Upload
hoangliem
View
217
Download
2
Embed Size (px)
Citation preview
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 1
INTRODUCTION
M/s. Ion Exchange (India) Ltd. will engage for manufacturing of Cation & Anion Resins at
Plot No. 5811-12-13, GIDC Estate, Ankleshwar, Gujarat.
As per EIA notification 2006 and its amendment, the proposed project is falling under
category 5(f). The unit is having CCA for manufacturing of Cation & Anion Resins. They
have now proposed to go for expansion by increasing in production capacity.
The details of products are given below Table 1.
TABLE 1
LIST OF PRODUCTS
COST OF PROJECT
The expected cost of project is Rs. 25 Crores. The plot has been purchased by M/s. Ion
Exchange (India) Ltd. from GIDC. The total plot area of the unit is 46977 sq.m. The green
belt area will be 8937 sq.m.
FUEL CONSUMPTION
The proposed unit will use Natural gas and LDO as fuel for Boilers and diesel used for DG
Set. The existing Natural Gas consumption is 202.5 Nm3/Hr and Natural gas consumption
due to proposed expansion will be 47.5 Nm3/Hr. Total Natural Gas requirements after
proposed expansion will be 250.0 Nm3/Hr. There will be no changes in proposed expansion
for Diesel consumption for DG set and LDO for Boiler.
1.0 EXECUTIVE SUMMARY
Sr.
No.
Name of
Products
Existing quantity
as per Consent
No. AWH-56490
in (M3/Month)
Proposed quantity for
Expansion in
(M3/Month)
Total quantity
(M3/Month)
1. Resin-Anion 250 750 1000
2. Resin-
Cation
1400 600 2000
By-Product
1. Sulphuric
Acid
(60-70%)
350 250 600
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 2
ELECTRICITY CONSUMPTION
The unit have electricity from Daxin Gujarat Vij Company Ltd. The existing electricity
consumption is 900 KVA and electricity consumption due to proposed expansion will be 700
KVA. Total electricity requirement after proposed expansion will be 1600 KVA.
WATER CONSUMPTION
As per Consent
The source of water will be from GIDC water supply scheme.
The water consumption for industrial purpose is 857 KL/day. The unit is use 657 KL/day
fresh water and 200 KL/day recovered water. The water consumption for the domestic
purpose is 8 KL/day fresh water.
Proposed scenario
There will be increase in fresh water 185 KL requirement. The unit has proposed to install RO
system and recover additional 150 KL water. The efficiency of RO plant will be almost 54%
permeate and 46 % reject. Earlier it was only 50% efficiency.
WASTE WATER GENERATION
As per Consent
Total waste water generation is 800 KL/Day. It is sent to RO Plant and Bio stream. 200 KL/
Day RO permeate water is recovered and reuse in process. Rejected from RO 200 KL/ Day,
Recycle stream 200 KL/Day and Bio stream 200 KL/Day is sent to the NCTL for further
treatment.
Proposed scenario
The unit will be segregating its effluent in to high COD (Bio stream) and low COD stream.
The high COD stream will be treated to required norms and discharge in to GIDC drainage
line. The low COD stream along with sewage, cooling tower blow down and boiler blow
down will be treated separately and subjected to RO. The permeate will be recycled back in
process and reject will be discharged.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 3
GASEOUS EMISSION
There will be flue gas emission from Boiler (I to IV & V) having capacity of 850 Kg/Hr each.
Also emissions will come from two D.G. sets having capacity of 200 KVA and 475 KVA
respectively. The D.G. sets will be used in case of emergency only. There will be no change
in Flue gas emission due to Proposed Scenario.
There will be process emission from one vent of the HCl process scrubber, one vent of the
SO2 process scrubber. There will be no additional new process stacks due to proposed
expansion.
HAZARDOUS WASTE MANAGEMENT
As per Consent
As per CCA order no. AWH-56490, the hazardous waste generation are Used Oil (1.2
MT/year), Discarded Barrels (1200 No/Year), discarded Liners (24 MT/Year), Insulation
Waste (0.78 MT/year), Personal Protective Equipment’s (3 MT/Year), Broken Glassware
(0.24 MT/Year). Chemical Gypsum & Bio-Mass from Waste Water Treatment (7860
MT/Year) and Spent Resin/Fines Resin from Ion Exchange Type Material Used For Water
Purification (Non-Toxic & Non-Hazardous) (600 MT/Year), Spent Carbon (120 MT/Year),
Wet Scrubber Residue (0.12 MT/Year) and Spent Acid (H2SO4) (4200 M3/Year).
Used oil is sold to MoEF approved vendors. Discarded Barrels, Discarded Liners, Insulation
Waste, Personal Protective Equipment’s, Broken Glassware are sold to GPCB approved
vendors after decontamination & other items will be disposed to TSDF-BEIL, Ankleshwar.
Gypsum will be sold to Cement Industry, M/s. Gujarat, Ambuja Cement, Kodinar, Gujarat &
M/s. Ultratech Ltd (A Unit Of Gujarat Cement Works), Kovaya, Rajulacity, Amreli & Bio-
Mass will Be Disposed to BEIL, Ankleshwar. Spent Resin/Fines Resin From Ion Exchange
Type Material Used for Water Purification (Non-Toxic & Non-Hazardous) and Spent carbon
are Disposed to BEIL - Ankleshwar. Wet Scrubber Residue is send to ETP for further
treatment. Spent Acid (H2SO4) is sold to actual end users.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 4
Proposed scenario
The hazardous waste generation will be Used Oil (2.4 MT/year), Discarded Barrels (6000
No/Year), Discarded Liners (36 MT/Year), Insulation Waste (1.02 MT/year), Personal
Protective Equipment’s (5.4 MT/Year), Broken Glassware (0.48 MT/Year), Distilled Solvent
(60 MT/Year) and Spent Acid (H2SO4) (7200 M3/Year) as by product. There will be no
change in quantity of Chemical Gypsum & Bio-Mass from Waste Water Treatment, Spent
Resin/Fines Resin from Ion Exchange Type Material Used for Water Purification (Non-Toxic
& Non-Hazardous), Spent Carbon and Wet Scrubber Residue.
Used oil will be sold to MoEF approved vendors. Discarded Barrels, Discarded Liners,
Insulation Waste, Personal Protective Equipment’s, Broken Glassware will be sold to GPCB
approved vendors after decontamination & other items will be disposed to TSDF-BEIL,
Ankleshwar. Gypsum will be sold to Cement Industry, M/s. Gujarat, Ambuja Cement,
Kodinar, Gujarat & M/s. Ultratech Ltd (A Unit of Gujarat Cement Works), Kovaya, Rajula
city, Amreli & Bio-Mass will be Disposed to BEIL, Ankleshwar. Spent Resin/Fines Resin
From Ion Exchange Type Material Used for Water Purification (Non-Toxic & Non-
Hazardous) and Spent carbon will be Disposed to BEIL - Ankleshwar. Wet Scrubber Residue
will be Send to ETP for further treatment. Spent Acid (H2SO4) will be sold to actual end
users. Distilled Solvent will be sold to actual end users.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 5
2.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION
M/s. Ion Exchange (India) Ltd. will engage for manufacturing of Cation & Anion Resins at
plot no. 5811-12-13, GIDC Estate, Ankleshwar, Dist. Bharuch, Gujarat.
