Upload
lyhanh
View
219
Download
2
Embed Size (px)
Citation preview
PROJECT MANUAL
EXPANSION, RENOVATIONS AND
SITE IMPROVEMENTS
CLASSROOM BUILDING ADDITION
BID SUBMITTAL &
POD RENOVATION SUBMITTAL
NEASE HIGH SCHOOL
ST. AUGUSTINE, FLORIDA
FOR THE
ST. JOHNS COUNTY
SCHOOL DISTRICT
PROJECT NO. 2015-30
JUNE 10, 2016
MARCH 30 2017, Pod Renovation Submittal
ARCHITECT
10199 SOUTHSIDE BLVD., SUITE 103
JACKSONVILLE, FL 32256
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
TOC - 1
TABLE OF CONTENTS
Section Title
Specification sections edited or added for the Pod Renovation GMP and/or Phase 2 Sitework
Submittal, dated March 30 2017, are in bold font.
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 07 Seals Page
DIVISION 01 - GENERAL REQUIREMENTS
Provided by Construction Manager at Risk.
DIVISION 02 - EXISTING CONDITIONS
Not Applicable
DIVISION 03 - CONCRETE
03 30 00 Cast-in-Place Concrete
03 47 13 Tilt-Up-Concrete
DIVISION 04 - MASONRY
Not Used
DIVISION 05 - METALS
05 12 00 Structural Steel Framing
05 21 00 Steel Joist Framing
05 31 00 Steel Decking
05 40 00 Cold-Formed Metal Framing
05 50 00 Metal Fabrications
05 51 13 Metal Pan Stairs
05 58 13 Columns Covers (added by ASI-8)
05 73 00 Decorative Metal Railings
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 53 Miscellaneous Rough Carpentry
06 41 16 Plastic-Laminate-Faced Architectural Cabinets
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 17 00 Bentonite Waterproofing
07 18 00 Traffic Coatings
07 21 00 Thermal Insulation
07 22 00 Lightweight Insulated Concrete Roof Insulation
07 24 19 Water-Drainage Exterior Insulation and Finish System (EIFS)
07 52 16 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing
07 62 00 Sheet Metal Flashing and Trim
07 72 00 Roof Accessories
07 84 13 Penetration Firestopping
07 92 00 Joint Sealants
07 95 00 Expansion Joint Covers
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
TOC - 2
TABLE OF CONTENTS
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors And Frames
08 14 16 Flush Wood Doors
08 31 13 Access Doors and Frames
08 33 13 Coiling Counter Doors (section added for Pod Renovation Submittal,
dated Mar. 30, 2017)
08 41 13 Aluminum-Framed Entrances And Storefronts
08 44 23 Structural-Silicone-Glazed Curtain Walls
08 71 00 Door Hardware (section edited by the addition of Hardware Groups for
Pod Renovation Submittal, dated Mar. 30, 2017)
08 80 00 Glazing
08 88 13 Fire-Resistant Glazing
08 91 19 Fixed Louvers
DIVISION 09 - FINISHES
09 05 61.13 Moisture Vapor Emission Control
09 22 16 Non-Structural Metal Framing
09 25 13.13 Direct Applied Exterior Finish System
09 29 00 Gypsum Board
09 30 13 Ceramic Tiling
09 51 13 Acoustical Panel Ceilings
09 65 13 Resilient Base And Accessories
09 65 16 Hybrid Resilient Sheet Flooring
09 65 19 Resilient Tile Flooring and Stair Accessories
09 65 43 Linoleum Flooring
09 91 13 Exterior Painting
09 91 23 Interior Painting
09 96 00 High Performance Coatings
09 97 26 Cementitious Coatings
DIVISION 10 - SPECIALTIES
10 11 00 Visual Display Units
10 14 19 Dimensional Letter Signage
10 14 23.13 Room-Identification Signage
10 21 13.19 Plastic Toilet Compartments
10 21 23 Cubicle Curtains and Track
10 22 39 Folding Panel Partitions
10 26 13 Corner Guards
10 28 00 Toilet, Bath, and Laundry Accessories
10 44 13 Fire Protection Cabinets
10 44 16 Fire Extinguishers
10 51 13 Metal Lockers (section edited by the addition of Varsity Lockers for
Pod Renovation Submittal, dated Mar. 30, 2017)
10 51 23 Phenolic Lockers
10 73 00 Pre-Engineered Aluminum Protective Covers
DIVISION 11 - EQUIPMENT
Not Applicable
DIVISION 12 – FURNISHINGS
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
TOC - 3
TABLE OF CONTENTS
12 21 13 Horizontal Louver Blinds
12 36 61.16 Solid Surfacing Countertops
12 36 61.19 Quartz Agglomerate Countertops
DIVISION 13 - SPECIAL CONSTRUCTION
Not Applicable
DIVISION 14 - CONVEYING EQUIPMENT
14 24 00 Hydraulic Elevators
DIVISION 21 - FIRE SUPPRESSION
21 13 00 Fire Suppression Systems – Performance Based
DIVISION 22 - PLUMBING
22 05 00 Common Work Results for Plumbing
22 05 10 Basic Materials and Methods for Plumbing System
22 05 23 General-Duty Valves for Plumbing Piping
22 05 29 Hangers and Supports for Plumbing Piping and Equipment
22 05 53 Identification for Plumbing Piping and Equipment
22 07 00 Plumbing Insulation
22 11 16 Domestic Water Piping
22 11 19 Domestic Water Piping Specialties
22 11 23 Domestic Water Pumps
22 13 16 Sanitary Waste and Vent Piping
22 13 17 Rain Leader Piping
22 13 19 Sanitary Waste Piping Specialties
22 14 23 Storm Drainage Piping Specialties
22 14 29 Sump Pumps
22 33 00 Electric, Domestic Water Heaters
22 42 00 Plumbing Fixtures and Trim
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
23 05 00 Common Work Results for HVAC Systems
23 05 10 Basic Materials and Methods for HVAC Systems
23 05 13 Motor Requirements for HVAC Equipment
23 05 17 Adjustable Frequency Drives
23 05 18 Control Wiring
23 05 19 Meters, Gages and Accessories for HVAC Piping
23 05 23 General-Duty Valves for HVAC Piping.
23 05 29 Hangers and Supports for HVAC Systems
23 05 48 Vibration and Seismic Controls for HVAC
23 05 53 Identification for HVAC Piping and Equipment
23 05 80 Air Controls and Accessories
23 05 93 Testing, Balancing and Commissioning of HVAC Systems
23 07 00 Insulation
23 09 23 Instrumentation and Control Devices for HVAC
23 09 93 Sequence of Operations for HVAC Controls
23 21 13 Hydronic Piping
23 21 13.13 Underground Hydronic Piping
23 23 00 Refrigerant Piping
23 25 00 HVAC Water Treatment
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
TOC - 4
TABLE OF CONTENTS
23 31 00 HVAC Ducts and Casings
23 31 01 Shop Fabricated Ductwork
23 33 00 Air Duct Accessories
23 34 00 HVAC Fans
23 36 00 Air Terminal Units – Variable Volume
23 37 13 Grilles, Registers and Diffusers
23 41 00 Particulate Air Filtration
23 44 00 Air Purification System (section added for Pod Renovation Submittal,
dated Mar. 30, 2017)
23 73 00 Packaged Air Handling Units
23 81 43 Ductless Split-System Air Conditioner Unit Air Cooled
23 82 16 Coils
DIVISION 25 - INTEGRATED AUTOMATION
Not Applicable
DIVISION 26 - ELECTRICAL
26 05 00 Basic Electrical Materials and Methods
26 05 19 Conductors and Cables
26 05 26 Grounding and Bonding
26 05 29 Hangers and Supports for Electrical Systems
26 05 33 Raceways and Boxes
26 05 53 Electrical Identification
26 22 00 Dry Type Transformer
26 24 16 Panelboards
26 24 20 Enclosed Controllers
26 24 41 Switchboards
26 25 11 Interior Lighting
26 25 21 Exterior Lighting
26 26 60 Lightning Protection
26 27 26 Wiring Devices
26 28 16 Enclosed Switches and Circuit Breakers
26 43 13 Surge Protective Devices (SPDs)
DIVISION 27 - COMMUNICATIONS
27 51 23 Educational Intercommunications Program System (section edited for
Pod Renovation Submittal dated Mar. 30, 2017)
27 53 00 GPS Clock System
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 05 00 Data, Voice and Video
Attachment: SJCSD Voice and Data Structured Cabling Standards
updated to Version 7, March 2017 version
28 16 00 Intrusion Detection System
28 23 00 Video Surveillance System
28 31 11 Fire Alarm
DIVISION 31 - EARTHWORK
31 11 00 Clearing, Grubbing, and Stripping
31 15 00 Demolition
31 20 00 Earthwork
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
TOC - 5
TABLE OF CONTENTS
31 23 16 Excavation and Backfill for Utilities and Structures
31 23 19 Dewatering System
31 31 16 Termite Control
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 24 Concrete Reinforcement
32 05 25 Construction and Expansion Joints
32 12 16 Pavement
32 12 23 Prime and Tack Coats
32 14 13 Brick Paving
32 16 00 Sitework Concrete
32 17 23 Pavement Markings
32 31 13 Chain Link Fence
32 31 16 Welded Wire Fencing and Gates
32 32 23 Concrete Segmental Retaining Wall System (section added for
Phase 2 Sitework Submittal dated Mar. 30, 2017)
32 93 00 Plants
32 92 23 Grassing
DIVISION 33 - UTILITIES
33 11 00 Potable Water Mains
33 31 00 Gravity Sewers
33 40 00 Drainage
END OF TABLE OF CONTENTS
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
COILING COUNTER DOORS 083313 - 1
SECTION 083313 - COILING COUNTER DOORS (Pod J Renovation Only)
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Counter doors, manual push-up operation.
1.2 ACTION SUBMITTALS
A. Product Data: For each type and size of coiling counter door and accessory.
B. Shop Drawings: For each installation and for special components not dimensioned or detailed in
manufacturer's product data.
1. Include points of attachment and their corresponding static and dynamic loads imposed
on structure.
C. Samples: For each exposed product and for each color and texture specified.
1.3 CLOSEOUT SUBMITTALS
A. Maintenance data.
1.4 QUALITY ASSURANCE
A. Installer Qualifications: An entity that employs installers and supervisors who are trained and
approved by manufacturer for both installation and maintenance of units required for this
Project.
PART 2 - PRODUCTS
2.1 COUNTER DOOR ASSEMBLY (Pod J Renovation)
A. Counter Door: Coiling counter door formed with curtain of interlocking metal slats.
1. Manufacturers: Subject to compliance with requirements, available manufacturers
offering products that may be incorporated into the Work include, but are not limited to
the following:
a. C.H.I. Overhead Doors, Inc.
b. Clopay Building Products.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
COILING COUNTER DOORS 083313 - 2
c. Cookson Company.
d. Cornell Iron Works, Inc.
e. Overhead Door Corporation; Basis-of-Design Model 657 Stainless Steel.
f. Raynor.
g. Wayne-Dalton Corp.
B. Operation Cycles: Door components and operators capable of operating for not less than
20,000.
C. Door Curtain Material: Stainless steel.
D. Door Curtain Slats: Flat profile slats of 1-1/4-inch (32-mm) to 1-1/2-inch (38-mm) center-to-
center height.
E. Bottom Bar: Manufacturer's standard continuous channel or tubular shape, fabricated stainless
steel and finished to match door.
F. Curtain Jamb Guides: Stainless steel with exposed finish matching curtain slats. Provide
continuous integral wear strips to prevent metal-to-metal contact and to minimize operational
noise.
G. Integral Frame, Hood, and Fascia: Stainless steel.
1. Mounting: Between jambs.
H. Sill Configuration: Integral metal sill.
I. Locking Devices: Equip door with locking device assembly.
1. Locking Device Assembly: locking bars, operable from inside with thumb turn.
J. Manual Door Operator: Push-Up operator.
K. Door Finish:
1. Stainless-Steel Finish: No. 4 (polished directional satin).
2.2 DOOR CURTAIN MATERIALS AND CONSTRUCTION
A. Door Curtains: Fabricate coiling counter-door curtain of interlocking metal slats in a continuous
length for width of door without splices. Unless otherwise indicated, provide slats of thickness
and mechanical properties recommended by door manufacturer for performance, size, and type
of door indicated, and as follows:
B. Curtain Jamb Guides: Manufacturer's standard angles or channels and angles of same material
and finish as curtain slats unless otherwise indicated, with sufficient depth and strength to retain
curtain, to allow curtain to operate smoothly, and to withstand loading. Slot bolt holes for guide
adjustment. Provide removable stops on guides to prevent overtravel of curtain.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
COILING COUNTER DOORS 083313 - 3
2.3 HOODS
A. General: Form sheet metal hood to entirely enclose coiled curtain and operating mechanism at
opening head. Contour to fit end brackets to which hood is attached. Roll and reinforce top and
bottom edges for stiffness. Form closed ends for surface-mounted hoods and fascia for any
portion of between-jamb mounting that projects beyond wall face. Equip hood with
intermediate support brackets as required to prevent sagging.
B. Integral Frame, Hood, and Fascia: Welded stainless-steel sheet metal.
2.4 LOCKING DEVICES
A. Locking Device Assembly: Fabricate with cylinder lock, spring-loaded dead bolt, operating
handle, cam plate, and adjustable locking bars to engage through slots in tracks.
1. Lock Cylinders: Cylinders standard with manufacturer and keyed to building keying
system.
2. Keys: Three for each cylinder.
2.5 COUNTER DOOR ACCESSORIES
A. Integral Metal Sill: Fabricate sills as integral part of frame assembly of Type 304 stainless steel
in manufacturer's standard thickness with No. 4 finish.
2.6 COUNTERBALANCING MECHANISM
A. General: Counterbalance doors by means of manufacturer's standard mechanism with an
adjustable-tension, steel helical torsion spring mounted around a steel shaft and contained in a
spring barrel connected to top of curtain with barrel rings. Use grease-sealed bearings or self-
lubricating graphite bearings for rotating members.
B. Brackets: Manufacturer's standard mounting brackets of either cast iron or cold-rolled steel
plate.
2.7 MANUAL DOOR OPERATORS
A. General: Equip door with manual door operator by door manufacturer.
A. Push-up Door Operation: Design counterbalance mechanism so that required lift or pull for door
operation does not exceed 25 lbf (111 N).
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
COILING COUNTER DOORS 083313 - 4
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install coiling counter doors and operating equipment complete with necessary hardware,
anchors, inserts, hangers, and equipment supports; according to manufacturer's written
instructions and as specified.
B. Adjust hardware and moving parts to function smoothly so that doors operate easily, free of
warp, twist, or distortion. Lubricate bearings and sliding parts as recommended by
manufacturer.
3.2 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to
adjust, operate, and maintain coiling counter doors.
END OF SECTION 083313
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 1
SECTION 087100 - DOOR HARDWARE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Mechanical door hardware for the following:
a. Swinging doors.
2. Cylinders for door hardware specified in other Sections.
3. Electrified door hardware.
4. Surface mounted automatic door operators.
B. Related Requirements:
1. Section 064116 "Plastic-Laminate-Faced Architectural Cabinets" for cabinet door
hardware provided with cabinets.
2. Section 081113 "Hollow Metal Doors and Frames" for astragals provided as part of
labeled fire-rated assemblies and for door silencers provided as part of hollow-metal
frames.
3. Section 081416 "Flush Wood Doors" for astragals and integral intumescent seals
provided as part of labeled fire-rated assemblies.
4. Section 083113 "Access Doors and Frames" for access door hardware, including
cylinders.
5. Section 084113 "Aluminum-Framed Entrances and Storefronts" for entrance door
hardware, except cylinders.
1.3 PREINSTALLATION MEETINGS
A. Keying Conference: Conduct conference at Project site.
1. Conference participants shall include Installer's Architectural Hardware Consultant and
Owner's security consultant.
2. Incorporate conference decisions into keying schedule after reviewing door hardware
keying system including, but not limited to, the following:
a. Flow of traffic and degree of security required.
b. Preliminary key system schematic diagram.
c. Requirements for key control system.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 2
d. Requirements for access control.
e. Address for delivery of keys.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components
and profiles, and finishes.
B. Shop Drawings: For electrified door hardware.
1. Include diagrams for power, signal, and control wiring.
2. Include details of interface of electrified door hardware and building safety and security
systems.
3. Tag Samples with full product description to coordinate Samples with door hardware
schedule.
C. Door Hardware Schedule: Prepared by or under the supervision of Installer's Architectural
Hardware Consultant. Coordinate door hardware schedule with doors, frames, and related work
to ensure proper size, thickness, hand, function, and finish of door hardware.
1. Submittal Sequence: Submit door hardware schedule concurrent with submissions of
Product Data, Samples, and Shop Drawings. Coordinate submission of door hardware
schedule with scheduling requirements of other work to facilitate the fabrication of other
work that is critical in Project construction schedule.
2. Format: Use same scheduling sequence and format and use same door numbers as in door
hardware schedule in the Contract Documents.
3. Content: Include the following information:
a. Identification number, location, hand, fire rating, size, and material of each door
and frame.
b. Locations of each door hardware set, cross-referenced to Drawings on floor plans
and to door and frame schedule.
c. Complete designations, including name and manufacturer, type, style, function,
size, quantity, function, and finish of each door hardware product.
d. Description of electrified door hardware sequences of operation and interfaces with
other building control systems.
e. Fastenings and other installation information.
f. Explanation of abbreviations, symbols, and designations contained in door
hardware schedule.
g. Mounting locations for door hardware.
h. List of related door devices specified in other Sections for each door and frame.
D. Keying Schedule: Prepared by or under the supervision of Installer's Architectural Hardware
Consultant, detailing Owner's final keying instructions for locks. Include schematic keying
diagram and index each key set to unique door designations that are coordinated with the
Contract Documents.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 3
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Architectural Hardware Consultant.
B. Product Certificates: For each type of electrified door hardware.
1. Certify that door hardware for use on each type and size of labeled fire-rated doors
complies with listed fire-rated door assemblies.
C. Product Test Reports: For compliance with accessibility requirements, for tests performed by
manufacturer and witnessed by a qualified testing agency, for door hardware on doors located in
accessible routes.
D. Sample Warranty: For special warranty.
1.6 CLOSEOUT SUBMITTALS
A. Maintenance Data: For each type of door hardware to include in maintenance manuals.
B. Schedules: Final door hardware and keying schedule.
1.7 QUALITY ASSURANCE
A. Installer Qualifications: Supplier of products and an employer of workers trained and approved
by product manufacturers and of an Architectural Hardware Consultant who is available during
the course of the Work to consult Contractor, Architect, and Owner about door hardware and
keying.
1. Warehousing Facilities: In Project's vicinity.
2. Scheduling Responsibility: Preparation of door hardware and keying schedule.
3. Engineering Responsibility: Preparation of data for electrified door hardware, including
Shop Drawings, based on testing and engineering analysis of manufacturer's standard
units in assemblies similar to those indicated for this Project.
B. Architectural Hardware Consultant Qualifications: A person who is experienced in providing
consulting services for door hardware installations that are comparable in material, design, and
extent to that indicated for this Project and who is currently certified by DHI as an Architectural
Hardware Consultant (AHC).
1.8 DELIVERY, STORAGE, AND HANDLING
A. Inventory door hardware on receipt and provide secure lock-up for door hardware delivered to
Project site.
B. Tag each item or package separately with identification coordinated with the final door
hardware schedule, and include installation instructions, templates, and necessary fasteners with
each item or package.
C. Deliver keys to manufacturer of key control system for subsequent delivery to Owner.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 4
D. Deliver keys and permanent cores to Owner by registered mail or overnight package service.
1.9 WARRANTY
A. Special Warranty: Manufacturer agrees to repair or replace components of door hardware that
fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Structural failures including excessive deflection, cracking, or breakage.
b. Faulty operation of doors and door hardware.
c. Deterioration of metals, metal finishes, and other materials beyond normal
weathering and use.
