Prefeasibility Report Page 1 INDEX S.NO DESCRIPTION PAGE NO. 1. EXECUTIVE SUMMARY 02 2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 03 3. PROJECT DESCRIPTION 05 4. SITE ANALYSIS 15 5. PLANNING BRIEF 18 6. PROPOSED INFRASTRUCTURE 18 7. REHABILITATION AND RESETTLEMENT(R&R PLAN) 18 8. PROJECT SCHEDULE AND COST ESTIMATES 18 9. ANALYSIS OF PROPOSAL (FINAL RECCOMDATION) 18

Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

  • Upload
    lamnhu

  • View
    217

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 1

INDEX

S.NO DESCRIPTION PAGE NO.

1. EXECUTIVE SUMMARY 02

2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION 03

3. PROJECT DESCRIPTION 05

4. SITE ANALYSIS 15

5. PLANNING BRIEF 18

6. PROPOSED INFRASTRUCTURE 18

7. REHABILITATION AND RESETTLEMENT(R&R PLAN) 18

8. PROJECT SCHEDULE AND COST ESTIMATES 18

9. ANALYSIS OF PROPOSAL (FINAL RECCOMDATION) 18

Page 2: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 2

EXECUTIVE SUMMARY

1.0 INTRODUCTION

The unit will function in the name and style of M/S- Pureganic Health Care. It is proposing toset up an industrial unit (Small scale industry) at Mauza Kuanwala, District and TehsilDehradun, Uttarakhand with a view to manufacture various Ayurvedic, Herbal, Food, Pharmaproducts & Wire Drawing.

Ayurvedic, Herbal, Food & Pharma products are safe and effective in treatment of variousdiseases especially which is chronic in nature. Recently there has been a shift in universaltrend from synthetic to herbal medicine, which we can say ‘Return to Nature’. Medicinal plantshave been known for millennia and are highly esteemed all over the world as a rich source oftherapeutic agents for the prevention of diseases and ailments. Nature has bestowed ourcountry with an enormous wealth of medicinal plants; therefore India has often been referredto as the Medicinal Garden of the world. No doubts that the herbal drugs are popular amongrural and urban community of India. The one reason for the popularity and acceptability isbelief that all natural products are safe. The demand for plant based medicines, healthproducts, food supplement, cosmetics etc are increasing in both developing and developedcountries, due to the growing recognition that the natural products are non-toxic, have lessside effects and easily available at affordable prices. Now a days, there is a revival of interestwith herbal-based medicine due to the increasing realization of the health hazards associatedwith the indiscriminate use of modern medicine and the herbal drug industries is now very fastgrowing sector in the international market. But unfortunately, India has not done well in thisinternational trade of herbal industry due to lack of scientific input in herbal drugs. So, it wouldbe appropriate to highlight the market potential of herbal products and that would openfloodgate for development of market potential in India.

At present the company is going to manufacture the products in bulk quantities and thoseshall be sold to Ayurvedic/Pharma Industries (Manufacturing Finished Products) in India andabroad. Herbal / Ayurvedic / Pharma products are used in manufacture of i.e.

Ayurvedic Medicines

Skin Care Products

Hair Care Products

Food Products and Supplements

Pharma Products

Cosmetic Products

Ayurvedic And Herbal Products

These products have great potential in Indian as well as International market. These productsshall be sold to manufacturer’s like Fem Pharma, Brihans, Zandu Pharmaceuticals, SanduBrothers, Patanjali Ayurved Ltd., Gurukul Kangri Pharmacy & their associates.

Background of the promoter

Smt. Bhumika Mittal & Shri Manish Mittal (Partner) is spearheading the Company. Shri ManishMittal is managing partner and is solely responsible for the works, action, management, govt.department responsibilities and liabilities etc. Partnership business shall be carried under thename and style of M/S- Pureganic Health Care at Khasra No-44A, Mauza Kuanwala,Dehradun, Uttarakhand. The business of the firm shall be trading and manufacturing of

Page 3: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 3

Ayurvedic, Herbal, Food & Pharma products with capacity of 35,900 Tonnes Per Annum.Manufacturing of wire drawing (Copper Rod to Thin copper wire) with the capacity of100 Tonnes/Annum.

1.1 Salient Features of The Project

Proponent Name M/S- Pureganic Health CareLocation Khasra No-44A, Mauza Kuanwala,

Dehradun, Uttarakhand. Location map isshown in Fig.1.1 below

Latitude 30°15'1.18"NLongitude 78° 6'3.37"ELand use IndustrialNearest Habitate/ Town DevshreepuramNearest Railways Station Dehradun Railway Station–9KmNearest Airport Jolly grant – 10.50 KmNearest Highway NH-72Water Demand and Supply source 28 KLD Supply of Bore well out of which 24

KLD Net Fresh Water will be required aftertreatment.