The list of products is provided in Table -1.
2.2 Introduction of Project Proponent
M/s. Ion Exchange (India) Ltd. is a steady growing company incorporated in 1994. It is a
registered as Large Scale industrial unit. The project proponents are already in market and
doing manufacturing and trading of these products.
Quality Policy:
The quality policy and environment policy of the company is as under:
“We are committed to manufacture, deliver and Service Ion exchangers and related Products
conforming to customer requirements and to enhance customer satisfaction by
• Implementing and Maintaining ISO 9001: 2008 quality management system and
continual improvement of its performance.
• Training our employees in quality management systems, behavioral and functional
and other areas.
• Providing safe and hazard free work environment.
• Achieving higher levels of quality productivity and safety.
• Improving process for batter efficiency.
• Timely delivers.
Environment Policy
Ion exchange (India) Ltd. has specialized in water and waste water treatment for over three
decades using a wide range of processes and products the company offers total water
management solution for industry homes and communities.
We at Ankleshwar unit are involved in the Manufacture of Ion Exchange Resins.
2.1. Introduction of the Project
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 6
We Commit Ourselves To:-
• Conservation of Resources and Continual improvement of our processes and activities
to minimize their Environment Impact.
• Compliance with Legal & other requirements.
• Cultivate more and more activities having positive Environmental Impacts.
• Providing a safe and healthy working Environment and Demonstrating responsibility
towards the environment around us.
• Communicating our environmental policy to all persons working for or on behalf of
the organisation and the public.
• Facilitating employee participation in implementation of system.
• Regular reviews of our environmental performance and practices against Objectives
and Targets.
• Prevention of pollution by minimizing pollution at source.”
The name and address of Directors are given in Table 2.
TABLE 2
CONTACT DETAILS OF THE DIRECTORS
Sr.
No.
Name Address Contact No.
1. Mr. Rajesh
Sharma
32, Vidhani Apartments, Narayan Dabholkar
Marg, Mumbai – 400 006
9324414305
2. Dr. Vijay Narhar
Gupchup
76, Blue Haven, B. Hire Marg, Malabar Hill,
Mumbai – 400 006
022 – 2364 1183
09820020207
3. Mr. Mahabir
Prasad Patni
P-491, CIT Scheme, XL VII Keyatalla Lane,
Kolkata – 700 029.
09830049093
4. Mr. Thekkekkara
Meloth Mohan
Nambiar
172, Jupiter Apartment, Cuffe Parade, Colaba,
Mumbai – 05
022- 2218 2544/4170
09821014261
5. Mr. Parthasarathy
Sampath Kumar
Flat No. 502, EDEN-1,
Hiranandani Estate, Ghodbunder road,
Patahlipada, Thane (w)- 400607
022 – 2218 2960
09821231790
6. Mr. Dinesh
Sharma
Flat No. 64, Vijay Appt, 16, Carmichael Road,
Bh. Jaslok Hospital, Mumbai – 400 026
9324226540
7. Mr. Ankur Patni
P-491 ,CIT, Scheme XLVII, Keyatolla lane ,
Kolkata -700 029
9339871575
8. Mr. Abhiram Seth 18, Anandlok, New Delhi – 110 049 9810182441
9. Mr. Shishir
Tamotia
B98, Surya Vihar, Ph-II, Bhilai, Chattisgarh –
490 020
64848326,
9819889972/
9773301119
10. Mrs. Kishori
Udeshi
15, Sumit Apts., Carmichael Road, Mumbai –
400 026
--
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 7
2.3 Nature of project
The unit will manufacture Resin- Cation (600 MT/Month) and Resin- Anion (750
MT/Month) and By-product will Sulphuric acid (250 MT/Month). As per EIA notification
2006 and its amendment, the proposed project is falling under category B-5(f).
2.4 Market Feasibility
In recent years, market demands for chemical products have become increasingly diverse and
specialized, meaning that one must be able to offer customers a diverse range of synthesis
techniques. Keeping in mind this trend, demand for products is increasing.
Ion Exchange (India) Limited pioneered water treatment in India & today they are the
country’s premier company in water & environment management, with a strong global
presence. Among few companies worldwide, with the entire range of technologies, processes,
products & services, they are able to provide solutions for every sector – industrial,
institutional, municipal and household for both urban and rural markets.
They manufacture world class ion exchange resins of all types - gel, macroporous and
isoporous, for water, non-water and speciality applications in industries such as pharma, food
& beverage, nuclear, chemical, bio-diesel, hydrometallurgy, sugar and many more. Located
in Ankleshwar, a well developed industrial and economic zone in Gujarat it is one of the
largest resin producing units and the first ion exchange resin manufacturing plant to receive
ISO 9001:2000 and 14001 certification, in India.
2.5 Employment generation due to the project
Approx 32 persons will get employment from this proposed expansion project. The details
are given below.
Sr.
No.
Category Existing
Manpower
Proposed additional
Manpower
Total Manpower
1 Managerial 28 2 30
2 Technical 79 16 95
3 Administrative 17 2 19
4 Skilled workers 15 2 17
5 Unskilled
workers 68 10 78
Total: 207 32 239
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 8
3.0 PROJECT DESCRIPTION
3.1 Type of project
The proposed project will not include any interlinked and interdependent projects. It is
Chemical manufacturing project.
3.2 Project location
The proposed project site is located at plot no 5811-12-13, GIDC Estate, Ankleshwar, Dist.
Bharuch in the state of Gujarat. It is approximately 20 km distance from district head quarter
Bharuch. The approximate geographical positioning of the project site is at Latitude:
21037’59.03”N, Longitude: 73
02’54.75”E. The location of the project site can be identified
from the location map shown in Figure-1 & 2.
The salient features of the location of the project site are presented in give below Table 3.
TABLE 3
SALIENT FEATURES OF THE PROJECT SITE
Particulars Details
Taluka/ Tehsil Ankleshwar
District Bharuch
Approx. Geographical
positioning
Latitude: 21037’59.03”N
Longitude:7302’54.75”E
Nearest City Bharuch about 20 KM
Nearest Town Ankleshwar
Nearest Highway NH No. 8
Nearest State highway Old National Highway No. 8
Nearest Railway line/
Railway station
Ankleshwar Railway Station
Nearest Airport/ Airbase Surat
Protected Areas/
Sanctuaries
--
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 9
FIGURE 1
LOCATION OF THE PROJECT SITE
FIGURE -2
SATELLITE IMAGE OF THE PROJECT SITE
Ankleshwar Industrial area
Panoli Industrial area
Jhagadia industrial area
Priaman CETP
Canal
Piraman to Katiyajal Effluent
Pipe
Jhagadia to Piraman CETP
Panoli to Piraman CETP
PROJECT
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 10
3.3 Criteria for Site selection
This is expansion project. So the proponent did not consider any other alternative site for
proposed expansion. The existing plot has sufficient area for carrying out expansion.