2. Warranty Period: Three years from date of Substantial Completion unless otherwise
indicated below:
a. Electromagnetic Locks: Five years from date of Substantial Completion.
b. Exit Devices: Two years from date of Substantial Completion.
c. Manual Closers: 10 years from date of Substantial Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain each type of door hardware from single manufacturer.
1. Provide electrified door hardware from same manufacturer as mechanical door hardware
unless otherwise indicated. Manufacturers that perform electrical modifications and that
are listed by a testing and inspecting agency acceptable to authorities having jurisdiction
are acceptable.
2.2 PERFORMANCE REQUIREMENTS
A. Fire-Rated Door Assemblies: Where fire-rated doors are indicated, provide door hardware
complying with NFPA 80 that is listed and labeled by a qualified testing agency, for fire-
protection ratings indicated, based on testing at positive pressure according to NFPA 252 or
UL 10C.
B. Smoke- and Draft-Control Door Assemblies: Where smoke- and draft-control door assemblies
are required, provide door hardware that complies with requirements of assemblies tested
according to UL 1784 and installed in compliance with NFPA 105.
1. Air Leakage Rate: Maximum air leakage of 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) at
the tested pressure differential of 0.3-inch wg (75 Pa) of water.
C. Electrified Door Hardware: Listed and labeled as defined in NFPA 70, by a qualified testing
agency, and marked for intended location and application.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 5
D. Means of Egress Doors: Latches do not require more than 15 lbf (67 N) to release the latch.
Locks do not require use of a key, tool, or special knowledge for operation.
E. Accessibility Requirements: For door hardware on doors in an accessible route, comply with the
DOJ's "2010 ADA Standards for Accessible Design" and Florida Building Code-Accessibility.
1. Provide operating devices that do not require tight grasping, pinching, or twisting of the
wrist and that operate with a force of not more than 5 lbf (22.2 N).
2. Comply with the following maximum opening-force requirements:
a. Interior, Non-Fire-Rated Hinged Doors: 5 lbf (22.2 N) applied perpendicular to
door.
b. Fire Doors: Minimum opening force allowable by authorities having jurisdiction.
3. Bevel raised thresholds with a slope of not more than 1:2. Provide thresholds not more
than 1/2 inch (13 mm) high.
4. Adjust door closer sweep periods so that, from an open position of 90 degrees, the door
will take at least 5 seconds to move to a position of 12 degrees from the latch.
5. Adjust spring hinges so that, from an open position of 70 degrees, the door will take at
least 1.5 seconds to move to the closed position.
2.3 SCHEDULED DOOR HARDWARE
A. Provide products for each door that comply with requirements indicated in Part 2 and door
hardware schedule.
1. Door hardware is scheduled in Part 3.
2.4 HINGES
A. Hinges: BHMA A156.1. Provide template-produced hinges for hinges installed on hollow-metal
doors and hollow-metal frames.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or comparable products by one of the following:
a. Hager Companies.
b. McKinney Products Company; an ASSA ABLOY Group company.
c. Stanley Commercial Hardware; a division of Stanley Security Solutions.
2.5 CONTINUOUS HINGES
A. Continuous Hinges: BHMA A156.26; minimum 0.120-inch- (3.0-mm-) thick, hinge leaves with
minimum overall width of 4 inches (102 mm); fabricated to full height of door and frame and to
template screw locations; with components finished after milling and drilling are complete.
B. Continuous, Gear-Type Hinges: Extruded-aluminum, pinless, geared hinge leaves joined by a
continuous extruded-aluminum channel cap; with concealed, self-lubricating thrust bearings.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 6
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Hager Companies.
b. McKinney Products Company; an ASSA ABLOY Group company.
c. Stanley Commercial Hardware; a division of Stanley Security Solutions.
2.6 MECHANICAL LOCKS AND LATCHES
A. Lock Functions: As indicated in door hardware schedule.
B. Lock Throw: Comply with testing requirements for length of bolts required for labeled fire
doors, and as follows:
1. Mortise Locks: Minimum 3/4-inch (19-mm) latchbolt throw.
2. Deadbolts: Minimum 1-inch (25-mm) bolt throw.
C. Lock Backset: 2-3/4 inches (70 mm) unless otherwise indicated.
D. Lock Trim:
1. Description: As indicated in Hardware Schedule.
2. Levers: Cast.
a. As indicated in Hardware Schedule.
3. Escutcheons (Roses): [Wrought] [Forged] [Cast].
4. Dummy Trim: Match lever lock trim and escutcheons.
E. Strikes: Provide manufacturer's standard strike for each lock bolt or latchbolt complying with
requirements indicated for applicable lock or latch and with strike box and curved lip extended
to protect frame; finished to match lock or latch.
F. Mortise Locks: BHMA A156.13; Operational Grade 1; stamped steel case with steel or brass
parts; Series 1000.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Falcon MA Series scheduled or a comparable product by one of the following:
a. Best Access Systems; Stanley Security Solutions, Inc.; 45H series.
b. SARGENT Manufacturing Company; ASSA ABLOY; 8200 series.
2.7 SELF-CONTAINED ELECTRONIC LOCKS
A. Self-Contained Electronic Locks: BHMA A156.25; mortise; with internal, battery-powered,
self-contained electronic locks; consisting of complete lockset, motor-driven lock mechanism,
and actuating device; enclosed in zinc-dichromate-plated, wrought-steel case, and strike that
suits frame. Provide key override, low-battery detection and warning, LED status indicators,
and ability to program at the lock.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 7
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Sclage CO series scheduled or a comparable product by one of the following:
a. Best Access Systems; Stanley Security Solutions, Inc; EXZ Series
b. SARGENT Manufacturing Company; ASSA ABLOY; KP Series.
2.8 EXIT LOCKS AND EXIT ALARMS
A. Exit Locks and Alarms: BHMA A156.29, Grade 1.
2.9 SURFACE BOLTS
A. Surface Bolts: BHMA A156.16.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Trimco.
b. Rockwood.
2.10 MANUAL FLUSH BOLTS
A. Manual Flush Bolts: BHMA A156.16; minimum 3/4-inch (19-mm) throw; designed for
mortising into door edge.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Trimco.
b. Rockwood.
2.11 AUTOMATIC AND SELF-LATCHING FLUSH BOLTS
A. Automatic and Self-Latching Flush Bolts: BHMA A156.16; minimum 3/4-inch (19-mm) throw;
designed for mortising into door edge.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Trimco.
b. Rockwood.
2.12 EXIT DEVICES AND AUXILIARY ITEMS
A. Exit Devices and Auxiliary Items: BHMA A156.3.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 8
1. Manufacturers: Subject to compliance with requirements, available manufacturers
offering products that may be incorporated into the Work include, but are not limited to
the following:
a. Allegion plc.
b. Corbin Russwin, Inc.; an ASSA ABLOY Group company.
c. SARGENT Manufacturing Company; ASSA ABLOY.
d. Yale Security Inc; an ASSA ABLOY Group company.
2.13 LOCK CYLINDERS
A. Lock Cylinders: Tumbler type, constructed from brass or bronze, stainless steel, or nickel silver.
B. Standard Lock Cylinders: BHMA A156.5; Grade 1 permanent cores; face finished to match
lockset.
1. Core Type: Interchangeable or Removable as required by Owner.
C. Construction Cores: Provide construction cores that are replaceable by permanent cores.
Provide 10 construction master keys.
2.14 KEYING
A. Keying System: Factory registered, complying with guidelines in BHMA A156.28, appendix.
Provide one extra key blank for each lock. Incorporate decisions made in keying conference.
Provide key system as required by Owner
1. Grand Master Key System: Change keys, a master key, and a grand master key operate
cylinders.
a. Provide three cylinder change keys and five each of master and grand master keys.
2. Existing System:
a. Master key or grand master key locks to Owner's existing system.
B. Keys: Nickel silver or Brass.
1. Stamping: Permanently inscribe each key with a visual key control number and include
the following notation:
a. Notation: Information to be furnished by Owner.
2.15 KEY CONTROL SYSTEM
A. Key Control Cabinet: BHMA A156.28; metal cabinet with baked-enamel finish; containing
key-holding hooks, labels, two sets of key tags with self-locking key holders, key-gathering
envelopes, and temporary and permanent markers; with key capacity of 150 percent of the
number of locks.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 9
1. Wall-Mounted Cabinet: Grade 1 cabinet with hinged-panel door equipped with key-
holding panels and pin-tumbler cylinder door lock.
B. Key Lock Boxes: Designed for storage of two keys.
2.16 OPERATING TRIM
A. Operating Trim: BHMA A156.6; stainless steel unless otherwise indicated.
2.17 ACCESSORIES FOR PAIRS OF DOORS
A. Coordinators: BHMA A156.3; consisting of active-leaf, hold-open lever and inactive-leaf
release trigger; fabricated from steel with nylon-coated strike plates; with built-in, adjustable
safety release.
B. Carry-Open Bars: BHMA A156.3; prevent the inactive leaf from opening before the active leaf;
provide polished brass or bronze carry-open bars with strike plate for inactive leaves of pairs of
doors unless automatic or self-latching bolts are used.
C. Astragals: BHMA A156.22.
2.18 SURFACE CLOSERS
A. Surface Closers: BHMA A156.4; rack-and-pinion hydraulic type with adjustable sweep and
latch speeds controlled by key-operated valves and forged-steel main arm. Comply with
manufacturer's written instructions for size of door closers depending on size of door, exposure
to weather, and anticipated frequency of use. Provide factory-sized closers, adjustable to meet
field conditions and requirements for opening force.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
LCN4040XP series products or a comparable product by one of the following:
a. SARGENT Manufacturing Company; ASSA ABLOY; 281 Series.
b. Stanley Commercial Hardware; a division of Stanley Security Solutions;
D-4550 Series.
2.19 MECHANICAL STOPS AND HOLDERS
A. Wall- and Floor-Mounted Stops: BHMA A156.16.
2.20 OVERHEAD STOPS AND HOLDERS
A. Overhead Stops and Holders: BHMA A156.8.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Glynn Johnson products scheduled or a comparable product by one of the following:
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 10
a. SARGENT Manufacturing Company; ASSA ABLOY.
b. Rockwood.
c. Trimco.
2.21 Door Gasketing: BHMA A156.22; with resilient or flexible seal strips that are easily replaceable
and readily available from stocks maintained by manufacturer.
A. Maximum Air Leakage: When tested according to ASTM E 283 with tested pressure
differential of 0.3-inch wg (75 Pa), as follows:
1. Smoke-Rated Gasketing: 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) of door opening.
2. Gasketing on Single Doors: 0.3 cfm/sq. ft. (3 cu. m per minute/sq. m) of door opening.
3. Gasketing on Double Doors: 0.50 cfm per foot (0.000774 cu. m/s per m) of door opening.
B. Basis-of-Design Product: Subject to compliance with requirements, provide Zero International,
Inc. products or comparable products by one of the following:
a. Hager Companies.
b. National Guard Products, Inc.
c. Pemko Manufacturing Co.
2.22 THRESHOLDS
A. Thresholds: BHMA A156.21; fabricated to full width of opening indicated.
B. Basis-of-Design Product: Subject to compliance with requirements, provide Zero International,
Inc. products or comparable products by one of the following:
a. Hager Companies.
b. National Guard Products, Inc.
c. Pemko Manufacturing Co.
2.23 METAL PROTECTIVE TRIM UNITS
A. Metal Protective Trim Units: BHMA A156.6; fabricated from 0.050-inch- (1.3-mm-) thick
stainless steel; with manufacturer's standard machine or self-tapping screw fasteners.
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Trimco.
b. Rockwood.
2.24 AUXILIARY DOOR HARDWARE
A. Auxiliary Hardware: BHMA A156.16.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 11
1. Basis-of-Design Product: Subject to compliance with requirements, provide Allegion plc;
Ives products scheduled or a comparable product by one of the following:
a. Trimco.
b. Rockwood.
2.25 FABRICATION
A. Manufacturer's Nameplate: Do not provide products that have manufacturer's name or trade
name displayed in a visible location except in conjunction with required fire-rating labels and as
otherwise approved by Architect.
1. Manufacturer's identification is permitted on rim of lock cylinders only.
B. Base Metals: Produce door hardware units of base metal indicated, fabricated by forming
method indicated, using manufacturer's standard metal alloy, composition, temper, and
hardness. Furnish metals of a quality equal to or greater than that of specified door hardware
units and BHMA A156.18.
C. Fasteners: Provide door hardware manufactured to comply with published templates prepared
for machine, wood, and sheet metal screws. Provide screws that comply with commercially
recognized industry standards for application intended, except aluminum fasteners are not
permitted. Provide Phillips flat-head screws with finished heads to match surface of door
hardware unless otherwise indicated.
1. Concealed Fasteners: For door hardware units that are exposed when door is closed,
except for units already specified with concealed fasteners. Do not use through bolts for
installation where bolt head or nut on opposite face is exposed unless it is the only means
of securely attaching the door hardware. Where through bolts are used on hollow door
and frame construction, provide sleeves for each through bolt.
2. Fire-Rated Applications:
a. Wood or Machine Screws: For the following:
1) Hinges mortised to doors or frames.
2) Strike plates to frames.
3) Closers to doors and frames.
b. Steel Through Bolts: For the following unless door blocking is provided:
1) Surface hinges to doors.
2) Closers to doors and frames.
3) Surface-mounted exit devices.
3. Spacers or Sex Bolts: For through bolting of hollow-metal doors.
4. Gasketing Fasteners: Provide noncorrosive fasteners for exterior applications and
elsewhere as indicated.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 12
2.26 FINISHES
A. Provide finishes complying with BHMA A156.18 as indicated in door hardware schedule.
B. Protect mechanical finishes on exposed surfaces from damage by applying a strippable,
temporary protective covering before shipping.
C. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are
acceptable if they are within one-half of the range of approved Samples. Noticeable variations
in the same piece are not acceptable. Variations in appearance of other components are
acceptable if they are within the range of approved Samples and are assembled or installed to
minimize contrast.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine doors and frames, with Installer present, for compliance with requirements for
installation tolerances, labeled fire-rated door assembly construction, wall and floor
construction, and other conditions affecting performance of the Work.
B. Examine roughing-in for electrical power systems to verify actual locations of wiring
connections before electrified door hardware installation.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Steel Doors and Frames: For surface-applied door hardware, drill and tap doors and frames
according to ANSI/SDI A250.6.
B. Wood Doors: Comply with door and hardware manufacturers' written instructions.
3.3 INSTALLATION
A. Mounting Heights: Mount door hardware units at heights to comply with the following unless
otherwise indicated or required to comply with governing regulations.
1. Standard Steel Doors and Frames: ANSI/SDI A250.8.
2. Custom Steel Doors and Frames: HMMA 831.
3. Wood Doors: DHI's "Recommended Locations for Architectural Hardware for Wood
Flush Doors."
B. Install each door hardware item to comply with manufacturer's written instructions. Where
cutting and fitting are required to install door hardware onto or into surfaces that are later to be
painted or finished in another way, coordinate removal, storage, and reinstallation of surface
protective trim units with finishing work. Do not install surface-mounted items until finishes
have been completed on substrates involved.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 13
1. Set units level, plumb, and true to line and location. Adjust and reinforce attachment
substrates as necessary for proper installation and operation.
2. Drill and countersink units that are not factory prepared for anchorage fasteners. Space
fasteners and anchors according to industry standards.
C. Hinges: Install types and in quantities indicated in door hardware schedule, but not fewer than
the number recommended by manufacturer for application indicated or one hinge for every 30
inches (750 mm) of door height, whichever is more stringent, unless other equivalent means of
support for door, such as spring hinges or pivots, are provided.
D. Lock Cylinders: Install construction cores to secure building and areas during construction
period.
1. Replace construction cores with permanent cores as directed by Owner.
2. Furnish permanent cores to Owner for installation.
E. Key Control System:
1. Key Control Cabinet: Tag keys and place them on markers and hooks in key control
system cabinet, as determined by final keying schedule.
2. Key Lock Boxes: Install where indicated or approved by Architect to provide controlled
access for fire and medical emergency personnel.
F. Boxed Power Supplies: Locate power supplies as indicated or, if not indicated, above accessible
ceilings. Verify location with Architect.
1. Configuration: Provide one power supply for each door opening least number of power
supplies required to adequately serve doors with electrified door hardware.
G. Thresholds: Set thresholds for exterior doors and other doors indicated in full bed of sealant
complying with requirements specified in Section 079200 "Joint Sealants."
H. Stops: Provide floor stops for doors unless wall or other type stops are indicated in door
hardware schedule. Do not mount floor stops where they will impede traffic.
I. Perimeter Gasketing: Apply to head and jamb, forming seal between door and frame.
1. Do not notch perimeter gasketing to install other surface-applied hardware.
J. Meeting Stile Gasketing: Fasten to meeting stiles, forming seal when doors are closed.
K. Door Bottoms: Apply to bottom of door, forming seal with threshold when door is closed.
3.4 ADJUSTING
A. Initial Adjustment: Adjust and check each operating item of door hardware and each door to
ensure proper operation or function of every unit. Replace units that cannot be adjusted to
operate as intended. Adjust door control devices to compensate for final operation of heating
and ventilating equipment and to comply with referenced accessibility requirements.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 14
1. Door Closers: Adjust sweep period to comply with accessibility requirements and
requirements of authorities having jurisdiction.
2. Spring Hinges: Adjust to achieve positive latching when door is allowed to close freely
from an open position of 70 degrees and so that closing time complies with accessibility
requirements of authorities having jurisdiction.
3. Electric Strikes: Adjust horizontal and vertical alignment of keeper to properly engage
lock bolt.
B. Occupancy Adjustment: Approximately 8 months after date of Substantial Completion,
Installer's Architectural Hardware Consultant shall examine and readjust each item of door
hardware, including adjusting operating forces, as necessary to ensure function of doors, door
hardware, and electrified door hardware.
3.5 CLEANING AND PROTECTION
A. Clean adjacent surfaces soiled by door hardware installation.
B. Clean operating items as necessary to restore proper function and finish.
C. Provide final protection and maintain conditions that ensure that door hardware is without
damage or deterioration at time of Substantial Completion.
3.6 MAINTENANCE SERVICE
A. Maintenance Tools and Instructions: Furnish a complete set of specialized tools and
maintenance instructions for Owner's continued adjustment, maintenance, and removal and
replacement of door hardware.
3.7 DOOR HARDWARE SCHEDULE
Hardware Group No. 01
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
2 EA CONT. HINGE 112HD EPT 628 IVE
1 EA POWER TRANSFER EPT10 CON 689 VON
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
1 EA ELEC PANIC
HARDWARE
RX-QEL+-HH-99-DT-CON 626 VON
1 EA ELEC PANIC
HARDWARE
RX-QEL+-HH-99-NL-CON 626 VON
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA MORTISE CYLINDER 20-061-ICX 626 SCH
2 EA FSIC CORE 23-030 626 SCH
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 15
1 EA SURF. AUTO
OPERATOR
9542 MS ANCLR LCN
2 EA ACTUATOR, WALL
MOUNT
8310-853T 630 LCN
2 EA FLOOR STOP FS18S BLK IVE
1 EA POWER SUPPLY PS902 900-2RS LGR SCE
1 BALANCE OF HARDWARE BY DOOR
MANUFACTURER
2 EA WIRE HARNESS CON-12 VON
2 EA WIRE HARNESS CON-192P VON
2 EA SECURITY CONTACTS 1090-G GE
Presentation of valid credential retracts latch on panic hardware and allows for door to auto open.