Nearest Tourism Place Mussoorie22 KmNational Park Rajaji National Park at distance 10kmSeismic Zone Zone – IVAltitude 1900 ft. (581 meters)Proposed Production process Ayurvedic Medicines, Skin Care Products

Hair Care Products, Food Products andSupplements, Pharma Products, CosmeticProducts, Ayurvedic And Herbal Products

Estimated Project Cost INR 450 lakhsWorking Days 26 days in a MonthMan Power 250

Note:- All distance in km (Aerial)

2. INTRODUCTION OF THE PROJECT /BACKGROUND INFORMATION

A. Identification of the project and project proponent.

Category of Project: Category B2 ( Doon Valley)

The project proponent is M/s Pureganic Health Care which is incorporated undercompanies act.

B. Brief Description of Nature of Project.

M/s Pureganic Health Care proposes to manufacture Ayurvedic, Herbal, Food & Pharmaproducts in preparation of medicines and various Skin & Hair care products like; Creams,Shampoos, sunscreen Lotions, Antiseptic Creams, Hair style Gel, Anti-Wrinkle Cream, Mouthwash, Tooth Gel etc.

Page 4: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 4

Figure 1.1: Showing Location Map of the study area

Figure 1.2: Showing Project Location, Surrounding Features & Connectivity

PROJECT SITE

30°15'1.18"N

78° 6'3.37"E

DEHRADUN

DEHRADUN RLY.

STN

SONG RIVER

9KM

3.5 KMRAJA JI NATIONAL PARK- 10KM

PS

Page 5: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 5

C. Need for the Project & Importance to the Country

The proposed project is for setting up an industrial unit for manufacturing of Ayurvedic, Herbal,Food & Pharma products are safe and effective in treatment of various diseases especiallywhich is chronic in nature. Recently there has been a shift in universal trend from synthetic toherbal medicine. The demand for plant based medicines, health products, food supplement,cosmetics etc are increasing in both developing and developed countries, due to the growingrecognition that the natural products are non-toxic, have less side effects and easily availableat affordable prices. A need has therefore been felt to establish the unit for manufacturing.

D. Demand and supply gap

These products are having National market and still demand is more than supply somanufacturing of these items are feasible.

The Proposed Company does not see any difficulty in marketing their products as the twoessential points in marketing a product i.e. product quality & packing and experience arereasonable in favour of the Promoters.

E. Export Possibility

Yes .Entire product shall be of export quality and possibilities of export will be explored.

F. Domestic/Export Markets

There is domestic market of this product but export shall also be done.

G. Employment Generation (Direct & Indirect) due to the project

With this proposed project direct employment generation of 250 persons will be there inworker/supervisor/ managerial category. Indirect generation of employment will also be therein way of contractors, transportation, suppliers, other service providers with continues chain ofemployment.

3. PROJECT DESCRIPTION

A. Type of Project including Interlinked and Interdependent Projects, if any

There is no interlinked and/or interdependent project linked with it. No other allied activitiesand/ or services will be carried out with this project.

B. Location (map showing general location, specific location, and project boundary & projectsite layout) with coordinates.

The unit situated at Khasra No 44A, Mauza Kuanwala, Dehradun, Uttarakhand is a well-defined and developed industrial area in Mauza Kuanwala, District Dehradun at a distance of8Km North West of Dehradun on National Highway No 72 to Haridwar. Fig. 1.1, 1.2 & 1.4showing general location, specific location, and project boundary & project site layout) withcoordinates.

Page 6: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 6

C. Details of alternate sites considered and the basis of selecting the proposed site,particularly the environmental consideration gone into should be highlighted.

No alternate site.

D. Size and Magnitude of the operation.

The Company is proposing to setting up an industrial unit for manufacture of Ayurvedic,Herbal, Food & Pharma products in preparation of medicines and various Skin & Hair careproducts like; Creams, Shampoos, sunscreen Lotions, Antiseptic Creams, Hair style Gel, Anti-Wrinkle Cream, Mouth wash, Tooth Gel etc. at khasra No-44A, Kuanwala, Dehradun, in thestate of Uttrakhand. The total plot area is 2445.35sq.m. Fig. 1.4 below showing the proposedlayout (Building, Greenbelt, Road etc) of the study area. The proposed Capacity of the unit tomanufacture Ayurvedic, Herbal, Food & Pharma products are the following.

