Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
PRE – FEASIBILITY REPORT
for
PRIOR ENVIRONMENTAL CLEARANCE
Expansion & Modernization of existing project for manufacturing of explosives and defense products
At
Village Chakdoh, Near Bazargaon, Tal-Katol, Dist- Nagpur Pin Code – 440 023, Maharashtra
Project Proponent
M/s Solar Industries India Limited
Environment Consultant
Anacon Laboratories Pvt. Ltd.
Recognized by MoEF (GOI) as per EPA and valid upto Jan’2019 Accredited by NABL for Chemical & Biological), valid up to 03.10.2016
Accredited under the QCI-NABET Scheme for EIA Consultant Certified by ISO 9001:2008, ISO 14001:2004, OHSAS 18001:2007
Head Office: 60, Bajiprabhu Nagar, Nagpur-440 033, MS Lab. : FP-34, 35, Food Park, MIDC, Butibori, Nagpur – 441122
Ph. : (0712) 2242077, 9373287475 Fax: (0712) 2242077 Email: [email protected], [email protected]
website: www.anaconlaboratories.com
JANUARY, 2017
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 1
1. EXECUTIVE SUMMARY
1.1 Name of the Project Proponent: : M/s Solar Industries India Limited
1.2 Location : Village – Chakdoh Near Bazargaon, Tahsil - Katol, Dist. Nagpur-440 023 (Figures 1 & 2)
1.3 Office (Regd.) : 11, Zade Layout, Bharat Nagar, Nagpur – 440 033, Maharashtra Phone: 0712 256 0010
1.4 Name of Promoters : Mr. Satyanarayan Nuwal , Chairman
1.5 Existing and Proposed products with their Capacities are provided in following four tables based on their units and respective consent.
Table-I (Product Units are in Million Nos./Annum)
Sr. No.
Name of products Existing capacity
Per Annum
Consent (Water/Air/HW) vide
no. 1612001045 Dated 30/12/2016
Proposed Additions
Per Annum
Total Capacity after Expansion Per Annum Proposed EC capacity
1. DETONATORS (FINISHED) 125 125
Nil 125
2. FILLING / PRESSING FOR FILLED SHELL (CAPTIVE)
63 63 Nil 63
3. GI / CU WIRE COATING 90 90 Nil 90
Table-II (Product Units are in Million Meters/Annum)
Sr. No.
Name of products Existing capacity
Per Annum
Consent (Water/Air/HW) vide
no. 1612001045 Dated 30/12/2016
Proposed Additions
Per Annum
Total Capacity after Expansion Per Annum Proposed EC capacity
1. DETONATING FUSE 75 75 75 150
Table-III (Product Units are in M.T./Annum)
Sr. No.
Name of products Existing capacity
Per Annum
Consent (Water/Air/HW) vide
no. 1612001045 Dated 30/12/2016
Proposed Additions
Per Annum
Total Capacity after Expansion Per Annum Proposed EC capacity
1. SLURRY EMULSION EXPLOSIVES (FINISHED)
100000
1,00,000 56,250 1,56,250
2. SORBITAN MONO OLEATE (SMO) (C & F)
9162
9162
Nil 9162
3. POLY ISO BUTYLENE SUCCINIC ANHYDRIDE (PIBSA) C & F
6000 6000 Nil 6000
4. PETN -(PENTA ERITHRITOL TETRA NITRATE) I & C & F
2062.5 2062.5
937.5 3000
5. PENTOLITE / CAST BOOSTER (FINISHED)
1875 1875
1125 3000
6. CALCIUM / SODIUM NITRATE MELT (CAPTIVE)
3600 3600 Nil 3600
7. DUST SUPPRESSANT (FINISHED)
1000 1000
Nil 1000
8. LEAD AZIDE (CAPTIVE) 9 9 Nil 9
9. LEAD STYPHANATE (CAPTIVE)
3 3 Nil 3
10. ASA MIXING & DRYING (CAPTIVE)
12 12
Nil 12
Table-IV (Product Units are in M.T./Annum)
Sr. No.
Name of products Existing capacity
Per Annum
Consent to Establish
(Water/Air/HW) vide no. 7819 Dated
15/06/2016
Proposed Additions
Per Annum
Total Capacity after Expansion Per Annum Proposed EC capacity
1. CYCLOTETRA METHYLENE TETRA NITRAMINE- HMX & HMX COMPOUNDED PRODUCT
62.5 62.5 237.5 300
2. RDX AND RDX COMPOUNDED PRODUCT
Nil 125 2875 3000
3. BULK EMULSION Nil Nil 125,000 125,000
4. TNT Nil 625 2375 3000
Proposed Boiler
1. COAL FIRED BOILER 12 TPH
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 2
1.6 Total Project Area : Presently 273.910 acres land area is under possession.
1.7 Water Requirement : Source: Groundwater within plant area Existing water requirement: 646 KLD Proposed additional water requirement: 234 KLD Total water requirement after expansion: 880 KLD
1.8 Power Requirement : The industry has been obtained contract demand for 2000 KVA by MSEDCL (Load sanction Letter-Annexure – IX). The present power requirement of the plant is met from connected power supply of 2350 KW. Additional power requirement of 1000 KW will be sourced from the MSEDCL grid.
DG sets with capacity(KVA)
Existing Proposed addition
2 x 380 1x300
1 x 400
1x 600
Total=1680
The DG sets as a standby arrangement.
1.9 Number of Shift : Three Shift Basis ( Round the clock)
1.10 No. of Working Days : 300 Days
1.11 Total Cost of Project : Rs. 184.01 Crore
1.12 Man Power Utilization : Sr. No.
Category Existing Additional for Project under execution
Total after completion of Project
1 Skilled/Unskilled workers
1278 145 1423
2 Supervisory Staff
200 42 242
3 Managerial Staff 35 10 45
Total 1513 197 1710
1.13 Schedule of Implementation
: Particulars Implementation
Date/Time Period
Commercial Production of proposed additional
products
Commercial Production
will be started
After Receipt of
Environmental Clearance
1.14 Environment Consulting Organization
: Anacon Laboratories Pvt. Ltd.
FP-34, 35, Food Park, MIDC, Butibori, Nagpur – 441122 Ph. : (0712) 2242077, 9373287475 Fax: (0712) 2242077 Email: [email protected], [email protected] website: www.anaconlaboratories.com
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 3
2.0 INTRODUCTION
2.1 Identification of project and project proponent
Solar Industries India Ltd. (SIIL) has been incorporated on 24 Feb, 1995. The manufacturing unit of SIIL
is located at Village-Chakdoh, Tahsil-Katol, Dist. Nagpur, Maharashtra. The location falls in Backward
D+ Region as per PSI-07 policy of Government of Maharashtra. The company produces explosives of various
types and its accessories. SIIL is implementing Mega project as per PSI-2007 policy by expanding plant
capacities.
SIIL is the largest industrial/ defence explosives manufacturer in India and the fastest growing Company in the
sector. Over the years, the Company leveraged its competitive advantage - high quality, wide product range,
efficient manufacturing, large capacity and integration to emerge as the largest sectorial exporter from India.
SIIL is India’s largest manufacturer, supplier and exporter of Industrial Explosives and Initiating Systems.
Looking at the major developments taking place in defense segment in the form of liberalized Defence
Procurement Policy of Ministry of Defence, Govt. of India, based on the policy of “Make Indian” and
“Buy & Make Indian”. The liberalized policy of Govt. at the center to allow private participation in Defence
production has opened up vast potential for Defence product manufacturing by private parties. The Company is
now extending its presence from long-standing explosives segment to the manufacturing of products used by
Indian Armed Forces.
Consequent to the development explained above and looking at the large demand for Warhead explosives like
HMX, RDX, TNT and their Compounds and other defense products and the natural synergy, SIIL has, in terms
of production, safety and security aspects of manufacture of civilian explosives, decided to create production
capacities for defense products.