3.4 Neighboring Industries
The industry is located in an area, which is already industrialized. The industries in the
vicinity of the proposed project are given in the table 4:
TABLE 4
NEARBY INDUSTRIES IN THE VICINITY
Name of
Industry
Direction with respect to
project site Address
Open plot of
GIDC
East side of company Open GIDC Plot
Open plot of
GIDC
North side of company Ankleshwar to Jhagadia Railway Line
Heubach
Colour Pvt.
Ltd.
South side of company Plot No. 9113/2, GIDC Estate,
Ankleshwar
Sajjan India
Ltd
West side of company Plot No. 6117-19 GIDC Estate,
Ankleshwar
3.5 Size of Project
The expected cost of proposed project is Rs. 25 Crores.
New Plant and machinery installations will also have to be acquired and installed.
Environment Protection and safety systems have also been considered in planning the Cost
Projection. Green belt development, provision of fire extinguishers etc. are also calculated.
The following table shows the break-up of the proposed project cost.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 11
TABLE 5
CAPITAL COST OF PROJECTION
Sr. No. Purpose Proposed
1. Land --
2. Building
Rs. 20.00 Crores
3. Plant and Machinery
4. Q.A. Lab set up
5. Environment Protection & Safety
a) Effluent treatment Plant Rs. 4.98 Crores
b) Safety Equipment (PPE, fire
extinguishers, Ventilation, etc.)
Rs. 0.02 Crores
c) Green belt development --
d) Fire --
Total Rs. 25.00/- Crores
3.6 Process Technology
The details are covered in Annexure-IV of Form-I.
3.7 Raw-Materials
The proposed products are Cation & Anion Resins and the required raw materials will be
purchased from the local/ Indian market. Details of raw-material consumption are attached as
Annexure-III of Form-I.
3.8 Resource optimization/recycling and reuse
3.8.1 Solvent Recovery
Methanol and EDC solvents are used for manufacture, Distilled solvent will be sent to end
users.
3.9 Resource Requirements
3.9.1 Land
The plot has been purchased by M/s. Ion Exchange (India) Ltd. The total plot area of the unit
is 46977 sq. m.
3.9.2 Building
The new building will be constructed. The approximate requirement or construction materials
are given below table. Details are provided in plant lay out.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 12
TABLE 6
APPROXIMATE REQUIREMENT OF CONSTRUCTION MATERIALS
Sr.
No.
Construction material Proposed Quantity
1. Stone 78.44 m2
2. Sand 62.84 m3
3. Aggregate 76.73 m3
4. Soil 209.56 m3
3.9.3 Power and Fuel
The unit’s power and fuel requirement is provided in Table 7. There will not be any increase
in fuel consumption. The unit is using natural gas as fuel in normal circumstances. Whenever,
any issue of availability of natural gas is there, unit use LDO as fuel.
TABLE 7
POWER AND FUEL REQUIREMENT
Sr.
No
Name Existing
Quantity As
per Consent
Proposed
Quantity
Total Quantity Source
1. Natural
Gas for
Boilers
202.5 M3/Hr. 47.5 M
3/Hr. 250.0 M
3/Hr. GGCL
2. LDO as
Alternate
Fuel to
Boilers
0.025
Kl/Hr.(Only
When Natural
Gas not
Available)
00 0.025
Kl/Hr.(Only
When Natural
Gas not
Available)
LOCAL
MARKET
3. Diesel For
DG Sets
0.135 Kl/Hr. 00 0.135 Kl/Hr. LOCAL
MARKET
4. Energy-
Electricity
900 KVA 700 KVA 1600 KVA DGVCL
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 13
The category wise bifurcation of the water requirement is given in Table 8. The source of
water will be from GIDC water supply scheme. There will be increase in fresh water
requirement. The unit has proposed to install RO system and recover additional 150 KL
water. The efficiency of RO plant will be almost 54% permeate and 46 % reject. Earlier it
was only 50% efficiency. The detail of water consumption is given in Table 8.
TABLE 8
DETAILS OF WATER CONSUMPTION
Particulars Existing Quantity
(KL/Day)
Proposed
Quantity
(KL /Day)
Total Quantity
(Proposed Scenario)
(KL/Day)
i) Domestic 8 +4 12
ii) Industrial
Process
527 (Fresh) +
200 (Reused RO
Permeate)
+90 (Fresh)+ 150
(Reused RO
Permeate)
617 (Fresh)+ 350
(Reused RO
Permeate)
Boiler +
Cooling 90 +70 160
Washing 26 +5 31
Gardening 14 +16 30
Total
665 (Fresh) + 200
(Reused RO
Permeate
185 (Fresh) + 150
(Reused RO
Permeate)
850 (Fresh) + 350
(Reused RO
Permeate)
3.9.5 Manpower
The manpower required for the project as well as during the construction/ commissioning
activities will be employed from the local area. The details are provided in Table 9.
TABLE 9
DETAILS OF MAN POWER REQUIREMENT
Sr.
No.
Category Existing
Manpower
Proposed additional
Manpower
Total Manpower
1. Managerial 28 2 30
2. Technical 79 16 95
3. Administrative 17 2 19
4. Skilled workers 15 2 17
5. Unskilled
workers
68 10 78
Total: 207 32 239
3.9.4 Water
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 14
3.10 Mitigation Measures & EMP
Based on overall manufacturing & operation activities, the mitigation measures have been
proposed by the company for the control of the anticipated pollution load.
3.10.1 Wastewater Management
3.10.1.1 Wastewater Generation
The category-wise bifurcation of the anticipated wastewater generation details is given in the
below Table.10. The unit will be segregating its effluent in to high COD (Bio stream) and
low COD stream. The high COD stream will be treated to required norms and discharge in to
GIDC drainage line. The low COD stream along with sewage, cooling tower blow down and
boiler blow down will be treated separately and subjected to RO. The permeate will be
recycled back in process and reject will be discharged. Total Waste water generation will be
1100 KL/Day. It will be sent to RO Plant and Bio stream. 350 KL/ Day permeate water will
be recovered and reuse in process. Rejected from RO 300 KL/ Day, Recycle Stream 100
KL/Day and Bio stream 350 KL/Day will be sent to the NCTL after treatment for final
disposal. When we have received permission of NCTL for wastewater generation, the
quantity of wastewater generation is 750 KL/day otherwise we will be send wastewater
generation quantity (600 KL/day) to NCTL. In future we will plan to 70-80 % efficiency of
RO plant.
The detailed water balance diagram is provided in Figure 3A and 3 B.