Card reader by security supplier
Wiring Diagram by Hardware Supplier
Hardware Group No. 02
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
1 EA FIRE EXIT
HARDWARE
HH-99-DT-F 626 VON
1 EA FIRE EXIT
HARDWARE
HH-99-NL-F 626 VON
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA MORTISE CYLINDER 20-061-ICX 626 SCH
2 EA FSIC CORE 23-030 626 SCH
2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN
2 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
2 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 03
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
1 EA PANIC HARDWARE HH-99-DT 626 VON
1 EA PANIC HARDWARE HH-99-NL 626 VON
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA MORTISE CYLINDER 20-061-ICX 626 SCH
2 EA FSIC CORE 23-030 626 SCH
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 16
2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN
2 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
2 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 04
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
2 EA PANIC HARDWARE HH-99-L-BE-06 626 VON
2 EA SURFACE CLOSER 4040XP EDA TBSRT 689 LCN
2 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
Hardware Group No. 05
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
8 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
2 EA FIRE EXIT
HARDWARE
HH-99-L-BE-F-06 626 VON
1 EA MORTISE CYLINDER 20-061-ICX 626 SCH
1 EA FSIC CORE 23-030 626 SCH
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
2 EA DOOR SWEEP 8192AA AA ZER
1 EA THRESHOLD 545A-MSLA-10 A ZER
Hardware Group No. 06
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
8 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
2 EA SURFACE BOLT SB360 12" T 604 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA LOCK GUARD LG12 630 IVE
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 17
1 EA THRESHOLD 65A-MSLA-10 A ZER
2 EA SECURITY CONTACTS 1090-G GE
With Metal Z-Astragal
Hardware Group No. 06A (added as part of Pod Renovations)
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
2 EA SURFACE BOLT SB360 12" T 604 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA LOCK GUARD LG12 630 IVE
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
2 EA SECURITY
CONTACTS
1090-G GE
With Metal Z-Astragal
Hardware Group No. 07
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA PANIC HARDWARE HH-99-L-NL-17 626 VON
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA FSIC CORE 23-030 626 SCH
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 08
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON
1 EA ELEC EXIT DEVICE
TRIM
CO-100-993R-70-KP-SPA-PD 626 SCE
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 18
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY CONTACTS 1090-G GE
Stand Alone keypad trim
Hardware Group No. 09
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
1 EA CONT. HINGE 112HD 628 IVE
1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON
1 EA ELEC EXIT DEVICE
TRIM
CO-100-993R-70-KP-SPA-PD 626 SCE
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA FLOOR STOP FS18S BLK IVE
1 EA SECURITY CONTACTS 1090-G GE
1 BALANCE OF HARDWARE BY DOOR
MANUFACTURER
Stand Alone keypad trim
Hardware Group No. 10
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
1 EA CONT. HINGE 112HD 628 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA FLOOR STOP FS18S BLK IVE
1 EA SECURITY CONTACTS 1090-G GE
1 BALANCE OF HARDWARE BY DOOR
MANUFACTURER
Hardware Group No. 11
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA LOCK GUARD LG12 630 IVE
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 12
Provide each SGL door(s) with the following:
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 19
Qty Description Catalog Number Finish Mfr
4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA CLASSROOM LOCK MA561P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 13
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
4 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA CLASSRM SEC LOCK MA441P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY CONTACTS 1090-G GE
Hardware Group No. 14
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA KEYED REMOVABLE
MULLION
KR4954-STAB 689 VON
2 EA PANIC HARDWARE 99-L-17-SNB 626 VON
2 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA MORTISE CYLINDER 20-061-ICX 626 SCH
3 EA FSIC CORE 23-030 626 SCH
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
2 EA SILENCER SR64 GRY IVE
Hardware Group No. 15
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA KEYED FIRE RATED
REMOVABLE
MULLION
KR9954-STAB 689 VON
1 EA FIRE EXIT
HARDWARE
99-L-BE-F-17-SNB 626 VON
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 20
2 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
2 EA GASKETING 188S-BK S-Bk ZER
Hardware Group No. 16
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 SET CONST LATCHING
BOLT
FB53 630 IVE
1 EA CLASSROOM LOCK MA561P6 QN 626 FAL
1 EA COORDINATOR COR X FL 628 IVE
2 EA MOUNTING BRACKET MB 689 IVE
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
1 EA ASTRAGAL 905A A ZER
2 EA SILENCER SR64 GRY IVE
Hardware Group No. 17
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 SET CONST LATCHING
BOLT
FB53 630 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA COORDINATOR COR X FL 628 IVE
2 EA MOUNTING BRACKET MB 689 IVE
2 EA SURFACE CLOSER 4040XP CUSH 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA ASTRAGAL 905A A ZER
Hardware Group No. 18
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 SET CONST LATCHING
BOLT
FB53 630 IVE
1 EA CLASSROOM LOCK MA561P6 QN 626 FAL
1 EA COORDINATOR COR X FL 628 IVE
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
1 EA ASTRAGAL 905A A ZER
2 EA SILENCER SR64 GRY IVE
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 21
Hardware Group No. 19
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 SET CONST LATCHING
BOLT
FB53 630 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA COORDINATOR COR X FL 628 IVE
2 EA MOUNTING BRACKET MB 689 IVE
2 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
2 EA KICK PLATE 8400 10" X 1" LDW B4E 630 IVE
2 EA WALL STOP WS406/407CCV 630 IVE
1 EA ASTRAGAL 905A A ZER
2 EA SILENCER SR64 GRY IVE
Hardware Group No. 20
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA PANIC HARDWARE 99-EO 626 VON
1 EA ELEC EXIT DEVICE
TRIM
CO-100-993R-70-KP-SPA-PD 626 SCE
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA FSIC CORE 23-030 626 SCH
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
Stand Alone keypad trim
Hardware Group No. 21
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA CLASSRM SEC LOCK MA441P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
Hardware Group No. 22
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 22
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA STOREROOM LOCK MA581P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
Hardware Group No. 23
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA CLASSROOM LOCK MA561P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
Hardware Group No. 24
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA PRIVACY LOCK MA301 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA GASKETING 188S-BK S-Bk ZER
Hardware Group No. 25
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA PUSH PLATE 8200 6" X 16" 630 IVE
1 EA PULL PLATE 8303 10" 4" X 16" 630 IVE
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
3 EA SILENCER SR64 GRY IVE
Hardware Group No. 26
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA OFFICE LOCK MA521P6 QN 626 FAL
1 EA WALL STOP WS406/407CCV 630 IVE
3 EA SILENCER SR64 GRY IVE
Hardware Group No. 27 - GATE
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 23
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
2 EA PANIC HARDWARE HH-99-NL 626 VON
2 EA RIM CYLINDER 20-057-ICX 626 SCH
2 EA FSIC CORE 23-030 626 SCH
BALANCE OF HARDWARE BY GATE
MANUFACTURER
NOTE: Hardware sets below are additional sets added for the Pod Renovation Buildings C, D, G, J,
M, and NJROTC addition. The new doors scheduled also utilize the same Hardware Group num-
bers as the Classroom Building. Hardware shall be furnished as Assa-Abloy/Sargent Brands equiv-
alent to the Allegion Brands indicated below, as was also furnished on the Classroom Building.
Hardware Group No. 28
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 NRP 630 IVE
1 EA PANIC HARDWARE HH-99-EO-SNB 626 VON
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA FLOOR STOP FS18S BLK IVE
1 EA GASKETING 188S-BK S-Bk ZER
1 EA THRESHOLD 65A-MSLA-10 A ZER
1 EA SECURITY
CONTACTS
1090-G GE
Hardware Group No. 29
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA PANIC HARDWARE 99-L-17-SNB 626 VON
1 EA RIM CYLINDER 20-057-ICX 626 SCH
1 EA FSIC CORE 23-030 626 SCH
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA KICK PLATE 8400 10" X 2" LDW B4E 630 IVE
1 EA WALL STOP WS406/407CCV 630 IVE
1 EA SILENCER SR64 GRY IVE
Hardware Group No. 30
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 3CB1 4.5 X 4.5 652 IVE
1 EA PASSAGE SET MA301P6 QN 626 FAL
1 EA SURFACE CLOSER 4040XP TBSRT 689 LCN
1 EA WALL STOP WS406/407CCV 630 IVE
3 EA SILENCER SR64 GRY IVE
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
DOOR HARDWARE 087100 - 24
Hardware Group No. 31
Provide each SGL door(s) with the following: Qty Description Catalog Number Finish Mfr
3 EA HINGE 5 KNUCKLE BALL BEARING, NRP 632 --
1 EA PANIC HARDWARE DOOR MANUF. STD. CVR 626 --
1 EA 10” OFFSET PULL DOOR MANUF. STD. 632 --
1 EA SURFACE CLOSER DOOR MANUF. STD. 689 --
1 EA SECURITY
CONTACTS
1090-G GE
1 BALANCE OF HARDWARE BY
DOOR MANUFACTURER
Hardware Group No. 32
Provide each PR door(s) with the following: Qty Description Catalog Number Finish Mfr
6 EA HINGE 5 KNUCKLE BALL BEARING, NRP 632 --
2 EA PANIC HARDWARE DOOR MANUF. STD. CVR 626 --
2 EA 10” OFFSET PULL DOOR MANUF. STD. 632 --
2 EA SURFACE CLOSER DOOR MANUF. STD. 689 --
2 EA SECURITY
CONTACTS
1090-G GE
2 BALANCE OF HARDWARE BY
DOOR MANUFACTURER
END OF SECTION 087100
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 1
SECTION 105113 - METAL LOCKERS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Welded (interior) corridor lockers.
2. Welded, open-front athletic lockers. (Added for Pod G Locker Room Expansion)
1.3 ACTION SUBMITTALS
A. Product Data: For each type of metal locker.
1. Include construction details, material descriptions, dimensions of individual components
and profiles, and finishes for each type of metal locker.
B. Sustainable Design Submittals:
1. Recycled Content:
a. Indicate recycled content; indicate percentage of pre-consumer and post-consumer
recycled content per unit of product.
b. Indicate relative dollar value of recycled content product to total dollar value of
product included in project.
c. If recycled content product is part of an assembly, indicate the percentage of
recycled content product in the assembly by weight.
d. If recycled content product is part of an assembly, indicate relative dollar value of
recycled content product to total dollar value of assembly.
2. Local/Regional Materials: Sourcing Location(s): Indicate location of extraction,
harvesting, and recovery; indicate distance between extraction, harvesting, and recovery
and the project site.
a. Manufacturing Location(s): Indicate location of manufacturing facility; indicate
distance between manufacturing facility and the project site.
b. Product Value: Indicate dollar value of product containing local/regional
materials; include materials cost only.
c. Product Component(s): Where product components are sourced or manufactured
in separate locations, provide location information for each component. Indicate
the percentage by weight of each component per unit of product.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 2
C. Shop Drawings: For metal lockers.
1. Include plans, elevations, sections, details, and attachments to other work.
2. Show locker trim and accessories.
3. Include locker identification system and numbering sequence.
D. Samples: For each color specified, in manufacturer's standard size.
E. Product Schedule: For lockers.
1.4 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer.
B. Sample Warranty: For special warranty.
1.5 CLOSEOUT SUBMITTALS
A. Maintenance Data: For adjusting, repairing, and replacing locker doors and latching
mechanisms to include in maintenance manuals.
1.6 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents.
1. Full-size units of the following metal locker hardware items equal to 10 percent of
amount installed for each type and finish installed, but no fewer than five units:
a. Locks.
b. Hooks.
1.7 DELIVERY, STORAGE, AND HANDLING
A. Do not deliver metal lockers until spaces to receive them are clean, dry, and ready for their
installation.
B. Deliver master and control keys and combination control charts to Owner.
1.8 FIELD CONDITIONS
A. Field Measurements: Verify actual dimensions of openings by field measurements before
fabrication.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 3
1.9 COORDINATION
A. Coordinate sizes and locations of framing, blocking, furring, reinforcements, and other related
units of work specified in other Sections to ensure that metal lockers can be supported and
installed as indicated.
1.10 WARRANTY
A. Special Warranty: Manufacturer agrees to repair or replace components of metal lockers that
fail in materials or workmanship, excluding finish, within specified warranty period.
1. Failures include, but are not limited to, the following:
a. Structural failures.
b. Faulty operation of latches and other door hardware.
2. Damage from deliberate destruction and vandalism is excluded.
3. Warranty Period for Welded Metal Lockers: 10 years from date of Final Completion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain metal lockers and accessories from single source from single locker
manufacturer.
1. Obtain locks from single lock manufacturer.
2.2 PERFORMANCE REQUIREMENTS
A. Accessibility Requirements: For lockers indicated to be accessible, comply with applicable
provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA
Accessibility Guidelines and Florida Building Code-Accessibility.
2.3 WELDED CORRIDOR LOCKERS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering
products that may be incorporated into the Work include, but are not limited to the following:
1. Art Metal Products.
2. ASI Storage Solutions; ASI Group.
3. General Storage Systems Ltd.
4. List Industries Inc. (Superior, Classmate Unibody All-Welded Lockers used as the
Basis-of Design
5. Lyon Workspace Products, LLC.
6. Penco Products, Inc.
7. Republic Storage Systems, LLC.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 4
B. Size: Triple-tier, 12-inch wide by 15-inch deep by 72-inch height (exclusive of 4-inch height
continuous zee base), unless noted otherwise.
C. Doors: One piece; fabricated from 0.075-inch (1.90-mm) nominal-thickness steel sheet; formed
into channel shape with double bend at vertical edges and with right-angle single bend at
horizontal edges.
1. Reinforcement: Manufacturer's standard reinforcing angles, channels, or stiffeners for
doors more than 15 inches (381 mm) wide; welded to inner face of doors.
2. Door Stiffener: Manufacturer’s standard 3-inch wide, 0.075-inch (1.90-mm) thick, full
height door stiffener spot welded to the inner door face and welded to the hinge side as
well as the top and bottom door flanges.
3. Door Style: Vented panel as follows:
a. Louvered Vents: No fewer than two louver openings at top and bottom, or three
louver openings at top or bottom, for triple-tier lockers.
D. Body: Assembled by welding body components together. Fabricate from unperforated steel
sheet with thicknesses as follows:
1. Tops, Bottoms, and Sides: 0.060-inch (1.52-mm) nominal thickness.
2. Backs: 0.048-inch (1.21-mm) nominal thickness.
3. Shelves: 0.060-inch (1.52-mm) nominal thickness, with double bend at front and single
bend at sides and back.
E. Frames: Channel formed; fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet;
lapped and factory welded at corners; with top and bottom main frames factory welded into
vertical main frames. Form continuous, integral, full-height door strikes on vertical main
frames.
1. Cross Frames between Tiers: Channel formed and fabricated from same material as main
frames; welded to vertical main frames.
F. Hinges: Welded to door and attached to door frame with no fewer than two factory-installed
rivets per hinge that are completely concealed and tamper resistant when door is closed;
fabricated to swing 180 degrees.
1. Hinges: Manufacturer's standard, steel, continuous or knuckle type.
G. Recessed Door Handle and Latch: Stainless-steel cup with integral door pull, recessed so
locking device does not protrude beyond door face; pry and vandal resistant.
1. Multipoint Latching: Finger-lift latch control designed for use with built-in combination
locks or padlocks; positive automatic latching.
a. Latch Hooks: Equip doors 48 inches (1219 mm) and higher with three latch hooks
and doors less than 48 inches (1219 mm) high with two latch hooks; fabricated
from 0.105-inch (3.04-mm) nominal-thickness steel sheet; welded to full-height
door strikes; with resilient silencer on each latch hook.
H. Locks: Combination padlocks (Owner Furnished).
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 5
I. Identification Plates: Manufacturer's standard, etched, embossed, or stamped aluminum plates,
with numbers and letters at least 3/8 inch (9 mm) high.
J. Hooks: Manufacturer's standard ball-pointed type, aluminum or steel; zinc plated.
K. Continuous Zee Base: Fabricated from, manufacturer's standard thickness, but not less than
0.060-inch (1.52-mm) nominal-thickness steel sheet.
1. Height: 4 inches (102 mm).
L. Continuous Integral Sloping Tops: Fabricated from 0.060-inch (1.21-mm) nominal-thickness
steel sheet, with a pitch of approximately 20 degrees, continuous across multiple units and
factory welded. Locker sides are sloped at top providing rigid support beneath the sloped top
between each unit.
1. Closures: Vertical-end type.
M. Filler Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.
N. Boxed End Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.
O. Materials:
1. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B,
suitable for exposed applications.
P. Finish: Baked enamel or powder coat.
1. Color: As indicated by manufacturer's designations or if not indicated, as selected by
Architect from manufacturer's full range.
2.4 WELDED OPEN FRONT ATHLETIC LOCKERS (Pod G Renovation)
A. Basis-of-Design Product: Subject to compliance with requirements, provide ASI Storage
Solutions; ASI Group; All-Welded Competitor or a comparable product by one of the
following:
1. Art Metal Products.
2. General Storage Systems Ltd.
3. List Industries Inc.
4. Lyon Workspace Products, LLC.
5. Penco Products, Inc.
6. Republic Storage Systems, LLC.
B. Size: Single-tier, 18-inch wide by 18-inch deep by 60-inch height, unless noted otherwise.
C. Locker Arrangement: Open front, with upper shelf with security box and configuration as
indicated on Drawings.
D. Perforated Doors: One piece; fabricated from 0.075-inch (1.90-mm) nominal-thickness
steel sheet with manufacturer's standard diamond perforations; formed into channel
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 6
shape with double bend at vertical edges and with right-angle single bend at horizontal
edges.
1. Reinforcement: Manufacturer's standard reinforcing angles, channels, or stiffeners
for doors more than 15 inches (381 mm) wide; welded to inner face of doors.
E. Body: Assembled by welding body components together. Fabricate from unperforated
steel sheet with thicknesses as follows:
1. Tops and Bottoms: 0.060-inch (1.52-mm) nominal thickness, with single bend at
edges.
2. Backs: 0.048-inch (1.21-mm) nominal thickness.
3. Shelves: 0.060-inch (1.52-mm) nominal thickness, with double bend at front and
single bend at sides and back.
F. Perforated Sides: Fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet
with manufacturer's standard diamond perforations.
G. Frames: Channel formed; fabricated from 0.060-inch (1.52-mm) nominal-thickness steel
sheet or 0.097-inch (2.45-mm) nominal-thickness steel angles; lapped and factory welded
at corners; with top and bottom main frames factory welded into vertical main frames.
Form continuous, integral, full-height door strikes on vertical main frames.
H. Security Boxes: Consisting of partition extending from upper shelf to top of metal locker,
fabricated from 0.060-inch (1.52-mm) nominal-thickness steel sheet; with channel-formed,
0.060-inch (1.52-mm) nominal-thickness, steel sheet door frame, and door fabricated from
0.075-inch (1.90-mm) nominal-thickness steel sheet with right-angle single bend at edges;
with manufacturer's standard, steel continuous hinge that is completely concealed and
tamper resistant when door is closed; fabricated to swing 180 degrees.
I. Locks: Combination padlocks, Owner Furnished.
J. Identification Plates: Manufacturer's standard, etched, embossed, or stamped aluminum
plates, with numbers and letters at least 3/8 inch (9 mm) high.
1. Number locker units starting at 1 for both the Boys Locker Room and the Girls
Locker Room.
K. Hooks: Manufacturer's standard ball-pointed type, aluminum or steel; zinc plated.
L. Continuous Sloping Tops: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel
sheet, with a pitch of approximately 20 degrees.
1. Closures: Vertical-end type.
M. Filler Panels: Fabricated from 0.048-inch (1.21-mm) nominal-thickness steel sheet.
N. Materials:
1. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B,
suitable for exposed applications.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 7
O. Finish: Baked enamel or powder coat.
1. Color: #53 Pine Forest Green.
2.5 LOCKS
A. Combination Padlocks: Provide key-controlled, three-number dialing combination locks;
capable of five combination changes.
2.6 FABRICATION
A. Fabricate metal lockers square, rigid, without warp, and with metal faces flat and free of dents
or distortion. Make exposed metal edges safe to touch and free of sharp edges and burrs.