SIIL is the first Company in the private sector to set up a state-of-the-art technology based plant to manufacture
high energy materials such as HMX and HMX based compositions required for Defence sector. The HMX plant
with production capacity of 50 MTPA has been set up and successfully commenced production and further
granted the enhanced the production capacity to 300 MTPA. The HMX and HMX compounded products have
been supplied to Defence Research and Development Organisation (DRDO), Terminal Ballistic Research
Laboratory (TBRL), Advance Center for Energetic Materials (ACEM), Bharat Dynamics Limited, High Energy
Materials Research Laboratory (HEMRL) and Ordnance Factory, Khamaria.
Based on the existing Industrial licensed capacities TNT for 500 MT/Annum and RDX 100 MT/Annum, company
has further approached to DIPP, Govt. of India for enhancement of capacity of TNT and RDX for 3000 MTPA
respectively and initiated finalization of technologies and critical equipment’s from overseas sources.
The capacity enhancement has also been planned for Slurry /Emulsion Explosives 56250 MTPA, PETN 3000
MTPA and initiating explosives like Detonating fuse 150 Million meters/Annum & Cast Booster 3000 MTPA.
The existing products before expansion does not fall under the purview of the EIA Notification 2006 and
subsequent amendments with respect to its capacity to produce various explosive products. However, SIIL has
obtained valid consents; CTE/CTO required from MPCB.
Now, expansion & modernization activity is falling under schedule (5f) of EIA notification 2006 and prior
environment clearance is needs to be obtained from MoEF&CC, GOI.).
Background of Company
Mr. Satyanarayan Nandlal Nuwal, Chairman of Solar Industries India Limited, Aged - 64 years, who hails from
Bhilwara (Rajasthan), is the founder of SIIL.
“Solar Industries India Limited” is a parent company of “Solar Group” of companies and is a Public Limited
Company, listed on the BSE and the NSE. The consolidated net worth of the company is Rs. 867.57 Crores as
on 31/03/2016 with a present market capitalization of over Rs. 6000 Crores.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 4
Moreover, SIIL is the only company in explosives manufacturing segment in the country having accredited with
ISO-14001:2004, OHSAS 18001:2007 and ISO-9001:2008 certification and authorised by GB EXPLOSIVES
NOTIFIED BODY, Health & Safety Laboratory, UK to use “CE” mark on explosives products. SIIL has also
been assigned “AA-/Stable” and “A1+” rating by CRISIL, which indicates that, the degree of safety with regard
to timely payment of interest and principal on the instrument is very strong.
Manufacturing facilities
Solar Group has 25 manufacturing plants across 8 states in India and has overseas manufacturing
facilities at Zambia, Nigeria and Turkey. Our products are exported to over 40 countries across the
globe. The past performance of Solar Industries India Ltd. is summarized below:
Rs. in lacs
Particulars 31.03.16 31.03.15 31.03.14 31.03.13 31.03.12
Total Income 109969.00 103458.00 92112.55 90463.24 74871.44
Profit Before Tax 16690.00 14034.85 10265.48 8529.04 7917.99
Profit After Tax 11126.00 10792.34 8384.44 7581.55 6088.60
Board of Directors
Sl. No. Name of Directors Designation
1. Mr. Satyanarayan Nandlalji Nuwal, Chairman and Executive Director
2. Mr. Kailashchandra Nandlalji Nuwal Vice Chairman and Executive Director
3. Mr. Manish Satyanarayanji Nuwal Managing Director and CEO
4. Mr. Roomie Dara Vakil Executive Director
5. Mr. Anil Kumar Jain Executive Director
2.2 Brief Description and Nature of the Project
The existing project located at Village - Chakdoh, Tahsil - Katol, District- Nagpur was set up in 1995.
The location falls under industrially backward D+ backward region as per PSI-07 policy of
Government of Maharashtra. Details of existing product wise capacities are as under:
S. No. Name of Products Production Capacity Per Annum 1. Slurry/Emulsion Explosives 100000 MT/Year
2. Detonators (Finished) 125 Million Nos./Year
3. PETN (Intermediate & Finished) 2062.5 MT/Year
4. HMX & HMX compounded Products 62.5 MT/Year
5. Detonating Fuse (Finished) 93.75 Million Meters/Year
6. Pentolite/ Cast Booster (Finished) 1875.0 MT/Year
7. Sorbitan Mono Oleate –SMO (I & F) 9155 MT/Year
8. Calcium/Sodium Nitrate Melt (Captive) 3600 MT/Year
9. Dust Suppressant (Finished) 1000 MT/Year
10. Poly isobutylene succinic anhydride (PIBSA) (Captive & Finished)
6000 MT/Year
11. Filling & Pressing of filled shells (Captive) 62.5 Million Nos./Year
12. Lead Azide (Captive) 9.0 MT/Year
13. Lead Styphnate (Captive) 3.0 MT/Year
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 5
S. No. Name of Products Production Capacity Per Annum 14. ASA Mixing & Drying (Captive) 12.0 MT/Year
15. GI/CU Wire Coating 90.0 Million Nos./Year
M/s Solar Industries India Limited has now planned to undertake capacity enhancement of HMX and
HMX compounds manufacturing and also added few other defense products and defense related
activities as follows:
1.3 Need for the project and its importance to the country and/or region
M/s. Solar Industry India Limited has setup manufacturing facilities for production of various types of
explosives including Defence products (HMX and its compounds). GOI Ministry of Defence under
make in India policy has issued policy’2013 amendments to produce indigenous products. Based
upon past performance and indigenous capability M/s. Solar Industry India Limited granted the
license to manufacture for Defence products. Proposed products are categorized (5f) as per EIA
notification and prior environment clearance will be obtained from MoEF&CC, GOI.
2.4 Demand-Supply Gap
A demand-supply gap, huge potential in terms of increased Defence outlay and economies of scale
prompted us to foray into the Defence space. SIIL expanding capacity at strategic locations and
diversifying to meet the growing resource demand. M/s SIIL not only scaled up its production capacity
since inception, but also developed a well-diversified portfolio of products. Today, Solar have a wide
product range and the market leaders in each of SIIL product categories.
Global Scenario
Solar products and services have successfully captured the needs and expectations of its valuable
customers in India and abroad. With willingness and a continuous zeal to explore growth frontiers, the
company is expanding the horizons of growth by further scaling up the domestic manufacturing
capacities and by spreading its wings outside India. Nigeria is one of the fastest growing economies
in Africa. Solar has formed a joint venture in Nigeria by acquiring majority stake in 'Nigachem Nigeria
Limited'. Whereby pairing Solar's robust and modern manufacturing experience with its partner's
market intelligence and have installed production units of cartridge explosive of 5000 MTPA and bulk
explosives of 2000 MTPA .
At Zambia, in a Joint Venture with Ortin Investments Limited, to service the open pit mining projects
by supplying explosives in Zambia and Congo, Solar has incorporated 5000 MT Cartridge 10000 MT
S. No. Items Total Capacity after Expansion
1. HMX and HMX Compounded Products 300 MTPA
2. RDX and RDX Compounded Products 3000 MTPA
3. Bulk Explosives 125000 MTPA
4. Slurry/Emulsion Explosives 56200 MTPA
5. TNT Explosives 3000 MTPA
6. PETN 3000 MTPA
7. Cast Booster 3000 MTPA
8. Detonating Fuse 150 MILLION METER/ANNUM
9. Boiler 12 TPH (Coal fired) 12 TPH
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 6
Bulk explosives mmanufacturing units along with Storage capacities, Detonator Assembly plant and
ANFO manufacturing plant.
Solar along with local Turkish shareholders having an in-depth knowledge on Explosives business
established a joint venture. Solar has set-up a state-of-the-art explosive manufacturing plant for
Emulsion Explosives, ANFO and initiating systems.
The company's plan is to invest in explosive manufacturing facilities, and serve the mining,
construction, and explosive industries in Turkey and nearby countries.
