33 1633.33 16.33

18977.92

5% ohd/.supervision+ water + el.power 5.00 948.90 9.49

10% profit on cement supply by owner 10.00 575.00 57.50 0.58

15% profit on other material 15.00 16769.58 2515.44 25.15

profit on labor part 15.00 1633.33 245.00 2.45

total cost 22744.75

227.45

Page 55: Rate Analysis

Page 55SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

111 Glaze tile (6" x 8") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 6" x 8" with wastage 105.00 10.50 120.00 1260.00 12.60

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 1944.00

labor cost 100.00 sft 8.17 816.67 8.17

2760.67

5% ohd/.supervision+ water + el.power 5.00 138.03 1.38

10% profit on cement & tiles supply by owner 10.00 1720.00 172.00 1.72

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 3226.80

32.27

112 Glaze tile (8" x 8") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 8" x 8" with wastage 105.00 10.50 160.00 1680.00 16.80

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 2364.00

labor cost 100.00 sft 8.17 816.67 8.17

3180.67

5% ohd/.supervision+ water + el.power 5.00 159.03 1.59

10% profit on cement & tiles supply by owner 10.00 2140.00 214.00 2.14

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 3709.80

37.10

113 Glaze tile (8" x 12") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 8" x 12" with wastage 105.00 10.50 110.00 1155.00 11.55

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 1839.00

labor cost 100.00 sft 8.17 816.67 8.17

2655.67

5% ohd/.supervision+ water + el.power 5.00 132.78 1.33

10% profit on cement & tiles supply by owner 10.00 1615.00 161.50 1.62

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 3106.05

31.06

Page 56: Rate Analysis

Page 56SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

114 Glaze tile (12" x 12") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 12" x 12" with wastage 105.00 10.50 165.00 1732.50 17.33

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 2416.50

labor cost 100.00 sft 8.17 816.67 8.17

3233.17

5% ohd/.supervision+ water + el.power 5.00 161.66 1.62

10% profit on cement & tiles supply by owner 10.00 2192.50 219.25 2.19

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 3770.18

37.70

115 Glaze tile (12" x 18") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 12" x 18" with wastage 105.00 10.50 230.00 2415.00 24.15

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 3099.00

labor cost 100.00 sft 8.17 816.67 8.17

3915.67

5% ohd/.supervision+ water + el.power 5.00 195.78 1.96

10% profit on cement & tiles supply by owner 10.00 2875.00 287.50 2.88

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 4555.05

45.55

116 Glaze tile (12" x 24") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 12" x 24" with wastage 105.00 10.50 330.00 3465.00 34.65

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 4149.00

labor cost 100.00 sft 8.17 816.67 8.17

4965.67

5% ohd/.supervision+ water + el.power 5.00 248.28 2.48

10% profit on cement & tiles supply by owner 10.00 3925.00 392.50 3.93

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 5762.55

57.63

Page 57: Rate Analysis

Page 57SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

117 Glaze tile (13" x 10") dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 12" x 24" with wastage 105.00 10.50 230.00 2415.00 24.15

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 3099.00

labor cost 100.00 sft 8.17 816.67 8.17

3915.67

5% ohd/.supervision+ water + el.power 5.00 195.78 1.96

10% profit on cement & tiles supply by owner 10.00 2875.00 287.50 2.88

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 4555.05

45.55

118 RUSTIK TILES ( 12 X 12 )Nitco ceramic dodo / flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.13 0.125 1600.00 200.00 2.00

tiles 12" x 24" with wastage 105.00 105.00 25.50 2677.50 26.78

white cement for joints 2.00 2.00 12.00 24.00 0.24

mat. Cost 3361.50

labor cost 100.00 sft 8.17 816.67 8.17

4178.17

5% ohd/.supervision+ water + el.power 5.00 208.91 2.09

10% profit on cement & tiles supply by owner 10.00 3137.50 313.75 3.14

15% profit on other material 15.00 224.00 33.60 0.34

profit on labor part 15.00 816.67 122.50 1.23

total cost 4856.93

48.57

119 Waterproofing with brick mortar(on terrace)

100.00 1.000 100.00

cement 4.00 4.00 230.00 920.00 9.20

sand 0.27 0.274 1600.00 438.56 4.39

brick bats 1024.00 1024.00 0.65 665.60 6.66

mat. Cost 2024.16

labor cost 100.00 sft 10.50 1050.00 10.50

3074.16

5% ohd/.supervision+ water + el.power 5.00 153.71 1.54

10% profit on cement supply by owner 10.00 920.00 92.00 0.92

15% profit on other material 15.00 1104.16 165.62 1.66

profit on labor part 15.00 1050.00 157.50 1.58

total cost 3642.99

36.43

Page 58: Rate Analysis

Page 58SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

120 Waterproofing with brick- mortar(in bathroom sunk with base plaster)

100.00 1.000 100.00

cement 4.00 4.00 230.00 920.00 9.20

sand 0.27 0.274 1600.00 438.56 4.39

brick bats 1024.00 1024.00 0.65 665.60 6.66

mat. Cost 2024.16

labor cost 100.00 sft 15.17 1516.67 15.17

3540.83

5% ohd/.supervision+ water + el.power 5.00 177.04 1.77

10% profit on cement supply by owner 10.00 920.00 92.00 0.92

15% profit on other material 15.00 1104.16 165.62 1.66

profit on labor part 15.00 1516.67 227.50 2.28

total cost 4202.99

42.03

121 Waterproofing vatta/kani vatta

1 feet wide 100.00 1.000 100.00

cement 4.00 4.00 230.00 920.00 9.20

sand 0.27 0.274 1600.00 438.56 4.39

brick bats 1024.00 1024.00 0.65 665.60 6.66

mat. Cost 2024.16

labor cost 100.00 rft 10.50 1050.00 10.50

3074.16

5% ohd/.supervision+ water + el.power 5.00 153.71 1.54

10% profit on cement supply by owner 10.00 920.00 92.00 0.92

15% profit on other material 15.00 1104.16 165.62 1.66

profit on labor part 15.00 1050.00 157.50 1.58

total cost 3642.99

36.43

122 Horizontal patta on sloping slab.

100.00 0.500 50.00

cement 3.00 0.50 230.00 345.00 3.45

sand 0.09 0.500 1600.00 72.00 0.72

mat. Cost 417.00

labor cost 100.00 rft 6.00 600.00 6.00

1017.00

5% ohd/.supervision+ water + el.power 5.00 50.85 0.51

10% profit on cement supply by owner 10.00 345.00 34.50 0.35

15% profit on other material 15.00 72.00 10.80 0.11

profit on labor part 15.00 600.00 90.00 0.90

total cost 1203.15

12.03

123 china mosaic flooring

100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.40 0.400 1600.00 640.00 6.40

