53
INDUSTRIAL TRAINING REPORT CHUA CHONG LIANG Bachelor of Science (Hons) Quantity Surveying Lee Kong Chian Faculty of Engineering and Science Universiti Tunku Abdul Rahman December 2015

QS Industrial Training Report - CHUA CHONG LIANG 1104838

Embed Size (px)

Citation preview

Page 1: QS Industrial Training Report - CHUA CHONG LIANG 1104838

INDUSTRIAL TRAINING REPORT

CHUA CHONG LIANG

Bachelor of Science (Hons) Quantity Surveying

Lee Kong Chian Faculty of Engineering and Science

Universiti Tunku Abdul Rahman

December 2015

Page 2: QS Industrial Training Report - CHUA CHONG LIANG 1104838

ii

DECLARATION

I sincerely declare that:

1. I am the sole writer of this report.

2. The details of training and experience contained in this report describe my

involvement as a trainee in the field of quantity surveying.

3. All the information contained in this report is certain and correct to the

knowledge of the author.

Signature : _________________________

Name : _________________________

ID No. : _________________________

Date : _________________________

Page 3: QS Industrial Training Report - CHUA CHONG LIANG 1104838

iii

ACKNOWLEDGEMENTS

I would like to express my utmost gratitude to UTAR for providing opportunity to

me to pursue the quantity surveying training as a partial fulfilment of the requirement

for the degree of Bachelor of Science.

I would like to thank Datuk Tee Eng Ho for giving me an opportunity to

undergo my industrial training at Kerjaya Prospek (M) Sdn. Bhd as well as Ms

Joanne Yap who arrange my industrial training. Throughout this training, I am very

honoured to have Mr. Loh Zhen Shen as my mentor, with his encouragement and

guidance from time to time and advise me to perform the program. It never felt

boring before as we have wasted his valuable time. In addition, I would also like to

thank Ms. Nadzirah as my visiting lecturer who came to the company for visiting us.

Lastly, I would like to express my appreciation to all the staffs in Kerjaya

Prospek (M) Sdn. Bhd., without their sharing of their experiences and help, I

wouldn’t have come so far and grow so much and gain a lot of knowledge.

Page 4: QS Industrial Training Report - CHUA CHONG LIANG 1104838

iv

ABSTRACT

Kerjaya Prospek (M) Sdn. Bhd was my choice to undergo my 26 weeks of Industrial

Training. The company was known as a main contractor firm. During the 26 weeks

period of industrial training, I was supervised by Mr Loh Zhen Shen. I have been

assigned to accomplish various tasks which included measurement of work done,

work done and defect inspection, horizontal levelling and vertical levelling, and the

preparation of debit note and weekly progress report. Throughout my industrial

training, I was able to apply the skill and knowledge acquired from lecture to

complete my work in practice. Besides, I learn and experience new things which

were never taught in lecture for example preparing weekly progress report and debit

note, work done and defect inspection and vertical levelling. On the other hands, as a

trainee, good attitude is a must to have in order to follow and complete the

instructions given although it is a miscellaneous works. Lastly, within 6 months

industrial training I had gained uncountable knowledge and experience and

understand more on the roles of quantity surveyor in construction industry.

Page 5: QS Industrial Training Report - CHUA CHONG LIANG 1104838

v

TABLE OF CONTENTS

DECLARATION ii

ACKNOWLEDGEMENTS iii

ABSTRACT iv

TABLE OF CONTENTS v

LIST OF TABLES vii

LIST OF FIGURES viii

LIST OF SYMBOLS / ABBREVIATIONS ix

CHAPTER

1 INTRODUCTION 10

1.1 Background 10

1.2 Objective of the Report 11

1.3 Description of Report Structure 11

2 RELATED LEARNING OUTCOMES 13

2.1 Company Background 13

2.2 Description of Tasks Setting 18

2.2.1 Measurement of Work Done 18

2.2.2 Horizontal Levelling and Vertical Levelling 20

2.2.3 Preparation of Debit Note 23

2.2.4 Preparation of Weekly Progress Report 24

2.2.5 Work done and Defect Inspection 26

2.3 Report Achievement of Tasks Set 28

2.3.1 Measurement of Work Done 28

Page 6: QS Industrial Training Report - CHUA CHONG LIANG 1104838

vi

2.3.2 Horizontal Levelling and Vertical Levelling 28

2.3.3 Preparation of Debit Note 29

2.3.4 Preparation of Weekly Progress Report 29

2.3.5 Work Done and Defect Inspection 30

2.4 Limitations and Recommendations 30

2.5 Expectation After Graduation and Career 32

3 MONTLY REPORT 33

3.1 Month 1 – June 2015 33

3.2 Month 2 – July 2015 37

3.3 Month 3 – August 2015 39

3.4 Month 4 – September 2015 42

3.5 Month 5 – October 2015 44

3.6 Month 6 – November 2015 46

4 CONCLUSION 47

4.1 Summary 47

4.1.1 Apply and Link the Theoretical Knowledge to Solve

the Problem in Practice 47

4.1.2 Demonstrate Technical Competence in QS

Technical Competence 48

4.1.3 Develop Emotional Intelligent and Auxiliary Skills

49

4.2 Concluding Remarks 49

REFERENCES 50

APPENDICES Error! Bookmark not defined.

Page 7: QS Industrial Training Report - CHUA CHONG LIANG 1104838

vii

LIST OF TABLES

TABLE TITLE PAGE

Table 2.1.1 Company's Information 15

Page 8: QS Industrial Training Report - CHUA CHONG LIANG 1104838

viii

LIST OF FIGURES

FIGURE TITLE PAGE

Figure 2.1.1 Company's Logo 13

Figure 2.1.2 Logo of award by UKAS 14

Figure 2.1.3 Organization Chart 16

Figure 2.2.1 Measurement of Work done in Microsoft Excel 18

Figure 2.2.2 Setting Up The Laser Level on The Marking Line 21

Figure 2.2.3 The Use of Measuring Tape 22

Figure 2.2.4 Rectifying The Wall of Aluminium Formwork 22

Figure 2.2.5 Debit Note 23

Figure 2.2.6 Weekly Progress Report 25

Figure 2.2.7 Wire Testing 26

Figure 2.2.8 Water Flow Testing 26

Figure 2.2.9 Water Flow Test Report 27

Figure 3.1.1 Site Walk 34

Figure 3.1.2 Safety and Health Meeting 36

Figure 3.3.1 Housekeeping 41

Figure 3.3.2 Release of Start Work by DBKL 42

Figure 3.4.1 Summary of Debit Note 44

Page 9: QS Industrial Training Report - CHUA CHONG LIANG 1104838

ix

LIST OF SYMBOLS / ABBREVIATIONS

UTAR University of Tunku Abdul Rahman

TARC Tunku Abdul Rahman College

FCCA Charted Certified Accountant

ICSA Institute of Chartered Secretaries and Administrations

UK United Kingdom

PPE Personal Protective Equipment

MC Medical Certificate

DBKL. Dewan Bandaraya Kuala Lumpur

Page 10: QS Industrial Training Report - CHUA CHONG LIANG 1104838

CHAPTER 1

1 INTRODUCTION

1.1 Background

The preparation of this Industrial Training Report is to enhance the writing skills of

the student on recording down the daily tasks given and new experience and task

learned as well as the commitment and responsibility to record down the daily tasks

every day and to prepare this Industrial Training Report given. Besides, it helps the

student to understand the format of the Final Year Project which is required to

accomplish in final year for two semesters by every UTAR students.

