Social Monitoring Report Project Number: 43031-013 Semi-Annual Report July 2016 PRC: Hunan Xiangjiang Inland Waterway Transport Project Prepared by Hunan Yuhui Hydraulic and Hydropower Construction Supervision and Consulting Co., Ltd. for the People’s Republic of China and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. Asian Development Bank

PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

Social Monitoring Report Project Number: 43031-013 Semi-Annual Report July 2016

PRC: Hunan Xiangjiang Inland Waterway Transport Project Prepared by Hunan Yuhui Hydraulic and Hydropower Construction Supervision and Consulting Co., Ltd. for the People’s Republic of China and the Asian Development Bank. This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Asian Development Bank

Page 2: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

SJJZZ Certificate for No. 20010176 Loan No.: 2962-PRC

Hunan Xiangjiang River

Tugutang Navigation and Hydropower Complex

Monitoring and Evaluation Report of Land

Acquisition and Resettlement

(The Sixth Issue)

Hunan Yuhui Hydraulic and Hydropower Construction Supervision

and Consulting Co. Ltd

July, 2016

Page 3: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

2

Approved by: Xiong Zhifeng

Reviewed by: Xiao Lu

Checked by: Xu Jinyuan

Prepared by: Xu Jinyuan

Luo Zhilong Peng Hongwu

Page 4: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

Introduction

Entrusted by Hunan Provincial Water Transportation Construction &

Investment Group Co. Ltd. (hereinafter called the construction unit, i.e.

HPWTCIG), Hunan Yuhui Hydraulic and Hydropower Construction Supervision

and Consulting Co. Ltd.(hereinafter called our company), as the independent

external monitoring and evaluation unit, is responsible for independent external

monitoring and evaluation on land acquisition and resettlement for ADB loaned

Tugutang Navigation and Hydropower Complex Hunan of Xiang River Inland

Water Transportation Project.

Our company established Monitoring and Evaluation Department of Land

Acquisition and Resettlement for Tugutang Navigation and Hydropower Complex

(hereinafter called the M&E Department) in Dec. 2012. In April, 2013, the M&E

Department worked out Terms of Reference for Monitoring and Evaluation on

Land Acquisition and Resettlement for Tugutang Navigation and Hydropower

Complex, and started monitoring and evaluation work from May of 2013. The

M&E Department has performed five field monitoring respectively in June 10~13,

2013, June 3~6, 2014, Jan. 4~7, 2015, July 10~13, 2015, and Dec. 26~30, 2015,

and has relevantly submitted the M&E reports for five times to HPWTCIG and

ADB.

In June. 26~30, 2016, the M&E Department has organized the investigators

to perform a 5-day on-site investigation: the monitoring personnel, the

construction unit (HPWTCIG), the migration management institution in the project

site, the design unit, the migration integrated monitoring and some of the affected

people's representatives have participated the meeting, collected the

resettlement relocation data, and knew the resettlement progress. In June 16~17,

the construction unit (HPWTCIG) invited the ADB experts to perform professional

training to the various participating parties and propose instructive advices to the

monitoring report. On this basis, we have completed the Sixth Monitoring and

Evaluation Report (this Report is up to the end of June 2016).

Page 5: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

2

The M&E Department personnel have sincere thanks to the active

cooperation and support from the ADB, the construction unit (HPWTCIG) and the

migration management agents in the project site and other relevant units and

personnel.

Page 6: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

1

Contents 1. GENERAL ....................................................................................................................... 1 

1.1 REPORT BACKGROUND ............................................................................................................................... 1 

1.2 INFLUENCE RANGE FOR RESETTLEMENT ................................................................................................... 2 

1.3 RESETTLEMENT PLANNING ........................................................................................................................ 4 

1.4 RESETTLEMENT IMPLEMENTATION STATUS ................................................................................................ 5 

1.5 RESETTLEMENT IMPLEMENTATION MONITORING OBJECTIVES AND WORK CONTENT ............................. 10 

2 MONITORING & ASSESSMENT OF RESETTLEMENT IMPLEMENTATION ..... 1 

2.1 MONITORING METHOD ............................................................................................................................... 1 

2.2 MONITORING AND EVALUATION ON PERMANENT LAND ACQUISITION ...................................................... 3 

2.3 MONITORING AND EVALUATION ON HOUSE DEMOLITION AND RESETTLEMENT ....................................... 5 

2.4 MONITORING AND EVALUATION OF RESIDENTS RELOCATION ................................................................... 9 

2.5 M&E OF TEMPORARY LAND OCCUPATION .............................................................................................. 10 

2.6 M&E OF SPECIAL WORKS AND PROTECTION WORKS ............................................................................. 11 

2.7 M&E OF RESETTLEMENT COMPENSATION ............................................................................................... 13 

3. EVALUATION ON ADMINISTRATIVE ORGANIZATIONS OF RESETTLEMENT IMPLEMENTATION AND THEIR OPERATION CONDITIONS17 

3.1 ORGANIZATION SETUP .............................................................................................................................. 17 

3.2 ORGANIZATION RESPONSIBILITIES ........................................................................................................... 19 

3.3 OPERATION CONDITIONS OF ORGANIZATIONS ......................................................................................... 26 

4 MONITORING & EVALUATION OF MEASURES ON RESTORATION OF LIVING STANDARD OF RELOCATEES ...................................................................... 28 

4.1 RESTORATION PLAN OF LIVING STANDARD OF RELOCATEES .................................................................. 28 

4.2 IMPLEMENTATION CONDITIONS OF RECOVERY MEASURES OF LIVING STANDARD OF RELOCATEES ...... 29 

4.3 EVALUATION OF RECOVERY CONDITIONS OF RELOCATEES LIVING STANDARD ...................................... 31 

5 ALTERATION OF ACCESS ROAD AT SONGBAI KILOTON TERMINAL AND EXECUTION ............................................................................................................ 31 

6. EVALUATION OF AID OF VULNERABLE GROUPS ........................................... 34 

6.1 STATUS QUO OF VULNERABLE GROUPS ................................................................................................... 34 

6.2 VULNERABLE GROUPS AID PLAN ............................................................................................................. 34 

6.3 ASSISTANCE IMPLEMENTATION OF VULNERABLE GROUPS ...................................................................... 34 

7 RELOCATEE COMPLAINT AND GRIEVANCE MECHANISM EVALUATION .. 37 

Page 7: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

2

7.1 EXISTING GRIEVANCE MECHANISM ......................................................................................................... 37 

7.2 PROPOSED GRIEVANCE MECHANISM........................................................................................................ 38 

7.3 COMPLAINT RECORDS .............................................................................................................................. 39 

7.4 EFFECTIVENESS OF GRIEVANCE ............................................................................................................... 40 