glaze tiles pieces sq.ft 0.80 0.80 10.00 8.00 0.08

white cement 30.00 30.00 12.00 360.00 3.60

mat. Cost 1468.00

labor cost 100.00 sft 14.00 1400.00 14.00

2868.00

5% ohd/.supervision+ water + el.power 5.00 143.40 1.43

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

Page 59: Rate Analysis

Page 59SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

15% profit on other material 15.00 1008.00 151.20 1.51

profit on labor part 15.00 1400.00 210.00 2.10

total cost 3418.60

34.19

Page 60: Rate Analysis

Page 60SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

124 china mosaic vatta

1 FEET WIDE 100.00 1.000 100.00

cement 2.00 2.00 230.00 460.00 4.60

sand 0.40 0.400 1600.00 640.00 6.40

glaze tiles pieces sq.ft 0.70 0.70 10.00 7.00 0.07

white cement 30.00 30.00 12.00 360.00 3.60

mat. Cost 1467.00

labor cost 100.00 rft 14.00 1400.00 14.00

2867.00

5% ohd/.supervision+ water + el.power 5.00 143.35 1.43

10% profit on cement supply by owner 10.00 460.00 46.00 0.46

15% profit on other material 15.00 1007.00 151.05 1.51

profit on labor part 15.00 1400.00 210.00 2.10

total cost 3417.40

34.17

125 BBCC 1:4:8 in sunk

total concrete 100.00 1.00 100.00

cement 8.11 8.11 230.00 1865.30 18.65

sand 0.61 0.61 1600.00 976.00 9.76

RODA 0.81 0.81 1500.00 1215.00 12.15

mat. Cost 4056.30

labor cost 100.00 9.33 933.33 9.33

4989.63

5% ohd/.supervision+ water + el.power 5.00 249.48 2.49

10% profit on cement supply by owner 10.00 1865.30 186.53 1.87

15% profit on other material 15.00 2191.00 328.65 3.29

profit on labor part 15.00 933.33 140.00 1.40

total cost 5894.30

58.94

126 Rough kota flooring.

100.00 1.000 100.00

cement 1.50 1.50 230.00 345.00 3.45

sand 0.15 0.150 1600.00 240.00 2.40

r kota 100.00 100.00 15.00 1500.00 15.00

mat. Cost 2085.00

labor cost 100.00 sft 6.00 600.00 6.00

2685.00

5% ohd/.supervision+ water + el.power 5.00 134.25 1.34

10% profit on cement supply by owner 10.00 345.00 34.50 0.35

15% profit on other material 15.00 1740.00 261.00 2.61

profit on labor part 15.00 600.00 90.00 0.90

total cost 3204.75

32.05

Page 61: Rate Analysis

Page 61SR PARTICULAR QTY QTY RATE AMOUNT UNIT RATE

127 Chiken mesh with elec zari filling.

6" wide 100.00 0.500 50.00

cement 1.50 0.50 230.00 172.50 1.73

sand 0.15 0.500 1600.00 120.00 1.20

Chiken mesh 100.00 1.000 1.00 100.00 1.00

mat. Cost 392.50

labor cost 100.00 sft 2.00 200.00 2.00

592.50

5% ohd/.supervision+ water + el.power 5.00 29.63 0.30

10% profit on cement supply by owner 10.00 172.50 17.25 0.17

15% profit on other material 15.00 220.00 33.00 0.33

profit on labor part 15.00 200.00 30.00 0.30

total cost 702.38

7.02

128 Filling yellow soil brought from stack yard.

Supplied free of cost

yellow soil (excn,transport,load,unload) by machin 1.00 150.00 150.00 1.50

shrinkage 35 % 0.35 52.50 0.53

mat. Cost 202.50

labor cost 100.00 2.00 200 2.00

402.50

5% ohd/.supervision 5.00 20.13 0.20

profit on material transport 15.00 202.50 30.38 0.30

profit on labour part 15.00 200.00 30.00 0.30

total cost 483.00

4.83

Page 62: Rate Analysis

Page 62

TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

1/2" -3/4" THICK

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

Page 63: Rate Analysis

Page 63INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

INC.TAX

Page 64: Rate Analysis

Page 64

UNIT

cft

cft

Page 65: Rate Analysis

Page 65UNIT

cft

cft

Page 66: Rate Analysis

Page 66UNIT

cft

sq.ft

sq.ft

Page 67: Rate Analysis

Page 67UNIT

sq.ft

Page 68: Rate Analysis

Page 68UNIT

sq.ft

sq.ft

sq.ft

Page 69: Rate Analysis

Page 69UNIT

sq.ft

Page 70: Rate Analysis

Page 70UNIT

rft

cft

rft

Page 71: Rate Analysis

Page 71UNIT

rft

Page 72: Rate Analysis

Page 72UNIT

rft

rft

rft

Page 73: Rate Analysis

Page 73UNIT

cft

Page 74: Rate Analysis

Page 74UNIT

sft

sft

sft

Page 75: Rate Analysis

Page 75UNIT

sft

Page 76: Rate Analysis

Page 76UNIT

sft

sft

rft

Page 77: Rate Analysis

Page 77UNIT

rft

Page 78: Rate Analysis

Page 78UNIT

rft

rft

rft

Page 79: Rate Analysis

Page 79UNIT

rft

Page 80: Rate Analysis

Page 80UNIT

rft

rft

sft

Page 81: Rate Analysis

Page 81UNIT

sq.ft

Page 82: Rate Analysis

Page 82UNIT

sq.ft

rft

sft

Page 83: Rate Analysis

Page 83UNIT

sft

sft

sft

Page 84: Rate Analysis

Page 84UNIT

sft

Page 85: Rate Analysis

Page 85UNIT

rft

cft

rft

Page 86: Rate Analysis

Page 86UNIT

rft

rft

rft

Page 87: Rate Analysis

Page 87UNIT

rft

Page 88: Rate Analysis

Page 88UNIT

sft

rft

sft

Page 89: Rate Analysis

Page 89UNIT

sft

Page 90: Rate Analysis

Page 90UNIT

sft

sft

sft

Page 91: Rate Analysis

Page 91UNIT

rft

sft

rft

Page 92: Rate Analysis

Page 92UNIT

rft

Page 93: Rate Analysis

Page 93UNIT

rft

rft

rft

Page 94: Rate Analysis

Page 94UNIT

kg

sft

cft

Page 95: Rate Analysis

Page 95UNIT

cft

Page 96: Rate Analysis

Page 96UNIT

sft

sft

sft

Page 97: Rate Analysis

Page 97UNIT

sft

Page 98: Rate Analysis

Page 98UNIT

sft

sft

sft

Page 99: Rate Analysis

Page 99UNIT

rft

rft

rft

Page 100: Rate Analysis

Page 100UNIT

rft

Page 101: Rate Analysis

Page 101UNIT

rft

rft

rft

Page 102: Rate Analysis

Page 102UNIT

rft

rft

sft

Page 103: Rate Analysis

Page 103UNIT

rft

sft

sft

Page 104: Rate Analysis

Page 104UNIT

sft

sft

sft

Page 105: Rate Analysis

Page 105UNIT

sft

Page 106: Rate Analysis

Page 106UNIT

sft

sft

rft

Page 107: Rate Analysis

Page 107UNIT

rft

rft

rft

Page 108: Rate Analysis

Page 108UNIT

sft

rft

rft

Page 109: Rate Analysis

Page 109UNIT

rft

rft

rft

Page 110: Rate Analysis

Page 110UNIT

rft

rft

rft

Page 111: Rate Analysis

Page 111UNIT

rft

rft

rft

Page 112: Rate Analysis

Page 112UNIT

sft

sft

sft

Page 113: Rate Analysis

Page 113UNIT

sft

sft

sft

Page 114: Rate Analysis

Page 114UNIT

sft

sft

sft

Page 115: Rate Analysis

Page 115UNIT

sft

rft

rft

Page 116: Rate Analysis

Page 116UNIT

sft

Page 117: Rate Analysis

Page 117UNIT

rft

cft

sft

Page 118: Rate Analysis

Page 118UNIT

rft

cft

Page 119: Rate Analysis

157

SCHEDULE-AABSTRACT OF ITEM RATES (with cement )