1. Form body panels, doors, shelves, and accessories from one-piece steel sheet unless
otherwise indicated.
2. Provide fasteners, filler plates, supports, clips, and closures as required for complete
installation.
B. Fabricate each metal locker with an individual door and frame; individual top, bottom, and
back; and common intermediate uprights separating compartments. Factory weld frame
members of each metal locker together to form a rigid, one-piece assembly.
C. Equipment: Provide each locker with an identification plate and the following equipment:
1. Triple-Tier Units: One double-prong ceiling hook.
D. Welded Construction: Factory preassemble metal lockers by welding all joints, seams, and
connections; with no bolts, nuts, screws, or rivets used in assembly of main locker groups.
Factory weld main locker groups into one-piece structures. Grind exposed welds flush.
E. Accessible Lockers: Fabricate as follows:
1. Locate bottom shelf no lower than 15 inches (381 mm) above the floor.
2. Where hooks or additional shelves are provided, locate no higher than 48 inches (1219
mm) above the floor.
3. Provide a minimum of 5% of total number of lockers to meet accessibility requirements,
distributed throughout the various groupings.
F. Continuous Base: Formed into channel or zee profile for stiffness, and fabricated in lengths as
long as practical to enclose base and base ends of metal lockers; finished to match lockers.
G. Continuous Integral Sloping Tops: Fabricated in lengths as long as practical, without visible
fasteners at splice locations; finished to match lockers.
1. Sloping-top corner fillers, mitered.
H. Filler Panels: Fabricated in an unequal leg angle shape; finished to match lockers. Provide slip-
joint filler angle formed to receive filler panel.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 8
I. Boxed End Panels: Fabricated with 1-inch- (25-mm-) wide edge dimension, and designed for
concealing fasteners and holes at exposed ends of nonrecessed metal lockers; finished to match
lockers.
1. Provide one-piece panels for double-row (back-to-back) locker ends.
2.7 ACCESSORIES
A. Fasteners: Zinc- or nickel-plated steel, slotless-type, exposed bolt heads; with self-locking nuts
or lock washers for nuts on moving parts.
B. Anchors: Material, type, and size required for secure anchorage to each substrate.
1. Provide nonferrous-metal or hot-dip galvanized anchors and inserts on inside face of
exterior walls for corrosion resistance.
2. Provide toothed-steel or lead expansion sleeves for drilled-in-place anchors.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine walls, floors, and support bases, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting performance of the Work.
B. Prepare written report, endorsed by Installer, listing conditions detrimental to performance of
the Work.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. General: Install lockers level, plumb, and true; shim as required, using concealed shims.
1. Anchor locker runs at ends and at intervals recommended by manufacturer, but not more
than 36 inches (910 mm) o.c. Using concealed fasteners, install anchors through backup
reinforcing plates, channels, or blocking as required to prevent metal distortion.
2. Anchor single rows of metal lockers to walls near top of lockers and either bottom of
lockers or to floor.
B. Welded Lockers: Connect groups together with standard fasteners, with no exposed fasteners on
face frames.
C. Equipment:
1. Attach hooks with at least two fasteners.
2. Identification Plates: Identify metal lockers with identification indicated on Drawings.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 1
SECTION 23 44 00 - AIR PURIFICATION SYSTEM PART 1 – GENERAL 1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 DESCRIPTION OF WORK
A. This section describes the design, performance and installation of an air purification system intended for use as part of another manufacturer’s air handling unit or mounted on the duct as shown on the plans, details and equipment schedules.
1.3 REFERENCED CODES & STANDARDS
A. The following codes and standards are referenced through out. The edition to be used is
that currently enforced by the authority having jurisdiction (AHJ) or in absence of such direction that referenced by the current enforceable IBC code or as indicated by the contract documents, except where specifically referenced by this section of the specifications. 1. ASHRAE Standards 62 & 52 2. National Electric Code NFPA 70 3. UL 867 including ozone chamber test required as of December 21, 2007 4. The ionization equipment and power supply shall be UL and CE listed.
1.4 RELATED WORK
A. Testing, Adjusting and Balancing B. Facility Access and Protection C. Ductwork D. Filters E. Water and Refrigerant Piping F. Electrical Wiring G. Control Wiring
1.5 QUALITY ASSURANCE
A. Basis of design is Global Plasma Solutions. Plasma Air and Active Air Solutions shall be considered equal subjects to meeting ALL specifications herein. All other manufacturers requesting prior approval must submit product drawings, specifications and test results specified in section 2.2 at least four weeks prior to bid date.
B. The Air Purification System shall be a product of an established manufacturer within the
USA and shall be made of 100% USA sourced raw materials and components. C. A qualified representative from the manufacturer shall be available to inspect the
installation of the air purification system to ensure installation in accordance with manufacturer's recommendation.
D. Technologies that do not address gas disassociation such as UV Lights, Powered
Particulate Filters and/or polarized media filters shall not be considered. Uni-polar ion generators shall not be acceptable. “Plasma” particulate filters shall not be acceptable.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 2
E. Projects designed using ASHRAE Standard 62, IAQ Procedure shall require the manufacturer to provide Indoor Air Quality calculations using the formulas within ASHRAE Standard 62.1-2007 to validate acceptable indoor air quality at the quantity of outside air scheduled with the technology submitted. The manufacturer shall provide independent test data on a previous installation performed within the last two years and in a similar application, that proves compliance to ASHRAE 62 and the accuracy of the calculations.
F. The Air Purification Technology shall have been tested by UL or Intertek/ETL to prove
conformance to UL 867-2007 including the ozone chamber testing and peak ozone test for electronic devices. Manufacturers that achieved UL 867 prior to December 21, 2007 and have not been tested in accordance with the newest UL 867 standard with the ozone amendment shall not be acceptable. All manufacturers shall submit their independent UL 867 test data with ozone results to the engineer during the submittal process. All manufacturers shall submit a copy with their quotation. Contractors shall not accept any proposal without the proper ozone testing documentation.
G. The maximum allowable ozone concentration per the UL 867-2007 chamber test shall be
0.007 PPM. The maximum peak ozone concentration per the UL 867-2007 peak test as measured 2 inches away from the electronic air cleaner’s output shall be no more than 0.0042 PPM. Manufacturers with ozone output exceeding these ozone values shall not be acceptable.
1.6 SUBMITTALS
A. Product Data: Submit manufacturer's technical product data for ion generators including: 1. Schedule of plasma generators indicating unit designation, number of each type
required for each unit/application. 2. Data sheet for each type of plasma generator, plasma detector and accessory
furnished; indicating construction, sizes, and mounting details. 3. Performance data for each type of plasma device furnished. 4. Indoor Air Quality calculations using the formulas within ASHRAE Standard 5. 62.1-2007 to validate acceptable indoor air quality at the quantity of outside air 6. Scheduled (when projects are designed with outside air reduction). 7. Product drawings detailing all physical, electrical and control requirements. 8. Copy of UL 867 independent ozone test.
B. Operating & Maintenance Data: Submit O&M data and recommended spare parts lists.
1.7 PRODUCT DELIVERY, STORAGE AND HANDLING
A. Deliver in factory fabricated shipping containers. Identify on outside of container type of product and location to be installed. Avoid crushing or bending.
B. Store in original cartons and protect from weather and construction work traffic. C. Store indoors and in accordance with the manufacturers’ recommendation for storage.
1.8 WARRANTY
A. Equipment shall be warranted by the manufacturer against defects in material and
workmanship for a period of eighteen months after shipment or twelve months from owner acceptance, whichever occurs first. Labor to replace equipment under warranty shall be provided by the installing contractor.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 3
PART 2 - PRODUCTS 2.1 GENERAL
A. The air purification system(s) shall be of the size, type, arrangement and capacity indicated and required by the unit furnished and shall be of the manufacturer specified.
B. Acceptable manufacturers: 1. Active Air Solutions 2. Bioclimatic 3. Global Plasma Solutions (Basis of Design) 4. Plasma Air
C. All other Suppliers of comparable products requesting prior approval shall:
1. Submit for prior approval four weeks in advance. 2. In addition, manufacturers submitting for prior approval for Bi-Polar Ionization must
as part of the prior approval request provide their ASHRAE 62.1-2010 calculations that prove conformance to the ASHRAE Standard with the reduction of outside air to the scheduled values. A letter on the manufacturer’s letterhead requesting prior approval must accompany the request for prior approval stating their calculations are ASHRAE compliant. A third party validation study performed on a previous installation of the same application shall also be included.
3. Submit independent test data from ETL or UL showing ozone levels produced during the UL 867 ozone chamber test. Manufacturers without this test data shall not be acceptable.
4. Submit pathogen testing per section 2.2. 5. Submit at least two other end user references in the same application with contact
phone number, email, equipment used and application for the equipment at that facility. Manufacturers not having the above references in similar applications using the same equipment models as proposed on the current project shall not be acceptable.
2.2 BI-POLAR IONIZATION DESIGN & PERFORMANCE CRITERIA
A. Each piece of air handling equipment, so designated on the plans, details, equipment schedules and/or specifications shall contain a Plasma Generator with Bi-polar Ionization output as described here within.
B. The Bi-polar Ionization system shall be capable of:
1. Effectively killing microorganisms downstream of the bi-polar ionization equipment (mold, bacteria, virus, etc.).
2. Controlling gas phase contaminants generated from human occupants, building structure, furnishings and outside air contaminants.
3. Capable of reducing static space charges. 4. Effectively reducing space particle counts. 5. When mounted to the air entering side of a cooling coil, keep the cooling coil free
from pathogen and mold growth. 6. All manufacturers shall provide documentation by an independent NELEC
accredited laboratory that proves the product has minimum kill rates for the following pathogens given the allotted time and in a space condition:
a. MRSA - >96% in 30 minutes or less
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 4
b. E.coli - > 99% in 15 minutes or less c. TB - > 69% in 60 minutes or less d. C. diff - >86% in 30 minutes or less
7. Manufacturers not providing the equivalent space kill rates shall not be acceptable. All manufactures requesting prior approval shall provide to the engineer independent test data from a NELEC accredited independent lab confirming kill rates and time meeting the minimum requirements stated in section 2.2 B, points 6A, 6B and 6C. Products tested only on Petri dishes to prove kill rates shall not be acceptable. Products being sold under different trade names than those tested shall not be acceptable.
C. The bi-polar ionization system shall operate in a manner such that equal amounts of
positive and negative ions are produced. Uni-polar ion devices shall not be acceptable. 1. Air exchange rates may vary through the full operating range of a constant
Volume or VAV system. The quantity of air exchange shall not be increased due to requirements of the air purification system.
2. Velocity Profile: The air purification device shall not have maximum velocity profile.
D. Humidity: Plasma Generators shall not require preheat protection when the relative humidity of the entering air exceeds 85%. Relative humidity from 0 - 100%, condensing, shall not cause damage, deterioration or dangerous conditions within the air purification system. Air purification system shall be capable of wash down duty.
E. Equipment Requirements:
1. Electrode Specifications (Bi-polar Ionization):
a. Each Plasma Generator with Bi-polar Ionization output shall include the required number of electrodes and power generators sized to the air handling equipment capacity. A minimum of sixteen 316 medical grade stainless steel ion needles per foot of coil face width shall be provided. The entire cooling coil shall width shall have equal distribution of ionization across the face. The plasma electrode shall require no more than one inch in the direction of airflow for mounting. All hardware required for mounting shall be provided by the air handler unit manufacturer. Bi-polar ionization tubes manufactured of glass and steel mesh shall not be acceptable due to replacement requirements, maintenance, and performance output reduction over time, ozone production and corrosion. Plasma generators with recessed needles shall not be acceptable.
b. Electrodes shall be energized when the main unit disconnect is turned on and the fan is operating.
F. Air Handler Mounted Units: 1. Where so indicated on the plans and/or schedules Plasma Generator(s) shall be
supplied and installed. The mechanical contractor shall mount the Plasma Generator and wire it to the remote mount power supply using the high voltage cables provided by the air purification manufacturer. An 115VAC or 230VAC circuit shall be provided to the ion generator power supply panel. Each ion generator shall be designed with an aluminum casing, integral grounding connection and high voltage quick connector.
G. Ionization Requirements:
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 5
1. Plasma Generators with Bi-polar ionization output shall be capable of controlling gas phase contaminants and shall be provided for all equipment listed above.
a. The Bi-polar ionization system shall consist of Bi-Polar Plasma Generator
and power supply. The Bi-polar system shall be installed where indicated on the plans or specified to be installed. The device shall be capable of being powered by 115VAC or 230VAC without the use of an external transformer. Ionization systems requiring isolation transformers shall not be acceptable.
b. Ionization Output: he ionization output shall be controlled such that an equal number of positive and negative ions are produced. Imbalanced levels shall not be acceptable.
c. Ionization output from each electrode shall be a minimum of 20 million ions/cc when tested at 2” from the ionization generator.
2. Ozone Generation:
a. The operation of the electrodes or Bi-polar ionization units shall conform
to UL 867-2007 with respect to ozone generation.
H. Electrical Requirements:
1. Wiring, conduit and junction boxes shall be installed within housing plenums in accordance with NEC NFPA 70. Plasma Generator shall accept an electrical service of 115 VAC or 230VAC, 1 phase, 50/60 Hz. The contractor shall coordinate electrical requirements with air purification manufacturer during submittals.
I. Control Requirements:
1. All Plasma Generators shall have internal short circuit protection, overload protection, and automatic fault reset.
2. The ionization system shall be provided with a stand-alone, independent ion sensor designed for duct mounting to monitor the ion output and report to the BAS system that the ion device is working properly. Ion systems provided without an independent ion sensor, shall not be permitted. The control voltage to power the ion sensor shall be 12VDC, 24VDC or 24VAC and draw no more than 150mA of current. The sensor shall provide at minimum, dry contact status to the BAS and optionally a BacNet interface as specified on the control drawings.
3. The installing contractor shall mount and wire the Plasma device within the air handling unit specified or as shown or the plans. The contractor shall follow all manufacturer IOM instructions during installation.
4. Provide interlock to AHU fan to energize the BPI unit, ONLY when the fan is “ON”. Fully coordinate all requirements with the BCS Contractor prior to bid.
2.3 PLASMA DETECTOR DESIGN & PERFORMANCE CRITERIA
A. Each piece of air handling equipment, so designated on the plans, details, equipment schedules and/or specifications shall contain a Plasma Detector with integral BAS contacts.
B. The Plasma Detector sensor shall be designed to these minimum standards:
1. Ability to detect both positive and negative ion levels from 1,000 ions/cc to 20 million ions/cc minimum. Detection limit shall be field adjustable based on sensor mounting location and manufacturer being sensed.
2. Plasma detector shall have integral dry alarm contacts for connection to the BAS to prove the ion system is operating properly and the ion system output is above the
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Buildings 3, 4, 7, 10, 13, 14, 18
AIR PURIFICATION SYSTEM 23 44 00 - 6
minimum preset threshold from the sensor manufacturer. The alarm shall activate when either positive or negative ion output drops below the preset setpoint. Cold plasma systems only providing indication the input power is applied or output power is present shall not be acceptable. The independent cold plasma detector shall be capable of working with any air purification manufacturer’s system.
3. Cold plasma detector shall have an input voltage of 12VDC, 24VDC or 24VAC user selectable.
4. Cold plasma detector shall be capable of duct mounting or integral air stream mounting.
5. Housing shall be constructed of fire retardant ABS plastic. 6. Temperature and humidity shall have no affect on the cold plasma detector output
accuracy. 7. The alarm output shall be provided with NO, NC and C terminals for ease of
integration to the BAS. The contacts shall be rated for up to 5 amps at 230VAC or up to 24VDC at 2 amps.
8. A BACnet control interface shall be provided by the cold plasma detector manufacturer.
PART 3 - EXECUTION 3.1 GENERAL
A. The Contractor shall be responsible for maintaining all air systems until the owner accepts the building (Owner Acceptance).
3.2 ASSEMBLY & ERECTION: PLASMA GENERATOR WITH BI-POLAR IONIZATION & COLD
PLASMA DETECTOR
A. All equipment shall be assembled and installed in a workman like manner to the satisfaction of the owner, architect, and engineer.
B. Any material damaged by handling, water or moisture shall be replaced, by the mechanical contractor, at no cost to the owner.
C. All equipment shall be protected from dust and damage on a daily basis throughout construction.
3.3 TESTING
A. Provide the manufacturers recommended electrical tests.
3.4 COMMISSIONING & TRAINING
A. A manufacturer's authorized representative shall provide start-up supervision. END OF SECTION 23 44 00
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
METAL LOCKERS 105113 - 9
a. Attach plates to each locker door, near top, centered, with at least two aluminum
rivets.
D. Trim: Fit exposed connections of trim, fillers, and closures accurately together to form tight,
hairline joints, with concealed fasteners and splice plates.
1. Attach filler panels with concealed fasteners. Locate filler panels where indicated on
Drawings.
2. Attach sloping-top units to metal lockers, with closures at exposed ends.
3. Attach boxed end panels using concealed fasteners to conceal exposed ends of
nonrecessed metal lockers.
3.3 ADJUSTING
A. Clean, lubricate, and adjust hardware. Adjust doors and latches to operate easily without
binding.
3.4 PROTECTION
A. Protect metal lockers from damage, abuse, dust, dirt, stain, or paint. Do not permit use during
construction.
B. Touch up marred finishes, or replace metal lockers that cannot be restored to factory-finished
appearance. Use only materials and procedures recommended or furnished by locker
manufacturer.
END OF SECTION 105113
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-1
SECTION 275123 - EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes user-programmable, multichannel, microprocessor-switched, centrally
controlled, school intercom and program equipment independent of telephone equipment.
Provide connection to school telephone switch.
1.3 SUBMITTALS
A. Product Data: For the following:
1. Speaker-microphone stations.
2. Call-switch units.
3. Volume controls.
4. Speakers.
5. Horns.
6. Amplifier.
B. Shop Drawings:
1. Equipment Details: Detail equipment assemblies and indicate dimensions, weights,
required clearances, method of field assembly, components, and location of each field
connection.
2. Station-Arrangement Details: Scaled drawings for built-in equipment.
3. Wiring Diagrams: Power, signal, and control wiring. Include the following:
a. Identify terminals to facilitate installation, operation, and maintenance.
b. Single-line diagram showing interconnection of components.
c. Cabling diagram showing cable routing.
C. Coordination Drawings: Reflected ceiling plans, drawn to scale, on which the following items
are shown and coordinated with each other, based on input from installers of the items involved:
1. Ceiling-mounted items including lighting fixtures, diffusers, grilles, speakers, sprinklers,
access panels, and special moldings.
D. Field quality-control test reports.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-2
1.4 QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved
for installation of units required for this Project.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Comply with NFPA 70.
D. Comply with UL 50.
1.5 COORDINATION
A. Coordinate layout and installation of ceiling-mounted speaker microphones and suspension
system with other construction that penetrates ceilings or is supported by them, including light
fixtures, HVAC equipment, fire-suppression system, and partition assemblies.
PART 2 - PRODUCTS
2.1 EQUIPMENT AND MATERIALS
A. Existing console, Telecor XL.
B. Coordinate features to form an integrated system. Match components and interconnections for
optimum performance of specified functions.
C. Provide additional amplifiers station cards, extension modules and other equipment as required
for complete operable system.
2.2 CONE-TYPE LOUDSPEAKERS/SPEAKER MICROPHONES
A. Comply with TIA/EIA SE-103.
B. Minimum Axial Sensitivity: TIA/EIA SE-103 pressure rating of 45 dB.
C. Frequency Response: Within plus or minus 3 dB from 70 to 15,000 Hz.
D. Minimum Dispersion Angle: 100 degrees.
E. Line Transformer: Comply with TIA/EIA-160, maximum insertion loss of 0.5 dB, power rating
equal to speaker's, and at least 4 level taps.