The manufacturing facilities were setup here in 2012 and currently, Plant has capacities of 40000
MTPA ANFO and Non Electric Detonator (NONEL) assembly & 5000 MTPA of Cartridge explosives.
2.5 Imports vs. Indigenous production
M/s Solar Industries India Limited has setup manufacturing facilities for Defence products (HMX and
its compounds).
HMX and HMX Compounded Products:
The present total estimated demand for HMX and HMX compounded products viz. OCTOL, SOKFOL
and SOMA are around 200 MTPA and is estimated to go up to 250 MTPA by 2016-17. The
indigenous production is 2 MT only. Balance requirement of HMX is imported from foreign sources.
RDX and RDX Compounded Products:
The estimated present RDX requirement for making RDX compounds like A 5, 60:40, etc. is 600 MT
and is estimated to go up to around 750 MT by 2016-17. The indigenous production is 300 MT and
balance is imported from foreign sources.
TNT Explosives:
The present estimated demand for TNT is 1500 MT and is estimated to go up to 2500 MT by 2016-
17. The indigenous production is around 600 MT. Balance quantity is imported from the foreign
sources.
Looking at the requirement of various Defence products in near future and the Policy of Ministry of
Defence, Govt. of India, to maximize procurement of Defence products from Indigenous sources
under the Defence Procurement Policy-2013, industry do not anticipate any difficulty in selling of the
products being considered under the proposed project.
2.6 Export possibility
Solar is the largest exporter of Explosives and Initiating Systems from India. Solar's products and
services have successfully met the needs and discerning expectations of its valuable customers not
only in India but also overseas. In fact, SIIL, export products to more than 42 countries across the
Middle-East, Africa, and the South East Asia is well accepted by the end users.
2.7 Domestic/ Export Markets
Solar plans to support all existing customers and potential customers with product, services and
potential technology upgrade in Indonesia and Australia subject to meeting all local regulatory
approvals and securing long term supply contracts. Solar is pursing and investigating such
opportunities. Solar is the largest exporter of Explosives and Initiating Systems from India. There is a
huge demand of the proposed products in the export market.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 7
2.8 Employment Generation (Direct and Indirect) due to the project
SIIL is presently employing 1513 persons comprising of various categories such as managers,
officers, supervisors and all types of workers and van drivers. The additional manpower requirement
for project under revision is 197 persons details of which are given below:
Sr.
No.
Category Manpower in
existing Project
Additional manpower for
Project under execution
Total after completion
of Project
1 Skilled/Unskilled workers 1278 145 1423
2 Supervisory Staff 200 42 242
3 Managerial Staff 35 10 45
Total 1513 197 1710
3.0 PROJECT DESCRIPTIONS
3.1 Type of project including interlinked and interdependent projects, if any.
The proposed expansion project is for manufacturing of Defense explosives, commercial explosive,
its components, etc. Proposed products are categorized (5f) as per EIA notification and prior
environment clearance will be obtained from MoEF&CC, GOI, falling under “A” category. Project is
located at Village- Chakdoh, Near Bazargaon, Taluka -Katol, District- Nagpur- 440 023, Maharashtra.
3.2 Location (map showing general location, specific location and project boundary and
project site layout) with coordinates.
Details about the Project area are presented in Table 1.
TABLE - 1
DETAILS ABOUT THE PROJECT AREA
State Maharashtra
Tehsil / District Katol, Nagpur
Village Chakdoh near Bazargaon
Khasra No. 37, 38, 39, 40, 70, 71, 72, 73/1, 73/2, 74, 75, 78, 79, 81, 82, 83, 85, 88, 28, 30,
31,1, 3, 8/1, 8/2, 4/1, 4/2, 4/3, 29/1, 29/2,124/1, 124/2, 124/3, 69, 84, 90.
Pin Code 440 023
Area Presently 273.910 acres land area is under possession.
Topo sheet No. 55k_12, 55k_16
Geo-coordinates
Latitude : 21°8'33.16"N,
Longitude: 78°44'42.96"E
The index map is presented in Figure 1, Location map showing 10 km radius of study area shown in
Figure 2 and layout plan is given in Figure 3.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 8
FIGURE 1: INDEX MAP
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 9
FIGURE 2: STUDY AREA MAP
(10 KM RADIAL DISTANCE FROM THE PROJECT SITE)
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 10
FIGURE 3: LAYOUT PLAN
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 11
3.3 Details of alternate sites considered and the basis of selecting the proposed site,
particularly the environmental considerations gone into should be highlighted.
The land is procured by project proponent for manufacturing Defence warhead/ explosives. The
location falls under industrially backward D+ backward region as per PSI-07 policy of Government of
Maharashtra. Hence site is already selected by project proponent and no alternative site is required.
SIIL has adequate land area for proposed expansion and hence expansion is proposed within
existing land area. No additional land is required.
3.4 Size or Magnitude of Project
3.5 Project description with process details
3.5.1 Project description
SIIL have applied for total 18 numbers of products (refer table point 1.5 page1) out of this only five
products as mentioned in following table attracts Environment clearance as advised by MPCB vide
consent to Establish no. dt.15.6.2016.
Sr. No. Product name Maximum quantity (MTPA)
1. HMX and HMX Compounded Product 300
2. RDX and RDX Compounded Product. 125
3. Slurry /Emulsion Explosives 56250
4. Bulk Emulsion Explosives 125000
5. TNT (Tri Nitro Toluene) 625
6. Boiler 12 TPH (Coal fired) 12 TPH
3.5.2 Process Description for above five products
1. HMX:
HMX is high energy material and requires manufacturing various HMX based compositions for
Defence sector. The solution of Hexamine and Nitric Acid and Ammonium Nitrate and Acetic Acid is
nitrated under controlled conditions. Acetic Anhydride absorbs water released during reaction and
convert to Acetic acid. The product is simmered and crystallized and filtered via high performance
sieving media.
S. No. Items Total Capacity after Expansion
1. HMX and HMX Compounded Products 300 MTPA
2. RDX and RDX Compounded Products 3000 MTPA
3. Bulk Explosives 125000 MTPA
4. Slurry/Emulsion Explosives 56200 MTPA
5. TNT Explosives 3000 MTPA
6. PETN 3000 MTPA
7. Cast Booster 3000 MTPA
8. Detonating Fuse 150 MILLION METER/ANNUM
9. Boiler 12 TPH (Coal fired) 12 TPH
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 12
HMX Compounded Products:
HMX Compounded Products viz. OCTOL, SOKFOL AND SOMA is manufactured with mixing of TNT
or HMX and wax/polymer/ aluminium powder/graphite in the water medium at a temperature of
90-95 0C . When HMX is coated, the material is cooled, filtered and dried.
2. RDX:
Hexamine is nitrated with Nitric acid and Ammonium nitrate in Acetic acid medium. Acetic Anhydride
absorbs water released during reaction to convert to Acetic acid. The process is similar to HMX
manufacture except the reaction temperatures.
RDX Compounded Products:
RDX and TNT or RDX and wax/polymer are mixed in water at a temperature of 90-95oC when RDX
gets coated, the material is cooled, filtered and dried.
3. TNT Explosives:
TNT is explosives which required for manufacturing of initiating explosives viz. cast booster and
Defence compositions. Toluene is nitrated in two stages to get ONT, DNT and finally Tri nitro Toluene
(TNT) at high temperature. Further processes involves like washing, drying, flaking and finishing.
4. Slurry Emulsion Explosives :
These cartridge shaped explosives vary in size and diameter, depending on the blasting requirement.
These are mostly used in construction sites for building of roads and houses, quarrying, tunnelling,
small mines, underground work and for seismic exploration.