SR. ITEMS RATE UNITS

CONSIDERING 10% PROFIT ON MATERIAL SUPPLIED BY OWENER

1 Pro.& filling black sand brought from outside. 25.44 cft

2 Pro.& filling yellow soil brought from outside. 10.50 cft

3 Pro.& filling quarry spoil brought from outside. 15.36 cft

4 Rubble soaling 9" thk. 18.00 cft

5 Rubble soaling thk. Above 9" 20.40 cft

6 2" THK PCC (1:4:8) 12.35 sq.ft

7 3" THK PCC (1:4:8) 17.93 sq.ft

8 3" THK PCC (1:3:6) 19.93 sq.ft

9 4" THK PCC (1:4:8) 22.30 sq.ft

10 4" THK PCC (1:3:6) 24.98 sq.ft

11 6" THK PCC (1:4:8) 32.26 sq.ft

12 6" THK PCC (1:3:6) 36.26 sq.ft

13 9" AUGER (M-20) 59.60 rft

14 FOUNDATION (M-20) 110.06 cft

15 6"x 9" BEAM ( M-20) 81.27 rft

16 6"x 12" BEAM / ( M-20) 92.03 rft

17 9"x 9" BEAM / COLUMN ( M-20) 97.41 rft

18 9"x 12" BEAM / COLIMN ( M-20) 113.54 rft

19 9"x 15" BEAM / COLIMN ( M-20) 129.68 rft

20 COLUMN /BEAM S/C >=1CFT (M-20) 135.06 cft

21 4.5" thick SLAB (M-20) 54.67 sft

22 5" THICK SLAB ( M-20 ) 59.66 sft

23 6" THICK SLAB ( M-20 ) 68.23 sft

24 4.5" THICK SLOPING SLAB ( M-20 ) 65.87 sft

25 5" THICK SLOPING SLAB ( M-20 ) 69.46 sft

26 6" THICK SLAB ( M-25 ) 74.95 sft

27 9"x 4" LINTEL / COPING ( M-20) 43.91 rft

28 9"x 6" LINTEL / COPING ( M-20) 54.67 rft

29 9"x 7" LINTEL / COPING / RUNNER BEAM ( M-20) 60.05 rft

30 6"x 6" LINTEL / COPING ( M-20) 43.91 rft

31 6"x 4" Chajja STRIPS ( M-20) 42.20 rft

32 6"x 7" Chajja STRIPS ( M-20) 52.96 rft

33 4.5"x 4" LINTEL / COPING ( M-20) 30.36 rft

34 4.5"x 6" LINTEL / COPING ( M-20) 35.74 rft

35 4" THICK CHHAJA / LOFT (M-20) 56.69 sft

36 5" THICK CHHAJA / LOFT (M-20) 63.86 sq.ft

37 7" THICK CHHAJA / LOFT (M-20) 77.91 sq.ft

38 STAIR STEPS WITH WAIST SLAB (M-20) 193.79 rft

39 4" THICK FLOOR SLAB (M-15) with steel 30.71 sft

40 6" THICK FLOOR SLAB (M-15) with steel 42.47 sft

41 9" THICK BRICK MASONARY ( 1 :6 ) 56.76 sft

42 4.5" THICK BRICK MASONARY ( 1 :4 ) 29.64 sft

43 14" THICK BRICK MASONARY ( 1 :6 ) 89.94 sft

44 4.5" brick mas. Cornice 26.30 rft

45 MASS MASONARY (1:6) 76.85 cft

Page 120: Rate Analysis

157

SR. ITEMS RATE UNITS

46 9"x 9" PILLAR 52.85 rft

47 9"x 12" PILLAR 69.94 rft

48 9"x 15" PILLAR 81.47 rft

49 9"x 18" PILLAR 93.23 rft

50 9"x 24" PILLAR 109.91 rft

51 SMALL PADESTALS/WALLS. 56.76 sft

52 12"x 12" PILLAR 86.10 rft

53 INTERNAL MALA PLASTER 12.67 sft

54 EXTRA OVER MALA PLASTER FOR NEERU PLASTER 1.72 sft

55 EXTERNAL SINGLE COAT SANDFACE PLASTER 14.48 sft

56 EXTERNAL DOUBLE COAT SANDFACE PLASTER 21.89 sft

57 EXTERNAL DOUBLE COAT OF GUTKA /MALA/ROLLER PLASTER 26.67 sft

58 PATTA/TAPAK IN GUTKA /MALA PLASTER 13.54 rft

59 STONECRETE /MALAD PLASTER 45.35 sft

60 PATTA IN STONECRETE /MALAD PLASTER 20.07 rft

61 vata plaster work (1:4) 12.30 rft

62 tapak plaster work (1:4) 10.45 rft

63 Patta plaster work (1:4) 10.82 rft

64 Stonecrete tapak plaster work (1:4) 12.59 rft

65 REINFORCEMENT 35.10 kg

66 Ips floor finish 2" thick 22.88 sft

67 U.C.R masonary in c.m 1:6 without pointing. 47.75 cft

68 Plum concrete 45.38 cft

69 Flush pointing on rubble masonary 6.24 sft

70 Exposed pointing on rubble masonary 12.97 sft

71 Mala plaster on rubble masonary (1:4) 16.73 sft

72 KOTA Flooring with ordinary Polish & cutting(22 x 16,18 x 18, 24 x 24) 52.33 sft

73 KOTA slab Flooring with ordinary Polish & cutting 60.32 sft

74 GreenMarble Flooring 78.38 sft

75 White Marble slab (rajnagar) Flooring 71.78 sft

76 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 2.75" width) 21.28 rft

77 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" to 5.75" widt 30.01 rft

78 P.KOTA for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 6" to 11.75" wid 53.39 rft

79 P.KOTA for sill / james / tappa / riser / shelves with cutting & jari finishing ( up to 12" to 17.75" width) 80.09 rft

80 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" width) 30.02 rft

81 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 3" to 6" width) 43.24 rft

82 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing ( up to 6" to 9" width) 54.88 rft

83 P.Marble for sill / james / skirting / tappa / riser / shelves with cutting & jari finishing( up to 9" to 12" width 67.58 rft

84 P.Marble for tappa / riser / shelves with cutting & jari finishing ( up to 12" to 18" width) 101.37 rft

85 Parsolina Ceramic tiles Flooring 49.37 sft

86 Parsolina Ceramic tiles skirting (3" width) 19.69 rft

87 Granamite(Vitrified) tiles Flooring 24" x 24" 59.32 sft

88 Granamite(Vitrified) tiles Flooring 32" x 32" 71.39 sft

89 Granamite(Vitrified) tiles Flooring 36" x 36" 99.17 sft

90 Granamite(Vitrified) tiles Flooring 39" x 39" 105.20 sft

91 Granamite(Vitrified) tiles Dado 24" x 24" 59.46 sft

92 Granamite(Vitrified) tiles Dado 32" x 32" 71.54 sft

93 Granamite(Vitrified) tiles Dado 36" x 36" 99.31 sft

94 Granamite(Vitrified) tiles Dado 39" x 39" 105.35 sft

95 Granamite(Vitrified) tiles Skirting 24" x 24" (2" width) 19.80 rft

Page 121: Rate Analysis

157

SR. ITEMS RATE UNITS

96 Granamite(Vitrified) tiles Skirting 32" x 32" (2" width) 21.82 rft

97 Granamite(Vitrified) tiles Skirting 36" x 36" (2" width) 26.44 rft

98 Granamite(Vitrified) tiles Skirting 39" x 39" (2" width) 27.45 rft

99 Black Granite (south) stone Flooring 173.28 sft

100 GRANITE for sill / james / skirting cutting & jari finishing (up to 3" wide) 58.02 rft

101 GRANITE for sill / james / skirting / riser cutting & jari finishing (up to 3" to 6" wide) 96.44 rft

102 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 6" to 9" wide) 134.86 rft

103 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 9" to 12" wide) 173.28 rft