Starting off, for UTAR students to accomplish their Bachelor in Science

(HONS) Quantity Surveying study, 26 weeks of Industrial Training is part of the

programme of the graduation requirements which undergraduates must be

participated in the related industry. The 26 weeks Industrial Training started from 1st

June 2015 till 30th

November 2015. After the completion of the Industrial Training,

students will be preparing the Industrial Training Report which deadline on 15th

December 2015. As for my industrial training, I had joined Kerjaya Prospek (M) Sdn.

Bhd. which is a main contractor firm as well as a developer firm to undergo my 26

weeks industrial training and it took place at construction site office which is located

at Old Klang Road, Kuala Lumpur. The construction project is a high rise building

which client is the company itself. The work tasks assigned I had exposed most of

my time were supervision of structure formwork work and verifying subcontractor’s

claim. The work task of preparation of weekly report was assigned later after 13

weeks.

Page 11: QS Industrial Training Report - CHUA CHONG LIANG 1104838

1.2 Objective of the Report

The objectives of having industrial training are to allow the students to experience

new things, gain new knowledge that were not taught in lecture class, to build up the

responsibility and commitment on recording down the task into the log book every

day and also to improve the soft skill of the students which are communication skills,

leadership skills and teamwork that allow the student to learn how to approach to

outsiders, giving orders and working together as one.

1.3 Description of Report Structure

In this Industrial Training Report, it has categorized into 4 chapters, there are

Introduction, Related Learning Outcomes, Monthly report and Conclusion. First,

Chapter One will be Introduction, which consists of background, objective of the

report and description of report structure. Background, this section will cover the

purpose of the preparation of Industrial Training Report and the background of the

introduction of industrial training. Objective of the report, in this section, it will

introduce the objective of the preparation of Industrial Training Report. As for the

description of report structure section, it describes the bone structure and the flow

line of the Industrial Training Report and explains what will be covered for each

chapter and section.

Chapter two, Related Learning Outcomes, in this chapter, it consists of 5

sections which are company background, description of task setting, report

achievement of tasks set, limitations and recommendations and expectation after

graduation and career. For the first section, company background, it will introduce

the background of the company and the nature of company. Second, description of

tasks setting section will described the process to accomplish the tasks that were

assigned in detail. Third, report achievement of tasks set section, it will describe the

process of the accomplishment of the achievement made on the first day of industrial

training after went through 26 weeks industrial training. Fourth, limitations and

recommendations section will covers the limitations that will face while doing this

Page 12: QS Industrial Training Report - CHUA CHONG LIANG 1104838

industrial training and the recommendations for better industrial training experience.

Lastly, expectation after graduation and career section, it will allow students to show

any expectation on after their graduation and their future career after undergo 26

weeks of industrial training.

Chapter Three, Monthly Report, this chapter will covers the summary of the

daily work task every month. Students will prepare this chapter of industrial training

report in monthly form. For the last chapter, Chapter Four, Conclusion, will conclude

overall of the industrial training report.

Furthermore, industrial training daily log book and area of work involvement

summary will be attached on the appendices section. The purpose of having

industrial training daily log book and area of work involvement summary are to keep

track and record down the daily activities and tasks assigned, signature of both

student and supervisor are required for industrial training daily log book.

Page 13: QS Industrial Training Report - CHUA CHONG LIANG 1104838

CHAPTER 2

2 RELATED LEARNING OUTCOMES

2.1 Company Background

Figure 2.1.1 Company's Logo

I have joined Kerjaya Prospek (M) Sdn. Bhd. for the 26 weeks of Industrial Training

which is classified as contract tenders of unlimited value. Kerjaya Prospek (M) Sdn.

Bhd. was incorporated in July 1995 and registered with the Construction Industry

Development (CIBD) as a Grade 7 Contractor. Kerjaya Prospek (M) Sdn. Bhd. has

been known as a high-end properties builder with industry leaders such as the E&O

Group on St Mary and Dua Residency projects. Kerjaya Prospek (M) Sdn. Bhd. has

also worked together with SP Setia, IOI Group, AP Land, UM Land, Malaysian

Resources Corporation Bhd, Belle View Group, and ECH Development Sdn Bhd. for

the Lumina development in Mont' Kiara. Kerjaya Prospek (M) Sdn. Bhd. has

achieved the converted ISO 9001:2008 Quality Management Systems Certification

by UKAS in year 2008.

Page 14: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 2.1.2 Logo of award by UKAS

Kerjaya Prospek (M) Sdn. Bhd. has evolved tremendously into a well-known player

in the property market in past 3 years by launching the luxury maiden condominium

projects which are 222 Residency and 288 Residency in Setapak, Kuala Lumpur.

Majority of the projects launched was successfully sold out including Residency V

where I am doing my 26 weeks of Industrial Training at. On August 2010, Kerjaya

Prospek (M) Sdn. Bhd. has evolved to developer from high-end project contractor

via setting up a Property Development Division.

The objective of this organisation is to tap on the experience and expertise to

deliver services and products of the highest quality to customers. For the business

objectives and mission of company, management excellence, strong corporate values,

business dynamism and focused vision were keys to its future success, Kerjaya

Prospek (M) Sdn. Bhd. believed.

Page 15: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.1.1 Company Information

Table 2.1.1 Company's Information

Name of Company Kerjaya Prospek (M) Sdn. Bhd

Address

No. 1, Jalan Wangsa Permai, 3rd Floor, Bangunan

One Wangsa, Taman Wangsa Permai, 52200

Kuala Lumpur.

Telephone No. 03-6277 5192

Facsimile No. 03-6277 5443 / 5772

E-mail [email protected]

Company Registration

No. 352407-U

CIDB Grade Grade 7

Page 16: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.1.2 Structure of Organisation Chart

Figure 2.1.3 Organization Chart

Page 17: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.1.3 Key of Personnel

Name: Datuk Tee Eng Ho

Age: 49

Position: Chief Executive Officer

Year of experience: 24 years

Qualification: Diploma in Technology (Building) TARC

Name: Mr. Tee Eng Seng

Age: 44

Position: Managing Director

Year of experience: 23 years

Qualification: SPM

Name: Datin Toh Siew Chuon

Age: 47

Position: Director

Year of experience: 23 years

Qualification: FCCA (UK) & ICSA (UK)

Name: Mr Yap Wee Kiat

Age: 37

Position: Project Manager

Year of experience: 11 years

Qualification: Diploma in Quantity Surveying TARC

Page 18: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.2 Description of Tasks Setting

2.2.1 Measurement of Work Done

The project I had involved in measurement of work done is “CADANGAN

PEMBANGUNAN SATU BLOK PANGSAPURI SERVIS 23 TINGKAT (412

UNIT) DI ATAS 6 TINGKAT PODIUM TEMPAT LETAK KERETA YANG

MENGANDUNGI KOLAM RENANG DAN KEMUDAHAN DI ATAS LOT 944

& 2733, MUKIM PETALING, WILAYAH PERSEKUTUAN KUALA LUMPUR.

(RESIDENCY V)" Measurement of work done is a technique to establish the time

for an average worker to carry out the task. There are several trades of the

measurement of work done for payment is applied in Residency V such as skim coat,

plaster, render, corner bead, brick and floor screed.