The production of emulsion explosives involves preparation of mother liquor solution made by chiefly
ammonium and sodium nitrate for use in the process is stored in insulated agitation tanks. For making
a batch, a measured quantity of mother liquor solution is transferred in to the mixing blender and
required quantity of fuel ingredients are added apart from emulsifiers. The slurry explosives
manufactured by mixing of ammonium nitrate and calcium nitrate mix apart from fuel like sulphate
and aluminium powder and at the prescribed time set, gaur gum and starch thickening agents are
added which increases the viscosity of the slurry matrix After developing the desired viscosity, the
cross linkers and gassing agents are added. The mix from the batch mixer is taken in to hopper
where it is cartridged in plastic leyflats / BMP tubes and finally packed in fiber board boxes and stored
at magazines for further use/ dispatch.
5. Bulk Emulsion:
These are essentially non explosives systems which are used for large scale blasting operations
where large quantity need to be charged every day viz. Open cast mines of Coal, Iron ore,
Manganese, Lime stone and Zinc among others.
Manufacturing of bulk emulsion process involves major three steps as manufacture of Emulsion
matrix (non explosive), preparation of Gassing agent and mixing of Emulsion matrix and Gassing
agent. The bulk matrix is transported to mining sites through bulk matrix delivery vehicles and
pumped down to the bore holes as per mining strata followed by chemicals mixing wherein it
becomes an explosive.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 13
3.6 Raw material required along with estimated quantity, likely source, marketing area of
final product/s, Mode of transport of raw Material and Finished Product.
Estimated raw materials quantity likely to be sourced from outside, mode of transportation is given in
Tables 2 and 3.
TABLE 2
REQUIREMENTS OF RAW MATERIALS FOR EXISTING & EXPANSION PRODUCTS
ANNUAL CAPACITIES
Sr.
No Name of Products Raw Material Requirement
(MTPA) for existing Capacity Raw Material Requirement (MTPA)
for Total Capacity after expansion 1. SLURRY / EMULSION
EXPLOSIVES (FINISHED) 1,00,000 MTPA 1,56,250 MTPA
1.1 Ammonium Nitrate 68900.000 107656.000
1.2 Calcium Nitrate 5000.000 7800.000
1.3 Sodium Nitrite 50.000 78.100
1.4 Sodium Chloride 17000.000 26562.500
1.5 Aluminium Powder 2600.000 4062.500
1.6 Sulphur 10200.000 15937.500
1.7 Mineral oil 2600.000 4062.500
1.8 Waxes 3200.000 5000.000
1.9 Emulsifier 2200.000 3437.500
2. PETN - (PENTA ERITHRITOL
TETRA NITRATE) (C & F) 2062.5 MTPA 3000 MTPA
2.1 Penta Erythritol 918.000 1335.000
2.2 Nitric Acid 5540.000 8060.000
2.3 Acetone 115.5.000 168.000
3.0 PENTOLITE / CAST BOOSTER
(FINISHED)
1875 MTPA 3000 MTPA
3.1 Trinitrotoluene (TNT) 940.000 1500.000
3.2 Penta Erithritol Tetra Nitrate
(PETN) (C & F)
940.000 1500.000
4.0 SORBITAN MONO OLEATE
(SMO) (C & F)
9162 MTPA 9162 MTPA
4.1 Oleic acid/ Fatty Acid 146.600 146.600
4.2 Fatty Acid 7605.000 7605.000
4.3 Sorbitol Syrup 5497.200 5497.200
4.4 Additives /Buffering Chemicals 64.100 64.100
5.0 POLY ISO BUTYLENE
SUCCINIC ANHYDRIDE
(PIBSA) C & F
6000 MTPA 6000 MTPA
5.1 Polyisobutylene 5680.000 5680.000
5.2 Maleic Anhydride 678.000 678.000
6.0 CALCIUM / SODIUM
NITRATE MELT (CAPTIVE)
3600 MTPA 3600 MTPA
6.1 Nitric acid (60%) 1980.000 1980.000
6.2 Sodium Carbonate 2345.000 2345.000
6.3 Calcium Carbonate 2345.000 2345.000
7.0 DUST SUPPRESSANT (Finished) 1000 MTPA 1000 MTPA 7.1 Lauric acid 150.000 150.000
7.2 Diethanolamine 150.000 150.000
7.3 Sodium Laurel Sulphate 3.000 3.000
7.4 SPP-3 100.000 100.000
7.5 Water 600.000 600.000
8.0 LEAD AZIDE (CAPTIVE) 9 MTPA 9 MTPA 8.1 Sodium Azide 4.380 4.380
8.2 Lead Nitrate 10.665 10.665
8.3 Dextrine 1.115 1.115
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 14
9.0 LEAD STYPHANATE (CAPTIVE) 3 MTPA 3 MTPA
9.1 Styphnic Acid 1.880 1.880
9.2 Magnesium oxide 0.300 0.300
9.3 Lead Nitrate 4.000 4.000
9.4 IPA 3.300 3.300
10. ASA MIXING & DRYING
(CAPTIVE)
12 MTPA 12 MTPA
10.1 Lead Azide 9.000 9.000
10.2 Lead Styphanate 2.550 2.550
10.3 Aluminium Powder 0.350 0.350
10.4 Sodium Stearate 0.100 0.100
11. HMX- Cyclotetra methylene
tetranitramine (C & F)
62.5 MTPA 300 MTPA
11.1 Hexamine 60.000 290.000
11.2 Nitric acid 145.000 700.000
11.3 Ammonium Nitrate 130.000 625.000
11.4 Acetic Acid 580.000 2790.000
11.5 Acetic Anhydride 530.000 2550.000
11.6 Para formaldehyde 5.000 150.000
11.7 Solvent 330.000 1670.000
12. FILLING / PRESSING FOR
FILLED SHELL (CAPTIVE)
62.5 Million Nos./A 62.5 Million Nos./A
12.1 ASA 9.400 MT 9.400 MT
12.2 PETN 1125.000 MT 1125.000 MT
12.3 Metallic Shells (Al/Cu) 62.5 Mill. Nos. 62.5 Mill. Nos.
13. DETONATORS (FINISHED) 125 Million Nos./A 125 Million Nos./A 13.1 Filled Shells 1.0 No./Unit 1.0 No./Unit 13.2 Fuse Head 1.0 No./Unit 1.0 No./Unit 13.3 GI/Cu wire set 1.0 No./Unit 1.0 No./Unit 13.4 Shock Tube (NONEL) 1.0 No./Unit 1.0 No./Unit 14. DETONATING FUSE 75 Million Meters/A 150 Million Meters/A
14.1 PETN 750.000 1500.000
14.2 PVC Granules 567.700 1135.000
14.3 BOPP 58.000 116.000
14.4 Fibrillated PP Yarn 155.000 310.000
14.5 Mercerized Thread 11.500 23.000
15. GI / CU WIRE COATING 90 Million Nos./A 90 Million Nos./A 15.1 PVC 360.000 360.000
15.2 GI/CU Wire 640.000 640.000
TABLE 3
REQUIREMENTS OF RAW MATERIALS FOR PROPOSED NEW PRODUCTS
ANNUAL CAPACITIES
Sr.
No. Name of Products Raw Material Requirement (MTPA)
for new product as applied CTE
Vide MPCB 7819 Dt. 15/06/2016
Raw Material Requirement(MTPA)
for Total Capacity of new product
after expansion 1. RDX AND RDX
COMPOUNDED PRODUCT
125 MTPA 3000 MTPA
1.1 Hexamine 54.000 1300.000
1.2 Nitric acid 102.500 2450.000
1.3 Ammonium Nitrate 87.500 2100.000
1.4 Acetic Acid 146.000 3500.000
1.5 Acetic Anhydride 360.000 8650.000
1.6 Solvent 62.500 1500.000
2. Bulk Emulsion 125000 MTPA 125000 MTPA 2.1 Ammonium Nitrate 80500.000 80500.000
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 15
Sr.
