Upload
nawang-negi
View
291
Download
7
Tags:
Embed Size (px)
Citation preview
RAMPUR HYDRO ELECTRIC PROJECT
IN
HIMACHAL PRADESH, INDIA
(412 MW)
“Project Description and Design of Anchor Block”
Under Guidance of: - Report prepared by:-
Er.J.P.Mahajan (Sr.Manager of Rhep cell) Nawang Chhonzer Negi
Er.Mahesh Civil Engineering Dprt.
Satluj Jal Vidyut Nigam Limited Shimla.
Introduction:-
Rampur Hydro-electric Project (412 MW) is located downstream of already executed 6 x 250 MW NJHEP and intends to use the desilted water discharged by the upstream project. As such the construction of Rampur HEP does not involve construction of any dam / desilting chambers and thus avoiding any serious environmental impact on local flora and fauna. It is proposed, to divert water from out-fall arrangement of NJHEP through a 10.5 meter diameter HRT of 15.177 Km Length. The construction of the project involves in addition to the Head Race Tunnel a 149.50 m above orifice slab. High and 38 m Diameter surge shaft, 3 numbers of pressure shafts/penstocks of 5.4 m/3.8 m diameter each and a surface Power House.
Location and layout of the Rampur project.
RHEP is located, near the town of Rampur in Shimla and Kullu districts of Himachal
Pradesh. The project area is enclosed by latitudes 77° 35’N and 77° 43’; and longitudes
31°23’E and 31° 30’E.
PROJECT DESCRIPTION:-
The Rampur Hydroelectric Project 412 MW is a tailrace development of 1500 MW
Nathpa Jhakri Hydroelectric Project with minimal social and environmental effects. Both
Jhakri and Rampur power stations are to be operated in tandem as at Jhakri tail race
pond very little storage is available.
The latter will be the master station while the former the slave. A small reservoir in the
shape of Pond of the Tailrace Outfall of NJHEP (tail pool) links the two projects. The
intake of the RHEP, which has been constructed as a part of the TRT Outfall, will draw
desilted water from the tail pool. Water leaving NJHEP will automatically enter Rampur
Intake whenever the TRT Outfall gates of Nathpa Jhakri are closed. It will utilize the
entire flow released by the latter which then flow through HRT on the same bank. The
head race tunnel, 15.08 km long will cross over to the right bank by means of a cut &
cover section, 43.2 m constructed in the river bed. An open to sky, throttled surge shaft,
38 m diameter, 140 m deep lies at the end of the HRT. Three pressure shafts take off at
the bottom of the surge shaft and emerge on the surface further downstream are of
5.40 m diameter. The penstocks continue up to the powerhouse near which they
bifurcate into 3.80 m diameter branches to supply water to six Francis turbines housed
in a surface Power House of size 138 m × 23.5 m × 48 m high. The tail water is let out in
to six draft tube tunnels leading into a collection gallery, which relays water to a 54 m
long tailrace tunnel of 10.5 m diameter, horse shoe shaped .The tailrace tunnel empties
in to open gated TRT Outfall structure. Beyond this, an exit channel leads the water to
the River as shown in figure.
The project with an installed capacity of 412 MW (6 × 68.67 MW) will generate
2025.55GWh of electrical energy in a 90% dependable year and 2182.06GWh in an
average year.
Penstock:-
The penstock, a pipe or conduit used to carry water to a water wheel or turbine. The pen-
stock can be supported in a variety of ways, depending on the existing geologic conditions
and penstock profile. The penstock can be totally buried, partially buried or supported
above ground. Generally, penstock is totally buried when either drainage is required and
when the penstock requires protection from falling tree or when dictated by economics.
And soil cover protects the penstock against the expansion or contraction. The buried
penstocks are difficult to inspect or repair. In the case of partially buried penstock
corrosion can be the problem due to contact with the soil. The above ground supports are
the better then totally buried or partially buried penstocks, and allow a better handling or
inspection or repair access. Aboveground anchor blocks and piers are used to support the
penstock.
Anchor block and Piers:-
Anchors are provided at bends to resist hydrostatic loads and accumulation of
longitudinal loads and to prevent the shift in the pipeline and to resist the vibrational
force that tend to cause displacement in the penstocks. Piers are used to support or
handle the different kind of load, such as bending stresses, concentrated loads at support,
dead load of the pipe and contained water, and resist the longitudinal force resulting from
temperature change, friction, and circumferential stresses.