Figure 2.2.1Measurement of Work done in Microsoft Excel

During the 26 weeks of Industrial Training, I was assigned to carry out this

task for 6 months. The task is required to carry out in the beginning of 15 days of the

month. I was assigned to measure the quantity of work done of skim coat, plaster,

brick, render, floor screed, corner bead and marking. There were quite numbers of

Page 19: QS Industrial Training Report - CHUA CHONG LIANG 1104838

group of sub-contractors on plaster, brick, render, skim coat and corner bead and

marking in Residency V project. For the first month of doing measurement of work

done, I was guided by my supervisor for the whole month. Measuring the quantity of

work done required measuring tape; the quantity of work done measured by sub-

contractor will be recorded down and the location of the quantity of work done

measured will be stated in order to prevent confusion when doing conversion.

Besides recording down the quantity of work done measured, the quantity of work

done measured also need to be ensured. Then, the quantity of work done measured

will be converting into Microsoft Excel file form. For floor screed, plaster, skim coat

and render will be in unit of area, bricks will be in unit of number and for corner

bead will be in unit of length. After the conversion of measurement of work done is

done, the file will be handled to my supervisor to do the checking. After that, it will

be sent to head quarter in order to allow the quantity surveyor to produce Interim

Certificate for the release of payment to the sub-contractors.

Throughout the process of measuring quantity of work done, I had learnt that

there are many types of plaster, corner bead, floor screed and render. As for plaster,

there are smooth plaster and rough plaster; same goes to floor screed and render. For

rough plaster and rough render, normally will be used on external; for the smooth

plaster and smooth render are for internal use. Rough floor screed is normally used

when the area is needed to be tiled and smooth floor screed is for receiving parquet.

As for corner bead and marking, corner bead is applied not only the edge of the wall;

it can be applied on circumference of windows and doors. There are also certain

types of corner bead which can be used as a function of water flow and also for

aesthetic use which I had come across while doing measurement of work done called

C Channel Corner Bead. The function of corner bead is to guide the thickness of the

plaster, render and skim coat should be. Whenever the area of the wall is big,

marking will be applied in the middle of the wall as a guide for the thicknesses.

For the last month of my industrial training, I was assigned to do filling on

the measurement of work done. The purpose of it is to prevent the double

measurement and also act as a reference for checking and knowing which part of the

construction building’s works are done and measured.

Page 20: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.2.2 Horizontal Levelling and Vertical Levelling

The project I had involved in horizontal and vertical levelling checking is

“CADANGAN PEMBANGUNAN SATU BLOK PANGSAPURI SERVIS 23

TINGKAT (412 UNIT) DI ATAS 6 TINGKAT PODIUM TEMPAT LETAK

KERETA YANG MENGANDUNGI KOLAM RENANG DAN KEMUDAHAN DI

ATAS LOT 944 & 2733, MUKIM PETALING, WILAYAH PERSEKUTUAN

KUALA LUMPUR. (RESIDENCY V)" Horizontal Levelling and Vertical Levelling

are technique to level the floor slab horizontality and the wall verticality. The

purpose of having horizontal levelling is to mark the level of thickness of the floor

slab to receive the concrete; after concreting and concrete is cured, floor slab

horizontality checking will be carry out to ensure the horizontal level of the floor

slab is even. As for the vertical levelling, before concreting, wall verticality levelling

checking will be carry out in order to check the verticality of the wall of aluminium

formwork is even.

I was involved on horizontal levelling for a month. The task is carry out

before concreting the residential units. There will be standardized thicknesses for

floor slab to receive the concrete. So, every reading will be drawn on the re-bars and

taped by red tapes to allow the workers to know where the level of the thickness

where the concrete needed to be. After concreting and letting the concrete to cure,

floor horizontality levelling checking is needed to be carry out to ensure the level of

floor slab is even. It is to make sure the height of the wall of next floor is in

accordance. So, every reading will be sprayed beside the re-bars to allow the workers

to know whether to hack the concreted floor slab to lower down the wall of

aluminium formwork for the next level of the floor slab or to add a wood plank to

elevate the wall of aluminium formwork for the next level of the floor slab.

Page 21: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 2.2.2 Setting Up The Laser Level on The Marking Line

After that, I was assigned fully on doing vertical levelling or wall verticality

levelling checking. The task is carry out before concreting the residential units. The

instrument used for vertical levelling is Laser Level. There will be line markings on

the floor; it is to allow the workers to know where the standardized point for the wall

of aluminium formwork to be installed and before the point, there will be gaps and

lines. The length of the gaps is 29.5 centimetre. So, the laser level will be placed in

the middle of the line, and then will be turned on and the laser has to be on the line of

the markings. Measuring tape will be used to check if the length of gaps of lower part

of the wall of aluminium formwork and upper part of the wall of aluminium

formwork are even. If so, the wall will be straight. If the lengths of both lower part of

the wall of aluminium formwork and upper part of the wall of aluminium formwork

are not even, I had to order the workers to rectify the wall of aluminium formwork.

Plus or minus 5 millimetre of the reading is acceptable. If the length of the lower part

of the wall of aluminium formwork is 30 centimetres and the length of the upper part

of the wall of aluminium formwork is 29.5 centimetres, it means that the lower part

is slanting in and it will allow the upper part to look like slanting out. So, the prop

that are supporting the lower part of the wall of aluminium formwork has to be

loosen in order to let the formwork to slant out. I had come across plenty of problems

regarding no marking line can be seen and it will be a problem to carry out wall

verticality levelling checking. The marking lines were usually washed off by the rain

Page 22: QS Industrial Training Report - CHUA CHONG LIANG 1104838

water after raining. So, the solution to check whether the verticality of the wall is

straight is by using measuring tape to check the length of the residential unit. If the

length of the upper part of the wall of the aluminium formwork and the length of the

lower part of the wall of the aluminium formwork are the same, it means that the

wall is straight. But, normally plus or minus 5 millimetre is acceptable. There is

another solution to prevent the verticality of the wall for slanting and in case the

marking lines were washed off was to asked the workers to drill holes on the marking

line and install the steel bar, so, when installing the aluminium formwork, the

aluminium formwork will attached on the steel bar and less movement of slanting

will be involved.

Figure 2.2.3The Use of Measuring Tape

Figure 2.2.4 Rectifying The Wall of Aluminium Formwork

Page 23: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.2.3 Preparation of Debit Note

The project I had involved in preparation of debit note is “CADANGAN

PEMBANGUNAN SATU BLOK PANGSAPURI SERVIS 23 TINGKAT (412

UNIT) DI ATAS 6 TINGKAT PODIUM TEMPAT LETAK KERETA YANG

MENGANDUNGI KOLAM RENANG DAN KEMUDAHAN DI ATAS LOT 944

& 2733, MUKIM PETALING, WILAYAH PERSEKUTUAN KUALA LUMPUR.

(RESIDENCY V)" Preparation of Debit Note is a task to prepare a document

regarding debiting the sub-contractor for not following the terms and conditions

which are mentioned in the contract. The purpose of having debit note is to prevent

the same action to happen again and also it act as a warning sign to the sub-

contractor.