S.No. Items of Manufacture/ Type of Service Quantity in Tonnes per annum1. Ayurvedic Medicines, Skin Care Products, Hair

Care Products, Cosmetic Products, AyurvedicAnd Herbal Products

35,900

Food Products and SupplementsPharma Products

2. Wire Drawing 100

The other information related to the project are the following

Sl.No. Particulars Capacity1 Electricity 300 KW2 Water consumption Domestic 7 KLD3 Water consumption Industry 21 KLD4 Manpower 2505 D.G Sets 250 KVA (TWO DG SET)6 Cost of the Project 450 lakhs7 ETP Capacity 5 KLD8 Manufacturing Process Manufacture Ayurvedic, Herbal, Food

& Pharma products in preparation ofmedicines and various Skin & Haircare products like; Creams,Shampoos, sunscreen Lotions,Antiseptic Creams, Hair style Gel,Anti-Wrinkle Cream, Mouth wash,Tooth Gel etc

Page 7: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 7

E. Project description with process details (a schematic diagram/flow chart showing theproject layout, components of the project etc. should be given)

PRODUCT NAME: ALOE VERA JUICE WITH ORANGE FLAVOUR

Composition Each 10 ml Contains

S.no Common name Latin name Parts used Qty.(ml)1. Ghrit Kumari Swaras Aloe Vera Leaf

Juice/pulp/extract9.45

Excepients; Sorbitol, Citric Acid, Carragenin, Flavour Orange-Q.S

Preservative: Sodium Benzoate, Potassium Sorbate Q.S.

Mfg Method: I. Prepare Juice of aloe Vera in mixer machine.

II. Prepare juice and add citric acid & Sweetener.

III. Mix juice well with preservative.

IV. Filter and pack in containers aseptically.

Presentation: 50/75/100/125/150/200/250/450/500/1000 ml in HDPE/Glass/Pet container/Pouch.

PRODUCT NAME: ALOE VERA GEL

Composition Each 5 gm Contain

S.no Common name Latin name Parts used Qty %1 Ghrit Kumari Juice

Kesar

Chandan

Aloe Vera Leaf/pulp/extract q.s.

2 Base material q.s.

Base material: Glyecrin-5-10%, thickner-0.5-1%, PG-2-5% TEA-QS. Vitamin E, Fragrance: QS.

Mfg. Method: I. Prepare base with base material

II. Mix base with aloe Vera juice/pulp/extract under continuous stirring.

III. Add fragrance on cooling.

IV. Pack in tube/ HDPE/pouch continuous.

Presentation: 20/40/50/60/80/100/120 gm/, ml in pouch/tube/containers

Page 8: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 8

PRODUCT NAME: FACE PACK

Composition Each 100 g Contains

S.no Common name Latin name Parts used Qty.(g)1. Ghrit Kumari Juice Aloe Vera Leaf 402. Neem Azadirachta

IndicaPowder 5

3. Multani mitti Fullers Earth Powder 14

4. Kheera Juice Cucumis sativus Juice 2

Base (Q.S): Dicococyl Pentaerythrityl, Citrates, Xanthan Gum, Methyl Aluminum Sulphate, Iso

propyl Alcohol, Xylocite.Zinc Oxide. Methyl Paraben sodium, Propyl Paraben sodium, Bentonite

Powder.DM water, IMD urea. Glycerin, Perfume.

Mfg. Method: I. Mix Aloe Vera juice, Neem, Cucumber and fuller earth.

