Prm minor_project.pdf.docx

Embed Size (px)

Citation preview

  • 8/10/2019 Prm minor_project.pdf.docx

    1/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A MINOR PROJECT

    ON

    COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT

    FORSTABILIZED AND UNSTABILIZED SOIL

    Submi tted to

    SANGHAVI INSTITUTE OF MANAGEMENT & SCIENCE,INDORE

    Institute of Technology and Management

    Rajiv Gandhi ProudyogikivVishwavidhyalayaBhopal (M.P.)

    2014-2015

    In The Partial fulfillment of Bachelor Degree in Civil Engineering

    Guided by: Submitted to: Submitted by:

    Er. Yogesh Sharma H O D CIVIL ParmanandPatidar

    BE VII Sem( Civil)Roll No: 0837CE111070

    RAJIV GANDHI PROUDYOGIKI VISHWAVIDHYALAYA,BHOPAL, (MP)

    SIMS,INDORE Page 1

  • 8/10/2019 Prm minor_project.pdf.docx

    2/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    SIMS,INDORE (2011-2015)

    CERTIFICATE

    This is to certify that the minor project entitled, COMPARATIVE STUDY

    BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    UNSTABILIZED SOIL Submitted by Mr.ParmanandPatidarinpartial

    fulfillment of the requirements for the award of bachelor of engineering degree in

    civil engineering under the subject minor civil engineering project at the

    RAJIV GANDHI PROUDYOGIKI VISHWAVIDYALAYA, BHOPAL.

    The work has been examined by us and recommended for acceptance.

    EXTERNAL EXAMINER INTERNAL EXAMINER

    DATE: DATE:

  • 8/10/2019 Prm minor_project.pdf.docx

    3/70

    SIMS,INDORE Page 2

  • 8/10/2019 Prm minor_project.pdf.docx

    4/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    ACKNOWLEDGMENT

    It is always a pleasure to remind the fine people in the Engineering Work u come

    to know for their sincere guidance I received to uphold my practical as well as

    theoretical skills in engineering.

    Mostly we would like to thank ER. Yogesh Sharma (Guide) for extending their

    friendship towards us and making a pleasure-working environment on the field and

    lab. A paper is not enough for me to express the support and guidance we received

    from them almost for all the work we did there. They were a great help not only on

    how work take place on field but also told some life learning experience they were

    blessed with.

    Secondly we would like to thank Prof. R P Pandey (HOD of Civil Engineering ) for

    giving opportunity for doing minor project.

    Thirdly we would like to thank ER. PushpendraSoni (Minor project co-ordinator)

    for the positive attitude he showed for our work, always allowing us to question

    him and giving prompt replies for our uncertainties in all the fields including

    educational, and managerial to practical work.

    Finally we apologize all other unnamed who helped us in various ways to have a

    good project.

    SIMS,INDORE Page 3

  • 8/10/2019 Prm minor_project.pdf.docx

    5/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    ABSTRACT

    India is an emerging economy and second faster growing country of the world and

    a developing country, Infrastructure is a key factor in the growth of each country,

    Infect it is a indicator that indicate how much a country is growing and at which

    rate.

    Transportation and road network is a major sector in the infrastructure. India

    a huge agricultural land and 65% of the population of country lives in rural areas,

    therefore it is very necessary to connect rural and urban areas for the socio

    economic growth of country.

    The village is only connected with fair weather road. If the said villages are

    connected with BT road by the approach road, the villages around the way will be

    economically benefited. The Villagers are mainly dependent on the agriculture and

    for proper transport and getting proper price of their produces, all weather road is

    necessary, A part from this, villagers will also get the facilities of good education

    and health. Therefore, to ensure socio-economic transforming breaking the

    isolation of village communities, elimination of disparity between rural and urban

    population and bringing about urban rural integration.

    SIMS,INDORE Page 4

  • 8/10/2019 Prm minor_project.pdf.docx

    6/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND2014 UNSTABILIZED SOIL

    CONTENT

    Page No.

    CHAPTER-1 INTRODUCTION 9

    1.1General 9

    1.2Pavement 10

    1.3Purpose Of Pavement 11

    1.4Selection Of Type Of Pavement 12

    1.5Selection Criteria 13

    1.6Factors For Comparing Flexible & Rigid Pavement 14-50

    1.7Considerations for Flexible vs. Rigid Pavements 51

    1.8 Soil Stabilization 52-53

    CHAPTER-2 EXPERIMENTAL PROGRAMME 54

    2.1Properties Of Soil 55-56

    2.2Particle Size Distribution (sieve analysis) 56-58

    2.3CBR Test 59-60

    CHAPTER-3 RESULTS 61-66

    CHAPTER-4 CONCLUSION 67-68

    REFERENCE 69

    SIMS,INDORE Page 5

  • 8/10/2019 Prm minor_project.pdf.docx

    7/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND2014 UNSTABILIZED SOIL

    LIST OF FIGURES

    Fig. 1 Typical Cross Section Of Flexible Pavement 14

    Fig. 2 . Layers Of Flexible Pavement 17

    Fig. 3 Typical Rigid Pavement 18Fig. 4 Layers Of Rigid Pavement 19

    Fig. 5 PCC Surface 20

    Fig. 6 Rigid Pavement Slab 21

    Fig. 7 Rigid Pavement Showing Contraction Joints 23

    Fig. 8 Skewed Contraction Joint 24

    Fig. 9 Construction Joint 25

    Fig.10 Longitudinal and Transverse Construction Joints 26

    Fig.11 Stainless Steel-Clad Dowel Bars 27

    Fig.12 Dowel Bars in Place at a Construction Joint 27

    Fig.13 CBR Curve For Flexible pavement Design 29

    Fig14 Thickness of crust required for different traffic 31

    Fig15 Thickness of crust required for different traffic 32

    Fig.16 Thickness of crust required for different traffic 34

    Fig.17 Flexible Pavement Load Distribution 43

    Fig.18 Rigid Pavement Load Distribution 45

    Fig.19 Stress Distribution In Flexible And Rigid 46

    Fig.20 Stress Distribution In Flexible And Rigid 47

    Fig 21 Pavements Stress Overlap Due to Dual Wheel 47

    Fig.22 Critical Line of Equal Costs (Swing Line) 50

    Fig.23 Variation of CBR w.r.t % of lime 65

    SIMS,INDORE Page 6

  • 8/10/2019 Prm minor_project.pdf.docx

    8/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND2014 UNSTABILIZED SOIL

    LIST OF TABLES

    Table 1 Cost of Flexible Pavements in Million Rupees for 48

    Different Combinations of Soil and Traffic

    Table 2 Cost of Rigid Pavements in Million Rupees for 49

    Different Combinations of Soil and Traffic

    Table 3 Stabilization methods for pavements (from rolling, 1996). 53

    Table 4 Observation of coarse sieving 57

    Table 5 Observation of fine sieving 58

    Table 6 Physical properties of various soils 62

    Table 7 Liquid limit (L.L.), plastic limit (P.L.), plasticity index (P.I.) 62

    at different percentage of lime.

    Table 8 variation of thickness of pavement for unstabilized soil 66

    Table 9 variation of thickness of pavement for stabilized soil 66

    SIMS,INDORE Page 7

  • 8/10/2019 Prm minor_project.pdf.docx

    9/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    CHAPTER 1

    INTRODUCTION

    SIMS,INDORE Page 8

  • 8/10/2019 Prm minor_project.pdf.docx

    10/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    INTRODUCTION

    1.1 GeneralThe two most important factors that govern pavement design are soil sub-grade strength and

    traffic loading. Depending on the strength of sub-grade soil, the layer thicknesses of flexible as

    well as rigid pavements are affected. IRC:37-20015 uses soil sub-grade strength in terms of CBR

    in flexible pavement; whereas IRC: 58 - 20026 uses the same in terms of modulus of sub-grade

    reaction (k) for rigid pavement. The traffic load is generally estimated from 3-day axle load

    survey. In the design of flexible pavements, traffic load is expressed in terms of million standard

    axles (msa); whereas it is expressed in terms of axle load distribution (ALD) in design of rigid

    pavements.

