108
PROJECT MANUAL EXPANSION, RENOVATIONS AND SITE IMPROVEMENTS CLASSROOM BUILDING ADDITION BID SUBMITTAL & POD RENOVATION SUBMITTAL NEASE HIGH SCHOOL ST. AUGUSTINE, FLORIDA FOR THE ST. JOHNS COUNTY SCHOOL DISTRICT PROJECT NO. 2015-30 JUNE 10, 2016 MARCH 30 2017, Pod Renovation Submittal ARCHITECT 10199 SOUTHSIDE BLVD., SUITE 103 JACKSONVILLE, FL 32256

PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

  • Upload
    lyhanh

  • View
    219

  • Download
    2

Embed Size (px)

Citation preview

Page 1: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

PROJECT MANUAL

EXPANSION, RENOVATIONS AND

SITE IMPROVEMENTS

CLASSROOM BUILDING ADDITION

BID SUBMITTAL &

POD RENOVATION SUBMITTAL

NEASE HIGH SCHOOL

ST. AUGUSTINE, FLORIDA

FOR THE

ST. JOHNS COUNTY

SCHOOL DISTRICT

PROJECT NO. 2015-30

JUNE 10, 2016

MARCH 30 2017, Pod Renovation Submittal

ARCHITECT

10199 SOUTHSIDE BLVD., SUITE 103

JACKSONVILLE, FL 32256

Page 2: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

TOC - 1

TABLE OF CONTENTS

Section Title

Specification sections edited or added for the Pod Renovation GMP and/or Phase 2 Sitework

Submittal, dated March 30 2017, are in bold font.

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 07 Seals Page

DIVISION 01 - GENERAL REQUIREMENTS

Provided by Construction Manager at Risk.

DIVISION 02 - EXISTING CONDITIONS

Not Applicable

DIVISION 03 - CONCRETE

03 30 00 Cast-in-Place Concrete

03 47 13 Tilt-Up-Concrete

DIVISION 04 - MASONRY

Not Used

DIVISION 05 - METALS

05 12 00 Structural Steel Framing

05 21 00 Steel Joist Framing

05 31 00 Steel Decking

05 40 00 Cold-Formed Metal Framing

05 50 00 Metal Fabrications

05 51 13 Metal Pan Stairs

05 58 13 Columns Covers (added by ASI-8)

05 73 00 Decorative Metal Railings

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 53 Miscellaneous Rough Carpentry

06 41 16 Plastic-Laminate-Faced Architectural Cabinets

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 17 00 Bentonite Waterproofing

07 18 00 Traffic Coatings

07 21 00 Thermal Insulation

07 22 00 Lightweight Insulated Concrete Roof Insulation

07 24 19 Water-Drainage Exterior Insulation and Finish System (EIFS)

07 52 16 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing

07 62 00 Sheet Metal Flashing and Trim

07 72 00 Roof Accessories

07 84 13 Penetration Firestopping

07 92 00 Joint Sealants

07 95 00 Expansion Joint Covers

Page 3: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

TOC - 2

TABLE OF CONTENTS

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors And Frames

08 14 16 Flush Wood Doors

08 31 13 Access Doors and Frames

08 33 13 Coiling Counter Doors (section added for Pod Renovation Submittal,

dated Mar. 30, 2017)

08 41 13 Aluminum-Framed Entrances And Storefronts

08 44 23 Structural-Silicone-Glazed Curtain Walls

08 71 00 Door Hardware (section edited by the addition of Hardware Groups for

Pod Renovation Submittal, dated Mar. 30, 2017)

08 80 00 Glazing

08 88 13 Fire-Resistant Glazing

08 91 19 Fixed Louvers

DIVISION 09 - FINISHES

09 05 61.13 Moisture Vapor Emission Control

09 22 16 Non-Structural Metal Framing

09 25 13.13 Direct Applied Exterior Finish System

09 29 00 Gypsum Board

09 30 13 Ceramic Tiling

09 51 13 Acoustical Panel Ceilings

09 65 13 Resilient Base And Accessories

09 65 16 Hybrid Resilient Sheet Flooring

09 65 19 Resilient Tile Flooring and Stair Accessories

09 65 43 Linoleum Flooring

09 91 13 Exterior Painting

09 91 23 Interior Painting

09 96 00 High Performance Coatings

09 97 26 Cementitious Coatings

DIVISION 10 - SPECIALTIES

10 11 00 Visual Display Units

10 14 19 Dimensional Letter Signage

10 14 23.13 Room-Identification Signage

10 21 13.19 Plastic Toilet Compartments

10 21 23 Cubicle Curtains and Track

10 22 39 Folding Panel Partitions

10 26 13 Corner Guards

10 28 00 Toilet, Bath, and Laundry Accessories

10 44 13 Fire Protection Cabinets

10 44 16 Fire Extinguishers

10 51 13 Metal Lockers (section edited by the addition of Varsity Lockers for

Pod Renovation Submittal, dated Mar. 30, 2017)

10 51 23 Phenolic Lockers

10 73 00 Pre-Engineered Aluminum Protective Covers

DIVISION 11 - EQUIPMENT

Not Applicable

DIVISION 12 – FURNISHINGS

Page 4: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

TOC - 3

TABLE OF CONTENTS

12 21 13 Horizontal Louver Blinds

12 36 61.16 Solid Surfacing Countertops

12 36 61.19 Quartz Agglomerate Countertops

DIVISION 13 - SPECIAL CONSTRUCTION

Not Applicable

DIVISION 14 - CONVEYING EQUIPMENT

14 24 00 Hydraulic Elevators

DIVISION 21 - FIRE SUPPRESSION

21 13 00 Fire Suppression Systems – Performance Based

DIVISION 22 - PLUMBING

22 05 00 Common Work Results for Plumbing

22 05 10 Basic Materials and Methods for Plumbing System

22 05 23 General-Duty Valves for Plumbing Piping

22 05 29 Hangers and Supports for Plumbing Piping and Equipment

22 05 53 Identification for Plumbing Piping and Equipment

22 07 00 Plumbing Insulation

22 11 16 Domestic Water Piping

22 11 19 Domestic Water Piping Specialties

22 11 23 Domestic Water Pumps

22 13 16 Sanitary Waste and Vent Piping

22 13 17 Rain Leader Piping

22 13 19 Sanitary Waste Piping Specialties

22 14 23 Storm Drainage Piping Specialties

22 14 29 Sump Pumps

22 33 00 Electric, Domestic Water Heaters

22 42 00 Plumbing Fixtures and Trim

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

23 05 00 Common Work Results for HVAC Systems

23 05 10 Basic Materials and Methods for HVAC Systems

23 05 13 Motor Requirements for HVAC Equipment

23 05 17 Adjustable Frequency Drives

23 05 18 Control Wiring

23 05 19 Meters, Gages and Accessories for HVAC Piping

23 05 23 General-Duty Valves for HVAC Piping.

23 05 29 Hangers and Supports for HVAC Systems

23 05 48 Vibration and Seismic Controls for HVAC

23 05 53 Identification for HVAC Piping and Equipment

23 05 80 Air Controls and Accessories

23 05 93 Testing, Balancing and Commissioning of HVAC Systems

23 07 00 Insulation

23 09 23 Instrumentation and Control Devices for HVAC

23 09 93 Sequence of Operations for HVAC Controls

23 21 13 Hydronic Piping

23 21 13.13 Underground Hydronic Piping

23 23 00 Refrigerant Piping

23 25 00 HVAC Water Treatment

Page 5: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

TOC - 4

TABLE OF CONTENTS

23 31 00 HVAC Ducts and Casings

23 31 01 Shop Fabricated Ductwork

23 33 00 Air Duct Accessories

23 34 00 HVAC Fans

23 36 00 Air Terminal Units – Variable Volume

23 37 13 Grilles, Registers and Diffusers

23 41 00 Particulate Air Filtration

23 44 00 Air Purification System (section added for Pod Renovation Submittal,

dated Mar. 30, 2017)

23 73 00 Packaged Air Handling Units

23 81 43 Ductless Split-System Air Conditioner Unit Air Cooled

23 82 16 Coils

DIVISION 25 - INTEGRATED AUTOMATION

Not Applicable

DIVISION 26 - ELECTRICAL

26 05 00 Basic Electrical Materials and Methods

26 05 19 Conductors and Cables

26 05 26 Grounding and Bonding

26 05 29 Hangers and Supports for Electrical Systems

26 05 33 Raceways and Boxes

26 05 53 Electrical Identification

26 22 00 Dry Type Transformer

26 24 16 Panelboards

26 24 20 Enclosed Controllers

26 24 41 Switchboards

26 25 11 Interior Lighting

26 25 21 Exterior Lighting

26 26 60 Lightning Protection

26 27 26 Wiring Devices

26 28 16 Enclosed Switches and Circuit Breakers

26 43 13 Surge Protective Devices (SPDs)

DIVISION 27 - COMMUNICATIONS

27 51 23 Educational Intercommunications Program System (section edited for

Pod Renovation Submittal dated Mar. 30, 2017)

27 53 00 GPS Clock System

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 05 00 Data, Voice and Video

Attachment: SJCSD Voice and Data Structured Cabling Standards

updated to Version 7, March 2017 version

28 16 00 Intrusion Detection System

28 23 00 Video Surveillance System

28 31 11 Fire Alarm

DIVISION 31 - EARTHWORK

31 11 00 Clearing, Grubbing, and Stripping

31 15 00 Demolition

31 20 00 Earthwork

Page 6: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

TOC - 5

TABLE OF CONTENTS

31 23 16 Excavation and Backfill for Utilities and Structures

31 23 19 Dewatering System

31 31 16 Termite Control

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 05 24 Concrete Reinforcement

32 05 25 Construction and Expansion Joints

32 12 16 Pavement

32 12 23 Prime and Tack Coats

32 14 13 Brick Paving

32 16 00 Sitework Concrete

32 17 23 Pavement Markings

32 31 13 Chain Link Fence

32 31 16 Welded Wire Fencing and Gates

32 32 23 Concrete Segmental Retaining Wall System (section added for

Phase 2 Sitework Submittal dated Mar. 30, 2017)

32 93 00 Plants

32 92 23 Grassing

DIVISION 33 - UTILITIES

33 11 00 Potable Water Mains

33 31 00 Gravity Sewers

33 40 00 Drainage

END OF TABLE OF CONTENTS

Page 7: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

COILING COUNTER DOORS 083313 - 1

SECTION 083313 - COILING COUNTER DOORS (Pod J Renovation Only)

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Counter doors, manual push-up operation.

1.2 ACTION SUBMITTALS

A. Product Data: For each type and size of coiling counter door and accessory.

B. Shop Drawings: For each installation and for special components not dimensioned or detailed in

manufacturer's product data.

1. Include points of attachment and their corresponding static and dynamic loads imposed

on structure.

C. Samples: For each exposed product and for each color and texture specified.

1.3 CLOSEOUT SUBMITTALS

A. Maintenance data.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and

approved by manufacturer for both installation and maintenance of units required for this

Project.

PART 2 - PRODUCTS

2.1 COUNTER DOOR ASSEMBLY (Pod J Renovation)

A. Counter Door: Coiling counter door formed with curtain of interlocking metal slats.

1. Manufacturers: Subject to compliance with requirements, available manufacturers

offering products that may be incorporated into the Work include, but are not limited to

the following:

a. C.H.I. Overhead Doors, Inc.

b. Clopay Building Products.

Page 8: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

COILING COUNTER DOORS 083313 - 2

c. Cookson Company.

d. Cornell Iron Works, Inc.

e. Overhead Door Corporation; Basis-of-Design Model 657 Stainless Steel.

f. Raynor.

g. Wayne-Dalton Corp.

B. Operation Cycles: Door components and operators capable of operating for not less than

20,000.

C. Door Curtain Material: Stainless steel.

D. Door Curtain Slats: Flat profile slats of 1-1/4-inch (32-mm) to 1-1/2-inch (38-mm) center-to-

center height.

E. Bottom Bar: Manufacturer's standard continuous channel or tubular shape, fabricated stainless

steel and finished to match door.

F. Curtain Jamb Guides: Stainless steel with exposed finish matching curtain slats. Provide

continuous integral wear strips to prevent metal-to-metal contact and to minimize operational

noise.

G. Integral Frame, Hood, and Fascia: Stainless steel.

1. Mounting: Between jambs.

H. Sill Configuration: Integral metal sill.

I. Locking Devices: Equip door with locking device assembly.

1. Locking Device Assembly: locking bars, operable from inside with thumb turn.

J. Manual Door Operator: Push-Up operator.

K. Door Finish:

1. Stainless-Steel Finish: No. 4 (polished directional satin).

2.2 DOOR CURTAIN MATERIALS AND CONSTRUCTION

A. Door Curtains: Fabricate coiling counter-door curtain of interlocking metal slats in a continuous

length for width of door without splices. Unless otherwise indicated, provide slats of thickness

and mechanical properties recommended by door manufacturer for performance, size, and type

of door indicated, and as follows:

B. Curtain Jamb Guides: Manufacturer's standard angles or channels and angles of same material

and finish as curtain slats unless otherwise indicated, with sufficient depth and strength to retain

curtain, to allow curtain to operate smoothly, and to withstand loading. Slot bolt holes for guide

adjustment. Provide removable stops on guides to prevent overtravel of curtain.

Page 9: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

COILING COUNTER DOORS 083313 - 3

2.3 HOODS

A. General: Form sheet metal hood to entirely enclose coiled curtain and operating mechanism at

opening head. Contour to fit end brackets to which hood is attached. Roll and reinforce top and

bottom edges for stiffness. Form closed ends for surface-mounted hoods and fascia for any

portion of between-jamb mounting that projects beyond wall face. Equip hood with

intermediate support brackets as required to prevent sagging.

B. Integral Frame, Hood, and Fascia: Welded stainless-steel sheet metal.

2.4 LOCKING DEVICES

A. Locking Device Assembly: Fabricate with cylinder lock, spring-loaded dead bolt, operating

handle, cam plate, and adjustable locking bars to engage through slots in tracks.

1. Lock Cylinders: Cylinders standard with manufacturer and keyed to building keying

system.

2. Keys: Three for each cylinder.

2.5 COUNTER DOOR ACCESSORIES

A. Integral Metal Sill: Fabricate sills as integral part of frame assembly of Type 304 stainless steel

in manufacturer's standard thickness with No. 4 finish.

2.6 COUNTERBALANCING MECHANISM

A. General: Counterbalance doors by means of manufacturer's standard mechanism with an

adjustable-tension, steel helical torsion spring mounted around a steel shaft and contained in a

spring barrel connected to top of curtain with barrel rings. Use grease-sealed bearings or self-

lubricating graphite bearings for rotating members.

B. Brackets: Manufacturer's standard mounting brackets of either cast iron or cold-rolled steel

plate.

2.7 MANUAL DOOR OPERATORS

A. General: Equip door with manual door operator by door manufacturer.

A. Push-up Door Operation: Design counterbalance mechanism so that required lift or pull for door

operation does not exceed 25 lbf (111 N).

Page 10: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

COILING COUNTER DOORS 083313 - 4

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install coiling counter doors and operating equipment complete with necessary hardware,

anchors, inserts, hangers, and equipment supports; according to manufacturer's written

instructions and as specified.

B. Adjust hardware and moving parts to function smoothly so that doors operate easily, free of

warp, twist, or distortion. Lubricate bearings and sliding parts as recommended by

manufacturer.

3.2 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to

adjust, operate, and maintain coiling counter doors.

END OF SECTION 083313

Page 11: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 1

SECTION 087100 - DOOR HARDWARE

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Mechanical door hardware for the following:

a. Swinging doors.

2. Cylinders for door hardware specified in other Sections.

3. Electrified door hardware.

4. Surface mounted automatic door operators.

B. Related Requirements:

1. Section 064116 "Plastic-Laminate-Faced Architectural Cabinets" for cabinet door

hardware provided with cabinets.

2. Section 081113 "Hollow Metal Doors and Frames" for astragals provided as part of

labeled fire-rated assemblies and for door silencers provided as part of hollow-metal

frames.

3. Section 081416 "Flush Wood Doors" for astragals and integral intumescent seals

provided as part of labeled fire-rated assemblies.

4. Section 083113 "Access Doors and Frames" for access door hardware, including

cylinders.

5. Section 084113 "Aluminum-Framed Entrances and Storefronts" for entrance door

hardware, except cylinders.

1.3 PREINSTALLATION MEETINGS

A. Keying Conference: Conduct conference at Project site.

1. Conference participants shall include Installer's Architectural Hardware Consultant and

Owner's security consultant.

2. Incorporate conference decisions into keying schedule after reviewing door hardware

keying system including, but not limited to, the following:

a. Flow of traffic and degree of security required.

b. Preliminary key system schematic diagram.

c. Requirements for key control system.

Page 12: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 2

d. Requirements for access control.

e. Address for delivery of keys.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, dimensions of individual components

and profiles, and finishes.

B. Shop Drawings: For electrified door hardware.

1. Include diagrams for power, signal, and control wiring.

2. Include details of interface of electrified door hardware and building safety and security

systems.

3. Tag Samples with full product description to coordinate Samples with door hardware

schedule.

C. Door Hardware Schedule: Prepared by or under the supervision of Installer's Architectural

Hardware Consultant. Coordinate door hardware schedule with doors, frames, and related work

to ensure proper size, thickness, hand, function, and finish of door hardware.

1. Submittal Sequence: Submit door hardware schedule concurrent with submissions of

Product Data, Samples, and Shop Drawings. Coordinate submission of door hardware

schedule with scheduling requirements of other work to facilitate the fabrication of other

work that is critical in Project construction schedule.

2. Format: Use same scheduling sequence and format and use same door numbers as in door

hardware schedule in the Contract Documents.

3. Content: Include the following information:

a. Identification number, location, hand, fire rating, size, and material of each door

and frame.

b. Locations of each door hardware set, cross-referenced to Drawings on floor plans

and to door and frame schedule.

c. Complete designations, including name and manufacturer, type, style, function,

size, quantity, function, and finish of each door hardware product.

d. Description of electrified door hardware sequences of operation and interfaces with

other building control systems.

e. Fastenings and other installation information.

f. Explanation of abbreviations, symbols, and designations contained in door

hardware schedule.

g. Mounting locations for door hardware.

h. List of related door devices specified in other Sections for each door and frame.

D. Keying Schedule: Prepared by or under the supervision of Installer's Architectural Hardware

Consultant, detailing Owner's final keying instructions for locks. Include schematic keying

diagram and index each key set to unique door designations that are coordinated with the

Contract Documents.

Page 13: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 3

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Architectural Hardware Consultant.

B. Product Certificates: For each type of electrified door hardware.

1. Certify that door hardware for use on each type and size of labeled fire-rated doors

complies with listed fire-rated door assemblies.

C. Product Test Reports: For compliance with accessibility requirements, for tests performed by

manufacturer and witnessed by a qualified testing agency, for door hardware on doors located in

accessible routes.

D. Sample Warranty: For special warranty.

1.6 CLOSEOUT SUBMITTALS

A. Maintenance Data: For each type of door hardware to include in maintenance manuals.

B. Schedules: Final door hardware and keying schedule.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: Supplier of products and an employer of workers trained and approved

by product manufacturers and of an Architectural Hardware Consultant who is available during

the course of the Work to consult Contractor, Architect, and Owner about door hardware and

keying.

1. Warehousing Facilities: In Project's vicinity.

2. Scheduling Responsibility: Preparation of door hardware and keying schedule.

3. Engineering Responsibility: Preparation of data for electrified door hardware, including

Shop Drawings, based on testing and engineering analysis of manufacturer's standard

units in assemblies similar to those indicated for this Project.

B. Architectural Hardware Consultant Qualifications: A person who is experienced in providing

consulting services for door hardware installations that are comparable in material, design, and

extent to that indicated for this Project and who is currently certified by DHI as an Architectural

Hardware Consultant (AHC).

