Upload
builien
View
220
Download
4
Embed Size (px)
Citation preview
M/s. VARDHMAN ACRYLICS LIMITED
PROJECT PRE-FEASIBILITY REPORT
ON
PROPOSED PROJECT
FOR
MANUFACTURING OF FIBERS & TOW
OF M/s. VARDHMAN ACRYLICS LIMITED
AT
PLOT NO:755
GIDC ESTATE,JHAGADIA,
DIST:BHARUCH
M/s. VARDHAMAN ACRYLICS LIMITED 1
CONTENTS
S. No. Particulars Page No.
1 SUMMARY 6
2 INTRODUCTION 7
2.1 The Project 7
2.2 Project Proponent 7
2.3 Quality Policy 8
2.4 Environmental Policy 9
2.5 Nature of project 11
2.6 Market Feasibility 11
3 PROJECT DESCRIPTION 11
3.1 Type of Project 11
3.2 Project Location 11-12
3.3 Site selection 13
3.4 Neighboring Industries 14
3.5 Size of project 14
3.6 Process Technology 15-17
3.7 Raw material 18
3.8 Resource requirement 18
3.8.1 Land 18
3.8.2 Fuel Consumption 18
3.8.3 Water 19
3.8.3.1 Water Consumption 19
3.8.4 Waste Water Management 20
M/s. VARDHAMAN ACRYLICS LIMITED 2
S. No. Particulars Page No.
3.8.4.1 Waste water characteristics 22
3.8.4.2 Waste water treatment and Disposal 22
3.9 Mitigation measures & EMP 22
3.9.1 Gaseous emission & Control 22
3.9.1.1 Flue gas emission 22
3.9.1.2 Process emission 23
3.9.2 Hazardous Waste Management 23
3.9.3 Noise control& odour 24
3.9.4 Storage ,handling and transport of Hazardous chemical 24
3.9.5 Health & Safety measures 24
4 SITE ANALYSIS 25
4.1 Connectivity 25
4.2 Land use and land ownership 25
4.3 Existing land-use 25
4.4 Existing infrastructure 26-27
4.5 Soil Classification 27
4.6 Climate Data 27
4.7 Social Infrastructure 28
5 PLANNING BRIEF 29
5.1 Planning concept 29
5.2 Population projection 29
5.3 Land use planning 29
6 PROPOSED INFRASTRUCTURE 29
6.1 Processing area 29
M/s. VARDHAMAN ACRYLICS LIMITED 3
S. No. Particulars Page No.
6.2 Non processing area 29
6.3 Green belt area 29
6.4 Social Infrastructure 30
6.5 Connectivity 30
6.6 Drinking water management 30
6.7 Industrial waste management 30
6.8 Solid waste management 30
6.9 Source of power 31
7 REHABILITATION & RESETTLEMENT (R & R) PLAN 31
8 PROJECT SCHEDULE & COST ESTIMATES 31
8.1 Project Implementation Schedule 31
8.2 Estimated project cost 31
9 ANALYSIS OF PROPOSAL 31-34
10 HONORS & ACHIEVEMENTS LIST 35-37
10.1 Honors & Achievements List(EHS) 35-36
10.2 Honors & Achievements List(Quality circle & TPM) 36-37
M/s. VARDHAMAN ACRYLICS LIMITED 4
LIST OF TABLES
Table
No.
Topic Page No.
1. List of Products 6
2. Contact details of the Directors 10
3. Salient features of the Project Site 11
4. Nearby Industries in the vicinity 14
5. Capital cost of projection 14
6. List of Raw Materials-Product wise 18
7. Fuel requirement 18
8. Power Consumption 19
9. Water Consumption 19
10 Waste water generation 20
11 Fuel gas emission 22
12 Details of hazardous waste 23
13 Details of different verities of plants planted in green belt area 25
14 Details of meteorological condition from March 2015 to May 2015.
27
15 Name of some prominent industries. 29
16 Projection implementation schedule 31
17 CSR Activities fy 13-14 32
18 CSR Activities fy 14-15 33
19 CSR Activities fy 15-16 34
20 Achievements list 35
21 Achievements list 36
M/s. VARDHAMAN ACRYLICS LIMITED 5
LIST OF FIGURES
Sr. No. Description Page No.
1. Location of the Project Site 12
2. Aerial view of the 5 km radial periphery from the Project Sites 13
3. Wind rose 28
M/s. VARDHAMAN ACRYLICS LIMITED 6
1.0 EXECUTIVE SUMMARY
M/s.Vardhman Acrylics Limited is a fiber manufacturing unit. The promoters are well
experienced in this field. They have proposed to do debottlenecking –that will result in the
increasing the production capacity of the unit. The Vardhman Acrylics Limited is involved in the
manufacturing of fiber and tow at Plot No:755, GIDC Estate, Jhagadia Dist. Bharuch.The
production capacity of the unit is 20,000 MT/Year. Due to the debottlenecking, 10% production
capacity will be increased and reach to 22,000 MT/Year. As per EIA notification 2006, the
proposed project falls under category 5(d)-B.
The details of products are given below table 1.
TABLE: 1
List of Product
Sr. No
Name of product Existing capacity in MT/Year
Proposed capacity in MT/Year
Total capacity in MT/Year
1. Acrylic fiber & Tow
20,000 2,000 22,000
2. Captive Power Plant (Coal Based)
5.5MW -- 5.5MW
COST OF PROJECT The expected cost of project is Rs. 537 Lacs. The total plot area of the unit is 52.918 hecter. The total plantation and green belt area is 38.395 hecter. FUEL AND ELECTRICITY CONSUMPTION The Unit is using Furnace Oil, Coal and high speed diesel as a fuel. The existing consumption of
Furnace Oil, Coal, and High speed diesel is 2.25 KL/Hr and 8.0 MT/Hr and160 Ltr/Hr/DG
respectively. Unit has its own power generation facility of 5.5 MW.
There will be no any additional requirement of fuel due to proposed project.
WATER CONSUMPTION The total water consumption permission for industrial purpose and domestic purpose is 3105
M3/day and 95 M3/day respectively. There will be no additional requirement of fresh water due
to the proposed project.