    The present study was undertaken in two parts. In the first part, mathematical models are

    developed to obtain the ALD on a highway from its vehicle volume count. The ability to convert

    the soil sub-grade strength given in terms of CBR into modulus of subgrade reaction (k), and a

    traffic load given in terms of msa into ALD makes it possible to design the two types of

    pavements for the same soil and traffic conditions expressed differently. In the second part,

    flexible and rigid pavements are designed for similar soil and traffic conditions and their costs

    are compared.

    SIMS,INDORE Page 9

  • 8/10/2019 Prm minor_project.pdf.docx

    11/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.2 PAVEMENT

    A pavement is usually a combination of several layers placed on top of an existing subgrade

    (usually soil) so that vehicle loads from traffic can be transmitted safely to the subgrade without

    failure or excessive damage (i.e., deformation, strain, cracking, rutting, etc.) that may affect the

    serviceability of the road during the design lifespan of the pavement.

    The two most important factors that govern pavement design are soil sub-grade strength and

    traffic loading. Depending on the strength of sub-grade soil, the layer thicknesses of flexible as

    well as rigid pavements are affected.

    SIMS,INDORE Page 10

  • 8/10/2019 Prm minor_project.pdf.docx

    12/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.3 PURPOSE OF PAVEMENT

    Typically, pavements are built for three main purposes:

    Load support:

    Pavement material is generally stiffer than the material upon which it is placed, thus it assists the

    in situ material in resisting loads without excessive deformation or cracking.

    Smoothness:

    Pavement material can be placed and maintained much smoother than in situ material. This helps

    improve ride comfort and reduce vehicle operating costs.

    Drainage:

    Pavement material and geometric design can effect quick and efficient drainage thus eliminating

    moisture problems such as mud and ponding (puddles).

    SIMS,INDORE Page 11

  • 8/10/2019 Prm minor_project.pdf.docx

    13/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.4 SELECTION OF TYPE OF PAVEMENT

    The types of pavement generally considered for new construction and rehabilitation in California

    are rigid, flexible and composite pavements. Rigid pavement should be considered as a potential

    alternative for all Interstate and other high traffic volume interregional freeways. Flexiblepavement should be considered as a potential alternative for all other State highway facilities.

    Composite pavement, which consists of a flexible layer over a rigid pavement have mostly been

    used for maintenance and rehabilitation of rigid pavements on State highway facilities.

    SIMS,INDORE Page 12

  • 8/10/2019 Prm minor_project.pdf.docx

    14/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.5 Selection Criteria

    Because physical conditions and other factors considered in selecting pavement type vary

    significantly from location to location, the Project Engineer must evaluate each project

    individually to determine the most appropriate and cost-effective pavement type to be used. Theevaluation should be based on good engineering judgment utilizing the best information

    available during the planning and design phases of the project together with a systematic

    consideration of the following project specific conditions:

    Pavement design life

    Traffic considerations

    Soils characteristics

    Weather (climate zones)

    Existing pavement type and conditionAvailability of materials

    Recycling

    Maintainability

    Constructibility

    Cost comparisons (initial and life-cycle)

    SIMS,INDORE Page 13

  • 8/10/2019 Prm minor_project.pdf.docx

    15/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6 FACTORS FOR COMPARING FLEXIBLE ANDRIGID PAVEMENT

    1.6.1 BASIC ELEMENTS OF PAVEMENT

    Flexible Pavement :-

    A flexible pavement structure is typically composed of several layers of material

    with better quality materials on top where the intensity of stress from traffic loads is high and

    lower quality materials at the bottom where the stress intensity is low. Flexible pavements can be

    analyzed as a multilayer system under loading.

    A typical flexible pavement structure consists of the surface course and underlying

    base and sub-base courses. Each of these layers contributes to structural support and drainage.

    When hot mix asphalt (HMA) is used as surface course, it is the stiffest (as measured by resilient

    modulus) and underlying layers are less stiff but are still important to pavement strength as well

    as drainage and frost protection

    Fig. 1 Typical Cross Section Of Flexible Pavement

    SIMS,INDORE Page 14

  • 8/10/2019 Prm minor_project.pdf.docx

    16/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    The Subgrade

    It is the natural in situ material. The top 500 mm of subgrade should be compacted to the

    desirable density near the optimum moisture content. This compacted subgrade may be the in-

    situ soil or a layer of selected material.

    The Base Course

    The base course is the layer of materialimmediately beneath the surface or binder course. It can

    be composed of crushed stone, crushed slag, or other untreated or stabilized materials.

    Sub-base Course

    The sub-base course is the layer of material beneath the base course. The reason that two

    different granular materials are used is for economy. Instead of using the more expensive base

    course material for the entire layer, local and cheaper materials can be used as a sub-base course

    on top of the subgrade. If the base course is opening graded, the sub-base course with more fines

    can serve as a filter between the subgrade and the base course. Sometimes the base course could

    be cemented (in rigid pavement).

    Prime Coat

    Itis an application of low-viscosity cutback asphalt to an absorbent surface, such as an untreated

    granular base on which an asphalt layer will be placed. Its purpose is to bind the granular base to

    the asphalt layer.

    Tack Coat

    It is a very light application of asphalt, usually asphalt emulsion diluted with water, used to

    ensure a bond between the surface being paved and the overlying course. It is important that each

    layer in an asphalt pavement be bonded to the layer below. Tack coats are also used to bond the

    asphalt layer to a PCC base or an old asphalt pavement. The three essential requirements of a

    tack coat are that it must be very thin; uniformly cover the entire surface to be paved is allowed

    to cure before the HMA is laid.

    SIMS,INDORE Page 15

  • 8/10/2019 Prm minor_project.pdf.docx

    17/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    The Seal Coat

    It is a thin bituminous layer used to waterproof the surface or to provide skid resistance where

    the aggregates in the surface course could be polished by traffic and become slippery.

    Asphalt/Bitumen

    Asphaltic bitumen is obtained by refining the petroleum crude. It is the costliest and a very

    important component of the bituminous mix. The applicability and adhesive properties of

    bitumen along with the proper proportioning with stone aggregates is the basic requirement to

    make workable layer mixes.

    SIMS,INDORE Page 16

  • 8/10/2019 Prm minor_project.pdf.docx

    18/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Layers of construction: section of 2 lanes

    Fig.2 Layers Of Flexible Pavement

    SIMS,INDORE Page 17

  • 8/10/2019 Prm minor_project.pdf.docx

    19/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Rigid Pavement:-

    Rigid pavement structure is composed of a hydraulic cement concrete surface course and

    underlying base and sub base courses (if used). Another term commonly used is Portland cement

    concrete (PCC) pavement, although with today's pozzolanic additives, cements may no longer be

    technically classified as "Portland".

    The surface course (concrete slab) is the stiffest layer and provides the majority of strength. The

    base or sub-base layers are orders of magnitude less stiff than the PCC surface but still make

    important contributions to pavement drainage and frost protection and provide a working

    platform for constructions equipment.

    Rigid pavements are substantially 'stiffer' than flexible pavements due to the high

    modulus of elasticity of the PCC material, resulting in very low deflection under loading. The

    rigid pavements can be analyzed by the plate theory. Rigid pavements can have reinforcing steel,

    which is generally used to handle thermal stresses to reduce or eliminate joints and maintain tight

    crack width. Figure shows typical section for a rigid pavement.