II. Add preservative in this and mix well.

III. Then add glycerin and perfume in this and mix it well.

IV. Add base material in this at 40 C temp. And mix well.

V. Allow it cool and then fill in the tubes.

Presentation: 5, 8, 50, 60,100,200,500 ml.in pouch/ tube/containers

Page 9: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 9

MANUFACTURING PROCESS CHART

TABLETS

Raw & packing Material Storage Area

Raw & Packing Materials Testing

Dispensing

Shifting

Mixing

Blending

Wet Milling

Drying

Shifting

Dry Milling

Blending

PackingLubrication

TestingBlend Analysis

Transfer to Finished Goods

CompressionDispatch to Customers

Coating

Page 10: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 10

Syrup Process Chart

Raw & Packing Material Stores

Raw & Packing Materials Testing

Pharma Grade Sugar Drying

Shifting of all Raw Material

Blending of above material

Testing

Filling

Packing

Testing

Transfer to Finished Goods

Dispatch to Customers

Page 11: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 11

Capsules Process Chart

Raw & packing Material Stores Raw & Packing Materials Testing Dispensing

Shifting

Blending

Lubrication

Blend Analysis

Filling

CPolishing

Packing Testing

Transfer to Finished Goods

Dispatch to Customer

Wire Drawing Process Chart

CCSR COPPER ROD

COPPER RODS TO DRAWING

DRAWING TO DIFFERENT FINE GAUGES AS PER MARKET REQUIREMENT

THEN ON TO THEN ANNEALING FOR COPPER

ONLINE (24 HEADS) x 2 …………… (MACHINE) GAUGES FROM

PULLER

PLASTIC SPOOLS FURNISH PRODUCT

Page 12: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 12

EXTERNAL PREPARATIONS (CREAMS/GELS/COSMETICS)

PROCESS FLOW CHART

Non AqueousAqueous Phase Preparation

Batch Preparation

Batch Storage Sampling

Analysis & Approval

Tube Filling / Crimping

Mono carton packing

Final Packing

Transfer to FG Store

Dispatch

Pri. Pkg. Material

Dispensing

Sec. Pkg. Material

Dispensing

Sampling

Filter & Transfer

under vacuum

Filter &Transfer

vacuum

In process checking

In process checking

Analysis & Approval

In process checking

RM Dispensing In process checking

In process checking

Page 13: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 13

PLANT AND MACHINERY

Sr. No. PARTICULARS

1. Washing units

2. Extractors

3. Inspection Conveyors

4. Juicers

5. Nutche Filters

6. Sparkers Filter

7. Cartridge Filter

8. Homogeniser

9. Mixing Tanks

10. Storage Tank

11. Filling Machines

12. Mixers

13. Water Treatment Plant

14. Multi Mills

15. Fixtures including pipelines, pumps, taks etc

LIST OF LAB EQUIPMENTS

Disintegration Test Apparatus Dissolution Test Apparatus Hardness Tester Single pan Balance Analytical Balance Friability Test Apparatus pH Meter Melting Point Apparatus Incubator U.V. Spectrophotometer HPLC KarlfisherTitrator Colony Counter Potentiometer Titrator Stability Chamber BOD Incubator Zone Reader FTIR Leak Test Apparatus Polorimeter Refractometer

Page 14: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 14

F. Raw Material Required Along Estimated Quantity, Likely Source, and Marketing Area OfFinal Product/s Mode Of Transport Of Raw Material And Finished Product.

All raw materials are indigenously available in Indian market.

Raw Materials

Aloe vera leaf/juice/dry extract, Amla, Kerela, Wheat grass powder/juice/leaf, Loki, Multanimitti, Neem leaf, Cucumber fruit/ extract, Bentonite powder, Kaolin powder, Mineral clay,Sodium benzoate, Potassium sorbate, Citric acid, Methyl paraben sodium, Proply parabensodium, Imd. Urea, Glycerine, Polyethene glycolhydrogenated castor oil, Silicon oil, Sles,Sodium polystyrene sulfonate, Dicococyl pentaerythrityl distearyl citrate, SodiumBenzotriazolul Butylphenol Sulfonate, Buteth-3, Tributyl Citrate, Magnesium aluminum silicate,M icropil-500, EDTA, Zine oxide, Sodium silicate, Isopropyl alcohol ,Perfume, Red lentil ,Neem ext. , Xanthan gum. Apricot shell powder, Sodium Benzotriazolul Butylphenol Sulfonate,Buteth-3, Tributyl Citrate, Light liquid paraffin , PEG-60, Stearate glyceryl, Stearate cetearylalcohol, Stearicacid, Palmitic acid, Polysorbate 80, Cetearyl alcohol , Polyglycery1-2sesquiisostearate, Cera alba , Cera microcrystalline, Mineral oil, Magnesium stearate,Aluminum stearate, Sodium silicate, Vit. E Carbopol, Hydrogenated castor oil, Sorbitol,Flavours, Perfume.

Raw Materials for Manufacturing of Wire Drawing: Copper & Aluminum ROD

Products

Aloe vera juice (plain, fiber and flavoured) Aloe vera gel (plain, kesar chandan etc) Face pack (Mulatni mitti, neem cucumber, etc.) Face scrub (Apricot, walnut, etc.) Face wash (Neem - aloevera, Mint, tulsi, etc.) Hair oil ( anti dandruff , medicated, etc) Hair colour( Black, brown, etc) Anti mosquito gel Anti mosquito cream kerela juice Amla juice 12.1oki juice wheat grass juice wheat grass powder Aloe vera juice powder Herbal juices Herbal powder body wash Hand wash Shampoo Hair wash Lip guard Herbal teas Anti aging cream Hair gel Hair cream

Page 15: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 15

G. Power Requirement:

Total Power requirement is 300 KW and will be met from Uttarakhand electricity board, also

Two DG set of 250 KVA each is proposed. DG set shall be used at the time of power failure

only.