TABLE 10
DETAILS OF WASTEWATER GENERATION
Particulars Existing
Quantity
(KL/Day)
Proposed
Quantity
(KL /Day)
Total Quantity
(Proposed
scenario)
(KL /Day)
i) Domestic
a) Domestic 8 +4 12
ii) Industrial
a) Process (Including Recycle
water) 723 +234 957
b) Boiler + Cooling Tower 45 +58 103
c) Washing 24 +4 28
d) Gardening 0 0 0
Total 800 +300 1100
Recovered by RO plant 200 +150 350
Actual Discharge 600 +150 750
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 15
FIGURE -3A
WATER BALANCE DIAGRAM (EXISTING)
Gardening
(14 KL)
Process:
(Fresh: 527 KL + RO Permeate:
200.0* KL)
Boiler + Cooling Tower
(Fresh: 90 KL)
Domestic
(8 KL)
General Washing
(26 KL)
Low COD effluent
to recycle stream
(523 KL)
Blow down
(45 KL)
Sewage-
soak pit
(8 KL)
From
Washing
(24 KL)
Effluent Treatment Plant (800 KL/D)
(Bio Stream: 200 KL/D +
Recycle Stream: 600 KL/D)
High COD
Effluent to
Biostream
(200 KL)
Evaporation
Loss
(20 KL)
RO Plant (400KL)
RO Reject
(200 KL)
Waste Water Tank
(200 +200+ 200) = 600 KL
Final Discharge to NCTL
(600 KL/D)
GIDC Water Consumption (665.0 KL/D)
Bio Stream
(200 KL)
RO Permeate
(200.0* KL)
Reuse in
Process
Evaporation
Loss
(2 KL)
Evaporation
Loss
(4 KL)
Steam Water (25)*
(Recycle)
Recycle Stream (600 KL
From Bio
Stream
(200 KL)
From
Recycle
Stream
(200 KL)
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 16
FIGURE -3B
WATER BALANCE DIAGRAM (PROPOSED)
Process:
(Fresh: 617 KL + RO Permeate:
350.0* KL)
Boiler + Cooling Tower
(Fresh: 160 KL)
Domestic
(12 KL)
General Washing
(31 KL)
Gardening
(30 KL)
Low COD/TDS
effluent to recycle
stream (607 KL)
Blow down
(103 KL)
Sewage-
soak pit
(12 KL)
From
Washing
(28 KL)
Effluent Treatment Plant (1100 KL/D)
(Bio Stream: 350 KL/D +
Recycle Stream: 750 KL/D)
High COD/TDS
Effluent to
Biostream
(350 KL)
Evaporation
Loss
(30 KL)
RO Plant (650 KL)
RO Reject
(300 KL)
Waste Water Tank
(350 + 100 + 300) = 750 KL
Final Discharge to NCTL
(750 KL/D)
GIDC Water Consumption (Existing: 665.0 KL/D
+ Proposed: 185 KL/D)
Bio Stream (350
KL)
RO Permeate
(350.0* KL)
Reuse in Process
Evaporation
Loss
(3 KL)
Evaporation
Loss
(10 KL)
Steam Water (27)*
(Recycle)
Recycle Stream (750 KL)
From Bio
Stream
(350 KL)
From
Recycle
Stream
(100 KL)
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 17
3.10.1.2 Wastewater Characteristics
Industrial wastewater will be generated from process, cooling tower and boiler. The expected
characteristics of industrial wastewater are provided in Table 11.
TABLE 11
CHARACTERISTICS OF WASTEWATER
Sr.
No.
Parameter Unit Recycle
Stream
Bio Stream Final Treated
Effluent
1 pH -- 3.20 – 12.04 3.00 – 13.13 6.88 – 7.88
2 COD Ppm 818 10049 98
3 Total Dissolved Solids Ppm 7174 16126 1978
4 Suspended Solids Ppm 121 308 69
5 Ammonical Nitrogen Ppm 9.20 134.31 8.2
3.10.1.3 Wastewater Treatment & Disposal
BRIEF DESCRIPTION OF THE EFFLUENT TREATMENT PLANT
• MODE OF COLLECTION Mainly two types of effluent streams are generated in this scheme. One of recycle stream for
recycle through biological, UF and RO system and another Biostream are for treatment through
anaerobic & biological system.
Recycle stream contain low COD generated within the manufacturing plant will be conveyed to
the effluent treatment plant after due neutralization and collection in the separate equalization
tank, equalization tank is designed for 1400 m3 / day.
Bio stream contain high COD generated within the manufacturing plant will be conveyed to the
effluent treatment plant after due neutralization and collection in the separate equalization tank,
equalization tank is designed for 450 m3 / day.
A. Effluent Collection Tank (200 m3):
The Recycle stream effluent from the production units comes to the tank through by gravity and
domestic sewage comes to the tank through pump. It follows the treatment mentioned below.
B. Neutralisation Tank: Pump the effluent from the common collection sump to neutralization tank. Effluent is mixed up
with 5% caustic lye solution to make pH 7-8. For this operation we are having dedicated one
caustic lye dosing tank.
C. Equalization Tank (1400 m3):
We are having one Equalization tank of having total capacity of 1400 m3. Equalisation tank is
equipped with perforated pipe grid to supply air to mix the contents of equalization. Then transfer
to mixing tank.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 18
D. Mixing Tank (20 m3):
The effluent coming from the Equalization is mixed up with 2% of lime solution to adjust pH.
Here, ferric chloride is added for floc generation. For this operation we are having dedicated one
lime dosing tank and one ferric chloride dosing tank.
E. High Rated Solid Contact Clarifier (HRSCC) (100 m3):
Neutral effluent with suspended particles comes here by gravity from mixing tank. Here,
polyelectrolyte is added approximately 2-4 ppm in concentration. Hence, suspended particles are
settled down. The clean supernatant effluent is transferred to aeration Tank and settled sludge is
transferred to sludge pit for further treatment.
F. Aeration Tank (850 m3):
The neutral effluent is comes to the aeration tank for bio degradation, which is, equipped with
imported silicone membranes for diffused aeration. The capacity of tank is 850 m3. One air
blower is operating on continuously and another one for standby.
G. Lamella Clarifier : The mixed liquor from aeration tank comes to this system by gravity. Here, biodegradable
polyelectrolyte is added, so the active sludge is settled down and recycled to aeration tank. The
supernatant effluent is transferred to clarifier water tank for further treatment in UF and RO plant.
Here, sodium hypo chlorite is added in supernatant for antibacterial treatment.
H. Clarifier Water Tank (40 m3):
The supernatant from secondary clarifier comes to clarifier water tank by gravity for further
treatment. Then water transfer through multi grade filter (MGF) and activated carbon filter to
Ultra filtration (UF) plant by pump.
I. Ultra Filtration (UF) (34 m3/Hrs):
After passing through ACF, effluent feed into UF via cartridge filter for ultra filtration which is
set in auto system. UF permeate water taken in UF permeate tank for treatment of RO plant.
J. Reverse Osmosis Plant (807 m3/Day) :
After treatment of UF plant, UF permeate water feeding in RO plant. RO Permeate water taken in
RO permeate tank through degasser tower. Permeate water reusing for Process/Boiler/Cooling
Tower. RO Reject water transfer to final collection sump.
K. Final Collection Sump (50 m3):
The effluent coming from the RO plant, after blending with MBR permeate water and then
discharge to the GIDC drainage system for further treatment to NCTL through final outlet tank.