1.8 DELIVERY, STORAGE, AND HANDLING

A. Inventory door hardware on receipt and provide secure lock-up for door hardware delivered to

Project site.

B. Tag each item or package separately with identification coordinated with the final door

hardware schedule, and include installation instructions, templates, and necessary fasteners with

each item or package.

C. Deliver keys to manufacturer of key control system for subsequent delivery to Owner.

Page 14: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 4

D. Deliver keys and permanent cores to Owner by registered mail or overnight package service.

1.9 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of door hardware that

fail in materials or workmanship within specified warranty period.

1. Failures include, but are not limited to, the following:

a. Structural failures including excessive deflection, cracking, or breakage.

b. Faulty operation of doors and door hardware.

c. Deterioration of metals, metal finishes, and other materials beyond normal

weathering and use.

2. Warranty Period: Three years from date of Substantial Completion unless otherwise

indicated below:

a. Electromagnetic Locks: Five years from date of Substantial Completion.

b. Exit Devices: Two years from date of Substantial Completion.

c. Manual Closers: 10 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations: Obtain each type of door hardware from single manufacturer.

1. Provide electrified door hardware from same manufacturer as mechanical door hardware

unless otherwise indicated. Manufacturers that perform electrical modifications and that

are listed by a testing and inspecting agency acceptable to authorities having jurisdiction

are acceptable.

2.2 PERFORMANCE REQUIREMENTS

A. Fire-Rated Door Assemblies: Where fire-rated doors are indicated, provide door hardware

complying with NFPA 80 that is listed and labeled by a qualified testing agency, for fire-

protection ratings indicated, based on testing at positive pressure according to NFPA 252 or

UL 10C.

B. Smoke- and Draft-Control Door Assemblies: Where smoke- and draft-control door assemblies

are required, provide door hardware that complies with requirements of assemblies tested

according to UL 1784 and installed in compliance with NFPA 105.

1. Air Leakage Rate: Maximum air leakage of 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) at

the tested pressure differential of 0.3-inch wg (75 Pa) of water.

C. Electrified Door Hardware: Listed and labeled as defined in NFPA 70, by a qualified testing

agency, and marked for intended location and application.

Page 15: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 5

D. Means of Egress Doors: Latches do not require more than 15 lbf (67 N) to release the latch.

Locks do not require use of a key, tool, or special knowledge for operation.

E. Accessibility Requirements: For door hardware on doors in an accessible route, comply with the

DOJ's "2010 ADA Standards for Accessible Design" and Florida Building Code-Accessibility.

1. Provide operating devices that do not require tight grasping, pinching, or twisting of the

wrist and that operate with a force of not more than 5 lbf (22.2 N).

2. Comply with the following maximum opening-force requirements:

a. Interior, Non-Fire-Rated Hinged Doors: 5 lbf (22.2 N) applied perpendicular to

door.

b. Fire Doors: Minimum opening force allowable by authorities having jurisdiction.

3. Bevel raised thresholds with a slope of not more than 1:2. Provide thresholds not more

than 1/2 inch (13 mm) high.

4. Adjust door closer sweep periods so that, from an open position of 90 degrees, the door

will take at least 5 seconds to move to a position of 12 degrees from the latch.

5. Adjust spring hinges so that, from an open position of 70 degrees, the door will take at

least 1.5 seconds to move to the closed position.

2.3 SCHEDULED DOOR HARDWARE

A. Provide products for each door that comply with requirements indicated in Part 2 and door

hardware schedule.

1. Door hardware is scheduled in Part 3.

2.4 HINGES

A. Hinges: BHMA A156.1. Provide template-produced hinges for hinges installed on hollow-metal

doors and hollow-metal frames.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or comparable products by one of the following:

a. Hager Companies.

b. McKinney Products Company; an ASSA ABLOY Group company.

c. Stanley Commercial Hardware; a division of Stanley Security Solutions.

2.5 CONTINUOUS HINGES

A. Continuous Hinges: BHMA A156.26; minimum 0.120-inch- (3.0-mm-) thick, hinge leaves with

minimum overall width of 4 inches (102 mm); fabricated to full height of door and frame and to

template screw locations; with components finished after milling and drilling are complete.

B. Continuous, Gear-Type Hinges: Extruded-aluminum, pinless, geared hinge leaves joined by a

continuous extruded-aluminum channel cap; with concealed, self-lubricating thrust bearings.

Page 16: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 6

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Hager Companies.

b. McKinney Products Company; an ASSA ABLOY Group company.

c. Stanley Commercial Hardware; a division of Stanley Security Solutions.

2.6 MECHANICAL LOCKS AND LATCHES

A. Lock Functions: As indicated in door hardware schedule.

B. Lock Throw: Comply with testing requirements for length of bolts required for labeled fire

doors, and as follows:

1. Mortise Locks: Minimum 3/4-inch (19-mm) latchbolt throw.

2. Deadbolts: Minimum 1-inch (25-mm) bolt throw.

C. Lock Backset: 2-3/4 inches (70 mm) unless otherwise indicated.

D. Lock Trim:

1. Description: As indicated in Hardware Schedule.

2. Levers: Cast.

a. As indicated in Hardware Schedule.

3. Escutcheons (Roses): [Wrought] [Forged] [Cast].

4. Dummy Trim: Match lever lock trim and escutcheons.

E. Strikes: Provide manufacturer's standard strike for each lock bolt or latchbolt complying with

requirements indicated for applicable lock or latch and with strike box and curved lip extended

to protect frame; finished to match lock or latch.

F. Mortise Locks: BHMA A156.13; Operational Grade 1; stamped steel case with steel or brass

parts; Series 1000.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Falcon MA Series scheduled or a comparable product by one of the following:

a. Best Access Systems; Stanley Security Solutions, Inc.; 45H series.

b. SARGENT Manufacturing Company; ASSA ABLOY; 8200 series.

2.7 SELF-CONTAINED ELECTRONIC LOCKS

A. Self-Contained Electronic Locks: BHMA A156.25; mortise; with internal, battery-powered,

self-contained electronic locks; consisting of complete lockset, motor-driven lock mechanism,

and actuating device; enclosed in zinc-dichromate-plated, wrought-steel case, and strike that

suits frame. Provide key override, low-battery detection and warning, LED status indicators,

and ability to program at the lock.

Page 17: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 7

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Sclage CO series scheduled or a comparable product by one of the following:

a. Best Access Systems; Stanley Security Solutions, Inc; EXZ Series

b. SARGENT Manufacturing Company; ASSA ABLOY; KP Series.

2.8 EXIT LOCKS AND EXIT ALARMS

A. Exit Locks and Alarms: BHMA A156.29, Grade 1.

2.9 SURFACE BOLTS

A. Surface Bolts: BHMA A156.16.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Trimco.

b. Rockwood.

2.10 MANUAL FLUSH BOLTS

A. Manual Flush Bolts: BHMA A156.16; minimum 3/4-inch (19-mm) throw; designed for

mortising into door edge.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Trimco.

b. Rockwood.

2.11 AUTOMATIC AND SELF-LATCHING FLUSH BOLTS

A. Automatic and Self-Latching Flush Bolts: BHMA A156.16; minimum 3/4-inch (19-mm) throw;

designed for mortising into door edge.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Trimco.

b. Rockwood.

2.12 EXIT DEVICES AND AUXILIARY ITEMS

A. Exit Devices and Auxiliary Items: BHMA A156.3.

Page 18: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 8

1. Manufacturers: Subject to compliance with requirements, available manufacturers

offering products that may be incorporated into the Work include, but are not limited to

the following:

a. Allegion plc.

b. Corbin Russwin, Inc.; an ASSA ABLOY Group company.

c. SARGENT Manufacturing Company; ASSA ABLOY.

d. Yale Security Inc; an ASSA ABLOY Group company.

2.13 LOCK CYLINDERS

A. Lock Cylinders: Tumbler type, constructed from brass or bronze, stainless steel, or nickel silver.

B. Standard Lock Cylinders: BHMA A156.5; Grade 1 permanent cores; face finished to match

lockset.

1. Core Type: Interchangeable or Removable as required by Owner.

C. Construction Cores: Provide construction cores that are replaceable by permanent cores.

Provide 10 construction master keys.

2.14 KEYING

A. Keying System: Factory registered, complying with guidelines in BHMA A156.28, appendix.

Provide one extra key blank for each lock. Incorporate decisions made in keying conference.

Provide key system as required by Owner

1. Grand Master Key System: Change keys, a master key, and a grand master key operate

cylinders.

a. Provide three cylinder change keys and five each of master and grand master keys.

2. Existing System:

a. Master key or grand master key locks to Owner's existing system.

B. Keys: Nickel silver or Brass.

1. Stamping: Permanently inscribe each key with a visual key control number and include

the following notation:

a. Notation: Information to be furnished by Owner.

2.15 KEY CONTROL SYSTEM

A. Key Control Cabinet: BHMA A156.28; metal cabinet with baked-enamel finish; containing

key-holding hooks, labels, two sets of key tags with self-locking key holders, key-gathering

envelopes, and temporary and permanent markers; with key capacity of 150 percent of the

number of locks.

Page 19: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 9

1. Wall-Mounted Cabinet: Grade 1 cabinet with hinged-panel door equipped with key-

holding panels and pin-tumbler cylinder door lock.

B. Key Lock Boxes: Designed for storage of two keys.

2.16 OPERATING TRIM

A. Operating Trim: BHMA A156.6; stainless steel unless otherwise indicated.

2.17 ACCESSORIES FOR PAIRS OF DOORS

A. Coordinators: BHMA A156.3; consisting of active-leaf, hold-open lever and inactive-leaf

release trigger; fabricated from steel with nylon-coated strike plates; with built-in, adjustable

safety release.

B. Carry-Open Bars: BHMA A156.3; prevent the inactive leaf from opening before the active leaf;

provide polished brass or bronze carry-open bars with strike plate for inactive leaves of pairs of

doors unless automatic or self-latching bolts are used.

C. Astragals: BHMA A156.22.

2.18 SURFACE CLOSERS

A. Surface Closers: BHMA A156.4; rack-and-pinion hydraulic type with adjustable sweep and

latch speeds controlled by key-operated valves and forged-steel main arm. Comply with

manufacturer's written instructions for size of door closers depending on size of door, exposure

to weather, and anticipated frequency of use. Provide factory-sized closers, adjustable to meet

field conditions and requirements for opening force.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

LCN4040XP series products or a comparable product by one of the following:

a. SARGENT Manufacturing Company; ASSA ABLOY; 281 Series.

b. Stanley Commercial Hardware; a division of Stanley Security Solutions;

D-4550 Series.

2.19 MECHANICAL STOPS AND HOLDERS

A. Wall- and Floor-Mounted Stops: BHMA A156.16.

2.20 OVERHEAD STOPS AND HOLDERS

A. Overhead Stops and Holders: BHMA A156.8.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Glynn Johnson products scheduled or a comparable product by one of the following:

Page 20: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 10

a. SARGENT Manufacturing Company; ASSA ABLOY.

b. Rockwood.

c. Trimco.

2.21 Door Gasketing: BHMA A156.22; with resilient or flexible seal strips that are easily replaceable

and readily available from stocks maintained by manufacturer.

A. Maximum Air Leakage: When tested according to ASTM E 283 with tested pressure

differential of 0.3-inch wg (75 Pa), as follows:

1. Smoke-Rated Gasketing: 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) of door opening.

2. Gasketing on Single Doors: 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) of door opening.

3. Gasketing on Double Doors: 0.50 cfm per foot (0.000774 cu. m/s per m) of door opening.

B. Basis-of-Design Product: Subject to compliance with requirements, provide Zero International,

Inc. products or comparable products by one of the following:

a. Hager Companies.

b. National Guard Products, Inc.

c. Pemko Manufacturing Co.

2.22 THRESHOLDS

A. Thresholds: BHMA A156.21; fabricated to full width of opening indicated.

B. Basis-of-Design Product: Subject to compliance with requirements, provide Zero International,

Inc. products or comparable products by one of the following:

a. Hager Companies.

b. National Guard Products, Inc.

c. Pemko Manufacturing Co.

2.23 METAL PROTECTIVE TRIM UNITS

A. Metal Protective Trim Units: BHMA A156.6; fabricated from 0.050-inch- (1.3-mm-) thick

stainless steel; with manufacturer's standard machine or self-tapping screw fasteners.

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Trimco.

b. Rockwood.

2.24 AUXILIARY DOOR HARDWARE

A. Auxiliary Hardware: BHMA A156.16.

Page 21: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 11

1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;

Ives products scheduled or a comparable product by one of the following:

a. Trimco.

b. Rockwood.

2.25 FABRICATION

A. Manufacturer's Nameplate: Do not provide products that have manufacturer's name or trade

name displayed in a visible location except in conjunction with required fire-rating labels and as

otherwise approved by Architect.

1. Manufacturer's identification is permitted on rim of lock cylinders only.

B. Base Metals: Produce door hardware units of base metal indicated, fabricated by forming

method indicated, using manufacturer's standard metal alloy, composition, temper, and

hardness. Furnish metals of a quality equal to or greater than that of specified door hardware

units and BHMA A156.18.

C. Fasteners: Provide door hardware manufactured to comply with published templates prepared

for machine, wood, and sheet metal screws. Provide screws that comply with commercially

recognized industry standards for application intended, except aluminum fasteners are not

permitted. Provide Phillips flat-head screws with finished heads to match surface of door

hardware unless otherwise indicated.

1. Concealed Fasteners: For door hardware units that are exposed when door is closed,

except for units already specified with concealed fasteners. Do not use through bolts for

installation where bolt head or nut on opposite face is exposed unless it is the only means

of securely attaching the door hardware. Where through bolts are used on hollow door

and frame construction, provide sleeves for each through bolt.

2. Fire-Rated Applications:

a. Wood or Machine Screws: For the following:

1) Hinges mortised to doors or frames.

2) Strike plates to frames.

3) Closers to doors and frames.

b. Steel Through Bolts: For the following unless door blocking is provided:

1) Surface hinges to doors.

2) Closers to doors and frames.

3) Surface-mounted exit devices.

3. Spacers or Sex Bolts: For through bolting of hollow-metal doors.

4. Gasketing Fasteners: Provide noncorrosive fasteners for exterior applications and

elsewhere as indicated.

Page 22: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 12

2.26 FINISHES

A. Provide finishes complying with BHMA A156.18 as indicated in door hardware schedule.

B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable,

temporary protective covering before shipping.

C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are

acceptable if they are within one-half of the range of approved Samples. Noticeable variations

in the same piece are not acceptable. Variations in appearance of other components are

acceptable if they are within the range of approved Samples and are assembled or installed to

minimize contrast.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine doors and frames, with Installer present, for compliance with requirements for

installation tolerances, labeled fire-rated door assembly construction, wall and floor

construction, and other conditions affecting performance of the Work.

B. Examine roughing-in for electrical power systems to verify actual locations of wiring

connections before electrified door hardware installation.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Steel Doors and Frames: For surface-applied door hardware, drill and tap doors and frames

according to ANSI/SDI A250.6.

B. Wood Doors: Comply with door and hardware manufacturers' written instructions.

3.3 INSTALLATION

A. Mounting Heights: Mount door hardware units at heights to comply with the following unless

otherwise indicated or required to comply with governing regulations.

1. Standard Steel Doors and Frames: ANSI/SDI A250.8.

2. Custom Steel Doors and Frames: HMMA 831.

3. Wood Doors: DHI's "Recommended Locations for Architectural Hardware for Wood

Flush Doors."

B. Install each door hardware item to comply with manufacturer's written instructions. Where

cutting and fitting are required to install door hardware onto or into surfaces that are later to be

painted or finished in another way, coordinate removal, storage, and reinstallation of surface

protective trim units with finishing work. Do not install surface-mounted items until finishes

have been completed on substrates involved.

Page 23: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 13

1. Set units level, plumb, and true to line and location. Adjust and reinforce attachment

substrates as necessary for proper installation and operation.

2. Drill and countersink units that are not factory prepared for anchorage fasteners. Space

fasteners and anchors according to industry standards.

C. Hinges: Install types and in quantities indicated in door hardware schedule, but not fewer than

the number recommended by manufacturer for application indicated or one hinge for every 30

inches (750 mm) of door height, whichever is more stringent, unless other equivalent means of

support for door, such as spring hinges or pivots, are provided.

D. Lock Cylinders: Install construction cores to secure building and areas during construction

period.

1. Replace construction cores with permanent cores as directed by Owner.

2. Furnish permanent cores to Owner for installation.

E. Key Control System:

1. Key Control Cabinet: Tag keys and place them on markers and hooks in key control

system cabinet, as determined by final keying schedule.

2. Key Lock Boxes: Install where indicated or approved by Architect to provide controlled

access for fire and medical emergency personnel.

F. Boxed Power Supplies: Locate power supplies as indicated or, if not indicated, above accessible

ceilings. Verify location with Architect.

1. Configuration: Provide one power supply for each door opening least number of power

supplies required to adequately serve doors with electrified door hardware.

G. Thresholds: Set thresholds for exterior doors and other doors indicated in full bed of sealant

complying with requirements specified in Section 079200 "Joint Sealants."

H. Stops: Provide floor stops for doors unless wall or other type stops are indicated in door

hardware schedule. Do not mount floor stops where they will impede traffic.

I. Perimeter Gasketing: Apply to head and jamb, forming seal between door and frame.

1. Do not notch perimeter gasketing to install other surface-applied hardware.

J. Meeting Stile Gasketing: Fasten to meeting stiles, forming seal when doors are closed.

K. Door Bottoms: Apply to bottom of door, forming seal with threshold when door is closed.

3.4 ADJUSTING

A. Initial Adjustment: Adjust and check each operating item of door hardware and each door to

ensure proper operation or function of every unit. Replace units that cannot be adjusted to

operate as intended. Adjust door control devices to compensate for final operation of heating

and ventilating equipment and to comply with referenced accessibility requirements.

Page 24: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 14

1. Door Closers: Adjust sweep period to comply with accessibility requirements and

requirements of authorities having jurisdiction.

2. Spring Hinges: Adjust to achieve positive latching when door is allowed to close freely

from an open position of 70 degrees and so that closing time complies with accessibility

requirements of authorities having jurisdiction.

3. Electric Strikes: Adjust horizontal and vertical alignment of keeper to properly engage

lock bolt.

B. Occupancy Adjustment: Approximately 8 months after date of Substantial Completion,

Installer's Architectural Hardware Consultant shall examine and readjust each item of door

hardware, including adjusting operating forces, as necessary to ensure function of doors, door

hardware, and electrified door hardware.

3.5 CLEANING AND PROTECTION

A. Clean adjacent surfaces soiled by door hardware installation.

B. Clean operating items as necessary to restore proper function and finish.

C. Provide final protection and maintain conditions that ensure that door hardware is without

damage or deterioration at time of Substantial Completion.

3.6 MAINTENANCE SERVICE

A. Maintenance Tools and Instructions: Furnish a complete set of specialized tools and

maintenance instructions for Owner's continued adjustment, maintenance, and removal and

replacement of door hardware.

3.7 DOOR HARDWARE SCHEDULE

Hardware Group No. 01

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

2 EA CONT. HINGE 112HD EPT 628 IVE

1 EA POWER TRANSFER EPT10 CON 689 VON

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

1 EA ELEC PANIC

HARDWARE

RX-QEL+-HH-99-DT-CON 626 VON

1 EA ELEC PANIC

HARDWARE

RX-QEL+-HH-99-NL-CON 626 VON

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA MORTISE CYLINDER 20-061-ICX 626 SCH

2 EA FSIC CORE 23-030 626 SCH

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

Page 25: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 15

1 EA SURF. AUTO

OPERATOR

9542 MS ANCLR LCN

2 EA ACTUATOR, WALL

MOUNT

8310-853T 630 LCN

2 EA FLOOR STOP FS18S BLK IVE

1 EA POWER SUPPLY PS902 900-2RS LGR SCE

1 BALANCE OF HARDWARE BY DOOR

MANUFACTURER

2 EA WIRE HARNESS CON-12 VON

2 EA WIRE HARNESS CON-192P VON

2 EA SECURITY CONTACTS 1090-G GE

Presentation of valid credential retracts latch on panic hardware and allows for door to auto open.