Criteria for design of Anchor Blocks for the Penstock with
expansion joints:-
Note:-Design of anchor block is carried out as per IS : 5330-1984.
1. The foundation of anchor blocks shall be designed so that the maximum pressure
on the foundation shall not exceed the allowable bearing pressure of the soil,
which is 100 t/m2 in our case.
2. When the profile is sloping, the safe bearing capacity shall be reduced to take
into account the decrease due to non- normality of resultant to the surface in
accordance with IS:6403-1971. The angle set up by resultant with ground shall
not be less than 30° for stability of the soil below anchor.
3. Anchor block shall be designed to be safe against sliding on the foundation. The
sliding friction factor is computed by dividing the total horizontal forces by the
total vertical forces shall be less than given below (∑H/∑M<Sliding factor).
Surface Sliding Factor
Concrete on rock 0.50
Concrete on gravel 0.40
Concrete on sand 0.33
concrete on clayey soil 0.25
4. In case the anchor blocks rests on solid rock, without any weak planes
capable of sliding, the sliding factor shall be designed for 0.75. Where however,
weak seams or joints along which sliding may be apprehended in the rock below,
the stability be checked by the following formula:
µ’=co-efficient of internal friction between foundation, concrete and foundation
under saturated condition,
∑V’=total vertical force,
a”=area under compression in m3,
τ=shearing strength in N/mm2,
∑T=total horizontal forces.
Note:- The weight of the anchor block may get reduced if the anchor block and the rock
above of such a seam is anchored into the rock below the seam.
5. Anchor block shall be designed to be safe against overturning. And to avoid the
overturning of anchor block at bend, the ratio of stabilizing moment to
destabilizing moment should be greater than 2.0.
6. The design of the anchor blocks shall be such that the resultant of all the forces
falls within themiddle B/6 portion of the base where B is base width . For anchor
blocks with stepped bottom the designs shall be made so that the resultant falls
within the kern of the projection of the anchor base on the plane perpendiculr to
the resultant as shown in figure.
Figure Stability of Anchor Block with Stepped Foundation
Problem: - Design an anchor block against bend forces to stabilize the penstock at
bend considering earthquake forces taking
Notation
V=velocity,
A=Cross sectional area of pipe at anchor,
P=Dead weight of pipe from anchor uphill to expansion joint,
P’=Dead weight of the pipe from anchor downhill to expansion joint,
H=Maximum Head at any point including water hammer,
f’= friction of expansion joints per meter of circumference,
µ=coefficient of friction between packing and liner,
e=packing length,
f=coefficient of friction of pipe,
g=acceleration due to gravity.
p=weight of the pipe and contained water from the anchor to adjacent uphill pier
in N.
d diameter of pipe
e=packing length
∑V= total vertical force
∑M= total moment
Given Data
Diameter of penstock D =5.4m
Thickness of pipe t =44mm
Discharge Q=135 m3/s
Length of the penstock L =25m
Then we can calculate:-
A=3.14 X 2.72=22.8906 m2
V= Q/A
V=135/22.89 =5.9 m/s
P=wAL
P=7.5 X (AR-Ar) X L
P=7.5 X 0.7525 X 6
P=33.86 t
P’=0 (Because no piers or support is provided in downhill)
And weight of water in pipe
W=wAL
W=1 X π X 2.72 X 6
W=137.41 t
H= (1058.4 -905.3) m
H=153.1 m
µ=0.26, e=0.16
f’= 1.5µwHe
f’=1.5 X 0.26 X 7.5 X 153.1 X 0.16
f’=71.604
Load and force acting on anchor
1) Hydrostatic force:-
Fs= wAH
Fs=1X123.1X22.89
Fs=3504.459 t
Fsh1=3504.459 t ,
Fsv1=0
Fsh2=3504.459Xcos 40.15°
Fsh2=2678.67 t
Fsv2= 3504.459Xsin40.15°
Fsv2=2678.67 t
2) Dynamic force:-
Fd=QwV/g
Fd=796.5 t
Fdh1=796.5 t
Fdv1=0
Fdh2=796.5Xcos40.15°
Fdh2=608.81 t
Fdv2=796.5Xsin40.15°
Fdv2=513.57 t
3) Force due to the dead weight of pipe from anchor uphill to expansion joint
Du=0
Duh=0 and Duv=0
4) Force due to dead weight of pipe from the anchor downhill to the expansion
joint.
