OVERALL LOCATION PLAN - SPACES RELOCATION A COLLEGE AVENUE WEST SMITH LANE Surgery Anesthesia Medical Records Office BLDG#046 SPD Graduate Students Ultrasound Endo- -scopy Therio Large Animals Imaging BLDG#049 BLDG#044 BLDG#040 BLDG #077 BLDG #003 BLDG#039 BLDG #047 BLDG#183 BLDG#045 BLDG#046 BLDG#049 BLDG#183 BLDG#044 BLDG #003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom GRADUATED STUDENTS SPD LEARNING ANESTHESIA KEY: •Offices/Meeting •Graduate Students Cubicles •Medical Records Offices •Medical Records Files MEDICAL RECORDS ULTRASOUND OFFICES L.A. IMAGING THERIO CORRIDOR C1443 •Medical Records Office •Medical Records Files ENDOSCOPY C1443 Water Entry Elec.&IT PROPOSED PROJECT FIRST FLOOR PROPOSED PROJECT SECOND FLOOR 1 1 2 2 2 4+5 3 3 7 7 7 PANEL NUMBER n SURGERY 6

PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

OVERALL LOCATION PLAN - SPACES RELOCATION ACOLLEGE AVENUE WEST

SMIT

H L

ANE

SurgeryAnesthesia

Medical RecordsOffice

BLDG#046

SPD

Graduate Students

UltrasoundEndo--scopy

Therio

LargeAnimalsImaging

BLDG#049

BLDG#044

BLDG#040

BLDG#077

BLDG#003

BLDG#039

BLDG#047

BLDG#183BLDG#045

BLDG#046

BLDG#049

BLDG#183

BLDG#044

BLDG#003

BLDG#039

BLDG#047

BLDG#045

BLDG#077

BLDG#040

TemporaryClassroom

Medical RecordsFiles

Offices/Meeting

•Temporary Large Classroom

GRADUATEDSTUDENTS

SPD LEARNING ANESTHESIA

KEY:

•Offices/Meeting•Graduate Students Cubicles

•Medical Records Offices•Medical Records Files

MEDICAL RECORDS ULTRASOUND OFFICES L.A. IMAGING THERIO CORRIDOR C1443

•Medical Records Office•Medical Records Files

ENDOSCOPY

C1443

Water Entry

Elec.&IT

PROPOSED PROJECTFIRST FLOOR

PROPOSED PROJECTSECOND FLOOR

1 1 2 2 2 4+5

3 3 7 7 7

PANEL NUMBERn

SURGERY6

Page 2: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

OVERALL LOCATION PLAN - PHASES BCOLLEGE AVENUE WEST

SMIT

H L

ANE

SurgeryAnesthesia

Medical RecordsOffice

BLDG#046

SPD

Graduate Students

UltrasoundEndo--scopy

Therio

LargeAnimalsImaging

BLDG#049

BLDG#044

BLDG#040

BLDG#077

BLDG#003

BLDG#039

BLDG#047

BLDG#183BLDG#045

BLDG#046

BLDG#049

BLDG#183

BLDG#044

BLDG#003

BLDG#039

BLDG#047

BLDG#045

BLDG#077

BLDG#040

TemporaryClassroom

Medical RecordsFiles

Offices/Meeting

PHASE 9 PHASE 8

KEY:

Renovation:• Medical Records• Offices/Meetings• Ultrasound• Large Animal Imaging• Graduate Students• Temporary Classroom

Renovation:• Corridor C1443 Relocation

PHASE 3 PHASE 5 PHASE 1 PHASE 4 PHASE 6 PHASE 7

PHASE 10

Demolition:• Building #044 - Existing Radiology, Auditorium, Offices• Building #045 - Existing Surgery

Renovation:• Surgery• Anesthesia (partial)• SPD (partial)

Demolition:• Building #45 - Existing L.A. Surgery, Changeroom

Renovation:• Sterile Processing Department

Building #044Corridor Relocation

Renovation:• Endoscopy• Anesthesia

Demolition:• Building #044 - Existing Sterile Processing Department

PHASE 2Renovation:• Therio

C1443

PROPOSED PROJECTFIRST FLOOR

PROPOSED PROJECTSECOND FLOOR

Page 3: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

OVERALL LOCATION PLAN - WORK PLAN C

PHASE ONE & TWO COMPLETED

J

CONSTRUCTIONSTART

PHASE SIXCOMPLETED

PHASE SEVENCOMPLETED

SPD RELOCATION

PHASE EIGHTCOMPLETED

PHASE THREECOMPLETED

DEPART./ STAFFRELOCATION

PHASE FOUR COMPLETED

PHASE FIVECOMPLETED

PHASE NINECOMPLETED

PHASE TENCOMPLETED

CONSTRUCTIONCOMPLETED

SEPT 12, 2016

OCT 3, 2016

OCT 31, 2016

MAY 8, 2017

SEPT 11, 2017

OCT 9, 2017

MAR 20,2018

SURGERY CHANGERM RELOCATION

APRIL 24, 2017

SEPT 18, 2017

F M A M J J A S O N D J F M A M J J A S O N D J F M2016 2017 2018

JUNE 9, 2016

JUNE 10, 2016

SEPT 13, 2016

OCT 4, 2016

APRIL 17, 2017

MAR 30, 2018

NOV 28, 2016

NOV 6, 2017

NOV 1, 2016

APRIL 25, 2017

MAY 9, 2017

SEPT 19, 2017

NOV 7, 2017

APRIL 18, 2017

SEPT 12, 2017

NOV 29, 2016

OCT 10, 2017

Page 4: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE ONE - MEDICAL RECORD/ADMIN & BUSINESS OFFICES