F. Enclosures: Steel housings or back boxes, acoustically dampened, with front face of at least
0.0478-inch (1.2-mm) steel and whole assembly rust proofed and factory primed; complete with
mounting assembly and suitable for surface ceiling, flush ceiling, pendant or wall mounting;
and with relief of back pressure.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-3
G. Baffle: For flush speakers, minimum thickness of 0.032-inch (0.8-mm) aluminum, with textured
white finish.
H. Size: 8 inches (200 mm) with 1-inch (25-mm) voice coil and minimum 5-oz. (140-g) ceramic
magnet.
2.3 HORN-TYPE LOUDSPEAKERS/SPEAKER MICROPHONES
A. Comply with TIA/EIA SE-101-A. All-metal, weatherproof construction; complete with
universal mounting brackets.
B. Frequency Response: Within plus or minus 3 dB from 275 to 14,000 Hz.
C. Minimum Power Rating of Driver: 15 W, continuous.
D. Minimum Dispersion Angle: 110 degrees.
E. Line Transformer: Comply with TIA/EIA-160, maximum insertion loss of 0.5 dB, power rating
equal to speaker's, and at least 4 level taps.
F. Provide weatherproof adapter.
2.4 CALL-SWITCH UNIT
A. Enclosure: Single-gang box with stainless-steel faceplate.
B. Call Switch: Momentary contact signals system that a call has been placed. Switch shall
be rocker style.
2.5 VOLUME CONTROL UNIT
A. Enclosure: Single-gang box with stainless-steel faceplate. For surface mount locations,
provide extensions to back boxes to allow sufficient space for terminations. For locations
recessed in walls, terminate conduits towards the back of the device box and provide same
extensions for additional room to allow sufficient space for terminations.
B. Volume Control: Operated by knob / dial to adjust output level of associated speaker.
2.6 CONDUCTORS AND CABLES
A. Conductors: Jacketed, twisted pair and twisted multi-pair, untinned solid copper. Sizes as
recommended by system manufacturer, but not smaller than No. 22 AWG. Use multi
conductor cables from control equipment to communication rooms (single station cables will
not be acceptable).
B. Insulation: Thermoplastic, not less than 1/32 inch (0.8 mm) thick.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-4
C. Shielding: For speaker-microphone leads and elsewhere where recommended by manufacturer;
No. 34 AWG tinned, soft-copper strands formed into a braid or equivalent foil.
1. Minimum Shielding Coverage on Conductors: 60 percent.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Wiring Method: Install wiring in raceways except within communication room, consoles,
desks, and counters. Conceal cables and raceways except in unfinished spaces.
B. Wiring within Enclosures and Communication Room: Bundle, lace, and train conductors to
terminal points with no excess. Use lacing bars.
C. Control-Circuit Wiring: Install number and size of conductors as recommended by system
manufacturer for control functions indicated.
D. Splices, Taps, and Terminations: Arrange on numbered terminal strips in junction, pull, and
outlet boxes; terminal cabinets; and equipment enclosures.
E. Match input and output impedances and signal levels at signal interfaces. Provide matching
networks where required.
F. Identification of Conductors and Cables: Color-code conductors and apply wire and cable
marking tape to designate wires and cables so they identify media in coordination with system
wiring diagrams.
G. Weatherproof Equipment: For units that are mounted outdoors, in damp locations, or where
exposed to weather, install consistent with requirements of weatherproof rating.
3.2 GROUNDING
A. Ground cable shields and equipment to eliminate shock hazard and to minimize ground loops,
common-mode returns, noise pickup, cross talk, and other impairments.
B. Signal Ground Terminal: Locate at main equipment cabinet. Isolate from power system and
equipment grounding.
3.3 FIELD QUALITY CONTROL
A. Manufacturer's Field Service: Engage a factory-authorized service representative to
inspect, test, and adjust field-assembled components and equipment installation, including
connections, and to assist in field testing. Report results in writing.
B. Perform the following field tests and inspections and prepare test reports:
1. Schedule tests with at least seven days' advance notice of test performance.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-5
2. After installing school intercom and program equipment and after electrical circuitry has
been energized, test for compliance with requirements.
3. Operational Test: Test originating station-to-station, all-call, and page messages at each
intercom station. Verify proper routing and volume levels and that system is free of noise
and distortion. Test each available message path from each station on system.
4. Frequency Response Test: Determine frequency response of two transmission paths,
including all-call and paging, by transmitting and recording audio tones. Minimum
acceptable performance is within 3 dB from 150 to 2500 Hz.
5. Signal-to-Noise Ratio Test: Measure signal-to-noise ratio of complete system at normal
gain settings as follows:
a. Disconnect speaker microphone and replace it in the circuit with a signal generator
using a 1000-Hz signal. Measure signal-to-noise ratio at paging speakers.
b. Repeat test for three speaker microphones, one master station microphone, and for
each separately controlled zone of paging loudspeakers.
c. Minimum acceptable ratio is 45 dB.
6. Distortion Test: Measure distortion at normal gain settings and rated power. Feed
signals at frequencies of 150, 200, 400, 1000, and 2500 Hz into each intercom, paging,
and all-call amplifier. For each frequency, measure distortion in the paging and all-call
amplifier outputs. Maximum acceptable distortion at any frequency is 5 percent total
harmonics.
7. Acoustic Coverage Test: Feed pink noise into system using octaves centered at 500 and
4000 Hz. Use sound-level meter with octave-band filters to measure level at five
locations in each paging zone. Maximum permissible variation in level is plus or minus
3 dB; in levels between adjacent zones, plus or minus 5 dB.
8. Power Output Test: Measure electrical power output of each paging amplifier at normal
gain settings of 150, 1000, and 2500 Hz. Maximum variation in power output at these
frequencies is plus or minus 3 dB.
9. Signal Ground Test: Measure and report ground resistance at system signal ground.
Comply with testing requirements in Division 26 Section "Grounding and Bonding for
Electrical Systems."
C. Retesting: Correct deficiencies and retest. Prepare a written record of tests.
D. Inspection: Verify that units and controls are properly labeled and interconnecting wires and
terminals are identified. Prepare a list of final tap settings of paging and independent room
speaker-line matching transformers.
E. Prepare written test reports.
1. Include a record of final speaker-line matching transformer-tap settings, and signal
ground-resistance measurement certified by Installer.
3.4 STARTUP SERVICE
A. Engage a factory-authorized service representative to perform startup service and initial system
programming.
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
EDUCATIONAL INTERCOMMUNICATIONS PROGRAM SYSTEM 275123-6
B. Verify that electrical wiring installation complies with manufacturer's submittal and installation
requirements.
C. Complete installation and startup checks according to manufacturer's written instructions.
3.5 ADJUSTING
A. On-Site Assistance: Engage a factory-authorized service representative to provide on-site
assistance in adjusting sound levels, resetting transformer taps, and adjusting controls to meet
occupancy conditions.
B. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion,
provide on-site assistance in adjusting system to suit actual occupied conditions. Provide up to
four visits to site outside normal occupancy hours for this purpose, without additional cost.
3.6 DEMONSTRATION
A. Engage a factory-authorized service representative to train Owner's maintenance personnel to
adjust, operate, and maintain school intercom and program equipment. Refer to Division 01
Section "Demonstration and Training."
Train Owner's maintenance personnel on programming equipment for starting up and
shutting down, troubleshooting, servicing, and maintaining equipment.
END OF SECTION 275123
Nease High School Project Number 2015-30
Expansion, Renovations, and Site Improvements Pod Renovations
DATA, VOICE AND VIDEO 280500-1
SECTION 280500 - DATA, VOICE AND VIDEO
THE COMMUNICATIONS AND ELETRICAL CONTRACTORS SHALL OBTAIN AND
THOROUGHLY FAMILIARIZE THEMSELVES WITH THE MOST CURRENT RELEASE OF THE
ST. JOHNS COUNTY SCHOOL DISTRICT TECHNOLOGY DEPARTMENT “VOICE AND DATA
STRUCTURED CABLING STANDARD” (ATTACHED) WHICH BY REFERENCE SHALL
BECOME A PART OF THIS SPECIFICATION. IN EVENT OF CONFLICT WITH PROJECT
SPECIFICATIONS, THE SJCSD “STRUCTURED CABLING STANDARD” SHALL PREVAIL.
END OF SECTION 280500
IT Department
Revised Mar 2017 1 Structured Cabling Standards-Version 7.0
St Johns County School District
Voice and Data
Structured Cabling Standards
IT Department
Revised Mar 2017 2 Structured Cabling Standards-Version 7.0
Table of Contents
Article 1. General Information ...................................................................................................... 5
Article 2. Telecommunications Conduit Systems ......................................................................... 6
Article 3. Telecommunications Rooms ......................................................................................... 7
Article 4. Support Systems .......................................................................................................... 10
Article 5. Electrical Power .......................................................................................................... 10
Article 6. Telecommunications Systems Grounding/Bonding .................................................... 11
Article 7. Environmental Requirements for Telecommunications Rooms ................................. 11
Article 8. Horizontal Structured Cabling .................................................................................... 12
Article 9. Backbone Cabling and Installation ............................................................................. 16
Article 10. Wireless Voice and Data Network Design Requirements ....................................... 18
Article 11. Labeling and Administration .................................................................................. 19
Article 12. Testing and Documentation ..................................................................................... 22
Article 13. Relocatable Classroom Systems Specs. .................................................................. 23
Article 14. Classroom Audio/Visual Technology ..................................................................... 31
Article 15. Applicable Industry Standards ................................................................................ 42
IT Department
Revised Mar 2017 3 Structured Cabling Standards-Version 7.0
Document Updates:
Section/
Article Summary of Changes Changes by
Change
Date
Document
Version #
11.02 Added test results submittal email Justin Forfar 10 Oct 06 V4.0
All Version 4.2 Released Justin Forfar 11 Oct 06 V4.2
All Changed from Cat5E to Cat6 spec Justin Forfar 8 Nov 06 V4.2
9.01(c) Addressed space issues brought up by
engineers
Justin Forfar 14 Nov 06 V4.2
8 Added Cat6 performance spec Justin Forfar 14 Nov 06 V4.2
3 Added cable mgmt and cable tray
reqs
Justin Forfar 27 Feb 07 V4.21
10 Added wireless network spec article Justin Forfar 19 Nov 07 V4.22
3.01(b) Added requirement for ER and TR
detail drawings
Justin Forfar 10 Dec 07 V4.22
5.02(b) Removed requirement isolated ground Justin Forfar 24 Sep 08 V4.22
9.02(e) Removed fiber jumper provision Justin Forfar 8 Oct 08 V4.22
14 New Chris Petrello 10 Oct 08 V4.22
All Format, add TOC Bruce Patrou 14 Oct 08 V4.22.3
All Released Version 4.22.4 Justin Forfar 15 Oct 08 V4.22.4
14.01(b) Clarified requirement for master
volume control via teacher control
wallplate
Justin Forfar 6 Jan 10 V4.3
14 Added Model Classroom AV
inspection requirement
Justin Forfar 6 Jan 10 V4.3
14.01(l) Clarification of AV shelf mounting
height and location
Justin Forfar 6 Jan 10 V4.3
14.01(e) Added model number for Wall Plate 1 Justin Forfar 6 Jan 10 V4.3
All Released Version 4.3 Justin Forfar 6 Jan 10 V4.3
11 Clarified labeling and install
requirements for WAP WAOs, MLC
WAOs
Justin Forfar 10 Mar 11 V5.0
8.05 Clarified TR side requirements for
modular jack color codes
Justin Forfar 10 Mar 11 V5.0
8.01 Clarified horizontal data cabling
options
Justin Forfar 10 Mar 11 V5.0
9.02 Updated Fiber Optic cabling
specifications
Justin Forfar 22 Mar 11 V5.0
IT Department
Revised Mar 2017 4 Structured Cabling Standards-Version 7.0
14 Complete rewrite to include Extron
PoleVault Standard including new
AVerMedia Tuners, Clarified
projection screen size and throw
distance
Justin Forfar 30 Mar 11 V5.0
13 General update of portables section-
new pedestal types, added detail
drawings for portables.
Justin Forfar 30 Mar 11 V5.0
13.01 Added diagram for standard
relocatable classroom data pedestal
buildout.
Justin Forfar 3 May 12 V5.5
8.04 Edited section title to include
faceplates as well as patch panels
Justin Forfar 3 May 12 V5.5
10.0 Revised wireless standards to include
AP mfr, two cables per location
Justin Forfar 3 May 12 V5.5
14.03 Added Chief CMA470 Plenum
enclosure to PoleVault System parts
list
Justin Forfar 3 May 12 V5.5
14 Edited Exhibit E to reflect use of
Chief CMA470 Plenum enclosure
Justin Forfar 3 May 12 V5.5
14 Removed Extron PoleVault Standard
and added “New Solution TBD”
Justin Forfar 21 Mar 16 V6
8 Removed reference to AMP product
line. Added Panduit and General Cat6
parts as approved cabling options
Justin Forfar 21 Mar 16 V6
9.02 Corrected reference to LC singlemode
connectors with SC.
Justin Forfar 21 Mar 16 V6
8.03 Reduced the number of data cables in
each CWAO from three to two. Total
number of CWAOs within a
classroom DID NOT change.
Justin Forfar 23 Mar 16 V6
14 Added equipment performance
standards and diagrams outlining new
AV standard
Justin Forfar 10 Mar 17 V7.0
8 Removed plenum cable requirement Justin Forfar 10 Mar 17 V7.0
9 Added clarification regarding
plenum/non-plenum cabling
requirements
Justin Forfar 10 Mar 17 V7.0
IT Department
Revised Mar 2017 5 Structured Cabling Standards-Version 7.0
Article 1. General Information
Section 1.01 Statement of Purpose
The purpose of this document is to enumerate the standards and practices to be followed when designing
structured cabling systems for the St Johns County School District. Each section of this document outlines: 1)
a specific part of a structured cabling system or manner in which a product or technology should be installed
or 2) a specific product line or product that shall be used for a certain part of an installation. This document is
to be used in conjunction with all applicable industry standards and codes to provide the St Johns County
School District with a flexible, scalable, easily managed, properly documented structured cabling network.
Section 1.02 General Voice and Data Network Service Requirements
(a) All areas of a building shall be equipped with voice and data network access during the design
phase. These areas include but are not limited to:
(i) Classroom and learning spaces including teacher planning rooms
(ii) Administrative offices including conference rooms and work rooms
(iii) Storage spaces including book storage and central receiving
(iv) Media/Library spaces including all work rooms, professional work spaces, and group project
areas
(v) Auditorium spaces including ticket windows, concessions, dressing areas, and control booth
(vi) Gym spaces including all coaches offices, breakout rooms, trainer’s offices, and nurse’s offices
(vii) Athletic fields including all field houses and press boxes
Section 1.03 Terminology
(a) MTR – Main telecommunications room that houses all core electronics and telephone service
provider demark
(b) TR –Telecommunications room located throughout site as cable length requires
(c) Work Area Outlet (WAO) - a location within a classroom or office that offers a connection or
group of connections to the structured cabling network.
(d) TBB- Telecommunications Bus Bar
(e) WAP- Wireless access point
(f) EC- Equipment cabinet – may house active or passive equipment
IT Department
Revised Mar 2017 6 Structured Cabling Standards-Version 7.0
Article 2. Telecommunications Conduit Systems
Section 2.01 General Standards for Conduit
(a) All voice or data conduits installed between an MTR or TR and another MTR/TR shall be filled
to capacity with 1” nominal inside diameter corrugated innerduct.
(b) A ½” 1200lb rated pull tape shall be installed in each innerduct and secured at each end.
(c) Each conduit shall be capped with a duplex, triplex, or quadplex divider based on conduit size
and installation requirements.
Section 2.02 Outside Plant Conduit
(a) Future Relocatable Classroom Service
(i) A minimum of two (2) each four inch (4”) plastic Polyvinyl Chloride(PVC) conduits of schedule
40 or equivalent shall be installed from the MTR/TR nearest the forecasted relocatable classroom
site and terminated at least ten feet from the building to allow for the installation of future voice
and data backbone cabling to the relocatable classrooms
1) End of conduits shall be clearly identified by a concrete marker as shown below:
IT Department
Revised Mar 2017 7 Structured Cabling Standards-Version 7.0
Article 3. Telecommunications Rooms
Section 3.01 Telecommunications Room Design and Build-out Requirements
(a) Engineer or designer shall consult w/ the current Information Technology Department project
contact to determine specific MTR/TR layout needs.
(b) Engineer or designer shall provide detail drawings for MTR and each TR in the telecom section
of drawings. Detail drawings shall include at a minimum:
(i) Front views of each equipment rack to be installed in the respective MTR/TR showing actual
LIU and horizontal patch panel locations and quantity, type and quantity of cables to be
terminated on said patch panel, panel numbers and jack labels, and open space for customer
provided equipment
(ii) A chart outlining the quantities of each drop type to be installed in each respective
MTR/TR.(example below)
Table 3.01.1
TR-XXX Cable Count
(iii) Each detail drawing shall be clearly labeled by TR’s
FISH number.
(c) All TRs shall be designed with sufficient floor space to
facilitate the use of floor standing racks for the support of all
voice and data cabling and electronics.
(i) The use of wall mounted racks, either swing-gate or fixed is prohibited unless prior written
approval is given by the current Information Technology Department project contact. These
WAO Type Qty
TWAO 5
AWAO 4
SWAO 3
WAP 3
… …
IT Department
Revised Mar 2017 8 Structured Cabling Standards-Version 7.0
types of racks are notoriously difficult for District IT staff and vendors to service once
electronics, fiber jumpers, and copper patch cords have been installed in/on them.
(d) Each MTR and TR shall have a drop ceiling set at 10’AFF.
(e) All TRs shall have 3/4” plywood backboard covering all four (4) walls from 12” AFF to a
height of 9’ AFF. All plywood backboard shall be painted with 2 coats fire retardant on all 6
sides. All plywood backboard shall be A/C grade with the "A" side out.
(f) Ladder rack shall be installed around perimeter of TR at 8’ AFF. All floor standing racks shall
be mechanically bonded to the installed ladder rack for support.
(i) Ladder rack should be Chatsworth Products Inc. Cable Runway® and Radii Bends® or
approved equal. A minimum width of 12” is required.
(ii) A cable runway radius drop (waterfall) must be used to support cables transitioning from ladder
tray to equipment racks or another cable tray above or below the transition point.
Section 3.02 Equipment Rack and Enclosure Requirements
(a) Floor mounted equipment racks (ER)
(i) A standard 84” two post rack shall be provided and securely fastened to bare concrete or tile
floor.
(ii) Isolation pads shall be placed between the rack and the bare concrete floor.
(b) Enclosures/Cabinets-
(i) Floor mounted equipment cabinets (EC) shall be installed in a manner that allows full access to
both the front and the rear of the cabinet. Where a specific part number is listed, only that part
number will be accepted unless prior written approval is received from the current Information
Technology project contact.
1) 70” Floor-mount EC
a) Hubbell part number HPW70C19X30
(ii) Wall mounted cabinets shall be mounted in a manner that allows the EC’s front door and center
to swing fully open. Additionally, all wall mounted cabinets shall be affixed to a ¾” plywood
backboard that has been painted with a fire retardant paint.
1) 48” Wall-mount/Floor-mount EC
a) Hubbell part number HSQ4826
2) 36” Wall-mount/Floor-mount EC
a) Hubbell part number HSQ3626
IT Department
Revised Mar 2017 9 Structured Cabling Standards-Version 7.0
Section 3.03 Equipment Rack Cable Management
(a) Approved vertical and horizontal wire management is listed below (no other models will be
accepted under ANY circumstances):
(i) Horizontal Management – Panduit Part # WMPH2E
(ii) Vertical Management – Panduit Part # WMPVHC45E
IT Department
Revised Mar 2017 10 Structured Cabling Standards-Version 7.0
Article 4. Support Systems
Section 4.01 TBD
Article 5. Electrical Power
Section 5.01 General Power Requirements
(a) All power outlets that serve communications rooms shall originate from a branch panel that
serves only this sensitive equipment.
