55
Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October 11, 2019

Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

Project No. 49852, Review of Summer 2019

ERCOT Market Performance

ERCOT’s Review of Summer 2019

ERCOT Public

October 11, 2019

Page 2: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Key Observations for Summer 2019

• Early summer was mild, and August was very hot (September was also above

normal).

• There were many days with tight conditions, and an Energy Emergency Alert

(EEA) Level 1 was declared twice.

– Emergency Response Service (ERS) deployments prevented the need for EEA2.

• Peak demand day saw higher Intermittent Renewable Resource (IRR)

production.

– As a result, it was not one of the highest-priced days, and there was no EEA.

• Tightest conditions frequently occurred earlier than time of peak demand.

• Resource performance continues to outpace historical patterns.

• Overall, the market outcomes supported reliability needs.

• Even with significant pricing events, there were no mass transitions.

2

(Board slide 2)

Page 3: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Outline

• Summer overall

• Peak week

• Peak day

• EEA days

• Commercial information

3

(Board slide 3, modified)

Page 4: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Summer Overall

Page 5: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Weather

• June – July 2019 was the coolest since 2007*

• August 2019 was the 2nd hottest on record*

• Overall, June – August 2019 was 21st hottest on record

• Extended period of above normal heat in Texas – but not much

extreme heat (105 or greater)

5

• Comparison to 2018 differed

across the state

– Dallas cooler

– Austin/San Antonio similar

– Houston, South Texas hotter

• More heat along coast

*Based on mean temperature

(Board slide 4)

Page 6: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Daily Peak Hour Demands

6

40

45

50

55

60

65

70

75

801 3 5 7 9

11

13

15

17

19

21

23

25

27

29 1 3 5 7 9

11

13

15

17

19

21

23

25

27

29

31 2 4 6 8

10

12

14

16

18

20

22

24

26

28

30

June July August

GW

Higher demands

in August

June was

cool and wet

July was warm

and dry

(Board slide 5)

Page 7: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Comparison of Summer Monthly Peak Demand

• A new all-time record for

system demand peak was set

at 74,666 MW on Aug. 12,

2019.

• A new all-time record for

weekend system demand

peak was set at 71,915 MW

on Aug. 11, 2019.

• Monthly peak demands in

June and July 2019 were

lower than 2018.

7

* Data: Hourly integrated peak demand as published in the ERCOT D&E report.

67,6

33

69,5

12

67,8

89

69,1

23

73,4

73

69,9

19

68,1

59

70,8

55

74,6

66

-

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

June July August

MW

2017 2018 2019

(Board slide 6)

Page 8: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Day-Ahead Load Forecast Performance

8

June July August

Average

YTD

MAPE 2019

Average

Monthly

MAPE3.03 2.21 2.15

2.50

Lowest

Daily

MAPE in

Month

0.95 0.64 0.40

Highest

Daily

MAPE in

Month

9.62 4.55 9.00

• Mean Absolute Percent Error (MAPE) for ERCOT Mid-Term Load Forecast

(MTLF) at 14:00 Day-Ahead trended as normal on average.

Page 9: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

0

2000

4000

6000

8000

10000

12000

14000

16000

6/1

6/3

6/5

6/7

6/9

6/1

1

6/1

3

6/1

5

6/1

7

6/1

9

6/2

1

6/2

3

6/2

5

6/2

7

6/2

9

7/1

7/3

7/5

7/7

7/9

7/1

1

7/1

3

7/1

5

7/1

7

7/1

9

7/2

1

7/2

3

7/2

5

7/2

7

7/2

9

7/3

1

8/2

8/4

8/6

8/8

8/1

0

8/1

2

8/1

4

8/1

6

8/1

8

8/2

0

8/2

2

8/2

4

8/2

6

8/2

8

8/3

0

MW

2018 Wind 2019 Wind

2018 Peak

Day 7/19

2019 Peak

Day 8/12

Wind Output

• ERCOT had approximately 2,400 MWs of additional installed wind capacity

going into summer 2019 compared to 2018.

9

For hour ending 15:00

(Board slide 7)

Page 10: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Timing of Peak Load and Peak Net Load (Load-IRR)

10

12:00

13:00

14:00

15:00

16:00

17:00

18:00

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

June July August

Hour

Max Load Time Max Net Load Time

• During summer 2019, the peak net load frequently occurred prior to peak load.