Figure 2.2.5 Debit Note

On the fourth month of my industrial training, I was assigned to prepare the

debit note every single week. It was requested by the project manager because due to

too many problems happened on site regarding the sub-contractors are not following

the terms and conditions that stated in the contract. We have form a group on

whatsapps internally for posting photos as evident to debit the sub-contractor for not

Page 24: QS Industrial Training Report - CHUA CHONG LIANG 1104838

following the terms and conditions which are stated in the contract. I had to prepare

the document of debit note according to the format given with the photos taken. The

purpose of this was to give warning to the sub-contractor on not following the terms

and conditions as stated. It is to prevent such action to happen again.

2.2.4 Preparation of Weekly Progress Report

The project I had involved in preparation of weekly progress report is

“CADANGAN PEMBANGUNAN SATU BLOK PANGSAPURI SERVIS 23

TINGKAT (412 UNIT) DI ATAS 6 TINGKAT PODIUM TEMPAT LETAK

KERETA YANG MENGANDUNGI KOLAM RENANG DAN KEMUDAHAN DI

ATAS LOT 944 & 2733, MUKIM PETALING, WILAYAH PERSEKUTUAN

KUALA LUMPUR." Preparation of Weekly Progress Report is a task to update the

progress of the construction project every week. The task of preparing Weekly

Progress Report is mainly prepared for the client use.

Page 25: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 2.2.6 Weekly Progress Report

On the fourth month of my industrial training, I was assigned to prepare

weekly progress report every single week. It was requested by the client. The

purpose of having weekly progress report is to update the client regarding the

progress of the construction project. The contents that needed for weekly progress

report are the progress of the works of structure, mechanical and electrical and

architecture with photos of the building and work done attached. The work required

to site walk the whole construction site and every work done will be recorded down

and photos will be taken. Every Friday, I will spend two to three hours on site

walking the whole construction site, recording down the progress of work done and

taking photos of the work done. After that, everything will be keyed into the

computer as softcopy file; then, it will be emailed to the secretary of the client’s.

Page 26: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.2.5 Work done and Defect Inspection

The project I had involved in work done and defect inspection is “CADANGAN

PEMBANGUNAN SATU BLOK PANGSAPURI SERVIS 23 TINGKAT (412

UNIT) DI ATAS 6 TINGKAT PODIUM TEMPAT LETAK KERETA YANG

MENGANDUNGI KOLAM RENANG DAN KEMUDAHAN DI ATAS LOT 944

& 2733, MUKIM PETALING, WILAYAH PERSEKUTUAN KUALA LUMPUR."

Work done and defect inspection is a task to inspect the work done and defect of one

particular work. The purpose of the task is to check whether the work is done and no

defects; otherwise the defects found needed to be rectify.

Figure 2.2.7 Wire Testing

Figure 2.2.8 Water Flow Testing

Page 27: QS Industrial Training Report - CHUA CHONG LIANG 1104838

On the second month of my industrial training, I was assigned for a task to

replaced one of my colleagues who fell down during work and hurt his knee. He was

on Medical Certificate (MC) as he undergone a surgery on his knee and couldn’t

walk for two months. I was assigned to do the inspection of work done and defect on

the wire and pipe for air-conditioning. The task was to ensure that the work is done

and there were no leakage on the pipe and no tripping on the wire. To check the

water pipes whether is there any leakage, water will be poured on the top of the pipe

and the water will flow through the entire pipe till the end point. If water did not flow

successfully, it means that there is a leakage on the pipe; actions will be taken in

order to rectify it. As for the wire, the wire will be tested by using a component

called clamp meter. The black point and red point will be attached to the different

colour of the wires; if the clamp meter sounds, it means that the wires are tangled and

tripping. I have to inspect every residential unit one by one. If defects were found,

the sub-contractor has to rectify the defect; otherwise the Inspection Document will

not be signed by contractor and the payment will not be released until the work is

done and defects are rectified. Photos of every residential unit will be taken after the

success of inspection to act as an evident of work done and no defects as well as the

signature of the inspection document.

Figure 2.2.9 Water Flow Test Report

Page 28: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.3 Report Achievement of Tasks Set

2.3.1 Measurement of Work Done

Throughout the entire 26 weeks of Industrial Training, I had involved in

Measurement of Work done. During the measurement of work done, the quantity of

the work done measured is required to record down then converting them into

Microsoft Excel file form. For the first time doing measurement of work done, it was

challenging and confusing to me as I had to record down all the quantity of work

done measured and to remember which part the quantity of the work done belongs to

because of the speedy measuring of sub-contractor and the accent of the sub-

contractor who is not local citizen. On the third month of my industrial training, I did

a few mistakes on wrongly converting the quantity of work done measured.

After experiencing a few times of measurement of work done, I overcame the

problems I faced on the first time and improved myself from making mistakes. In

order to ensure the accuracy of the quantity of work done measured, I had to

communicate more with the sub-contractor to gain the communication skills as well

as being alert and focus when recording down the quantity of work done measured.

Every time after I had done with the conversion of the quantity of work done and to

ensure no mistakes will be done again, I do double checking on the conversion of the

quantity of work done before submitting to my supervisor and head quarter.

2.3.2 Horizontal Levelling and Vertical Levelling

I have no issues on horizontal levelling as it was taught during Site Surveying

Classes. As for vertical levelling, I was having trouble on coming up with solutions

to rectify the problems faced due to the lack of experience. The problems that I faced

was that the verticality of the wall of aluminium formwork is not even and it is

slanting in or out and there were no markings seen as it was washed off by rain

water after raining.

Page 29: QS Industrial Training Report - CHUA CHONG LIANG 1104838

After experiencing vertical levelling for months, I had gain the knowledge

and experience on how to solve the problems I faced previously. In order to gain the

knowledge and experience, observing and asking were the keys to improve.

Whenever there are problems, asking is required as you ask senior colleague for

advice on how to solve the problems. When the advice given, observing is very

important in order to know what is wrong with the problem and what to rectify it.

2.3.3 Preparation of Debit Note

I was assigned to prepare the debit note every week. For the first time doing debit

note, I have no idea on how the format of the debit note is going to be and how to

prepare the debit note and I have no clue on what is the purpose of having debit note.

After discussion with my site manager and supervisor, I know the purpose of

having debit note, it is to debit the sub-contractor regarding not following the terms

and conditions stated in the contract and act as a warning to minimize the same

mistake happen again. I was given an example to refer to on preparing debit note. I

read through and study the example and I know the format of the debit note and how

to prepare the debit note.

2.3.4 Preparation of Weekly Progress Report

I was assigned to prepare the weekly progress report every week in order to update

the client on the progress of the construction project. Due to the first time of me

doing the weekly progress report, the contents of first weekly progress report were

too little. Also, during the site walk, I kept left out with the important part of work

that need to include in the report.

After doing it a few times, I know which importance parts that need to be

included. To ensure that I am doing it right, every single time before submitting, I

Page 30: QS Industrial Training Report - CHUA CHONG LIANG 1104838

will let my site manager to scan through if there were no left out. After a few times

of letting my site manager to scan through before submitting, I observe the

importance parts of the work that needed to be include in the progress report. Every

time before site walk, I will write down a lists of work that are required to record

down the progress and take photos of.

2.3.5 Work Done and Defect Inspection

Within the 26 weeks of Industrial Training, I was assigned to inspect the work done

and defect of the wire and pipe of air-conditioning. For the first time of doing the

inspection, I have no clue on what the purpose of it. The inspection is very important

as I am going to be the witness of signing the document of successful inspection.