L. Effluent Collection Tank (450 m3):
The Bio stream effluents from the production units comes to the tank through pumps and
Decantor washing effluent comes to the tank through pump. Equalisation tank is equipped with
perforated pipe grid to supply air to mix the contents of equalization. Then transfer to mixing
tank. It follows the treatment mentioned below.
M. Mixing Tank (10 m3):
The effluent coming from the Equalization is mixed up with 2% of lime solution to adjust pH.
Here, poly alluminium chloride is added for floc generation. For this operation we are having
dedicated one lime dosing tank and one poly alluminium chloride dosing tank.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 19
N. High Rated Solid Contact Clarifier (HRSCC) (45 m3):
Neutral effluent with suspended particles comes here by gravity from mixing tank. Here,
polyelectrolyte is added approximately 8-10 ppm in concentration. Hence, suspended particles are
settled down. The clean supernatant effluent is transferred to recirculation tank and settled sludge
is transferred to sludge pit for further treatment.
O. Recirculation Tank (30 m3) :
The supernatant from HRSCC comes to recirculation tank by gravity for further treatment. Here,
nutrients are added for bacteria growth and sodium carbonate is added for maintain alkalinity. The
effluent is transferred to UASB reactor.
P. Up flow Anaerobic Sludge Blanket Reactor (UASB) (1100 m3) :
Effluent from the recirculation tank is pumped to the two numbers of division boxes placed at the
platform above the UASB reactor. Effluent is then further distributed to the ten numbers of inlet
boxes from where by gravity effluent is fed to the UASB reactor with the help of 20 Nos HDPE
pipes connected on each inlet box. Treated effluent is collected through two FRP launders and
falls in to the common RCC launder. From this launder, one part of the UASB treated effluent is
recycled back to the UASB through the UASB buffer tank, while other part is clarified in a
lamella clarifier. Flow equal to the HRSCC outlet shall be sent to the lamella clarifier the other
part has to be recycled back to UASB tank. The settled sludge, in normal operation is disposed off
through centrifuge after Mixing with other sludge. Biogas is flared off through a biogas flare
system installed at site and excess biomass has to be disposed above a certain level of MLSS in
the reactor.
Q. Lamella Clarifier:
The treated effluent from UASB comes to lamella clarifier by gravity for further treatment. The
clean supernatant effluent is transferred to pre aeration tank and settled sludge is transferred to
sludge pit for further treatment.
R. Pre Aeration Tank (30 m3) :
Clarified effluent from lamella clarifier is collected by gravity in to the Pre-aeration tank
from where it is pumped to the aeration tank for its further treatment.
S. First Aeration Tank (366 m3):
The neutral effluent is comes from pre aeration to the aeration tank for bio degradation, which is,
equipped with imported silicone membranes for diffused aeration. The capacity of tank is 366 m3.
One air blower is operating on continuously and another one for standby.
T. Second Aeration Tank (315 m3):
The effluent is comes from first bio aeration to the second aeration tank for bio degradation,
which is, equipped with imported silicone membranes for diffused aeration. The capacity of tank
is 366 m3. One air blower is operating on continuously and another one for standby.
U. Membrane Bio Reactor (117 m3):
The mixed liquor from aeration tank comes to this system by gravity. Always keep the flow at
higher than the permeate flow so that the effluent is always in a circulation mode. MBR tank
blower will always be in continuously operation. One air blower is operating on continuously and
another one for standby. MBR permeate water taken in MBR permeate tank for further treatment.
The effluent coming from the MBR permeate water, after blending with RO plant effluent and
then discharge to the GIDC drainage system
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 20
Highly Acidic effluent of the plant is neutralized with 10% of lime solution in separate
neutralizer reactor. After neutralization of effluent, drain to decanter feed tank. Here,
other tanks drain sludge is mixed with these neutral effluents.
V. Decanter:
The slurry of decanter feed tank is pumped into the decanter for dewatering. Here,
polyelectrolyte is added approximately 8-10 ppm in concentration. The clean supernatant effluent
is transferred to bio effluent collection tank for further treatment and separated sludge is
transferred to sludge storage area and finally sent to cement industries for recycle purpose.
Decanter will always be in continuously operation. One decanter is operating on continuously and
another one for standby.
DIMENTIONAL DETAILS OF ETP UNITS
Sr.
No.
Tank Name Unit Bio Stream Recycle
Stream
1 Effluent Collection Tank 01 NA 200 m3
2 Equalization Tank 02 450 m3 1400 m
3
3 Mixing tank 02 10 m3 20 m
3
4 HRSCC Tank 02 45 m3 100 m
3
5 Aeration Tank
03
First - 315 m3
Second – 366 m3
850 m3
6 Clarifier water tank 01 NA 40 m3
7 Recirculation tank (PCO) 01 30 m3 NA
8 UASB 01 1100 m3 NA
9 Pre Aeration Tank 01 30 m3 NA
10 MBR 01 10 m3/hr NA
11 MBR Permeate Tank 01 87 m3 NA
12 MGF 02 NA 34 m3/hr
(02 nos.)
13 ACF 01 NA 34 m3/hr
14 UF Plant 01 NA 34 m3/hr
15 UF Permeate tank 01 NA 100 m3
16 RO Plant 01 NA 807 m3/Day
17 RO Permeate Tank 01 NA 100 m3
18 Final Collection Sump 02 50 m3 50 m
3
19 Sludge Pit for HRSCC 01 10 m3 Common
20 Final Outlet Tank 01 Common 50 m3
21 MBR (117 m3) 01 20 m
3/hr NA
22 Lime preparation Reactor 02 10 m3 10 m
3
23 Neutralizer Reactor 02 10 m3 10 m
3
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 21
FLOW DIAGRAM OF ETP FACILITY
FLOW DIAGRAM OF ETP ANIONIC - ACIDIC STREAM
POLYELECTROLYTE
LIME ADD
SLUDGE
FROM MBR & BOTH HRSCC’s& Secondary clarifier
SLUDGE
EFFLUENT TREATMENT VIA
ANIONIC (BIO STREAM)
ACID
NEUTRALIZATI
ON
DECANTO
R FEED
TANK
ANIONIC
EFFLUENT
(ACIDIC
STREAM)
DECENTOR
CENTRIFUGE
SLUDGE
COLLECTION
TANK LIME SLURRY TANK
PRIMARY
TREATMENT
SLUDGE STORAGE
AREA
EQUALIZATION
TANK (450KL)
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 22
FLOW DIAGRAM OF ETP CATIONIC - RECYCLE STREAM
FeCL3, LIME poly electrolyte
POLYELECTROLYTE, HYPO
RO PERMEATE
RO ROJECT
CATIONIC
EFFLUENT
(RECYCLE
STREAM)
EQUALI
ZATION
TANK
(1400KL)
MIXING
TANK
HRSCC
MULTI
GRADE
FILTER
LAMELLA
CLARIFIER AERATION TANK
(850 KL)
ULTRA
FILTRATION
PLANT
REVERSE
OSMOSIS
PLANT
ACTIVETED
CARBON FILTER
EFFLUENT
COLLECTIO
N TANK
FINAL
COLLECTION
SUMP
OXIDATION
SUMP
CARBON
FILTER
TREATED
EFFLUENT
OUTLET
TANK
GIDC
DRAIN
PERMEATE FOR
REUSE
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 23
FLOW DIAGRAM OF ETP ANIONIC - BIO STREAM
POLYELECTROLYTE
PAC, LIME
HRSCC TANK
DAP, Na2CO3
CULTURE ADDED
RECIRCULATION
TANK
PRE-AERATION TANK
DAP, CULTURE
DAP, CULTURE
GIDC DRAIN
ANIONIC
EFFLUENT
(BIO STREAM)
UASB TANK
MEMBRANE
BIO REACTOR
FINAL
COLLE
CTION
SUMP
LAMELLA CLARIFIER
OXIDATION
TANK
COLLECTION /
EQUALIZATIO
TANK (450 KL)
Second
AERATION
TANK
TREATED
EFFLUENT
OUTLET TANK
FOR
DISCHARGE
MIXING
TANK (BIO
STREAM)
First
AERATION
TANK
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 24
3.10.2 Gaseous emissions & control
There will be flue gas emission from five boilers and Two DG sets. Natural gas is regular fuel
and LDO as alternate fuel will be used as in boilers and diesel will be used as fuel in DG set.