No. Name of Products Raw Material Requirement (MTPA)
for new product as applied CTE
Vide MPCB 7819 Dt. 15/06/2016
Raw Material Requirement(MTPA)
for Total Capacity of new product
after expansion Calcium Nitrate 12500.000 12500.000
2.2 Furnace oil 5700.000 5700.000
2.3 SMO 1250.000 1250.000
2.4 Sodium nitrite 250.000 250.000
3. Trinitro toluene (TNT) 625 MTPA 3000 MTPA
3.1 Ortho nitrotoluene (ONT) 415.000 1995.000
3.2 Oleum (20%) 1250.000 6000.000
3.3 Nitric Acid (58%) 680.000 3265.000
3.4 Nitric Acid (98%) 370.000 1765.000
4. Boiler 12 TPH (Coal fired)
4.1 Coal @ 50 MT/Hr x 20 Hr/day x
300 days
300000 300000
Source: All the raw materials are available from indigenous sources. Proposed raw materials will also
be received by road transport from adjoining destinations of Maharashtra, Gujarat, Rajasthan and
Chhattisgarh. And finished products will be supplied to various parts of India as mentioned in Table 4.
TABLE 4
LIST OF FINISHED GOODS CONSUMERS
S. No. Party Name Location
1 ACC Ltd. Kymore, MP
2 Apple Valley Kullu ,HP
3 Aparna Explosives Dehradun,UP
4 BCCL Dhanbad, Jharkhand
5 Bharat Dynamics Limited Hyderabad,AP
6 Central Coal fields Ltd. Rachi, Jharkhand
7 DGBR Shimla, Manali
8 Defence R & D Organisations (DRDO) Pune,MS
9 Eastern Coalfield Ltd. Asansol, WB
10 Gulab Explosives Kishangarh ,Rajshthan
11 Gaytri Enterprises (ALPHAGEO) Gujarat
12 Hutti Gold mines Raichur, Karnatak
13 Hindustan Zinc Limited Udaypur ,Rajshthan
14 Indian Dynamite Dehradun,UP
15 India Explosives Asansol,WB
16 Indian Ordinance Factories Khamaria,MP
17 Jindal Steel & Power Limited CG
18 Lafarge Cement CG
19 Mining Explosives Limited Satna ( MP)
20 Manganese Ore India Limited (MOIL) MP, Maharashtra
21 National Hydro Power Corporation H P
22 ONGC MP, HP, Chennai
23 Ragvendra Explo Chemicals Limited Jammu
24 Salvo Explosives Andhra Pradesh
25 Singreni Coalfields Ltd. AP
26 South Eastern Coalfield Ltd. M.P., C.G.,
27 Terminal Ballistics TN
28 Uranium Corporation Ltd. (UCIL) TN, Orissa
29 Ultratech Cement CG, Gujrat
30 Western Coalfield Ltd. M.P., Maharashtra
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 16
3.7 Resource optimization/ recycling and reuse envisaged in the project, if any, should be
briefly outlined.
By proper and efficient handling of raw materials to minimize the wastage.
By adopting continuous improvement in technology and processes for optimum yield and
minimum waste generation (product wise) will be achieved.
3.8 Environmental and Infrastructural Aspects
Availability of water its source, Energy/ Power requirement and source:
3.8.1 Availability of water and its source:
The existing water requirement is 646 KLD. Proposed additional water requirement will be 234 KLD.
Total water requirement 880KLD and shown in Table 5.
TABLE- 5 WATER REQUIREMENT (KL/DAY)
S. No.
Consent no.>>> ACTIVITIES
Formate1.0/BO /CAC-Cell/EIC No. NG-9456-13 23
rd CAC/1612001045
Dated 30/12/2016 (Existing)
Proposed water required for ultimate production capacity
Total water Requirement
1 Industrial cooling and boiler feed 310 0 310
2 Domestic purposes 95 25 120
3 Process whereby water gets polluted & pollutants are easily biodegradable
210 120 330
4 Process whereby water gets polluted & pollutants are not easily biodegradable and are toxic
0 10 10
5 Gardening
31 79 110
TOTAL
646 234 880
Source: Groundwater
The water requirement will be met through Tube wells. As the factory area is large, there is scope for
going for additional bore-wells to meet the additional water requirement.
3.8.2 Energy/ Power requirement and source:
The industry has been obtained contract demand for 2000 KVA by MSEDCL. (Load sanctions
Letter-Annexure – IX).
The present power requirement of the plant is met from connected power supply of 2350 KW.
Additional power requirement of 1000 KW will be sourced from the MSEDCL grid.
The Company has installed DG sets with capacities of 2 x 380 KVA, 1 x 400 KVA, 1 x 600 KVA each
as a standby arrangement so that production can be carried out uninterrupted which is necessary for
continuous process. Proposed for 1x300 KVA DG set in the proposed project site.
Fuel
The fuel i.e. Furnace Oil and Light Diesel Oil is sufficiently available domestically. The Company’s
process steam generation boilers would require coal, which is proposed to be procured from the
nearby coal mining areas of WCL.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 17
3.9 Quantity of wastes to be generated (liquid and solid) and scheme for their
Management/disposal:
3.9.1 Waste water generation & management plan Waste water generation given below Table 6
TABLE 6
WASTE WATER GENERATION (KLD)
Sr. No.
Use Effluent Loss Reuse*/ Recycle
Total waste water generation
1 Treated by Softener, RO & DM (All process use and other use )
110 22 88 110
2 Use in Various Processes
170 25 145 170
3 Use in Boiler, cooling, Scribing & Humidifies
23 287 23 23
4 Domestic Use (Plant + Hostel)
78 18 63 78
5 Plantation 110 22 110* 00
Total 491 374 319 381
The water and waste water management describes as below:
Drinking and industrial water requirement of the factory is fulfilled by bore wells /dug wells located
within the factory. Bore well water is treated via softener, RO and DM plants as per process
requirements otherwise fed directly to the process tanks. Water purification units and water coolers
are provided for drinking water in respective process buildings.
In all of the process plants effluent collection tanks have been provided to collect and recycle the
effluent within the plant. The Softener’s and DM plant regeneration waste water and RO reject water
is recycled fully in the plants.
The processes wise effluent treatment plants are located in the factory premises are described below:
3.9.1.1 ETP for Emulsion/Slurry, PETN, Cast Booster effluents:
In the manufacture process of slurry/emulsion explosives, periodic floor washing are necessary. This
gives rise to effluent generation from the process buildings. Effluents streams of all the processes are
connected via RCC/PVC pipe lines to the separate ETP tanks located in the respective plants. The
effluents from utilities area and laboratory are collected in the collections cum equalization tank.
i. Slurry plant effluents:
Effluent is pumped to central collection tank, from where it is pumped to aeration tank and then to
flash mixer where flocculating solution is added to the effluent. Subsequently, effluent is admitted to
flocculation tank. Thereafter, effluent flows to sand filter by gravity. Sludge from the bottom of the
settling tank is taken on sludge drying beds for solar drying. Filtrate of the sludge drying beds is
taken to the collection/equalization tank. Treated effluent allowed pumping for land application.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 18
Ii. Emulsion plant effluent:
The streams of ammonium nitrate rich effluent is collected in the respective process buildings. This is
further taken to ETP through concealed pipes and processed in the vacuum distillation unit for
recovery of distillate water. Both distillate and ccondensate water is recycled in the boiler. Residual
containing mainly ammonium nitrate is used in the process.
iii. PETN Plant effluent:
The PETN plant effluent is collected in the effluent collection tank. The effluent is neutralized by
mixing soda ash solution and send to the main ETP via counseled PVC pipe line. This is then passed
through tube settler and sand filter before sending to UF and RO. Treated water permeates is
recycled and RO reject water is further sent to vacuum distillation units.
iv. PETN Drying & Cast Booster plants effluent:
PETN drying plants and Cast booster plants generating effluents due to wetting of the floor for
maintaining humidity. These waters are collect in the ETP through counseled pipes / network of the
drains.
The entire effluents collected in the dedicated sintex tanks. From where it is transferred to aeration
tank and supernatant send to mixer cum settler where pH is adjusted by addition of MOL/Alum.