• Net peak load occurred prior to 4 p.m. nearly 2/3 of the days in August.

Time is rounded to nearest 5-minute interval

(Board slide 8)

Page 11: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Minimum Wind Generation for June – August

11

• Looking at the minimum wind each day for each hour and taking the average,

the wind output was lower earlier in the afternoon and higher later in the

afternoon when compared to 2018.

0

1000

2000

12 13 14 15 16 17 18

Min

imu

m A

ve

rage

Win

d M

W

HE

Summer-19 Wind Min Summer-18 Wind Min

(Board slide 9)

Page 12: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Day-Ahead IRR Forecast Performance

12

June July August

Average

YTD

2019

Wind

Average

Monthly

MAPE4.1 4.1 4.7 4.9

Solar

Average

Monthly

MAPE

6.38 4.94 4.79 6.98

• Mean Absolute Percent Error (MAPE) for ERCOT wind and solar forecast

at 14:30 Day-Ahead trended as normal on average.

*Solar calculations are for all hours where solar production is greater than 5 MW

Page 13: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

COP Variance - September 2018 vs. 2019

13

For Hour Ending 1700

• Current Operating Plan (COP) – “A

plan by a QSE reflecting anticipated

operating conditions for each of the

Resources that it represents for each

hour in the next seven Operating

Days, including Resource operational

data, Resource Status, and Ancillary

Service Schedule.”

• COP variance shows the difference

between predicted online MWs as

reflected in the COPs and the actual

online MWs for thermal generators.

• The COP variance during the

Operating Day was higher in summer

2019, e.g., September.-18,000

-16,000

-14,000

-12,000

-10,000

-8,000

-6,000

-4,000

-2,000

0

2,000

DA11:00

DA12:00

DA13:00

DA14:00

DA15:00

OD5:00

OD6:00

OD7:00

OD8:00

OD9:00

OD10:00

OD11:00

MW

Hour

Submitted Average COP Variance

Sep-18

Sep-19

COP Variance = COP HSL – SCED HSL for online units and COP HSL – SCED MW for

startup and shutdown units. SCED values are time-weighted for the delivery hour.

Page 14: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Number of RUC Instructions Continued to Decrease

14

0

50

100

150

200

250

300

Capacity Congestion#

of H

ou

rs

Primary Driver for the Instruction

2017 to 2019 Effective RUC Resource-Hours

June through August

2017 2018 2019

• Noticeable trend toward self-

commitment during peak

periods.

• June instructions were all

extensions of self-committed

hours when the unit was

needed for congestion.

• August instructions (occurred

on two different days) were

driven by capacity shortage

and longer lead times.

Note: this does not include VDIs

(Board slide 11)

Page 15: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Operating Notices Issued in June – August 2019

15

• 8 Operating Condition Notices (OCNs) for reserve capacity shortage

• 25 Advisories due to Physical Responsive Capability (PRC) less than 3,000 MW

• 2 Watches due to PRC less than 2,500 MW

• 2 EEA Level 1 events

• 2 conservation requests during August EEAs

• 1 TCEQ Notice of Enforcement Discretion

– Effective for Operating Days 8/13-8/21

6/0

1

6/0

3

6/0

5

6/0

7

6/0

9

6/1

1

6/1

3

6/1

5

6/1

7

6/1

9

6/2

1

6/2

3

6/2

5

6/2

7

6/2

9

7/0

1

7/0

3

7/0

5

7/0

7

7/0

9

7/1

1

7/1

3

7/1

5

7/1

7

7/1

9

7/2

1

7/2

3

7/2

5

7/2

7

7/2

9

7/3

1

8/0

2

8/0

4

8/0

6

8/0

8

8/1

0

8/1

2

8/1

4

8/1

6

8/1

8

8/2

0

8/2

2

8/2

4

8/2

6

8/2

8

8/3

0

Operating Notices for June - August

Conservation PRC < 2500 OCN PRC < 3000 TCEQ

EEA1 EEA1

(Board slide 10)

Page 16: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Operating Notices Issued in September 2019