(b) Any and all circuits serving an MTR or TR are critical for building support and life safety
systems (Voice, Data, BMS, EMS, A/C controls, security, surveillance, etc) and are required to
be serviced by the site’s backup generator.
Section 5.02 Power Conditioning and Protection Requirements
(a) Transient voltage surge suppression (TVSS) systems shall be installed, at a minimum, in front
of every branch panel that will service communications rooms and equipment.
Section 5.03 Telecommunications Room Power Requirements
(a) A duplex NEMA5-20R receptacle serviced by a single 20Amp circuit shall be installed at a
minimum of every three feet (3’) at 18” AFF on all four (4) walls in all TR.
(b) A quad NEMA5-20R serviced by two 20Amp circuits, one circuit per duplex receptacle, shall
be provided at the base of each floor-mounted equipment rack. The installation method shall
not interfere with any horizontal or riser cable routing into the management, owner provided
equipment placement or create the potential for EMI.
(c) Any special receptacle and power needs will be specified on an individual project basis. Please
see current Information Technology Department project contact for locations and quantities of
special receptacles.
Section 5.04 Equipment Cabinet Power Requirements
(a) All equipment cabinets shall receive a duplex NEMA5-20R serviced by a single 20AMP circuit
mounted inside of the equipment cabinet in the top right corner in manner that does not interfere
with the locking mechanism of the cabinet or equipment mounting.
IT Department
Revised Mar 2017 11 Structured Cabling Standards-Version 7.0
Article 6. Telecommunications Systems Grounding/Bonding
Section 6.01 Design
(a) Grounding and bonding systems shall be designed using the TIA-942, ANSI/J-STD- 607-A,
NEC 800.90(A), NEC 250 and NFPA 780 standards. Whenever two or more standards are in
conflict with one another, the more stringent standard applies.
Section 6.02 Specific Grounding Requirements
(a) Relocatable Classroom Grounding and Bonding Requirements
(i) A TBB shall be installed in a relocatable classroom TR’s equipment cabinet (EC) and shall be
bonded directly to the nearest electrical panel ground using a green insulated 6 AWG
conductor. In cases where running a ground conductor to the nearest electrical panel is not
possible, a ground conductor shall be bonded to the structural steel of the relocatable
classroom.
Article 7. Environmental Requirements for Telecommunications Rooms
Section 7.01 Room Conditioning Requirements
(a) A single room AC unit shall be installed in the MTR and each TR located in a building to allow
the temperature in each MTR and TR to be maintained at the optimum level separate from the
building HVAC systems.
Section 7.02 Temperature Requirements
(a) All MTRs and TRs should be kept at a temperature range of 68-75 degrees Fahrenheit per
BICSI TDM Ch 8-19.
IT Department
Revised Mar 2017 12 Structured Cabling Standards-Version 7.0
Article 8. Horizontal Structured Cabling-- Cabling and connectivity installed in any St
Johns County School District building must carry at a minimum a 20 year warranty through the
cable manufacturer that will apply to the complete end-to-end installed solution. EIA/TIA
Standard 568B wiring scheme shall be used for all horizontal cabling terminations. Horizontal
Cat6 copper cable must be rated at 250 Mhz or better and must be appropriate and suitable for
the installation environment, whether plenum or non-plenum, for which it is destined Cabling
contractors shall possess Panduit PCI and Corning NPI/EWP manufacturer certifications.
Section 8.01 Approved Horizontal Copper Cabling Manufacturers and Models
(i) Belden DataTwist 2400 (non-bonded or bonded-pair) (minimum)
(ii) Panduit TX6 (minimum)
(iii) General GenSpeed 6000 (minimum)
Section 8.02 Horizontal Cabling Color Codes
The jacket color for all horizontal data cable installed in St Johns County School District building shall
follow the color codes listed below.
(a) Data- Yellow jacket
(b) Voice- Green jacket
(c) Wireless Access Point- Blue jacket
(d) Security, fire, building automation device or audio visual controller- White jacket
IT Department
Revised Mar 2017 13 Structured Cabling Standards-Version 7.0
Section 8.03 Communications Work Area Outlets (WAO)
(a) Administrative WAO (AWAO)
(i) An administrative WAO should consist of one (1) Cat6 voice connection and one (1) Cat6 data
connection.
(ii) Each administrative area/office shall have a minimum of two administrative WAOs on
opposite sides of the room and each WAO shall be no more than two feet away from power.
(b) Teacher WAO (TWAO)
(i) A teacher WAO shall consist of one (1) Cat6 voice connection, one (1) Cat6 data connection.
(ii) Each classroom and resource room shall have one teacher WAO and each WAO shall be no
more than two feet away from power
(c) Workrooms/Storage Rooms/School Store WAO (SWAO)
(i) A Workroom/Storage Room/School Store WAO shall consist of one (1) Cat6 voice connection
and one (1) Cat6 data connection
(ii) Each Workroom/Storage Room/School Store shall have one Workroom/Storage Room/School
Store WAO that is no more than two feet away from power.
(d) Classroom\Resource Room WAO (CWAO)
(i) A classroom WAO shall consist of two (2) Cat6 data connections
(ii) Each classroom and resource room shall have a minimum of two WAOs and each WAO should
be no more than two feet away from power.
(e) Media Center WAO (MWAO)
(i) A Media Center WAO shall consist of four (4) Cat6 data connections.
(ii) The exact quantity and placement of Media Center WAOs will be determined by room size and
furniture layout.
(f) Kitchen/Cafeteria Manager Office WAO (KWAO)
(i) A Kitchen/Cafeteria Manager Office WAO shall consist of one (1) Cat6 data connections and
(2) Cat6 voice connections terminated using shuttered jacks.
IT Department
Revised Mar 2017 14 Structured Cabling Standards-Version 7.0
(g) Wireless Access Point (WAP) WAO (WAP)
(i) A wireless access point WAO shall consist of two (2) Cat6 data connections
(ii) The exact quantity and placement of Wireless Access Point WAOs will be determined by
building size and layout. It should be assumed that ALL areas of a building shall require
complete, full, and redundant coverage. WAP WAOs shall be installed above the drop ceiling
and terminated in a 2 position surface mount (biscuit) box (Panduit part # CBXS2EI-A) w/ 10’
IT Department
Revised Mar 2017 15 Structured Cabling Standards-Version 7.0
of service loop at the station end to allow for a wireless access point to be placed where needed
by the IT Department. (see Section 10 for Wireless LAN Design requirements)
(iii) All WAP cables shall be terminated together on a patch panel that does not contain voice and
data cables
(h) Cafeteria Point of Sale WAO (PWAO)
(i) A Cafeteria Point of Sale WAO shall consist of two (2) Cat6 data connections terminated using
shuttered jacks.
(i) Classroom AV WAO (AVWAO)
(i) A Classroom AV WAO shall consist of one (1) Cat6 data connection to provide data
connectivity classroom AV interface panel.
(ii) Drop shall terminate in a male RJ-45 connector at the station side.
Section 8.04 Patch panels and Faceplates
(a) Modular patch panels are to be used for horizontal copper connectivity. Approved
manufacturers are Panduit (Part # CPP24FMWBL 24 port unloaded or Part# CPP48FMWBL 48
port unloaded).
(b) Faceplates will have two (2) or four (4) positions and must be angled. Only Panduit Part #
CFPSE4EI (4 port only).
Section 8.05 Cat6 Modular Jack Color Codes and Part Numbers- Color codes shall be used for all
modular jacks including both station and telecommunications rack side.
(a) Yellow- Data
(i) Panduit part # CJ688TGYL
(b) Green – Voice
(i) Panduit part # CJ688TGGR
(c) Blue – Wireless
(i) Panduit part # CJ688TGBU
(d) Red – Telco Provider Demark Extension
(i) Panduit part # CJ688TGRD
(e) White – Building controls connections to include security, fire, BMS/EMS, and Classroom A/V
(i) Panduit part # CJ6X88TGIW
IT Department
Revised Mar 2017 16 Structured Cabling Standards-Version 7.0
Article 9. Backbone Cabling and Installation
Section 9.01 Copper Backbone Cabling
(a) All Copper Backbone cabling shall consist of a Cat5 multi-conductor cable and a minimum of
25 pairs shall be installed between an MTR and TR.
Note: Copper backbone specifications for TRs that service relocatable classrooms fall under
section 13.03.
(i) Approved multi-conductor copper cabling manufacturers are as follows:
1) TBD
(b) Inside Riser Copper Cabling Terminations
(i) All inside riser copper backbone cabling shall terminate on standard Cat5 rated 110 punchdown
blocks that have been mounted to the installed backboard forming a wall field.
(c) Outside Plant Copper Cabling Terminations
(i) All copper backbone cabling that leaves the main footprint of the building and/or travels
underground shall be terminated, at both ends, on lightning protection. A cross connect
consisting of the same number of pairs as the installed outside rated cable should be installed
from the “in” or “protected” side of the lightning protector and terminate on Cat5 rated 110
punch down blocks that have been mounted to the installed backboard forming a wall field.
(d) Copper Backbone Cabling Cross Connects – The District uses a modular approach to its voice
cross connects and requires the installation of tie cables from the 110 block wall field, where
backbone cabling from TR(s) is terminated, to patch panels (part number below) mounted in
data racks in each MTR/TR.
(i) Standard MTR Cross Connect Requirements
1) A minimum of 50 pairs of Cat5 rated multi-conductor copper cabling shall be installed from
the 110 block wall field to the data rack that houses the site’s IP Voice Gateway and shall
terminate on standard 110-style Cat5 patch panels (Panduit Part #DP485E88TG) using 1
pair per patch panel port on the blue pair to serve as a cross connect. The District IT staff
will be responsible for making the final cross connects between the 110 side of the cross
connect and the 110 wall field made up of the 50 pair cables to the TRs during the IP Voice
Gateway installation to bring phone service to the TRs based on need.
(ii) Standard TR Cross Connect Requirements
1) Copper backbone cabling installed between a site’s MTR and a TR that does not require
lightning protection shall have 10’ of usable service located in the ladder rack and shall
terminate at the TR directly on on standard 110-style Cat5e patch panels (Panduit Part
#DP485E88TG) using 1 pair per patch panel port on the blue pair.
2) If the path from the MTR to the TR requires the use of lightning protection, a pigtail shall be
installed from the “in” or “protected” side of the lightning protection to a standard 110-style
IT Department
Revised Mar 2017 17 Structured Cabling Standards-Version 7.0
Cat5e patch panel (Panduit Part #DP485E88TG) located in the TR’s data cabling rack, using
1 pair per patch panel port on the blue pair at the patch panel end.
Section 9.02 Fiber Optic Backbone Cabling
(a) Approved Fiber Optic Connectivity Manufacturers- The manufacturers listed below are
approved. The proposed fiber optic cable and connectors must both be sourced from one of the
approved manufacturers.
(i) Corning
(b) Approved Fiber Optic Connectivity Product Lines
(i) Corning Pretium Rack and Wallmount Enclosures
(ii) Corning Pretium Unicam Connectors
(c) A minimum of twenty-four (24) strands of multimode and twelve (12) strands of single-mode
fiber optic cabling shall be installed between the building MTR and each building TR. Note:
Optical fiber backbone specifications for TRs that service relocatable classrooms fall under
section 13.03.
(d) Unless otherwise recommended by the manufacturer, all fiber cables shall be run in innerduct.
All strands will be terminated in the MTR/TR using approved SC type connectors in wall
mounted interconnect centers(must have prior Information Technology project contact
approval) or Pretium rack mounted LIUs equipped with sufficient ports, slack storage space and
splice tray storage, if required, to terminate and secure all fibers.
(e) Fiber Optic Cable Requirements
(i) The fiber optic cabling included in the solution must be optimized for a 10Gbps VCSEL system
(OM3/OM4).
(ii) All multimode fiber optic backbone cabling shall have a core diameter of 50 microns and a core
cladding diameter of 125 microns.
(iii) All single-mode fiber optic backbone cabling installed shall have a core diameter of 8-9 microns
and a core cladding diameter of 125 microns and shall be terminated with blue SC connectors.
IT Department
Revised Mar 2017 18 Structured Cabling Standards-Version 7.0
Article 10. Wireless Voice and Data Network Design Requirements
Section 10.01 Wireless Design Requirements
(a) The exact quantity and placement of Wireless Access Point WAOs will be determined by
building size and layout. It should be assumed that ALL areas of every building shall require
complete, full, and redundant coverage. Required areas include but are not limited to; the gym,
auditorium, cafeteria, media center, all administrative spaces, and all classroom and learning
spaces, outlying PE buildings, etc.
(b) SJCSD requires that a wireless WAO is installed in every room (including but not limited to
classrooms, conference rooms, storage rooms, offices, kitchen, etc) of the building with
common areas such as gym, cafeteria and auditorium receiving additional locations based on
size
(c) Signal strength requirements shall be built around current best practice standards for a heavily
utilized enterprise class wireless LAN that will support both data and wireless IP telephony. AP
quantity and placement shall be optimized for signal density with the target signal-to-noise-ratio
(SNR) of -67dB.
IT Department
Revised Mar 2017 19 Structured Cabling Standards-Version 7.0
Article 11. Labeling and Administration- EIA/TIA 606-A specification shall be used as a
guideline
Section 11.01 MTR/TR Identification
(a) MTR
(i) A building MTR shall be labeled as follows:
MTR-XXX
where XXX is the FISH number that will be permanently associated with the room. This label shall be
permanently mounted in plain view on both the inside and outside of the door for easy identification.
(b) TR
(i) A building TR shall be labeled as follows:
TR-XXX
where XXX is the FISH number that will be permanently associated with the room. This label shall be
permanently mounted in plain view on both the inside and outside of the door for easy identification.
Section 11.02 Horizontal Connectivity Labeling
(a) Patch Panel Labeling
(i) Each patch panel shall be labeled with a number in the top left corner. This number shall be in
ascending order from top left to right bottom.
(ii) Each port on a patch panel in a MTR or TR shall be labeled with the room number and an
uppercase letter, A-Z, that corresponds to the faceplate and port labels at the station side of
each link.
(b) Individual Horizontal Station Cable Labeling
(i) Each station cable shall be labeled 2” from the termination with a permanent, water resistant,
electronically generated, sticker-type label, using the following scheme:
TRXXX-Y-nnnV
Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands
for the number of the patch panel on which the cabling terminates in TRXXX and where nnn
stands for the FISH number of the room the drop is located in and the V is a consecutive
identifier (A,B,C,D,etc) for each cable in the room. In the event that a single room contains
more than 26 single connections double letter designations shall be used to accommodate the
connections over 26 (AA, BB, etc).
IT Department
Revised Mar 2017 20 Structured Cabling Standards-Version 7.0
(c) Work Area Outlet Faceplate Labeling
(i) A WAO faceplate shall be labeled using the following scheme:
Top of faceplate - TRXXX-Y
Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands
for patch panel # where the cabling terminates in TRXXX
Each individual outlet on the faceplate – nnnV
Where nnn stands for the FISH number of the room the drop is located in and the V is a
consecutive identifier (A,B,C,D,etc) for each cable in the room starting at the left side of the
room and working clockwise. In the event that a single room contains more than 26 single
connections double letter designations shall be used to accommodate the connections over 26
(AA, BB, etc).
Section 11.03 Backbone Connectivity Labeling
(a) Copper Backbone Cabling shall be labeled on the cable jacket, using a permanent water and
tear-resistant label, three times starting from the patch panel, wall block, or lightning protection
and working down the cable at 12” increments using the following scheme:
Ppair-MTRXXX-TRYYY
Where P stands for the number of pairs in the cable and XXX is the FISH number of the MTR or
TR the cable originates from and YYY is the FISH number of the TR the cable terminates in.
(i) Patch panels used to terminate copper backbone cabling shall be labeled in the top center of each
panel using the following scheme:
Ppair-MTRXXX-TRYYY
Where P stands for the number of pairs in the cable and XXX is the FISH number of the MTR or
TR the cable originates from and YYY is the FISH number of the TR the cable terminates.
(b) Fiber optic backbone cabling shall be labeled on the jacket using a permanent water and heat
resistant label, three times starting from the termination tray and working down the cable at 12”
increments using the following scheme:
Pstrand-S/MM-MTRXXX-TRYYY
Where P stands for the number of strands in the cable and either S or M stands for single-mode
or multimode fiber and XXX is the FISH number of the MTR or TR the cable originates from
and YYY is the FISH number of the TR the cable terminates in.
IT Department
Revised Mar 2017 21 Structured Cabling Standards-Version 7.0
Section 11.04 Special Use Outlet Labeling
(a) Wireless Access Point (WAP) WAOs shall be labeled on the biscuit box and on the T-bar of the
drop ceiling directly below the biscuit box with a Yellow ¾” permanent label in plain view
using the following scheme:
TRXXX-Y-WAP-RRR-V
Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands
for the number of the patch panel on which the cabling terminates in TRXXX , the WAP is a
constant, the RRR is the FISH number of the room or corridor that the WAP is located in, and
the V is a consecutive identifier (A,B,C,D,etc) for each WAP located in the same room or
corridor. In the event that a single area contains more than 26 wireless access points a double
letter consecutive identifier shall be used to accommodate the WAPs over 26 (AA, BB, etc).
(b) Media Link Controller (MLC) WAOs shall be labeled on the cable using a permanent cable label
using the following scheme:
TRXXX-Y-MLC-RRR-V
Where XXX stands for the FISH number of the TR that the cabling originates from and Y stands
for the number of the patch panel on which the cabling terminates in TRXXX , the MLC is a
constant, the RRR is the FISH number of the room or commons area that the MLC panel is
located in, and the V is a consecutive identifier (A,B,C,D,etc) for each MLC panel. In the event
that a single building contains more than 26 MLC panels a double letter consecutive identifier
shall be used to accommodate the WAPs over 26 (AA, BB, etc). Note: MLC cables will not be
visible unless the MLC panel is removed from the wall. To see the cable label, remove the four
screws which secure it to the wall to expose the cable.
IT Department
Revised Mar 2017 22 Structured Cabling Standards-Version 7.0
Article 12. Testing and Documentation
Section 12.01 Testing shall follow all standards set forth in TIA/EIA-568-B.1, TIA/EIA-568-B.2,
TIA/EIA-568-B.3, TIA/EIA-TSB-140, TIA/EIA-526-14-A, and TIA/EIA-526-7
(a) Horizontal Copper Cabling
(i) Testing and certification of horizontal copper cabling shall be performed using the permanent
link method.
(b) Copper Backbone Cabling
(i) All copper backbone cabling shall be tested for continuity.
(c) Fiber Optic Backbone Cabling
(i) All fiber optic backbone cabling shall be tested and certified using the BICSI Tier 2 method for
testing optical fiber. A launch cable that is a minimum of 200 meters in length shall be utilized
during all OTDR tests to ensure accurate trace results.
Section 12.02 Documentation
(a) Submitting Test Results
(i) Cabling test results for Move, Add, or Change projects or Summer Relocatable Classroom
installs shall be submitted via electronic mail to the address below:
(ii) Cabling test results for large projects such as new schools and large scale additions and
renovations shall include each horizontal copper location and each backbone fiber strand and
must be submitted in triplicate in both of the following form (three each CD/DVD media):
1) Hard copy- Shall be neatly contained in a three-ring binder. The cover of the binder shall be
printed with, at a minimum, the following information, St Johns County school construction
name, school address, cabling contractor and their project manager’s name, and date of
cabling completion. The three-ring binder must have tabbed dividers labeled with the TR
that the tests originated separating each TR’s tests from the others.