H. Water Requirement:

Proposed water requirement is 28KLD and shall be met from bore well.

4. SITE ANALYSIS

A. Connectivity

Well connected with Road, Rail and air serviceNH-72 Dehradun to Haridwar – 0.5 kmDehradun Railway Station – 9.0 kmJolly Grant Airport – 10.50 km

B. Land form, Land use and Land owner ship

Plain and flat land having Industrial use falling Industrial area, Dehradun.

C. Topography –

Land is plane and flat with inclination towards South. Fig. 1.3 showing the topography of thestudy area below.

Figure 1.3 : Showing the Topography of the study area

Page 16: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 16

Figure 1.4: Layout Plan Showing proposed Manufacturing unit of the study area

Proposed

Building

Proposed

Green Area

TREE PLANTATION

Page 17: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 17

D. Existing land use pattern

The existing land use is Industrial.

E. Existing Infrastructure

All infrastructures have been developed by State Govt. New Infrastructure is not required

F. Climatic data from secondary sources

Monthly mean maximum & minimum temperature and total rainfall based upon 1961-1990 data:

Month Mean Temperature oC Mean Rainfall inmm

Maximum MinimumJanuary 19.3 6.0 55.0February 25.1 7.8 58.8

March 26.4 12.0 49.0April 32.1 16.7 22.5May 35.6 20.7 41.7June 34.8 23.0 201.8July 30.5 22.8 672.6

August 29.4 22.4 728.2September 29.7 20.8 296.5

October 28.5 15.7 49.8November 25.0 10.4 8.6December 21.1 6.8 24.4

Source- http://www.imd.gov.in/doc/climateimp.pdf

G. Social Infrastructure

The area is approved Industrial area in Mauza Kuanwala, Dehradun, in the state ofUttrakhand. and having sufficient social infrastructure such as School, Hospital, CommunityCentre etc

I. Drinking Water Management ( Source & Supply of water)

The source of the drinking water is Borewell

J. Sewage System.

Soak pit and septic tank arrangement shall be provided for the waste generated from toiletsand domestic use.

K. Industrial Waste Management.

Effluent Treatment Plant is proposed for industrial waste. Capacity of ETP shall be 5 KLD

Page 18: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 18

L. Solid Waste Management

1. Solid waste generated from sludge drying beds of ETP shall be disposed to TSDF as perthe norms of State Pollution Control Board.

2. Used oil shall be disposed to authorized recycler.

M. Power Requirements & Supply/ source.

Total Power requirement is 300 KW and will be met from Uttarakhand electricity board,capacity of two DG set of 250 KVA each is proposed. DG set shall be used at the time ofpower failure only.

5.0 PLANNING BRIEF

A. Planning concept (type of industries, facilities, transportation etc) town andcountry planning/Development authority Classification.

The proposed industry is small scale and established in a Industrial area, Dehradun.

6.0 PROPOSED INFRASTRUCTURE

A. Industrial Area (Processing Area) No additional infrastructure is proposed

B. Resident Area (Non Processing Area) as only local person will be given employment, noresidential area/ housing is proposed.

C. Green Belt - 33% area has been reserved for green belt Company will be developed densegreen belt around the plant premises with plant species.

D. Hazardous waste Management: Company shall get the Authorization under “Rule-5” of

the Hazardous Waste (Management, Handling & Trans-boundary Movement) Rule, 2008,

and maintain proper storage & safety management for Hazardous material. All Hazardous

waste shall be disposed through authorized vendor.

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

The unit is in developed industrial estate, so R & R plan is not required.

8.0 PROJECT SCHEDULE AND COST ESTIMATES

Project is expected to be complete in next 6 months Funds requirement shall be Rs 450 Lakhs including the machinery and plant.

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

The Indian industry is a success story providing employment for millions and ensuring that

Ayurvedic, Herbal, Food & Pharma products are safe and effective in treatment of various

diseases especially which is chronic in nature and easily available at affordable prices. Also

Page 19: Prefeasibility Report - environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/11022016I7... · Prefeasibility Report Page 2 EXECUTIVE SUMMARY 1.0 INTRODUCTION

Prefeasibility Report

Page 19

Improvement of infrastructure as well up-liftment of social structure in the area. The people

residing in the nearby areas have been benefited directly & indirectly.

***