Card reader by security supplier

Wiring Diagram by Hardware Supplier

Hardware Group No. 02

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

1 EA FIRE EXIT

HARDWARE

HH-99-DT-F 626 VON

1 EA FIRE EXIT

HARDWARE

HH-99-NL-F 626 VON

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA MORTISE CYLINDER 20-061-ICX 626 SCH

2 EA FSIC CORE 23-030 626 SCH

2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN

2 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

2 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 03

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

1 EA PANIC HARDWARE HH-99-DT 626 VON

1 EA PANIC HARDWARE HH-99-NL 626 VON

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA MORTISE CYLINDER 20-061-ICX 626 SCH

2 EA FSIC CORE 23-030 626 SCH

Page 26: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 16

2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN

2 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

2 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 04

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

2 EA PANIC HARDWARE HH-99-L-BE-06 626 VON

2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN

2 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

Hardware Group No. 05

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

8 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

2 EA FIRE EXIT

HARDWARE

HH-99-L-BE-F-06 626 VON

1 EA MORTISE CYLINDER 20-061-ICX 626 SCH

1 EA FSIC CORE 23-030 626 SCH

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

2 EA DOOR SWEEP 8192AA AA ZER

1 EA THRESHOLD 545A-MSLA-10 A ZER

Hardware Group No. 06

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

2 EA SURFACE BOLT SB360 12" T 604 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA LOCK GUARD LG12 630 IVE

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

Page 27: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 17

1 EA THRESHOLD 65A-MSLA-10 A ZER

2 EA SECURITY CONTACTS 1090-G GE

With Metal Z-Astragal

Hardware Group No. 06A (added as part of Pod Renovations)

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

2 EA SURFACE BOLT SB360 12" T 604 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA LOCK GUARD LG12 630 IVE

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

2 EA SECURITY

CONTACTS

1090-G GE

With Metal Z-Astragal

Hardware Group No. 07

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA PANIC HARDWARE HH-99-L-NL-17 626 VON

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA FSIC CORE 23-030 626 SCH

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 08

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON

1 EA ELEC EXIT DEVICE

TRIM

CO-100-993R-70-KP-SPA-PD 626 SCE

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

Page 28: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 18

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY CONTACTS 1090-G GE

Stand Alone keypad trim

Hardware Group No. 09

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

1 EA CONT. HINGE 112HD 628 IVE

1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON

1 EA ELEC EXIT DEVICE

TRIM

CO-100-993R-70-KP-SPA-PD 626 SCE

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA FLOOR STOP FS18S BLK IVE

1 EA SECURITY CONTACTS 1090-G GE

1 BALANCE OF HARDWARE BY DOOR

MANUFACTURER

Stand Alone keypad trim

Hardware Group No. 10

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

1 EA CONT. HINGE 112HD 628 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA FLOOR STOP FS18S BLK IVE

1 EA SECURITY CONTACTS 1090-G GE

1 BALANCE OF HARDWARE BY DOOR

MANUFACTURER

Hardware Group No. 11

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA LOCK GUARD LG12 630 IVE

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 12

Provide each SGL door(s) with the following:

Page 29: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 19

Qty Description Catalog Number Finish Mfr

4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA CLASSROOM LOCK MA561P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 13

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA CLASSRM SEC LOCK MA441P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY CONTACTS 1090-G GE

Hardware Group No. 14

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA KEYED REMOVABLE

MULLION

KR4954-STAB 689 VON

2 EA PANIC HARDWARE 99-L-17-SNB 626 VON

2 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA MORTISE CYLINDER 20-061-ICX 626 SCH

3 EA FSIC CORE 23-030 626 SCH

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

2 EA SILENCER SR64 GRY IVE

Hardware Group No. 15

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA KEYED FIRE RATED

REMOVABLE

MULLION

KR9954-STAB 689 VON

1 EA FIRE EXIT

HARDWARE

99-L-BE-F-17-SNB 626 VON

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

Page 30: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 20

2 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

2 EA GASKETING 188S-BK S-Bk ZER

Hardware Group No. 16

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 SET CONST LATCHING

BOLT

FB53 630 IVE

1 EA CLASSROOM LOCK MA561P6 QN 626 FAL

1 EA COORDINATOR COR X FL 628 IVE

2 EA MOUNTING BRACKET MB 689 IVE

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

1 EA ASTRAGAL 905A A ZER

2 EA SILENCER SR64 GRY IVE

Hardware Group No. 17

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 SET CONST LATCHING

BOLT

FB53 630 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA COORDINATOR COR X FL 628 IVE

2 EA MOUNTING BRACKET MB 689 IVE

2 EA SURFACE CLOSER 4040XP CUSH 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA ASTRAGAL 905A A ZER

Hardware Group No. 18

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 SET CONST LATCHING

BOLT

FB53 630 IVE

1 EA CLASSROOM LOCK MA561P6 QN 626 FAL

1 EA COORDINATOR COR X FL 628 IVE

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

1 EA ASTRAGAL 905A A ZER

2 EA SILENCER SR64 GRY IVE

Page 31: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 21

Hardware Group No. 19

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 SET CONST LATCHING

BOLT

FB53 630 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA COORDINATOR COR X FL 628 IVE

2 EA MOUNTING BRACKET MB 689 IVE

2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE

2 EA WALL STOP WS406/407CCV 630 IVE

1 EA ASTRAGAL 905A A ZER

2 EA SILENCER SR64 GRY IVE

Hardware Group No. 20

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA PANIC HARDWARE 99-EO 626 VON

1 EA ELEC EXIT DEVICE

TRIM

CO-100-993R-70-KP-SPA-PD 626 SCE

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA FSIC CORE 23-030 626 SCH

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

Stand Alone keypad trim

Hardware Group No. 21

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA CLASSRM SEC LOCK MA441P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

Hardware Group No. 22

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

Page 32: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 22

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA STOREROOM LOCK MA581P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

Hardware Group No. 23

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA CLASSROOM LOCK MA561P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

Hardware Group No. 24

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA PRIVACY LOCK MA301 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA GASKETING 188S-BK S-Bk ZER

Hardware Group No. 25

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA PUSH PLATE 8200 6" X 16" 630 IVE

1 EA PULL PLATE 8303 10" 4" X 16" 630 IVE

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

3 EA SILENCER SR64 GRY IVE

Hardware Group No. 26

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA OFFICE LOCK MA521P6 QN 626 FAL

1 EA WALL STOP WS406/407CCV 630 IVE

3 EA SILENCER SR64 GRY IVE

Hardware Group No. 27 - GATE

Page 33: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 23

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

2 EA PANIC HARDWARE HH-99-NL 626 VON

2 EA RIM CYLINDER 20-057-ICX 626 SCH

2 EA FSIC CORE 23-030 626 SCH

BALANCE OF HARDWARE BY GATE

MANUFACTURER

NOTE: Hardware sets below are additional sets added for the Pod Renovation Buildings C, D, G, J,

M, and NJROTC addition. The new doors scheduled also utilize the same Hardware Group num-

bers as the Classroom Building. Hardware shall be furnished as Assa-Abloy/Sargent Brands equiv-

alent to the Allegion Brands indicated below, as was also furnished on the Classroom Building.

Hardware Group No. 28

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE

1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA FLOOR STOP FS18S BLK IVE

1 EA GASKETING 188S-BK S-Bk ZER

1 EA THRESHOLD 65A-MSLA-10 A ZER

1 EA SECURITY

CONTACTS

1090-G GE

Hardware Group No. 29

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA PANIC HARDWARE 99-L-17-SNB 626 VON

1 EA RIM CYLINDER 20-057-ICX 626 SCH

1 EA FSIC CORE 23-030 626 SCH

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE

1 EA WALL STOP WS406/407CCV 630 IVE

1 EA SILENCER SR64 GRY IVE

Hardware Group No. 30

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 3CB1 4.5 X 4.5 652 IVE

1 EA PASSAGE SET MA301P6 QN 626 FAL

1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN

1 EA WALL STOP WS406/407CCV 630 IVE

3 EA SILENCER SR64 GRY IVE

Page 34: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

DOOR HARDWARE 087100 - 24

Hardware Group No. 31

Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr

3 EA HINGE 5 KNUCKLE BALL BEARING, NRP 632 --

1 EA PANIC HARDWARE DOOR MANUF. STD. CVR 626 --

1 EA 10” OFFSET PULL DOOR MANUF. STD. 632 --

1 EA SURFACE CLOSER DOOR MANUF. STD. 689 --

1 EA SECURITY

CONTACTS

1090-G GE

1 BALANCE OF HARDWARE BY

DOOR MANUFACTURER

Hardware Group No. 32

Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr

6 EA HINGE 5 KNUCKLE BALL BEARING, NRP 632 --

2 EA PANIC HARDWARE DOOR MANUF. STD. CVR 626 --

2 EA 10” OFFSET PULL DOOR MANUF. STD. 632 --

2 EA SURFACE CLOSER DOOR MANUF. STD. 689 --

2 EA SECURITY

CONTACTS

1090-G GE

2 BALANCE OF HARDWARE BY

DOOR MANUFACTURER

END OF SECTION 087100

Page 35: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 1

SECTION 105113 - METAL LOCKERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Welded (interior) corridor lockers.

2. Welded, open-front athletic lockers. (Added for Pod G Locker Room Expansion)

1.3 ACTION SUBMITTALS

A. Product Data: For each type of metal locker.

1. Include construction details, material descriptions, dimensions of individual components

and profiles, and finishes for each type of metal locker.

B. Sustainable Design Submittals:

1. Recycled Content:

a. Indicate recycled content; indicate percentage of pre-consumer and post-consumer

recycled content per unit of product.

b. Indicate relative dollar value of recycled content product to total dollar value of

product included in project.

c. If recycled content product is part of an assembly, indicate the percentage of

recycled content product in the assembly by weight.

d. If recycled content product is part of an assembly, indicate relative dollar value of

recycled content product to total dollar value of assembly.

2. Local/Regional Materials: Sourcing Location(s): Indicate location of extraction,

harvesting, and recovery; indicate distance between extraction, harvesting, and recovery

and the project site.

a. Manufacturing Location(s): Indicate location of manufacturing facility; indicate

distance between manufacturing facility and the project site.

b. Product Value: Indicate dollar value of product containing local/regional

materials; include materials cost only.

c. Product Component(s): Where product components are sourced or manufactured

in separate locations, provide location information for each component. Indicate

the percentage by weight of each component per unit of product.

Page 36: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 2

C. Shop Drawings: For metal lockers.

1. Include plans, elevations, sections, details, and attachments to other work.

2. Show locker trim and accessories.

3. Include locker identification system and numbering sequence.

D. Samples: For each color specified, in manufacturer's standard size.

E. Product Schedule: For lockers.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Sample Warranty: For special warranty.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance Data: For adjusting, repairing, and replacing locker doors and latching

mechanisms to include in maintenance manuals.

1.6 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective

covering for storage and identified with labels describing contents.

1. Full-size units of the following metal locker hardware items equal to 10 percent of

amount installed for each type and finish installed, but no fewer than five units:

a. Locks.

b. Hooks.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Do not deliver metal lockers until spaces to receive them are clean, dry, and ready for their

installation.

B. Deliver master and control keys and combination control charts to Owner.

1.8 FIELD CONDITIONS

A. Field Measurements: Verify actual dimensions of openings by field measurements before

fabrication.

Page 37: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 3

1.9 COORDINATION

A. Coordinate sizes and locations of framing, blocking, furring, reinforcements, and other related

units of work specified in other Sections to ensure that metal lockers can be supported and

installed as indicated.

1.10 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of metal lockers that

fail in materials or workmanship, excluding finish, within specified warranty period.

1. Failures include, but are not limited to, the following:

a. Structural failures.

b. Faulty operation of latches and other door hardware.

2. Damage from deliberate destruction and vandalism is excluded.

3. Warranty Period for Welded Metal Lockers: 10 years from date of Final Completion.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations: Obtain metal lockers and accessories from single source from single locker

manufacturer.

1. Obtain locks from single lock manufacturer.

2.2 PERFORMANCE REQUIREMENTS

A. Accessibility Requirements: For lockers indicated to be accessible, comply with applicable

provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA

Accessibility Guidelines and Florida Building Code-Accessibility.

2.3 WELDED CORRIDOR LOCKERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering

products that may be incorporated into the Work include, but are not limited to the following:

1. Art Metal Products.

2. ASI Storage Solutions; ASI Group.

3. General Storage Systems Ltd.

4. List Industries Inc. (Superior, Classmate Unibody All-Welded Lockers used as the

Basis-of Design

5. Lyon Workspace Products, LLC.

6. Penco Products, Inc.

7. Republic Storage Systems, LLC.

Page 38: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 4

B. Size: Triple-tier, 12-inch wide by 15-inch deep by 72-inch height (exclusive of 4-inch height

continuous zee base), unless noted otherwise.

C. Doors: One piece; fabricated from 0.075-inch (1.90-mm) nominal-thickness steel sheet; formed

into channel shape with double bend at vertical edges and with right-angle single bend at

horizontal edges.

1. Reinforcement: Manufacturer's standard reinforcing angles, channels, or stiffeners for

doors more than 15 inches (381 mm) wide; welded to inner face of doors.

2. Door Stiffener: Manufacturer’s standard 3-inch wide, 0.075-inch (1.90-mm) thick, full

height door stiffener spot welded to the inner door face and welded to the hinge side as

well as the top and bottom door flanges.

3. Door Style: Vented panel as follows:

a. Louvered Vents: No fewer than two louver openings at top and bottom, or three

louver openings at top or bottom, for triple-tier lockers.

D. Body: Assembled by welding body components together. Fabricate from unperforated steel

sheet with thicknesses as follows:

1. Tops, Bottoms, and Sides: 0.060-inch (1.52-mm) nominal thickness.

2. Backs: 0.048-inch (1.21-mm) nominal thickness.

3. Shelves: 0.060-inch (1.52-mm) nominal thickness, with double bend at front and single

bend at sides and back.

E. Frames: Channel formed; fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet;

lapped and factory welded at corners; with top and bottom main frames factory welded into

vertical main frames. Form continuous, integral, full-height door strikes on vertical main

frames.

1. Cross Frames between Tiers: Channel formed and fabricated from same material as main

frames; welded to vertical main frames.

F. Hinges: Welded to door and attached to door frame with no fewer than two factory-installed

rivets per hinge that are completely concealed and tamper resistant when door is closed;

fabricated to swing 180 degrees.

1. Hinges: Manufacturer's standard, steel, continuous or knuckle type.

G. Recessed Door Handle and Latch: Stainless-steel cup with integral door pull, recessed so

locking device does not protrude beyond door face; pry and vandal resistant.

1. Multipoint Latching: Finger-lift latch control designed for use with built-in combination

locks or padlocks; positive automatic latching.

a. Latch Hooks: Equip doors 48 inches (1219 mm) and higher with three latch hooks

and doors less than 48 inches (1219 mm) high with two latch hooks; fabricated

from 0.105-inch (3.04-mm) nominal-thickness steel sheet; welded to full-height

door strikes; with resilient silencer on each latch hook.

H. Locks: Combination padlocks (Owner Furnished).

Page 39: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 5

I. Identification Plates: Manufacturer's standard, etched, embossed, or stamped aluminum plates,

with numbers and letters at least 3/8 inch (9 mm) high.

J. Hooks: Manufacturer's standard ball-pointed type, aluminum or steel; zinc plated.

K. Continuous Zee Base: Fabricated from, manufacturer's standard thickness, but not less than

0.060-inch (1.52-mm) nominal-thickness steel sheet.

1. Height: 4 inches (102 mm).

L. Continuous Integral Sloping Tops: Fabricated from 0.060-inch (1.21-mm) nominal-thickness

steel sheet, with a pitch of approximately 20 degrees, continuous across multiple units and

factory welded. Locker sides are sloped at top providing rigid support beneath the sloped top

between each unit.

1. Closures: Vertical-end type.

M. Filler Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.

N. Boxed End Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.

O. Materials:

1. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B,

suitable for exposed applications.

P. Finish: Baked enamel or powder coat.

1. Color: As indicated by manufacturer's designations or if not indicated, as selected by

Architect from manufacturer's full range.

2.4 WELDED OPEN FRONT ATHLETIC LOCKERS (Pod G Renovation)

A. Basis-of-Design Product: Subject to compliance with requirements, provide ASI Storage

Solutions; ASI Group; All-Welded Competitor or a comparable product by one of the

following:

1. Art Metal Products.

2. General Storage Systems Ltd.

3. List Industries Inc.

4. Lyon Workspace Products, LLC.

5. Penco Products, Inc.

6. Republic Storage Systems, LLC.

B. Size: Single-tier, 18-inch wide by 18-inch deep by 60-inch height, unless noted otherwise.

C. Locker Arrangement: Open front, with upper shelf with security box and configuration as

indicated on Drawings.

D. Perforated Doors: One piece; fabricated from 0.075-inch (1.90-mm) nominal-thickness

steel sheet with manufacturer's standard diamond perforations; formed into channel

Page 40: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 6

shape with double bend at vertical edges and with right-angle single bend at horizontal

edges.

1. Reinforcement: Manufacturer's standard reinforcing angles, channels, or stiffeners

for doors more than 15 inches (381 mm) wide; welded to inner face of doors.

E. Body: Assembled by welding body components together. Fabricate from unperforated

steel sheet with thicknesses as follows:

1. Tops and Bottoms: 0.060-inch (1.52-mm) nominal thickness, with single bend at

edges.

2. Backs: 0.048-inch (1.21-mm) nominal thickness.

3. Shelves: 0.060-inch (1.52-mm) nominal thickness, with double bend at front and

single bend at sides and back.

F. Perforated Sides: Fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet

with manufacturer's standard diamond perforations.

G. Frames: Channel formed; fabricated from 0.060-inch (1.52-mm) nominal-thickness steel

sheet or 0.097-inch (2.45-mm) nominal-thickness steel angles; lapped and factory welded

at corners; with top and bottom main frames factory welded into vertical main frames.

Form continuous, integral, full-height door strikes on vertical main frames.

H. Security Boxes: Consisting of partition extending from upper shelf to top of metal locker,

fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet; with channel-formed,

0.060-inch (1.52-mm) nominal-thickness, steel sheet door frame, and door fabricated from

0.075-inch (1.90-mm) nominal-thickness steel sheet with right-angle single bend at edges;

with manufacturer's standard, steel continuous hinge that is completely concealed and

tamper resistant when door is closed; fabricated to swing 180 degrees.

I. Locks: Combination padlocks, Owner Furnished.

J. Identification Plates: Manufacturer's standard, etched, embossed, or stamped aluminum

plates, with numbers and letters at least 3/8 inch (9 mm) high.

1. Number locker units starting at 1 for both the Boys Locker Room and the Girls

Locker Room.

K. Hooks: Manufacturer's standard ball-pointed type, aluminum or steel; zinc plated.

L. Continuous Sloping Tops: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel

sheet, with a pitch of approximately 20 degrees.

1. Closures: Vertical-end type.

M. Filler Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.

N. Materials:

1. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B,

suitable for exposed applications.

Page 41: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 7

O. Finish: Baked enamel or powder coat.

1. Color: #53 Pine Forest Green.

2.5 LOCKS

A. Combination Padlocks: Provide key-controlled, three-number dialing combination locks;

capable of five combination changes.