2) Digital- CD or DVD media may be used and the files must be in the native database format
of the tester used for testing and certification. (Tab delimited, .CSV files, excel spreadsheets,
or other non-native file formats will not be accepted). The CD or DVD media must have a
computer generated label that includes at a minimum, the following information: St Johns
County school construction name, school address, cabling contractor and their project
manager’s name, and date of cabling completion. In addition to the test results in native
format each CD/DVD shall also contain an installable copy of all necessary proprietary
viewing software for the tester format used in the certification.
IT Department
Revised Mar 2017 23 Structured Cabling Standards-Version 7.0
Article 13. Relocatable Classroom Systems Specifications Structured cabling networks for relocatable classrooms are designed and installed to provide the
greatest scalability, flexibility and ease of management.
Section 13.01 Relocatable Classroom Conduit System Specifications (See diagrams 13.02a and 13.02d
for external conduit termination routing detail)
(a) All connectivity will originate from a pedestal, which should be a minimum of a 36” x 36” x
12” NEMA 3 rated (Acceptable Models - Cooper B-Line part number 363012RHCF or Hoffman
Cabinet part number A36H3612GQRLP) enclosure, securely mounted to/near the relocatable
classroom that houses the first TR installed. All future backbone cabling, both optical fiber and
IT Department
Revised Mar 2017 24 Structured Cabling Standards-Version 7.0
copper will originate from this enclosure. (See diagram 13.01a for pedestal buildout
requirements)
(b) A minimum of 2 ea 2” or 1 ea 4” conduit should be installed from the in-ground voice and data
network expansion box located closest to the pedestal mounted on/near the relocatable classroom
that is closest to the main building.
(c) A 2” conduit will be installed from each new relocatable classroom TR back to the pedestal using
the most direct path. A 12” x 12” pull box shall be installed at 150’ intervals or every 180 degrees
of bend (or two 90degree bends) in a conduit run to minimize strain on cables.
(d) External boxes shall be a minimum of 16” x 16” x 10” (Acceptable Model -Allied Moulded
Products part # AM1648RL ) and possess a minimum NEMA 3 rating.
(e) A minimum of a 1-1/2” conduit shall be installed in an unbroken path between a relocatable
classroom and nearest TR. Daisy chaining pipes between relocatable classrooms is prohibited
due to the added pull points, added distance, and 90 degree bends created.
(f) A single run of conduit between a relocatable classroom and a TR may contain no more than two
(2) 90 degree bends including the exit from the TR and entrance into the relocatable. Sweep bends
shall be used to minimize pull force needed.
(g) 1-1/2” conduits that will house horizontal copper cabling (Cat5e, Cat6, etc.) shall be no more than
220’ in length, not including turn-ups into the relocatable classroom, from TR to relocatable
classroom being served.
(h) No more than eight (8) cat6 gel-filled cables should be run in any 1-1/2” conduit between a TR
and relocatable classroom.
(i) All conduits shall be clearly marked at both ends and again every twenty-five feet (25’) w/
fluorescent orange spray paint to differentiate voice and data conduits from any other conduits
buried in the same trench.
IT Department
Revised Mar 2017 25 Structured Cabling Standards-Version 7.0
Diagram 13.01a – Voice and Data Pedestal for Relocatable Classrooms
IT Department
Revised Mar 2017 26 Structured Cabling Standards-Version 7.0
Section 13.02 Relocatable Classroom Horizontal Cabling and Connectivity Specifications
(a) A minimum of a 48” Hubbell Quad Cab (part # HSQ4826) shall be installed in the relocatable
that will serve as the TR. A 38”x28” backboard shall be painted on all six sides with fire-retardent
paint and affixed to the wall. The cabinet shall be mounted to the plywood and set on two sections
of uni-strut to relieve load strain from the wall. (see Diagram 13.02a and 13.02b and Image
13.02a and 13.02b for placement detail)
(b) Each relocatable classroom shall receive five (5) gel-filled Cat6 data cables.
(i) See diagram 13.02c for drop location placement detail
(ii) A single drop is to be installed in the ceiling and terminated with a Blue jack in a 2position surface
mount box (Panduit part # CBXS2EI-A or AMP part # 1116698-3) w/ 10’ of service loop at the
station end to allow for a wireless access point to be placed where needed by the IT Department.
(iii) Approved Horizontal Copper Cabling Manufacturers
1) See Article 8 for horizontal copper cabling requirements.
(c) Connectivity
(i) Copper Connectivity
1) Modular Patch panels are to be used for copper connectivity. Either Panduit (Part #
CPP24FMWBL 24 port unloaded or Part# CPP48FMWBL 48 port unloaded) or AMP (Part #
1116749-1 24 port unloaded or 1375119-1 48 port unloaded).
2) Modular Cat5E jacks are to be used. Colors for each jack at the panel side should match the
color at the station side and follow the owner’s color code.
a) Yellow- Data
i) Panduit part # CJ688TGYL
ii) AMP part # 1375187-8
b) Green – Voice
i) Panduit part # CJ688TGGR
ii) AMP part # 1375187-9
c) Blue – Wireless
i) Panduit part # CJ688TGBU
ii) AMP part # 1375187-6
3) Work area outlets
IT Department
Revised Mar 2017 27 Structured Cabling Standards-Version 7.0
a) Faceplates will have two (2) or four (4) positions and must be angled. Only Panduit Part #
CFPSE4EI 4 port only or AMP Part #1375155 2 port or Part # 406185 4 port will be accepted.
(ii) Management
1) Horizontal- Panduit finger duct where applicable. Space will usually prevent the use of
management in cabinets. If management is requested, use Panduit part # WMPLFSE
IT Department
Revised Mar 2017 28 Structured Cabling Standards-Version 7.0
Diagram 13.02a – Rear Elevation Telecom Room (TR) Relocatable
IT Department
Revised Mar 2017 29 Structured Cabling Standards-Version 7.0
Diagram 13.02b – Telecom Room (TR) Relocatable Overhead
IT Department
Revised Mar 2017 30 Structured Cabling Standards-Version 7.0
Diagram 13.02c – Typical Relocatable Work Area Outlet Layout
IT Department
Revised Mar 2017 31 Structured Cabling Standards-Version 7.0
Diagram 13.02d - Rear Elevation - Typical Relocatable
IT Department
Revised Mar 2017 32 Structured Cabling Standards-Version 7.0
Section 13.03 Relocatable Classroom Backbone Cabling Specifications – (See Diagram
13.01a for installation detail)
(a) Optical Fiber Backbone Cabling
(i) All fiber optic cabling installed for relocatable classrooms shall meet the
specifications outlined in section 9.02
(ii) 24 strands of 50/125 OM3 multimode optical fiber shall be installed from the
main building MTR located nearest to the newly installed relocatable classroom
that will serve as the first TR. All 24 strands of multimode optical fiber shall
terminate in an optical fiber enclosure located inside the 36”x36” pedestal
mounted on/near the portable that will house the first TR. SC connectors shall
be used to terminate all 24 strands of multimode optical fiber.
(iii) Six (6) strands of muilti-mode optical fiber shall be installed from the 36”x36”
pedestal located on/outside the first relocatable classroom TR to each
relocatable classroom TR. All six (6) strands shall be terminated at both ends
using SC connectors.
(iv) The connectors for each 6 strand cable installed between the data pedestal and a
TR portable shall be mounted in a standard 1U LIU at the TR portable side and
in a Panduit Multi-Media Surface-Mount Fiber Enclosure with 3 ea Duplex SC
Minicom modules as needed at the data pedestal side.
(v) All optical fiber backbone labeling shall follow the labeling scheme detailed in
Section 10.03b
(b) Copper Backbone Cabling
(i) A minimum of 50 pairs of Category 3 copper backbone cabling shall be installed
from the main building MTR/TR located nearest to the pedestal that has been
installed on/near the relocatable classroom that will serve as the first TR. All 50
pairs shall terminate on the “In” side of an appropriately sized 110 style
lightning protector located inside the 36”x36” pedestal.
(ii) A maximum of 12 pairs of copper backbone cabling shall be installed from the
36”x36” pedestal located on/outside the first relocatable classroom TR to each
relocatable classroom TR. Every pair of each 12 pair cable shall be terminated
on the “Out” side of the lightning protection installed in the 36”x36” pedestal
using the next available 12 pairs of the 100 pair cable.
(iii) All copper backbone cabling installed from a pedestal to a relocatable classroom
TR shall terminate at the relocatable classroom side on an appropriately sized
Circa 4000N building entrance terminal.
(iv) All copper backbone cabling shall terminate in the MTR/TR rack and relocatable
classroom TR cabinet on standard Cat5e patch panels (Panduit Part
IT Department
Revised Mar 2017 33 Structured Cabling Standards-Version 7.0
#DPA485E88TG or AMP Part #406331-1) for voice 1 pair per port on the blue
pair at both ends.
(v) All copper backbone cabling shall follow the labeling scheme detailed in Section
10.03a
IT Department
Revised Mar 2017 34 Structured Cabling Standards-Version 7.0
Article 14. Classroom Audio/Visual (AV) Systems
Section 14.01 General Information – The St. Johns County School District classroom
AV standard utilizes a combination of projectors, interactive panels and ultra-short throw
projectors, classroom sound reinforcement, and document cameras (where appropriate) to
provide teachers and students with a multimedia rich learning environment. Wall-
mounted interactive panels range in size from 65”-84” diagonal and are utilized in typical
new construction classrooms, common areas and training/conference rooms. Relocatable
classrooms (sometimes referred to as modular or portable classrooms) receive similar
65”-70” diagonal interactive panel which are mounted to a purpose-built wheeled cart.
Retrofit classroom AV solutions will be handled on a case-by-case basis, which will take
into account pre-existing hardware and room requirements.
Section 14.02 Classroom AV Systems Detail
(a) Classroom/Common Area/Extended Learning Area (ELA) Sound
Reinforcement – Each classroom, common area and ELA shall receive a
classroom sound reinforcement system to ensure consistent delivery of teacher
voice and digital content. (Gym, Cafetorium, Auditorium, Café systems shall be
purpose/custom designed to fit the space.)
(i) System shall consist of an amplifier in each learning area, 1, 2 or 4 ceiling
mounted speakers based on manufacturer’s recommended placement and
coverage specifications and 2 wireless teacher microphones (1 pendant mic with
necklace/lanyard and 1 handheld) with rechargeable batteries and charging
station.
1) Large format rooms such as ELA may require additional speakers. Designers
should again refer to manufacturers specifications for requirements.
(ii) System may utilize RF, infrared or other approved means to transmit wireless
signals between amplifiers, wireless microphones and/or speakers as needed.
(iii) System must have the ability to duck program audio in the event that a classroom
receives a page from the building’s paging system.
(b) Interactive Display Panel – Large interactive display panel – wall mounted or
cart mounted and serves as the primary display for newer construction and
retrofits in classroom and common area or extended learning areas.
(i) Panel Inputs/Outputs:
1) Inputs: 4 HDMI, 1 VGA, 1 3.5 mm audio, 4 USB A (2.0/3.0)
2) Outputs: Coax
IT Department
Revised Mar 2017 35 Structured Cabling Standards-Version 7.0
(ii) LED lamp life: 30,000 hours minimum
(iii) 3 year warranty
(iv) Integrated speakers
(v) Tempered glass
(vi) 10 points of touch minimum
(vii) Onboard operating system capable of supporting common interactive software
(viii) Includes interactive software
(ix) Capable of integrating with onboard Windows computer
(x) 65”- 84” diagonal screen size
(xi) Resolution to be 1080p or higher
(xii) Reference the District standard Interactive Panel model
(c) Multimedia Projector - (ceiling or ultra-short-throw wall-mounted) – the
projector may serve as the primary display in the classroom and common area
that does not have a large format interactive display. The image is projected onto
a classroom whiteboard or specified screen. The projector displays video from
laptop, document camera and TV tuner via HDMI (preferred) or VGA and/or
composite video inputs. Contact Information Technology department for current
projector manufacturer/model information.
(i) Projector Throw Distance –
1) Standard Ceiling Mounted Projector - Projector shall be centered in the
classroom facing the primary instructional wall and mounted between 13’
and 15’ from the projection surface.
2) Ultra Short-Throw Classroom/Common Area/Extended Learning Area –
Projector shall be oriented on the white board of the primary instructional
wall. Mounted per manufacturer’s recommendation.
(ii) Projector Input/Output Requirements
1) Inputs: 2 x VGA, 2x HDMI v1.3 or higher, S-Video, 2 x 3.5mm audio, RCA
Stereo Audio, USB – A Power, RS-232, RJ45
2) Outputs: VGA, 3.5mm audio
(iii) Minimum Classroom Projector Performance Specifications (Ultra Short-Throw
and Standard):
1) Native Resolution – WXGA (1280 x 800)
IT Department
Revised Mar 2017 36 Structured Cabling Standards-Version 7.0
2) Brightness -- 3600 lumens or higher (LCD or TLP or LED)
3) Contrast Ratio – Up to 22000:1
4) Please reference the District standard models
(iv) Minimum Large space Projector Performance Specifications:
1) Native Resolution – WUXGA (1920 x 1200)
2) Brightness -- 6000 lumens or higher (LCD or TLP or LED)
3) Contrast Ratio – Up to 10,000:1
(v) Warranty – 3-year advance replacement (projector) / 1 year unlimited hour (lamp
life)
(d) Document Camera - presents documents and live video through projector and
provides video switching capability for laptop. Laptop is connected to document
camera, which controls whether laptop video or document camera video is sent
through to display
(i) Inputs:
1) HDMI, VGA (active pass through from computer), USB 2.0
(ii) Outputs:
1) HDMI, VGA
(iii) Please reference the District Standard model
(e) Surge Protector Power Strip – Must provide at least five (5) outlets and have a
25’ input power cable with NEMA5-15P plug. Surge strip must protect
equipment from surges in electrical current
(f) Projection Surface – Projection surface for classroom and commons area
projectors can be pull-down screens or white board surfaces depending upon the
application. Classroom screens can be flush mounted to wall or hung from T-bar
depending on room requirements. Large format areas use pull-down or
motorized screens with specifications and sizing to meet design requirements.
1) New Construction Classroom Spaces, Common Areas, Extended Learning
Areas - NA, uses interactive panel.
2) Retrofit Classroom Spaces- Contact IT dept.
3) Common Areas/ELA – Contact IT dept.
4) Large Format Spaces (media center, cafeteria, gym, etc.) - Spec and size per
design needs.
IT Department
Revised Mar 2017 37 Structured Cabling Standards-Version 7.0
Section 14.03 Classroom Audio/Visual System Configuration Diagrams
(a) New Construction Classroom Components and Detail
IT Department
Revised Mar 2017 38 Structured Cabling Standards-Version 7.0
IT Department
Revised Mar 2017 39 Structured Cabling Standards-Version 7.0
(b) Large Room, Non-Standard Space Components
IT Department
Revised Mar 2017 40 Structured Cabling Standards-Version 7.0
(c) Retrofit Classroom and Common Area/ELA Components and Detail
IT Department
Revised Mar 2017 41 Structured Cabling Standards-Version 7.0
IT Department
Revised Mar 2017 42 Structured Cabling Standards-Version 7.0
Article 15. Applicable Industry Standards
BICSI, Telecommunications Distribution Methods Manual
ANSI/TIA/EIA-568B, Commercial Building Telecommunications Cabling Standard
TIA/EIA TSB-67 Transmission Performance Specifications for Field Testing of
Unshielded Twisted Pair Cabling Systems
TIA/EIA TSB-140 Additional Guidelines for Field-Testing Length, Loss and Polarity of
Optical Fiber Cabling Systems
TIA/EIA TSB-75, Additional Horizontal Cabling Practices for Open Offices.
ANSI/TIA/EIA-569A, Commercial Building Standard for Telecommunications
Pathways and Spaces
ANSI/TIA/EIA-606A, Administration Standard for Telecommunications Infrastructure of
Commercial Buildings
ANSI/TIA/EIA-607, Commercial Building Grounding and Bonding Requirements for
Telecommunications
TIA-942, Telecommunications Infrastructure Standard for Data Centers
ANSI/NFPA-70
NEC, National Electrical Code
NFPA-101, Life Safety Code
NFPA-780, Standard for the Installation of Lightning Protection Systems
Other applicable NFPA Codes.
ANSI/IEEE Codes, All Applicable Codes.
NESC, National Electrical Safety Code (ANSI/IEEE C-2, overhead and underground
telecommunications cable).
Local Uniform Building Codes
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-1
SECTION 32 32 23 - CONCRETE SEGMENTAL RETAINING WALL SYSTEM
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work consists of furnishing and construction of an Anchor Vertica Pro Retaining Wall System (or Equivalent) in accordance with these specifications and in general conformity with the lines, grades, design, and dimensions shown on the plans.
B. Earthwork includes: 1. Preparing Foundation Soil and Retained Soil to the lines and grades shown on the
construction drawings; 2. Furnishing and installing Leveling Pad, Reinforced Fill (where required) and Low
Permeability Soil (where required) to the lines and grades shown on the construction drawings; and,
C. Installation work includes: 1. Furnishing and installing Vertica Pro Concrete Facing Units (or Equivalent) and Unit Fill
to achieve the lines and grades shown on the construction drawings. 2. Furnishing and installing Geosynthetic Reinforcement and Separation Geotextile of the
type, size, location and lengths designated on the construction drawings (if required). 3. Furnishing and installing Subsurface Drainage System, including necessary fittings, of
the type, size, and location designated on the construction drawings.
1.02 RELATED SECTIONS
A. Section 01270 – Unit Prices
B. Section 02300 – Earthwork
1.03 REFERENCES
A. American Association of State Highway Transportation Officials (AASHTO)
1. AASHTO Standard Specifications for Highway Bridges 2. AASHTO M 288 Geotextile Specifications for Highway Applications 3. AASHTO M 252 Corrugated Polyethylene Drainage Pipe 4. AASHTO National Transportation Product Evaluation Program (NTPEP)
B. American Society for Testing and Materials (ASTM)
1. ASTM C140 Standard Test Methods for Sampling and Testing Concrete Masonry Units and Related Units
2. ASTM C1262 Standard Test Method for Evaluating the Freeze-Thaw Durability of Manufactured Concrete Masonry Units and Related Concrete Units
3. ASTM C1372 Standard Specification for Segmental Retaining Wall Units 4. ASTM D448 Standard Classification for Sizes of Aggregate for Road and Bridge
Construction 5. ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil
Using Standard Effort (12,400 ft-lbf/f3)(600 kN-m/m3) 6. ASTM D1556 Standard Test Method for Density and Unit Weight of Soil In Place by the
Sand Cone Method 7. ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil
Using Modified Effort (56,000 ft-lbf/f3)(2700 kN-m/m3) 8. ASTM D2487 Standard Classification of Soils for Engineering Purposes (Unified Soil
Classification System) 9. ASTM D2922 Standard Test Methods for Density of Soil and Soil-Aggregate In Place by
Nuclear Methods (Shallow Depth)
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-2
10. ASTM D3034 Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer pipe and Fittings
11. ASTM D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
12. ASTM D4491 Standard Test Method for Water Permeability of Geotextiles by the Permittivity Method
13. ASTM D4595 Standard Test Method for Tensile Properties of Geotextiles by the Wide-Width Strip Method
14. ASTM D4873 Standard Guide for Identification, Storage and Handling of Geosynthetics 15. ASTM D5084 Standard Test Method for Measurement of Hydraulic Conductivity of
Saturated Porous Materials Using a Flexible Wall Permeameter. 16. ASTM D5262 Standard Test Method for Evaluating the Unconfined Tension Creep
Behavior of Geosynthetics 17. ASTM D5321 Standard Test Method for Determining the Coefficient of Soil and
Geosynthetic or Geosynthetic and Geosynthetic Friction by the Direct Shear Method 18. ASTM D5818 Standard Practice for Obtaining Samples of Geosynthetics from a Test
Section for Assessment of Installation Damage 19. ASTM D6637 Standard Test Method for Determining Tensile Properties of Geogrids by
the Single or Multi-Rib Tensile Method 20. ASTM D6638 Standard Test Method for Determining Connection Strength Between
Geosynthetic Reinforcement and Segmental Concrete Units 21. ASTM D6916 Standard Test Method for Determining the Shear Strength Between
Segmental Concrete Units 22. ASTM D6706 Standard Test Method for Measuring Geosynthetic Pullout Resistance in
Soil 23. ASTM F405 Standard Specification for Corrugated Polyethylene (PE) Tubings and
Fittings 24. ASTM G51 Standard Test Method for Measuring pH of Soil for Use in Corrosion Testing
C. Federal Highway Administration
1. Samtani, Naresh C., Christopher, B., and Berg, R., “Design and Construction of Mechanically Stabilized Earth Walls and Reinforced Soil Slopes”, Volumes 1 and 2, Federal Highway Administration Report Nos. FHWA-NHI-10-024 and FHWA-NHI-10-025, November 2009.