    Fig. 3 Typical Rigid Pavement

    SIMS,INDORE Page 18

  • 8/10/2019 Prm minor_project.pdf.docx

    20/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Layers of constructions

    Fig. 4 Layers Of Rigid Pavement

    A typical rigid pavement structure (see Figure 3) consists of the surface course and the

    underlying base and subbase courses (if used). The surface course (made of PCC) is the stiffest

    (as measured by resilient modulus) and provides the majority of strength. The underlying layers

    are orders of magnitude less stiff but still make important contributions to pavement strength as

    well as drainage and frost protection.

    SIMS,INDORE Page 19

  • 8/10/2019 Prm minor_project.pdf.docx

    21/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Surface Course

    The surface course is the layer in contact with traffic loads and is made of PCC. It provides

    characteristics such as friction (see Figure 2.3),smoothness, noise control and drainage. In

    addition, it serves as a waterproofing layer to the underlying base, subbase and subgrade. The

    surface course can vary in thickness but is usually between 150 mm (6 inches) (for light loading)

    and 300 mm (12 inches) (for heavy loads and high traffic). Figure 2.4 shows a 300 mm (12 inch)

    surface course.

    Figure 5 PCC Surface

    SIMS,INDORE Page 20

  • 8/10/2019 Prm minor_project.pdf.docx

    22/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Figure 6 Rigid Pavement Slab

    (Surface Course) Thickness

    The base course is immediately beneath the surface course. It provides (1) additional load

    distribution, (2) contributes to drainage and frost resistance, (3) uniform support to the pavement

    and (4) a stable platform for construction equipment. Bases also help prevent subgrade soil

    movement due to slab pumping. Base courses are usually constructed out of:

    1. Aggregate base. A simple base course of crushed aggregate has been a common

    option since the early 1900s and is still appropriate in many situations today.

    2. Stabilized aggregate orStabilizing agents are used to bind otherwise loose particles to

    one another, providing strength and cohesion. Cement treated bases (CTBs) can be

    built to as much as 20 - 25 percent of the surface course strength (FHWA, 1999).

    However, cement treated bases (CTBs) used in the 1950s and early 1960s had a

    tendency to lose excessive amounts of material leading to panel cracking and settling.

    SIMS,INDORE Page 21

  • 8/10/2019 Prm minor_project.pdf.docx

    23/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    3. Dense-graded HMA. In situations where high base stiffness is desired base courses

    can be constructed using a dense-graded HMA layer.

    4. Permeable HMA. In certain situations where high base stiffness and excellent

    drainage is desired, base courses can be constructed using an open graded HMA.

    Sub base Course

    The sub base course is the portion of the pavement structure between the base course and the

    subgrade. It functions primarily as structural support but it can also:

    1. Minimize the intrusion of fines from the subgrade into the pavement structure.

    2.

    Improve drainage.

    3. Minimize frost action damage.

    4. Provide a working platform for construction.

    The sub base generally consists of lower quality materials than the base course but better than the

    subgrade soils. Appropriate materials are aggregate and high quality structural fill. A sub base

    course is not always needed or used.

    Joints

    Joints are purposefully placed discontinuities in a rigid pavement surface course. The most

    common types of pavement joints, defined by their function ,are : contraction, expansion,

    isolation and construction.

    (a) Contraction Joints

    A contraction joint is a sawed, formed, or tooled groove in a concrete slab that creates aweakened vertical plane. It regulates the location of the cracking caused by dimensional changes

    in the slab. Unregulated cracks can grow and result in an unacceptably rough surface as well as

    water infiltration into the base, subbase and subgrade, which can enable other types of pavement

    distress. Contraction joints are the most common type of joint in concrete pavements, thus the

    generic term "joint" generally refers to a contraction joint.

    SIMS,INDORE Page 22

  • 8/10/2019 Prm minor_project.pdf.docx

    24/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Contraction joints are chiefly defined by their spacing and their method of load transfer. They are

    generally between 1/4 - 1/3 the depth of the slab and typically spaced every 3.1 - 15 m (12 - 50

    ft.) with thinner slabs having shorter spacing (see Figure 2.25). Some states use a semi-random

    joint spacing pattern to minimize their resonant effect on vehicles. These patterns typically use a

    repeating sequence of joint spacing (for example: 2.7 m (9 ft.) then 3.0 m (10 ft.) then 4.3 m (14

    ft.) then 4.0 m (13 ft.)). Transverse contraction joints can be cut at right angles to the direction of

    traffic flow or at an angle (called a "skewed joint"). Skewed joints are cut at obtuse angles to the

    direction of traffic flow to help with load transfer. If the joint is properly skewed, the left wheel

    of each axle will cross onto the leave slab first and only one wheel will cross the joint at a time,

    which results in lower load transfer stresses.

    Figure 7 Rigid Pavement Showing Contraction Joints

    SIMS,INDORE Page 23

  • 8/10/2019 Prm minor_project.pdf.docx

    25/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Figure 8 Skewed Contraction Joint

    (The Tinning is Perpendicular to the Direction of Travel While the Contraction Joint is skewed)

    (b) Expansion Joints

    An expansion joint is placed at a specific location to allow the pavement to expand without

    damaging adjacent structures or the pavement itself. Up until the 1950s, it was common practice

    in the U.S. to use plain, jointed slabs with both contraction and expansion joints (Sutherland,

    1956). However, expansion joint are not typically used today because their progressive closure

    tends to cause contraction joints to progressively open (Sutherland, 1956). Progressive or even

    large seasonal contraction joint openings cause a loss of load transfer particularly so for joints

    without dowel bars.

    (c) Isolation Joints

    An isolation joint is used to lessen compressive stresses that develop at T- and unsymmetrical

    intersections, ramps, bridges, building foundations, drainage inlets, manholes, and anywhere

    differential movement between the pavement and a structure (or another existing pavement) may

    take place (ACPA, 2001). They are typically filled with a joint filler material to prevent water

    and dirt infiltration.

    SIMS,INDORE Page 24

  • 8/10/2019 Prm minor_project.pdf.docx

    26/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    (d) Construction Joints

    A construction joint (see Figure 2.7) is a joint between slabs that results when concrete is placed

    at different times. This type of joint can be further broken down into transverse and longitudinal

    construction joints (see Figure 2.31). Longitudinal construction joints also allow slab warping

    without appreciable separation or cracking of the slabs.

    Workers manually insert dowel bars into the construction joint at the end of the work day.

    Construction joints should be planned so that they coincide with contraction joint spacing toeliminate extra joints.

    Figure 9 - Construction Joint

    SIMS,INDORE Page 25

  • 8/10/2019 Prm minor_project.pdf.docx

    27/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Figure 10 - Longitudinal and Transverse Construction Joints

    Dowel Bars

    Dowel bars are short steel bars that provide a mechanical connection between slabs without

    restricting horizontal joint movement. They increase load transfer efficiency by allowing the

    leave slab to assume some of the load before the load is actually over it. This reduces jointdeflection and stress in the approach and leave slabs.

    Dowel bars are typically 32 to 38 mm (1.25 to 1.5 inches) in diameter, 460 mm (18 inches) long

    and spaced 305 mm (12 inches) apart. Specific locations and numbers vary by state, however a

    typical arrangement might look like Figure 2.34. In order to prevent corrosion, dowel bars are

    either coated with stainless steel (see Figure 2.9) or epoxy (see Figure 2.36). Dowel bars are

    usually inserted at mid-slab depth and coated with a bond-breaking substance to prevent bonding

    to the PCC. Thus, the dowels help transfer load but allow adjacent slabs to expand and contract

    independent of one another. Figure 2.10 shows typical dowel bar locations at a transverse

    construction joint.