M/s. VARDHAMAN ACRYLICS LIMITED 7
WASTEWATER GENERATION
The total industrial waste water generation from the unit is 1325 M3/day and waste water
generation from the domestic is 21 M3/day. There will be no any extra wastewater generation
due to proposed project.
GASEOUS EMISSION
There is a flue gas emission from the Boiler and D.G.Set stacks. Unit has installed ESP as an
APCM to prevent the pollution. There is a no process gas emission from the manufacturing
process.
There will be no any change in gas emission due to proposed project.
HAZARDOUS WASTE MANAGEMENT The Hazardous wastes from the unit are ETP Sludge, Used Oil, Discarded
Containers/Bags/Liners, Spent Carbon, Polymer Waste and Filter & Filter Materials.
2. INTRODUCTION
2.1 THE PROJECT
M/s. Vardhman Acrylics Limited is involving in the manufacturing of fiber and tow at
Plot No:755,GIDC Estate,Jhagadia,Dist:Bharuch.
The list of the product is provided in table -1.
2.2 PROJECT PROPONENT M/s.Vardhman Acrylics Limited is a fiber manufacturing unit. The promoters are well
experienced in this field. Now they want to increase the production capacity of the unit by
debottlenecking. The plant boasts of contemporary infrastructure facilities with advanced
machinery and automated processes. They are conscious of environment protection measures and
from the conception stage itself necessary care has been taken.
M/s. VARDHAMAN ACRYLICS LIMITED 8
QUALITY POLICY
The company’s commitment is to manufacturing of fiber. The company has in house testing
facility with modern testing equipments to ascertain the quality of raw materials as well as
finished products. Continued emphasis towards process and technology up gradation is being
done effectively to enrich the product quality. R & D with initiative & innovative ideas had
resulted into excellent performance in respect of quality products.
M/s. VARDHAMAN ACRYLICS LIMITED 9
ENVIRONMENTAL POLICY
The unit is committed to execute all operations, products and services by environmental
protection activities to the extent possible.
As a means of achieving these, the unit pledge to company with the legal & other requirements
to their core and focus on continually improving products, systems & operations.
M/s. VARDHAMAN ACRYLICS LIMITED 10
TABLE: 2
CONTACT DEAILS OF DIRECTORS
Sr. No
Name Present Residential Address
Designation Contact No.
1. Shri Paul. Oswal
Auro Mira Bhawan, H. No. 2722, Gurdev Nagar. Pakhowal Road, Ludhiana. Punjab.
Chairman & Director
Office : (0161) – 2228945
2. Shri Darshan Lal Sharma
B-xx-770/2, Gurdev Nagar, Ludhiana,141001, Punjab, India
Director Office : (0161) – 2228945
3. Shri Sachit Jain Auro Mirra Bhawan, 2722, Gurdev Nagar, Pakhowal Road, Ludhiana-141001, Punjab, India
Director Office : (0161) – 2228945
4. Shri Bal.Krishan Choudhary
1099, Sector 14, Faridabad-121007, Haryana, India
Managing Director
Office : (0124) – 4981610
5. Shri Surinder Kumar Bansal
D-7,Maharani Bagh, New Delhi- 110065, Delhi, India
Director --
6. Shri Sanjit.Paul. Singh
House No.202B, Court Greens, Lalburnum, Sector-28,Gurgaon-122001, Haryana, India
Director --
7. Shri Munish.Chandr
a.Gupta
House.No 771, sector-15,Part-11,Gurgaon-122001, Haryana, India.
Director --
8. Geeta Mathur B-1/8,Vasant Vihar, New Delhi-110057, Delhi, India
Director --
M/s. VARDHAMAN ACRYLICS LIMITED 11
The directors of the company have good experience in handling the production management,
financial management and all the allied areas.
2.3 NATURE OF PROJECT
The proposed unit will engage in the manufacturing of Fiber & Tow. The current production
capacity of the manufacturing unit is 20000 MT/year. The proposed production capacity will be
2000 MT/year. Thus total production capacity will be 22,000 MT/Year. As per EIA notification
2006, the proposed project falls under category 5(d)-B.
2.4 MARKET FEASIBILITY
Vardhman, a leading textiles group in India ventured into manufacture of Acrylic Fiber &
Acrylic Tow in 1999. A modern plant with technology from Japan Exlan Co. Ltd, Japan, a
company in forefront of innovation in this field was set-up initially as a joint venture with Japan
Exlan Co. and Marubeni Corporation, Japan in the state of Gujarat in western India.
The main application of these products is in the Hosiery of Sweater-Shirts, Scarf, Children cloths
and Jersey, in the Weaving of Shawl, Lohi, Check shirt, Sari and Bed spread, in the Home
furnishing of Table mat, Bath mat, Curtain, Carpets and Shoe laces and for the Industrial Filter
and Non Woven.
3.0 PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The proposed project is not including any interlinked and interdependent project
3.2 PROJECT LOCATION
The proposed project site is located at Plot No: 755, GIDC Estate, Jhagadia, and Dist: Bharuch in
the state of Gujarat. The approximate geographical positioning of the project site is at Latitude:
21038’38.96”N Longitude: 73008’44.62”E. It has an average elevation of 44 m. The location of
the project site can be identified from the location map shown in Figure-2.
The salient features of the location of the project site are presented in Table 3.
TABLE: 3
SALIENT FEATURES OF THE PROJECT SITE
Particulars Details Distance from Site
Villages Selod
Dadheda
4KM
4 KM
M/s. VARDHAMAN ACRYLICS LIMITED 12
Particulars Details Distance from Site
Talodara
Fulwari
2 KM
4 KM
Approx. Geographical positioning Latitude:
Longitude:
21038’38.96”N
73008’44.62”E
Nearest City Ankleshwar
Bharuch
14.5 Km
24.7 Km
Nearest Railway line/ Railway station
Ankleshwar 15.4 KM
Nearest Airport/ Airbase Baroda 99.7 KM
FIGURE -1
LOCATION OF THE PROJECT SITE
Ankleshwar Industrial area Panoli Industrial area Jhagadia industrial area Priaman CETP Canal Piraman to Katiyajal Effluent Pipe Jhagadia to Piraman CETP
PROJECT
M/s. VARDHAMAN ACRYLICS LIMITED 13
Figure-2
Aerial view of the 5km radial periphery from the project Site
3.3 SITE SELECTION
The project proponent did not consider any other alternative site for proposed project.