The air pollution control measures are covered in below table 13.
TABLE 13
DETAILS OF FLUE GAS EMISSIONS
Sr.
No.
Stack
Attach
to
Stack
Height in
Meter
Diameter
in meter
Parameter Permissible Limit
As per Consent No. AWH· 56490
1. Boiler
(I to IV)
30 0.45 Particulate Matter
SO2
NOx
150 Mg/Nm3
100 ppm
50 ppm 2. Boiler
(V)
30 0.45
3. D.G Set
(2 Nos.)
09 (Each)
0.1 Particulate Matter
SO2
NOx
150 Mg/Nm3
100 ppm
50 ppm
As per proposed expansion
1 There will be no change in Flue gas emission due to Proposed Scenario.
The process emissions from the proposed manufacturing activities are given in Table 14.
TABLE 14
DETAILS OF PROCESS EMISSION
Sr.
No.
Stack
Attached
to
Stack
Height
in meter
Stack
Diameter in
meter
APCM Parameter Permissible
Limit
As per Consent No. AWH· 56490
1. HCl
Process
Scrubber
27 0.1 Water
Scrubber
followed by
Alkali
scrubber
HCl
Cl2
20 Mg/Nm3
09 Mg/Nm3
2. SO2
Process
Scrubber
20 0.1 Caustic
Scrubber
SO2 40 Mg/Nm3
As per proposed expansion
There will be no additional new process stacks due to proposed expansion.
3.10.2.1 Flue gas emissions
3.10.2.2 Process emissions
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 25
3.10.3 Hazardous/ Non-hazardous waste management
The following type of hazardous waste will be generated from the operational activities. All
the waste will be stored separately in a designated storage area.
TABLE 15
DETAILS OF HAZARDOUS WASTE
Sr.
No.
Name of
waste
Cat.
No.
Quantity Method of
disposal As per
consent No.
AWH·
56490
As per
proposed
expansion
Total
1. Used Oil 5.1 100
Lit/Month
200
Lit/Month
300
Lit/Month
Collection,
Storage, Sold to
MoEF Approved
Vendors.
2. Discarded
Barrels
33.3 100
Nos./Month
500
Nos./Month
600
Nos./Month
Collection,
Storage, Sold to
GPCB approved
vendors after
decontamination
& other items will
be disposed to
TSDF-BEIL,
Ankleshwar.
Liners 2000
Kg/Month
3000
Kg/Month
5000
Kg/Month
Insulation
Waste
65
Kg/Month
85
Kg/Month
150
Kg/Month
Personal
Protective
Equipment’s
250
Kg/Month
450
Kg/Month
700
Kg/Month
Broken
Glassware
20
Kg/Month
40
Kg/Month
60
Kg/Month
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 26
3. Chemical
Gypsum &
Bio-Mass
from Waste
Water
Treatment
34.3 655
MT/Month
0 655
MT/Month
Gypsum Will Be
Sold to Cement
Industry, M/s.
Gujarat, Ambuja
Cement,
Kodinar, Gujarat
& M/s. Ultratech
Ltd (A Unit Of
Gujarat Cement
Works), Kovaya,
Rajulacity, Amreli
& Bio-Mass Will
Be Disposed to
BEIL,
Ankleshwar.
4. Spent
Resin/Fines
Resin From
Ion
Exchange
Type
Material
Used For
Water
Purification
(Non-Toxic
& Non-
Hazardous)
34.2 50
MT/Month
0 50
MT/Month
Disposed to BEIL
- Ankleshwar.
5. Spent
Carbon 35.3 10
MT/Month
0 10
MT/Month
Disposed to BEIL-
Ankleshwar.
6. Wet
Scrubber
Residue
36.1 10
Kg/Month
0 10
Kg/Month
Send to ETP for
further treatment.
7. Spent Acid
(H2SO4) D2 350
M3/Month
250
M3/Month
600
M3/Month
Sold to actual end
users.
8. Distilled
Solvent 36.1 --- 5 MT/Month 5 MT/Month Sold to actual end
users.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 27
3.10.4 Noise Control & Odour
Ear plugs will be provided to the operating personnel in boiler room. Low noise generating
equipments will be selected. Adequate engineering controls will be implemented to avoid
noise pollution.
The following steps will be taken for odour control.
• Raw-material feeding will be carried out by pumps and in close loop system.
• All reactions will be taken in closed reactor system.
• Roof top ventilation will be provided in the entire plant area.
• Regular monitoring will be done of piping and fittings for checking of any leakages.
3.10.5 Storage, Handling and Transport of Hazardous Chemicals
The storage and mode of transport of chemicals will be done as per detailed MSDS and
chemical hazards guide (NIOSH) for the hazardous chemicals.
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as per
the Schedule-1 of the MSIHC Rules, as amended in 2000.
3.10.6 Health and Safety measures
Few chemical to be used in the proposed activities are listed as ‘Hazardous Chemicals’ as per
the Schedule-1 of the MSIHC Rules, as amended in 2000.
Physical hazards may manifest as fires, explosions, excessive temperatures, or the release of
large volumes of gas or toxic or flammable gases or vapors. According to Schedule 2 & 3 of
MSIHC Rules.
Below mentioned is the summary proposed safety measures to be taken at site for control of
anticipated hazards.
Storage Hazards & Control Measures:
Main products are Anion and Cation resins. They are in granules form and packed in bags of
25 kg and higher size. They are stored in fully ventilated store age locations. Spillage of the
product may lead to slippery hazard and dusty atmosphere. People in the storage location
may get exposed to dust hazards. Leakage of these granules has no effect on health. Fire in
such go down can generate toxic fumes of the chemicals. Products flow along with firewater
and flowing outside the go down and spreading in surrounding can also cause toxic effect. In
case of fire, effluent generated from fire fighting operation is required to be collected, treated
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 28
and disposed off in environmental friendly manner. Therefore, precautions regarding
prevention of fire and leakage of such chemicals are most necessary. Fire detectors in product
go down will be useful in this regard. Similarly, for raw material go down, Hazardous RM is
being stored. These chemicals are hazardous, toxic and having fire hazards. Necessary
precautions signage should be displayed. Material handling signage should be displayed.