Dd=0
Ddh=0 and Ddv=0
5) Sliding friction of pipe on piers due to expansion or contraction uphill from
anchor
Spu=98.037 t
Spuh=98.037 t
Spuv=0
6) Sliding friction of the pipe on piers due to expansion or contraction downhill
from anchor
Spd=0
Spdh-0
Spdv=0
7) Sliding friction of uphill expansion joint
Sev-1.234 t
Sevh=1.234 t
Sevv=0
8) Sliding friction of downhill expansion joint
Sed=0
Sedh=0
Sedv=0
9) Hydrostatic pressure on exposed of pipe in uphill expansion joint.
Fu=0.785X10-3 t
Fuh=0.785X10-3 t
Fuv=0
10) Hydrostatic pressure on exposed end of pipe in downhill expansion joint
Fd=0
Fdh=0
Fdv=0
11) Longitudinal force due to reducer above anchor
Lu=wH(A’-A)
Lu=0
Luh=0 and Luv=0
12) Longitudinal force due to reducer below anchor
Ld=wH(A’-A’’)
Ld=0
Ldh=0
Ldv=0
Net horizontal force Rx
Rx=1112.75 t
Net vertical force Ry :
Ry= -2773.21 t
Resultant R:-
R=√(Rx2+Ry
2-2RxRy cos Ѳ)
R=2988.127 t
Now let’s assume the
Length of anchor block=25m
Width of anchor block=12m
Height of anchor block=18 m
Then self-weight of concrete= L X W X H X 2.4
=25 X 12 X 18 X 2.4
=12960 t
Net weight of the concrete= 12960-cross sectional area of penstock X L X 2.4
=12960-π X 2.7442 X 25 X 2.4
=12960-1419=11541 t
Weight of the penstock= π X (R2-r2) X full length X w
=3.14(2.7442-2.72) X 25 X 7.85
=147.68 t
Weight of water in penstock= π X 2.72 X 25X 1
=572.56 t
Now:-
Self-weight of anchor + weight of penstock +water
=11541+147.68+572.56
=12261.124 t
Term Force L.A Moment about toe
Self-weight of anchor + 12261.124 (↓) 12.5m 153264.05 tm
Block + penstock + water
Net horizontal force 1112.75 (→) 9m -10014.75 tm
Net vertical force -2773.21(↑) 12.5m -34665.13 tm
Seismic force (horizontal) 17716.56(→) 9m -15449.04 tm
Seismic force (vertical) -1144.37(↑) 12.5m -14304.64 m
Total: - ∑v=8343.54 ∑M=78830.54
∑H=2829.31
1) Check for the resultant from toe :-
Eccentricity=L/2 – (∑M/∑V) < (L/6)
E=25/2 – (78830.54/8343.54)
E=3.052 < (L/6) =4.17
Hence proved, safe against tension at base.
2) Check for Bearing pressure:-
Toe stress= (∑V/A) X (1+6e/L)
Toe stress= {83434.54 /(25X12)} X (1+6X3.052/25)
Toe stress=48.17 t/m2 <100 t/m2 in our case, in Rhep.
3) Check against stability:-
(∑H/∑V) <0.4
=2829.33/8343.54=034 <0.4
Hence safe against sliding
4) Check against overturning:-
(Stabilizing moment/destabilizing moment) > 2.0
= (153264.05/74433.76) =2.059 >2.0
Hence proved, the anchor block is safe against overturning.
Without considering the seismic force:-
Term Force L.A Moment about toe
Self-weight of anchor + 12261.124 (↓) 12.5m 153264.05 tm
Block + penstock + water
Net horizontal force 1112.75 (→) 9m -10014.75 tm
Net vertical force -2773.21(↑) 12.5m -34665.13 tm
Total:- ∑v=9487.914 t ∑M=108584.175 tm
∑H=1112.75 t
1) Check for the resultant from toe :-
Eccentricity=L/2 – (∑M/∑V) < (L/6)
E=25/2 – (108584.175/9487.914)
E=1.05 < (L/6) =4.17
Hence proved, safe against tension at base.
2) Check for Bearing pressure:-
Toe stress= (∑V/A) X (1+6e/L)
Toe stress= {9487.914 /(25X12)} X (1+6X1.05/25)
Toe stress=39.596 t/m2 <100 t/m2 in our case, in Rhep.
3) Check against stability:-
(∑H/∑V) <0.4
=1112.75/9487.914=0.117 <0.4
Hence safe against sliding
4) Check against overturning:-
(Stabilizing moment/destabilizing moment) > 2.0
=(153264.05/44679.87) =3.43 >2.0
Hence proved, the anchor block is safe against overturning.