104 GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 12" to 15" wide) 211.70 rft

105 COLOR GRANITE (SOUTH) STONE FLOORING 185.88 rft

106 COLOR GRANITE for skirting cutting & jari finishing( up to 2" wide) 61.17 rft

107 COLOR GRANITE for skirting cutting & jari finishing( up to 3" to 6" wide) 102.74 rft

108 COLOR GRANITE for skirting cutting & jari finishing( up to 6" to 9" wide) 144.31 rft

109 COLOR GRANITE for skirting cutting & jari finishing( up to 9" to 12" wide) 185.88 rft

110 COLOR GRANITE for sill / james / skirting /tappa/ riser cutting & jari finishing (up to 12" to 15" wide) 227.45 rft

111 Glaze tile (6" x 8") dodo / flooring 32.27 sft

112 Glaze tile (8" x 8") dodo / flooring 37.10 sft

113 Glaze tile (8" x 12") dodo / flooring 31.06 sft

114 Glaze tile (12" x 12") dodo / flooring 37.70 sft

115 Glaze tile (12" x 18") dodo / flooring 45.55 sft

116 Glaze tile (12" x 24") dodo / flooring 57.63 sft

117 Glaze tile (13" x 10") dodo / flooring 45.55 sft

118 RUSTIK TILES ( 12 X 12 )Nitco ceramic dodo / flooring 48.57 sft

119 Waterproofing with brick mortar(on terrace) 36.43 sft

120 Waterproofing with brick- mortar(in bathroom sunk with base plaster) 42.03 sft

121 Waterproofing vatta/kani vatta 36.43 rft

122 Horizontal patta on sloping slab. 12.03 rft

123 china mosaic flooring 34.19 sft

124 china mosaic vatta 34.17 rft

125 BBCC 1:4:8 in sunk 58.94 cft

126 Rough kota flooring. 32.05 sft

127 Chiken mesh with elec zari filling. 7.02 rft

128 Filling yellow soil brought from stack yard. 4.83 cft

129 Extra for bulb (auger) 92.77 NO

130 6" RCC WALL/ PARDI 72.43 sq.ft

131 9" RCC WALL/ PARDI 98.14 sq.ft

132-a WATER PROOFING- PLASTER (1:4) (with WP chemical)- 19MM THICK 19.00 sft

132-b SUNK - TOP FINISHING PLASTER layer (1:4) 9.27 sft

133 Water proofing chmical (Altret-ab-43) coating 2.27 sft

134 Waterproofing with KAPCHI - mortar(On rccwall,water tank with base plaster) 23.00 sft

Page 122: Rate Analysis

BASIC MATERIAL RATE CONSIDERED33 SAL WOOD 651.0034 TEAK WOOD (GHANA) 1200.0035 4MM PLAIN GLASS 24.0036 FLUSH DOOR MR GRADE 40.0037 FLUSH DOOR PF GRADE 50.0038 LAMINATE 0.8 MM THICK 10.0039 LAMINATE 1MM THICK 20.0040 VINEER LAMINATE 40.0041 WOODEN MOULDING 2 X 1/2 12.0042 MAIN DOOR LATCH LOCK 650.0043 MORTICE LOCK WITH KEY 350.0044 MORTICE LOCK WITHOUT KEY 350.0045 3" CP BRASS STOPPER 22.0046 4" CP BRASS STOPPER 25.0047 6" CP BRASS STOPPER 35.0048 4" CP BRASS HANDLE 18.0049 6" CP BRASS HANDLE 26.0050 10" CP BRASS HANDLE 175.0051 8" S.S WIN.HOOK 14.0052 3" S.S HINGES 9.5053 4" S.S HINGES 17.0054 5" S.S HINGES 26.0055 DOOR STOPPER CP BRASS 130.0056 DOOR EYE S.S. 80.0057 DOOR HOLDER MAGNET PVC 50.0058 6MM PLAIN GLASS 48.0059 HOLD FAST 5.0060 SCREWS(35X8 NATTLEFOLD) 0.5061 SCREWS(20X6 NATTLEFOLD) 0.3562 NAILS ETC 50.0063 FEVICOL 130.0064 10" ALLDROP CP 130.0065 4 MM FROSTED GLASS 50.00

LABOUR RATES

Flush door with frame-beading patti- laminate- hardware-fixing comp. 30.00

Window shutter with frame-glass- hardware-fixing comp. 35.00

Architave patti making & fixing 5.00

D/W frame erection labor 5.00Tar painting with material labor 3.00Oil paint with material 5.25French police with material 6.00

SCHEDULE : EDOOR & WINDOW RATE ANALYSIS

SR PARTICULARS NO L B

1 DOOR GD3 (7'6" X 2' 8") 7.50 2.67

Page 123: Rate Analysis

A WOOD ITEMSa Sal wood ft inch

fram 2 7.75 5.001 3.00 5.00

cross support patty 2 1.00 1.001 3.00 1.00

b Ghana teak woodTW beading to flush door 2.00 7.50 1.50

2.00 2.75 1.50

B FLUSH DOOR (MR grade) 1 7.25 2.50

C GLASS

D LAMINATEa lamination BACK SIDE WHITE 0.8 mm 1.10 7.25 2.25

b lamination FRONT SIDE 1.0 mm 1.10 7.25 2.25

D HARDWAREholdfasts

hinges 5" sonalock KEYLESS

4" cp brass stopper6" handle

pvc door stops.s door eye

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 2.67

Erection of frame 1 7.50 2.67

F COLOR WORKTar paint on fram backside 1 18.49

Oil paint frame 1 17.67Polishing to beading patti 1 19.33

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

2 DOOR GD2 (7'6" X 3' 2") 7.50 3.17

A WOOD ITEMSa Sal wood ft inch

Page 124: Rate Analysis

fram 2 7.75 5.001 3.75 5.00

cross support patty 2 1.00 1.001 3.25 1.00

b Ghana teak woodTW beading to flush door 2.00 7.50 1.50

2.00 3.00 1.50

B FLUSH DOOR (MR grade) 1 7.25 2.75

C GLASS

D LAMINATEa lamination BACK SIDE WHITE 0.8 mm 1.10 7.25 2.75

b lamination FRONT SIDE 1.0 mm 1.10 7.25 2.75

D HARDWAREholdfasts

hinges 5" sonalock with KEY

4" cp brass stopper6" handle

pvc door stops.s door eye

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 3.17

Erection of frame 1 7.50 3.17

F COLOR WORKTar paint on fram backside 1 18.98

Oil paint frame 1 18.16Polishing to beading patti 1 20.33

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

3 DOOR GD1 (7'6" X 3' 10") 7.50 3.83

A WOOD ITEMSa Sal wood ft inch

fram 2 7.75 6.00

Page 125: Rate Analysis

1 4.25 6.00cross support patty 2 1.00 1.00

1 3.83 1.00

b Ghana teak woodTW beading to flush door 2.00 7.50 1.50

2.00 3.75 1.50

B FLUSH DOOR (MR grade) 1 7.25 3.50

C GLASS

D LAMINATEa 0.00 0.00 0.00

b lamination both side 1.0 mm 2.00 8.00 4.00

D HARDWAREholdfasts

hinges 5" sonaMain door lock with lach KEY

4" cp brass stopper10" handle

pvc door stops.s door eye

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 3.83

Erection of frame 1 7.50 3.83

F COLOR WORKTar paint on fram backside 1 19.90

Oil paint frame 1 18.83Polishing to beading patti 1 21.67

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

4 DOOR GD4 (7'6" X 5' 8") 7.50 5.67

A WOOD ITEMSa Sal wood ft inch

fram 2 7.75 5.001 6.00 5.00

Page 126: Rate Analysis

cross support patty 2 1.00 1.001 6.00 1.00

b Ghana teak woodstyles 4 7.50 4.00

t/b/l rail 6 2.75 6.00Glass beading patti 8 3.00 0.75

8 2.25 0.75

B FLUSH DOOR (MR grade) 0 0.00 0.00

C GLASS6 mm thick plain glass 4 3.00 2.25

D LAMINATEa lamination BACK SIDE WHITE 0.8 mm 0.00 0.00 0.00

b lamination FRONT SIDE 1.0 mm 0.00 0.00 0.00

D HARDWAREholdfasts

hinges 5" sona10" CP brass aldrop6" cp brass stopper

6" handlepvc door stop

s.s door eyescrews(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 5.67

Erection of frame 1 7.50 5.67

F COLOR WORKTar paint on fram backside 1 21.74

Oil paint frame WITH SHUTTER 2 7.50 5.67Polishing to beading patti 0 0.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