    SIMS,INDORE Page 26

  • 8/10/2019 Prm minor_project.pdf.docx

    28/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Figure 11 - Stainless Steel-Clad Dowel Bars

    Figure 12 -Dowel Bars in Place at a Construction Joint

    SIMS,INDORE Page 27

  • 8/10/2019 Prm minor_project.pdf.docx

    29/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Tie Bars

    Tie bars are either deformed steel bars or connectors used to hold the faces of abutting slabs in

    contact Although they may provide some minimal amount of load transfer, they are not designed

    to act as load transfer devices and should not be used as such Tie bars are typically used at

    longitudinal joints or between an edge joint and a curb or shoulder. Typically, tie bars are about

    12.5 mm (0.5 inches) in diameter and between 0.6 and 1.0 m (24 and 40 inches long).

    Reinforcing Steel

    Reinforcing steel can also be used to provide load transfer. When reinforcing steel is used,

    transverse contraction joints are often omitted Therefore, since there are no joints, the PCC

    cracks on its own and the reinforcing steel provides load transfer across these cracks. Unlikedowel bars, reinforcing steel is bonded to the PCC on either side of the crack in order to hold the

    crack tightly together.

    Typically, rigid pavement reinforcing steel consists of grade 60 (yield stress of 60 ksi (414 MPa)

    No. 5 or No. 6 bars The steel constitutes about 0.6 - 0.7 percent of the pavement cross-sectional

    area and is typically placed at slab mid-depth or shallower. At least 63 mm (2.5 inches) of PCC

    cover should be maintained over the reinforcing steel to minimize the potential for steel

    corrosion by chlorides found in deicing agents .

    SIMS,INDORE Page 28

  • 8/10/2019 Prm minor_project.pdf.docx

    30/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6.2 DESIGN OF PAVEMENT

    A. Design Of Flexible Pavement :-

    The thickness of pavement is designed on the basis of projected number of commercial

    vehicles for the design life using the current commercial vehicles per day and its growth rate.

    Further, it requires the sub grade strength value is term of CBR. It is expected that rural road

    will not have more than 450 CBPD in any case. The design chart given in Figure-3 may be

    referred to obtained the total pavement crust thickness (granular curst thickness) required

    over the sub-grade for the design life of the pavement. Based on the strength of granular

    materials the are used, the total design thickness is divided into base and sub base thickness.

    However any other higher type of bituminous layer can be part of the designed thickness.

    However, any other higher type of bituminous layer can be part of the designed thickness,

    with exception of thin bituminous surfacing (PMC, MSS, etc). In case of rural roads with low

    volume of traffic, structural layer bituminous mix and not be provided, generally except is

    very special cases where the traffic volume is so high that the design suggest it whole range

    of traffic and CBR that exist for rural roads in various States of the country have been

    considered and flexible pavement thickness catalogues are given in Figures-14,15,16 for

    ready reference.

    Fig.13: CBR Curve For Flexible pavement Design

    SIMS,INDORE Page 29

  • 8/10/2019 Prm minor_project.pdf.docx

    31/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A B C D

    A B C D

    SIMS,INDORE Page 30

  • 8/10/2019 Prm minor_project.pdf.docx

    32/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A B C D

    Sub Base Course Base Course Surfacing

    Fig 14: Thickness of crust required for different traffic

    A

    B

    C

    D

    SIMS,INDORE Page 31

  • 8/10/2019 Prm minor_project.pdf.docx

    33/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A B C D

    A B C D

    Sub Base Course Base Course Surfacing

    Fig 15: Thickness of crust required for different traffic

    SIMS,INDORE Page 32

  • 8/10/2019 Prm minor_project.pdf.docx

    34/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A B C D

    A B C D

    SIMS,INDORE Page 33

  • 8/10/2019 Prm minor_project.pdf.docx

    35/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    A B C D

    Sub Base Course Base Course Surfacing

    Fig 16: Thickness of crust required for different traffic

    TYPICAL CROSS-SECTION OF ROAD

    SIMS,INDORE Page 34

  • 8/10/2019 Prm minor_project.pdf.docx

    36/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    B. Design Of Rigid Pavement:-

    Design the following details of a plain cement concrete pavement for a two lane highway.

    (a)Pavement slab thickness

    (b)Dowel bars for expansion joints

    (c)Tie bars for longitudinal joints

    Follow the design procedure recommended by IRC where ever applicable. Use the given data,

    IRC load stress charts for edge and corner regions, and assume any other data not provided here.

    Width of expansion joint gap = 2.5 cm

    Maximum variation in temperature between

    summer and winter = 35 C

    Thermal coefficient of concrete = 10x10" per C

    Allowable tensile stress in CC during curing = 0.8 kg/cm

    Coefficient of friction = 1.5

    Unit weight of CC = 2400 kg/cm3

    Design wheel load - 5100 kg

    Radius of contact area = 15 cm

    Present traffic intensity, = 950 commercial vehicles/day

    Modulus of reaction of sub-base course = 8 kg/cm3

    Flexural strength (allowable flexural stress) of concrete = 40 kg/cm2

    E value of concrete = 3 x 105kg/cm

    2

    SIMS,INDORE Page 35

  • 8/10/2019 Prm minor_project.pdf.docx

    37/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    / \ivalue = 0.15

    Design load transfer through dowel system = 40%

    Permissible flexural stress in dowel bar = 1400 kg/cm2

    Permissible shear stress in dowel bar - 1000 kg/cm2

    Permissible tensile stress in steel (tie bar) = 1400 kg/cm2

    Permissible bond stress in deformed (tie bars) = 24.6 kg/cm2

    Temperature differential values in the region:

    Slab thickness, cm 15 20 25

    Temperature differential in slab in the region, C 14.6 15.8 16.3

    (a) Joint Spacing

    1joint 2.51.25cm2 2

    Spacing of expansion joint Ls

    1.25

    35.7m100C(T 100x10x10

    x35T )

    2 1

    which is less than maximum specified spacing of 140 m and so acceptable. Contraction joint

    spacing in plain CC,

    Lc=2S

    c

    x104

    2x0.8x1044.45m

    W.f 2400x1.5

    which is less than maximum specified spacing of 4.5 m and hence acceptable.

    Therefore provide contraction joints at 4.45 m spacing and expansion joints at every 8th such

    joints i.e., 4.45 x 8 = 35.5 m spacing (instead of 35.7 m)

    SIMS,INDORE Page 36

  • 8/10/2019 Prm minor_project.pdf.docx

    38/70

  • 8/10/2019 Prm minor_project.pdf.docx

    39/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Cx= 0.80 (from chart Fig. 7.25); Cyat Ly// of 4.29 = 0.6

    Temperature differential for 24 cm thick slab (by interpolation) = 16.2C

    Ste =1/2 x3x 105xl 0 x 10

    -6x 16.2x0.8 = 19.44 kg/cm

    2

    Residual strength at the edge

    = 40.0-19.44 = 20.56 kg/cm2

    Load stress at edge, using stress chart (Fig. 7.23)

    for h = 4,K = 8,Se=19.2kg/cm2

    Factor of safety available 20.56

    1.07which is safe and acceptable value19.2

    Therefore provide a tentative design thickness of 24 cm.

    Check for comer load stress : Using IRC stress chart Fig. 7.24, for h = 24, K = 8, the value of Sc

    = 23.0 kg per cm .