2.6 FABRICATION

A. Fabricate metal lockers square, rigid, without warp, and with metal faces flat and free of dents

or distortion. Make exposed metal edges safe to touch and free of sharp edges and burrs.

1. Form body panels, doors, shelves, and accessories from one-piece steel sheet unless

otherwise indicated.

2. Provide fasteners, filler plates, supports, clips, and closures as required for complete

installation.

B. Fabricate each metal locker with an individual door and frame; individual top, bottom, and

back; and common intermediate uprights separating compartments. Factory weld frame

members of each metal locker together to form a rigid, one-piece assembly.

C. Equipment: Provide each locker with an identification plate and the following equipment:

1. Triple-Tier Units: One double-prong ceiling hook.

D. Welded Construction: Factory preassemble metal lockers by welding all joints, seams, and

connections; with no bolts, nuts, screws, or rivets used in assembly of main locker groups.

Factory weld main locker groups into one-piece structures. Grind exposed welds flush.

E. Accessible Lockers: Fabricate as follows:

1. Locate bottom shelf no lower than 15 inches (381 mm) above the floor.

2. Where hooks or additional shelves are provided, locate no higher than 48 inches (1219

mm) above the floor.

3. Provide a minimum of 5% of total number of lockers to meet accessibility requirements,

distributed throughout the various groupings.

F. Continuous Base: Formed into channel or zee profile for stiffness, and fabricated in lengths as

long as practical to enclose base and base ends of metal lockers; finished to match lockers.

G. Continuous Integral Sloping Tops: Fabricated in lengths as long as practical, without visible

fasteners at splice locations; finished to match lockers.

1. Sloping-top corner fillers, mitered.

H. Filler Panels: Fabricated in an unequal leg angle shape; finished to match lockers. Provide slip-

joint filler angle formed to receive filler panel.

Page 42: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 8

I. Boxed End Panels: Fabricated with 1-inch- (25-mm-) wide edge dimension, and designed for

concealing fasteners and holes at exposed ends of nonrecessed metal lockers; finished to match

lockers.

1. Provide one-piece panels for double-row (back-to-back) locker ends.

2.7 ACCESSORIES

A. Fasteners: Zinc- or nickel-plated steel, slotless-type, exposed bolt heads; with self-locking nuts

or lock washers for nuts on moving parts.

B. Anchors: Material, type, and size required for secure anchorage to each substrate.

1. Provide nonferrous-metal or hot-dip galvanized anchors and inserts on inside face of

exterior walls for corrosion resistance.

2. Provide toothed-steel or lead expansion sleeves for drilled-in-place anchors.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine walls, floors, and support bases, with Installer present, for compliance with

requirements for installation tolerances and other conditions affecting performance of the Work.

B. Prepare written report, endorsed by Installer, listing conditions detrimental to performance of

the Work.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION

A. General: Install lockers level, plumb, and true; shim as required, using concealed shims.

1. Anchor locker runs at ends and at intervals recommended by manufacturer, but not more

than 36 inches (910 mm) o.c. Using concealed fasteners, install anchors through backup

reinforcing plates, channels, or blocking as required to prevent metal distortion.

2. Anchor single rows of metal lockers to walls near top of lockers and either bottom of

lockers or to floor.

B. Welded Lockers: Connect groups together with standard fasteners, with no exposed fasteners on

face frames.

C. Equipment:

1. Attach hooks with at least two fasteners.

2. Identification Plates: Identify metal lockers with identification indicated on Drawings.

Page 43: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 1

SECTION 23 44 00 - AIR PURIFICATION SYSTEM PART 1 – GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 DESCRIPTION OF WORK

A. This section describes the design, performance and installation of an air purification system intended for use as part of another manufacturer’s air handling unit or mounted on the duct as shown on the plans, details and equipment schedules.

1.3 REFERENCED CODES & STANDARDS

A. The following codes and standards are referenced through out. The edition to be used is

that currently enforced by the authority having jurisdiction (AHJ) or in absence of such direction that referenced by the current enforceable IBC code or as indicated by the contract documents, except where specifically referenced by this section of the specifications. 1. ASHRAE Standards 62 & 52 2. National Electric Code NFPA 70 3. UL 867 including ozone chamber test required as of December 21, 2007 4. The ionization equipment and power supply shall be UL and CE listed.

1.4 RELATED WORK

A. Testing, Adjusting and Balancing B. Facility Access and Protection C. Ductwork D. Filters E. Water and Refrigerant Piping F. Electrical Wiring G. Control Wiring

1.5 QUALITY ASSURANCE

A. Basis of design is Global Plasma Solutions. Plasma Air and Active Air Solutions shall be considered equal subjects to meeting ALL specifications herein. All other manufacturers requesting prior approval must submit product drawings, specifications and test results specified in section 2.2 at least four weeks prior to bid date.

B. The Air Purification System shall be a product of an established manufacturer within the

USA and shall be made of 100% USA sourced raw materials and components. C. A qualified representative from the manufacturer shall be available to inspect the

installation of the air purification system to ensure installation in accordance with manufacturer's recommendation.

D. Technologies that do not address gas disassociation such as UV Lights, Powered

Particulate Filters and/or polarized media filters shall not be considered. Uni-polar ion generators shall not be acceptable. “Plasma” particulate filters shall not be acceptable.

Page 44: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 2

E. Projects designed using ASHRAE Standard 62, IAQ Procedure shall require the manufacturer to provide Indoor Air Quality calculations using the formulas within ASHRAE Standard 62.1-2007 to validate acceptable indoor air quality at the quantity of outside air scheduled with the technology submitted. The manufacturer shall provide independent test data on a previous installation performed within the last two years and in a similar application, that proves compliance to ASHRAE 62 and the accuracy of the calculations.

F. The Air Purification Technology shall have been tested by UL or Intertek/ETL to prove

conformance to UL 867-2007 including the ozone chamber testing and peak ozone test for electronic devices. Manufacturers that achieved UL 867 prior to December 21, 2007 and have not been tested in accordance with the newest UL 867 standard with the ozone amendment shall not be acceptable. All manufacturers shall submit their independent UL 867 test data with ozone results to the engineer during the submittal process. All manufacturers shall submit a copy with their quotation. Contractors shall not accept any proposal without the proper ozone testing documentation.

G. The maximum allowable ozone concentration per the UL 867-2007 chamber test shall be

0.007 PPM. The maximum peak ozone concentration per the UL 867-2007 peak test as measured 2 inches away from the electronic air cleaner’s output shall be no more than 0.0042 PPM. Manufacturers with ozone output exceeding these ozone values shall not be acceptable.

1.6 SUBMITTALS

A. Product Data: Submit manufacturer's technical product data for ion generators including: 1. Schedule of plasma generators indicating unit designation, number of each type

required for each unit/application. 2. Data sheet for each type of plasma generator, plasma detector and accessory

furnished; indicating construction, sizes, and mounting details. 3. Performance data for each type of plasma device furnished. 4. Indoor Air Quality calculations using the formulas within ASHRAE Standard 5. 62.1-2007 to validate acceptable indoor air quality at the quantity of outside air 6. Scheduled (when projects are designed with outside air reduction). 7. Product drawings detailing all physical, electrical and control requirements. 8. Copy of UL 867 independent ozone test.

B. Operating & Maintenance Data: Submit O&M data and recommended spare parts lists.

1.7 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Deliver in factory fabricated shipping containers. Identify on outside of container type of product and location to be installed. Avoid crushing or bending.

B. Store in original cartons and protect from weather and construction work traffic. C. Store indoors and in accordance with the manufacturers’ recommendation for storage.

1.8 WARRANTY

A. Equipment shall be warranted by the manufacturer against defects in material and

workmanship for a period of eighteen months after shipment or twelve months from owner acceptance, whichever occurs first. Labor to replace equipment under warranty shall be provided by the installing contractor.

Page 45: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 3

PART 2 - PRODUCTS 2.1 GENERAL

A. The air purification system(s) shall be of the size, type, arrangement and capacity indicated and required by the unit furnished and shall be of the manufacturer specified.

B. Acceptable manufacturers: 1. Active Air Solutions 2. Bioclimatic 3. Global Plasma Solutions (Basis of Design) 4. Plasma Air

C. All other Suppliers of comparable products requesting prior approval shall:

1. Submit for prior approval four weeks in advance. 2. In addition, manufacturers submitting for prior approval for Bi-Polar Ionization must

as part of the prior approval request provide their ASHRAE 62.1-2010 calculations that prove conformance to the ASHRAE Standard with the reduction of outside air to the scheduled values. A letter on the manufacturer’s letterhead requesting prior approval must accompany the request for prior approval stating their calculations are ASHRAE compliant. A third party validation study performed on a previous installation of the same application shall also be included.

3. Submit independent test data from ETL or UL showing ozone levels produced during the UL 867 ozone chamber test. Manufacturers without this test data shall not be acceptable.

4. Submit pathogen testing per section 2.2. 5. Submit at least two other end user references in the same application with contact

phone number, email, equipment used and application for the equipment at that facility. Manufacturers not having the above references in similar applications using the same equipment models as proposed on the current project shall not be acceptable.

2.2 BI-POLAR IONIZATION DESIGN & PERFORMANCE CRITERIA

A. Each piece of air handling equipment, so designated on the plans, details, equipment schedules and/or specifications shall contain a Plasma Generator with Bi-polar Ionization output as described here within.

B. The Bi-polar Ionization system shall be capable of:

1. Effectively killing microorganisms downstream of the bi-polar ionization equipment (mold, bacteria, virus, etc.).

2. Controlling gas phase contaminants generated from human occupants, building structure, furnishings and outside air contaminants.

3. Capable of reducing static space charges. 4. Effectively reducing space particle counts. 5. When mounted to the air entering side of a cooling coil, keep the cooling coil free

from pathogen and mold growth. 6. All manufacturers shall provide documentation by an independent NELEC

accredited laboratory that proves the product has minimum kill rates for the following pathogens given the allotted time and in a space condition:

a. MRSA - >96% in 30 minutes or less

Page 46: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 4

b. E.coli - > 99% in 15 minutes or less c. TB - > 69% in 60 minutes or less d. C. diff - >86% in 30 minutes or less

7. Manufacturers not providing the equivalent space kill rates shall not be acceptable. All manufactures requesting prior approval shall provide to the engineer independent test data from a NELEC accredited independent lab confirming kill rates and time meeting the minimum requirements stated in section 2.2 B, points 6A, 6B and 6C. Products tested only on Petri dishes to prove kill rates shall not be acceptable. Products being sold under different trade names than those tested shall not be acceptable.

C. The bi-polar ionization system shall operate in a manner such that equal amounts of

positive and negative ions are produced. Uni-polar ion devices shall not be acceptable. 1. Air exchange rates may vary through the full operating range of a constant

Volume or VAV system. The quantity of air exchange shall not be increased due to requirements of the air purification system.

2. Velocity Profile: The air purification device shall not have maximum velocity profile.

D. Humidity: Plasma Generators shall not require preheat protection when the relative humidity of the entering air exceeds 85%. Relative humidity from 0 - 100%, condensing, shall not cause damage, deterioration or dangerous conditions within the air purification system. Air purification system shall be capable of wash down duty.

E. Equipment Requirements:

1. Electrode Specifications (Bi-polar Ionization):

a. Each Plasma Generator with Bi-polar Ionization output shall include the required number of electrodes and power generators sized to the air handling equipment capacity. A minimum of sixteen 316 medical grade stainless steel ion needles per foot of coil face width shall be provided. The entire cooling coil shall width shall have equal distribution of ionization across the face. The plasma electrode shall require no more than one inch in the direction of airflow for mounting. All hardware required for mounting shall be provided by the air handler unit manufacturer. Bi-polar ionization tubes manufactured of glass and steel mesh shall not be acceptable due to replacement requirements, maintenance, and performance output reduction over time, ozone production and corrosion. Plasma generators with recessed needles shall not be acceptable.

b. Electrodes shall be energized when the main unit disconnect is turned on and the fan is operating.

F. Air Handler Mounted Units: 1. Where so indicated on the plans and/or schedules Plasma Generator(s) shall be

supplied and installed. The mechanical contractor shall mount the Plasma Generator and wire it to the remote mount power supply using the high voltage cables provided by the air purification manufacturer. An 115VAC or 230VAC circuit shall be provided to the ion generator power supply panel. Each ion generator shall be designed with an aluminum casing, integral grounding connection and high voltage quick connector.

G. Ionization Requirements:

Page 47: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 5

1. Plasma Generators with Bi-polar ionization output shall be capable of controlling gas phase contaminants and shall be provided for all equipment listed above.

a. The Bi-polar ionization system shall consist of Bi-Polar Plasma Generator

and power supply. The Bi-polar system shall be installed where indicated on the plans or specified to be installed. The device shall be capable of being powered by 115VAC or 230VAC without the use of an external transformer. Ionization systems requiring isolation transformers shall not be acceptable.

b. Ionization Output: he ionization output shall be controlled such that an equal number of positive and negative ions are produced. Imbalanced levels shall not be acceptable.

c. Ionization output from each electrode shall be a minimum of 20 million ions/cc when tested at 2” from the ionization generator.

2. Ozone Generation:

a. The operation of the electrodes or Bi-polar ionization units shall conform

to UL 867-2007 with respect to ozone generation.

H. Electrical Requirements:

1. Wiring, conduit and junction boxes shall be installed within housing plenums in accordance with NEC NFPA 70. Plasma Generator shall accept an electrical service of 115 VAC or 230VAC, 1 phase, 50/60 Hz. The contractor shall coordinate electrical requirements with air purification manufacturer during submittals.

I. Control Requirements:

1. All Plasma Generators shall have internal short circuit protection, overload protection, and automatic fault reset.

2. The ionization system shall be provided with a stand-alone, independent ion sensor designed for duct mounting to monitor the ion output and report to the BAS system that the ion device is working properly. Ion systems provided without an independent ion sensor, shall not be permitted. The control voltage to power the ion sensor shall be 12VDC, 24VDC or 24VAC and draw no more than 150mA of current. The sensor shall provide at minimum, dry contact status to the BAS and optionally a BacNet interface as specified on the control drawings.

3. The installing contractor shall mount and wire the Plasma device within the air handling unit specified or as shown or the plans. The contractor shall follow all manufacturer IOM instructions during installation.

4. Provide interlock to AHU fan to energize the BPI unit, ONLY when the fan is “ON”. Fully coordinate all requirements with the BCS Contractor prior to bid.

2.3 PLASMA DETECTOR DESIGN & PERFORMANCE CRITERIA

A. Each piece of air handling equipment, so designated on the plans, details, equipment schedules and/or specifications shall contain a Plasma Detector with integral BAS contacts.

B. The Plasma Detector sensor shall be designed to these minimum standards:

1. Ability to detect both positive and negative ion levels from 1,000 ions/cc to 20 million ions/cc minimum. Detection limit shall be field adjustable based on sensor mounting location and manufacturer being sensed.

2. Plasma detector shall have integral dry alarm contacts for connection to the BAS to prove the ion system is operating properly and the ion system output is above the

Page 48: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18

AIR PURIFICATION SYSTEM 23 44 00 - 6

minimum preset threshold from the sensor manufacturer. The alarm shall activate when either positive or negative ion output drops below the preset setpoint. Cold plasma systems only providing indication the input power is applied or output power is present shall not be acceptable. The independent cold plasma detector shall be capable of working with any air purification manufacturer’s system.

3. Cold plasma detector shall have an input voltage of 12VDC, 24VDC or 24VAC user selectable.

4. Cold plasma detector shall be capable of duct mounting or integral air stream mounting.

5. Housing shall be constructed of fire retardant ABS plastic. 6. Temperature and humidity shall have no affect on the cold plasma detector output

accuracy. 7. The alarm output shall be provided with NO, NC and C terminals for ease of

integration to the BAS. The contacts shall be rated for up to 5 amps at 230VAC or up to 24VDC at 2 amps.

8. A BACnet control interface shall be provided by the cold plasma detector manufacturer.

PART 3 - EXECUTION 3.1 GENERAL

A. The Contractor shall be responsible for maintaining all air systems until the owner accepts the building (Owner Acceptance).

3.2 ASSEMBLY & ERECTION: PLASMA GENERATOR WITH BI-POLAR IONIZATION & COLD

PLASMA DETECTOR

A. All equipment shall be assembled and installed in a workman like manner to the satisfaction of the owner, architect, and engineer.

B. Any material damaged by handling, water or moisture shall be replaced, by the mechanical contractor, at no cost to the owner.

C. All equipment shall be protected from dust and damage on a daily basis throughout construction.

3.3 TESTING

A. Provide the manufacturers recommended electrical tests.

3.4 COMMISSIONING & TRAINING

A. A manufacturer's authorized representative shall provide start-up supervision. END OF SECTION 23 44 00

Page 49: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

METAL LOCKERS 105113 - 9

a. Attach plates to each locker door, near top, centered, with at least two aluminum

rivets.

D. Trim: Fit exposed connections of trim, fillers, and closures accurately together to form tight,

hairline joints, with concealed fasteners and splice plates.

1. Attach filler panels with concealed fasteners. Locate filler panels where indicated on

Drawings.

2. Attach sloping-top units to metal lockers, with closures at exposed ends.

3. Attach boxed end panels using concealed fasteners to conceal exposed ends of

nonrecessed metal lockers.

3.3 ADJUSTING

A. Clean, lubricate, and adjust hardware. Adjust doors and latches to operate easily without

binding.

3.4 PROTECTION

A. Protect metal lockers from damage, abuse, dust, dirt, stain, or paint. Do not permit use during

construction.

B. Touch up marred finishes, or replace metal lockers that cannot be restored to factory-finished

appearance. Use only materials and procedures recommended or furnished by locker

manufacturer.

END OF SECTION 105113

Page 50: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-1

SECTION 275123 - EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes user-programmable, multichannel, microprocessor-switched, centrally

controlled, school intercom and program equipment independent of telephone equipment.

Provide connection to school telephone switch.

1.3 SUBMITTALS

A. Product Data: For the following:

1. Speaker-microphone stations.

2. Call-switch units.

3. Volume controls.

4. Speakers.

5. Horns.

6. Amplifier.

B. Shop Drawings:

1. Equipment Details: Detail equipment assemblies and indicate dimensions, weights,

required clearances, method of field assembly, components, and location of each field

connection.

2. Station-Arrangement Details: Scaled drawings for built-in equipment.

3. Wiring Diagrams: Power, signal, and control wiring. Include the following:

a. Identify terminals to facilitate installation, operation, and maintenance.

b. Single-line diagram showing interconnection of components.

c. Cabling diagram showing cable routing.

C. Coordination Drawings: Reflected ceiling plans, drawn to scale, on which the following items

are shown and coordinated with each other, based on input from installers of the items involved:

1. Ceiling-mounted items including lighting fixtures, diffusers, grilles, speakers, sprinklers,

access panels, and special moldings.

D. Field quality-control test reports.

Page 51: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-2

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved

for installation of units required for this Project.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,

Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for

intended use.

C. Comply with NFPA 70.

D. Comply with UL 50.

1.5 COORDINATION

A. Coordinate layout and installation of ceiling-mounted speaker microphones and suspension

system with other construction that penetrates ceilings or is supported by them, including light

fixtures, HVAC equipment, fire-suppression system, and partition assemblies.

PART 2 - PRODUCTS

2.1 EQUIPMENT AND MATERIALS

A. Existing console, Telecor XL.

B. Coordinate features to form an integrated system. Match components and interconnections for

optimum performance of specified functions.

C. Provide additional amplifiers station cards, extension modules and other equipment as required

for complete operable system.