5 DOOR FD3 (7'6" X 7' 8") 7.50 7.67

A WOOD ITEMSa Sal wood ft inch

Page 127: Rate Analysis

fram 2 7.75 5.001 8.25 5.00

cross support patty 2 1.00 1.002 7.75 1.00

b Ghana teak woodstyles 8 7.50 4.00

t/b/l rail 12 2.00 6.00Glass beading patti 16 3.00 0.75

16 1.25 0.75

B FLUSH DOOR (MR grade) 0 0.00 0.00

C GLASS6 mm thick plain glass 6 3.00 1.25

D LAMINATEa lamination BACK SIDE WHITE 0.8 mm 0.00 0.00 0.00

b lamination FRONT SIDE 1.0 mm 0.00 0.00 0.00

D HARDWAREholdfasts

hinges 5" sona10" CP brass aldrop6" cp brass stopper

6" handlepvc door stop

s.s door eyescrews(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 7.67

Erection of frame 1 7.50 7.67

F COLOR WORKTar paint on fram backside 1 23.73

Oil paint frame WITH SHUTTER 2 7.50 7.67Polishing to beading patti 0 0.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

6 DOOR GD5 (7'6" X 4' 2") 7.50 4.17

Page 128: Rate Analysis

A WOOD ITEMSa Sal wood ft inch

fram 2 7.75 5.001 4.50 5.00

cross support patty 2 1.00 1.001 4.50 1.00

b Ghana teak woodstyles 4 7.50 4.00

t/b/l rail 6 2.00 6.00Glass beading patti 8 3.00 0.75

8 1.25 0.75

B FLUSH DOOR (MR grade) 0 0.00 0.00

C GLASS6 mm thick plain glass 4 3.00 1.25

D LAMINATEa lamination BACK SIDE WHITE 0.8 mm 0.00 0.00 0.00

b lamination FRONT SIDE 1.0 mm 0.00 0.00 0.00

D HARDWAREholdfasts

hinges 5" sona10" CP brass aldrop6" cp brass stopper

6" handlepvc door stop

s.s door eyescrews(35x8 nattlefold)screws(20x6 nattlefold)

nails etcfevicol

E LABOURMaking of frame with shutter complete 1 7.50 4.17

Erection of frame 1 7.50 4.17

F COLOR WORKTar paint on fram backside 1 20.24

Oil paint frame WITH SHUTTER 2 7.50 4.17Polishing to beading patti 0 0.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

Page 129: Rate Analysis

7 WINDOW FW3 (1'8" X 4' 0") 1.67 4.00

A WOOD ITEMSa Sal wood ft inch

fram 2 2.00 5.002 4.00 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 3 1.50 3.00VER rail 2 3.75 3.00

Glass beading patti 2 3.00 0.754 1.00 0.75

B GLASS4 mm thick plain glass 1 2.50 1.00

4 mm thick Frosted glass 1 1.00 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 1.67 4.00

Erection of frame 1 1.67 4.00

E COLOR WORKTar paint on fram backside 1 13.33

Oil paint frame WITH SHUTTER 2 1.67 4.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

8 WINDOW GW1 (1'8" X 7' 0") 1.67 7.00

A WOOD ITEMSa Sal wood ft inch

fram 2 2.00 5.00

Page 130: Rate Analysis

2 7.00 5.00cross support patty 4 1.00 1.00

0 0.00 1.00

b Ghana teak woodHZ styles 3 1.50 3.00VER rail 2 6.75 3.00

Glass beading patti 2 5.50 0.754 1.00 0.75

B GLASS4 mm thick plain glass 1 5.50 1.00

4 mm thick Frosted glass 1 1.00 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 1.67 7.00

Erection of frame 1 1.67 7.00

E COLOR WORKTar paint on fram backside 1 19.33

Oil paint frame WITH SHUTTER 2 1.67 7.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

9 WINDOW GW4(2'2" X 5' 0") 2.17 5.00

A WOOD ITEMSa Sal wood ft inch

fram 2 2.50 5.002 5.00 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 3 2.00 3.00

Page 131: Rate Analysis

VER rail 2 4.75 3.00Glass beading patti 2 4.00 0.75

4 1.50 0.75

B GLASS4 mm thick plain glass 1 3.50 1.50

4 mm thick Frosted glass 1 1.50 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 2.17 5.00

Erection of frame 1 2.17 5.00

E COLOR WORKTar paint on fram backside 1 16.33

Oil paint frame WITH SHUTTER 2 2.17 5.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

10 WINDOW FW1 (3'4" X 5' 0") 3.33 5.00

A WOOD ITEMSa Sal wood ft inch

fram 2 3.75 5.002 5.00 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 6 1.75 3.00VER rail 4 4.75 3.00

Glass beading patti 4 4.00 0.756 1.25 0.75

B GLASS

Page 132: Rate Analysis

4 mm thick plain glass 2 3.50 1.254 mm thick Frosted glass 2 1.25 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 3.33 5.00

Erection of frame 1 3.33 5.00

E COLOR WORKTar paint on fram backside 1 18.67

Oil paint frame WITH SHUTTER 2 3.33 5.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

11 WINDOW GW5(4'8" X 5' 0") 4.67 5.00

A WOOD ITEMSa Sal wood ft inch

fram 2 5.00 5.003 5.00 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 6 2.25 3.00VER rail 4 4.75 3.00

Glass beading patti 4 4.00 0.756 1.75 0.75

B GLASS4 mm thick plain glass 2 3.50 1.75

4 mm thick Frosted glass 2 1.75 0.75

C HARDWAREholdfasts

Page 133: Rate Analysis

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 4.67 5.00

Erection of frame 1 4.67 5.00

E COLOR WORKTar paint on fram backside 1 21.33

Oil paint frame WITH SHUTTER 2 4.67 5.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

12 WINDOW GW6(5'5" X 3' 6") 5.42 3.50

A WOOD ITEMSa Sal wood ft inch

fram 2 6.00 5.004 3.50 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 6 1.75 3.00VER rail 4 3.25 3.00

Glass beading patti fix 2 1.75 0.752 3.25 0.75

Glass beading patti shutter glass 4 2.50 0.756 1.25 0.75

B GLASS4 mm thick plain glass 2 2.00 1.25

4 mm thick plain glass fix 1 3.25 1.754 mm thick Frosted glass 2 1.25 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handle

Page 134: Rate Analysis

s.s Window hook screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 5.42 3.50

Erection of frame 1 5.42 3.50

E COLOR WORKTar paint on fram backside 1 19.83

Oil paint frame WITH SHUTTER 2 5.42 3.50

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

13 WINDOW FW4(5'4" X 4' 0") 5.33 4.00

A WOOD ITEMSa Sal wood ft inch

fram 2 5.75 5.004 4.00 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 6 1.75 3.00VER rail 4 3.75 3.00

Glass beading patti fix 2 1.75 0.752 3.75 0.75

Glass beading patti shutter glass 4 3.00 0.756 1.25 0.75

B GLASS4 mm thick plain glass 2 2.50 1.25

4 mm thick plain glass fix 1 3.75 1.754 mm thick Frosted glass 2 1.25 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

Page 135: Rate Analysis

D LABOURMaking of frame with shutter complete 1 5.33 4.00

Erection of frame 1 5.33 4.00

E COLOR WORKTar paint on fram backside 1 20.67

Oil paint frame WITH SHUTTER 2 5.33 4.00

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

14 WINDOW W Landing (1'3.5" X 6' 4.75"") 1.29 6.40

A WOOD ITEMSa Sal wood ft inch

fram 2 1.75 5.002 6.50 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 3 1.00 3.00VER rail 2 6.25 3.00

Glass beading patti 2 5.50 0.754 0.50 0.75

B GLASS4 mm thick plain glass 1 5.00 0.75

4 mm thick Frosted glass 1 0.75 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 1.29 6.40

