34
Presentation Title Presentation Title Presentation Title Presentation Title The Hooley Cutting Stabilisation Project YGG – Geotechnics in the Rail Industry Andrew J O’Donovan - BAM Ritchies

Presentation Title YGG – Geotechnics in the Rail Industry · 2019. 11. 19. · −Protected species of Roman Snail. History • Two adjacent cuttings • 10-miles north of Gatwick

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Presentation TitlePresentation TitlePresentation TitlePresentation TitleThe Hooley Cutting Stabilisation Project

    YGG – Geotechnics in the Rail Industry

    Andrew J O’Donovan - BAM Ritchies

  • Introduction

    • Why is this project relevant to the future of rail?• Background to the project• Design and Methodology Development

    – Feasibility and Options• Implementation

    – Enabling works– Main scheme– Resident interaction

    • Safety and the Public• Innovation and Best Practice• Lessons learnt for the future

  • Project Teamand Stakeholders• Customer – Network Rail• Main Contractor – BAM – an integrated delivery team of

    BAM Nuttall Rail and specialist ground engineering contractor BAM Ritchies

    • Designer – Arup• Principal stakeholders

    − Travelling public including Gatwick Airport passengers

    − Train operating companies− Local residents− Local businesses including adjacent petrol station− Protected species of Roman Snail

  • History• Two adjacent cuttings

    • 10-miles north of Gatwick

    • Built c.1850

    • 30m deep

  • Ground Investigation• 21nr BH; rotary follow-on up to 30m

    • Rope access face inspection

    •Window Samples and Trial pits

  • Ground Investigation

  • Feasibility Study

    Dry Valley GravelsDry Valley GravelsDry Valley GravelsDry Valley Gravels

  • Enabling Works

    • Nine day Christmas blockade

    • 1000 lin-m of temp catch fence

    • 260 lin-m of scaffold deck

    • Improvements to RRV access point at the nearby mud flats

  • Main Works• 14,000m3 excavation• 55,000 lin m of drilling

    – 3 types of drill rig• Beam and Grillage

    – 220m3 spray concrete• Upside crest beam• 18,0002 meshing• Auxiliary works

    – Demolition of two properties

    – upper catch fence– removal of enabling works– reinstate 24nr gardens

  • Partial rePartial rePartial rePartial re----grading, soil nailing and mesh facinggrading, soil nailing and mesh facinggrading, soil nailing and mesh facinggrading, soil nailing and mesh facing

    Soil nailing and mesh facing

    Scheme Design

  • Area 1 - Tunnel Houses (up-line)

  • Upside crest view north

    Upside crest looking north

  • Section 2 - Esso Houses (up-line)

  • Construction – Upside

    Upside crest view north

    Upside crest view south

  • Section 3 - Beam & Grillage

  • New beam and grillage

    New beam and grillage

  • New beam and grillage

    New beam and grillage

  • Previous Beam and Grillage Construction 2001

  • Section 4 – Central Spine (down-line)

  • Section 4 – Excavation and re-grade

  • View north to spine

    View south from spine

  • Construction Issues

    THE ROMAN SNAIL!THE ROMAN SNAIL!THE ROMAN SNAIL!THE ROMAN SNAIL!

  • • One team approach• Collaborative working• Observation cards from all on site• Safety committee meeting• Joint NR safety tours• Refined look-out system• Emergency procedure

    – abseil rescue– line protection procedure

    • High risk activities– operational railway– plant movements– working at height

    Safety

  • • Steep slope working• Lightweight plant and equipment• High output plant• Methodologies• Latest high strength meshes• Training and safe systems• Use of sprayed concrete for Beam and Grillage• Bespoke temporary safety barriers to protect track and trains• Improved look-out system

    Innovation and Best Practice

  • • Collaboration between Customer, Main Contractor and Designer makes for a better project

    • One team approach provides for a integrated solution• Carefully developed safe systems of work enable work to be

    undertaken while train operations continue as normal • Using modern advanced materials enable a ‘Do and forget’

    approach• Use of active high strength materials rather than containment

    materials• Everyone buying into a common safety regime leads to

    improvements• Consideration of whole life costings essential on critical

    structures especially on high use lines

    Lessons Learnt

  • Presentation TitlePresentation TitlePresentation TitlePresentation Title

    Thank you for your timeThank you for your timeThank you for your timeThank you for your time