M/s. VARDHAMAN ACRYLICS LIMITED 14
3.4 NEIGHBORING INDUSTRIES
The industry is located in an area, which is already industrialized. The industries in the vicinity
of the proposed project are given in the table-4 below:
TABLE: 4
NEARBY INDUSTRIES IN THE VICINITY
Sr. No. Plot No Industries Name
1 754 HUBER CHEM LTD.
2 750 UNITED PHOSP LTD.
3. 892 GALAXY LTD
4. 772 NITREX LTD
5. 797 MTZ LTD
3.5 SIZE OF PROJECT
The proposed unit is involving in the manufacturing of Acrylic Fiber and Tow. The exiting
production capacity of the unit is 20000 MT/year. The proposed additional production capacity
will be 2000 MT/Year. Thus total production capacity will be 22,000 MT/Year. The expected
cost of proposed project is Rs.537 lacs. New Plant and machinery installations will also have to
be acquired and installed. Environment Protection and safety systems have also been considered
in planning the Cost Projection. The break-up of the proposed project cost is given in below table
no:-5.
TABLE: 5
CAPITAL COST PROJECTION
Sr. No. Purpose Total (Rs. In Lacs)
1. Land NIL 2. Building NIL 3. Plant and Machinery 510 4. Environment Protection & Safety a) Effluent treatment Plant 20.0 b) Safety Equipment (PPE, fire
extinguishers, Ventilation, etc.) 2.0
c) Green belt development 5.0 Total 537
M/s. VARDHAMAN ACRYLICS LIMITED 15
3.6 PROCESS TECHNOLOGY
Unit is involving in the manufacturing of Acrylics fiber & Tow. Process details like Process
description, chemical reactions and mass balance for each product are as below:
MANUFACTURING PROCESS AND MATERIAL BALANCE Japan Exlan’s acrylic fiber process is divided into 2 areas, namely CHEMICAL AREA & FIBER
AREA.
A. Chemical Area:
Chemical Area consists of Polymerisation, dope making & solvent recovery.
1. Polymerisation:
Polymerisation is prepared by the continuous aqueous suspension polymerization of the reactive
ingredients (Acrylonitrile + VAM) in a precisely controlled reactor system to provide a raw
polymer characterised by constant composition and close control of molecular weight. The
unique catalyst system (Sodium chlorate & Sodium metabisulphite) results in close control of
molecular weight and high percent conversion.
Untreated monomer is stripped under vacuum then condensed and reused. Polymer in slurry
form is continuously overflowed from reactor and it is washed in polymer washing machine to
remove contaminated materials. Washed polymer now stored in polymer holding tank.
2. Dope Making:
Polymer in slurry form dissolved with highly concentrated solvent (Sodium thio-cyanate) by
continuous dissolver. The dissolved spinning solution (dope) with good uniformity is fed to a
flash deaerator, then to a dope heater and then transferred to spinning.
3. Solvent Recovery:
As the solvent (Sodium thio-cyanate) in the coagulation bath of spinning machine is diluted, the
diluted coagulant is transferred to a solvent recovery. The grain form active carbon is used for
purification of the recovered solvent. Highly efficient 5-effect evaporator is applied for
concentration of solvent. The recovered condensed water which is vaporized in the evaporator is
used in tow washing as wash water. Concentrated solvent is adjusted for pH and to the
concentration required and send to dope making.
M/s. VARDHAMAN ACRYLICS LIMITED 16
B. Fiber Area:
Fiber Area is divided in two process, namely spinning and After Treatment.
1. Spinning:
Spinning dope is extruded in the diluted coagulant through the spinnerets and gel fiber is fed to a
tow washing process. Uniformly coagulated gel tow is completely washed out from solvent and
then processed in hot stretching machine. For purpose of getting dense and solid fiber without
void structure tow from Hot stretching machine is fed to apron dryer (Ist heat treatment).
2. After Treatment:
Conditioned tow from dryer is immersed in finishing bath and fed to Crimper. The crimped tow
is fed to 2nd heat treatment at steamer for permanent setting of fiber properties. In these way
physical properties such as stress-strain, toughness, uniformity in fiber structure, durability of
crimp is attained. Finally tow is transferred to a final dryer for being dried to certain moisture
content and then to a tow baler or to staple baler after cutting.