Erection of frame 1 1.29 6.40

E COLOR WORKTar paint on fram backside 1 17.38

Oil paint frame WITH SHUTTER 2 1.29 6.40

Page 136: Rate Analysis

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

15 WINDOW W st.cabin (1'3.5" X 1' 3.5") 1.29 1.29

A WOOD ITEMSa Sal wood ft inch

fram 2 1.75 5.002 1.50 5.00

cross support patty 4 1.00 1.000 0.00 1.00

b Ghana teak woodHZ styles 2 1.00 3.00VER rail 2 1.00 3.00

Glass beading patti 2 0.75 0.752 0.75 0.75

B GLASS4 mm thick plain glass 1 0.75 0.75

4 mm thick Frosted glass 1 0.00 0.75

C HARDWAREholdfasts

hinges 4" sona4" cp brass stopper

4" handles.s Window hook

screws(35x8 nattlefold)screws(20x6 nattlefold)

nails etc

D LABOURMaking of frame with shutter complete 1 1.29 1.29

Erection of frame 1 1.29 1.29

E COLOR WORKTar paint on fram backside 1 7.17

Oil paint frame WITH SHUTTER 2 1.29 1.29

TOTAL

5% ohd/.supervision+ water + el.power 5.00

15% profit on other material + labour 15.00

total costtotal cost per sq.ft

Page 137: Rate Analysis

1 DOOR GD3 (7'6" X 2' 8") 271.86 sq.ft2 DOOR GD2 (7'6" X 3' 2") 251.26 sq.ft3 DOOR GD1 (7'6" X 3' 10") 294.41 sq.ft4 DOOR GD4 (7'6" X 5' 8") 237.93 sq.ft5 DOOR FD3 (7'6" X 7' 8") 241.62 sq.ft6 DOOR GD5 (7'6" X 4' 2") 260.89 sq.ft7 WINDOW FW3 (1'8" X 4' 0") 348.79 sq.ft8 WINDOW GW1 (1'8" X 7' 0") 305.13 sq.ft9 WINDOW GW4(2'2" X 5' 0") 287.48 sq.ft

10 WINDOW FW1 (3'4" X 5' 0") 279.25 sq.ft11 WINDOW GW5(4'8" X 5' 0") 257.50 sq.ft12 WINDOW GW6(5'5" X 3' 6") 280.50 sq.ft13 WINDOW FW4(5'4" X 4' 0") 269.76 sq.ft14 WINDOW W Landing (1'3.5" X 6' 4.75"") 367.86 sq.ft15 WINDOW W st.cabin (1'3.5" X 1' 3.5") 630.81 sq.ft

AP Pro. & fixing archtrieve of size 1.5"x0.25" to door/window frame with two coats of paint

cost of wood 1.00 1.75 0.50cost of making & fixing 1.00cost of painting 1.00

5% ohd & sup 5.00profit 15.00

FW3 Bright bar in win. Fram - 1'8"x4'0" window size. kg/mt10.00 1.66 1.28

cost of making & fixing 10.00 1.66 1.28cost of painting 2 1.67 4

5% ohd & sup 5.00profit 15.00totalsize of window 1.67 4.00cost per sft

12.8mm bright bars

Page 138: Rate Analysis

FW1 Bright bar in win. Fram - 3'4"x5'0" window size. kg/mt14.00 3.33 1.28

cost of making & fixing 14.00 3.33 1.28cost of painting 2 3.33 5

5% ohd & sup 5.00profit 15.00totalsize of window 3.33 5.00cost per sft

FW4 Bright bar in win. Fram - 5'4"x4'0" window size. kg/mt10.00 5.33 1.28

cost of making & fixing 10.00 5.33 1.28cost of painting 2 5.33 4.00

5% ohd & sup 5.00profit 15.00totalsize of window 5.33 4.00cost per sft

GW1 Bright bar in win. Fram - 1'8"x7'0" window size. kg/mt20.00 1.67 1.28

cost of making & fixing 20.00 1.67 1.28cost of painting 2 1.67 7.00

5% ohd & sup 5.00profit 15.00totalsize of window 1.67 7.00cost per sft

GW4 Bright bar in win. Fram - 2'2"x5'0" window size. kg/mt14.00 2.17 1.28

cost of making & fixing 14.00 2.17 1.28cost of painting 2 2.17 5.00

5% ohd & sup 5.00

12.8mm bright bars

12.8mm bright bars

12.8mm bright bars

12.8mm bright bars

Page 139: Rate Analysis

profit 15.00totalsize of window 2.17 5.00cost per sft

GW5 Bright bar in win. Fram - 4'8"x5'0" window size. kg/mt14.00 4.67 1.28

cost of making & fixing 14.00 4.67 1.28cost of painting 2 4.67 5.00

5% ohd & sup 5.00profit 15.00totalsize of window 4.67 5.00cost per sft

GW6 Bright bar in win. Fram - 5'5"x3'6" window size. kg/mt8.00 5.42 1.28

cost of making & fixing 8.00 5.42 1.28cost of painting 2 5.42 3.50

5% ohd & sup 5.00profit 15.00totalsize of window 5.42 3.50cost per sft

12.8mm bright bars

12.8mm bright bars

Page 140: Rate Analysis

CFT INC.TAXCFT INC.TAXSFT INC.TAXSFT INC.TAXSFT INC.TAXSFT INC.TAXSFT INC.TAXSFT INC.TAXRFT INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXSFT INC.TAXNO INC.TAXNO INC.TAXNO INC.TAXKG INC.TAXKG INC.TAXNO INC.TAXSFT INC.TAX

sftsftrftsftrftrftsft/rft

D Q UNIT RATE AMOUNT

20.00 sft 271.86 sq.ft

Page 141: Rate Analysis

inch3.00 1.6153.00 0.3130.50 0.0070.50 0.010

1.94 CFT 651.00 1265.83 D3

1.00 0.1561.00 0.057

0.214 CFT 1200.00 256.25 D4

18.13 SFT 40.00 725.00 D6

17.94 SFT 10.00 179.44 d8

17.94 SFT 20.00 358.88 d9

6.00 NO 5.00 30.00 D293.00 NO 26.00 78.00 d241.00 NO 350.00 350.00 d140.00 NO 25.00 0.00 d160.00 NO 26.00 0.00 d190.00 NO 50.00 0.00 d270.00 NO 80.00 0.00 d26

24.00 NO 0.50 12.00 D304.00 NO 0.35 1.40 D311.00 KG 50.00 50.00 D322.00 KG 130.00 260.00 D33

20.00 sft 30.00 600.00 d3620.00 sft 5.00 100.00 d39

18.49 rft 3.00 55.47 d4017.67 rft 5.25 92.77 d4119.33 rft 6.00 116.00 d42

4531.03

226.55

679.66

5437.24

271.86 sq.ft

23.75 sft 251.26 sq.ft

inch

Page 142: Rate Analysis

3.00 1.6153.00 0.3910.50 0.0070.50 0.011

2.02 CFT 651.00 1317.26 D3

1.00 0.1561.00 0.063

0.219 CFT 1200.00 262.50 D4

19.94 SFT 40.00 797.50 D6

21.93 SFT 10.00 219.31 d8

21.93 SFT 20.00 438.63 d9

6.00 NO 5.00 30.00 D293.00 NO 26.00 78.00 d241.00 NO 350.00 350.00 d130.00 NO 25.00 0.00 d160.00 NO 26.00 0.00 d191.00 NO 50.00 50.00 d270.00 NO 80.00 0.00 d26