8. PUBLIC PARTICIPATION AND INFORMATION DISCLOSURE EVALUATION41 

8.1 PUBLIC PARTICIPATION.............................................................................................................................. 41 

8.2 INFORMATION DISCLOSURE ...................................................................................................................... 41 

8.3 FOLLOW-UP WORK .................................................................................................................................... 42 

9 RESULTS OF MONITORING AND EVALUATION .................................................. 42 

9.1 EVALUATION OF RESETTLEMENT IMPLEMENTATION ................................................................................ 42 

9.2. EVALUATION ON RESETTLEMENT IMPLEMENTATION & MANAGEMENT ORGANIZATIONS AND THEIR

OPERATION CONDITIONS ................................................................................................................................ 43 

9.3 MONITORING & EVALUATION ON MEASURES FOR RESTORATION OF LIVING STANDARD OF

RELOCATEES ................................................................................................................................................... 43 

9.4. EVALUATION ON AID TO VULNERABLE GROUPS ..................................................................................... 43 

9.5 EVALUATION ON RELOCATEE'S COMPLAINT AND GRIEVANCE MECHANISM ............................................ 43 

9.6. PUBLIC PARTICIPATION AND INFORMATION DISCLOSURE EVALUATION .................................................. 43 

9.7 PROBLEMS AND FOLLOW-UP WORK ......................................................................................................... 44 

10 COMPLIANCE OF LOAN AGREEMENT ............................................................... 44 

SCHEDULE 1:SUMMARY TABLE OF PERMANENT LAND REQUISITION ...... 41

SCHEDULE2: SUMMARY OF HOUSING DEMOLITION ..................................... 42

SCHEDULE 3:TABLE OF LAND ACQUISITION AND RESETTLEMENT INFLUENCES ........................................................................................................ 44

SCHEDULE4: COMPENSATION AND RECOVERY OF TEMPORARY LAND OCCUPATION ........................................................................................................ 46

SCHEDULE5: INVESTMENT OF LAND ACQUISITION AND RESETTLEMENT COMPENSATION .................................................................................................. 47

ATTACHMENT1:NAME LIST OF MONITORING AND EVALUATION MEETING STAFF ................................................................................................... 51

ATTACHMENT 2: MAIN DATA CONTENT FOR SUPERVISION AND EVALUATION CONSULTING ................................................................................ 52

ATTACHMENT 3: NAME LIST OF AFFECTED PEOPLE BEING CONSULTED 53

ATTACHMENT 4: SITE PHOTOS ......................................................................... 54

ATTACHMENT 5: COMPLAINT LETTER ............................................................. 58

Page 8: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

1

1. General

1.1 Report Background

The dam site of Hunan Xiangjiang Tugutgang Navigation Complex is located in

Yunji Town, Hengnan County, Hunan Province, 39km away from Hengyang City. The

Complex belongs to a Grade II project; main permanent hydraulic structures are in

Class 3. The main structures of the Complex include: one kiloton single-line ship lock,

with annual through capacity of 14.2 million ton; 17-sluice gate, with net width of 20m;

one hydropower station, with total installed capacity of 90MW(4×22.5MW bulb-type

tubular units) and annual power generation of 359 million kWh; one 728.5m fish way;

access roads on both banks; working auxiliary bridge on dam crest; bank protections;

administrative area of the Complex; waterway and navigation marks and auxiliary

works; one highway bridge crossing the river, with the length of 1,138m and width of

15m; and construction of kiloton docks in Songbai Terminal of Changning and Yunji

Terminal of Hengnan, the aid work to women and children; and Hengnan new water

source project.

The Complex is a project with major functioning as navigation, combined with

power generation, and compatible with irrigation, water supply and aquaculture. The

Project aims at improving a low carbon waterway transport system on the Xiangjiang

River in Hunan province, and developing an efficient, safe, affordable, and sustainable

inland waterway transport system in the province.

Estimated total investment of the Project is 2.954 billion Yuan, of which, ADB loan

is 150 million USD.

Total planned construction period of the Project is 50 months (from November of

2011 to December of 2016).

By the end of June, 2016, two sets of 22.5MW unit have been commissioned for

power generation.

The Hunan Provincial Department of Transportation (HPDOT) is the project

execution unit, being responsible for the overall project implementation; Hunan

Provincial Water Transportation Construction & Investment Group Co. Ltd.(HPWTCIG,

the original Hunan Xiangjiang Navigation Construction Co., Ltd.) is the project

implementation unit, being responsible for the project construction; and Hunan

Hydro&Power Design Institute is the resettlement planning and design unit, being

responsible for the resettlement project planning and design for project construction

Page 9: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

2

land requisition; Hunan Xiangyi Resettlement and Engineering Supervision

Consulting Company is the comprehensive supervision unit for resettlement.

1.2 Influence Range for Resettlement

1) Affected Area of Reservoir Inundation

(1) Inundated Area

At the normal reservoir level of 58m, reservoir inundation involves 98 villages in 13

townships of Hengnan, Changning and Leiyang.

Population and houses: 74 persons of 16 households are in inundated area, with

houses area of 8367.81m2 (of which, private house is 4908.25m2 and public house is

3459.56m2); 126 persons of 24 households are affected, with house area of 2807.9m2

(all in private).

Land: inundated water area of 39602.76 mu and inundated land area of 9831.72

mu (of which, 6036.9mu are farmland).

Special facilities: submerging 0.851km Class IV road, 6.883km rough road, right

highway bridge, 13 highway culvert, one ferry, and 72 landing stages; affecting 0.932km

110kV lines, 0.32km 35kV lines, 9.203km 10kV lines, 18.374km 380kV lines, 11.016km

China Telecom lines, 2.53km China Unicom lines, 2.402km China Mobile lines, 1.52km

radio and television lines, 0.77km national defense optical cables, 3.6km post and

telecommunications lines; and the inundation affects one medium electric pumping

station, 24 sluice gates, three mini-hydroelectric stations, and eight water supply

pumping houses.

(2) Affected Area

Total length of bank failure in reservoir area is 34.39km; areas of affected

farmland and house site in inundated area are respectively 319.41mu and 2.46mu,

with affected population of 22 persons in 4 house of 4 households and affected house

area of 760.38m2.

2) Construction Area of the Complex

The construction area of the Complex requires permanent land acquisition of

818.45mu (including 475.13mu farmland), relocation of 78 persons from 19

households, house removal of 5939.53m2, and temporary land occupation of

386.33mu (including 179.58mu farmland).