M/s. VARDHMAN ACRYLICS LIMITED
NOTE *ACN=ACRYLONITRILE, VAM=VENYL ACETATE MONOMER, SC=SODIUM CHLORATE, SMBS=SODIUM METABI SULPHITE TG=2-MERCAPTO ETHANOL **TIO2=TITANIUM DIOXIDE, PRS=SODIUM THIOCYANATE, TDDM=TITANEUM DIOXIDE DISPERSING MACHINE
Solvent Filtration
Evaporator (Concentrate or of solvent)
Solvent Recover
TDR (TOW
DRIER)
FAT (FINISH APPLICATION TROUGH)
CRIMPER
ADR (APPRON DRIER) (Drying)
Tow Washin
Polymerization Reactor
Polymer Washing Machine
Polymer Storage
Dope (Polymer Solution
Making)
Deairation & Filtration
**TDDM
SPM (SPINNING MACHINE)
Monomer
RECYCLED TO REACTOR
**TIO2
(For Dull Fiber production l )
Finish Oil
Baling (Finished Product) Staple & Tow
**PRS
ACN, VAM, SC, SMBS,TG
M/s. VARDHAMAN ACRYLICS LIMITED 17
MANUFACTURING PROCESS
Basis: (Poly prod.)2.471 MT/hr
RM & Additives 2.711 MT/hr
DM water 19.328 MT/hrRO water 10.000 MT/hr
Soft water 3.1 MT/hr To RO: 15.500 MT/hr
Raw water 0.05 MT/hrTo ETP: 14.218 MT/hr
Steam: 1.65 MT/hr
36.839 MT/hr 29.718 MT/ hr7.121 MT/hr
Basis: (Fibre prod.) 2.5 MT/hr
To Textile: 20.833 MT/hr
DM water 0.025 MT/hr To CT: 0.229 MT/hr
Steam: 0.275 MT/hr Losses: 0.023 MT/hr
21.09 MT/hr 21.09 MT/hr13.664 MT/hr
Strong PRSFrom Text: 46.62 MT/hrWeak PRS
Sodiumthiocyanate
0.005 MT/hr
To Text (ED): 37.0 MT/hrDM water 6.25 MT/hr To ETP: 3.672 MT/hr
Raw water 0.042 MT/hr To CT: 6.747 MT/hr
Steam: 9.167 MT/hr Losses: 1.0 MT/hr
62.083 MT/hr 48.419 MT/hr
Basis: (Fibre prod.) Dope 20.83 MT/hr 2.5 MT/hr
ED water 37.000 MT/hr WPRS to Solv 46.62 MT/hr
DM Water 4.815 MT/hrRaw Water 1 MT/hr Evoperation loss 5.31 RO Water 4.16 MT/hr
Effluent to ETP 15.700 MT/hrSteam 5.725 MT/hr losses 3.4
73.530 MT/hr 71.030 MT/hr2.500 MT/hr
Raw Water 1.000 MT/hr To ETP: 4.050 MT/hrDM water 3.950 MT/hr Evoperation: 2.570 MT/hr
Steam: 3.225 MT/hr Losses: 1.555 MT/hr
8.18 MT/hr 8.18 MT/hr
2.5
Final product MT/hr
POLYMERIZATION
SPG
DOPE MAKING
SOLVENTRECOVERY
AFT
M/s. VARDHAMAN ACRYLICS LIMITED 18
3.7 RAW MATERIAL
Unit is involving in the manufacturing of Acrylics fibers & TOW and purchasing required raw
material from local/Indian market. Details of raw-material consumption are as shown in table
no.6.
TABLE: 6
LIST OF RAW MATERIALS-PRODUCT WISE
Sr. no
Name of product Production capacity MT/Year
Sr. No.
Name of Raw Material
Consumption quantity kg/kg of product
1. Acrylics fibers & TOW
22,000 1. Acrylonitrile 0.909 2. VAM 0.090 3. Sodium thiocyanate 0.002 4. Sodium
Metabisulphite 0.024 5. Sodium Chlorate 0.009 6. Thioglycol 0.002
2. Captive Power Plant (Coal Based)
5.5MW 1. Coal 8.0 MT/Hr
3.8 RESOURCE REQUIREMENTS
3.8.1 LAND
The total plot area of the unit is 52.918 Hect.
3.8.2 FUEL
For production activity, fuel requirement is as per below table 7.
TABLE: 7
FUEL CONSUMPTION
SR.
NO
FUEL QUANTITY
(As per current CCA
No:-AWH-49945)
QUANTITY
(As per Proposed
Expansion)
TOTAL
1. Furnace Oil 2.25 KL/Hr NIL 2.25KL/Hr
2. Coal 8.0 Mt/Hr NIL 8.0Mt/Hr
3. High Speed Diesel 160 Ltr/Hr/DG NIL 160Ltr/Hr/DG
M/s. VARDHAMAN ACRYLICS LIMITED 19
TABLE: 8
POWER CONSUMPTION
3.8.3 WATER
3.8.3.1 WATER CONSUMPTION
In existing condition, Unit is consuming 3105 M3/day water for industrial purpose and 95 M3/day
for domestic purpose. The total water consumption will remain same after proposed project.
TABLE: 9
WATER CONSUMPTION
Sr. No. Section Water Consumption Existing
KL/Day as per current
CCA NO:AWH-
49945
Proposed KL/Day
Total KL/Day
1 Domestic 95 NIL 95
2 Industrial 2.1 Process 1420 NIL 1420 2.2 Soft water + CT 910 NIL 910 2.3 Boiler 450 NIL 450 2.4 Others 325 NIL 325
Total (Industrial) 3105 NIL 3105 TOTAL
(Domestic + Industrial) 3200 NIL 3200
SR. NO
POWER QUANTITY (As per current CCA
No:-AWH-49945)
QUANTITY (As per proposed
expansion)
TOTAL QUANTITY
1. Electricity 5.5MW NIL 5.5MW
M/s. VARDHAMAN ACRYLICS LIMITED 20
3.8.4 WASTEWATER MANAGEMENT
The total industrial waste water generation from the unit is 1325 M3/day and from the domestic is
21 M3/day. There will be no any change in waste water generation due to proposed project. The
category-wise bifurcation of the waste water generation is given in Table 10.
TABLE: 10
WASTE WATER GENERATION
Sr. No. Section Waste Water Generation
Existing KL/Day as per
current CCA
NO:AWH-
49945
Proposed
KL/Day
Total
KL/Day
1. Domestic 21 NIL 21 INDUSTRIAL
2. Process 970 NIL 970 3. Soft Water+ CT 295 NIL 295 4. Boiler 60 NIL 60 5. Others 0 NIL 0
Total (Industrial) 1325 NIL 1325
TOTAL
(Domestic + Industrial)
1346 NIL 1346
M/s. VARDHAMAN ACRYLICS LIMITED 21
WATER BALANCE DIA-GRAM
DOMESTIC95 M3
WATER CONSUMPTION
(3105M3/day) + (95 M3/Day)
PROCESS 1420 M3
BOILER 450M3
OTHERS 325 M3
COOLING WATER 910 M3
EVAPORATION LOSS 615 M3
COOLING WATER 295 M3
BLOW DOWN 60 M3
EVAPORATION LOSS 840 M3
TOTAL EFFLUENT (1346 M3)
(1325 M3 (Industrial) +
21 M3 (Domestic)
450 M3 390 M3
970 M3
21 M3
SOAK PIT
LOSSES-325
60 M3 295 M3
1325 M3
M/s. VARDHAMAN ACRYLICS LIMITED 22
3.8.4.1 WASTEWATER CHARACTERISTICS
Existing & proposed effluent characteristic before treatment and after treatment in ETP is covered
in Annexure-10 of FORM - I.