CONSTRUCTION START : 06 JUNE, 2016

CONSTRUCTION COMPLETION : 12 SEPTEMBER, 2016

DURATION : 9 WEEKS

** DEPARTMENT & STAFF RELOCATION: 13 SEPTEMBER ~ 3 OCTOBER, 2016

LAB #103,#103A, #104 & #104A

LAB #1115,#1115A & #1116

LAB #1116,#1118,#1121,#1122 & #1123

• DEMOLITION PLAN

• RENOVATION PLAN

MEETING BUSINESS OFFICES

MED.RECORD OFFICEMED.RECORDS FILES ADMIN. OFFICES

1

Page 5: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE ONE & PHASE TWO - ULTRASOUND/ L.A.IMAGING/ THERIO

SEMINAR

ULTRASOUND #1429, #1430

LAB#1448

CORRIDOR#C1471

LARGE ANIMAL

IMAGING#1471

ULTRASOUND

THERIO.#1429,#1430

• DEMOLITION PLAN • RENOVATION PLAN

CONSTRUCTION START : 10 JUNE, 2016

CONSTRUCTION COMPLETION : 12 SEPTEMBER, 2016

DURATION : 9 WEEKS* ULTRASOUND COMPLETION: 18 JULY, 2016* ULTRASOUND RELOCATION, RENOVATION START ON THERIO (PHASE 2): 25 JULY, 2016* L.A.I. RELOCATION: 13 SEPTEMBER ~ 03 OCTOBER, 2016

2

#1296

CORRIDOR#C1471

#1296

Page 6: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE ONE - GRADUATE STUDENT CUBICLES & TEMPORARY CLASSROOM

CONSTRUCTION START : 10 JUNE, 2016

CONSTRUCTION COMPLETION : 12 SEPTEMBER, 2016

DURATION : 9 WEEKS

** DEPARTMENT & STAFF RELOCATION : 13 SEPTEMBER ~ 3 OCTOBER, 2016

STUDY ROOM #2660,#2661,

& #2661D

TEMPORARYCLASSROOM

LAB #2115,#2120,#2120B & C2120

GRADUATE STUDENT CUBICLES

• DEMOLITION PLAN_GRADUATE STUDENT CUBICLES

• RENOVATION PLAN_GRADUATE STUDENT CUBICLES

3

• DEMOLITION PLAN_TEMPORARY CLASSROOM

• RENOVATION PLAN_TEMPORARY CLASSROOM

Page 7: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE THREE (partial) - EXISTING OFFICES DEMOLITION

PHASE THREE (PARTIAL)CONSTRUCTION START : 4 OCTOBER, 2016

CONSTRUCTION COMPLETION : 31 OCTOBER, 2016

DURATION : 3 WEEKS

NEWL.A.I.

EXIST.OFFICES

• DEMOLITION PLAN temporary path during demolition

EXIST.RECORDS

EXIST.L.A.

IMAGING

EXIST. AUDITORIUM

EXIST.S.P.D.

4

Page 8: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE THREE & FOUR - CORRIDOR C1443 (partial)/SURGERY/SPD (partial)/ ANESTHESIA (partial)

PHASE THREE TO FOURCONSTRUCTION START : 4 OCTOBER, 2016

CONSTRUCTION COMPLETION : 28 NOVEMBER, 2016

DURATION : 7 WEEKS

NEWL.A.I.

• DEMOLITION PLAN

hoardingtemporary corridor C1443

EXIST.RECORDS

EXIST.L.A.

IMAGING

EXIST. AUDITORIUM

EXIST.S.P.D.

5

Page 9: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE FIVE - CORRIDOR C1443 (partial)/SURGERY/SPD (partial)/ ANESTHESIA (partial)

PHASE FIVECONSTRUCTION START : 29 NOVEMBER, 2016

CONSTRUCTION COMPLETION : 17 APRIL, 2017

DURATION : 18 WEEKS

• RENOVATION PLANhoarding

ANESTHESIA(partial)

EXISTINGS.P.D.

SPD (partial)

LAI

THE-RIO

CORRIDOR C1443 (partial)

* LARGE ANIMAL SURGERY SWITCH-OVER TO NEW WASH/CHANGEROOMS: 24 APRIL, 2017

SURGERY

6

next phase completion area

Page 10: PROPOSED PROJECT - Ontario Veterinary College...#003 BLDG#039 BLDG#047 BLDG#045 BLDG#077 BLDG#040 Temporary Classroom Medical Records Files Offices/ Meeting •Temporary Large Classroom

PHASE SIX TO TEN - SPD/ENDOSCOPY/ANESTHESIA

PHASE SIX TO EIGHTCONSTRUCTION START : 25 APRIL, 2017

CONSTRUCTION COMPLETION : 09 OCT, 2017

DURATION : 10 WEEKS

temporary corridor

ANESTHESIA

• RENOVATION PLAN

EXISTINGS.P.D.

• DEMOLITION PLAN

• RENOVATION PLAN• DEMOLITION PLAN

PHASE NINE TO TENCONSTRUCTION START : 10 OCT, 2017

CONSTRUCTION COMPLETION : 20 MAR, 2018

DURATION : 22 WEEKS

CONSTRUCTION TOTAL PERFORMANCE/OCCUPANCY30 MARCH, 2018

CORRIDOR C1443

ENDOSCOPY

SPD

* CORRIDOR C1443 COMPLETE SWITCH-OVER: 06 NOV, 2017

7

hoarding

* SPD SWITCH-OVER TO NEW AREA: 12 SEP ~ 18 SEPT, 2017