3) Construction Area of 1,000dwt berth

In August 2014, the access road program of Changning Songbai 1,000dwt berth

Page 10: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

3

has been changed, the changed content and reasons are as follows: in October 2013,

the People's Government of Changning City assigned the working team to perform

field investigation of initial construction according to the Songbai 1,000dwt berth's red

line graph of land occupation supplied by Hunan Provincial Transportation & Survey

Design Institute (hereinafter called the transportation institute), as per the Hunan

Xiangjiang Tugutang Navigation Complex Construction Land Requisition and

Resettlement Planning Design Report authorized by Hunan Provincial Reservoir

Resettlement and Development Management Bureau in June, 2012. During

investigation, they extensively consulted with local masses, and after investigation

they thought that the land occupation planning of berth was reasonable, but the use of

the existing vegetable Village Road as an access road had two major problems: (a)

the village road is 4m wide, which will be difficult for large freight vehicles; (2) as the

dwellings on both sides of the village are dense, the terminal building will cause large

traffic potential danger with noise pollution and dust issues. For the above reasons,

the People's Government of Changning City hopes to be able to choose a more

reasonable access road.

The construction unit (HPWTCIG) paid high attention to the issues proposed by

the mass in berth construction, and organized the relevant units to hold a meeting on

Nov. 19, 2013 about berht's access road disposal for Songbai 1,000dwt berth. The

Meeting decided to take account of local people's reasonable proposals, re-select a

site to build the access road, and urge the transportation institute to compile a design

alteration drawing as soon as possible.

From April 2014 to August 2014, in the light of the new design alteration drawing,

the construction unit (HPWTCIG) organized Changning city relevant units and Hunan

Hydro & Power Design Institute, as well as the resettlement comprehensive

supervision to re-investigate, count, re-check and confirm the physical indexes of the

land requisition scope (incl. wharf area and wharf access road) of Songbai 1,000dwt

berth, and make relevant modifications to the resettlement planning in the land

requisition area. After this alteration, the Songbai 1,000dwt berth has permanent land

requisition of 41.16 Mu, including paddy field of 31.65 Mu and pond of 5.2 Mu; 7

households with 33 rural people need to be relocated with demolition of houses of

2020.86 m2 , including public house of 60m2 and private house of 1960.86m2.

Overall cost for compensation of land acquisition of Songbai berth after such

alteration will be 5.2337 million yuan, including compensation cost of rural

Page 11: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

4

resettlement of 3.3175 million yuan, compensation cost of re-built of special facilities

of 0.7647 million yuan, other costs of 0.4127 million yuan, basic reserve cost of

0.3596 million yuan and related taxes and charges of 0.3792 million yuan.

The permanent land requisition of Hengnan County Yunji 1,000dwt berth will be

17.82 Mu (grass land of 17.31 Mu and residential land of 0.51 Mu). The house

demolition will be 258.4 m2 that all are private houses.

1.3 Resettlement Planning

1) Reservoir Area

At design level year, relocated population in reservoir area is 203 persons from

40 households; resettled population for production is 7487 persons.

Relocations and resettlements adopt method of decentralized backward moving.

Production settlement: 5514 persons are arranged in farmland protection works,

1182 persons have monetary compensation, 646 persons are arranged in adjusted

farmlands, and 145 persons are arranged in the secondary and the tertiary industries.

Protective Works: 75 farmland shelter-forests are planned to protect 4838mu

farmland; 6 immersion treatment areas are constructed to protect 79.64mu farmland;

reservoir bank protection of 30.037km are constructed.

2) Construction Area of the Complex

At design level year, relocated population in the Complex construction area is 80

persons of 19 households; resettled population for production is 405 persons.

Relocations and resettlements adopt method of decentralized backward moving.

Production settlement: 93 persons have monetary compensation, 312 persons

are arranged in adjusted farmlands.

3) Construction Area of 1,000dwt berth

At the design level year, the Songbai 1,000dwt berth construction area will

relocate 7 households with 33 people and production resettlement of population is 67

people after alteration.

Relocation and resettlement adopts method of decentralized backward moving.

Production settlement: 5 persons have monetary compensation, 62 persons are

Page 12: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

5

arranged in adjusted farmlands.

Hengnan County Yunji 1,000dwt berth has no relocation population and no

production resettlement of population.

1.4 Resettlement Implementation Status

On Sep.14, 2013, Ministry of Land and Resources approved land use for

construction purpose of Tugutang Navigation and Hydropower Complex through

No.719 MLR Letter (2013).

1) Land Acquisition and Resettlement

Reservoir Area: According to Resettlement Plan, total permanent land

acquisition in reservoir is 5605.71mu. Up to now, all permanent land acquisitions of

5605.71mu (including 1878.34mu farmlands) in reservoir have been 100%

accomplished.

The temporary land requisition compensation is undergoing along with the

construction progress of special project in the reservoir area, which can satisfy the

project building at present.

11175.71 m2 of houses were planned to be demolished. A total of 10204.35 m2

had been demolished in actual. Due to protective schemes taken, the houses of

Leiyang City would not be demolished any longer. All house demolition therefore had

been completed.

40 household with 203 rural persons were planned to be relocated. 38

households with 180 rural persons had been actually relocated excluding 7

households with 41 persons from Yajiang Village, Daheyu township of Leiyang City

due to design optimization through protective schemes rather than house demolition.

The demolition and relocation of the reservoir area had been completed.

Totally 538 copies of land requisition and production Resettlement Agreement are

signed with relocation population of 5872, occupying 75% of the planned production

resettlement population.

Dam Area: According to Resettlement Plan, total permanent land acquisition of

dam is 818.45mu. In actual, permanent land acquisition of 802.61mu (including

641.19mu farmland) of four villages in dam area had been accomplished.

Page 13: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

6

The planned temporary land occupation is 386.33 Mu (including cultivated land of

179.58 Mu and the pond of 17.55 Mu). The temporary land requisition has been

completed.

The planned house demolition is 5,939.53m2. In actual, 5939.53m2 house

demolition had been accomplished.

The planned rural population to be relocated are 19 households with 80 people.

In actual 23 households of 90 persons had been relocated, which had been

completed.

Berth construction area: after the alteration, Songbai 1,000dwt berth had

completed permanent land requisition of 41.16 Mu, relocated 7 households with 33

people, and housing demolition of 2020.86 m2. All displaced households chose

backward relocation and scattering in the village. Constructions of the berth and

ancillary facilities have been all completed, and gotten acceptance, with total

investment of 33.28 million Yuan, including equipment fund 1.553 million Yuan.

Construction of Yunji Berth has not started yet.

New water source construction area: the land requisition has been fully

completed: land compensation and land rehabilitation work for permanent land

requisition is 8.65 Mu (all being cultivated land), temporary land requisition is 251.09

Mu (including cultivated land of 106.32 Mu).The construction had been completed.

2) Construction and Compensation of Special Project

①Construction and Compensation of Special Project in Reservoir Area

1. The reservoir and bank protection works including 56 places of 30.037km

were procured in Nov. 2013. Only three sections with 1.398km have not been

completed yet. The completed works amount to 95.4% of total quantity. Water

impounding has reached El.58m now. The uncompleted section is due to

inconvenient transportation, and will be treated as per the modified design scheme.