3.8.4.2 WASTEWATER TREATMENT & DISPOSAL
A detail of existing & proposed effluent treatment plant (ETP) is covered in Annexure-10 of
FORM - I. The effluent conforming the specified standard is utilized on land for
gardening/plantation within the industrial premises and excess waste water, if any or in case of
accident/emergency,& in monsoon season it is discharged into GIDC underground drainage
leading FETP and for further disposal into deep sea, through BEAIL pipeline project.
3.9 MITIGATION MEASURES & EMP
Based on overall manufacturing & operation activities, the mitigation measures have been
proposed by the company for the control of the anticipated pollution load.
3.9.1 GASEOUS EMISSIONS & CONTROL
3.9.1.1 FLUE GAS EMISSION
In existing condition, Unit has installed 2 Boilers and 6 D.G.Sets as mentioned in below table no:-
11.
TABLE: 11
FLUE GAS EMISSION
Stack No.
Source of emission
Stack height
(m)
Air Pollution Control System
Type of emission
Permissible Limit
EXISTING 1. Boiler- I
(Low Pressure GT-4013)
67 --
PM SO2 NOx
150 mg/Nm3 100 ppm 50 ppm
2. Boiler-II (High Pressure
GT- 4069)
62 ESP
3. D.G.Set (6 Nos)
16 each (2stack/ D.G.Set)
--
Proposed: There will not be any changed in Flue gas emission due to proposed project.
M/s. VARDHAMAN ACRYLICS LIMITED 23
3.9.1.2 PROCESS EMISSIONS In existing process as well as after proposed expansion, there is no process gas emission during
the production of Fiber & Tow.
3.9.2 HAZARDOUS WASTE MANAGEMENT The following types of hazardous wastes are being generated during the operational activities.
All the wastes are being stored separately in a designated storage area. The details of hazardous
waste are below given Table 12.
TABLE 12
DETAILS OF HAZARDOUS WASTE
Sr. No.
Waste Category Quantity/ Year
(As per current CCA)
Quantity/ Year
(As per Proposed
Expansion)
Total Facility
1 ETP 35.3 600 MT 0 MT 600 MT
Collection, storage,
Transportation and Disposal at TSDF at
BEIL. 2 Used Oil 5.1 12 MT 0 MT 12 MT Collection,
Storage, Transportation, Disposal by
selling to Registered Re-
refiners. 3 Discarded
Containers/ Bags/Liners
33.1 200 MT 0 MT 200 MT
Collection, Storage,
Decontamination
4. Spent Carbon
35.3 0.5 MT 0 MT 0.5 MT Collection, Storage,
Transportation, Disposal by incineration at
CHWIF-BEIL.
5. Polymer Waste
21.1 1.1 MT 0 MT 1.1 MT Collection, Storage,
M/s. VARDHAMAN ACRYLICS LIMITED 24
Due to this project there will be no extra hazardous waste generation.
3.9.3 NOISE CONTROL & ODOUR
The major noise generating installation is the D.G. Set. Unit has installed it in a closed room and
provided acoustic enclosure around it. Unit has also provided ear plugs to the operating person of
Boiler room.
Unit is following below steps to Noise control and Odour.
• Raw-material feeding is being carried out by pumps.
• All reactions are being taken in closed reactor system.
• Roof top ventilation is installed in the entire plant area.
• Regular monitoring of piping and fittings is carried out to prevent the leakages.
3.9.4 STORAGE, HANDLING AND TRANSPORT OF HAZARDOUS CHEMICALS
The storage and mode of transport of chemicals are being done as per detailed MSDS and
chemical hazards guide (NIOSH) for the hazardous chemicals.
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as per the
Schedule-1 of the MSIHC Rules, as amended in 2000.
3.9.5 HEALTH AND SAFETY MEASURES
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as per the
Schedule-1 of the MSIHC Rules, as amended in 2000.
Physical hazards may manifest as fires, explosions, excessive temperatures, or the release of large
volumes of gas or toxic or flammable gases or vapors. According to Schedule 2 & 3 of MSIHC
Rules,
Transportation, Disposal by incineration at
CHWIF-BEIL.
6. Filter & Filter
material
36.2 24 MT 0 MT 24 MT Collection, Storage,
Transportation, Disposal by incineration at
CHWIF-BEIL.
M/s. VARDHAMAN ACRYLICS LIMITED 25
Moreover transport activity is being done through drums, so there is a manual loading and
unloading and no unloading through pipe at the site. Hence, the risk of static charge generation
during transfer of such chemicals is not significant.
4.0 SITE ANALYSIS
4.1 CONNECTIVITY
Jhagadia estate is connected with Ankleshwar. Ankleshwar is known for Pigment and
Pharmaceutical Industry. Ankleshwar is connected by Indian National Highway
8 (Mumbai to New Delhi) and by the Western Railway Division of Indian Railways. The railway
division runs the broad gauge train services to Rajpipla. The 133-year-old Golden
Bridge connects Ankleshwar to Bharuch across the Narmada on the station front while a new
bridge connects the highway, the other bridge on the highway is now ready to use.
Ankleshwar railway station is centrally located at the intersection of NH8 & Station Road.
Ankleshwar City Bus stand is located on Station Road (i.e. located in the City, the western
section).Development projects of Ankleshwar Airport & City Bus are in last stage.
4.2 LAND USE AND LAND OWNERSHIP
The proposed project site is located at plot No: 755, GIDC Estate, Jhagadia, and Dist: Bharuch.
The total plot area of the unit is 52.918 hect in which 14.523 is total construction area and 38.395
is total green belt area.
4.3 EXISTING LAND USE
The proposed project site is located at plot No: 755, GIDC Estate, Jhagadia, and Dist: Bharuch.
The plot is notified by GIDC for industrial purpose. The total plot area of the unit is 52.918 ha.
Unit has allotted 38.395 ha area for green belt development. A detail of different varieties of plant
planted in green area is mentioned in below table no:-13.