To know what I am doing for the task, asking and observing is the most

crucial thing to do. I ask my supervisor regarding the purpose of the inspection and

the sub-contractor regarding on how to inspect the work and know if there is defect

or no defect. After sharing and showing, I understand the purpose of the inspection

and I observe the action taken on the wire and pipe when there is defect.

2.4 Limitations and Recommendations

Throughout these 26 weeks of Industrial Training, I had encounter with a few

limitations. The first one would be the limited desktops in the construction site office.

There were only 6 desktops in the construction site office and there were 14 of us

working for the company including trainees. Some of the staffs get to have the

desktop on their table, so, people without desktop will be sharing desktop with the

person with desktop. It is very troublesome when one is working using desktop and

the other one in needs to use the desktop for work for a while in sudden. It would be

very disturbance for the person who is in the process of working using desktop. In

my case, I will need the desktop for preparing measurement of work done for claim,

Page 31: QS Industrial Training Report - CHUA CHONG LIANG 1104838

debit notes and weekly progress report. It is very troublesome for me to share the

desktop with my colleagues who need the desktop all the time, so, in the end, I had to

used my own laptop to do my work. On the other hand, my laptop couldn’t access

the internet, so, I have to copy the files and use my colleagues’ desktop to print the

files. And every time, I had had to check if there is virus from others’ desktops. It is

very inconvenience whenever I need the internet to print the documents and send

emails to the head quarter office. In additions, it was very inconvenience of not

having the drawing’s soft copy files organized. When the construction drawings are

in need to print out or use for taking-off works, it would consume a lot of time to

look for one particular drawing’s soft copy file. So, I had to organized the files and

categorised each of them into different use of purpose and elements, so that, it will be

much easier to access the files when in need out of the blue.

Secondly, it would be the executing of taking-off works. The taking-off

works were executed by using Microsoft Office Excel. There was a lot of taking-off

works required for the project, so, the consumption of time of executing taking-off

works would be longer. Therefore, it is suggested to purchase an efficient taking-off

software to eliminate the time waste and it would take much lesser time on taking-off

works.

Lastly, I sincerely am recommending UTAR to provide more site visitation,

practical classes and assignments that required site visitation. It is to enhance the

imaginations of students towards construction drawings and also more understanding

on how one particular thing is constructed. During the Industrial Training, I was

having hard time on understanding the ways of how one particular work is done. So

in order to understand how one particular thing is constructed, I had to witness on the

work to understand the process of how it is constructed. For example, there are a lot

of pictures or animations of how the tower crane jacking up, students have to

imagine on how it works by seeing it through animation or pictures and sometimes it

is hard to understand by seeing it through them. When it is seen and witnessed on site,

the perception of individual will be changed. At first, I thought the process of jacking

up and upload a new mass of the tower crane is as fast as from the animation I had

seen; I never thought the whole process takes few hours to install 3 masses of the

tower crane.

Page 32: QS Industrial Training Report - CHUA CHONG LIANG 1104838

2.5 Expectation After Graduation and Career

After going through these 26 weeks of Industrial Training, I planned to join the

consultant firm after completing my studies as I undergone my Industrial Training in

a contractor firm. Throughout these 26 weeks of Industrial Training, I was exposed

more in construction phase, on how the process runs. I would love to gain more

knowledge that is related to pre-construction phase, such as call for quotation, cost

estimating, preparing bill of quantities, contractual documents, tendering which are

great deal of tasks that I could have never get the opportunity to learn in construction

phase.

For the next few years’ time after graduating, I would like to spend my time

on overseas’ international consultant firm. Besides of learning the knowledge in pre-

construction phase, I also would like to explore and learn different cultures of the

work ethic towards construction. During my Industrial Training, there was a Korean

supervisor who supervises on the installation of the climbing scaffolding which my

company had purchased from them; I had come across with a few conversations with

the person on sharing his experience, I found out that their work ethic towards

construction is much more crucial compared to our own local’s.

Besides, I hope to involve myself to various types of project such as

infrastructure, factory, hospital, in order to enrich my experience and knowledge as

there are so much differences and requirements when constructing different types of

project.

Page 33: QS Industrial Training Report - CHUA CHONG LIANG 1104838

CHAPTER 3

3 MONTLY REPORT

3.1 Month 1 – June 2015

The first day of working in Kerjaya Prospek (M) Sdn. Bhd. Kuala Lumpur

construction site located at Old Kland Road, I was first introduced to my supervisor,

then briefing regarding the project presented by supervisor and the basis of safety

and health presented by safety officer. The briefing of the project was about the

current progress of the construction project, drawings of the project and the

organization chart of the project. Later on, safety officer brief about the precaution

and rules and regulations of the safety and health. The precaution and rules and

regulations of the safety and health are required to be followed; otherwise penalty

and action will be taken. I was provided with safety helmet, safety vest and safety

boots.

I was informed that every Monday morning will be having site walk with

client, project manager, site manager, staffs and sub-contractors. After that, site

meeting will be carry on regarding the process of the project and any problems or

issues and difficulties faced on site. So the first day, I had to attend the meeting. It

was totally new to me as I had never attended a meeting before. So, it was an

opportunity for me to experience and learn. Observing and asking are the most

important actions to do in site, so, we can know what is happening and had happened.

The first day of attending the site meeting, I had no clue on what they were talking

about as I was still new to everything but what I did observe is the way of how they

manage and clearing the problems.

Page 34: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 3.1.1Site Walk

On the first day of working, I was assigned to do measurement of the work

done of skim coat with the sub-contractor in order to verify the claim on site. I never

expected the measurement of work done was done with measuring the completed

work using measuring tape on site, and then the quantity will be recorded down and

converted into Microsoft Excel file form in order to produce the measurement of

work done in Microsoft Excel file form. It was quite challenging for me as I need to

know what I am recording down, every quantity is required to record down and state

which type of particular material and particular location. After that, the measurement

of work done will be sent to the Head Quarter in order to let the quantity surveyor to

produce the Interim Certificate to allow the release of payment to sub-contractors. Of

course, I was guided throughout the work for a month by my supervisor to prevent

me from getting cheated on the quantity of the measurement of work done as I was

new to the work. I was guided throughout every measurement of work done. There

were quite numbers of measurement of work done which are skim coat, plaster,

render, brick, corner bead and marking. I was informed that measurement of work

done is needed to be done on the beginning of 15 days of every month and sent to the

Head Quarter’s quantity surveyor. On week 3, I was asked to follow my supervisor

to the company’s client’s friend’s residential house which is renovating to do

measurement of work done. As I was getting along with doing measurement on

residential apartment, residential house was totally new to me and it is different from

Page 35: QS Industrial Training Report - CHUA CHONG LIANG 1104838

apartment regarding the design; it was very confusing when recording down the

quantity. I had cleared my mind in order to remember which quantity belongs to

which particular part of the house. It took me a week to complete the measurement of

work done. It was quite an experience for me.

On the second day of working, I was assigned to help on doing horizontal

levelling for the floor slab of aluminium formwork of residential units in order to

receive concrete. It was not a problem for me as I had learnt on how to use the

theodolite and measuring rod in Site Surveying classes. There were standardized

thicknesses for concrete. So, every reading will be drawn on the re-bars to allow the

workers to know where the level of the thickness where the concrete needed to be.