2. The 21 culvert gates and Lijiang power station rehabilitation works together

with reservoir bank protection works have been all completed. The completed works

amounts to 100% of the total contract quantity.

3. The reconstruction length of reservoir road and tractor path is 6.683km, it has

been completed 5.399km by end of this June, accounting for 84% of total work,

Page 14: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

7

including 4.38km completed this Jan¬Jun, accounting for 65.5%.

4. It proposed to rebuild 9 bridges at reservoir area. All have been rebuilt,

accounting for 100% of total work, including 4 bridges completed this Jan¬Jun,

accounting for 44%.

5. The first batch of reclamation works (farmland protection) on Nov. 3rd, 2014

includes 3191mu, of which, 43 blocks are in Hengnan County and 5 blocks in are

Changning City (including inundation treatment). Hengnan County and Changning

City made binding bids of 4 bid sections to those large and concentrated blocks, and

made inviting bids of 14 bid sections to those small and scattered blocks. Regarding

constructions of all the 18 bid sections (contract sections), 3.985 million m3 earthwork

had been completed, accounting for 99.5% of the contract quantity, including 485

thousand m3 in this Jan¬Jun, accounting for 10% of total quantity; the length of

excavation and lining of main canals & ditches is 12.6km, and 8.4km has been

completed, accounting for 66% of total work. In which, A,B and C blocks (90 mu) in

Shuangfa of Changning City have been all completed and gotten acceptance of

separated project which has been handed over to the villagers for cultivation. Main

works of the first-batch reclamation works has been basically completed. However,

the uncompleted works includes lining of 1.26km main drainage ditches in 8 blocks, 9

foot bridges, and about 5,000m3 filling and reclamation earthwork in Block B in Binghe

of Hengnan.

6. The second batch of reservoir reclamation works (farmland protection) bidding

in middle of November 2015 includes 29 blocks of 2121mu (including 17 blocks of

1543 mu in Changning city and 12 blocks of 587mu in Leiyang City, 10 bid sections in

total). Four bid sections in Changning reservoir have started, and the top soil stripping

have been completed, accounting for 30% of total work; the fifth bid section (Qingnian

Village Block B, C, D) has not started, as the ground (EL.56.8m) immerse in the water.

The Employer plans to lift up the gate and release water until to the lower level. In

terms of the reclamation works of 5 bids sections in 12 blocks in Leiyang City, it has

been finished with technical disclosure, borrow area acquisition, building of access

road, and topsoil stripping, accounting for 28% of total work. Due to frequent rainy

days, the second batch of reclamation work is in slow progress.

7. The other ground attachments (small special facilities) in the reservoir area has

Page 15: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

8

been completed by one-time monetary compensation.

Construction and compensation of Special Facilities in Dam Area:

compensation and renovation work of temporary water system recovery, transport

facilities, power transmission and conversion facilities, communication facilities,

power line etc. have been completed. Water pumps have been installed, 2880m canal

has been completed, accounting for 96% of total work, including 2340m in Jan-Jun.

2016.

Compensation of Special Facilities in Berth Area: restoration of water system,

transport facilities, power transmission and conversion facilities, communication

facilities, etc. of Songbai berth had all been completed.

3) Land Requisition and Resettlement Funds Appropriation

The total investment for land requisition and resettlement compensation of the

Tugutang Navigation Complex Project at preliminary design phase is 515.1779 million

Yuan, of which the land requisition and resettlement investment of the reservoir

inundation affected area is 466.002 million Yuan, the land requisition and resettlement

investment of the complex project construction area is 46.9344 million Yuan, of the

1,000dwt berth area is 2.2415 million Yuan. After the adjustment of land

compensation fee and alteration of Songbai 1,000dwt berth, the total investment for

land requisition and resettlement compensation (with tax) of the Tugutang Navigation

Complex Project is 559.5112 million Yuan, of which the land requisition resettlement

investment of the reservoir inundation affected area is 496.5111 million Yuan, the land

requisition resettlement investment of the complex project construction area is

57.4354 million Yuan, of the 1,000dwt berth area is 5.5647 million Yuan. The total

investment condition of land requisition and resettlement compensation after

adjustment refers to Table 1.4-1.

Total Investment Condition of Land Requisition Resettlement Compensation after Adjustment

Table 1.4-1 Unit: 104 Yuan

No. Item Total Reservoir

Area Dam site Dock area Part I Rural resettlement compensation 15407.3 11456.49 3591.23 359.58

Land Compensation Subsidy 11740.48 8453.22 3106.23 181.03

2. Compensation for Houses and Ancillary Facilities 1223.98 735.78 342.09 146.11

3 Subsidy for housing poverty household 115.98 75.48 40.5

Page 16: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

9

Total Investment Condition of Land Requisition Resettlement Compensation after Adjustment

Table 1.4-1 Unit: 104 Yuan

No. Item Total Reservoir

Area Dam site Dock area

4 Living subsidy during transition period 204 197.3 6.7

5. production relocation Supplemental Fee 88.73 88.73

6. Infrastructural Compensation 156.57 101.28 39.57 15.72 7. Subsidy for relocation 20.28 13.5 4.8 1.98

8 Sporadic fruit tree and tomb compensation 56.84 45.04 7.06 4.74

9. Agriculture and subsidiary facilities compensation 348.96 347.36 1.6

10. Rural small scale Hydropower facilities compensation 1451.48 1398.8 49.38 3.3

Part II Special project recovery and rebuilding compensation fee 8304.64 7560.56 667.61 76.47

1. Grade road rehabilitation costs 369.22 369.22

2. Rehabilitation and renovation fee of transportation facilities around the reservoir 3005.72 2971.36 28.86 5.5

3. Rehabilitation and renovation fee of transmission and transformation facilities 148.22 79.62 41.08 27.52

4. Rehabilitation and renovation fee of communication facilities 155.41 106.08 5.88 43.45

5. Rehabilitation and renovation fee of hydropower facilities 4530.07 3938.28 591.79

6. the historic site protection fee 96 96 Part III 3. Protection work fee 20827.42 20827.42

1. Lifting and filling project 15234.39 15234.39

2. Reservoir and bank protection project 5451.88 5451.88

3. Inundation treatment project 141.15 141.15 Part IV bottom cleaning fee 72.98 72.98 Part V 5 Other fees 4645.84 4170.72 431.03 44.09

1. Previous preparation fee 1115.3 997.95 106.45 10.9

2. Survey, design, and research fee 1338.36 1197.52 127.76 13.08

3. Management fee 1338.36 1197.52 127.76 13.08

4. Establishment fee of implementation organization 210 210

5. Technical training fee 77.06 57.31 17.95 1.8 6. Assessment fee 446.14 399.18 42.6 4.36 7. Consulting Service Fee 89.22 79.84 8.51 0.87 8. Women's Aid Fund 31.4 31.4