TABLE 13
DETAILS OF DIFFERENT VARITIES OF PLANTS PLANTED IN GREENBELT AREA
SR. NO
Local Name English Name Scientific Name
Family TOTAL NO. OF PLANTS
1 Nilgiri Eucalyptus Eucalyptus tereticornis
Myrtaceae 43000
2 Sharu Beefwood Casuarina equisetifolia
Casuarinaceae 39000
3 Sonmahor Copper pod tree Peltophorum Caesalpiniaceae 10000
M/s. VARDHAMAN ACRYLICS LIMITED 26
pterocarpum 4 Jambu Black plum Syzygium
cumini Myrtaceae 1887
5 Kashid Yellow cassia Cassia siamea Caesalpiniaceae 2219 6 Deshi
badam Indian almond Terminalia
catappa Combretaceae 1755
7 Katis vans Thorny bamboo Bambusa arundinacea
Gramineae 1638
8 Royal (Bottle) palm
Mountain glory Roystonea regia
Palmae 1100
9 Limdo Margosa tree Azadirachta indica
Meliaceae 2700
10 Bengali babul
Australian babul Acacia auriculiformis
Mimosaceae 1864
11 Sissoo Indian redwood Dalbergia sissoo
Papilionaceae 3625
12 Goras ambli ManilaTamarind Pithocellebium dulce
Mimosaceae 5000
13 Bottle brush Bottle brush tree Callistemon lanceolatus
Myrtaceae 174
14 Safed Shimdo
Kapok Ceiba pentandra
Bombacaceae 50
15 Ambli Tamarind Tamarindus indica
Caesalpiniaceae 35
16 Gulmahor Royal poinciana Delonix regia Caesalpiniaceae 1000 17 Khair Cutch tree Acacia
catechu Mimosaceae 112
18 Rayan Rayan Manilkera hexandra
Sapotaceae 60
19 Ambo Mango tree Mangifera indica
Anacardiaceae 150
20 Bakan limdo Persian lilac Melia azedarach
Meliaceae 200
21 Subabul subabul leuceina leucocephela
6500
22 Others spp. 23017
TOTAL TREES 145086
4.4 EXISTING INFRASTRUCTURE
The plant is located in a well-developed industrial zone, which has all essential facilities such as
internal roads, arrangement for supply of water and power to industries, effluent disposal
facilities, gas etc.
M/s. VARDHAMAN ACRYLICS LIMITED 27
The proposed project is relatively small in size and will be employing some skilled and unskilled
people. First preference will be given to local people, so there will be no change in population
pattern due to the proposed project.
4.5 SOIL CLASSIFICATION
The soil of the district can be classified as light, medium and heavy according to depth, texture
and location. There is sandy loam to loamy in texture, brownish black in color.
4.6 CLIMATE DATA
Based on the meteorological data, wind rose is prepared for the summer season period between
the March 2015 to May 2015. The wind rose diagram prepared from same data is shown in
Figure 3.
TABLE: 14
METEOROLOGICAL DATA
(Data from Indian Meteorological Department, Ahmadabad, Station:-Baroda)
Month Temperature(oC) Humidity (%) Rain fall (mm)Maximum Minimum Maximum Minimum Maximum Minimum
March-15 41 17 57 32 012.1 00 April-15 41.4 22.4 67 30 006.9 00 May-15 42.7 27.0 75 29 0.0 00
M/s. VARDHAMAN ACRYLICS LIMITED 28
FIGURE: 4
WIND ROSE DIAGRAM FOR PERIOD OF MARCH-2015 TO MAY-2015
Observation: It was observed that wind is blowing mainly towards the NE direction from SW.
Average wind speed was 3.26 m/s with calm winds recorded to be 5.57%.
4.7 SOCIAL INFRASTRUCTURE
There are 41 villages in Jhagadia Taluka. Population density and sex ratio of Jhagadia Taluka was
reported 212 persons/sq.km. And 937 females per 1000 males respectively in 2001 census report.
Total literacy of Jhagadia Taluka was found 65.92 %.The basic amenities like primary and
secondary education schools, community health workers, primary health sub centre, private
practitioners, primary health centre, maternity and child welfare, dispensaries, T.B clinic, family
welfare centre, hospital, drinking water, transportation facilities, electricity , telephone etc. are
available.
M/s. VARDHAMAN ACRYLICS LIMITED 29
5.0 PLANNING BRIEF
5.1 PLANNING CONCEPT:
Jhagadia is largely an industrial area dominated by large scale industries, especially chemical
Plants. Government agencies provide many basic facilities like uninterrupted water supply, power
and road network.
5.2 POPULATION PROJECTION.
As of 2011 India census, Ankleshwar had a population of 140,839. Males constitute 53% of the
population and females 47%. 13% of the population is under 6 years of age.
5.3 LAND USE PLANNING
The names of prominent industries are shown in table no: 14
Table: 15
NAME OF SOME PROMINENT INDUSTRIES
Sr. No. Name of industry 1 DCM SHRI RAM LTD 2 UNITED PHOSPHOROUS LTD 3 MTZ TRIBUTON ESXPORTS LTD 4 HUBER CHEM LTD 5 LANXESS INDIA PVT LTD 6 KOHLER INDIA CORPORATION. PVT. LTD.
6.0 PROPOSED INFRASTRUCTURE
6.1 PROCESSING AREA
The process area is covered plant area, raw material storage area, hazardous waste storage area,
workshop and utilities.
6.2 NON PROCESSING AREA
The non process area is covered Admin Building, toilet blocks, change room and security cabin.
6.3 GREEN BELT AREA
Total plot area of the unit is 52.918 Hect. Total Construction area of the unit is 14.523 Hect. Unit
has allotted 38.395 hect area for green belt.There will be provision of budget of 5 lakh rupees for
green belt development. . A detail of different varieties of plant planted in green area is mentioned
in below table no:-13.
M/s. VARDHAMAN ACRYLICS LIMITED 30
6.4 SOCIAL INFRASTRUCTURE
The availability of basic amenities is covered as under:
• Training & Education: All the employees are being trained and educated periodically about
the hazardous nature of chemicals used in the process. Also, training for fire fighting, work
permits system, first aid, safe handling of hazardous chemicals and integrating safety, in all
activities.