• 11 OCNs for reserve capacity shortage

• 4 Advisories due to PRC less than 3,000 MW

• 1 voluntary conservation request for Operating Days 9/5 and 9/6

• 2 TCEQ Notices of Enforcement Discretion

– 1 system-wide notice for Operating Days 9/5 and 9/6

– 1 notice for Permian Basin units for Operating Days beginning 9/25

16

9/0

1

9/0

2

9/0

3

9/0

4

9/0

5

9/0

6

9/0

7

9/0

8

9/0

9

9/1

0

9/1

1

9/1

2

9/1

3

9/1

4

9/1

5

9/1

6

9/1

7

9/1

8

9/1

9

9/2

0

9/2

1

9/2

2

9/2

3

9/2

4

9/2

5

9/2

6

9/2

7

9/2

8

9/2

9

9/3

0

Operating Notices in September

Conservation PRC < 2500 OCN PRC < 3000 TCEQ

Page 17: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Advisory for PRC < 3,000 MW on July 24, 2019

• Advisories for PRC < 3,000 MW were issued on several days (e.g. July 24).

• On these days, while PRC was low, there was non-frequency responsive

capacity (which does not contribute to PRC) and offline Quick Start Generating

Resource (QSGR) capacity still available.

17

0

5,000

10,000

15,000

20,000

25,000

Re

se

rve

s (

MW

)

July 24, 2019

RTOLCAP

PRC

Page 18: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Online Reserves Above PRC Due to Unfired Combined

Cycle Duct Capacity (NFRC) and Offline Quick Starts

18

0

2,500

5,000

7,500

10,000

12,500

15,000

17,500

On

line

Re

se

rve

s in

Exce

ss o

f P

RC

(M

W)

Online Reserves in Excess of PRC - July 24, 2019

Other

Differences Between MW and BP

Offline Quick Start Resources

Non-Frequency Responsive Capacity

Capacity > 20% of HSL - NFRC

Page 19: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Planned Transmission Outages

19

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

Jan Feb Mar Apr May Jun Jul Aug Sep

Count

of

# o

uta

ges a

ctive e

ach d

ay

Comparison 2018 vs. 2019Daily Count of All Transmission Outages

2018 2019

• Restrictions on summer transmission outages were again implemented to avoid planned

transmission outages that could require generation curtailment during high load periods.

• With longer lead time to adjust outage plans to meet the restrictions compared to 2018,

more maintenance and upgrade outages were approved, even during summer.

(Board slide 12)

Page 20: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Transmission Outages in Summer 2019

• There are impacts of meeting these restrictions, such as starting

outages very early in the day.

20

160

165

170

175

180

185

190

35

40

45

50

55

60

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Sp

rin

g O

uta

ge

Co

un

t

Su

mm

er

Ou

tag

e C

ou

nt

Hour Ending (HE)

Average Planned Transmission Outages

Summer Spring

Complete outages

before peak hours

during Summer

Outages start later

and are completed

after peak hours

Data only includes Line and Transformer Outages

Note: the y-axis scales are different to show detail

(Board slide 13)

Page 21: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Peak Week

Page 22: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Temperature Trend at Major Load Centers

• Temperatures at most major load centers between Aug. 12 and Aug. 16

were at or above 90th percentile levels in comparison with what these

regions have experienced in past summers (1950 thru 2019).

22

69,000

70,000

71,000

72,000

73,000

74,000

75,000

0102030405060708090

100

HE17 HE17 HE17 HE17 HE17

Mon, Aug 12 Tue, Aug 13 Wed, Aug 14 Thu, Aug 15 Fri, Aug 16

Lo

ad

(M

W)

Pe

rce

nti

le

Dallas/Fort Worth Houston Austin

San Antonio Brownsville Midland

Load

Page 23: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Difference of Load and Net Load Peak Times

23

14:5015:15

17:40 15:25

15:15

16:40 15:20 16:50

16:2516:25

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

8/12/2019 8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019

MW

Net Load Load MaxNet MaxLd

EEAEEA

8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019

Page 24: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Daily DC-Tie Schedule for August at Peak Hour