    Comer warping stress Ste=

    E.e.t. 1

    3(1 ) l

    3x155x10x10

    6x16.2

    15

    7.1kg/ cm2

    3(10.15) 81.53

    The worst combination of stresses at the comer is 23.0 + 7.1 = 30.1 kg/cm2, which is also less

    than the allowable flexural strength of 40 kg/cm and hence the design is safe.

    Adjustment for Trafficintensity Ad= P'[(l+r)]

    (n+20)

    Assuming a growth factor r = 7.5% and the number of years after the last count before the new

    pavement is opened to traffic, n = 3.

    Ad=9507.5 (n20)

    1 5013cv/ day100

    This traffic intensity being in the range > 4500, falls in group G and die adjustment factor is + 2

    cm.

    Therefore the revised design thickness of the slab

    = 24 + 2 = 26 cm (c)

    SIMS,INDORE Page 38

  • 8/10/2019 Prm minor_project.pdf.docx

    40/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    (c)Dowel bars

    Assume dowel bar diameter = 2.5 cm

    Joint width, 8 = 2.5 cm

    For Equal capacity in bending and bearing

    1F (L

    d 1.5)Ld =5d 1xF

    b (Ld 8.8) 1

    1400 L 1.5x2.5=5x2.5

    d

    100 Ld8.8x2.5

    By substituting different values of Ld by trials (as in Example 7.22), the value of Ldi found to be

    42.2 cm.

    Length of dowel bar = Ld+ = 42.2 + 2.5 = 44.7 cm Therefore provide 45 cmlong dowel bars of diameter 2.5 cm

    Actual value of Ld+ 45.0 - 2.5 = 42.5 cm Load transfer capacity of single

    dowel:

    P'(shear) = 0.785 d2Fs

    = 0.785 x 2.52x 1000 = 4906 kg

    2d2F 2x2.5

    5x1400

    P' (bending) 1 678kgLd8.8 42.5 8.8x2.5F .L .d 100x42.5 x2.5

    P' (baring) b d 781kg12.5(Ld1.5) 12.5(42.5 1.5x2.5)

    Taking the lowest value for design, P (design) =678 kg.

    Load capacity factor required:

    40

    Load capacity of the dowel group = 5100 x -----= 2040 kg

    100

    Capacity factor required = =3.0

    SIMS,INDORE Page 39

  • 8/10/2019 Prm minor_project.pdf.docx

    41/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Spacing of dowel bars :

    Radius of relative stiffness for revised slab thickness o 1 24 cm,

    3x105x26

    3 14

    l 86.6cm2)12x8(1 0.15

    Effective distance up to which there is load

    transfer = 1.8 /= 1.8x86.6 155.9 cm

    Assuming a trial spacing of 35 cm between the dowel bars, the capacity available for the group

    1 155.9 35

    155.9 70

    155.9 105

    155.9 140

    155.9 155.9 155.9 155.9

    = 2.77< the required value of 3.0.

    Assume dowel bar spacing of 30 cm.

    155.9-30155.9-60155.9-90 ,

    Capacity factor = 1 + ------- + ------ -----' ------------ +

    As this value is greater than the required capacity factor of 3.0, 30 cm spacing of the dowel bars

    is adequate. Therefore provide 2.5 cm dia. Dowel bars at expansion joints, of total length 45 cm

    at a spacing of 30 cm centres.

    (d) Tie Bars

    Area of steel .per metre length longitudinal joint,b.f.h.W 3.5x1.5x26x2400 , ,

    As=............... = .......................... = 2.34 cm2per m length

    100SSS100x1400

    Assuming 1 cm diameter of the bars, cross sectional area of each tie bar as =

    0.785cm2. Perimeter of the tie bar = 3.14cm

    Number of tie bars required per meter length of joint

    A

    s

    2.342.98as0.785

    Spacing of tie bar = -------------- = 33.5 cm

    Provide a spacing of tie bar, say 33 cm

    The length of tie bar may be increased by 5 cm for tolerance in placement.

    Therefore provide 1 cm diameter deformed tie bars, 34 cm in length at a spacing of 33 cm.

    SIMS,INDORE Page 40

  • 8/10/2019 Prm minor_project.pdf.docx

    42/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6.3 ADVANTAGES OF PAVEMENT

    Flexible pavement

    Load is transferred by grain to grain contact

    Force of friction is less deformation in the sub grade is not transferred to the upper layers.

    Expansion joints are not needed

    Road can be used for traffic within 24 hours

    No thermal stresses are induced as the pavement have the ability to contract and expand

    freely

    Have low completion cost

    Design is based on load distributing characteristics of the component layers

    Deformation in the sub grade is transferred to the upper layers

    Rigid pavement

    Design is based on flexural strength or slab action

    Have high flexural strength

    Deformation in the subgrade is not transferred to subsequent layers

    No such phenomenon of grain to grain load transfer exists

    Rolling of the surfacing in not needed

    Have low repairing cost

    Life span is more

    Surfacing can be directly laid on the sub grade

    No damage from oils and greases.

    SIMS,INDORE Page 41

  • 8/10/2019 Prm minor_project.pdf.docx

    43/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6.4 LIMITATIONS OF PAVEMENT

    Flexible pavement

    Have low flexural strength

    Surfacing cannot be laid directly on the sub grade but a sub base is needed

    Strength of the road is highly dependent on the strength of the sub grade

    Repairing cost is high

    Rolling of the surfacing is needed

    Have low life span

    Rigid pavement

    Thermal stresses are more vulnerable to be induced as the ability to contract and expand

    is very less in concrete

    Expansion joints are needed

    Strength of the road is less dependent on the strength of the sub grade

    Road cannot be used until 14 days of curing

    Force of friction is high

    Completion cost is high

    SIMS,INDORE Page 42

  • 8/10/2019 Prm minor_project.pdf.docx

    44/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6.5 LOAD DISTRIBUTION

    Flexible Pavement:-

    Flexible pavements are so named because the total pavement structure deflects, or flexes, under

    loading. A flexible pavement structure is typically composed of several layers of material. Each

    layer receives the loads from the above layer, spreads them out, then passes on these loads to the

    next layer below. Thus, the further down in the pavement structure a particular layer is, the less

    load (in terms of force per area) it must carry.

    Figure 17: Flexible Pavement Load Distribution

    In order to take maximum advantage of this property, material layers are usually arranged in

    order of descending load bearing capacity with the highest load bearing capacity material (and

    most expensive) on the top and the lowest load bearing capacity material (and least expensive)

    on the bottom. This section describes the typical flexible pavement structure consisting of:

    SIMS,INDORE Page 43

  • 8/10/2019 Prm minor_project.pdf.docx

    45/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Surface course. This is the top layer and the layer that comes in contact withtraffic. It

    may be composed of one or several different HMA sub layers.

    Base course. This is the layer directly below the HMA layer and generally consistsof

    aggregate (either stabilized or unstabilized).

    Subbase course. This is the layer (or layers) under the base layer. A subbase is

    notalways needed.

    Rigid Pavement:-

    Rigid pavements are so named because the pavement structure deflects very little under loading

    due to the high modulus of elasticity of their surface course. A rigid pavement structure is

    typically composed of a PCC surface course built on top of either (1) the subgrade or (2) an

    underlying base course. Because of its relative rigidity, the pavement structure distributes loads

    over a wide area with only one, or at most two, structural layers

    SIMS,INDORE Page 44

  • 8/10/2019 Prm minor_project.pdf.docx

    46/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Figure 18: Rigid Pavement Load Distribution

    This section describes the typical rigid pavement structure consisting of:

    Surface course. This is the top layer, which consists of the PCC slab.

    Base course. This is the layer directly below the PCC layer and generally consists

    ofaggregate or stabilized subgrade.