Part VI preparatory costs 3940.64 3527.05 375.18 38.41 Part VII Relevant Taxes 2752.3 2035.89 678.49 37.92

1. Cultivated Land Occupancy Tax 471.91 374.86 91.98 5.07

2. Cultivation Fee of Cultivated Land 1803.71 1306.06 464.8 32.85

3. Forest Vegetation restoration 476.68 354.97 121.71

Page 17: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

10

Total Investment Condition of Land Requisition Resettlement Compensation after Adjustment

Table 1.4-1 Unit: 104 Yuan

No. Item Total Reservoir

Area Dam site Dock area Cost

Part VIII Total investment 55951.12 49651.11 5743.54 556.47

By the end of June in 2016, total fund appropriation for land acquisition and

resettlement is 527.5 million Yuan. In which, Hengnan accounts for 276.2 million

Yuan, Changning accounts for 122.9 million Yuan, Leiyang accounts for 35.4 million

Yuan, as well as other costs, contingencies and relevant taxes accounts for 93 million

Yuan.

Hengnan County had completed the land requisition and resettlement investment

of 286 million Yuan, including reservoir area investment of 248.26 million Yuan, dam

area investment of 36 million Yuan, and the new water source land requisition and

resettlement of 1.74 million Yuan.

Changning City had completed the investment of land requisition resettlement

compensation 76.25 million Yuan, including reservoir area compensation of 71.02

million Yuan, and Songbai kiloton terminal of 5.23 million Yuan.

Leiyang city had completed construction land requisition and resettlement

compensation investment of 24.20 million Yuan.

The historic site preservation fee is 960 thousand Yuan, which is directly invested

by the project construction unit (HPWTCIG).

In the late days of April 2016, the Audit Department of Hunan auditted the

resettlement special fund of Tugutang project and make a conclusion that the using of

the project resettlement fund complied with relevant laws and regulations.

1.5 Resettlement Implementation Monitoring objectives and Work

Content

1) Objectives of Monitoring and Evaluation

According to the objective and requires in the ADB RP (Objective: try to reduce

involuntary resettlement; try to promote the living standard, at least let the relocate

recovery to the living standard before project implementation; promote the living

standard of poor affected people and other vulnerable groups. Requires: completed

Page 18: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

11

RP, scientific management, objective and independent monitoring assessment. The

assessment department proposed assessment advices for the whole resettlement

process and the relocatee's production and living restoring levels as per the track

monitoring activities, provided early warning system for the project management

department, provide reflecting channel for resettlement issues, to ensure that the

resettlement planning implementation can conform to the national and local laws and

regulations, and ensure that the entire project resettlement to achieve the desired

objective, eliminating the complex construction effect to the local villagers, while

providing basis for the smooth continuing of the complex construction. The objectives

are to:

(1) Carry out tracking monitoring on implementation of the resettlement work

(including implementation of resettlement policies, operation of resettlement agencies,

production resettlement, house reconstruction and livelihood arrangement for

relocated residents, recovery of relocated residents' incoming and production & living,

complaints and grievance, public participation and negotiation, information disclosure,

etc.), collect resettlement related information, provide continuous information

feedbacks for the implementation of resettlement plan, and assist the resettlement

administrative departments and the project owner to understand realization status of

the resettlement objectives and results and effects of the resettlement.

(2) Through objective evaluation on resettlement implementation effects, ensure

the resettlement administrative departments and the project owner to understand

actual progress of the resettlement work within the area under administration in more

details, discover and rectify existing problems in the implementation process, timely

improve working procedure, and put forward treatment measures, and thus promote

implementation of resettlement as planned, and fulfill the needs of the Project

construction.

(3) Check the resettlement implementation plan to see if it satisfy the actual

resettlement needs, check the resettlement implementation if it conforms to the

relevant policies and the resettlement planning requirements, find the already existed

issues or the problems that may occur, make recommendations or pre-Warning to

avoid that the relocatees' production and living cannot be reached or exceed before

removal due to resettlement planning or implement deviation.

Page 19: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

12

2) Main Contents of Monitoring and Evaluation

According to the Terms of Reference of Xiangjiang Tugutang Navigation Complex

Project Construction Land Requisition and Resettlement Monitoring and Evaluation

(M&E), the main working contents of this M&E are established as the following on the

basis of completion of the first, the second, the third and the fourth and the fifth M&E:

(1) Monitoring and evaluation on implementation of the resettlement;

(2) Evaluation on administrative organizations of resettlement implementation

and their operation conditions;

(3) Monitoring assessment of relocatee's living standard restoring measures;

(4) Evaluation on aids to vulnerable groups;

(5) Evaluation on grievance redress mechanism;

(6) Evaluation on public participation and information disclosure

(7) Compliance status of the loan covenants;

(8) Problems and follow up actions:

Page 20: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

1

2 Monitoring & Assessment of Resettlement Implementation

Engineering construction of Tugutang Complex, reservoir inundation,

construction of special works in reservoir area, construction of Songbai and Yunji

Berths, and construction of New Water Source Project cause the impacts of land

acquisition and resettlement. Main impacts include: permanent land acquisition of

6481.79 mu, temporary land occupation of 6303.35 mu, relocation of 310 persons in

68 households, and house demolition of 19136.1m2.

2.1 Monitoring Method

From Jun. 26th to 30th of 2016, the M&E Department setup a three-person

evaluation team, i.e. Mr. Xu Jinyuan (resettlement supervision engineer, team leader),

Mr. Luo Zhilong and Mr. Peng Hongwu, to carry out field investigation on land

acquisition and resettlement conditions of Tugutang Complex, and understand the

progress of land acquisition and resettlement for the project construction. The team

then checked and reviewed documents relating to land acquisition and resettlement,

and met with HPWTCIG Management Department of Tugutang Complex, local

resettlement administrative authorities, design unit, comprehensive supervision unit,

as well some affected people. Details are as followed:

In the morning of June 26th. 2016, the M&E team met with representatives from

HPWTCIG Management Department of Tugutang Complex, Hengnan County

Coordinate Headquarters for Tugutang Project, Changning Resettlement Bureau,

Leiyang Resettlement Bureau, Hunan Hydro & Power Design Institute (design unit),

and Hunan Xiangyi Resettlement and Engineering Supervision Consulting Company

(comprehensive supervision) (list of meeting personnel refer to Attachment 1). The

team introduced objectives, contents and approaches of this monitoring and

evaluation, and required related units to provide resettlement progress plan,

Page 21: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

2

resettlement implementation scheme, overall progress, fund appropriation, skill

training of land-losing peasants and other relevant data for checking and reviewing. In

the very afternoon, the M&E team inspected dam area relocation and resettlement

site in right bank: Tanggu group, Xintangzhan village, Yunji Town, Hengnan County;

Shani group and Dawu group, Pengci village, Xiangyang town, Hengnan county in the

dam relocation resettlement points. They also meet some of the representatives of

relocatees.