2.2 CONE-TYPE LOUDSPEAKERS/SPEAKER MICROPHONES

A. Comply with TIA/EIA SE-103.

B. Minimum Axial Sensitivity: TIA/EIA SE-103 pressure rating of 45 dB.

C. Frequency Response: Within plus or minus 3 dB from 70 to 15,000 Hz.

D. Minimum Dispersion Angle: 100 degrees.

E. Line Transformer: Comply with TIA/EIA-160, maximum insertion loss of 0.5 dB, power rating

equal to speaker's, and at least 4 level taps.

F. Enclosures: Steel housings or back boxes, acoustically dampened, with front face of at least

0.0478-inch (1.2-mm) steel and whole assembly rust proofed and factory primed; complete with

mounting assembly and suitable for surface ceiling, flush ceiling, pendant or wall mounting;

and with relief of back pressure.

Page 52: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-3

G. Baffle: For flush speakers, minimum thickness of 0.032-inch (0.8-mm) aluminum, with textured

white finish.

H. Size: 8 inches (200 mm) with 1-inch (25-mm) voice coil and minimum 5-oz. (140-g) ceramic

magnet.

2.3 HORN-TYPE LOUDSPEAKERS/SPEAKER MICROPHONES

A. Comply with TIA/EIA SE-101-A. All-metal, weatherproof construction; complete with

universal mounting brackets.

B. Frequency Response: Within plus or minus 3 dB from 275 to 14,000 Hz.

C. Minimum Power Rating of Driver: 15 W, continuous.

D. Minimum Dispersion Angle: 110 degrees.

E. Line Transformer: Comply with TIA/EIA-160, maximum insertion loss of 0.5 dB, power rating

equal to speaker's, and at least 4 level taps.

F. Provide weatherproof adapter.

2.4 CALL-SWITCH UNIT

A. Enclosure: Single-gang box with stainless-steel faceplate.

B. Call Switch: Momentary contact signals system that a call has been placed. Switch shall

be rocker style.

2.5 VOLUME CONTROL UNIT

A. Enclosure: Single-gang box with stainless-steel faceplate. For surface mount locations,

provide extensions to back boxes to allow sufficient space for terminations. For locations

recessed in walls, terminate conduits towards the back of the device box and provide same

extensions for additional room to allow sufficient space for terminations.

B. Volume Control: Operated by knob / dial to adjust output level of associated speaker.

2.6 CONDUCTORS AND CABLES

A. Conductors: Jacketed, twisted pair and twisted multi-pair, untinned solid copper. Sizes as

recommended by system manufacturer, but not smaller than No. 22 AWG. Use multi

conductor cables from control equipment to communication rooms (single station cables will

not be acceptable).

B. Insulation: Thermoplastic, not less than 1/32 inch (0.8 mm) thick.

Page 53: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-4

C. Shielding: For speaker-microphone leads and elsewhere where recommended by manufacturer;

No. 34 AWG tinned, soft-copper strands formed into a braid or equivalent foil.

1. Minimum Shielding Coverage on Conductors: 60 percent.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Wiring Method: Install wiring in raceways except within communication room, consoles,

desks, and counters. Conceal cables and raceways except in unfinished spaces.

B. Wiring within Enclosures and Communication Room: Bundle, lace, and train conductors to

terminal points with no excess. Use lacing bars.

C. Control-Circuit Wiring: Install number and size of conductors as recommended by system

manufacturer for control functions indicated.

D. Splices, Taps, and Terminations: Arrange on numbered terminal strips in junction, pull, and

outlet boxes; terminal cabinets; and equipment enclosures.

E. Match input and output impedances and signal levels at signal interfaces. Provide matching

networks where required.

F. Identification of Conductors and Cables: Color-code conductors and apply wire and cable

marking tape to designate wires and cables so they identify media in coordination with system

wiring diagrams.

G. Weatherproof Equipment: For units that are mounted outdoors, in damp locations, or where

exposed to weather, install consistent with requirements of weatherproof rating.

3.2 GROUNDING

A. Ground cable shields and equipment to eliminate shock hazard and to minimize ground loops,

common-mode returns, noise pickup, cross talk, and other impairments.

B. Signal Ground Terminal: Locate at main equipment cabinet. Isolate from power system and

equipment grounding.

3.3 FIELD QUALITY CONTROL

A. Manufacturer's Field Service: Engage a factory-authorized service representative to

inspect, test, and adjust field-assembled components and equipment installation, including

connections, and to assist in field testing. Report results in writing.

B. Perform the following field tests and inspections and prepare test reports:

1. Schedule tests with at least seven days' advance notice of test performance.

Page 54: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-5

2. After installing school intercom and program equipment and after electrical circuitry has

been energized, test for compliance with requirements.

3. Operational Test: Test originating station-to-station, all-call, and page messages at each

intercom station. Verify proper routing and volume levels and that system is free of noise

and distortion. Test each available message path from each station on system.

4. Frequency Response Test: Determine frequency response of two transmission paths,

including all-call and paging, by transmitting and recording audio tones. Minimum

acceptable performance is within 3 dB from 150 to 2500 Hz.

5. Signal-to-Noise Ratio Test: Measure signal-to-noise ratio of complete system at normal

gain settings as follows:

a. Disconnect speaker microphone and replace it in the circuit with a signal generator

using a 1000-Hz signal. Measure signal-to-noise ratio at paging speakers.

b. Repeat test for three speaker microphones, one master station microphone, and for

each separately controlled zone of paging loudspeakers.

c. Minimum acceptable ratio is 45 dB.

6. Distortion Test: Measure distortion at normal gain settings and rated power. Feed

signals at frequencies of 150, 200, 400, 1000, and 2500 Hz into each intercom, paging,

and all-call amplifier. For each frequency, measure distortion in the paging and all-call

amplifier outputs. Maximum acceptable distortion at any frequency is 5 percent total

harmonics.

7. Acoustic Coverage Test: Feed pink noise into system using octaves centered at 500 and

4000 Hz. Use sound-level meter with octave-band filters to measure level at five

locations in each paging zone. Maximum permissible variation in level is plus or minus

3 dB; in levels between adjacent zones, plus or minus 5 dB.

8. Power Output Test: Measure electrical power output of each paging amplifier at normal

gain settings of 150, 1000, and 2500 Hz. Maximum variation in power output at these

frequencies is plus or minus 3 dB.

9. Signal Ground Test: Measure and report ground resistance at system signal ground.

Comply with testing requirements in Division 26 Section "Grounding and Bonding for

Electrical Systems."

C. Retesting: Correct deficiencies and retest. Prepare a written record of tests.

D. Inspection: Verify that units and controls are properly labeled and interconnecting wires and

terminals are identified. Prepare a list of final tap settings of paging and independent room

speaker-line matching transformers.

E. Prepare written test reports.

1. Include a record of final speaker-line matching transformer-tap settings, and signal

ground-resistance measurement certified by Installer.

3.4 STARTUP SERVICE

A. Engage a factory-authorized service representative to perform startup service and initial system

programming.

Page 55: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-6

B. Verify that electrical wiring installation complies with manufacturer's submittal and installation

requirements.

C. Complete installation and startup checks according to manufacturer's written instructions.

3.5 ADJUSTING

A. On-Site Assistance: Engage a factory-authorized service representative to provide on-site

assistance in adjusting sound levels, resetting transformer taps, and adjusting controls to meet

occupancy conditions.

B. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion,

provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to

four visits to site outside normal occupancy hours for this purpose, without additional cost.

3.6 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to

adjust, operate, and maintain school intercom and program equipment. Refer to Division 01

Section "Demonstration and Training."

Train Owner's maintenance personnel on programming equipment for starting up and

shutting down, troubleshooting, servicing, and maintaining equipment.

END OF SECTION 275123

Page 56: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30

Expansion, Renovations, and Site Improvements Pod Renovations

DATA, VOICE AND VIDEO 280500-1

SECTION 280500 - DATA, VOICE AND VIDEO

THE COMMUNICATIONS AND ELETRICAL CONTRACTORS SHALL OBTAIN AND

THOROUGHLY FAMILIARIZE THEMSELVES WITH THE MOST CURRENT RELEASE OF THE

ST. JOHNS COUNTY SCHOOL DISTRICT TECHNOLOGY DEPARTMENT “VOICE AND DATA

STRUCTURED CABLING STANDARD” (ATTACHED) WHICH BY REFERENCE SHALL

BECOME A PART OF THIS SPECIFICATION. IN EVENT OF CONFLICT WITH PROJECT

SPECIFICATIONS, THE SJCSD “STRUCTURED CABLING STANDARD” SHALL PREVAIL.

END OF SECTION 280500

Page 57: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 1 Structured Cabling Standards-Version 7.0

St Johns County School District

Voice and Data

Structured Cabling Standards

Page 58: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 2 Structured Cabling Standards-Version 7.0

Table of Contents

Article 1. General Information ...................................................................................................... 5

Article 2. Telecommunications Conduit Systems ......................................................................... 6

Article 3. Telecommunications Rooms ......................................................................................... 7

Article 4. Support Systems .......................................................................................................... 10

Article 5. Electrical Power .......................................................................................................... 10

Article 6. Telecommunications Systems Grounding/Bonding .................................................... 11

Article 7. Environmental Requirements for Telecommunications Rooms ................................. 11

Article 8. Horizontal Structured Cabling .................................................................................... 12

Article 9. Backbone Cabling and Installation ............................................................................. 16

Article 10. Wireless Voice and Data Network Design Requirements ....................................... 18

Article 11. Labeling and Administration .................................................................................. 19

Article 12. Testing and Documentation ..................................................................................... 22

Article 13. Relocatable Classroom Systems Specs. .................................................................. 23

Article 14. Classroom Audio/Visual Technology ..................................................................... 31

Article 15. Applicable Industry Standards ................................................................................ 42

Page 59: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 3 Structured Cabling Standards-Version 7.0

Document Updates:

Section/

Article Summary of Changes Changes by

Change

Date

Document

Version #

11.02 Added test results submittal email Justin Forfar 10 Oct 06 V4.0

All Version 4.2 Released Justin Forfar 11 Oct 06 V4.2

All Changed from Cat5E to Cat6 spec Justin Forfar 8 Nov 06 V4.2

9.01(c) Addressed space issues brought up by

engineers

Justin Forfar 14 Nov 06 V4.2

8 Added Cat6 performance spec Justin Forfar 14 Nov 06 V4.2

3 Added cable mgmt and cable tray

reqs

Justin Forfar 27 Feb 07 V4.21

10 Added wireless network spec article Justin Forfar 19 Nov 07 V4.22

3.01(b) Added requirement for ER and TR

detail drawings

Justin Forfar 10 Dec 07 V4.22

5.02(b) Removed requirement isolated ground Justin Forfar 24 Sep 08 V4.22

9.02(e) Removed fiber jumper provision Justin Forfar 8 Oct 08 V4.22

14 New Chris Petrello 10 Oct 08 V4.22

All Format, add TOC Bruce Patrou 14 Oct 08 V4.22.3

All Released Version 4.22.4 Justin Forfar 15 Oct 08 V4.22.4

14.01(b) Clarified requirement for master

volume control via teacher control

wallplate

Justin Forfar 6 Jan 10 V4.3

14 Added Model Classroom AV

inspection requirement

Justin Forfar 6 Jan 10 V4.3

14.01(l) Clarification of AV shelf mounting

height and location

Justin Forfar 6 Jan 10 V4.3

14.01(e) Added model number for Wall Plate 1 Justin Forfar 6 Jan 10 V4.3

All Released Version 4.3 Justin Forfar 6 Jan 10 V4.3

11 Clarified labeling and install

requirements for WAP WAOs, MLC

WAOs

Justin Forfar 10 Mar 11 V5.0

8.05 Clarified TR side requirements for

modular jack color codes

Justin Forfar 10 Mar 11 V5.0

8.01 Clarified horizontal data cabling

options

Justin Forfar 10 Mar 11 V5.0

9.02 Updated Fiber Optic cabling

specifications

Justin Forfar 22 Mar 11 V5.0

Page 60: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 4 Structured Cabling Standards-Version 7.0

14 Complete rewrite to include Extron

PoleVault Standard including new

AVerMedia Tuners, Clarified

projection screen size and throw

distance

Justin Forfar 30 Mar 11 V5.0

13 General update of portables section-

new pedestal types, added detail

drawings for portables.

Justin Forfar 30 Mar 11 V5.0

13.01 Added diagram for standard

relocatable classroom data pedestal

buildout.

Justin Forfar 3 May 12 V5.5

8.04 Edited section title to include

faceplates as well as patch panels

Justin Forfar 3 May 12 V5.5

10.0 Revised wireless standards to include

AP mfr, two cables per location

Justin Forfar 3 May 12 V5.5

14.03 Added Chief CMA470 Plenum

enclosure to PoleVault System parts

list

Justin Forfar 3 May 12 V5.5

14 Edited Exhibit E to reflect use of

Chief CMA470 Plenum enclosure

Justin Forfar 3 May 12 V5.5

14 Removed Extron PoleVault Standard

and added “New Solution TBD”

Justin Forfar 21 Mar 16 V6

8 Removed reference to AMP product

line. Added Panduit and General Cat6

parts as approved cabling options

Justin Forfar 21 Mar 16 V6

9.02 Corrected reference to LC singlemode

connectors with SC.

Justin Forfar 21 Mar 16 V6

8.03 Reduced the number of data cables in

each CWAO from three to two. Total

number of CWAOs within a

classroom DID NOT change.

Justin Forfar 23 Mar 16 V6

14 Added equipment performance

standards and diagrams outlining new

AV standard

Justin Forfar 10 Mar 17 V7.0

8 Removed plenum cable requirement Justin Forfar 10 Mar 17 V7.0

9 Added clarification regarding

plenum/non-plenum cabling

requirements

Justin Forfar 10 Mar 17 V7.0

Page 61: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 5 Structured Cabling Standards-Version 7.0

Article 1. General Information

Section 1.01 Statement of Purpose

The purpose of this document is to enumerate the standards and practices to be followed when designing

structured cabling systems for the St Johns County School District. Each section of this document outlines: 1)

a specific part of a structured cabling system or manner in which a product or technology should be installed

or 2) a specific product line or product that shall be used for a certain part of an installation. This document is

to be used in conjunction with all applicable industry standards and codes to provide the St Johns County

School District with a flexible, scalable, easily managed, properly documented structured cabling network.

Section 1.02 General Voice and Data Network Service Requirements

(a) All areas of a building shall be equipped with voice and data network access during the design

phase. These areas include but are not limited to:

(i) Classroom and learning spaces including teacher planning rooms

(ii) Administrative offices including conference rooms and work rooms

(iii) Storage spaces including book storage and central receiving

(iv) Media/Library spaces including all work rooms, professional work spaces, and group project

areas

(v) Auditorium spaces including ticket windows, concessions, dressing areas, and control booth

(vi) Gym spaces including all coaches offices, breakout rooms, trainer’s offices, and nurse’s offices

(vii) Athletic fields including all field houses and press boxes

Section 1.03 Terminology

(a) MTR – Main telecommunications room that houses all core electronics and telephone service

provider demark

(b) TR –Telecommunications room located throughout site as cable length requires

(c) Work Area Outlet (WAO) - a location within a classroom or office that offers a connection or

group of connections to the structured cabling network.

(d) TBB- Telecommunications Bus Bar

(e) WAP- Wireless access point

(f) EC- Equipment cabinet – may house active or passive equipment

Page 62: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 6 Structured Cabling Standards-Version 7.0

Article 2. Telecommunications Conduit Systems

Section 2.01 General Standards for Conduit

(a) All voice or data conduits installed between an MTR or TR and another MTR/TR shall be filled

to capacity with 1” nominal inside diameter corrugated innerduct.

(b) A ½” 1200lb rated pull tape shall be installed in each innerduct and secured at each end.

(c) Each conduit shall be capped with a duplex, triplex, or quadplex divider based on conduit size

and installation requirements.

Section 2.02 Outside Plant Conduit

(a) Future Relocatable Classroom Service

(i) A minimum of two (2) each four inch (4”) plastic Polyvinyl Chloride(PVC) conduits of schedule

40 or equivalent shall be installed from the MTR/TR nearest the forecasted relocatable classroom

site and terminated at least ten feet from the building to allow for the installation of future voice

and data backbone cabling to the relocatable classrooms

1) End of conduits shall be clearly identified by a concrete marker as shown below:

Page 63: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 7 Structured Cabling Standards-Version 7.0

Article 3. Telecommunications Rooms

Section 3.01 Telecommunications Room Design and Build-out Requirements

(a) Engineer or designer shall consult w/ the current Information Technology Department project

contact to determine specific MTR/TR layout needs.

(b) Engineer or designer shall provide detail drawings for MTR and each TR in the telecom section

of drawings. Detail drawings shall include at a minimum:

(i) Front views of each equipment rack to be installed in the respective MTR/TR showing actual

LIU and horizontal patch panel locations and quantity, type and quantity of cables to be

terminated on said patch panel, panel numbers and jack labels, and open space for customer

provided equipment

(ii) A chart outlining the quantities of each drop type to be installed in each respective

MTR/TR.(example below)

Table 3.01.1

TR-XXX Cable Count

(iii) Each detail drawing shall be clearly labeled by TR’s

FISH number.

(c) All TRs shall be designed with sufficient floor space to

facilitate the use of floor standing racks for the support of all

voice and data cabling and electronics.

(i) The use of wall mounted racks, either swing-gate or fixed is prohibited unless prior written

approval is given by the current Information Technology Department project contact. These

WAO Type Qty

TWAO 5

AWAO 4

SWAO 3

WAP 3

… …

Page 64: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 8 Structured Cabling Standards-Version 7.0

types of racks are notoriously difficult for District IT staff and vendors to service once

electronics, fiber jumpers, and copper patch cords have been installed in/on them.

(d) Each MTR and TR shall have a drop ceiling set at 10’AFF.

(e) All TRs shall have 3/4” plywood backboard covering all four (4) walls from 12” AFF to a

height of 9’ AFF. All plywood backboard shall be painted with 2 coats fire retardant on all 6

sides. All plywood backboard shall be A/C grade with the "A" side out.

(f) Ladder rack shall be installed around perimeter of TR at 8’ AFF. All floor standing racks shall

be mechanically bonded to the installed ladder rack for support.

(i) Ladder rack should be Chatsworth Products Inc. Cable Runway® and Radii Bends® or

approved equal. A minimum width of 12” is required.

(ii) A cable runway radius drop (waterfall) must be used to support cables transitioning from ladder

tray to equipment racks or another cable tray above or below the transition point.

Section 3.02 Equipment Rack and Enclosure Requirements

(a) Floor mounted equipment racks (ER)

(i) A standard 84” two post rack shall be provided and securely fastened to bare concrete or tile

floor.

(ii) Isolation pads shall be placed between the rack and the bare concrete floor.

(b) Enclosures/Cabinets-

(i) Floor mounted equipment cabinets (EC) shall be installed in a manner that allows full access to

both the front and the rear of the cabinet. Where a specific part number is listed, only that part

number will be accepted unless prior written approval is received from the current Information

Technology project contact.

1) 70” Floor-mount EC

a) Hubbell part number HPW70C19X30

(ii) Wall mounted cabinets shall be mounted in a manner that allows the EC’s front door and center

to swing fully open. Additionally, all wall mounted cabinets shall be affixed to a ¾” plywood

backboard that has been painted with a fire retardant paint.

1) 48” Wall-mount/Floor-mount EC

a) Hubbell part number HSQ4826

2) 36” Wall-mount/Floor-mount EC

a) Hubbell part number HSQ3626

Page 65: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 9 Structured Cabling Standards-Version 7.0

Section 3.03 Equipment Rack Cable Management

(a) Approved vertical and horizontal wire management is listed below (no other models will be

accepted under ANY circumstances):

(i) Horizontal Management – Panduit Part # WMPH2E

(ii) Vertical Management – Panduit Part # WMPVHC45E

Page 66: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 10 Structured Cabling Standards-Version 7.0

Article 4. Support Systems

Section 4.01 TBD

Article 5. Electrical Power

Section 5.01 General Power Requirements

(a) All power outlets that serve communications rooms shall originate from a branch panel that

serves only this sensitive equipment.