    Sub base course. This is the layer (or layers) under the base layer. A sub base is

    notalways needed and therefore may often be omitted.

    SIMS,INDORE Page 45

  • 8/10/2019 Prm minor_project.pdf.docx

    47/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Comparison:-

    The primary structural difference between a rigid and flexible pavement is the manner in

    which each type of pavement distributes traffic loads over the sub-grade. A rigid pavement has a

    very high stiffness and distributes loads over a relatively wide are of sub-grade a major portion

    of the structural capacity is contributed by the slab itself.

    Fig.19 Stress Distribution In Flexible And Rigid

    SIMS,INDORE Page 46

  • 8/10/2019 Prm minor_project.pdf.docx

    48/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Fig.20 Stress Distribution In Flexible And Rigid

    Fig. 21 Pavements Stress Overlap Due to Dual Wheel

    SIMS,INDORE Page 47

  • 8/10/2019 Prm minor_project.pdf.docx

    49/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.6.6 COSTING OF PAVEMENT

    Flexible Pavement

    The costs of different pavements are obtained by multiplying the volumes of materials by their

    respective costs. The costs of the different materials were calculated using 2006 schedule of rates

    for Dehradun district. Bageshwar Prasad2 used a maintenance cost of Rs 1.5 million for flexible

    pavements and the same was uniformly added to all the pavements in this study. Therefore, the

    costs computed in this study include both construction and maintenance costs. Table 3 gives the

    costs of flexible pavements designed for different combinations of soil CBR and traffic

    conditions. Fig shows the variation in cost of flexible pavements with respect to traffic loading.

    Equation relates the cost of flexible pavements with soil CBR and traffic loading.

    Cost = -16.98+12.136*CBR

    -0.3

    +15.476*msa

    0.10

    Table 1 Cost of Flexible Pavements in Million Rupees for Different Combinations of Soil

    and Traffic

    Soil Traffic Load(msa)

    CBR 1 2 3 5 10 20 30 50 100 150

    %

    2 7.12 8.49 9.09 10.67 12.60 14.29 15.25 16.32 18.00 18.85

    3 7.12 7.69 8.28 9.45 11.51 13.19 14.14 15.33 16.77 17.49

    4 5.80 7.18 7.76 9.17 11.01 12.33 13.29 14.58 16.14 16.74

    5 5.45 6.682 7.39 8.67 10.56 11.76 12.59 13.77 15.08 15.68

    6 5.17 6.53 7.11 8.26 10.03 11.23 11.94 12.88 14.07 14.78

    7 5.07 6.36 6.89 8.04 9.81 10.77 11.60 12.54 13.72 14.56

    8 5.07 6.36 6.82 7.83 9.59 10.56 11.27 12.20 13.39 14.22

    9 5.07 6.36 6.82 7.83 9.48 10.21 10.91 11.97 13.15 13.98

    10 5.07 6.36 6.82 7.83 9.48 10.21 10.80 11.62 12.91 13.75

    SIMS,INDORE Page 48

  • 8/10/2019 Prm minor_project.pdf.docx

    50/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Rigid Pavement

    The cost of construction and maintenance are considered in this study. The cost of sub-grade, dry

    lean concrete sub-base, pavement quality concrete slab, shoulders, dowel bars, and tie bars were

    computed as per 2006 schedule of rates for Dehradun district. Maintenance cost is adopted from

    a study made by Bageshwar Prasad2. The total cost of construction and maintenance costs for all

    the pavements are shown in Table 4. Fig. 10 shows the cost of rigid pavements against traffic

    loading for different values of sub-grade CBR. Equation 14 was developed using multiple

    regression analysis.

    Cost = 8.284 + 4.719 * CBR-0.9

    + 20.8 * msa0.15

    Table 2 Cost of Rigid Pavements in Million Rupees for Different Combinations of Soil and

    Traffic

    Soil Traffic Load (msa)

    CBR % 7 10 20 30 50 100 150

    2 13.32 13.92 13.92 14.54 14.85 15.15 15.15

    3 12.41 13.01 13.01 13.63 13.93 14.24 14.24

    4 12.15 12.74 12.74 13.36 13.36 13.66 13.96

    5 11.87 12.46 12.46 13.07 13.37 13.37 13.69

    6 11.87 12.19 12.48 13.09 13.09 13.39 13.39

    7 11.90 12.19 12.50 12.80 13.09 13.41 13.41

    8 11.61 12.21 12.21 12.82 12.82 13.11 13.41

    9 11.64 11.92 12.24 12.53 12.82 13.13 13.13

    10 11.36 11.95 11.95 12.53 12.53 12.84 13.13

    SIMS,INDORE Page 49

  • 8/10/2019 Prm minor_project.pdf.docx

    51/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    COMPARISON:-

    The design and cost computations for flexible and rigid pavements are discussed in Sections 3

    and 4 respectively. The initial aim of this study was to determine the threshold values of CBR

    and msa beyond which one of the pavements becomes economical in its combined construction

    and maintenance cost. The points of equal cost on the CBR vsmsa graph were determined using

    Equations 13 and 14 and these are plotted in Fig.11. Rigid pavements are found to be economical

    in the upper portion of the graph and flexible pavements are economical in the lower portion of

    the graph. Mathematically:

    If msa12.48+6.05 x CBR, rigid pavement will be economical;

    If msa=12.48+6.05 x CBR, both pavements will have the same cost.

    The above mathematical equation is developed by fitting a straight line to the points of equal

    costs. It has an R2 value of 0.998. The equation is valid for soil CBR values ranging from 2

    percent to 10 percent.

    Fig.22 Critical Line of Equal Costs (Swing Line)

    SIMS,INDORE Page 50

  • 8/10/2019 Prm minor_project.pdf.docx

    52/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.7 Considerations for Flexible vs. Rigid Pavements

    Explains how the state Departments of Transportation have begun to implement the

    practice of including rigid versus flexible pavement structure alternatives in construction plans in

    order to provide flexibility in contractor competition. Ideally, the inclusion of alternate pavementdesigns early in the bidding process would allow DOTs to achieve a best -value bid price, but

    there is concern that alternative pavement designs might not be truly equivalent. Several Life-

    Cycle Cost Analysis (LCCA) studies have been conducted in order to determine whether the

    alternate designs included in contracts will display comparable performance lives. In California,

    pavement design alternatives are analyzed for design lives of 10, 20, and 40 years, in order to

    determine the most cost-effective alternate pavement design life. Furthermore, the Colorado

    Department of Transportation recommends a 40-year analysis period when comparing flexible

    and rigid pavements, and the Alternate Design Alternate Bid (ADAB) procedure developed by

    the Louisiana DOT appears to have been adopted as standard industry practice. This protocol

    includes an analysis of general project information, an LCCA comparison of flexible and rigid

    pavement designs, and a final engineering project evaluation. Equivalent pavement designs

    should be considered for major highway projects, and projects with a high volume of trucks.

    why one pavement is used versus another. Basically, state highway agencies generally

    select pavement type either by policy, economics or both. Flexible pavements generally require

    some sort of maintenance or rehabilitation every 10 to 15 years. Rigid pavements, on the other

    hand, can often serve 20 to 40 years with little or no maintenance or rehabilitation. Thus, it

    should come as no surprise that rigid pavements are often used in urban, high traffic areas. But,

    naturally, there are trade-offs. For example, when a flexible pavement requires major

    rehabilitation, the options are generally less expensive and quicker to perform than for rigid

    pavements.