Effluent is treated by addition of coagulant and flocculent chemicals followed by sludge separation
and allowed to settle. The settled water from the settler overflows by gravity to the sand filter and
collected in treated water tank. The sludge collected from gravity sand filters and sludge drying beds
packed in the LDPE lined bags and send to CHWTSDF (MEPL) Butibori, Nagpur.
v. COB and Bulk Plant effluent:
The effluents from ammonium nitrate melt storage area and centralized oxidiser blend (COB) and
Bulk emulsion plant are mainly condensate water and floor washing contaminated with ammonium
nitrates. The condensate water is collected in SS collection tank and sending to boiler. Other waste
water is collected separately in a SS tank and recycled for dissolution of solid ammonium nitrate (AN)
and distillate in the ETP vacuum distillation units.
3.9.1.2 ETP for Chemicals plant LA/LS/ASA
The effluent arises from the lead azide, lead styphnate and ASA drying mainly during washing of the
explosives material and floor in the respective process. These effluents contaminated with residual
explosives and specific chemicals used for explosives destruction.Then effluent allowed draining via
counseled stainless steel pipe line to the respective collection tanks of the ETP.
The effluents are treated following the neutralization, settling and RO treatment. The RO treated
water is recycled in the process and rejects water send to the Multi effect evaporation system (MEES)
for distillation. Distillate water from MEES is recovered and sent to the boilers. The residual
concentrated sludge is disposed to CHWTSDF (MEPL) Butibori, Nagpur
3.9.1.3 ETP for SMO, PIBSA & CFB plant
In the manufacture process of SMO, PIBSA the reactors required periodic washing. This washed
water is collected in the oil removals cum collections tank. Then water is pumped to flash mixer where
flocculating solutions are added to the effluent. Subsequently, water flows to sand filter by gravity.
Sludge from the bottom of the settling tank is taken on sludge drying beds for solar drying. Filtrate of
the sludge drying beds is taken back to the collection/ aeration tank. Treated water is further treated
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 19
through aeration, clarification, UF and RO treatment in the STP. The treated water is used for
plantation.
3.9.1.4 HMX plant effluent
The effluent from HMX plant is neutralized in the reactor by soda ash and allowed to settle prior to
sending for vacuum distillation unit (VDU). Distilled water is used in the process. Concentrated waste
recovered from VDU is used suitably for dissolution of liquor in the slurry manufacturing process.
Spent acetic acid generated from the process is sold.
3.9.2 Total water balance
Total water requirement for the existing and proposed expansion is estimated to be 753 KLD. Total
water balance is shown in below Table 7 and water balance diagram presented in Figure 4.
TABLE 7 TOTAL WATER BALANCE (KLD)
Sr. No.
Use Intake Loss*/ Effluent
Reuse*/ Recycle
Fresh Water Requirements
1 Treated by Softener, RO & DM (All process use and other use )
880 22*/ 110 88 753
2 Use in Various Processes 340 25*/170 145 340
3 Use in Boiler, cooling, Scribing & Humidifies
310 287*/23 23 228
4 Domestic Use (Plant + Hostel)
120 18*/78 63 120
5 Plantation 110 22*/110 110* 00
Total 319 1441
1760 1760
880m3 water (Source from – existing Bore well 646+ Dug well 234m3) will use initially and treated
by Softener, RO & DM for various processes and Uses (in Various Processes +in Boiler, cooling,
Scribing & Humidifies + Domestic Use (Plant + Hostel) + Plantation). In this process effluent will
be generated 110 m3, out of which Recycle water will be available 88 m3 hence finally fresh water
requirements will be753 m3.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 20
FIGURE 4: WATER BALANCE DIAGRAM 3.9.3 Solid/hazardous waste generation and Management plan
Management plan for proposed EC
Solid and Hazardous wastes generated by the factory are boiler ash, chemical sludge and
ash from burning of sweeping wastes of the plants, damaged cartridges discarded liners/plastic bags,
cardboard boxes, etc. The details of solid and hazardous wastes generation and their disposal
practices are as discussed below:
1.0 Solid Waste (Non- Hazardous)
1.1 Boiler Ash
Boiler ash generated from boiler is removed from bag filters. The boiler ash collected and sold to the
brick manufacturers. The bio fuel ash of boiler (briquettes feeding) is utilized for leveling of the low
lying areas within the factory premises.
Values in (m3/day)
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 21
1.2 Biological Sludge from STP (Non- Hazardous)
The sludge collected on the sludge drying bed is allowed to sun dried. This is utilized as manure in
the plantation and gardening for green belt development within the factory premises.
TABLE 8 (A) DETAILS OF SOLID WASTE GENERATION
(AS PER CONSENT TO OPERATE: vide no. 1612001045 Dated 30/12/2016) Sr. No. Type of waste Quantity and UoM Treatment Disposal
1. Boiler Ash 45 MT/M Collection Brick manufacturing
2. Biological sludge 0.1MT/M Collection In the gardening
TABLE 8 (B)
DETAILS OF SOLID WASTE GENERATION (AS PER CONSENT TO ESTABLISH: vide no. 7819 Dated 15/06/2016)
Sr. No. Type of waste Quantity and UoM Treatment Disposal
1. Coal Ash 5775 MT/A -- Sale to Brick manufactures
2.0 Hazardous Waste
3.0 Chemical Sludge from Effluent Treatment Plant: (Category No. 34.3)
ETP sludge is separated at the sludge drying beds of ETP. Sun dried sludge is collected and stored
in LDPE lined bags and disposed to CHWTSDF, Butibori of M/s Maharashtra Enviro Power Limited,
Nagpur (Agreement Copy CHWTSDF-MEPL-SOLAR Annexure X).
4.0 Ash from destruction of contaminated discarded containers/ barrel/ liners/ cardboard
boxes, explosives wastes etc. (Category No. 36.2)
Empty HDPE bags of are collected and temporarily stored in the covered shed. The empty bags,
liners cardboard boxes and discarded containers and barrels have traces of explosives
contamination. Hence, all these materials are safely burnt under the supervision of competent person
at place approved by licensing authority in the licensed premises of the factory in compliance of Rule
42 of Explosives Rules, 2008. Ash is packed in the LDPE lined bags, stored in the covered shed in
the factory premises and disposed periodically to CHWTSDF, Butibori, of M/s Maharashtra Enviro
Power Limited, Nagpur.
TABLE 9 (A)
DETAILS OF HAZARDOUS WASTE GENERATION (AS PER CONSENT TO OPERATE: vide no. 3882 Dated 25/04/2014)
Sr. No. Type of waste Category Quantity UOM Treatment Disposal
1. Chemical sludge from ETP 34.3 25 MT/Y In-house CHWTSDF
2. Ash from burning of Explosives contaminated wastes
36.4 4 MT/Y CHWTSDF
3. Discarded containers/ barrels/ Ash from burning of discarded explosives contaminated liners /CFB/bags
36.2 50 MT/Y CHWTSDF
4. Waste oil 5.1 0.5 KL/Y Sale/ Recycle/ Reprocess
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 22
TABLE 9 (B)
DETAILS OF HAZARDOUS WASTE GENERATION (AS PER CONSENT TO ESTABLISH: vide no. 7819 Dated 15/06/2016)
Sr. No. Type of waste Category Quantity UOM Treatment Disposal
1. Waste /residues containing oil
5.2 0.5 MT/A -- CHWTSDF
2. Chemical sludge from waste water treatment
34.3 10 MT/A -- CHWTSDF
3. Ash from incineration of hazardous wastes
36.2 5 MT/A -- CHWTSDF
4. Distillation residue from contaminated organic solvents
36.4 8 MT/A -- CHWTSDF
3.9.4 Stack details and air pollution control measures
The modern set ups including scrubbers, de-dusting and bag filters for combating fugitive emissions
and particulate matter have been installed in the respective processes. Existing fuel burning air
pollution sources are:
i) Boilers stack Existing : 3 No. [6 T, (Stand by 2.0 T & 3.0 TPH)
Proposed : 12 TPH
ii) Thermo pack : 1 Nos. (1+1S)
iii) D.G. sets (Existing) : 4 Nos. (2 x 380 KVA & 1 x 600 KVA, 1x 400KVA)
(Proposed) : 1 No. x 300 KVA
5.0 Boiler:
There is coal/briquette fired boiler of 6 TPH. Other boilers of 2 TPH and 3 TPH are standby. The
changeover of boiler fuel from coal to biomass has greatly help in reducing the air pollution. Bag
filters (AJC-120-360 THERMAX make) have been installed in all the boilers. Coal dust is collected at
the bottom of bag filter hopper and sold to the brick manufacturers. The flue gases after bag filters
are discharged to atmosphere through Chimney of height 30 meter. The emissions of the boilers are
monitored periodically.