24

816 816

676

766

816 815 816 816 816 816 816 816 816 816

876

816

850

782

816 816 816

598

845816

854

816

669

455

816 816

866

0

100

200

300

400

500

600

700

800

900

1000A

ug-0

1

Au

g-0

2

Au

g-0

3

Au

g-0

4

Au

g-0

5

Au

g-0

6

Au

g-0

7

Au

g-0

8

Au

g-0

9

Au

g-1

0

Au

g-1

1

Au

g-1

2

Au

g-1

3

Au

g-1

4

Au

g-1

5

Au

g-1

6

Au

g-1

7

Au

g-1

8

Au

g-1

9

Au

g-2

0

Au

g-2

1

Au

g-2

2

Au

g-2

3

Au

g-2

4

Au

g-2

5

Au

g-2

6

Au

g-2

7

Au

g-2

8

Au

g-2

9

Au

g-3

0

Au

g-3

1

Additional 60 MW of

emergency energy provided

from CENACE

EEA1 events

Page 25: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Load Patterns – 13:00-20:00 on 8/12-8/16

25

8/12 (Peak)

8/13 (EEA)

8/14

8/15 (EEA)

8/16

64000

66000

68000

70000

72000

74000

76000

12 13 14 15 16 17 18 19

MW

Hour

8/12 (Peak) 8/13 (EEA) 8/14 8/15 (EEA) 8/16

(Board slide 25)

Page 26: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Preliminary Load Reduction Observations for Peak Week

26

• The information needed to accurately evaluate demand response during 2019 is not

yet available.

– Customer-level data is needed to evaluate the occurrence and load reductions in response to

various factors. Data and results for summer are expected to be available by December 2019.

• Reductions shown below are estimates of the total of all load reduction (including

ERS, 4CP and for high prices), calculated using regression baseline estimates of

ERCOT total load.

– Load reductions are small relative to the total load, so the accuracy of the load reduction

estimates is relatively low.

Date Characteristics Max RT Load

Zone SPP

Estimated HE 17 Load

Reduction

Aug. 12 Actual 4CP Day $6,537 2,500 MW

Aug. 13 EEA1/Near 4CP $9,159 3,100 MW

Aug. 14 - $1,807 200 MW

Aug. 15 EEA1 $9,053 1,800 MW

Aug. 16 Near 4CP $1,583 1,600 MW

(Board slide 26)

Page 27: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Aug. 12 – Peak Day

Page 28: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Peak Demand Day of Aug. 12

28

0

2

4

6

8

10

12

14

16

18

0

10

20

30

40

50

60

70

80

00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Win

d O

utp

ut

(GW

)

Po

wer

(GW

)

Delivery Hour

Nuclear Coal Gas Traditional Simple Cycle

Combined Cycle Wind Solar Diesel

Hydro Renewables Total Dispatch Wind Output

ERCOT “Peak” Hours

Page 29: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 12 – Peak Day

29

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

G, H

, a

nd

I (

MW

)

A, B

, C

, D

, E

an

d F

(M

W)

Hour Ending

Hourly Average Demand, Capacity, and Reserves on 8/12/2019

A: Outages B: Quick-Start Resources C: Off-Line

D: Renewable HSL E: Non-renewable HSL F: Load

G: PRC H: Wind I: Solar

PRC = 2300

(Board slide 14)

Page 30: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 12

30

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Hour Ending

Off-Line Resources and Resources on Outage on 8/12/2019

Outages Off-Line - Not Providing Non-Spin

Off-Line - Providing Non-Spin Quick-Start Resources

(Board slide 15)

Page 31: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

The Summer 2019 Seasonal Assessment of Resource

Adequacy (SARA) Values vs. Actuals at Peak Demand

31

Source: Final 2019 Summer SARA

*The totals for the Final 2019 Summer SARA column combine multiple rows into a single row in some cases.

(E.g., already in-service Thermal and Hydro Resources with planned Thermal and Hydro Resources).