(b) Any and all circuits serving an MTR or TR are critical for building support and life safety

systems (Voice, Data, BMS, EMS, A/C controls, security, surveillance, etc) and are required to

be serviced by the site’s backup generator.

Section 5.02 Power Conditioning and Protection Requirements

(a) Transient voltage surge suppression (TVSS) systems shall be installed, at a minimum, in front

of every branch panel that will service communications rooms and equipment.

Section 5.03 Telecommunications Room Power Requirements

(a) A duplex NEMA5-20R receptacle serviced by a single 20Amp circuit shall be installed at a

minimum of every three feet (3’) at 18” AFF on all four (4) walls in all TR.

(b) A quad NEMA5-20R serviced by two 20Amp circuits, one circuit per duplex receptacle, shall

be provided at the base of each floor-mounted equipment rack. The installation method shall

not interfere with any horizontal or riser cable routing into the management, owner provided

equipment placement or create the potential for EMI.

(c) Any special receptacle and power needs will be specified on an individual project basis. Please

see current Information Technology Department project contact for locations and quantities of

special receptacles.

Section 5.04 Equipment Cabinet Power Requirements

(a) All equipment cabinets shall receive a duplex NEMA5-20R serviced by a single 20AMP circuit

mounted inside of the equipment cabinet in the top right corner in manner that does not interfere

with the locking mechanism of the cabinet or equipment mounting.

Page 67: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 11 Structured Cabling Standards-Version 7.0

Article 6. Telecommunications Systems Grounding/Bonding

Section 6.01 Design

(a) Grounding and bonding systems shall be designed using the TIA-942, ANSI/J-STD- 607-A,

NEC 800.90(A), NEC 250 and NFPA 780 standards. Whenever two or more standards are in

conflict with one another, the more stringent standard applies.

Section 6.02 Specific Grounding Requirements

(a) Relocatable Classroom Grounding and Bonding Requirements

(i) A TBB shall be installed in a relocatable classroom TR’s equipment cabinet (EC) and shall be

bonded directly to the nearest electrical panel ground using a green insulated 6 AWG

conductor. In cases where running a ground conductor to the nearest electrical panel is not

possible, a ground conductor shall be bonded to the structural steel of the relocatable

classroom.

Article 7. Environmental Requirements for Telecommunications Rooms

Section 7.01 Room Conditioning Requirements

(a) A single room AC unit shall be installed in the MTR and each TR located in a building to allow

the temperature in each MTR and TR to be maintained at the optimum level separate from the

building HVAC systems.

Section 7.02 Temperature Requirements

(a) All MTRs and TRs should be kept at a temperature range of 68-75 degrees Fahrenheit per

BICSI TDM Ch 8-19.

Page 68: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 12 Structured Cabling Standards-Version 7.0

Article 8. Horizontal Structured Cabling-- Cabling and connectivity installed in any St

Johns County School District building must carry at a minimum a 20 year warranty through the

cable manufacturer that will apply to the complete end-to-end installed solution. EIA/TIA

Standard 568B wiring scheme shall be used for all horizontal cabling terminations. Horizontal

Cat6 copper cable must be rated at 250 Mhz or better and must be appropriate and suitable for

the installation environment, whether plenum or non-plenum, for which it is destined Cabling

contractors shall possess Panduit PCI and Corning NPI/EWP manufacturer certifications.

Section 8.01 Approved Horizontal Copper Cabling Manufacturers and Models

(i) Belden DataTwist 2400 (non-bonded or bonded-pair) (minimum)

(ii) Panduit TX6 (minimum)

(iii) General GenSpeed 6000 (minimum)

Section 8.02 Horizontal Cabling Color Codes

The jacket color for all horizontal data cable installed in St Johns County School District building shall

follow the color codes listed below.

(a) Data- Yellow jacket

(b) Voice- Green jacket

(c) Wireless Access Point- Blue jacket

(d) Security, fire, building automation device or audio visual controller- White jacket

Page 69: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 13 Structured Cabling Standards-Version 7.0

Section 8.03 Communications Work Area Outlets (WAO)

(a) Administrative WAO (AWAO)

(i) An administrative WAO should consist of one (1) Cat6 voice connection and one (1) Cat6 data

connection.

(ii) Each administrative area/office shall have a minimum of two administrative WAOs on

opposite sides of the room and each WAO shall be no more than two feet away from power.

(b) Teacher WAO (TWAO)

(i) A teacher WAO shall consist of one (1) Cat6 voice connection, one (1) Cat6 data connection.

(ii) Each classroom and resource room shall have one teacher WAO and each WAO shall be no

more than two feet away from power

(c) Workrooms/Storage Rooms/School Store WAO (SWAO)

(i) A Workroom/Storage Room/School Store WAO shall consist of one (1) Cat6 voice connection

and one (1) Cat6 data connection

(ii) Each Workroom/Storage Room/School Store shall have one Workroom/Storage Room/School

Store WAO that is no more than two feet away from power.

(d) Classroom\Resource Room WAO (CWAO)

(i) A classroom WAO shall consist of two (2) Cat6 data connections

(ii) Each classroom and resource room shall have a minimum of two WAOs and each WAO should

be no more than two feet away from power.

(e) Media Center WAO (MWAO)

(i) A Media Center WAO shall consist of four (4) Cat6 data connections.

(ii) The exact quantity and placement of Media Center WAOs will be determined by room size and

furniture layout.

(f) Kitchen/Cafeteria Manager Office WAO (KWAO)

(i) A Kitchen/Cafeteria Manager Office WAO shall consist of one (1) Cat6 data connections and

(2) Cat6 voice connections terminated using shuttered jacks.

Page 70: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 14 Structured Cabling Standards-Version 7.0

(g) Wireless Access Point (WAP) WAO (WAP)

(i) A wireless access point WAO shall consist of two (2) Cat6 data connections

(ii) The exact quantity and placement of Wireless Access Point WAOs will be determined by

building size and layout. It should be assumed that ALL areas of a building shall require

complete, full, and redundant coverage. WAP WAOs shall be installed above the drop ceiling

and terminated in a 2 position surface mount (biscuit) box (Panduit part # CBXS2EI-A) w/ 10’

Page 71: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 15 Structured Cabling Standards-Version 7.0

of service loop at the station end to allow for a wireless access point to be placed where needed

by the IT Department. (see Section 10 for Wireless LAN Design requirements)

(iii) All WAP cables shall be terminated together on a patch panel that does not contain voice and

data cables

(h) Cafeteria Point of Sale WAO (PWAO)

(i) A Cafeteria Point of Sale WAO shall consist of two (2) Cat6 data connections terminated using

shuttered jacks.

(i) Classroom AV WAO (AVWAO)

(i) A Classroom AV WAO shall consist of one (1) Cat6 data connection to provide data

connectivity classroom AV interface panel.

(ii) Drop shall terminate in a male RJ-45 connector at the station side.

Section 8.04 Patch panels and Faceplates

(a) Modular patch panels are to be used for horizontal copper connectivity. Approved

manufacturers are Panduit (Part # CPP24FMWBL 24 port unloaded or Part# CPP48FMWBL 48

port unloaded).

(b) Faceplates will have two (2) or four (4) positions and must be angled. Only Panduit Part #

CFPSE4EI (4 port only).

Section 8.05 Cat6 Modular Jack Color Codes and Part Numbers- Color codes shall be used for all

modular jacks including both station and telecommunications rack side.

(a) Yellow- Data

(i) Panduit part # CJ688TGYL

(b) Green – Voice

(i) Panduit part # CJ688TGGR

(c) Blue – Wireless

(i) Panduit part # CJ688TGBU

(d) Red – Telco Provider Demark Extension

(i) Panduit part # CJ688TGRD

(e) White – Building controls connections to include security, fire, BMS/EMS, and Classroom A/V

(i) Panduit part # CJ6X88TGIW

Page 72: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 16 Structured Cabling Standards-Version 7.0

Article 9. Backbone Cabling and Installation

Section 9.01 Copper Backbone Cabling

(a) All Copper Backbone cabling shall consist of a Cat5 multi-conductor cable and a minimum of

25 pairs shall be installed between an MTR and TR.

Note: Copper backbone specifications for TRs that service relocatable classrooms fall under

section 13.03.

(i) Approved multi-conductor copper cabling manufacturers are as follows:

1) TBD

(b) Inside Riser Copper Cabling Terminations

(i) All inside riser copper backbone cabling shall terminate on standard Cat5 rated 110 punchdown

blocks that have been mounted to the installed backboard forming a wall field.

(c) Outside Plant Copper Cabling Terminations

(i) All copper backbone cabling that leaves the main footprint of the building and/or travels

underground shall be terminated, at both ends, on lightning protection. A cross connect

consisting of the same number of pairs as the installed outside rated cable should be installed

from the “in” or “protected” side of the lightning protector and terminate on Cat5 rated 110

punch down blocks that have been mounted to the installed backboard forming a wall field.

(d) Copper Backbone Cabling Cross Connects – The District uses a modular approach to its voice

cross connects and requires the installation of tie cables from the 110 block wall field, where

backbone cabling from TR(s) is terminated, to patch panels (part number below) mounted in

data racks in each MTR/TR.

(i) Standard MTR Cross Connect Requirements

1) A minimum of 50 pairs of Cat5 rated multi-conductor copper cabling shall be installed from

the 110 block wall field to the data rack that houses the site’s IP Voice Gateway and shall

terminate on standard 110-style Cat5 patch panels (Panduit Part #DP485E88TG) using 1

pair per patch panel port on the blue pair to serve as a cross connect. The District IT staff

will be responsible for making the final cross connects between the 110 side of the cross

connect and the 110 wall field made up of the 50 pair cables to the TRs during the IP Voice

Gateway installation to bring phone service to the TRs based on need.

(ii) Standard TR Cross Connect Requirements

1) Copper backbone cabling installed between a site’s MTR and a TR that does not require

lightning protection shall have 10’ of usable service located in the ladder rack and shall

terminate at the TR directly on on standard 110-style Cat5e patch panels (Panduit Part

#DP485E88TG) using 1 pair per patch panel port on the blue pair.

2) If the path from the MTR to the TR requires the use of lightning protection, a pigtail shall be

installed from the “in” or “protected” side of the lightning protection to a standard 110-style

Page 73: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 17 Structured Cabling Standards-Version 7.0

Cat5e patch panel (Panduit Part #DP485E88TG) located in the TR’s data cabling rack, using

1 pair per patch panel port on the blue pair at the patch panel end.

Section 9.02 Fiber Optic Backbone Cabling

(a) Approved Fiber Optic Connectivity Manufacturers- The manufacturers listed below are

approved. The proposed fiber optic cable and connectors must both be sourced from one of the

approved manufacturers.

(i) Corning

(b) Approved Fiber Optic Connectivity Product Lines

(i) Corning Pretium Rack and Wallmount Enclosures

(ii) Corning Pretium Unicam Connectors

(c) A minimum of twenty-four (24) strands of multimode and twelve (12) strands of single-mode

fiber optic cabling shall be installed between the building MTR and each building TR. Note:

Optical fiber backbone specifications for TRs that service relocatable classrooms fall under

section 13.03.

(d) Unless otherwise recommended by the manufacturer, all fiber cables shall be run in innerduct.

All strands will be terminated in the MTR/TR using approved SC type connectors in wall

mounted interconnect centers(must have prior Information Technology project contact

approval) or Pretium rack mounted LIUs equipped with sufficient ports, slack storage space and

splice tray storage, if required, to terminate and secure all fibers.

(e) Fiber Optic Cable Requirements

(i) The fiber optic cabling included in the solution must be optimized for a 10Gbps VCSEL system

(OM3/OM4).

(ii) All multimode fiber optic backbone cabling shall have a core diameter of 50 microns and a core

cladding diameter of 125 microns.

(iii) All single-mode fiber optic backbone cabling installed shall have a core diameter of 8-9 microns

and a core cladding diameter of 125 microns and shall be terminated with blue SC connectors.

Page 74: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 18 Structured Cabling Standards-Version 7.0

Article 10. Wireless Voice and Data Network Design Requirements

Section 10.01 Wireless Design Requirements

(a) The exact quantity and placement of Wireless Access Point WAOs will be determined by

building size and layout. It should be assumed that ALL areas of every building shall require

complete, full, and redundant coverage. Required areas include but are not limited to; the gym,

auditorium, cafeteria, media center, all administrative spaces, and all classroom and learning

spaces, outlying PE buildings, etc.

(b) SJCSD requires that a wireless WAO is installed in every room (including but not limited to

classrooms, conference rooms, storage rooms, offices, kitchen, etc) of the building with

common areas such as gym, cafeteria and auditorium receiving additional locations based on

size

(c) Signal strength requirements shall be built around current best practice standards for a heavily

utilized enterprise class wireless LAN that will support both data and wireless IP telephony. AP

quantity and placement shall be optimized for signal density with the target signal-to-noise-ratio

(SNR) of -67dB.

Page 75: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 19 Structured Cabling Standards-Version 7.0

Article 11. Labeling and Administration- EIA/TIA 606-A specification shall be used as a

guideline

Section 11.01 MTR/TR Identification

(a) MTR

(i) A building MTR shall be labeled as follows:

MTR-XXX

where XXX is the FISH number that will be permanently associated with the room. This label shall be

permanently mounted in plain view on both the inside and outside of the door for easy identification.

(b) TR

(i) A building TR shall be labeled as follows:

TR-XXX

where XXX is the FISH number that will be permanently associated with the room. This label shall be

permanently mounted in plain view on both the inside and outside of the door for easy identification.

Section 11.02 Horizontal Connectivity Labeling

(a) Patch Panel Labeling

(i) Each patch panel shall be labeled with a number in the top left corner. This number shall be in

ascending order from top left to right bottom.

(ii) Each port on a patch panel in a MTR or TR shall be labeled with the room number and an

uppercase letter, A-Z, that corresponds to the faceplate and port labels at the station side of

each link.

(b) Individual Horizontal Station Cable Labeling

(i) Each station cable shall be labeled 2” from the termination with a permanent, water resistant,

electronically generated, sticker-type label, using the following scheme:

TRXXX-Y-nnnV

Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands

for the number of the patch panel on which the cabling terminates in TRXXX and where nnn

stands for the FISH number of the room the drop is located in and the V is a consecutive

identifier (A,B,C,D,etc) for each cable in the room. In the event that a single room contains

more than 26 single connections double letter designations shall be used to accommodate the

connections over 26 (AA, BB, etc).

Page 76: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 20 Structured Cabling Standards-Version 7.0

(c) Work Area Outlet Faceplate Labeling

(i) A WAO faceplate shall be labeled using the following scheme:

Top of faceplate - TRXXX-Y

Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands

for patch panel # where the cabling terminates in TRXXX

Each individual outlet on the faceplate – nnnV

Where nnn stands for the FISH number of the room the drop is located in and the V is a

consecutive identifier (A,B,C,D,etc) for each cable in the room starting at the left side of the

room and working clockwise. In the event that a single room contains more than 26 single

connections double letter designations shall be used to accommodate the connections over 26

(AA, BB, etc).

Section 11.03 Backbone Connectivity Labeling

(a) Copper Backbone Cabling shall be labeled on the cable jacket, using a permanent water and

tear-resistant label, three times starting from the patch panel, wall block, or lightning protection

and working down the cable at 12” increments using the following scheme:

Ppair-MTRXXX-TRYYY

Where P stands for the number of pairs in the cable and XXX is the FISH number of the MTR or

TR the cable originates from and YYY is the FISH number of the TR the cable terminates in.

(i) Patch panels used to terminate copper backbone cabling shall be labeled in the top center of each

panel using the following scheme:

Ppair-MTRXXX-TRYYY

Where P stands for the number of pairs in the cable and XXX is the FISH number of the MTR or

TR the cable originates from and YYY is the FISH number of the TR the cable terminates.

(b) Fiber optic backbone cabling shall be labeled on the jacket using a permanent water and heat

resistant label, three times starting from the termination tray and working down the cable at 12”

increments using the following scheme:

Pstrand-S/MM-MTRXXX-TRYYY

Where P stands for the number of strands in the cable and either S or M stands for single-mode

or multimode fiber and XXX is the FISH number of the MTR or TR the cable originates from

and YYY is the FISH number of the TR the cable terminates in.

Page 77: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 21 Structured Cabling Standards-Version 7.0

Section 11.04 Special Use Outlet Labeling

(a) Wireless Access Point (WAP) WAOs shall be labeled on the biscuit box and on the T-bar of the

drop ceiling directly below the biscuit box with a Yellow ¾” permanent label in plain view

using the following scheme:

TRXXX-Y-WAP-RRR-V

Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands

for the number of the patch panel on which the cabling terminates in TRXXX , the WAP is a

constant, the RRR is the FISH number of the room or corridor that the WAP is located in, and

the V is a consecutive identifier (A,B,C,D,etc) for each WAP located in the same room or

corridor. In the event that a single area contains more than 26 wireless access points a double

letter consecutive identifier shall be used to accommodate the WAPs over 26 (AA, BB, etc).

(b) Media Link Controller (MLC) WAOs shall be labeled on the cable using a permanent cable label

using the following scheme:

TRXXX-Y-MLC-RRR-V

Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands

for the number of the patch panel on which the cabling terminates in TRXXX , the MLC is a

constant, the RRR is the FISH number of the room or commons area that the MLC panel is

located in, and the V is a consecutive identifier (A,B,C,D,etc) for each MLC panel. In the event

that a single building contains more than 26 MLC panels a double letter consecutive identifier

shall be used to accommodate the WAPs over 26 (AA, BB, etc). Note: MLC cables will not be

visible unless the MLC panel is removed from the wall. To see the cable label, remove the four

screws which secure it to the wall to expose the cable.

Page 78: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 22 Structured Cabling Standards-Version 7.0

Article 12. Testing and Documentation

Section 12.01 Testing shall follow all standards set forth in TIA/EIA-568-B.1, TIA/EIA-568-B.2,

TIA/EIA-568-B.3, TIA/EIA-TSB-140, TIA/EIA-526-14-A, and TIA/EIA-526-7

(a) Horizontal Copper Cabling

(i) Testing and certification of horizontal copper cabling shall be performed using the permanent

link method.

(b) Copper Backbone Cabling

(i) All copper backbone cabling shall be tested for continuity.

(c) Fiber Optic Backbone Cabling

(i) All fiber optic backbone cabling shall be tested and certified using the BICSI Tier 2 method for

testing optical fiber. A launch cable that is a minimum of 200 meters in length shall be utilized

during all OTDR tests to ensure accurate trace results.

Section 12.02 Documentation

(a) Submitting Test Results

(i) Cabling test results for Move, Add, or Change projects or Summer Relocatable Classroom

installs shall be submitted via electronic mail to the address below:

[email protected]

(ii) Cabling test results for large projects such as new schools and large scale additions and

renovations shall include each horizontal copper location and each backbone fiber strand and

must be submitted in triplicate in both of the following form (three each CD/DVD media):

1) Hard copy- Shall be neatly contained in a three-ring binder. The cover of the binder shall be

printed with, at a minimum, the following information, St Johns County school construction

name, school address, cabling contractor and their project manager’s name, and date of

cabling completion. The three-ring binder must have tabbed dividers labeled with the TR

that the tests originated separating each TR’s tests from the others.

2) Digital- CD or DVD media may be used and the files must be in the native database format

of the tester used for testing and certification. (Tab delimited, .CSV files, excel spreadsheets,

or other non-native file formats will not be accepted). The CD or DVD media must have a

computer generated label that includes at a minimum, the following information: St Johns

County school construction name, school address, cabling contractor and their project

manager’s name, and date of cabling completion. In addition to the test results in native

format each CD/DVD shall also contain an installable copy of all necessary proprietary

viewing software for the tester format used in the certification.