6.0 Thermic Fluid Heater:
The thermic fluid is heated through tubular coils. Briquette (agro waste product) is used as fuel in
thermo pack heaters. To discharge the emissions a chimney of height 30 m has been installed. The
mechanical dust collector has been installed as APC facility. The stack emissions is monitored
periodically.
7.0 D. G. Sets
The existing D.G. sets 2x 380 KVA, 1x 400 KVA and 1x 600 KVA are provided for emergency
operation of manufacturing process to avoid any accidental situation during MSEB power failure.
Proposed for 1x300 KVA. These DG sets are confirming the requirements of emissions standards of
E.P. Act. The expected pollutants emitted from the DG sets will be PM, SO2, NOx and CO. There will
not be any impact on surrounding area as this will be the occasional activities.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 23
4.0 SITE ANALYSIS
4.1 Connectivity.
The location falls under industrially backward D+ backward region as per PSI-07 policy of
Government of Maharashtra. The proposed project area located at Village Chakdoh, Near
Bazargaon, Tal-Katol, Dist- Nagpur Pin Code –440023, Maharashtra.
The site is well connected with Road/Rail. The details are as follows:
Nearest NH/Road: NH6 ~30.0 m, S (from main gate)
Dr. Babasaheb Ambedkar International Airport. Nagpur ~31.65 Km, SE
Nagpur Railway Station ~34.7 Km, E
4.2 Land Form, Land use and Land ownership.
The proposed activities will be within the existing plant. Presently 273.910 acres land area is under
possession. The total land identified for the proposed project is 2590.44 sq/m. The location falls
under industrially backward D+ backward region as per PSI-07 policy of Government of Maharashtra.
The details regarding the breakup of the land for the various activities of the proposed project is as
follows (Tables 10).
TABLE 10
AREA STATEMENT Name Of Building Area In Sq.M. Area in Acres Area in %
Approved proposed 2590.44 0.640 0.23
Ammonium nitrate storage section 5638.75 1.393 0.51
Magazine buildings 2797.55 0.691 0.25
(A) Explosives plant buildings 3786.67 0.935 0.34
(B) Explosives plant buildings 5827.74 1.440 0.53
(C) Explosives plant buildings 802.00 0.198 0.07
Non explosives buildings 7698.87 1.902 0.69
Green belt area 365795.35 90.390 33.00
Open space + additional green belt 713537.10 176.318 64.37
Total 1108474.47 273.91 100
4.3 Topography of the project area
The proposed project area located within the existing plant at Village Chakdoh, Near Bazargaon, Tal-
Katol, Dist- Nagpur Pin Code – 440023, Maharashtra. The project site lies at the Latitude: 21°
8'33.16"N and Longitude: 78°44'42.96"E on the Topo sheet No. 55k_12, 55k_16. The site specific
Topography map is given in Figure 5.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 24
FIGURE 5: SITE SPECIFIC TOPOGRAPHY MAP (10 KM Radius)
4.4 Existing land use pattern (agriculture, non-agriculture, forest, water bodies
(distance from HFL to the river), CRZ. In case of notified industrial area, a copy of Gazette
Notification should be given:-
The proposed project area located within the existing plant at Village Chakdoh, Near Bazargaon, Tal-
Katol, Dist- Nagpur Pin Code-440023, Maharashtra. The land is being used for Industrial Purpose.
Land allotment letter is enclosed as Annexures V, VI, VII & VIII.
There is no national park, wild life sanctuary, eco sensitive areas in surrounding 10 Km from the plant
boundary. CRZ is not applicable to the project.
Existing infrastructure
Project site photographs are attached in following Figure 6.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 25
FIGURE 6: PROJECT SITE PHOTOGRAPHS
5.0 PLANNING BRIEF
5.1 Planning concept (type of industries, facilities transportation Town and Country
Planning Development authority Classification.
Type of Industry
Manufacture Industrial Explosives and its Accessories.
Town and Country Planning Development authority Classification
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 26
The location falls under industrially backward D+ backward region as per PSI-07 policy of
Government of Maharashtra. The proposed project area located at Village Chakdoh, Near
Bazargaon, Tal-Katol, Dist- Nagpur Pin Code - 440023, Maharashtra. Adequate road facilities are
already available for transportation of raw materials as well as finished products.
5.2 Population Projection
The SIIL is presently employing 1513 and after proposed expansion 197 direct manpower will be
employed, in addition there will be approx 200 - 250 numbers will be engaged as indirect
employment. Since the proposed plant is located in the Nagpur district in which trained manpower
are readily available, therefore the employment will be given mostly to local people, so there will not
be any substantial increase in the population of local villages. However, due to increase economic
growth, the local youth will be benefited with respect to employment.
5.3 Land use planning (breakup along with green belt etc.) to be checked
The plantation and green belt covered land is 365795.35 sq.mt (90.39 acres), which is 33% of total project
area.
The breakup of the land along with greenbelt for the proposed project is given in Table 11.
TABLE 11 LANDUSE BREAKUP ALONG WITH GREENBELT
Name Of Building Area In Sq. M. Area in Acres Area in %
Approved proposed 2590.44 0.640 0.23
Ammonium nitrate storage section 5638.75 1.393 0.51
Magazine buildings 2797.55 0.691 0.25
(A) Explosives plant buildings 3786.67 0.935 0.34
(B) Explosives plant buildings 5827.74 1.440 0.53
(C) Explosives plant buildings 802.00 0.198 0.07
Non explosives buildings 7698.87 1.902 0.69
Green belt area 365795.35 90.390 33.00
Open space + additional green belt 713537.10 176.318 64.37
Total 1108474.47 273.91 100
5.4 Assessment of Infrastructure Demand
The basic infrastructure (Connective roads, Water resource vicinity) is required for the proposed
project is available at the project site as the proposed project is within existing plant. Apart from that
the additional infrastructure will be developed by the company as per the requirement.
5.5 Facilities Availability
Major basic facilities are available for the proposed project. Road, electricity, water, transportation
facility etc. are well developed in the surrounding area. The major new facilities required to be set for
the proposed project will be installation of process equipment at site within the premises along with all
the necessary infrastructures like storage house, internal access roads, office buildings, equipment
sheds etc.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The proposed activities will be within the existing plant. Presently 273.910 acres land area is under
possession. The total land identified for the proposed project is 2590.44 sq/m. The location falls
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 27
under industrially backward D+ backward region as per PSI-07 policy of Government of Maharashtra.
Remaining open area will be for future development as well as green belt development, parking bay,
etc. as given in land use statement (Table 10).
6.2 Residential Area (Non Processing Area)
Accommodation and hostel facilities are provided for limited staff/workers.
6.3 Green Belt
The plantation and green belt covered land is 365795.35 sq.mt (90.39 acres), which is 33% of total project
area.
6.4 Social Infrastructure:
The project area lies within the district of Nagpur. There is no requirement to build any social
infrastructure within the proposed plant area, however, the infrastructure for amenities to the workers
such as residential accommodation, kitchen, canteen, rest room etc. will be provided.