2. Elias, V., Fishman, K., Christopher, B., and Berg, R., “Corrosion/Degradation of Soil Reinforcements for Mechanically Stabilized Earth Walls and Reinforced Soil Slopes”, Federal Highway Administration Report No. FHWA-NHI-09-087, November 2009.
D. National Concrete Masonry Association (NCMA) 1. NCMA Design Manual for Segmental Retaining Walls, Third Edition, 2010
1.04 DEFINITIONS
A. Segmental Retaining Wall (SRW) Units: Dry-stacked concrete masonry units used as the
retaining wall fascia.
B. Reinforced Fill: Soil which is used as fill behind the SRW unit and within the reinforced soil mass (if applicable).
C. Unit Fill and Drainage Aggregate: Material used (if applicable) within, between, and directly
behind the concrete retaining wall units.
D. Geotextile Separation Fabric: Material used for separation and filtration of dissimilar soil types.
E. Foundation Soil: Soil mass supporting the leveling pad and reinforced soil zone of the retaining wall system.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-3
F. Retained Soil: The soil mass located behind the reinforced soil zone, either undisturbed native
soils or compacted fill.
G. Leveling Pad: A level surface consisting of crushed stone, sand and gravel or unreinforced concrete placed to provide a working surface for placement of the SRW unit.
H. Geosynthetic Reinforcement: Polymeric material designed specifically to reinforce the soil mass.
I. Pre-fabricated Drainage Composite: three-dimensional geosynthetic drainage medium
encapsulated in a geotextile filter, used to transport water.
J. Subsurface Drainage System: horizontal pipe encapsulated within drainage aggregate at or near the base of the reinforced soil to facilitate removal of water from the wall system.
K. Low Permeability Soil: Clay soil or low permeability geosynthetic used to prevent water percolation into the drainage zone and reinforced backfill behind the wall.
L. Global Stability: The general mass movement of a soil reinforced segmental retaining wall
structure and adjacent soil mass.
M. Project Geotechnical Engineer: A registered engineer who provides site observations, recommendations for foundation support/global stability, and verifies soil shear strength parameters.
1.05 SUBMITTALS / CERTIFICATION
A. Product Data 1. Product Data: Material description and installation instructions for each manufactured
product specified 2. Name and address of the production facility where the proposed facing units will be
manufactured. All units shall be manufactured at the same facility. 3. Notarized letter from the facing unit manufacturer stating that the units supplied for this
project are manufactured in complete compliance with this specification. The letter shall state that the units shown in the attached test reports are representative samples of the plants normal mix design and regular production runs.
4. Notarized letter from the reinforcement manufacturer stating that the geosynthetic reinforcement has been manufactured in complete compliance with the reinforcement manufacturer’s current NTPEP report.
B. Samples: 1. Contractor shall submit to the owner for approval, and retain for the balance of the
project, a minimum of one SRW unit that represents the range of texture and color permitted.
C. Test Reports: 1. Independent Laboratory reports indicating compressive strength, moisture absorption and
freeze-thaw durability of the concrete retaining wall units from the proposed production facility.
2. Independent test reports verifying the long-term design strength properties (creep, installation damage, and durability) and soil interaction properties of the geosynthetic reinforcement.
3. Independent test reports verifying the connection capacity between the geosynthetic reinforcement and the concrete retaining wall units.
D. Wall Design Engineer Qualifications:
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-4
1. Current insurance policy verifying professional liability and errors and omissions insurance coverage for an aggregate and per claim limit of at least one million dollars ($1,000,000).
2. Notarized letter certifying the proposed retaining wall Design Engineer is a licensed professional engineer in the state of wall installation and has a minimum of 4 years and 200,000 square feet of retaining wall system design experience.
E. Retaining Wall Contractor Qualifications: 1. Notarized statement showing that the retaining wall contractor has installed a minimum of
100,000 square feet of segmental retaining walls. 2. The Retaining Wall Installer shall furnish five (5) project references of similar size and
scope to this project including the wall(s) height and square footage. References shall include the contact information of Owner or General Contractor.
F. Retaining Wall Design: 1. Shop Drawings: One digitally signed set of the retaining wall system design, including
wall elevation views, geosynthetic reinforcement layout, pertinent details, and drainage provisions. A registered professional engineer licensed in the state of wall installation shall sign and certify that the shop drawings are designed in accordance with the project civil plans and specifications.
2. Design Calculations: One digitally signed set of engineering design calculations prepared in accordance with the NCMA Design Manual for Segmental Retaining Walls, 3rd Edition or the AASHTO Standard Specifications for Highway Bridges (whichever is applicable). Analysis shall include Internal, External and Bearing Capacity Calculations and include the short term and long term loading conditions on the wall. A Global Stability analysis should be coordinated with the project geotechnical engineer and incorporated into the wall design.
1.06 DELIVERY, STORAGE AND HANDLING
A. SRW Units and Accessories: Deliver, store, and handle materials in accordance with manufacturer's recommendations, in such a manner as to prevent damage. Check the materials upon delivery to assure that proper material has been received. Store SRW units above ground on wood pallets or blocking. Remove damaged or otherwise unsuitable material, when so determined, from the site.
B. Exposed faces of SRW units shall be relatively free of chips, cracks, stains, and other imperfections detracting from their appearance, when viewed from a distance of 20 feet under diffused lighting.
C. Prevent mud, wet cement, adhesives and similar materials that may harm appearance of SRW
units, from coming in contact with system components.
D. Geosynthetics (including geosynthetic reinforcement, geotextile filter, pre-fabricated drainage composite) shall be delivered, stored, and handled in accordance with ASTM D4873.
1.07 EXTRA MATERIALS
A. Furnish Owner with 3 replacement SRW units identical to those installed on the Project. PART 2 - PRODUCTS
2.01 MATERIALS
A. SRW Units: Anchor Vertica Pro Retaining Wall Units"(or Equivalent) as manufactured under license from Anchor Wall Systems.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-5
1. Physical Requirements a. Meet requirements of ASTM C1372, except the unit height dimensions shall not
vary more than plus or minus 1/16 inch from that specified in the ASTM reference, not including textured face.
b. Unit Face Area: Not less than 1.0 square foot. c. Color: Selected by the [Architect] [Engineer] [Owner] from manufacturer's full
range of standard colors. d. Face Pattern Geometry: Straight e. Texture: Split Rock Face. f. Batter: Include an integral concrete shear connection flange/locator to provide a
9/16ths inch setback for each wall course.
B. Geosynthetic Reinforcement: Polyester fiber geogrid or geotextile, or polypropylene woven geotextile, as shown on the Drawings.
C. Leveling Pad 1. Aggregate Base: Crushed stone or granular fill meeting the following gradation as
determined in accordance with ASTM D448: Sieve Size Percent Passing
1 inch 100 No. 4 35 to 70 No. 40 10 to 35 No. 200 3 to 10
a. Base Thickness: 6 inches (minimum compacted thickness). 2. Concrete Base: Non-reinforced lean concrete base.
a. Compressive Strength: 3,000 psi (maximum). b. Base Thickness: At least 2 inches.
D. Unit Fill and Drainage Aggregate: Clean crushed stone or granular fill meeting the following
gradation as determined in accordance with ASTM D448: Sieve Size Percent Passing
1 inch 100 3/4 inch 75 to 100 No. 4 0 to 60 No. 40 0 to 50 No. 200 0 to 5
E. Reinforced Fill: Soil free of organics and debris and consisting of either GP, GW, SP, SW, or SM type, classified in accordance with ASTM D2487 and the USCS classification system and meeting the following gradation as determined in accordance with ASTM D448:
Sieve Size Percent Passing
1 inch 100 No. 4 20 to 100 No. 40 0 to 60 No. 200 0 to 35
1. Plasticity Index (PI) < 6 per ASTM D4318. 2. Maximum particle size for backfill is 1 inch unless field tests have been performed to
evaluate potential strength reduction to the geosynthetic reinforcement due to damage during construction per ASTM D5818.
3. Unsuitable soils are organic soils and those soils classified as SC, CL, ML, CH, OH, MH, OL, or PT.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-6
F. Low Permeability Soil: Clayey soil or other similar material which will prevent percolation into the
drainage zone behind the wall.
G. Drainage Pipe: Perforated or slotted PVC or corrugated HDPE pipe manufactured in accordance with D3034 and/or ASTM F405. All connectors and fittings shall match the piping material.
H. Geotextile Separation Fabric: Geotextile Separation fabric shall be minimum 4.0 oz/sy,
polypropylene, needle-punched nonwoven fabric.
I. Construction Adhesive: Exterior grade adhesive as recommended by the retaining wall unit manufacturer.
PART 3 – EXECUTION
3.01 EXAMINATION
A. Prior to commencing work, the retaining wall contractor shall examine the areas and conditions
under which the retaining wall system is to be erected, and notify the [Architect] [Engineer] [Owner] [General Contractor] in writing of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected.
B. Promptly notify the wall design engineer of site conditions which may affect wall performance, soil conditions observed other than those assumed, or other conditions that may require a reevaluation of the wall design.
C. Verify the location of existing structures and utilities prior to excavation.
3.02 PREPARATION
A. Ensure surrounding structures are protected from the effects of wall excavation.
B. Excavation support, if required, is the responsibility of the Contractor, including the stability of the excavation and its influence on adjacent properties and structures.
3.03 EXCAVATION
A. Excavate to the lines and grades shown on the Drawings. Over-excavation not approved by the
[Architect] [Engineer] [Owner (or Owner's representative)] will not be paid for by the Owner. Replacement of these soils with compacted fill and/or wall system components will be required at the Contractor's expense. Use care in excavating to prevent disturbance of the base beyond the lines shown.
3.04 FOUNDATION PREPARATION
A. Excavate foundation soil as required for footing or base dimension shown on the Drawings, or as directed by the Project geotechnical engineer.
B. The Project geotechnical engineer will examine foundation soil to ensure that the actual foundation soil strength meets or exceeds that indicated on the Drawings. At the direction of the project geotechnical engineer, remove soil not meeting the required strength. Oversize resulting excavation sufficiently from the front of the block to the back of the reinforcement, and backfill with suitable compacted backfill soils.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-7
C. The Project geotechnical engineer will determine if the foundation soils will require special treatment or correction to control total and differential settlement.
D. Fill over-excavated areas with suitable compacted backfill, as recommended by the Project
geotechnical engineer.
3.05 LEVELING PAD PREPARATION
A. Place base materials to the depths and widths shown on the Drawings, upon undisturbed soils, or foundation soils prepared in accordance with Article 3.04.
1. Extend the leveling pad laterally at least 6 inches in front and behind the lowermost SRW unit.
2. Provide aggregate base compacted to 6 inches thick (minimum) or as shown on the drawings.
3. The Contractor may at their option, provide a concrete leveling pad as specified in Subparagraph 2.01.C.2, in lieu of the aggregate base.
4. Where a reinforced footing is required by local code official, place footing below frost depth.
B. Compact aggregate base material to provide a level, hard surface on which to place the first course of SRW units.
C. Prepare base materials to ensure complete contact with SRW units. Gaps are not allowed. 3.06 ERECTION
A. General: Erect SRW units in accordance with manufacturer's instructions and recommendations, and as specified herein.
B. Place first course of concrete wall units on the prepared base material. Check units for level and alignment. Maintain the same elevation at the top of each unit within each section of the base course.
C. Ensure that foundation units are in full contact with the leveling pad.
D. Place concrete wall units side-by-side for full length of wall alignment. Alignment may be done by
using a string line measured from the back of the block. Gaps are not allowed between the foundation concrete wall units.
E. Place drainage aggregate between and directly behind the SRW. Fill any voids in SRW units with
drainage aggregate. Provide a drainage zone behind the SRW units a minimum of 12 inches wide to within 8 inches of the final grade. Cap the backfill and drainage aggregate zone with separation fabric and then 8 inches of low permeability soil.
F. Install drainage pipe at the lowest elevation possible to maintain gravity flow of water to outside of
the reinforced zone. Slope the main collection drainage pipe 2 percent (minimum) to provide gravity flow to the daylighted areas. Daylight the main collection drainage pipe through the face of the wall, and/or to an appropriate location away from the wall system at each low point or at 50 foot (maximum) intervals along the wall. Alternately, the drainage pipe can be connected to a storm sewer system at 50 foot (maximum) intervals.
G. Remove excess fill from top of SRW units and install next course. Ensure drainage aggregate and backfill are compacted before installation of next course.
H. Check each course for level and alignment. Adjust SRW units as necessary to maintain level and
alignment prior to proceeding with each additional course.
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-8
I. Install each succeeding course. Backfill as each course is completed. Pull the SRW units forward until the locating surface of the SRW unit contacts the locating surface of the SRW units in the preceding course. Interlock wall segments that meet at corners by overlapping successive courses. Attach SRW units at exterior corners with adhesive specified.
J. Install geosynthetic reinforcement in accordance with geosynthetic manufacturer's
recommendations and the shop drawings. 1. Orient geosynthetic reinforcement with the highest strength axis perpendicular to the wall
face. 2. Prior to geosynthetic reinforcement placement, place the backfill and compact to the
elevation of the top of the wall units at the elevation of the geosynthetic reinforcement. 3. Place geosynthetic reinforcement at the elevations and to the lengths shown on the
Drawings. 4. Lay geosynthetic reinforcement horizontally on top of the SRW units and the compacted
backfill soils. Place the geosynthetic reinforcement within one inch of the face of the SRW units. Place the next course of SRW units on top of the geosynthetic reinforcement.
5. The geosynthetic reinforcement shall be in tension and free from wrinkles prior to placement of the backfill soils. Pull geosynthetic reinforcement hand-taut and secure in place with staples, stakes, or by hand-tensioning until the geosynthetic reinforcement is covered by 6 inches of loose fill.
6. The geosynthetic reinforcements shall be continuous throughout their embedment lengths. Splices in the geosynthetic reinforcement strength direction are not allowed.
7. Do not operate tracked construction equipment directly on the geosynthetic reinforcement. At least 6 inches of compacted backfill soil is required prior to operation of tracked vehicles over the geosynthetic reinforcement. Keep turning of tracked construction equipment to a minimum.
8. Rubber-tired equipment may pass over the geosynthetic reinforcement at speeds of less than 10 miles per hour. Turning of rubber-tired equipment is not allowed on the geosynthetic reinforcement.
3.07 BACKFILL PLACEMENT
A. Place reinforced fill, spread and compact in a manner that will minimize slack in the
reinforcement.
B. Place fill within the reinforced zone and compact in lifts not exceeding 6 inches (loose thickness) where hand-operated compaction equipment is used, and not exceeding 12 inches (loose thickness) where heavy, self-propelled compaction equipment is used.
1. Only lightweight hand-operated compaction equipment is allowed within 3 feet of the back of the retaining wall units. If the specified compaction cannot be achieved within 3 feet of the back of the retaining wall units, replace the reinforced soil in this zone with drainage aggregate material.
C. Compaction testing shall be done in accordance with ASTM D1556 or ASTM D2922.
D. Minimum Compaction Requirements for Fill Placed in the Reinforced and Retained Zone. 1. The minimum compaction requirement shall be determined by the project geotechnical
engineer testing the compaction. At no time shall the soil compaction requirements be less than 95 percent of the soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor maximum dry density (ASTM D1557)] for the entire wall height.
2. Utility Trench Backfill: Compact utility trench backfill in or below the reinforced soil zone to 98 percent of the soil's standard Proctor maximum dry density (ASTM D698) [modified Proctor maximum dry density (ASTM D1557)], or as recommended by the Project geotechnical engineer. If the height from the utility to finish grade is higher than 30 feet, increase compaction to 100 percent of the standard Proctor density [modified Proctor
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-9
density]. a. Utilities must be properly designed (by others) to withstand all forces from the
retaining wall units, reinforced soil mass, and surcharge loads, if any. 3. Moisture Content: Within 2 percentage points of the optimum moisture content for all wall
heights. 4. These specifications may be changed based on recommendations by the Project
geotechnical engineer. a. If changes are required, the Contract Sum will be adjusted by written Change
Order.
E. At the end of each day's operation, slope the last level of compacted backfill away from the interior (concealed) face of the wall to direct surface water runoff away from the wall face.
1. The General Contractor is responsible for ensuring that the finished site drainage is directed away from the retaining wall system.
2. In addition, the General Contractor is responsible for ensuring that surface water runoff from adjacent construction areas is not allowed to enter the retaining wall area of the construction site.
F. Refer to Article 3.10 for compaction testing. 3.08 CAP UNIT INSTALLATION
A. Apply adhesive to the top surface of the SRW unit below and place the cap unit into desired position.
B. Cut cap SRW units as necessary to obtain the proper fit.
C. Backfill and compact to top of SRW unit. 3.09 SITE CONSTRUCTION TOLERANCES
A. Site Construction Tolerance 1. Vertica Prol (or Equivalent) Alignment: Plus or minus 1-1/2 inches over any 10-foot
distance, with a maximum differential of 3 inches over the length of the wall. 2. Horizontal Location Control from Grading Plan
a. Straight Lines: Plus or minus 1-1/2 inches over any 10-foot distance. b. Corner and Radius Locations: Plus or minus 12 inches. c. Curves and Serpentine Radii: Plus or minus 2 feet.
3. Immediate Post Construction Wall Batter: Within 2 degrees of the design batter of the concrete retaining wall units.
4. Bulging: Plus or minus 1-1/4 inches over any 10-foot distance.
3.10 FIELD QUALITY CONTROL A. Installer is responsible for quality control of installation of system components.
B. The Owner or General Contractor, at their expense, will retain a qualified professional to perform
quality assurance checks of the installer's work.
C. Correct work which does not meet these specifications or the requirements shown on the Drawings at the installer's expense.
D. Perform compaction testing of the reinforced backfill placed and compacted in the reinforced
backfill zone. 1. Testing Frequency
a. One test for every 2 feet (Vertica Prol or Equivalent) of fill placed and compacted,
Nease High School Project Number 2015-30 Expansion, Renovations, and Site Improvements Classroom Bldg. Addition
CONCRETE SEGMENTAL RETAINING WALL SYSTEM 323223-10
for every 50 lineal feet of retaining wall. b. Vary compaction test locations to cover the entire area of the reinforced soil
zone, including the area compacted by the hand-operated compaction equipment.
3.11 ADJUSTING AND CLEANING
A. Replace damaged SRW units with new units as the work progresses.
B. Remove debris caused by wall construction and leave adjacent paved areas broom clean.
3.12 MEASUREMENT AND PAYMENT
A. Measurement of segmental retaining wall shall be on an installed square foot basis computed on the total face area of wall installed. Wall face area includes the bottom of the base course to the top of the wall, and the entire length of the wall.
B. Payment for the wall will be made on a square foot basis at the agreed upon Contract Unit Price. 1. Payment should be considered full compensation for labor, materials, equipment and
testing required to install the wall in accordance with these specifications and the Drawings.
2. Quantities may vary from that shown on the Drawings depending on existing topography. Change to the total quantity of wall face area will be paid or withheld at the agreed upon Contract Unit Price.
END OF SECTION