Page 79: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 23 Structured Cabling Standards-Version 7.0

Article 13. Relocatable Classroom Systems Specifications Structured cabling networks for relocatable classrooms are designed and installed to provide the

greatest scalability, flexibility and ease of management.

Section 13.01 Relocatable Classroom Conduit System Specifications (See diagrams 13.02a and 13.02d

for external conduit termination routing detail)

(a) All connectivity will originate from a pedestal, which should be a minimum of a 36” x 36” x

12” NEMA 3 rated (Acceptable Models - Cooper B-Line part number 363012RHCF or Hoffman

Cabinet part number A36H3612GQRLP) enclosure, securely mounted to/near the relocatable

classroom that houses the first TR installed. All future backbone cabling, both optical fiber and

Page 80: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 24 Structured Cabling Standards-Version 7.0

copper will originate from this enclosure. (See diagram 13.01a for pedestal buildout

requirements)

(b) A minimum of 2 ea 2” or 1 ea 4” conduit should be installed from the in-ground voice and data

network expansion box located closest to the pedestal mounted on/near the relocatable classroom

that is closest to the main building.

(c) A 2” conduit will be installed from each new relocatable classroom TR back to the pedestal using

the most direct path. A 12” x 12” pull box shall be installed at 150’ intervals or every 180 degrees

of bend (or two 90degree bends) in a conduit run to minimize strain on cables.

(d) External boxes shall be a minimum of 16” x 16” x 10” (Acceptable Model -Allied Moulded

Products part # AM1648RL ) and possess a minimum NEMA 3 rating.

(e) A minimum of a 1-1/2” conduit shall be installed in an unbroken path between a relocatable

classroom and nearest TR. Daisy chaining pipes between relocatable classrooms is prohibited

due to the added pull points, added distance, and 90 degree bends created.

(f) A single run of conduit between a relocatable classroom and a TR may contain no more than two

(2) 90 degree bends including the exit from the TR and entrance into the relocatable. Sweep bends

shall be used to minimize pull force needed.

(g) 1-1/2” conduits that will house horizontal copper cabling (Cat5e, Cat6, etc.) shall be no more than

220’ in length, not including turn-ups into the relocatable classroom, from TR to relocatable

classroom being served.

(h) No more than eight (8) cat6 gel-filled cables should be run in any 1-1/2” conduit between a TR

and relocatable classroom.

(i) All conduits shall be clearly marked at both ends and again every twenty-five feet (25’) w/

fluorescent orange spray paint to differentiate voice and data conduits from any other conduits

buried in the same trench.

Page 81: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 25 Structured Cabling Standards-Version 7.0

Diagram 13.01a – Voice and Data Pedestal for Relocatable Classrooms

Page 82: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 26 Structured Cabling Standards-Version 7.0

Section 13.02 Relocatable Classroom Horizontal Cabling and Connectivity Specifications

(a) A minimum of a 48” Hubbell Quad Cab (part # HSQ4826) shall be installed in the relocatable

that will serve as the TR. A 38”x28” backboard shall be painted on all six sides with fire-retardent

paint and affixed to the wall. The cabinet shall be mounted to the plywood and set on two sections

of uni-strut to relieve load strain from the wall. (see Diagram 13.02a and 13.02b and Image

13.02a and 13.02b for placement detail)

(b) Each relocatable classroom shall receive five (5) gel-filled Cat6 data cables.

(i) See diagram 13.02c for drop location placement detail

(ii) A single drop is to be installed in the ceiling and terminated with a Blue jack in a 2position surface

mount box (Panduit part # CBXS2EI-A or AMP part # 1116698-3) w/ 10’ of service loop at the

station end to allow for a wireless access point to be placed where needed by the IT Department.

(iii) Approved Horizontal Copper Cabling Manufacturers

1) See Article 8 for horizontal copper cabling requirements.

(c) Connectivity

(i) Copper Connectivity

1) Modular Patch panels are to be used for copper connectivity. Either Panduit (Part #

CPP24FMWBL 24 port unloaded or Part# CPP48FMWBL 48 port unloaded) or AMP (Part #

1116749-1 24 port unloaded or 1375119-1 48 port unloaded).

2) Modular Cat5E jacks are to be used. Colors for each jack at the panel side should match the

color at the station side and follow the owner’s color code.

a) Yellow- Data

i) Panduit part # CJ688TGYL

ii) AMP part # 1375187-8

b) Green – Voice

i) Panduit part # CJ688TGGR

ii) AMP part # 1375187-9

c) Blue – Wireless

i) Panduit part # CJ688TGBU

ii) AMP part # 1375187-6

3) Work area outlets

Page 83: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 27 Structured Cabling Standards-Version 7.0

a) Faceplates will have two (2) or four (4) positions and must be angled. Only Panduit Part #

CFPSE4EI 4 port only or AMP Part #1375155 2 port or Part # 406185 4 port will be accepted.

(ii) Management

1) Horizontal- Panduit finger duct where applicable. Space will usually prevent the use of

management in cabinets. If management is requested, use Panduit part # WMPLFSE

Page 84: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 28 Structured Cabling Standards-Version 7.0

Diagram 13.02a – Rear Elevation Telecom Room (TR) Relocatable

Page 85: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 29 Structured Cabling Standards-Version 7.0

Diagram 13.02b – Telecom Room (TR) Relocatable Overhead

Page 86: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 30 Structured Cabling Standards-Version 7.0

Diagram 13.02c – Typical Relocatable Work Area Outlet Layout

Page 87: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 31 Structured Cabling Standards-Version 7.0

Diagram 13.02d - Rear Elevation - Typical Relocatable

Page 88: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 32 Structured Cabling Standards-Version 7.0

Section 13.03 Relocatable Classroom Backbone Cabling Specifications – (See Diagram

13.01a for installation detail)

(a) Optical Fiber Backbone Cabling

(i) All fiber optic cabling installed for relocatable classrooms shall meet the

specifications outlined in section 9.02

(ii) 24 strands of 50/125 OM3 multimode optical fiber shall be installed from the

main building MTR located nearest to the newly installed relocatable classroom

that will serve as the first TR. All 24 strands of multimode optical fiber shall

terminate in an optical fiber enclosure located inside the 36”x36” pedestal

mounted on/near the portable that will house the first TR. SC connectors shall

be used to terminate all 24 strands of multimode optical fiber.

(iii) Six (6) strands of muilti-mode optical fiber shall be installed from the 36”x36”

pedestal located on/outside the first relocatable classroom TR to each

relocatable classroom TR. All six (6) strands shall be terminated at both ends

using SC connectors.

(iv) The connectors for each 6 strand cable installed between the data pedestal and a

TR portable shall be mounted in a standard 1U LIU at the TR portable side and

in a Panduit Multi-Media Surface-Mount Fiber Enclosure with 3 ea Duplex SC

Minicom modules as needed at the data pedestal side.

(v) All optical fiber backbone labeling shall follow the labeling scheme detailed in

Section 10.03b

(b) Copper Backbone Cabling

(i) A minimum of 50 pairs of Category 3 copper backbone cabling shall be installed

from the main building MTR/TR located nearest to the pedestal that has been

installed on/near the relocatable classroom that will serve as the first TR. All 50

pairs shall terminate on the “In” side of an appropriately sized 110 style

lightning protector located inside the 36”x36” pedestal.

(ii) A maximum of 12 pairs of copper backbone cabling shall be installed from the

36”x36” pedestal located on/outside the first relocatable classroom TR to each

relocatable classroom TR. Every pair of each 12 pair cable shall be terminated

on the “Out” side of the lightning protection installed in the 36”x36” pedestal

using the next available 12 pairs of the 100 pair cable.

(iii) All copper backbone cabling installed from a pedestal to a relocatable classroom

TR shall terminate at the relocatable classroom side on an appropriately sized

Circa 4000N building entrance terminal.

(iv) All copper backbone cabling shall terminate in the MTR/TR rack and relocatable

classroom TR cabinet on standard Cat5e patch panels (Panduit Part

Page 89: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 33 Structured Cabling Standards-Version 7.0

#DPA485E88TG or AMP Part #406331-1) for voice 1 pair per port on the blue

pair at both ends.

(v) All copper backbone cabling shall follow the labeling scheme detailed in Section

10.03a

Page 90: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 34 Structured Cabling Standards-Version 7.0

Article 14. Classroom Audio/Visual (AV) Systems

Section 14.01 General Information – The St. Johns County School District classroom

AV standard utilizes a combination of projectors, interactive panels and ultra-short throw

projectors, classroom sound reinforcement, and document cameras (where appropriate) to

provide teachers and students with a multimedia rich learning environment. Wall-

mounted interactive panels range in size from 65”-84” diagonal and are utilized in typical

new construction classrooms, common areas and training/conference rooms. Relocatable

classrooms (sometimes referred to as modular or portable classrooms) receive similar

65”-70” diagonal interactive panel which are mounted to a purpose-built wheeled cart.

Retrofit classroom AV solutions will be handled on a case-by-case basis, which will take

into account pre-existing hardware and room requirements.

Section 14.02 Classroom AV Systems Detail

(a) Classroom/Common Area/Extended Learning Area (ELA) Sound

Reinforcement – Each classroom, common area and ELA shall receive a

classroom sound reinforcement system to ensure consistent delivery of teacher

voice and digital content. (Gym, Cafetorium, Auditorium, Café systems shall be

purpose/custom designed to fit the space.)

(i) System shall consist of an amplifier in each learning area, 1, 2 or 4 ceiling

mounted speakers based on manufacturer’s recommended placement and

coverage specifications and 2 wireless teacher microphones (1 pendant mic with

necklace/lanyard and 1 handheld) with rechargeable batteries and charging

station.

1) Large format rooms such as ELA may require additional speakers. Designers

should again refer to manufacturers specifications for requirements.

(ii) System may utilize RF, infrared or other approved means to transmit wireless

signals between amplifiers, wireless microphones and/or speakers as needed.

(iii) System must have the ability to duck program audio in the event that a classroom

receives a page from the building’s paging system.

(b) Interactive Display Panel – Large interactive display panel – wall mounted or

cart mounted and serves as the primary display for newer construction and

retrofits in classroom and common area or extended learning areas.

(i) Panel Inputs/Outputs:

1) Inputs: 4 HDMI, 1 VGA, 1 3.5 mm audio, 4 USB A (2.0/3.0)

2) Outputs: Coax

Page 91: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 35 Structured Cabling Standards-Version 7.0

(ii) LED lamp life: 30,000 hours minimum

(iii) 3 year warranty

(iv) Integrated speakers

(v) Tempered glass

(vi) 10 points of touch minimum

(vii) Onboard operating system capable of supporting common interactive software

(viii) Includes interactive software

(ix) Capable of integrating with onboard Windows computer

(x) 65”- 84” diagonal screen size

(xi) Resolution to be 1080p or higher

(xii) Reference the District standard Interactive Panel model

(c) Multimedia Projector - (ceiling or ultra-short-throw wall-mounted) – the

projector may serve as the primary display in the classroom and common area

that does not have a large format interactive display. The image is projected onto

a classroom whiteboard or specified screen. The projector displays video from

laptop, document camera and TV tuner via HDMI (preferred) or VGA and/or

composite video inputs. Contact Information Technology department for current

projector manufacturer/model information.

(i) Projector Throw Distance –

1) Standard Ceiling Mounted Projector - Projector shall be centered in the

classroom facing the primary instructional wall and mounted between 13’

and 15’ from the projection surface.

2) Ultra Short-Throw Classroom/Common Area/Extended Learning Area –

Projector shall be oriented on the white board of the primary instructional

wall. Mounted per manufacturer’s recommendation.

(ii) Projector Input/Output Requirements

1) Inputs: 2 x VGA, 2x HDMI v1.3 or higher, S-Video, 2 x 3.5mm audio, RCA

Stereo Audio, USB – A Power, RS-232, RJ45

2) Outputs: VGA, 3.5mm audio

(iii) Minimum Classroom Projector Performance Specifications (Ultra Short-Throw

and Standard):

1) Native Resolution – WXGA (1280 x 800)

Page 92: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 36 Structured Cabling Standards-Version 7.0

2) Brightness -- 3600 lumens or higher (LCD or TLP or LED)

3) Contrast Ratio – Up to 22000:1

4) Please reference the District standard models

(iv) Minimum Large space Projector Performance Specifications:

1) Native Resolution – WUXGA (1920 x 1200)

2) Brightness -- 6000 lumens or higher (LCD or TLP or LED)

3) Contrast Ratio – Up to 10,000:1

(v) Warranty – 3-year advance replacement (projector) / 1 year unlimited hour (lamp

life)

(d) Document Camera - presents documents and live video through projector and

provides video switching capability for laptop. Laptop is connected to document

camera, which controls whether laptop video or document camera video is sent

through to display

(i) Inputs:

1) HDMI, VGA (active pass through from computer), USB 2.0

(ii) Outputs:

1) HDMI, VGA

(iii) Please reference the District Standard model

(e) Surge Protector Power Strip – Must provide at least five (5) outlets and have a

25’ input power cable with NEMA5-15P plug. Surge strip must protect

equipment from surges in electrical current

(f) Projection Surface – Projection surface for classroom and commons area

projectors can be pull-down screens or white board surfaces depending upon the

application. Classroom screens can be flush mounted to wall or hung from T-bar

depending on room requirements. Large format areas use pull-down or

motorized screens with specifications and sizing to meet design requirements.

1) New Construction Classroom Spaces, Common Areas, Extended Learning

Areas - NA, uses interactive panel.

2) Retrofit Classroom Spaces- Contact IT dept.

3) Common Areas/ELA – Contact IT dept.

4) Large Format Spaces (media center, cafeteria, gym, etc.) - Spec and size per

design needs.

Page 93: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 37 Structured Cabling Standards-Version 7.0

Section 14.03 Classroom Audio/Visual System Configuration Diagrams

(a) New Construction Classroom Components and Detail

Page 94: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 38 Structured Cabling Standards-Version 7.0

Page 95: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 39 Structured Cabling Standards-Version 7.0

(b) Large Room, Non-Standard Space Components

Page 96: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 40 Structured Cabling Standards-Version 7.0

(c) Retrofit Classroom and Common Area/ELA Components and Detail

Page 97: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 41 Structured Cabling Standards-Version 7.0

Page 98: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

IT Department

Revised Mar 2017 42 Structured Cabling Standards-Version 7.0

Article 15. Applicable Industry Standards

BICSI, Telecommunications Distribution Methods Manual

ANSI/TIA/EIA-568B, Commercial Building Telecommunications Cabling Standard

TIA/EIA TSB-67 Transmission Performance Specifications for Field Testing of

Unshielded Twisted Pair Cabling Systems

TIA/EIA TSB-140 Additional Guidelines for Field-Testing Length, Loss and Polarity of

Optical Fiber Cabling Systems

TIA/EIA TSB-75, Additional Horizontal Cabling Practices for Open Offices.

ANSI/TIA/EIA-569A, Commercial Building Standard for Telecommunications

Pathways and Spaces

ANSI/TIA/EIA-606A, Administration Standard for Telecommunications Infrastructure of

Commercial Buildings

ANSI/TIA/EIA-607, Commercial Building Grounding and Bonding Requirements for

Telecommunications

TIA-942, Telecommunications Infrastructure Standard for Data Centers

ANSI/NFPA-70

NEC, National Electrical Code

NFPA-101, Life Safety Code

NFPA-780, Standard for the Installation of Lightning Protection Systems

Other applicable NFPA Codes.

ANSI/IEEE Codes, All Applicable Codes.

NESC, National Electrical Safety Code (ANSI/IEEE C-2, overhead and underground

telecommunications cable).

Local Uniform Building Codes

Page 99: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-1

SECTION 32 32 23 - CONCRETE SEGMENTAL RETAINING WALL SYSTEM

PART 1 - GENERAL

1.01 DESCRIPTION

A. Work consists of furnishing and construction of an Anchor Vertica Pro Retaining Wall System (or Equivalent) in accordance with these specifications and in general conformity with the lines, grades, design, and dimensions shown on the plans.

B. Earthwork includes: 1. Preparing Foundation Soil and Retained Soil to the lines and grades shown on the

construction drawings; 2. Furnishing and installing Leveling Pad, Reinforced Fill (where required) and Low

Permeability Soil (where required) to the lines and grades shown on the construction drawings; and,

C. Installation work includes: 1. Furnishing and installing Vertica Pro Concrete Facing Units (or Equivalent) and Unit Fill

to achieve the lines and grades shown on the construction drawings. 2. Furnishing and installing Geosynthetic Reinforcement and Separation Geotextile of the

type, size, location and lengths designated on the construction drawings (if required). 3. Furnishing and installing Subsurface Drainage System, including necessary fittings, of

the type, size, and location designated on the construction drawings.

1.02 RELATED SECTIONS

A. Section 01270 – Unit Prices

B. Section 02300 – Earthwork

1.03 REFERENCES

A. American Association of State Highway Transportation Officials (AASHTO)

1. AASHTO Standard Specifications for Highway Bridges 2. AASHTO M 288 Geotextile Specifications for Highway Applications 3. AASHTO M 252 Corrugated Polyethylene Drainage Pipe 4. AASHTO National Transportation Product Evaluation Program (NTPEP)

B. American Society for Testing and Materials (ASTM)

1. ASTM C140 Standard Test Methods for Sampling and Testing Concrete Masonry Units and Related Units

2. ASTM C1262 Standard Test Method for Evaluating the Freeze-Thaw Durability of Manufactured Concrete Masonry Units and Related Concrete Units

3. ASTM C1372 Standard Specification for Segmental Retaining Wall Units 4. ASTM D448 Standard Classification for Sizes of Aggregate for Road and Bridge

Construction 5. ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil

Using Standard Effort (12,400 ft-lbf/f3)(600 kN-m/m3) 6. ASTM D1556 Standard Test Method for Density and Unit Weight of Soil In Place by the

Sand Cone Method 7. ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil

Using Modified Effort (56,000 ft-lbf/f3)(2700 kN-m/m3) 8. ASTM D2487 Standard Classification of Soils for Engineering Purposes (Unified Soil

Classification System) 9. ASTM D2922 Standard Test Methods for Density of Soil and Soil-Aggregate In Place by

Nuclear Methods (Shallow Depth)

Page 100: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-2

10. ASTM D3034 Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer pipe and Fittings

11. ASTM D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils

12. ASTM D4491 Standard Test Method for Water Permeability of Geotextiles by the Permittivity Method

13. ASTM D4595 Standard Test Method for Tensile Properties of Geotextiles by the Wide-Width Strip Method

14. ASTM D4873 Standard Guide for Identification, Storage and Handling of Geosynthetics 15. ASTM D5084 Standard Test Method for Measurement of Hydraulic Conductivity of

Saturated Porous Materials Using a Flexible Wall Permeameter. 16. ASTM D5262 Standard Test Method for Evaluating the Unconfined Tension Creep

Behavior of Geosynthetics 17. ASTM D5321 Standard Test Method for Determining the Coefficient of Soil and

Geosynthetic or Geosynthetic and Geosynthetic Friction by the Direct Shear Method 18. ASTM D5818 Standard Practice for Obtaining Samples of Geosynthetics from a Test

Section for Assessment of Installation Damage 19. ASTM D6637 Standard Test Method for Determining Tensile Properties of Geogrids by

the Single or Multi-Rib Tensile Method 20. ASTM D6638 Standard Test Method for Determining Connection Strength Between

Geosynthetic Reinforcement and Segmental Concrete Units 21. ASTM D6916 Standard Test Method for Determining the Shear Strength Between

Segmental Concrete Units 22. ASTM D6706 Standard Test Method for Measuring Geosynthetic Pullout Resistance in

Soil 23. ASTM F405 Standard Specification for Corrugated Polyethylene (PE) Tubings and

Fittings 24. ASTM G51 Standard Test Method for Measuring pH of Soil for Use in Corrosion Testing

C. Federal Highway Administration

1. Samtani, Naresh C., Christopher, B., and Berg, R., “Design and Construction of Mechanically Stabilized Earth Walls and Reinforced Soil Slopes”, Volumes 1 and 2, Federal Highway Administration Report Nos. FHWA-NHI-10-024 and FHWA-NHI-10-025, November 2009.