**The outage information in this table was extracted on Sept. 16, 2019.

2019 Actual Peak

Demand (8/12/19)

Final 2019

Summer SARA* Difference

Total Resources, MW 80,098 78,930 1,168

Thermal and Hydro 64,401 65,526 (1,125)

Private Use Networks, Net to Grid 3,203 3,437 (234)

Switchable Generation Resources 2,837 2,726 111

Wind Capacity Contribution 7,447 4,898 2,549

Solar Capacity Contribution 1,394 1,405 (11)

Non-Synchronous Ties 816 938 (122)

Peak Demand, MW 74,666 74,853 (187)

Reserve Capacity, MW 5,432 4,077 1,355

Total Outages, MW 3,972 4,226 (254)

Extreme Outage Scenario 6,891

Capacity Available for Operating

Reserves, MW 1,460 (149) 1,609

**

Largest absolute difference

31(Board slide 16)

Page 32: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

EEA1 Days

Page 33: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Load, Wind, and Outage Differences – 8/12-8/13

33

Outages Shown are non-IRR Outages

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

65,000

66,000

67,000

68,000

69,000

70,000

71,000

72,000

73,000

74,000

75,000

8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019

Win

d a

nd O

uta

ges (

MW

)

Load (

MW

)

Load Wind Outages

At Time of Lowest Reserves

14:51 15:14 17:47 15:2015:18

(Board slide 17)

Page 34: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 13 – EEA1 Day

34

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

G, H

, a

nd

I (

MW

)

A, B

, C

, D

, E

an

d F

(M

W)

Hour Ending

Hourly Average Demand, Capacity, and Reserves on 8/13/2019

A: Outages B: Quick-Start Resources C: Off-Line

D: Renewable HSL E: Non-renewable HSL F: Load

G: PRC H: Wind I: Solar

PRC = 2300

(Board slide 18)

Page 35: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 13 – EEA1 Day

35

0

2,000

4,000

6,000

8,000

10,000

12,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Hour Ending

Off-Line Resources and Resources on Outage on 8/13/2019

Outages Off-Line - Not Providing Non-Spin

Off-Line - Providing Non-Spin Quick-Start Resources

(Board slide 19)

Page 36: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Aug. 13 EEA Level 1 Timeline

36

Time Events

05:00 Issued OCN for HE 14 to HE 18

13:50 Issued Advisory for PRC < 3,000 MW

14:46 Sent VDIs to 5 hydro units for HE17

14:55 Issued Watch for PRC < 2,500 MW

15:15 Issued EEA1 for PRC < 2,300 MW

15:16 Issued a public appeal for voluntary energy conservation

15:16 Deployed all 10-min and 30-min ERS (926 MW)

15:56 Recalled 10-min ERS (93 MW)

16:02 Re-deployed 30-min ERS

16:14 Recalled 30-min ERS

17:00 Cancelled EEA1

17:30 Cancelled Watch

18:00 Cancelled Advisory and OCN

Page 37: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

PRC on Aug. 13 – EEA1 Day

37

• ERCOT declared EEA Level 1 at 15:10 when the PRC was 2,156 MW.

• PRC was under 2,300 MW for 35 minutes.

• EEA Level 1 continued for 1 hour and 50 minutes until deployed resources

were recovered and reserves sustained an upward trend.

PRC=2300

PRC=1750

PRC=1000

45,000

50,000

55,000

60,000

65,000

70,000

75,000

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00

Lo

ad

(M

W)

PR

C (

MW

)

PRC (Load) PRC (Hydro) PRC (Generation) PRC (Wind) PRC (Total) Load (MW)

EEA Level 1

PRC < 2,300 MW

15:10 17:00

Minimum PRC:

2,025 MW @ 15:14

(Board slide 20)

Page 38: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Aug. 13 ERS Deployment

38

Deployment Instruction*Recall Instruction*

Start Sustained

Response Period*

• Fleet-wide, ERS deployment exceeded the obligation.

*Refers to ERS-30 only. All MW quantities include both ERS-30 and ERS-10.

Page 39: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Load, Wind, and Outage Differences – 8/12-8/15

39

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

65,000

66,000

67,000

68,000

69,000

70,000

71,000

72,000

73,000

74,000

75,000

8/12/2019 8/13/2019 8/14/2019 8/15/2019 8/16/2019

Win

d a

nd O

uta

ges (

MW

)

Load (

MW

)

Load Wind Outages

At time of lowest reserves

15:2014:51 15:14 15:1817:47

Outages shown are non-IRR outages

(Board slide 21)

Page 40: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 15 – EEA1 Day

40

0

2,000

4,000

6,000

8,000

10,000

12,000

14,000

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

G, H

, a

nd

I (

MW

)

A, B

, C

, D

, E

an

d F

(M

W)