On June 27th. 2016, the M&E team arrived the construction field of Changning

Songbai 1,000dwt berth, and met with the personnel from Changning Resettlement

Bureau and some of the relocatee's representatives from Shucai village and Qingnian

village, Shuikoushan office.

On June 28th. 2016, the M&E team arrived in Hebian team of Mashi Village and

Qishang group of Xinlong Village in Yanzhou Town of Changning City, and Tianqin

Village and Xintong Village of Songbai Town, and met with staff of Resettlement

Bureau of Changning City, as well representatives of local relocatees.

On June 29th. 2016, the M&E team arrived the construction field of Yajiang

Yuchang, Yajiang village, and Xinhua village No.15 group, Daheyu town, Leiyang city,

and met with the personnel from Leiyang Resettlement Bureau, and some of the

relocatee's representatives.

The M&E team mainly consulted the followings with the persons met (list of

persons met refers to Attachment 3): land requisition and house demolition

compensation standard, compensation fund payment condition, relocating house

construction, housing condition improvement, production restoring after relocation,

household income level before and after relocation, and disposal of relocatees'

complaints (refer to Section 6.2 Complaint Record).

Page 22: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

3

On June 30th, 2016, the M&E team arrived the construction field of Lijiang power

station in Lijiang town of Hengnan county, Block A of Xiangjiang River, Binhe Block B

in Yunji Town, Zhuchong Block C of reclamation and filling site of Xiangyang Town in

Hengnan County. In the same afternoon, the M&E team communicated with the

construction unit (HPWTCIG) about the issues reflected by the relocatees (refer to

Section 6.2 Complaints record), and reviewed the relevant documents with drawings

attached.

2.2 Monitoring and Evaluation on Permanent Land Acquisition

2.2.1 Implementation of Permanent Land Acquisition

1) Reservoir Area

Permanent land acquisition in reservoir area of Tugutang Complex is 5605.71mu,

including farmland of 1878.34mu, land of water area and water resources facilities of

281.8mu, garden land of 8.5mu, forest land of 642.8mu, grassland of 2741.45mu, and

other lands of 52.82mu.

The permanent land requisition in the reservoir area had been completed by the

end of the second M&E period (the end of June, 2014).

2) Dam Area

Permanent land acquisition in dam area of Tugutang Complex is 818.45mu,

including farmland of 475.13mu, land of water area and water resources facilities of

24.8mu, forest land of 186.2mu, grassland of 53.36mu, other lands of 2.38mu,

residential land of 8.0mu, and other construction land of 68.58mu.

The permanent land requisition in the dam area had been completed by the end

of the second M&E period (the end of June, 2014).

3) Construction Area of 1,000dwt berth

The permanent land acquisition for Yunji Berth of Hengnan county is 17.82 mu,

Page 23: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

4

including, grass land of 17.31 mu and residential land of 0.51 mu.

After alteration, the Songbai 1,000dwt berth of Changning city will acquire

permanent land acquisition of 41.16 mu, including paddy field of 31.65 mu, pond

water level of 5.2 mu, inland tidal flat of 2.12 mu, rural residential land of 1.2 mu and

transportation land of 0.99 mu.

The permanent land requisition of Songbai Berth had been completed by the end

of the fourth M&E period (by the end of Dec., 2015). For Yunji Berth, one road has

been constructed to connect Yunji and upstream port of Hengyang City, which

facilitate the transportation between Yunji and this port.The experts argue that the

proposed Yunji Berth would have very small cargo throughput, which has little

economic, social and environmental benefits. Its construction therefore has been

suspended.

4) Construction Area of New Water Source

The new water source project of Hengnan County will acquire land of 8.65 mu,

including cultivated land of 8.25 mu and other land of 0.4 mu.

The permanent land requisition had been completed by the end of the second

M&E period (the end of June, 2014).

2.2.2 Evaluation on Permanent Land Acquisition

Progress: The permanent land requisition of the reservoir area, the dam area,

Changning Songbai 1,000dwt berth and new water source construction area had

been completed (details refer to attached table 1).

Alteration: The construction area of Songbai Berth has newly increased

permanent land requisition of 3.32 Mu due to design alteration, including decreasing

grass land of 19.42Mu, increasing paddy field of 14.29Mu, pond of 4.14Mu, inland

tidal flat of 2.12Mu, house site of 1.2Mu and transport land of 0.99Mu.

Page 24: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

5

2.3 Monitoring and Evaluation on House Demolition and

Resettlement

2.3.1 Progress of House Demolition

1) Reservoir Area

Planned house demolition in reservoir area is 11,175.71m2, including private

houses of 7,716.15m2, and public houses of 3,459.56m2.

By the third M&E period (the end of December, 2014), the house demolition in

reservoir area had been completed, no more house demolition was done during this

period. By this M&E period (the end of June, 2016), 10204.35m2 houses in reservoir

area have been removed, including private house of 6744.79m2 and public house of

3459.56 m2.

The house demolition of Hengnan reservoir area had been totally completed, A

total of 3206.3 m2 houses had been demolished, including private house of 1801.37

m2,newly foundation of 281.6 m2 and public house of 1404.93 m2.

The house demolition of Changning reservoir area had been totally completed, A

total of 3932.49 m2 houses had been demolished, including private house of 2249.42

m2 and public house of 1683.07 m2.

The house demolition of Leiyang reservoir area had been totally completed

(avoiding 7 households displaced due to design optimization by taking protective

measures). A total of 3065.56 m2 houses had been demolished including private

house of 2694 m2 and public house of 371.56 m2.

Some of the relocatees of the reservoir area chose to buy new houses in other

places according to their own willing.

2) Dam Area

Planned house demolition in dam area is 5939.53 m2, including private houses of

5778.63m2, and public houses of 160.9m2.

The house demolition in the dam area had been completed by the end of the

second M&E period (the end of June, 2014).

3) Construction Area of 1,000dwt berth

After alteration, the planned house demolition of Songbai Berth is 2020.86

Page 25: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

6

m2 ,including public house of 60 m2 and private house of 1960.86 m2.

The house demolition of Songbai 1,000dwt berth had been completed by the end

of the third M&E period (the end of Dec., 2014). The Yunji 1,000dwt berth has not

been implemented yet.

2.3.2 Resettlement area and house site

The houses are resettled in scattering and backward arrangement, the relocatee

could select the new house construction location by themselves, land occupation for

per capita house site is controlled by 130m2/household.

As the reconstruction area depends on the existing infrastructure and public

service system, the rural road and electrical network are complete, the flood affected

infrastructure is planned to be reconstructed, and the relocated houses are arranged

at the place with convenient conditions for traffic, water supply, and power supply.