6.5 Connectivity (Traffic and Transportation Road, Rail/Metro/Waterways etc.).
The location falls under industrially backward D+backward region as per PSI-07 policy of Government
of Maharashtra. The proposed project area located at Village Chakdoh, Near Bazargaon, Tal-Katol,
Dist- Nagpur Pin Code – 440023, Maharashtra
The site is well connected with Road/Rail. The details are as follows:
Nearest NH/Road: NH6 ~30.0 m, S (from main gate)
Dr. Babasaheb Ambedkar International Airport. Nagpur ~31.65 Km, SE
Nagpur Railway Station ~34.7 Km, E
6.6 Drinking Water Management (Source & Supply of water)
The existing water requirement is 646 KLD, proposed water requirement 234 KLD. Total estimated
water requirement of the company is 880 KLD.
6.7 Sewerage system
Industry has installed STP of capacity 150 KLD based on Membrane Bio Reactor (MBR) for treatment
of sewage waste water of factory and colony premises.
The waste water collected from the plant and colony via counseled pipelines to the STP collection
tank and treated water is further send to boiler for utilization as process feed water and also used for
plantation purposes.
6.8 Industrial Waste/ Solid Waste Management
The industrial wastes generated in the form of solid wastes, and hazardous wastes will be collected,
segregated and disposed off as per CPCB guideline.
7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN
7.1 Policy to be adopted (Central/ State) in respect of the project affected persons
including home oustees, land oustees and landless laborers (a brief outline to be
given).
The proposed project does not have any directly displaced persons, due to acquisition of land. There
are also no land oustees or project affected persons or home oustees, thus R&R plan is not
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 28
applicable here. However, the priority for employment will be given to local persons living in the
adjoining villages. In addition to this, promoter will also contribute for the welfare of the people of local
surrounding under company’s CSR policy.
DETAILS OF CORPORATE SOCIAL RESPONSIBILITY BY SOLAR INDUSTRIES INDIA LIMITED:
CSR Programs
Company will be giving preference for spending the amount earmarked for CSR activities for the local
area where it operates. CSR activities will be either implemented by the company on its own or
through specialized agencies. Only such agencies will be assigned responsibility that carry a good
track record of undertaking and implementing such activities successfully. Industry live by the thinking
that “Service to mankind is service to God”. Keeping in line with philosophy, several initiatives are
committed to remain dedicated towards investing in a “Better Tomorrow for People”. The industry’s
three pillars of being responsible corporate sector are Health care, Conservation of natural resources
and protection of Environment.
Cost incurred towards EMP for earlier EC and CSR activities.
1. Contribution for MRI machine at the Central Institute of Medical Science Hospital, Nagpur
2. Contribution for up grading general wards at Swami Vivekanand Hospital, Nagpur
3. Rs. 2 Crores has been allocated for spending on medical equipment’s at various hospitals
4. Non Integral Flood light of nearby villages- Rs. 91123 /-
5. High Mast Pole 16 M- Rs. 312000 /-
6. High Mast Pole 12 M- Rs. 89200 /
7. Solar Cookers distribution - Rs. 190000 /-
8. Distribution of 450 improved chullahs to reduce dependency on wood fuel /forest
9. Rain water harvesting projects at village Shiva under Rural Infrastructure Development
10. Contribution to “Vanrai Foundation” engaged in enabling environmental stability & ecology
11. Staff recreation - Rs. 8,54,266 /-
Infrastructure facilities developed by the company for the welfare of workers, employees and nearby
villages with budgetary provisions.
1. SIIL providing Residential quarters to workers.
2. Play ground with various equipment.
3. Providing health cover with Mediclaim policy.
4. Arranging Health Checkup camp, eye checkup camp.
5. Scholarships to the employees's children / allowance for workers.
Monitoring
CSR committee authorized by board of directors will monitor CSR activities and proper utilization of
funds. The CSR committee is fully authorized to delegate appropriate authority to any employee of
the company for properly carrying out CSR activities.
Environment Impacts and Measures
Schematic representations of the feasibility drawing which give information of EIA purpose.
S. No. Particulars Impacts Remediation Proposed
1. Change in
Land use.
There will be change in land
use on permanent basis due
There will be change in land use on permanent
basis due to installation of machineries and
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 29
S. No. Particulars Impacts Remediation Proposed
to installation of machineries
and equipment.
equipment. The land is procured by project
proponent.
The proposed project area located within the
existing plant at Village Chakdoh, Near
Bazargaon, Tal-Katol, Dist- Nagpur Pin Code
440023 Maharashtra. The land is being used for
Industrial Purpose.
2. Transportatio
n
of material
The existing network of
transport gets pressurized
The proposed activity will marginally increase in
Traffic density. The proposed project lies within
existing plant thus, infrastructural facilities/road
accessibility are already developed. However, will
maintain the existing road.
3. Gaseous and
Particulate
Emission to
the
atmosphere
Air quality All necessary steps will be followed to minimize
the emission from point sources as well as line
sources. Thus the standards of Stack Emission
and Ambient Air quality will be maintained as per
prescribed limits.
4. Discharge of
effluent
Impact of water quality. Zero discharge is proposed.
5. Withdrawal of
ground /
surface water
Availability of ground/surface
water is affected.
Water will be sourced from bore wells. Permission
regarding drawl of water is granted from water
resource department.
6. Operation of
equipment
and vehicles
likely to
generate
noise.
Impact on human health due
to excess noise level beyond
permissible level.
All the process equipment will be installed on anti-
vibration pad with sufficient provisions to minimize
generation of noise. The high noise generating
equipment like generator will be enclosed with
noise suppressing enclosures.
The buildings as well as boundary wall and green
belt will ensure the attenuation of noise outside
the boundary within the prescribed limits.
7. Fire Hazard
due to
storage
of fuel etc.
Risk to the surrounding
habitation.
Necessary precautions to prevent fire and all the
provisions to control fire shall be provided.
8. Employment
to outsiders
Socio-economic disparity with
local community
Priority of employment will be given to local
people, as already sufficient qualified and trained
local youth area available.
9. Cultural
impact
Local population feels isolated The promoters proposed to employ local masses
in the project hence no such impact on cultural
diversity is likely to take place.
10. Disposal of
solid and
hazardous
wastes
Create odorous problem,
nuisance condition related to
the disposal of solid wastes.
Deterioration of soil,
productivity pollution in ground
water/surface water due to
leaching and surface runoff.
Domestic wastes will be segregated for organic
and inorganic. Organic wastes will be used for
composting and inorganic for approved vendors.
Disposal of hazardous wastes will be done as per
hazardous wastes handling and disposal rule.
Prefeasibility Report
Anacon Laboratories Pvt. Ltd. Nagpur, Maharashtra. 30
8.0 PROJECT SCHEDULE & COST ESTIMATES
SCHEDULE FOR APPROVAL AND IMPLEMENTATION
Proposed Project
Activities at the site will be carried out after grant of Environmental clearance from Ministry of
Environment & Forests. The schedule for implementing the proposed project is given in Table 12.
TABLE 12
PROJECT IMPLEMENTATION SCHEDULE
Particulars Implementation Date/Time Period
Commercial Production of proposed additional products
Commercial Production will be started After Receipt of Environmental Clearance
8.1 Estimated project cost along with analysis in terms of economic viability of the project.
The project cost is estimated to be Rs. 184.01 Crores.
Sr. No. Fixed assets Proposed expansion project cost (Rs. Crores)
1. Land 005.29
2. Building / Premises 061.98
3. Plant, Machinery and equipment 113.28
4. Other miscellaneous 003.46
Total cost 184.01
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 Financial and social benefits with special emphasis on the benefit to the local People
Including Tribal Population, If Any, in the Area.
On overall assessment of the project with consideration of technical and financial aspects, it is
concluded that the proposed explosive manufacture plant is technically highly feasible and financially
highly profitable.