    SIMS,INDORE Page 51

  • 8/10/2019 Prm minor_project.pdf.docx

    53/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    1.8 SOIL STABILIZATION

    1.8.1Type Of stabilization

    Remove and replace

    Lime Piles Mechanical stabilization

    Admixture Stabilization (cement, lime, fly ash,bituminous)

    1.8.2Pavement Performance (Lime-Stabilized Subgrades and Base/Sub base Layers)

    The material properties of both lime-stabilized soils and lime-stabilized aggregates, as related to

    their impact on overall pavement performance, can be divided into four categories (Little, 1999):

    StrengthThe most obvious improvement in a lime-reactive soil or aggregate is strength

    gain over time. The various strength parameters impacted by the pozzolanic reactions that

    occur include unconfined compressive strength, tensile strength, flexural strength, and

    CBR

    Resilient modulus/stiffnessConcurrent with the strengthening of a soil brought about by

    pozzolanic reactions, are changes in the stressstrain relationship of the material . Lime-

    stabilized soils fail at much higher deviator stresses than their no stabilized counterparts,

    and at a much lower strain (typically about 1 percent strain for the stabilized mixture

    versus about 3 percent for the no stabilized material). Materials tested in the laboratory

    (repeated-load triaxial and indirect tensile tests) and in the field (impulse deflection

    testing, vibrational testing) both confirm significant increases over time in the resilient

    properties of lime-treated materials

    Fracture and fatigueFlexural fatigue strength is related to the number of loads that can be

    carried by a material at a given stress level, and it is an important consideration in theevaluation of limesoil and limeaggregate mixtures. The strength-gain effects produced

    by pozzolanic reactions are often substantial for reactive soils.

    DurabilityThe ability of lime-stabilized materials to resist the detrimental effects of

    moisture and freeze-thaw cycling over time has been evaluated in several ways, in both

    SIMS,INDORE Page 52

  • 8/10/2019 Prm minor_project.pdf.docx

    54/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    the laboratory and the field. The results of these evaluations have often shown only slight

    detrimental effects of environment on the levels of strength/stiffness produced by the

    addition of lime.

    Table 3. Stabilization methods for pavements (from rolling, 1996).

    Method Soil Effect Remarks

    Blending Moderately None Too difficult to mixplastic

    Others Improve gradation

    Reduce plasticity

    Reduce breakage

    Lime Plastic Drying Rapid

    Immediate strength gain Rapid

    Reduce plasticity Rapid

    Coarsen texture Rapid

    Long-term pozzolanic Slow

    cementing

    Coarse with Same as with plastic soils Dependent on quantity of

    fines plastic fines

    Non plastic None

    Cement Plastic Similar to lime Less pronounced

    Cementing of grains Hydration of cement

    Coarse Cementing of grains Hydration of cement

    Bituminous Coarse Strengthen/bind, Asphalt cement or liquidwaterproof asphalt

    Some fines Same as coarse Liquid asphalt

    Fine None Can't mix

    Pozzolanic and Silts and coarse Acts as a filler Denser and strongerSlags

    Cementing of grains Slower than cement

    Misc. methods Variable Variable Depends on mechanism

    SIMS,INDORE Page 53

  • 8/10/2019 Prm minor_project.pdf.docx

    55/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    CHAPTER 2

    EXPERIMENTAL PROGRAMME

    SIMS,INDORE Page 54

  • 8/10/2019 Prm minor_project.pdf.docx

    56/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    2.1 SOIL PROPERTIES

    2.1.1 Water Content/Moisture Content (w)

    w = *100

    w = * 100

    2.1.2 Degree Of Saturation (s)

    S = * 100

    0 < S < 100%

    2.1.3 Void Ratio (e)

    e = * 100

    2.1.4 Porosity (n)

    n = * 100

    0 < n < 1

    2.1.5 Air Content (a)

    a =

    a + S = 1

    2.1.6 Specific Gravity (G)

    G=

    2.1.7Density 2.1.7.1

    Bulk Density

    t =

    SIMS,INDORE Page 55

  • 8/10/2019 Prm minor_project.pdf.docx

    57/70

  • 8/10/2019 Prm minor_project.pdf.docx

    58/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    2.2 PARTICLE SIZE DISTRIBUTION (Sieve analysis)

    2.2.1 Coarse Sieving

    Sieves having square opening are arranged there decreasing size from top to bottom. The sieve

    used are80mm , 20mm , 10mm ,&4.75mm the sample is shaken for 10min by hands

    Table 4 Observation of coarse sieving

    S.no Sieve no. Mass retain % Retain % Cumulative % passing

    (gms) retain

    1. 80mm 0 0 0 100%

    2. 40mm 470gm 9.40 9.40 90.60

    3. 20mm 925gm 18.50 27.90 72.10

    4. 10mm 1412gm 28.24 56.14 43.60

    5. 4.75mm 976gm 19.50 75.64 24.36

    6. Pan 1219gm 24.36 100 0

    SIMS,INDORE Page 57

  • 8/10/2019 Prm minor_project.pdf.docx

    59/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    2.2.2 Fine Sieving

    The particles passing from 4.75m sieve are further analyzed and the sieve of 2mm , 1mm, 6oo,

    425, 212, 150, 75 are arranged in decreasing order.

    Table 5 Observation of fine sieving

    S.no Sieve no. Mass retain % Retain % Cumulative % passing

    (gms) retain

    1. 2mm

    2. 1mm

    3. 600

    4. 425

    5. 212

    6. 150

    7. 75

    8. Pan

    SIMS,INDORE Page 58

  • 8/10/2019 Prm minor_project.pdf.docx

    60/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    2.3 CBR TEST

    INTRODUCTION

    The California Bearing Ratio, believe it or not, was developed by The California State HighwaysDepartment.It is in essence a simple penetration test developed to evaluate the strength of roadsubgrades. CBR-value is used as an index of soil strength and bearing capacity. This value isbroadly used and applied in design of the base and the sub-base material for pavement.

    THE BASIC CBR TESTThis consists of causing a plunger of standard area to penetrate a soil sample, (this can be in the

    laboratory or on site). The force (load) required to cause the penetration is plotted against

    measured penetration, the readings noted at regular time intervals.

    This information is plotted on a standard graph, and the plot of the test data will establish the

    CBR result of the soil tested.

    THE REASON FOR THE CBR TEST

    It sounds complicated, but the basis behind it is quite simple.

    We are determining the resistance of the subgrade, (i.e. the layer of naturally occurring material

    upon which the road is built), to deformation under the load from vehicle wheels.

    Even more simply put, ''How strong is the ground upon which we are going to build the road''.

    The stronger the subgrade (the higher the CBR reading ) the less thick it is necessary to design

    and construct the road pavement, this gives a considerable cost saving.

    Conversely if CBR testing indicates the subgrade is weak (a low CBR reading) we must

    construct a suitable thicker road pavement to spread the wheel load over a greater area of the

    weak subgrade in order that the weak subgrade material is not deformed, causing the road

    pavement to fail.

    CBR VALUE SUBGRADE STRENGTH COMMENTS

    3% and less Poor " Capping is required

    3%- 5% NormalWidely encountered CBR range cappingconsidered according to road category

    5%- 15% Good"Capping" normally unnecessary except on veryheavily trafficked roads.

    SIMS,INDORE Page 59

  • 8/10/2019 Prm minor_project.pdf.docx

    61/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    2.3.1 CBR of unstabilized soil

    CBR-values of untreated compacted soils need to be interpreted in the context of the general

    relationship between the CBR-values and the consistency (quality) of the soils used in pavement

    applications (Bowles, 1992). CBR-values ranging from 3 to 7% are considered as a poor to fairconsistency.

    2.3.2 CBR of stabilized soil

    Soil-lime mixtures of the three tested soils were prepared at the optimum lime content,

    2%, and 4% above the optimum lime content and cured for 7 days.