Hour Ending

Hourly Average Demand, Capacity, and Reserves on 8/15/2019

A: Outages B: Quick-Start Resources C: Off-Line

D: Renewable HSL E: Non-renewable HSL F: Load

G: PRC H: Wind I: Solar

PRC = 2300

(Board slide 22)

Page 41: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Closer Look at Aug. 15

41

0

2,000

4,000

6,000

8,000

10,000

12,000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MW

Hour Ending

Off-Line Resources and Resources on Outage on 8/15/2019

Outages Off-Line - Not Providing Non-Spin

Off-Line - Providing Non-Spin Quick-Start Resources

(Board slide 23)

Page 42: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Aug. 15 EEA Level 1 Timeline

42

Time Events

05:00 Issued OCN for HE 14 to HE 18

13:30 Issued Advisory for PRC < 3,000 MW

15:00 Issued Watch for PRC < 2,500 MW

15:05 Declared EEA1 for PRC < 2,300 MW

15:05 Issued a public appeal for voluntary energy conservation

15:11 Deployed 30-min ERS (833 MW)

15:30 Sent VDI for emergency energy across the Railroad DC-Tie to ERCOT

15:53 Sent VDIs to keep two generators online for HE16 and HE17

16:54 Recalled all 30-min ERS

17:05 Terminated EEA1

17:15 Ended VDI for emergency energy across the Railroad DC-Tie

17:35 Cancelled Watch

18:00 Cancelled Advisory and OCN

Page 43: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

PRC on Aug. 15 – EEA1 Day

• ERCOT declared EEA Level 1 at 15:05 when the PRC was 2,245 MW.

• PRC was under 2,300 MW for 26 minutes.

• EEA Level 1 continued for 2 hours until deployed resources were recovered

and reserves sustained an upward trend.

43

PRC=2300

PRC=1750

PRC=1000

40,000

45,000

50,000

55,000

60,000

65,000

70,000

75,000

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

0:00 2:00 4:00 6:00 8:00 10:00 12:00 14:00 16:00 18:00

Lo

ad

(M

W)

PR

C (

MW

)

PRC (Load) PRC (Hydro) PRC (Generation) PRC (Wind) PRC (Total) Load (MW)

EEA Level 1

PRC < 2,300 MW

15:05 17:05

Minimum PRC:

2,134 MW @

15:18

(Board slide 24)

Page 44: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Aug. 15 ERS Deployment*

44

Deployment Instruction Recall Instruction

Start Sustained

Response Period

*Note: Weather sensitive and non-weather sensitive ERS-30 deployed

• Fleet-wide, ERS deployment exceeded the obligation.

Page 45: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Commercial Information

Page 46: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Day-Ahead Market (DAM)/Real-Time (RT) Price

Convergence

46

• On average, price convergence was within normal range over the summer.

• Day-to-day, significant volatility was observed.

Daily Average Unweighted Settlement Point Prices at ERCOT 345kV Hub Average

0

200

400

600

800

1000

1200

$/M

Wh

RT Settlement Point Price

DAM Settlement Point Price

Page 47: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Load Forecast for Sept. 5 and 6

47

• On both days, demand was lower than forecast due to lower than

expected temperatures.

67

68

69

70

71

72

73

74

75

DAM DRUC Midnight 8 a.m. Noon 4 p.m. Actual

GW

Reference -Peak on 8/12

HE 17 Forecasts vs. Actual

OD 9/5 OD 9/6

Page 48: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Record DAM Prices (Closer Look at Sept. 5 and 6)

48

• Day-Ahead Market (DAM) for Operating Day (OD) 9/5 had record prices.

– The RRS price was a result of a $6k offer plus ~$3k opportunity cost of energy.

• The overall increase in prices can be attributed to three things:

– Increase in both bid quantity and bid prices

– Prices in the offer stack increased earlier in the day compared to recent days

– Decrease in Ancillary Service quantities offered into the DAM

• DAM for OD 9/6 saw more RRS quantities offered in, though the energy bid/offer curves were similar

to OD 9/5. Therefore, energy prices were similar for the two days, but the RRS price was lower.