Scattering water supply is adopted, the traffic and power supply only require a little

supporting cost.

According to investigation, the resettlement area is mainly distributed with

cultivated land, the infrastructure subsidy standards of each household are: house site

acquisition at dam area is 40,029 Yuan/mu, acquisition at reservoir area is

35,943Yuan/mu in Hengnan County, 33,888Yuan/mu in Changning County,

35,974Yuan/mu in Leiyang City; land leveling subsidy is 3000Yuan/person, and water

& power supply is 400 Yuan/household.

Infrastructure compensation for house removal at reservoir area is 1.0128million

Yuan, including 73 thousand Yuan for Hengnan County, 126.9 thousand Yuan for

Changning City, 812.9 thousand Yuan for Leiyang City. Infrastructure compensation

for house removal at dam area is 395.7 thousand Yuan

By the end of this monitoring and evaluation period (the end of June, 2016), each

county and city had paid the infrastructure compensation as per agreement of removal

and resettlement compensation.

During site interview by the M&E personnel, the relocated residents reflected they

were satisfied with the mode that the house site was selected by themselves and land

using formalities was proceeded by county resettlement administrative agency. As the

resettlement is arranged within the village group, there is no objection among the

Page 26: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

7

public. Some residents chose the method of independent resettlement by purchasing

new houses in other places.

2.3.3 Transitional Period

Planned households during transitional period at the dam area are 19 households

with 78 persons; the actual is 23 households with 90 persons.

Planned households remove at the reservoir area are 40 households with 203

persons, of which, Songjiang Town, Hengnan County removes 3 households with 17

people, Yanzhou Town, Changning City removes 7 households with 26 people, and

Leiyang City removes 30 households of 160 people. The actual reservoir area

removes 38 households with 187 people, of which Songjiang County, Hengnan

removes 7 households with 25 persons, Yanzhou Town, Changning city removes 7

households with 36 persons. Leiyang City revomes 24 households with 126 persons

(excl. 7 households with 41 persons who are avoided by protective measures). The

later investigation and check found another 7 households were included in the house

removal, therefore, the quantity of relocatees increased from 119 in last period to 126

in this period.

After alteration, Songbai 1,000dwt berth needs to relocate rural population of 7

households with 33 persons, and has actual relocation population of 7 households

with 33 persons. The above mentioned population is considered during transitional

period.

Transition Duration is considered to be 1 year.

Living subsidy during transitional period: The living subsidy standard during

transitional period is planned to be 1000Yuan/Person. In Hengnan County, it

considered to keep the same compensation standard with that of other house removal

for key projects, therefore, the compensation standard is adjusted based on house

removal of 48Yuan/m2. In Changning and Leiyang city, the compensation is based on

the planned standard.

Evaluation of transitional period and subsidy: According to the relocated

residents' reflection, as the houses are rebuilt very fast, the living subsidy during

transitional period is sufficient enough, even some surplus was gained. All the

relocatees are satisfied.

Page 27: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

8

2.3.4 Evaluation of House Removal

Progress: house removal at dam area had been completed as schedule (refer to

Annex Table 2), which assured the smooth construction progress of Tugutang

Complex. In reservoir area, there are 7 households with 25 persons in Hengnnan

County (while the planning was 3 households with 17 persons, but 4 households of 8

persons were added in actual due to marriage, new birth and family separation); there

are 7 households wiht 36 persons in Changing City (while the planning was 7

households of 26 person, but 10 persons were added in actual due to marriage, new

birth and family separation); there are 24 households with 126 persons in Leiyang City

(while the planning was 30 households of 160 persons, but in actual 7 households of

41 persons voluntarily changed from demolition to protection in Daheyu of Yajiang

Village (protection was completed after the approval of Resettlement Administration

Bureau of Hunan Province), and one household of 7 persons are added due to family

splitting. Demolition in these three cities(counties) had been all completed and all

relocatees have moved into new houses, expect one household enjoying the Five

Guarantees moved into gerocomium arranged by Daheyu Village Government.

Songbai berth involved 7households with 33 persons. See Table2.3-1

Relocation Resettlement Implementation of Tugutang Project Table 2.3-1

Stage/area

Dam site Reservoir Area Dock area remarks

Number of households

Number of

Persons

Number of households

Number of

Persons

Number of households

Number of

Persons

planning design data

19 80 40 203 7 33

actual implement

data 23 90 38 187 7 33

the reservoir area excludes

the 7 protective

households from Leiyang

city. relocatee's household data in the

Null Null Null Null Null Null

Page 28: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

9

transition period at present

2.4 Monitoring and Evaluation of Residents Relocation

2.4.1 Impact of Land Acquisition and Resettlement

According to Resettlement Plan, the affected persons by reservoir inundation and

land occupation of Tugutang Complex Construction amount to be 7959, including

7487 persons by reservoir area, and 405 persons by dam area, and 67 persons by

1,000dwt berth construction area. The affected persons by house removal amount to

be 316 persons, including 203 persons by reservoir area, 97 persons by dam area,

and 33 persons by 1,000dwt berth construction area. The total affected

non-overlapped persons are 8275, including 6679 seriously affected persons that

suffers from losing above 15% or more production property. In the ADB’s RP, the

poverty caused by comprehensive factors such as illness, disabled, old and schooling

level. The rural poverty occurrence rate at project affected area is 7.8%. At present

the resettlement bureaus is responsible for statistics and report to the construction

unit (HPWTCIG). See details in Section 5.1 Status of Vulnerable Group.

According to resettlement plan, the 310 relocated people shall be resettled in

scattering and backwards arrangement; production resettlement population is 7959

persons, including 5514 persons by reservoir farm land protection resettlement, 1182

persons by monetary compensation resettlement, 646 persons by cultivated land

regulation resettlement, and 145 persons resettled by secondary & tertiary industry

development. For the dam area, 93 persons are resettled by monetary compensation

and 312 persons by cultivated land regulation resettlement. For berth construction

area, 5 persons are resettled by monetary compensation and 62 persons by cultivated

land regulation resettlement.

Page 29: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

10

2.4.2 Resettlement Implementation

1)Production Resettlement

The resettlement at dam and reservoir area in Hengnan County involves 110

village groups in 31 administrative villages of 6 towns. All the agreements of

production resettlement had been signed.

The resettlement in Changning City involves in 130 village groups in 35

administrative villages of 5 towns. All the agreements of production resettlement had

been signed.

The resettlement in Changning City involves in 56 village groups in 10

administrative villages of 2 towns. All the agreements of production resettlement had

been signed.