2. Elias, V., Fishman, K., Christopher, B., and Berg, R., “Corrosion/Degradation of Soil Reinforcements for Mechanically Stabilized Earth Walls and Reinforced Soil Slopes”, Federal Highway Administration Report No. FHWA-NHI-09-087, November 2009.

D. National Concrete Masonry Association (NCMA) 1. NCMA Design Manual for Segmental Retaining Walls, Third Edition, 2010

1.04 DEFINITIONS

A. Segmental Retaining Wall (SRW) Units: Dry-stacked concrete masonry units used as the

retaining wall fascia.

B. Reinforced Fill: Soil which is used as fill behind the SRW unit and within the reinforced soil mass (if applicable).

C. Unit Fill and Drainage Aggregate: Material used (if applicable) within, between, and directly

behind the concrete retaining wall units.

D. Geotextile Separation Fabric: Material used for separation and filtration of dissimilar soil types.

E. Foundation Soil: Soil mass supporting the leveling pad and reinforced soil zone of the retaining wall system.

Page 101: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-3

F. Retained Soil: The soil mass located behind the reinforced soil zone, either undisturbed native

soils or compacted fill.

G. Leveling Pad: A level surface consisting of crushed stone, sand and gravel or unreinforced concrete placed to provide a working surface for placement of the SRW unit.

H. Geosynthetic Reinforcement: Polymeric material designed specifically to reinforce the soil mass.

I. Pre-fabricated Drainage Composite: three-dimensional geosynthetic drainage medium

encapsulated in a geotextile filter, used to transport water.

J. Subsurface Drainage System: horizontal pipe encapsulated within drainage aggregate at or near the base of the reinforced soil to facilitate removal of water from the wall system.

K. Low Permeability Soil: Clay soil or low permeability geosynthetic used to prevent water percolation into the drainage zone and reinforced backfill behind the wall.

L. Global Stability: The general mass movement of a soil reinforced segmental retaining wall

structure and adjacent soil mass.

M. Project Geotechnical Engineer: A registered engineer who provides site observations, recommendations for foundation support/global stability, and verifies soil shear strength parameters.

1.05 SUBMITTALS / CERTIFICATION

A. Product Data 1. Product Data: Material description and installation instructions for each manufactured

product specified 2. Name and address of the production facility where the proposed facing units will be

manufactured. All units shall be manufactured at the same facility. 3. Notarized letter from the facing unit manufacturer stating that the units supplied for this

project are manufactured in complete compliance with this specification. The letter shall state that the units shown in the attached test reports are representative samples of the plants normal mix design and regular production runs.

4. Notarized letter from the reinforcement manufacturer stating that the geosynthetic reinforcement has been manufactured in complete compliance with the reinforcement manufacturer’s current NTPEP report.

B. Samples: 1. Contractor shall submit to the owner for approval, and retain for the balance of the

project, a minimum of one SRW unit that represents the range of texture and color permitted.

C. Test Reports: 1. Independent Laboratory reports indicating compressive strength, moisture absorption and

freeze-thaw durability of the concrete retaining wall units from the proposed production facility.

2. Independent test reports verifying the long-term design strength properties (creep, installation damage, and durability) and soil interaction properties of the geosynthetic reinforcement.

3. Independent test reports verifying the connection capacity between the geosynthetic reinforcement and the concrete retaining wall units.

D. Wall Design Engineer Qualifications:

Page 102: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-4

1. Current insurance policy verifying professional liability and errors and omissions insurance coverage for an aggregate and per claim limit of at least one million dollars ($1,000,000).

2. Notarized letter certifying the proposed retaining wall Design Engineer is a licensed professional engineer in the state of wall installation and has a minimum of 4 years and 200,000 square feet of retaining wall system design experience.

E. Retaining Wall Contractor Qualifications: 1. Notarized statement showing that the retaining wall contractor has installed a minimum of

100,000 square feet of segmental retaining walls. 2. The Retaining Wall Installer shall furnish five (5) project references of similar size and

scope to this project including the wall(s) height and square footage. References shall include the contact information of Owner or General Contractor.

F. Retaining Wall Design: 1. Shop Drawings: One digitally signed set of the retaining wall system design, including

wall elevation views, geosynthetic reinforcement layout, pertinent details, and drainage provisions. A registered professional engineer licensed in the state of wall installation shall sign and certify that the shop drawings are designed in accordance with the project civil plans and specifications.

2. Design Calculations: One digitally signed set of engineering design calculations prepared in accordance with the NCMA Design Manual for Segmental Retaining Walls, 3rd Edition or the AASHTO Standard Specifications for Highway Bridges (whichever is applicable). Analysis shall include Internal, External and Bearing Capacity Calculations and include the short term and long term loading conditions on the wall. A Global Stability analysis should be coordinated with the project geotechnical engineer and incorporated into the wall design.

1.06 DELIVERY, STORAGE AND HANDLING

A. SRW Units and Accessories: Deliver, store, and handle materials in accordance with manufacturer's recommendations, in such a manner as to prevent damage. Check the materials upon delivery to assure that proper material has been received. Store SRW units above ground on wood pallets or blocking. Remove damaged or otherwise unsuitable material, when so determined, from the site.

B. Exposed faces of SRW units shall be relatively free of chips, cracks, stains, and other imperfections detracting from their appearance, when viewed from a distance of 20 feet under diffused lighting.

C. Prevent mud, wet cement, adhesives and similar materials that may harm appearance of SRW

units, from coming in contact with system components.

D. Geosynthetics (including geosynthetic reinforcement, geotextile filter, pre-fabricated drainage composite) shall be delivered, stored, and handled in accordance with ASTM D4873.

1.07 EXTRA MATERIALS

A. Furnish Owner with 3 replacement SRW units identical to those installed on the Project. PART 2 - PRODUCTS

2.01 MATERIALS

A. SRW Units: Anchor Vertica Pro Retaining Wall Units"(or Equivalent) as manufactured under license from Anchor Wall Systems.

Page 103: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-5

1. Physical Requirements a. Meet requirements of ASTM C1372, except the unit height dimensions shall not

vary more than plus or minus 1/16 inch from that specified in the ASTM reference, not including textured face.

b. Unit Face Area: Not less than 1.0 square foot. c. Color: Selected by the [Architect] [Engineer] [Owner] from manufacturer's full

range of standard colors. d. Face Pattern Geometry: Straight e. Texture: Split Rock Face. f. Batter: Include an integral concrete shear connection flange/locator to provide a

9/16ths inch setback for each wall course.

B. Geosynthetic Reinforcement: Polyester fiber geogrid or geotextile, or polypropylene woven geotextile, as shown on the Drawings.

C. Leveling Pad 1. Aggregate Base: Crushed stone or granular fill meeting the following gradation as

determined in accordance with ASTM D448: Sieve Size Percent Passing

1 inch 100 No. 4 35 to 70 No. 40 10 to 35 No. 200 3 to 10

a. Base Thickness: 6 inches (minimum compacted thickness). 2. Concrete Base: Non-reinforced lean concrete base.

a. Compressive Strength: 3,000 psi (maximum). b. Base Thickness: At least 2 inches.

D. Unit Fill and Drainage Aggregate: Clean crushed stone or granular fill meeting the following

gradation as determined in accordance with ASTM D448: Sieve Size Percent Passing

1 inch 100 3/4 inch 75 to 100 No. 4 0 to 60 No. 40 0 to 50 No. 200 0 to 5

E. Reinforced Fill: Soil free of organics and debris and consisting of either GP, GW, SP, SW, or SM type, classified in accordance with ASTM D2487 and the USCS classification system and meeting the following gradation as determined in accordance with ASTM D448:

Sieve Size Percent Passing

1 inch 100 No. 4 20 to 100 No. 40 0 to 60 No. 200 0 to 35

1. Plasticity Index (PI) < 6 per ASTM D4318. 2. Maximum particle size for backfill is 1 inch unless field tests have been performed to

evaluate potential strength reduction to the geosynthetic reinforcement due to damage during construction per ASTM D5818.

3. Unsuitable soils are organic soils and those soils classified as SC, CL, ML, CH, OH, MH, OL, or PT.

Page 104: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-6

F. Low Permeability Soil: Clayey soil or other similar material which will prevent percolation into the

drainage zone behind the wall.

G. Drainage Pipe: Perforated or slotted PVC or corrugated HDPE pipe manufactured in accordance with D3034 and/or ASTM F405. All connectors and fittings shall match the piping material.

H. Geotextile Separation Fabric: Geotextile Separation fabric shall be minimum 4.0 oz/sy,

polypropylene, needle-punched nonwoven fabric.

I. Construction Adhesive: Exterior grade adhesive as recommended by the retaining wall unit manufacturer.

PART 3 – EXECUTION

3.01 EXAMINATION

A. Prior to commencing work, the retaining wall contractor shall examine the areas and conditions

under which the retaining wall system is to be erected, and notify the [Architect] [Engineer] [Owner] [General Contractor] in writing of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected.

B. Promptly notify the wall design engineer of site conditions which may affect wall performance, soil conditions observed other than those assumed, or other conditions that may require a reevaluation of the wall design.

C. Verify the location of existing structures and utilities prior to excavation.

3.02 PREPARATION

A. Ensure surrounding structures are protected from the effects of wall excavation.

B. Excavation support, if required, is the responsibility of the Contractor, including the stability of the excavation and its influence on adjacent properties and structures.

3.03 EXCAVATION

A. Excavate to the lines and grades shown on the Drawings. Over-excavation not approved by the

[Architect] [Engineer] [Owner (or Owner's representative)] will not be paid for by the Owner. Replacement of these soils with compacted fill and/or wall system components will be required at the Contractor's expense. Use care in excavating to prevent disturbance of the base beyond the lines shown.

3.04 FOUNDATION PREPARATION

A. Excavate foundation soil as required for footing or base dimension shown on the Drawings, or as directed by the Project geotechnical engineer.

B. The Project geotechnical engineer will examine foundation soil to ensure that the actual foundation soil strength meets or exceeds that indicated on the Drawings. At the direction of the project geotechnical engineer, remove soil not meeting the required strength. Oversize resulting excavation sufficiently from the front of the block to the back of the reinforcement, and backfill with suitable compacted backfill soils.

Page 105: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-7

C. The Project geotechnical engineer will determine if the foundation soils will require special treatment or correction to control total and differential settlement.

D. Fill over-excavated areas with suitable compacted backfill, as recommended by the Project

geotechnical engineer.

3.05 LEVELING PAD PREPARATION

A. Place base materials to the depths and widths shown on the Drawings, upon undisturbed soils, or foundation soils prepared in accordance with Article 3.04.

1. Extend the leveling pad laterally at least 6 inches in front and behind the lowermost SRW unit.

2. Provide aggregate base compacted to 6 inches thick (minimum) or as shown on the drawings.

3. The Contractor may at their option, provide a concrete leveling pad as specified in Subparagraph 2.01.C.2, in lieu of the aggregate base.

4. Where a reinforced footing is required by local code official, place footing below frost depth.

B. Compact aggregate base material to provide a level, hard surface on which to place the first course of SRW units.

C. Prepare base materials to ensure complete contact with SRW units. Gaps are not allowed. 3.06 ERECTION

A. General: Erect SRW units in accordance with manufacturer's instructions and recommendations, and as specified herein.

B. Place first course of concrete wall units on the prepared base material. Check units for level and alignment. Maintain the same elevation at the top of each unit within each section of the base course.

C. Ensure that foundation units are in full contact with the leveling pad.

D. Place concrete wall units side-by-side for full length of wall alignment. Alignment may be done by

using a string line measured from the back of the block. Gaps are not allowed between the foundation concrete wall units.

E. Place drainage aggregate between and directly behind the SRW. Fill any voids in SRW units with

drainage aggregate. Provide a drainage zone behind the SRW units a minimum of 12 inches wide to within 8 inches of the final grade. Cap the backfill and drainage aggregate zone with separation fabric and then 8 inches of low permeability soil.

F. Install drainage pipe at the lowest elevation possible to maintain gravity flow of water to outside of

the reinforced zone. Slope the main collection drainage pipe 2 percent (minimum) to provide gravity flow to the daylighted areas. Daylight the main collection drainage pipe through the face of the wall, and/or to an appropriate location away from the wall system at each low point or at 50 foot (maximum) intervals along the wall. Alternately, the drainage pipe can be connected to a storm sewer system at 50 foot (maximum) intervals.

G. Remove excess fill from top of SRW units and install next course. Ensure drainage aggregate and backfill are compacted before installation of next course.

H. Check each course for level and alignment. Adjust SRW units as necessary to maintain level and

alignment prior to proceeding with each additional course.

Page 106: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-8

I. Install each succeeding course. Backfill as each course is completed. Pull the SRW units forward until the locating surface of the SRW unit contacts the locating surface of the SRW units in the preceding course. Interlock wall segments that meet at corners by overlapping successive courses. Attach SRW units at exterior corners with adhesive specified.

J. Install geosynthetic reinforcement in accordance with geosynthetic manufacturer's

recommendations and the shop drawings. 1. Orient geosynthetic reinforcement with the highest strength axis perpendicular to the wall

face. 2. Prior to geosynthetic reinforcement placement, place the backfill and compact to the

elevation of the top of the wall units at the elevation of the geosynthetic reinforcement. 3. Place geosynthetic reinforcement at the elevations and to the lengths shown on the

Drawings. 4. Lay geosynthetic reinforcement horizontally on top of the SRW units and the compacted

backfill soils. Place the geosynthetic reinforcement within one inch of the face of the SRW units. Place the next course of SRW units on top of the geosynthetic reinforcement.

5. The geosynthetic reinforcement shall be in tension and free from wrinkles prior to placement of the backfill soils. Pull geosynthetic reinforcement hand-taut and secure in place with staples, stakes, or by hand-tensioning until the geosynthetic reinforcement is covered by 6 inches of loose fill.

6. The geosynthetic reinforcements shall be continuous throughout their embedment lengths. Splices in the geosynthetic reinforcement strength direction are not allowed.

7. Do not operate tracked construction equipment directly on the geosynthetic reinforcement. At least 6 inches of compacted backfill soil is required prior to operation of tracked vehicles over the geosynthetic reinforcement. Keep turning of tracked construction equipment to a minimum.

8. Rubber-tired equipment may pass over the geosynthetic reinforcement at speeds of less than 10 miles per hour. Turning of rubber-tired equipment is not allowed on the geosynthetic reinforcement.

3.07 BACKFILL PLACEMENT

A. Place reinforced fill, spread and compact in a manner that will minimize slack in the

reinforcement.

B. Place fill within the reinforced zone and compact in lifts not exceeding 6 inches (loose thickness) where hand-operated compaction equipment is used, and not exceeding 12 inches (loose thickness) where heavy, self-propelled compaction equipment is used.

1. Only lightweight hand-operated compaction equipment is allowed within 3 feet of the back of the retaining wall units. If the specified compaction cannot be achieved within 3 feet of the back of the retaining wall units, replace the reinforced soil in this zone with drainage aggregate material.

C. Compaction testing shall be done in accordance with ASTM D1556 or ASTM D2922.

D. Minimum Compaction Requirements for Fill Placed in the Reinforced and Retained Zone. 1. The minimum compaction requirement shall be determined by the project geotechnical

engineer testing the compaction. At no time shall the soil compaction requirements be less than 95 percent of the soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor maximum dry density (ASTM D1557)] for the entire wall height.

2. Utility Trench Backfill: Compact utility trench backfill in or below the reinforced soil zone to 98 percent of the soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor maximum dry density (ASTM D1557)], or as recommended by the Project geotechnical engineer. If the height from the utility to finish grade is higher than 30 feet, increase compaction to 100 percent of the standard Proctor density [modified Proctor

Page 107: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-9

density]. a. Utilities must be properly designed (by others) to withstand all forces from the

retaining wall units, reinforced soil mass, and surcharge loads, if any. 3. Moisture Content: Within 2 percentage points of the optimum moisture content for all wall

heights. 4. These specifications may be changed based on recommendations by the Project

geotechnical engineer. a. If changes are required, the Contract Sum will be adjusted by written Change

Order.

E. At the end of each day's operation, slope the last level of compacted backfill away from the interior (concealed) face of the wall to direct surface water runoff away from the wall face.

1. The General Contractor is responsible for ensuring that the finished site drainage is directed away from the retaining wall system.

2. In addition, the General Contractor is responsible for ensuring that surface water runoff from adjacent construction areas is not allowed to enter the retaining wall area of the construction site.

F. Refer to Article 3.10 for compaction testing. 3.08 CAP UNIT INSTALLATION

A. Apply adhesive to the top surface of the SRW unit below and place the cap unit into desired position.

B. Cut cap SRW units as necessary to obtain the proper fit.

C. Backfill and compact to top of SRW unit. 3.09 SITE CONSTRUCTION TOLERANCES

A. Site Construction Tolerance 1. Vertica Prol (or Equivalent) Alignment: Plus or minus 1-1/2 inches over any 10-foot

distance, with a maximum differential of 3 inches over the length of the wall. 2. Horizontal Location Control from Grading Plan

a. Straight Lines: Plus or minus 1-1/2 inches over any 10-foot distance. b. Corner and Radius Locations: Plus or minus 12 inches. c. Curves and Serpentine Radii: Plus or minus 2 feet.

3. Immediate Post Construction Wall Batter: Within 2 degrees of the design batter of the concrete retaining wall units.

4. Bulging: Plus or minus 1-1/4 inches over any 10-foot distance.

3.10 FIELD QUALITY CONTROL A. Installer is responsible for quality control of installation of system components.

B. The Owner or General Contractor, at their expense, will retain a qualified professional to perform

quality assurance checks of the installer's work.

C. Correct work which does not meet these specifications or the requirements shown on the Drawings at the installer's expense.

D. Perform compaction testing of the reinforced backfill placed and compacted in the reinforced

backfill zone. 1. Testing Frequency

a. One test for every 2 feet (Vertica Prol or Equivalent) of fill placed and compacted,

Page 108: PROJECT MANUAL EXPANSION, RENOVATIONS AND · PDF fileExpansion, Renovations, and Site Improvements Classroom Bldg ... 14 24 00 Hydraulic Elevators ... 23 05 48 Vibration and Seismic

Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition

CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-10

for every 50 lineal feet of retaining wall. b. Vary compaction test locations to cover the entire area of the reinforced soil

zone, including the area compacted by the hand-operated compaction equipment.

3.11 ADJUSTING AND CLEANING

A. Replace damaged SRW units with new units as the work progresses.

B. Remove debris caused by wall construction and leave adjacent paved areas broom clean.

3.12 MEASUREMENT AND PAYMENT

A. Measurement of segmental retaining wall shall be on an installed square foot basis computed on the total face area of wall installed. Wall face area includes the bottom of the base course to the top of the wall, and the entire length of the wall.

B. Payment for the wall will be made on a square foot basis at the agreed upon Contract Unit Price. 1. Payment should be considered full compensation for labor, materials, equipment and

testing required to install the wall in accordance with these specifications and the Drawings.

2. Quantities may vary from that shown on the Drawings depending on existing topography. Change to the total quantity of wall face area will be paid or withheld at the agreed upon Contract Unit Price.

END OF SECTION