On the second week of working, I was assigned to learn vertical levelling which it

was new to me and it was never taught during the Site Surveying classes. I was

assigned to learn the work because I will be taking over the work as there were not

enough staffs for structure work. The purpose of doing vertical levelling was to

check the verticality of the wall of aluminium formwork before concreting to allow

the straightness of the wall. The instrument used for vertical levelling is Laser Level.

There were markings on the floor; it is to allow the workers to know where the

standardized point for the wall of aluminium formwork to be installed and before the

point, there were gaps and lines. The length of the gaps is 29.5 centimetre which

means the gaps of lower part of the wall and upper part of the wall has to be 29.5

centimetre long, so, the wall will be straight. For a month time, I was assigned to tag

along with my colleague in order to learn and know the solutions for rectifying the

problems if the lengths of both lower and upper part of the wall of aluminium

formwork are not evenly.

On the fifth day of working, I was informed that every Friday morning will

be having a safety and health meeting with the site manager, staffs, sub-contractors

and workers regarding the issues that have faced throughout the whole week. I

realised that asking is the key of learning new things; I asked my safety officer

regarding the purpose of having safety and health meeting every Friday morning. I

was told that it was not just to bring out the issues and solving them. It was a

reminder to the workers regarding the precaution and rules and regulations of safety

and health; otherwise penalty and action will be taken, as majority of the workers

Page 36: QS Industrial Training Report - CHUA CHONG LIANG 1104838

was foreigners and hardly know our language. So, it needs to take time to let them to

understand and adapt. What I had observed is that safety officer has the right to stop

work if the workers did not follow the Personal Protective Equipment (PPE) and the

precaution and rules and regulations of safety and health. Every Friday before the

safety and health meeting finish, a few workers from every sub-contractor’s group

need to volunteer to do housekeeping for the construction site to keep the cleanliness

of the construction site.

Figure 3.1.2 Safety and Health Meeting

On week 2, I was assigned by my supervisor to do taking-off works of the

floor area, wall area and beam area of the aluminium formwork of residential units,

corridor, lift lobby and staircases for the measurement of work done of aluminium

formwork for the next month’s use. Every quantity will be recorded down and

converted into Microsoft Excel file form. Nevertheless, miscellaneous work like

printing, photocopying, scanning and filling is expected task for a trainee. Usually,

trainee will have to involve in miscellaneous work throughout their industrial

training. I was assigned to do photocopying delivery order and printing the photos

taken of the material delivered and attached both together in order to tally the actual

Page 37: QS Industrial Training Report - CHUA CHONG LIANG 1104838

delivery order and it shows as an evidence that the materials have delivered to the

site.

3.2 Month 2 – July 2015

At the beginning of this month, I was assigned with the same job, measurement of

work done by my supervisor but the difference of the task for this month was that I

will no longer be guided by my supervisor on measurement of work done on site

with sub-contractor but of course, anything happened or things that unfamiliar to me,

I am allowed to ask and seek for advice from my supervisor. I see this as an

opportunity on how independent I am towards working. I make sure I am cautious

and alert enough while doing the task and also it will allow me to improve my

communication skills on communicate with sub-contractors. I had recorded down the

quantity of work done and stated which location the quantity of work done belongs

to; other than recording and stating, I have to ensure the quantity with the sub-

contractor. The task went well for this month, I did ask and seek for advice from my

supervisor whenever I felt there were something wrong with the quantity and

measurement. I was assigned to do measurement of work done of skim coat, brick,

plaster, render and corner bead and marking.

As for the horizontal levelling task assigned, the task was carried out as usual.

But one extra task on horizontal levelling were assigned which is floor horizontality

levelling checking. After concreting and letting the concrete to cure, floor

horizontality levelling checking is needed to be carrying out to ensure the level of

floor slab is even. The purpose of doing this is to make sure the height of the wall of

next floor is in accordance. So, every reading will be sprayed beside the re-bars to

allow the workers to know whether to hack the concreted floor slab to lower down

the wall of aluminium formwork for the next level of the floor slab or to add a wood

plank to elevate the wall of aluminium formwork for the next level of the floor slab.

After 5 weeks of doing horizontal levelling and floor horizontality levelling checking,

I was assigned fully on doing vertical levelling or wall verticality levelling checking,

the task was carried out as usual too. But, this time round I had a little bit of

Page 38: QS Industrial Training Report - CHUA CHONG LIANG 1104838

experience on solving the problems faced. Still, I seek for advice whenever I couldn’t

solve the problems from my colleagues.

I was assigned for a task to replaced one of my colleagues who fell down

during work and hurt his knee. He was on Medical Certificate (MC) as he undergone

a surgery on his knee and couldn’t walk for two months. I had no choice to take the

task. The task was Work done and Defect Inspection. I was assigned to do the

inspection of work done and defect on the wire and pipe for air-conditioning. The

task was to ensure that the work is done and there were no leakage on the pipe and

no tripping on the wire. I have to inspect every residential unit one by one. If defects

were found, the sub-contractor has to repair the defect; otherwise the Inspection

document will not be signed by contractor and the payment will not be released until

the work is done and defects are repaired. Photos of every residential unit will be

taken after the success of inspection to act as an evident of work done and no defects

as well as the signature of the inspection document.

On this month, there were quite a few presentations of the material presented

by the supplier. There are water proofing presentation and adhesive tilling

presentation. The presentation was arranged by the head quarter office to allow us to

understand the use of product for the particular work. The presentations were all

about the proper way of installing them and explaining the types of materials used to

produce the product and the purpose use of different types of product. Nevertheless,

I was assigned to do miscellaneous work by photocopying delivery order and

printing the photos taken of the material delivered and attached both together in order

to tally the actual delivery order and it shows as an evidence that the materials have

delivered to the site.

Page 39: QS Industrial Training Report - CHUA CHONG LIANG 1104838

3.3 Month 3 – August 2015

I was assigned with the same job, measurement of work done on site with sub-

contractor by my supervisor. I continue on being cautious and alert while doing the

task of recording down the quantity of measurement of work done. I had recorded

down the quantity of measurement of work done and stated which location the

quantity of measurement of work done belongs to; other than recording and stating, I

have ensured the quantity with the sub-contractor. The task did not really go well for

this month, as I was informed that the quantity of measurement of work done of

corner bead and marking was not tally and found out that the conversion on every

quantity of measurement of work done were wrongly converted. So, the solution to

solve the problem was to rechecking on the conversion on every quantity of

measurement of work done from metre to feet or metre square to feet square. I did

ask and seek for advice from my supervisor whenever I felt there were something

wrong with the quantity and measurement. I was assigned to do measurement of

work done of skim coat, brick, plaster, render and corner bead and marking. On week

12, I was assigned to do the measurement of work done of client’s friend’s

residential house. I had recorded down the quantity of measurement of work done

and stated which location the quantity of measurement of work done belongs to;

other than recording and stating, I have ensured the quantity with the sub-contractor.

After the incident, I became more alert and focus than before while doing the

converting of the quantity of measurement of work done.