24.00 NO 0.50 12.00 D306.00 NO 0.35 2.10 D311.00 KG 50.00 50.00 D322.00 KG 130.00 260.00 D33

23.75 sft 30.00 712.50 d3623.75 sft 5.00 118.75 d39

18.98 rft 3.00 56.94 d4018.16 rft 5.25 95.34 d4120.33 rft 6.00 122.00 d42

4972.83

248.64

745.92

5967.39

251.26 sq.ft

28.75 sft 294.41 sq.ft

inch3.00 1.938

Page 143: Rate Analysis

3.00 0.5310.50 0.0070.50 0.013

2.49 CFT 651.00 1620.33 D3

1.00 0.1561.00 0.078

0.234 CFT 1200.00 281.25 D4

25.38 SFT 40.00 1015.00 D6

0.00 SFT 10.00 0.00 d8

64.00 SFT 20.00 1280.00 d9

6.00 NO 5.00 30.00 D293.00 NO 26.00 78.00 d241.00 NO 650.00 650.00 d130.00 NO 25.00 0.00 d162.00 NO 175.00 350.00 d201.00 NO 50.00 50.00 d271.00 NO 80.00 80.00 d26

24.00 NO 0.50 12.00 D306.00 NO 0.35 2.10 D311.00 KG 50.00 50.00 D322.00 KG 130.00 260.00 D33

28.75 sft 30.00 862.50 d3628.75 sft 5.00 143.75 d39

19.90 rft 3.00 59.70 d4018.83 rft 5.25 98.86 d4121.67 rft 6.00 130.00 d42

7053.49

352.67

1058.02

8464.19

294.41 sq.ft

42.50 sft 237.93 sq.ft

inch3.00 1.6153.00 0.625

Page 144: Rate Analysis

0.50 0.0070.50 0.021

2.27 CFT 651.00 1476.05 D3

1.50 1.2501.50 1.0310.75 0.0940.75 0.070

2.445 CFT 1200.00 2934.38 D4

0.00 SFT 40.00 0.00 D6

27.00 sft 48.00 1296.00 D28

0.00 SFT 10.00 0.00 d8

0.00 SFT 20.00 0.00 d9

6.00 NO 5.00 30.00 D296.00 NO 26.00 156.00 d241.00 NO 130.00 130.00 d133.00 NO 35.00 105.00 D174.00 NO 26.00 104.00 d192.00 NO 50.00 100.00 d270.00 NO 80.00 0.00 d26

48.00 NO 0.50 24.00 D3064.00 NO 0.35 22.40 D311.00 KG 50.00 50.00 D320.00 KG 130.00 0.00 D33

42.50 sft 30.00 1275.00 d3842.50 sft 5.00 212.50 D41

21.74 rft 3.00 65.22 D4285.00 SFT 5.25 446.25 D43

0.00 rft 6.00 0.00 D448426.80

421.34

1264.02

10112.16

237.93 sq.ft

57.50 sft 241.62 sq.ft

inch

Page 145: Rate Analysis

3.00 1.6153.00 0.8590.50 0.0070.50 0.054

2.53 CFT 651.00 1650.10 D3

1.50 2.5001.50 1.5000.75 0.1880.75 0.078

4.266 CFT 1200.00 5118.75 D4

0.00 SFT 40.00 0.00 D6

22.50 sft 48.00 1080.00 D28

0.00 SFT 10.00 0.00 d8

0.00 SFT 20.00 0.00 d9

6.00 NO 5.00 30.00 D2912.00 NO 26.00 312.00 d241.00 NO 130.00 130.00 d137.00 NO 35.00 245.00 D174.00 NO 26.00 104.00 d192.00 NO 50.00 100.00 d270.00 NO 80.00 0.00 d26

96.00 NO 0.50 48.00 D3064.00 NO 0.35 22.40 D311.00 KG 50.00 50.00 D320.00 KG 130.00 0.00 D33

57.50 sft 30.00 1725.00 d3857.50 sft 5.00 287.50 D41

23.73 rft 3.00 71.19 D42115.00 SFT 5.25 603.75 D43

0.00 rft 6.00 0.00 D4411577.69

578.88

1736.65

13893.23

241.62 sq.ft

31.25 sft 260.89 sq.ft

Page 146: Rate Analysis

inch3.00 1.6153.00 0.4690.50 0.0070.50 0.016

2.11 CFT 651.00 1370.94 D3

1.50 1.2501.50 0.7500.75 0.0940.75 0.039

2.133 CFT 1200.00 2559.38 D4

0.00 SFT 40.00 0.00 D6

15.00 sft 48.00 720.00 D28

0.00 SFT 10.00 0.00 d8

0.00 SFT 20.00 0.00 d9

6.00 NO 5.00 30.00 D296.00 NO 26.00 156.00 d241.00 NO 130.00 130.00 d133.00 NO 35.00 105.00 D172.00 NO 26.00 52.00 d192.00 NO 50.00 100.00 d270.00 NO 80.00 0.00 d26