• Medical facility: Pre-employment medical checkup at the time of employment. In order to
safe guard the health of the employees, all the employees undergo periodic health checkup.
• Drinking water: Unit has provided Aqua Guard/R.O at different places to provide purified
water for drinking purpose.
• Transportation: The unit is providing basic transportation facility to workers.
• Telegraph & Post: Unit has all the facilities like telephone, fax and internet for the employees.
6.5 CONNECTIVITY
This industrial estate is well connected to Ahmadabad/Mumbai/Vadodara through the
Ankleshwar. Rail services and Road services are available in Ankleshwar.
6.6 DRINKING WATER MANAGEMENT
Average daily water consumption of unit is 95KL/day for domestic purpose. GIDC water is a
source of domestic water.
6.7 INDUSTRIAL WASTE MANAGEMENT
The hazardous waste like discarded bag /containers and used oil, spent carbon, polymer waste and
filter & filter material is generating during the manufacturing process. The hazardous waste
management and disposal is shown in table 12.
6.8 SOLID WASTE MANAGEMENT
The record of hazardous waste and non hazardous solid waste like plastic waste, discarded bag &
containers and spent oil etc is being maintained by the unit.
6.9 SOURCE OF POWER
Unit has its own power generation facility. (5.5 MW)
M/s. VARDHAMAN ACRYLICS LIMITED 31
7.0 REHABILITATION AND RESETTLEMENT(R &R) PLAN
The proposed project is located in GIDC Estate, Jhagadia. There will be no any human settlement
affected by proposed project. So, there is no requirement of any R & R Plan.
8.0 PROJECT SCHEDULE & COST ESTIMATES
8.1 PROJECT IMPLEMENTATION SCHEDULE
The details of project Implementation Schedule is given in below table.
TABLE: 16
PROJECT IMPLEMENTATION SCHEDULE
Project implementation schedule after getting NOC from GPCB Sr. No. Activity Required Period1. Civil work Immediately after getting NOC 2. Procurement of machinery 1 month after getting NOC
3. Eraction & installation of machinery
Immediately after competition of activity no.2
4. Trial of machinery & equipment
Within 1 months after competition of activity no.3
5. Commercial activity 1 months after competition of activity no.4 8.2 ESTIMATED PROJECT COST
The details of Capital cost projection are given in table no. 5.
9.0 ANALYSIS OF PROPOSAL First preference will be given to local people for employment and Company will also try to
provide indirect employment opportunities by availing local contract services during
transportation and operational phase.
The company intends to donate 0.5 % of the profit to agencies like NGOs or social welfare
societies for projects carried out in nearby villages for their welfare and upliftment. In past years,
company has performed many CSR activities. List of activities is mentioned in below table No
17, 18 & 19.
M/s. VARDHAMAN ACRYLICS LIMITED 32
TABLE: 17
CSR ACTIVITY IS PERFORMED BY VAL-J DURING THE YEAR 2013-2014.
Sr. No
Location Activity Activity
performed in month
Actual Amount incurred
1 Talodara Village
Organizing the Navaratri Mahotsav with the support of village seniors & Distributed Gifts (kitchen appliances) to girls , children & youth for
participation & to inspire them for cultural activities
Oct-13 20,000
2 Talodara Village
Donation given to Talodara Yuvak Mandal for celebration of Ganesh Mahotsav. Amount utilize for mandap decoration, statue of Lord Ganesha, pooja
samagri & Prasad
Aug-13 2,101
3 Dadheda Village
Donation given to Dadheda Yuvak Mandal for celebration of Ganesh Mahotsav. Amount utilize for mandap decoration, statue of Lord Ganesha, pooja
samagri & Prasad
Aug-13 2,100
4 Dadheda Village
Major community of village is Muslims & having mosque for ibadat & other holy activities.
They don't have sufficient sitting arrangements. Hence
we have provided plastic chairs - 90 nos. to enhance the
sitting facilities.
Dec-13 30,780
5 Talodara Village
Fabricated MS grilled windows & doors have been installed in class rooms & offices of Amar Vidyalaya
(Higher Secondary School) to protect school properties
i.e.computers , stationaries , sports equipments
Aug-13 15,365
6
Talodara , Dadheda & Vakhatpura
villages
Celebration of Independent Day - Distribution of Gifts
(Stationary kit) to all students & small children of
neighbouring villages to motivate them & to interact
Aug-13 25,937
M/s. VARDHAMAN ACRYLICS LIMITED 33
TABLE: 18
CSR ACTIVITY IS PERFORMED BY VAL-J DURING THE YEAR 2014-2015.
with them. (Talodara - 400 , Dadheda -
375 , Vakhatpura - 50 = Total 825 sets)
7
Talodara , Dadheda & Vakhatpura
villages
Celebration of Republic Day - Distribution of Gifts
(Stationary kit) to all students & small children of
neighbouring villages to motivate them & to interact
with them. (Talodara - 400 , Dadheda -
375 , Vakhatpura - 50 = Total 825 sets)
Jan-14 25,987
8 Kapalsadi Village
Celebration of Ursh Festival in neighbouring village , donation given for organizing festival & for increase the moral support
of local villagers
Mar-14 3,000
Total Amount used for CSR
125,270
Sr. No
Location Activity Activity
performed in month
Actual Amount incurred
1 Dadheda PCC work of compound area
of primary school May-14 66263
2 Talodara Village Main gate of primary school -
Fabrication job Jul-14 12260
3
Talodara , Dadheda & Vakhatpura
Village
Celebration of Independent Day - Distribution of Gifts
(Stationary kit) to all students & small children of
neighbouring villages to motivate them & to interact with them. (Talodara - 400 ,
Dadheda - 375 , Vakhatpura - 50 = Total 825 sets)
Aug-14 25988
4 Talodara Village
Organizing the Navaratri Mahotsav with the support of village seniors & Distributed Gifts (kitchen appliances) to girls , children & youth for
Oct-14 25000
M/s. VARDHAMAN ACRYLICS LIMITED 34
TABLE: 19
CSR ACTIVITY IS PERFORMED BY VAL-J DURING THE YEAR 2016-2017.