As I mentioned that I was assigned fully on doing vertical levelling or wall

verticality levelling checking, the task was carried out as usual. Now, I had more

experience on solving the problems faced. Still, I seek for advice whenever I couldn’t

solve the problems from my colleagues. The purpose of doing vertical levelling was

to check the verticality of the wall of aluminium formwork before concreting to

allow the straightness of the wall. The instrument used for vertical levelling is Laser

Level. I have to ensure that the wall of aluminium formworks is installed in

accordance the marking line and the length of the gaps is 29.5 centimetre which

means the gaps of lower part of the wall and upper part of the wall has to be 29.5

centimetre long, so, the wall will be straight. I had come across plenty of problems

regarding no marking line can be seen, so, it will be a problem to carry out wall

Page 40: QS Industrial Training Report - CHUA CHONG LIANG 1104838

verticality levelling checking. Usually, the marking lines were washed off by the rain

water after raining. The solution to check whether the verticality of the wall is

straight is to use measuring tape to check the length of the residential unit. If the

length of the upper part of the wall and the length of the lower part of the wall are the

same, it means that the wall is straight. But, normally plus or minus 5 millimetre is

acceptable. After a few discussions with my colleagues, we came out with a solution

of preventing the verticality of the wall for slanting and in case the marking lines

were washed off. We asked the workers to drill holes on the marking line and install

the steel bar, so, when installing the aluminium formwork, the aluminium formwork

will stick on the steel bar and less movement of slanting will be involved.

I was assigned for a task to replaced one of my colleagues who fell down

during work and hurt his knee. He was on Medical Certificate (MC) as he undergone

a surgery on his knee and couldn’t walk for two months. So, this is the second month

of doing the task. The task was Work done and Defect Inspection. I was assigned to

do the inspection of work done and defect on the wire and pipe for air-conditioning.

The task was to ensure that the work is done and there were no leakage on the pipe

and no tripping on the wire. I have to inspect every residential unit one by one. If

defects were found, the sub-contractor has to repair the defect; otherwise the

Inspection document will not be signed by contractor and the payment will not be

released until the work is done and defects are repaired. Photos of every residential

unit will be taken after the success of inspection to act as an evident of work done

and no defects as well as the signature of the inspection document. Furthermore, I

was assigned to do miscellaneous work by photocopying delivery order and printing

the photos taken of the material delivered and attached both together in order to tally

the actual delivery order and it shows as an evidence that the materials have

delivered to the site. As for this month, the client has requested on having consultant

meeting every 2 weeks. After the consultant meeting, the site meeting will be carry

on. So, for the consultant meeting, progress report is needed. I was assigned on

filling the progress report. While doing the filling of progress report, I have to know

the contents of the progress report.

Page 41: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 3.3.1Housekeeping

As for this month, it was quite an interesting month for me. I personally think

that it is quite a rare chance for a trainee to experience stop work in construction site.

On week 11, we were informed by Dewan Bandaraya Kuala Lumpur (DBKL)

regarding the stop work for 2 weeks’ time. The reason of stop work was the

mosquito larvae found in our site and the cleanliness of the construction site was not

up to the standard. After being noticed, staff internal meeting was quickly held and

discussion on the housekeeping. After that, every sub-contractors and workers on site

were informed for the safety and health meeting regarding the issue of stop work and

housekeeping for a week. I was assigned to supervise a group of workers to clean up

the area assigned. During this period of time, I learnt on how to get along with the

workers and communicating with them and giving orders. Leadership skills and

teamwork were developed throughout this period of time. After a week, safety

officer send a request to Dewan Bandaraya Kuala Lumpur (DBKL) for allowing

continuing on construction work. I was told that the safety and health report and

inspection are needed in order to grant us on continuing on construction work. So

after everything was done, we were granted to continue the construction work. It was

a pleasant experience throughout this week.

Page 42: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Figure 3.3.2 Release of Start Work by DBKL

3.4 Month 4 – September 2015

As measurement of work done is required every month, I continue on doing the task.

I continue on being cautious and alert while doing the task of recording down the

quantity of measurement of work done. I had recorded down the quantity of

measurement of work done and stated which location the quantity of measurement of

work done belongs to; other than recording and stating, I have ensured the quantity

with the sub-contractor. After completing the measurement of work done, I do

checking on the conversion of every quantity of measurement of work done from

metre to feet or metre square to feet square before sending the measurement of work

done to head quarter. It is to ensure that there will be no mistake. I still continue on

asking and seeking for advice from my supervisor whenever I felt there were

something wrong with the quantity and measurement. I was assigned to do

measurement of work done of skim coat, brick, plaster, render and corner bead and

marking. As for this month, there were a few groups of new sub-contractors on doing

skim coat and corner bead. So there will be more measurement of work done for me

to do.

Page 43: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Besides, I continue on doing vertical levelling or wall verticality levelling

checking, the task was carried out as usual. I still seek for advice whenever I couldn’t

solve the problems from my colleagues. I continue on checking the wall verticality

levelling to ensure that the wall of aluminium formworks is installed in accordance

the marking line and the length of the gaps is 29.5 centimetre where the gaps of

lower part of the wall and upper part of the wall has to be 29.5 centimetre long, so,

the wall will be straight. Normally plus or minus 5 millimetre of the actual length is

acceptable. I also do check on the workers to ensure that they drilled the holes on the

marking line and installed the steel bar, so, when installing the aluminium formwork,

the aluminium formwork will stick on the steel bar and less movement of slanting

will be involved.

Furthermore, I was still assigned on doing miscellaneous work by

photocopying delivery order and printing the photos taken of the material delivered

and attached both together in order to tally the actual delivery. As progress report is

required every 2 weeks, I continue on helping to do filling on the progress report

twice a month. After a few times of filling progress report, I am familiar with the

contents needed in the progress report. The contents of the progress report are project

summary, progress report, Architect’s/ Engineer’s Instructions, master works

programme, organization chart, list of construction drawings issued to-date, request

for information, cube test summary, sub-contractor’s tradesman record, sub-

contractor’s plant/ machinery record, weather and progress photos.

As for this month, I was assigned with two new tasks which are the

preparation of debit note and preparation of weekly progress report. Both tasks are

needed to be completed every single week. We have form a group on whatsapps

internally for posting photos as evident to debit the sub-contractor for not following

the terms and conditions which are stated in the contract. I had to prepare the

document of debit note with the photos taken. The purpose of this was to give

warning to the sub-contractor on not following the terms and conditions as stated. It

is to prevent such action to happen again. As for the preparation of weekly progress

report, I was informed that it was requested from the client. The purpose of it is to

update the client every single week on the progress of the construction work. Photos

of every work done and the progress of the work done in word form are required to

Page 44: QS Industrial Training Report - CHUA CHONG LIANG 1104838

include in the weekly progress report. And then, it is to be sent to client’s secretary’s

email.

Figure 3.4.1 Summary of Debit Note

3.5 Month 5 – October 2015

As measurement of work done is required every month, I still continue on doing the

task. I continue on being cautious and alert while doing the task of recording down

the quantity of measurement of work done. I had recorded down the quantity of

measurement of work done and stated with the location the quantity of measurement

of work done belongs to; other than recording and stating, I have to ensure that the

quantity is right with the sub-contractor. After completing the measurement of work

done, I do checking on the conversion of every quantity of measurement of work

done from metre to feet or metre square to feet square before submitting the

measurement of work done to head quarter. I still continue on asking and seeking for

advice from my supervisor whenever I felt there were something wrong with the

quantity and measurement. As for this month, a group of new sub-contractor joined

the project on doing floor screed. I was informed what to do for the measurement of

work done of floor screed by my supervisor. In one residential unit, floor of toilet,

kitchen and door step were considered as rough floor screed and the rest will be

smooth floor screed. Rough floor screed will be measured on site with sub-contractor

Page 45: QS Industrial Training Report - CHUA CHONG LIANG 1104838

using measuring tape; the dimension will be recorded down in order to produce the

measurement of work done on rough floor screed. As for smooth floor screed, the

quantity will be measured by taking-off works then convert the quantity of the

measurement of work done into Microsoft Excel file form. I was assigned to do

measurement of work done as usual including floor screed.