The bulk storage areas are separated from main plant and transfer is thro pipe line which is a
safe handling. The storage tanks have dyke wall to take care in case of emergency. Looking
to the flammable and toxic property of certain raw material like methanol, Di-Methyl Amino
Ethanol, Iso-Butyl Alcohol, MYL (Di Methoxy Methane), Methacrylic Acid, Methacrylate
and many such chemicals, it is flame proof electrical fitting uniformly in the entire storage
sheds and provided proper ventilation to prevent accumulation of flammable vapors.
Installation of continuous LEL detector with hooter / alarm is also very much advisable.
The above ground storage tanks area and underground tank area pose high fire hazards. The
area need to be ensured cordoned off as per the drawing approved by PESO- Nagpur.
Necessary fire protection measures need to be ensured for the area viz keeping the fire
hydrant posts approachable, avoiding waste accumulation in the area. Heat / fire detectors
will help to detect fire and control it in time.
Process, hazards and controls:
Manufacturing process includes use of raw materials like styrene, DVB , H2SO4, Oleum,
EDC, Dilute H2SO4, DMA, TMA, DMEA, HCl, MYL, CSA, MF, Methanol, many other
flammable, toxic as well as reactive chemicals. Their reactions with other chemicals generate
toxic fumes and gases. These are toxic hazards. Necessary controls are provided on reaction
vessels viz suction of fumes with blower and scrubbing the fumes. Reaction controls are from
DCS. Most of the reactions are carried out at atmospheric pressure and required temperature.
Addition / transfer of solvent / chemicals in the Process vessel is run by trained people and
use of special PPEs. SOP’s is available and updated from time to time. Many operations
generate dust hazards where we provide dust control measures as necessary. Dilution
ventilation or Local exhaust ventilation are provided.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 29
Other Hazards:
Loading and unloading of materials, use of acids and alkalis, methanol handling and use of
flammable chemicals, working with hazardous processes, working near D.G. Sets, pumps and
motors, transmission machinery etc. and use of utilities contribute variety of hazards like
toxic effect, fire, dust exposures, high noise, hot surfaces, rotating part of the machines etc.
Necessary control measures depending on the type of hazards are provided. Their proper
maintenance and safe working methods are provided. The area is kept neat and clean and
housekeeping is maintained, unobstructed, No damaged floor and covered plant channels to
avoid primary hazards.
4.0 SITE ANALYSIS
4.1 Connectivity
The site is located at Plot no. 5811-12-13, GIDC Estate, Ankleshwar, Gujarat. The land and
Infrastructure is already available and the raw materials are easily available through the easy
transport via road connectivity.
Ankleshwar Industrial Estate was set up by Gujarat Industrial Development Corporation in
early 70s. This industrial estate is spread over an area of 1600 hectares in close proximity to
National Highway No.8 and Delhi-Mumbai Railway Line. Being an ideal location for
industrialization, as on date, more than 1500 industries, consisting of chemicals, pesticides,
pharmaceuticals, bulk drugs, petroleum products, engineering, textiles, plastics, rubber and
packaging etc. are located in this industrial estate.
The town is known for its industrial township called GIDC (Gujarat Industrial Development
Corporation). Ankleshwar has an office of the ONGC (Oil and Natural Gas Corporation
Limited). GIDC is organizing Trade fare and Industrial expo occasionally to attract large
number of industries all over from India. It also helps to get customer on large basis.
Ankleshwar is connected by Indian National Highway 8 (Mumbai to New Delhi) and by
the Western Railway Division of Indian Railways. The railway division also runs the broad
gauge train services to Rajpipla. The 133 year-old Golden Bridge connects Ankleshwar to
Bharuch across the Narmada on the station front while a new bridge connects the highway,
the other bridge on the highway is now ready to use.
Ankleshwar City Bus stand is located on Station Road (i.e. located in the City, the western
section).
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 30
Development project of Ankleshwar Airport & City Bus are in pipe line in last stage.
Ankleshwar is an educated city. It has an average literacy rate of 79%, higher than the
national average of 59.5%; with 56% of the males and 44% of females literate.
Ankleshwar JN Rail Way Station, Sanjali Railway Station are the very nearby railway station
to Ankleshwar GIDC. However Surat Railway Station is major railway station 56 KM near to
Ankleshwar GIDC.
Healthcare
Hospitals include are the
• Jayaben Modi Hospital,
• Sarvajanik Hospital,
• Sanjivani Hospital
• Sardar Patel Hospital.
• And now ESIC's (Employee State Insurance Corporation) New Hospital is under
Construction.
• In April 2014, the "New Life" private hospital was constructed in Jasaat Plaza
(Station Road). It is conveniently served by Ankleshwar's main bus & railway
stations.
Shopping and Recreation:
• There is a lake in GIDC & City area. Situated in front of GIDC Lake, Lakeview Plaza
Mall is city's first truly integrated mall for restaurants, entertainment and hotel stay.
• Nav Graha Jain Mandir (G.I.D.C), Manav Mandir, Sai & Swaminarayan Temple are
big temples in Ankleshwar. Ankleshwar City is also having big Mosques Halimsha
Datar Bhandari, Garib nawaz, etc.
• Centers of Brahma Kumaris World Spiritual University is located in both GIDC and
City area which helps you to Know your true self with the help of Free Rajyoga
Meditation Classes.
• There are parks such as The Millennium Park and old parks in Ankleshwar city, the
GIDC Water Reservoir, and sports center.
• There are swimming pools, Joggers park, children's park, Rotary library and other
recreation centers in the GIDC area.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 31
• There is an Open Air Theater in GIDC Area. Chauta Bazar is the biggest shopping
area in Ankleshwar.
4.2 Land use and land ownership
The proposed project site is located at plot no 5811-12-13, GIDC Estate, Ankleshwar,
Gujarat. The total plot area of the unit is 46977 Sq. M. The project is located at private land.
Land ownership is with project proponents. They have valid consent from Gujarat Pollution
Control Board, Gandhinagar. And the consent no. is AWH: 56490 and it is attached as an
Annexure-X.
4.3 Existing Land use
The proposed project site is located at plot no 5811-12-13, GIDC Estate, Ankleshwar, The
plot is notified by GIDC for industrial purpose.
4.4 Existing Infrastructure
The project is located in a well-developed zone, which have all essential facilities such as
well-connected road network with ease of transportation, arrangement for supply of water
and power to industries, effluent disposal facilities etc.
4.5 Soil Classification
The soils of the district are derived from the Deccan trap which is main rock formation of the
district. The soil of the district can be classified as light, medium and heavy according to
depth, texture and location. There is sandy loam to loamy in texture, brownish black in color.
4.6 Climate data
Vadodara is the nearest meteorological observatory station to the project site. The various
meteorological details of Vadodara station for the year of March, 2015 to May, 2015 are
given in below Table 16.