Sr. Project Brief Description Cost (Rs. in Lacs)
1 Talodara Village, Jhagadia GIDC area Construction of New Aaganwadi at Talodara village
1.62
2 Dadheda Village, Jhagadia GIDC area Extention of Primary School at Dadheda village with addition of computer room
6.16
3 Talodara Village, Jhagadia GIDC area Addition of a new class room at Amar Vidyalaya (Secondary School)
13.58
4 Toilets Project under Swachh Bharat Abhiyan, in GIDC Villages through Jhagadia Industries Association (Under Construction)
8.00
5 Construction of computer lab at Talodara primary school (Under Construction)
11.00
6 New building, Anganwadi , Sardarpura (Under Construction)
7.91
Grand Total 48.27
participation & to inspire them for cultural activities
5 Talodara Village Sports Equipment to Amar
Vidhyalaya Jan-15 6546
6 Utiya Village Repairing of floor of Gram Panchayat Building - Tiles
work (Massonary work) Mar-15 30000
7 Kapalsadi Village Celebration of Ursh Festival
(03.04.15/04.04.15) Mar-15 5000
8
Talodara , Dadheda & Vakhatpura
Village
Celebration of Republic Day - Distribution of Gifts
(Stationary kit) to all students & small children of
neighbouring villages to motivate them & to interact with them. (Talodara - 400 ,
Dadheda - 375 , Vakhatpura - 50 = Total 825 sets)
Jan-15 27826
Total Amount used for CSR
198883
M/s. VARDHAMAN ACRYLICS LIMITED 35
10. HONOURS & ACHIEVEMENTS LIST 10.1 HONOURS & ACHIEVEMENTS LIST (EHS)
We have participated in National Safety Council of India Awards for the year- 2013, 2014 &2015. Received certificate of Appreciation for the year 2013 & 2015 & Won 3rd Level award (Suraksha Puraskar) for the year-2014. For the year-2016, Result is awaited.
We have participated in Gujarat State Safety Award for the year- 2011, 2012, 2013& 2014. And won the 1staward as winner at state level 04 times in a row. For the Year-2015, Result is awaited.
Awards details are as under; TABLE: 20
ACHIEVEMENT LIST
Sr. No.
Type of Competition
Organized By
Level of Companies Participated
Prize(s) Awarded / won
1
National Safety Council of India Awards - 2013 (Manufacturing Sector)
National Safety Council of India
National level (companies)
Certificate of Appreciation
2
National Safety Council of India Awards - 2014 (Manufacturing Sector)
National Safety Council of India
National level (companies)
3rd Level (SURAKSHA PURASKAR) Bronze Trophy & Certificate
3
National Safety Council of India Awards - 2015 (Manufacturing Sector)
National Safety Council of India
National level (companies)
Certificate of Appreciation
National Safety Council of India Awards - 2015 (Manufacturing Sector)
National Safety Council of India
National level (companies)
Result yet to declare by Awarding Agency
4
Gujarat State Safety Award - 2011
Gujarat Safety Council & Directorate Industrial Safety & Health, Gujarat State
State Level (companies)
Winner (1st)
5
Gujarat State Safety
Gujarat Safety
State Level
Winner (1st)
M/s. VARDHAMAN ACRYLICS LIMITED 36
Award - 2012 Council & Directorate Industrial Safety & Health, Gujarat State
(companies)
6
Gujarat State Safety Award - 2013
Gujarat Safety Council & Directorate Industrial Safety &Health, Gujarat State
State Level (companies)
Winner (1st)
7
Gujarat State Safety Award - 2014
Gujarat Safety Council & Directorate Industrial Safety & Health, Gujarat State
State Level (companies)
Winner (1st)
8 Gujarat State Safety Award - 2015
Gujarat Safety Council & Directorate Industrial Safety & Health, Gujarat State
State Level (companies)
Result yet to declare by Awarding Agency
Company has applied for ISO 14001: 2015 &OHSAS 18001:2007 Certification .Final audit completed successfully. Recommended for certification of ISO 14001 & OHSAS 18001: 2007. 10.2 HONOURS & ACHIEVEMENTS (QUALITY CIRCLE & TPM) TABLE: 21
ACHIEVEMENT LIST
Sr.No.
Category of Award
Name of Award
Organizer Date Venue AWARDS
1 State Level Gujarat State Level Safety Competition
Directorate of Industrial Safety & Health
2011 Vadodara First Prize
2 State Level QCFI Annual Case study presentation
QCFI 9/24/2011 Vadodara Bronze award
3 State Level QCFI Annual Case study presentation
QCFI 9/16/2012 Vadodara Bronze award
4 State Level Gujarat State Directorate of 2012 Vadodara First Prize
M/s. VARDHAMAN ACRYLICS LIMITED 37
Level Safety Competition
Industrial Safety & Health
5 National Level
India Excellence Manufacturing Awards
Frost & Sullivan
9/15/2012 On site Audit
Significant progress towards reliable process Category (Silver Certificate of Merit)
6 State Level Gujarat State Level Safety Competition
Directorate of Industrial Safety & Health
2013 Vadodara First Prize
7 National Level
KAIZEN Conference
TPM Club of India
2/27/2013 Gurgaon Certificate of Appreciation
8 National Level
Suraksha Puraskar
National Safety Council
of India 2014 New Delhi
Bronze Trophy
9 National Level
KAIZEN Conference
CII New Delhi 2/26/2015 New Delhi Certificate of Appreciation
10 State Level QCFI Annual Case study presentation
QCFI, Vadodara Chapter
9/13/2015 Vadodara
Gold Medal (Two Teams) (Nishtha & Sankalp)
11 District Level
QCFI Annual Case study presentation
QCFI, Ankleshwar
Chapter 9/26/2015 Ankleshwar
Gold Medal (Two Teams) (Samadhan & Manthan)
12 State Level QCFI Annual Case study presentation
QCFI 9/12/2016 Vadodara
Gold Category award (Two Teams (Nishtha & Chintan)
13 State Level QCFI Annual Case study presentation
QCFI 9/23/2016 Ankleshwar
Gold Category award (Two Teams - Samadhan & Sankalp)
M/s. VARDHAMAN ACRYLICS LIMITED 38