    The addition of the optimum lime content led to an increase in the CBR-values for the three

    tested soils. The lime-tertiary clay mixtures have the highest CBR-values, whereas the lime-

    weathered soil mixtures have the lowest values. The reactivity of the tertiary clay with lime is

    stronger than the reactivity of both the weathered soil and the organic silt. The CBR -values of

    lime-tertiary clay mixtures increased slightly with increasing lime content (2 and 4% above the

    optimum lime content).

    SIMS,INDORE Page 60

  • 8/10/2019 Prm minor_project.pdf.docx

    62/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    CHAPTER 3

    RESULTS

    SIMS,INDORE Page 61

  • 8/10/2019 Prm minor_project.pdf.docx

    63/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Table 6 Physical properties of various soils

    S. Properties Banga Garshankar Nawanshahar

    No. Garshankar road Nawanshahar road Phagwara road soilsoil soil

    1. Plasticity Clay of low Plasticity Clay of low Plasticity Clay of low plasticity

    2. Specific gravity (G) 2.58 g/cm3 2.40 g/cm3 2.55 g/cm3

    3. Liquid limit L. L 32.5% . 27% 31%

    4. Plastic limit P. L. 14.5% 18% 17%

    5. Plasticity index P. I. 18% 9% 14%

    6. Optimum moisture

    Content (OMC) 14% 14% 12%

    7. Maximum dry density 1.72 g/cm3 1.68 g/cm3 1.75 g/cm3

    Table 7. Liquid limit (L.L.), plastic limit (P.L.), plasticity index (P.I.) atdifferent percentage of lime

    S. No. Percentage of Banga- Garshankar Nawanshahar-

    Lime Garshankar Nawanshahar PhagwaraRoad soil road soil road soil

    L.L. P.L. P.I. L.L. P.L. P.I. L.L. P.L. P.I.

    1 0 32.0 18.0 14.0 27.0 18.0 9.0 31.0 17.0 14.0

    2 1 32.8 26.0 6.8 33.0 27.0 6.0 31.3 24.0 7.3

    3 2 33.0 29.0 4.0 36.0 30.5 5.5 31.5 28.0 3.5

    4 3 33.0 30.5 2.5 36.5 31.5 5.0 31.5 29.5 2.0

    5 4 33.0 31.0 2.0 36.9 32.2 1.7 31.5 30.0 1.5

    SIMS,INDORE Page 62

  • 8/10/2019 Prm minor_project.pdf.docx

    64/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    3.2 Benefits of stabilization

    Lower material costs

    when soil stabilization is taken into account during the pavement design, a significant

    reduction in the required amount of base thickness and pavement surface materials willresult

    Lower construction costs

    when compared to traditional methods of complete removal and replacement or

    traditional undercuts, a cost savings of 30 to 50 percent may be achieved

    Reduced logistics costs and increased environmental responsibility

    stabilizing the existing soil eliminates the need to export the poor undesirable soils or

    import new usable fill material

    Increased strength

    a dramatic increase in CBR (California Bearing Ratio) can be achieved, changing

    unstable CBR values of 7 or less into highly stable CBR values

    Longer durability

    stabilized soil is highly resistant to water and frost (often the main causes of pavement

    failure), which increases the lifespan of the subgrade

    Safer operations

    the improved soil surface reduces the risks associated with persons slipping and falling,

    vehicles skidding, collisions and other accidents; emergency vehicles are able to travel

    the finished subgrade without restraint

    More reliable construction

    stabilized fills are less likely to suffer trench cave-ins and undesirable shifting of

    construction elements

    SIMS,INDORE Page 63

  • 8/10/2019 Prm minor_project.pdf.docx

    65/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Greater convenience

    in many circumstances, roads that are stabilized do not have to be shut down to traffic;

    even before they are paved, stabilized soil surfaces support foot and vehicle traffic, which

    helps to virtually eliminate complaints from nearby residents, employees and visitors

    3.2.1 Analysis of results for physical properties of soil with lime stabilization

    It is observed from Table 2 that with increase in lime content, optimum moisture

    content increases and maximum dry density decreases

    The liquid and plastic limit increased sharply for all the samples with lime content up to

    2 per cent and the increase was negligibly small beyond 2 per cent lime content.

    SIMS,INDORE Page 64

  • 8/10/2019 Prm minor_project.pdf.docx

    66/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    3.3 Effects on CBR value due lime stabilization

    3.3.1 CBR of Soil +20% lime

    The results of CBR tests for soil with 20% lime for three samples at different compaction efforts

    (10, 30 and 65 blows. By plotting the results as discussed earlier, the CBR value is determined

    at 25 blows to be 15.

    3.3.2 CBR of Soil +30% lime

    The results of CBR tests for soil with 30% lime for three samples at different compaction

    efforts (10, 30 and 65 blows). By plotting the results as discussed earlier, the CBR value is

    determined at 25 blows to be 18.

    Fig 23 Variation of CBR w.r.t % of lime

    SIMS,INDORE Page 65

  • 8/10/2019 Prm minor_project.pdf.docx

    67/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    Table 8. Variation of thickness of pavement for unstabilized soil

    Table 9. Variation of thickness of pavement for stabilized soil

    SIMS,INDORE Page 66

  • 8/10/2019 Prm minor_project.pdf.docx

    68/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    CHAPTER 4

    CONCLUSION

    SIMS,INDORE Page 67

  • 8/10/2019 Prm minor_project.pdf.docx

    69/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    It is observed with increase in lime content, optimum moisture content increases

    and maximum dry density decreases.

    The liquid and plastic limit increased sharply for all the samples with lime content upto

    2 per cent and the increase was negligibly small beyond 2 per cent lime content.

    The problem of settlement of roads is prevalent due to soil stabilization.

    If CBR value is found maximum without stabilization flexible pavement provided as

    for economically.

    If CBR value is found minimum without stabilization rigid pavement provided as

    for good strength and economically.

    If the soil is stabilized than the problem for settlement is prevents for any type

    of pavement.

    For required thickness of soil 2% of lime is required for addition.

    Soil properties have been improved with soil stabilization.

    Permeability decreased.

    Improvement in soil properties by adding Lime.

    Effect of lime is less for cohesion less soils.

    Curing Period increase in fatigue life up to 4 to 6 weeks of curing.

    The road constructed with enzyme stabilized soil has monitored for its performance at

    regular interval for 8-10 months. The road is performing well and field CBR test

    indicates that stabilized soil can be used as sub base material very effectively. But prior

    laboratory study is necessary to get the good result in the field

    Geotechnical properties of soil are increasing by stabilization of soil.

    SIMS,INDORE Page 68

  • 8/10/2019 Prm minor_project.pdf.docx

    70/70

    November 1, COMPARATIVE STUDY BETWEEN FLEXIBLE AND RIGID PAVEMENT FOR STABILIZED AND

    2014 UNSTABILIZED SOIL

    References

    http://www.civil.iitb.ac.in/~dns/IACMAG08/pdfs/N13.pdf

    Research paper- Jordan Journal of Civil Engineering, Volume 6, No. 1, 2012

    Research paper- highway research journal Vol 5 - No 2.

    Research paper- Comparative Study of Flexible and Rigid Pavements For Different

    Soil and Traffic Conditions.

    Indian Standard handbook for civil engineers by: Khanna

    HIGHWAY ENGINERRING BY : S.K. Khanna, C.E.G. Justo

    Highway material testing laboratory manual by: S.K. Khanna

    Ministry of Road Transport And Highway 4th Revised Publish By IRC (New

    Delhi) 2001.

    ER.Yogesh Sharma

    ER. Pushpendra Sir