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

$/M

Wh

HE

OD 9/5/2019 – DAM System Lambda and AS MCPCs

SystemLambda REGUP REGDN RRS NSPIN

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24HE

OD 9/6/2019 – DAM System Lambda and AS MCPCs

SystemLambda REGUP REGDN RRS NSPIN

Page 49: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Day-Ahead and Real-Time (RT) Market Congestion Rent

49

$0

$20

$40

$60

Acro

ss Z

on

e

Housto

n

No

rth

So

uth

We

st

Acro

ss Z

on

e

Ho

usto

n

No

rth

So

uth

We

st

Acro

ss Z

on

e

Ho

usto

n

No

rth

So

uth

We

st

June July August

Co

ng

estio

n R

en

t ($

in

Mill

ion

s)

Summer 2019 Congestion Rent by Zone

Real-Time DAM

• In summer 2018 there was

significant congestion, as

well as CRR underfunding in

July and higher RT Revenue

Neutrality Allocation (RENA)

overall.

• Summer 2019:

– No CRR underfunding

– RENA down to ~$5M from

~$50M last summer

– 2019 RT congestion rent

totaled approx. $180M; for

2018, it was $350M

(Board slide 27)

Page 50: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Congestion Revenue Rights (CRRs) Cost vs. Value

50

0

20

40

60

80

100

120

140

160

180

200

Jun Jul Aug Jun Jul Aug Jun Jul Aug

2017 2018 2019

$ M

illio

ns

Cost Value

(Board slide 28)

Page 51: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Net Allocation to Load Increased in August Due to

Higher Ancillary Service Costs

51

(100)

(50)

-

50

100

150

200

250

300

June July August June July August June July August

2017 2018 2019

$ M

illio

ns

Ancillary Service Balancing Account Payout to Load CRR Auction Distribution

ERCOT Administrative Fee ERS Settlement Real-Time Ancillary Service Imbalance

Real-Time Revenue Neutrality Other Settlements Total Allocation to Load

(Board slide 29)

Page 52: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Collateral

52

• In July, Total Potential Exposure (TPE) and collateral calls increased due to significantly high

Forward Adjustment Factors, which are driven by Intercontinental Exchange (ICE) North Hub prices.

• In September, the increase in TPE and collateral calls was driven more by the increase in ERCOT

Real-Time and Day-Ahead prices.

Page 53: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Other Summer Observations

53

• Despite record prices, there were no mass

transitions.

– There was only one default of a Market Participant

(MP) with no load or generation (occurred in

September).

– On one occasion in September, ERCOT was

required to short-pay the market due to a MP’s

failure to pay an invoice. ERCOT drew from the

MP’s available financial security, refunded MPs and

no default occurred.

• The Credit Work Group is evaluating this event and

re-examining surety bonds as financial security.

• Switchable generation coordination agreements

enabled effective communications during EEAs.

• Distributed generation increased net output by an

estimated 150-200 MW during Aug. 12-16 peaks.

(Board slide 30)

Page 54: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Future Opportunities

• Filed NOGRR to clearly allow operators to deploy smaller amounts

of RRS at a time.

• Use event data to inform a review of ERS assumptions used for the

reliability deployment price adder, such as the 10-hour recall period.

• Continue to focus on Real-Time Co-optimization, while assessing

whether any improvements can be made to the existing processes

in the interim.

– RTC would have increased reliability and economic efficiency by:

• Improving the ability of SCED to dispatch NFRC ahead of frequency

responsive capacity to maintain higher levels of PRC and reduce the

duration of the two EEA1 events on Aug. 13 and 15.

• Allowing more efficient dispatch of lower-cost capacity that was reserved

behind the High Ancillary Service Limit (HASL) and procurement of AS from

higher-generating cost capacity during tight conditions.

• Reducing the number of ramp-constrained dispatch conditions.

54

Page 55: Project No. 49852, Review of Summer 2019 ERCOT Market …€¦ · Project No. 49852, Review of Summer 2019 ERCOT Market Performance ERCOT’s Review of Summer 2019 ERCOT Public October

ERCOT Public

Future Opportunities

• Consider changes to OCN issuance procedures.

• Discuss switchable generation scenarios and possible market

rule changes.

• Continue to work with gas generators and gas companies on

coordinated communication processes.

• Work with fossil fuel generators on gathering appropriate

emission limitation data to assist in enforcement discretion

requests.

• Complete summer demand response study by December

2019.

55