TABLE 16
DETAILS OF MICRO METEOROLOGICAL DATA
Month Temperature(oC) Humidity (%) Rain fall (mm)
Maximum Minimum Maximum Minimum Maximum Minimum
March-15 41 17 57 32 012.1 00
April-15 41.4 22.4 67 30 006.9 00
May-15 42.7 27.0 75 29 0.0 00
(Data from Indian Meteorological Department, Baroda)
Based on the above metrological data, wind rose has been prepared for the summer season
period from March 2015 to May 2015. As per the metrological data, it shows that the
average wind speed in March, April, and May 2015 is 2.76 m/s with wind direction blowing
to NE.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 32
The wind rose prepared from same data is shown at Figure 8.
FIGURE 8
WIND ROSE DIAGARM FOR PERIOD (MARCH TO MAY, 2015)
4.7 Social Infra structure
Population density and sex ratio of Bharuch District was reported 238 persons/sq.km. and
920 females per 1000 males respectively in 2011 census report. Total literacy of Bharuch
District was found 81.51 %.The basic amenities like primary and secondary education
schools, community health workers, primary health sub centre, private practitioners, primary
health centre, maternity and child welfare, dispensaries, T.B clinic, family welfare centre,
hospital, drinking water, transportation facilities, electricity , telephone etc. are available.
5.0 PLANNING BRIEF
5.1 Planning concept
Ankleshwar is largely an industrial area dominated by large scale industries, especially
chemical plants.
Now the unit has proposed to manufacture Anion resins and Cation resins.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 33
Ankleshwar in Gujarat has an industrial area with common effluent treatment plant, common
incinerator and land fill site. Govt. agencies provide many basic facilities like uninterrupted
water supply, power and road network.
5.2 Population projection
As per provisional reports of Census India, Population of Bharuch District in 2011 is
1,551,019. Population of male and female are 805,707 and 713,676 respectively. The sex
ratio of Bharuch city is 920 females per 1000 males.
In education section, total literates in Vadodara District are 2,893,080 of which 1,614,087 are
males while 1,278,993 are females. Average literacy rate of Vadodara district is 78.92%.
5.3 Land use planning
The proposed project is on a GIDC land.
5.4 Assessment of Infrastructure Demand
The M/s. Ion Exchange (India) Ltd. shall get water from GIDC water supply scheme. So
there will be no additional stress on ground water resources and there will be no adverse
effect on the ground water resources available in the nearby area.
The unit has proposed 700 KVA connected load form DGVCL. The transportation facilities
will also expect to improve due to increase in the movement of workers and raw material and
finished products.
5.5 Amenities/Facilities
The available basic amenities are as under:
(A) Education Facilities:
All the villages have a minimum of one primary school.
(B) Medical Facilities:
All the surrounding villages have medical facilities.
(C) Drinking water Facilities & Power Supply:
All the villages have potable water supply and in 100% area the drinking water is
supplied through taps, wells and tube wells. All the villages have power supply
facilities in the study region.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 34
(D) Post, Telegraph & Telephone facilities
The information collected clearly indicates that the infrastructural facilities are
provided by respective government agencies for the development of this area. For
communication purpose, post office and phones are available in most of the villages.
(E) Transport Facilities:
Bus services are available in all the villages of the study region within 5 km area and
are the most preferable mode of transport in the region. Auto-rickshaw is also used as
transport facility. Villages are connected with paved roads. All the surrounding area is
covered with 108 emergency facilities.
6.0 PROPOSED INFRASTRUCTURE
6.1 Processing Area
The process area will cover plant area, raw material storage area, hazardous waste storage
area, ETP and utilities. The process area covered by the unit at ground level will be 21009
sq.m.
6.2 Non Processing Area
The non process area will cover Admin Building, and security cabin. The non process area
covered by unit at ground level will be 3744 sq. m.
6.3 Green Belt Area
The existing green belt area is 8937 sq. m. and the proposed green belt area is 8937 sq. m.
6.4 Social Infrastructure
The availability of basic amenities is covered as under:
(A) Training & Education: All the employees will be trained and educated periodically
about the hazardous nature of chemicals used in the process. Also, training for
firefighting, work permit system, first aid, safe handling of hazardous chemicals and
integrating safety, in all activities.
(B) Medical facility: Pre-employment medical checkup at the time of employment. In order
to safe guard the health of the employees, all the employees undergo periodic health
checkup.
(C) Drinking water: There will be provision of Aqua Guard/R.O. at different places to
provide purified water for drinking purpose.
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 35
(D) Transportation: The unit will provide basic transportation facility for workers.
(E) Telegraph & Post: There will be provision of telephone, fax & internet facility.
(F) Power supply: There will be total connected load of 1600 KVA from DGVCL.
6.5 Connectivity
Ankleshwar estate is well connected by rail and road to rest of country.
6.6 Drinking water Management
Average daily water consumption of unit will be 8 KL/Day for domestic purpose. The entire
water requirement will be meeting through GIDC water supply system.
6.7 Sewage system
The sewage will be treated in soak pit.
6.8 Industrial waste management
The hazardous waste like Used Oil, Discarded Barrels, Liners, Insulation Waste and
Chemical Gypsum & Bio-Mass from Waste Water Treatment, Spent Resin/Fines Resin,
Spent Carbon, Wet Scrubber Residue and Spent Acid (H2SO4) will be generated from the
proposed activity. The hazardous waste management and disposal is shown in Annexure-IX.
6.9 Solid waste management
The record of hazardous and non Hazardous waste solid waste like Personal Protective
Equipments and Broken Glassware etc. will be mentioned.
6.10 Power requirement & supply
The unit will use total 1600 KVA electricity connected load from DGVCL. And 684 HP D.G.
sets will be provided.
7.0 Rehabilitation and Resettlement(R &R) Plan
The proposed project is located in Plot No: 5811·12·13, GIDC Estate, Ankleshwar, Dist-
Bharuch, Gujarat-393002. There will be no any human settlement affected by proposed
project.
8.0 Project Schedule & cost estimates
8.1 Project implementation Schedule
M/s. ION EXCHANGE (INDIA) LTD., ANKLESHWAR.
M/s. JYOTI OM CHEMICAL RESEARCH CENTRE PVT. LTD., ANKLESHWAR 36
TABLE: 17
PROJECT IMPLEMENTATION SCHEDULE
Project implementation schedule after getting NOC from GPCB
Sr.
No.
Activity Required Period
1. Civil work Immediately after getting NOC
2. Procurement of
machinery
1 month after getting NOC
3. Eraction & installation
of machinery
Immediately after competition of activity no.2
4. Trial of machinery &
equipment
Within 1 months after competition of activity no.3
5. Commercial activity 1 months after competition of activity no.4
8.2 Estimated project cost
Total project cost is Rs. 25 Crores for this proposed project.
9.0 Analysis of proposal
All the manpower is utilized from local region around Ankleshwar. Company shall also try to
provide indirect employment opportunities by availing local contract services during
transportation during operational phase.
The company intends to donate Rupees 47, 83,379 of the profit to agencies like NGOs or
social welfare societies for projects carried out in nearby village for their welfare and
upliftment.