48.00 NO 0.50 24.00 D3040.00 NO 0.35 14.00 D311.00 KG 50.00 50.00 D320.00 KG 130.00 0.00 D33

31.25 sft 30.00 937.50 d3831.25 sft 5.00 156.25 D41

20.24 rft 3.00 60.72 D4262.50 SFT 5.25 328.13 D43

0.00 rft 6.00 0.00 D446793.91

339.70

1019.09

8152.70

260.89 sq.ft

Page 147: Rate Analysis

6.67 sft 348.79 sq.ft

inch3.00 0.4173.00 0.8330.50 0.0140.50 0.000

1.26 CFT 651.00 822.79 D3

1.50 0.1411.50 0.2340.75 0.0230.75 0.016

0.414 CFT 1200.00 496.88 D4

2.50 sft 24.00 60.00 D50.75 sft 50.00 37.50 D35

2.00 NO 5.00 10.00 D292.00 NO 17.00 34.00 d232.00 NO 25.00 50.00 d161.00 NO 18.00 18.00 d181.00 NO 14.00 14.00 d21

16.00 NO 0.50 8.00 D3014.00 NO 0.35 4.90 D310.10 KG 50.00 5.00 D32

6.67 sft 35.00 233.33 d396.67 sft 5.00 33.33 D41

13.33 rft 3.00 40.00 D4213.33 SFT 5.25 70.00 D43

1937.73

96.89

290.66

2325.28

348.79 sq.ft

11.67 sft 305.13 sq.ft

inch3.00 0.417

Page 148: Rate Analysis

3.00 1.4580.50 0.0140.50 0.000

1.89 CFT 651.00 1229.67 D3

1.50 0.1411.50 0.4220.75 0.0430.75 0.016

0.621 CFT 1200.00 745.31 D4

5.50 sft 24.00 132.00 D50.75 sft 50.00 37.50 D35

4.00 NO 5.00 20.00 D293.00 NO 17.00 51.00 d232.00 NO 25.00 50.00 d161.00 NO 18.00 18.00 d181.00 NO 14.00 14.00 d21

24.00 NO 0.50 12.00 D3014.00 NO 0.35 4.90 D310.10 KG 50.00 5.00 D32

11.67 sft 35.00 408.33 d3911.67 sft 5.00 58.33 D41

19.33 rft 3.00 58.00 D4223.33 SFT 5.25 122.50 D43

2966.55

148.33

444.98

3559.86

305.13 sq.ft

10.83 sft 287.48 sq.ft

inch3.00 0.5213.00 1.0420.50 0.0140.50 0.000

1.58 CFT 651.00 1026.23 D3

1.50 0.188

Page 149: Rate Analysis

1.50 0.2970.75 0.0310.75 0.023

0.539 CFT 1200.00 646.88 D4

5.25 sft 24.00 126.00 D51.13 sft 50.00 56.25 D35

2.00 NO 5.00 10.00 D292.00 NO 17.00 34.00 d232.00 NO 25.00 50.00 d161.00 NO 18.00 18.00 d181.00 NO 14.00 14.00 d21

16.00 NO 0.50 8.00 D3014.00 NO 0.35 4.90 D310.10 KG 50.00 5.00 D32

10.83 sft 35.00 379.17 d3910.83 sft 5.00 54.17 D41

16.33 rft 3.00 49.00 D4221.67 SFT 5.25 113.75 D43

2595.34

129.77

389.30

3114.41

287.48 sq.ft

16.67 sft 279.25 sq.ft

inch3.00 0.7813.00 1.0420.50 0.0140.50 0.000

1.84 CFT 651.00 1195.76 D3

1.50 0.3281.50 0.5940.75 0.0630.75 0.029

1.014 CFT 1200.00 1216.41 D4

Page 150: Rate Analysis

8.75 sft 24.00 210.00 D51.88 sft 50.00 93.75 D35

4.00 NO 5.00 20.00 D294.00 NO 17.00 68.00 d233.00 NO 25.00 75.00 d162.00 NO 18.00 36.00 d182.00 NO 14.00 28.00 d21

32.00 NO 0.50 16.00 D3034.00 NO 0.35 11.90 D310.20 KG 50.00 10.00 D32

16.67 sft 35.00 583.33 d3916.67 sft 5.00 83.33 D41

18.67 rft 3.00 56.00 D4233.33 SFT 5.25 175.00 D43

3878.48

193.92

581.77

4654.18

279.25 sq.ft

23.33 sft 257.50 sq.ft

inch3.00 1.0423.00 1.5630.50 0.0140.50 0.000

2.62 CFT 651.00 1704.35 D3

1.50 0.4221.50 0.5940.75 0.0630.75 0.041

1.119 CFT 1200.00 1342.97 D4

12.25 sft 24.00 294.00 D52.63 sft 50.00 131.25 D35

4.00 NO 5.00 20.00 D29

Page 151: Rate Analysis

4.00 NO 17.00 68.00 d234.00 NO 25.00 100.00 d162.00 NO 18.00 36.00 d182.00 NO 14.00 28.00 d21

32.00 NO 0.50 16.00 D3040.00 NO 0.35 14.00 D310.20 KG 50.00 10.00 D32

23.33 sft 35.00 816.67 d3923.33 sft 5.00 116.67 D41

21.33 rft 3.00 64.00 D4246.67 SFT 5.25 245.00 D43

5006.91

250.35

751.04

6008.29

257.50 sq.ft

18.96 sft 280.50 sq.ft

inch3.00 1.2503.00 1.4580.50 0.0140.50 0.000

2.72 CFT 651.00 1772.17 D3

1.50 0.3281.50 0.4060.75 0.0140.75 0.0250.75 0.0390.75 0.029

0.842 CFT 1200.00 1010.16 D4

5.00 sft 24.00 120.00 D55.69 sft 24.00 136.50 D51.88 sft 50.00 93.75 D35

2.00 NO 5.00 10.00 D294.00 NO 17.00 68.00 d234.00 NO 25.00 100.00 d162.00 NO 18.00 36.00 d18

Page 152: Rate Analysis

2.00 NO 14.00 28.00 d2132.00 NO 0.50 16.00 D3040.00 NO 0.35 14.00 D310.20 KG 50.00 10.00 D32

18.96 sft 35.00 663.54 d3918.96 sft 5.00 94.79 D41

19.83 rft 3.00 59.50 D4237.92 SFT 5.25 199.06 D43

4431.47

221.57

664.72

5317.76

280.50 sq.ft

21.33 sft 269.76 sq.ft

inch3.00 1.1983.00 1.6670.50 0.0140.50 0.000

2.88 CFT 651.00 1873.89 D3

1.50 0.3281.50 0.4690.75 0.0140.75 0.0290.75 0.0470.75 0.029

0.916 CFT 1200.00 1099.22 D4

6.25 sft 24.00 150.00 D56.56 sft 24.00 157.50 D51.88 sft 50.00 93.75 D35

2.00 NO 5.00 10.00 D294.00 NO 17.00 68.00 d234.00 NO 25.00 100.00 d162.00 NO 18.00 36.00 d182.00 NO 14.00 28.00 d21

32.00 NO 0.50 16.00 D3040.00 NO 0.35 14.00 D310.20 KG 50.00 10.00 D32

Page 153: Rate Analysis

21.33 sft 35.00 746.67 d3921.33 sft 5.00 106.67 D41

20.67 rft 3.00 62.00 D4242.67 SFT 5.25 224.00 D43

4795.69

239.78

719.35

5754.83

269.76 sq.ft

8.26 sft 367.86 sq.ft

inch3.00 0.3653.00 1.3540.50 0.0140.50 0.000

1.73 CFT 651.00 1127.95 D3

1.50 0.0941.50 0.3910.75 0.0430.75 0.008

0.535 CFT 1200.00 642.19 D4

3.75 sft 24.00 90.00 D50.56 sft 50.00 28.13 D35

4.00 NO 5.00 20.00 D293.00 NO 17.00 51.00 d232.00 NO 25.00 50.00 d161.00 NO 18.00 18.00 d181.00 NO 14.00 14.00 d21

24.00 NO 0.50 12.00 D3014.00 NO 0.35 4.90 D310.10 KG 50.00 5.00 D32

8.26 sft 35.00 289.14 d398.26 sft 5.00 41.31 D41

17.38 rft 3.00 52.13 D4216.52 SFT 5.25 86.74 D43

Page 154: Rate Analysis

2532.48

126.62

379.87

3038.98

367.86 sq.ft

1.67 sft 630.81 sq.ft

inch3.00 0.3653.00 0.3130.50 0.0140.50 0.000

0.69 CFT 651.00 449.82 D3

1.50 0.0631.50 0.0630.75 0.0060.75 0.006

0.137 CFT 1200.00 164.06 D4

0.56 sft 24.00 13.50 D50.00 sft 50.00 0.00 D35

2.00 NO 5.00 10.00 D292.00 NO 17.00 34.00 d232.00 NO 25.00 50.00 d161.00 NO 18.00 18.00 d181.00 NO 14.00 14.00 d21

16.00 NO 0.50 8.00 D3014.00 NO 0.35 4.90 D310.10 KG 50.00 5.00 D32

1.67 sft 35.00 58.39 d391.67 sft 5.00 8.34 D41

7.17 rft 3.00 21.50 D423.34 SFT 5.25 17.52 D43

877.04

43.85

131.56

1052.45

630.81 sq.ft

Page 155: Rate Analysis

Pro. & fixing archtrieve of size 1.5"x0.25" to door/window frame with two coats of paint 21.05 rft

1200.00 7.2925.00 5.005.25 5.25

17.540.882.63

21.05 rft

KG rate 84.88 sft6.476 50.00 323.826.476 12.00 77.72

13.33 5.25 70.00471.54

23.5870.73

565.846.67 sft

84.88 sft

Page 156: Rate Analysis

KG rate 93.87 sft18.207 50.00 910.3418.207 12.00 218.48

33.33 5.25 175.001303.82

65.19195.57

1564.5816.67 sft

93.87 sft

KG rate 85.17 sft20.808 50.00 1040.3820.808 12.00 249.69

42.67 5.25 224.001514.08

75.70227.11

1816.8921.33 sft

85.17 sft

KG rate 95.53 sft13.005 50.00 650.2413.005 12.00 156.06

23.33 5.25 122.50928.80

46.44139.32

1114.5611.67 sft

95.53 sft

KG rate 93.87 sft11.834 50.00 591.7211.834 12.00 142.01

21.67 5.25 113.75847.48

42.37

Page 157: Rate Analysis

127.121016.98

10.83 sft93.8748 sft

KG rate 93.87 sft25.489 50.00 1274.4725.489 12.00 305.87

46.67 5.25 245.001825.34

91.27273.80

2190.4123.33 sft

93.8748 sft

KG rate 78.95 sft16.906 50.00 845.3116.906 12.00 202.87

37.92 5.25 199.061247.25

62.36187.09

1496.7018.96 sft

78.9468 sft