Besides, I still continue on doing vertical levelling or wall verticality

levelling checking, the task was carried out as usual. As for this month, I was

informed to guide the new staff and trainee on doing vertical levelling and I will not

be handling the task for next month. So, as for this month, I tagged along with the

new staff and trainee in order to guide them on what they should know about the wall

verticality levelling and what they should do when facing the similar problem. I

advise them to do checking on the workers often, to ensure that the workers drilled

the holes on the marking line and installed the steel bar, so, when installing the

aluminium formwork, the aluminium formwork will stick on the steel bar and less

movement of slanting will be involved.

Furthermore, I was still assigned on doing miscellaneous work by

photocopying delivery order and printing the photos taken of the material delivered

and attached both together in order to tally the actual delivery. As progress report is

required every 2 weeks, I continue on helping to do filling on the progress report

accordingly twice a month.

Nevertheless, the preparation of debit note and weekly progress report are

prepared every single week. Every photos of the sub-contractor of not following the

terms and conditions that stated in the contract will be posted in the group on

whatsapp. Then, I had to go to the group on whatsapp to seek for the photos in order

to prepare the document of debit note with the photos taken. As for the preparation of

weekly progress report, the task is carrying out as usual. Photos of every work done

will be taken by me and attached in the weekly progress report with the progress of

the work done in word form. And then, it is to be sent to client’s secretary’s email.

Page 46: QS Industrial Training Report - CHUA CHONG LIANG 1104838

3.6 Month 6 – November 2015

As the beginning of 15 days of every month, measurement of work done is required

to be done and sent to the head quarter to allow the quantity surveyor to produce

Interim Certificate for the release of the payment of sub-contractor. I am doing the

task as usual, recording down the quantity of measurement of work done and stating

the location the quantity of measurement of work done belongs to and ensuring that

the quantity is right with the sub-contractor. Every quantity of the measurement of

work done will be converted into Microsoft Excel file form. Checking on the

conversion of every quantity of measurement of work done from metre to feet or

metre square to feet square will be done before submitting the measurement of work

done to head quarter. I was assigned to do measurement of work done of skim coat,

corner bead and marking, plaster, render, brick and floor screed.

I am not longer in charge of doing vertical levelling or wall verticality

levelling checking for this month. The task was carried out by my colleagues who

joined the company last month. I was still assigned on doing miscellaneous work by

photocopying delivery order and printing the photos taken of the material delivered

and attached both together in order to tally the actual delivery. As progress report is

required every 2 weeks, I continue on helping to do filling on the progress report

accordingly twice a month. Nevertheless, the preparation of debit note and weekly

progress report are prepared every single week. Both of the tasks are carried out as

usual and accordingly.

As this month is the last month of my industrial training, I was assigned to do

miscellaneous work by filling all the debit notes and measurement of work done by

monthly. The purpose of doing the filling of debit notes and measurement of work

done was for the reference use; in case anything happen or documents went missing,

the records are able to trace back. Besides, I was assigned to do presentation slides

regarding the progress of the construction project for my site manager which is

needed for the head quarter’s meeting use which is held once a month. Records on

the weekly progress will be converted into chart form. Photos of the work done will

be needed for the presentation slides as well as the information of the organizations

involved in the construction project.

Page 47: QS Industrial Training Report - CHUA CHONG LIANG 1104838

CHAPTER 4

4 CONCLUSION

4.1 Summary

Throughout these 26 weeks of time in Kerjaya Prospek (M) Sdn. Bhd., it was a

pleasant memory. I had encountered many things I never before and learnt

uncountable knowledge related to construction industry. I observed that there were

no limits on learning; every single time, things will keep on changing to adapt the

new technology in order to keep up with the society and also different solutions will

be used in order to solve the problem and not every day the problems will be the

same. Besides, I acknowledge that without good responsibility, discipline, whole

heartedness and right attitude and character, no matter how big or small the task is,

we will never do it the right way. Also, instead of just the knowledge related to

construction industry gained, I also developed good communication skill, leadership

skill and teamwork.

4.1.1 Apply and Link the Theoretical Knowledge to Solve the Problem in

Practice

After going through these 26 weeks of Industrial Training, the knowledge that I had

learnt from the lecture class were useful when it come in handy to apply them to

solve the problem in practice, such as Measurement, Site Surveying (Horizontal

Levelling) and Building Material. All these knowledge were enhanced during the

Page 48: QS Industrial Training Report - CHUA CHONG LIANG 1104838

Industrial Training period. Measurement, I was able to solve some part of the

drawings using the knowledge that I had learnt during the practical class: but some

part of the drawings were too complicated that I had to seek for guidance from my

supervisor and it helps me to open wide my eyes on understanding and reading the

drawings and solving them. Site Surveying (Horizontal Levelling), second day of my

industrial training, I was assigned to do horizontal levelling on the floor formwork to

receive concrete which I was able to do it because I was taught during Site Surveying

classes. After a while, I was assigned to vertical levelling which is totally new to me

and I learn in how to do the task. Building Material, there were a few building

materials I had learnt from the class and I was able to apply them during the work but

there were a lot of unknown building materials were not taught in class, so, I had to

learn the names of the building material in order to be able to give instruction on

work.

4.1.2 Demonstrate Technical Competence in QS Technical Competence

There were new things learnt during the 26 weeks of Industrial Training which I

could never learn in lecture class. I was assigned to do measurement of work done to

produce claim in Microsoft Excel form. The process and purpose of doing

measurement of work done were explained by my supervisor. Payment is crucial for

the sub-contractor, so the measurement of work done has to be submitted on time

with accurate amount to precede the release of Interim Certificate. Moreover, doing

vertical levelling checking has to be crucial; otherwise the verticality of the wall will

not be even after concreted. Nevertheless, weekly progress report task was assigned

to me and explained by supervisor that it is essential to update the client weekly on

the progress of the project.

Page 49: QS Industrial Training Report - CHUA CHONG LIANG 1104838

4.1.3 Develop Emotional Intelligent and Auxiliary Skills

I had come to a realisation of the importance of communication skill which allows us

to widen our social network that may assist us in future as well as the way we

communicate; it may bring different interpretation of others’. Leadership skill and

Teamwork are also crucial when it comes to work as a team, without either one of

them, there will be no purpose and goal to attain and mistake will be easily formed

which may cause a failure to the work.

4.2 Concluding Remarks

In conclusion, these 26 weeks of Industrial Training is able to let the students to

understand and experience what real working life is and also to build up the

interpersonal skill. It also enables students to be more understandable on the roles of

quantity surveyor in construction industry.

Page 50: QS Industrial Training Report - CHUA CHONG LIANG 1104838

REFERENCES

Page 51: QS Industrial Training Report - CHUA CHONG LIANG 1104838

APPENDICES

APPENDIX A: Log Book

Page 52: QS Industrial Training Report - CHUA CHONG LIANG 1104838

APPENDIX B: Area of Work Involvement Summary

Page 53: QS Industrial Training Report - CHUA CHONG LIANG 1104838