After the agreement of production resettlement was signed, the resettlement of

reservoir farm land protection had been implemented by batches, the resettlement of

secondary & tertiary industries is undergoing. At present, resettlement of adjusted

cultivated lands and currency compensation had all been completed. Part of the

farmland protection and resettlement of secondary & tertiary industries had been

completed. 472 people were resettled in Jan-Jun.2016. By June 2016, there were

5872 people resettled accumulatively, accounting for 75% of total relocatee.

2) Removal resettlement

House removal at dam area had been completed as schedule (refer to Annex

Table 2), which assured the smooth progress of Tugutang Complex.

2.4.3 Resettlement Evaluation

The production relocation of the reservoir area, dam area and 1,000dwt berth

basically complied with the planned schedule, with its compensation standard and

relevant procedure insisting the principle of legal, open and fair.

2.5 M&E of Temporary Land Occupation

2.5.1 Status of Temporary Land Occupation

The planned temporary land occupation is 6303.35 mu, of which, the reservoir

land occupation is 5665.93mu, with temporary land occupation compensation of

9.7104 million Yuan (including crop compensation), its land recovery area is 3248.05

Page 30: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

11

mu, with land recovery compensation of 18.1648 million Yuan. The dam temporary

land occupation is 386.33 mu, with compensation of 2.0696 million Yuan and crop

compensation of 349.8 thousand Yuan, its land recover area is 179.58 mu, with land

recovery compensation of 1.4147 million Yuan. For berth construction area, Songbai

1,000dwt berth of Changning city and Yunji 1,000dwt berth of Hengnan county have

no temporary land occupation; the new water source construction area has temporary

occupied land of 251.09 mu (refer to attached Table 4).

By end of this monitoring period, temporary land compensation of the reservoir

area is 3079.24mu, satisfying the construction requirement. The compensation of

temporary land occupation of 386.33 mu has been completed. Land restoring works is

under implementation, 370mu temporary land for bank protection and culvert gate

work in Hengnan County has been reclaimed, accounting for 84% of total work.

Temporary land compensation and land restoring at new water source construction

area had been completed. Compensation for temporary land in reservoir has all been

completed; reclamation will be implemented after completion of the special works in

reservoir area.

2.5.2 Evaluation of Temporary Land Occupation

Temporary land compensation at reservoir area is steadily promoted, which

ensures the smooth project progress.

Temporary land compensation at dam area had been completed, and the project

is in smooth progress. The right bank is being implemented land restoration works.

Temporary land compensation and land restoration at new water source

construction area have been completed.

2.6 M&E of Special Works and Protection Works

2.6.1 Implementation of Special Works

For the large scaled work at reservoir area (including bank protection, culvert

sluice, road, bridge, Lijiang Power station, and farmland protection project), the cost

estimation is 286.5325 million Yuan.

Reservoir bank protection works bidding in November, 2013 include 30.037km

in 56 sections. Except 1.398km in three sections needs design modification, all the

Page 31: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

12

other sections had been completed and passed through acceptance of separated

project. In order to guarantee people's life and property, a 2.7km-long bank

protection work was added based on actual field conditions after reservoir

impounding. The 21 culvert gates and Lijiang power station rehabilitation works that

was bidded together with reservoir bank protection works have been all completed

and passed through acceptance of separated project, and were handed over for

operation. Rebuilding work of reservoir road and tractor path is 6.683km, and

5.399km had been completed, accounting for 84% of total work. There completed

3.43km in Jan-Jun.2016, accounting for 65.5% of total work. 9 bridges rebuilding

had been completed, accounting for 100% of total work, including 4 bridges

rebuilding in Jan-Jun. 2016, accounting for 44% of total work.

The first batch of reclamation work (farmland protection), grade road, and the

rehabilitation project of the transport facilities around the reservoir is in a bundled

tender. By the end of June 2016, there has completed 3.985 million m3 earthwork,

accounting for 99.5% of work quantity in contract.

In Jan-Jun 2016, the second batch of reclamation works (farmland protection) in

reservoir area was completed with tendering and bidding, establishment of project

department, technical disclosure, earthwork repeating survey, acquisition of borrow

area, construction road. Topsoil stripping and earth backfill at partial section have

been completed for 395 thousand m3, accounting for 30% of total work in contract.

There are no other ground attachments (small special facilities) in the reservoir

area which need to be re-built. And the one-time monetary compensation had been

completed.

Construction and compensation of Special Facilities in Dam Area:

compensation and renovation work of temporary water system recovery, transport

facilities, power transmission and conversion facilities, communication facilities, etc.

had been completed. Restoration of permanent water system had been completed by

96%. 2.34km canals have been rebuilt in Jan-Jun. 2016, accounting for 18% of total

work.

Special project compensation in Berth Area Restoration of water system,

Page 32: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

13

transport facilities, power transmission and conversion facilities, communication

facilities, etc. of Songbai Berth had been completed. Construction of Songbai Berth

and the ancillary facilities had been completed, with the total investment of

32.754million Yuan (including equipment cost 1.558 million Yuan). The completion

and acceptance of Songbai Berth had been completed, which will be put into

operation in July 2016.

2.6.2 Evaluation of Special Works

The M&E personnel considered that the second batch of reclamation work is in

slow progress due to frequent rainy days and construction difficulty. Therefore, each

related company shall perform duty, catch up the work progress in the latter half of

year, and guarantee the work quality.

Follow-up: the first batch of works such as reclamation of reservoir area and

transport facility construction shall be accelerated with its winding-up work, excavation

and lining of main canals and ditches shall be completed soon, and catch up with the

second batch of reclamation work progress, so as to assure that all the work

completed in this year.

2.7 M&E of Resettlement Compensation

2.7.1 Compensation Standard of Land Acquisition and Removal

Before carrying out land acquisition and removal, executor of resettlement in

Hengnan County, Changning City and Leiyang City issued the following notices

publicly to flood affected zone of the Complex in form of governmental document:

Notice of issuing Implementation Plan of Land Acquisition and Resettlement of

Xiangjiang Tugutang Navigation and Hydropower Complex in Hengnan County by

Government Office of Hengnan County, Notice of issuing Implementation Plan of Land

Acquisition and Removal for Constructing Reservoir Area of Leiyang City of Tugutang

Navigation and Hydropower Complex by Government Office of Leiyang City. The

Notices include compensation standard of land acquisition and removal, laws and

regulations, procedure requirement of resettlement, deadline target, funds

management and etc. with detailed contents.

Standard of land acquisition and removal in notice is formulated by Design Report

of Land Acquisition and Resettlement Plan for Constructing Tugutang Navigation and

Page 33: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

14

Hydropower Complex (For Approval),Supplement Report of Adjusting Land

Compensation Fees of Tugutang Navigation and Hydropower Complex combined by

formulation of related regulations of local government of Hengyang City.

Since land acquisition work of new water source started in 2010, the

compensation standard is implemented as per Design Report of Land Acquisition and

Resettlement Plan for Constructing Tugutang Navigation and Hydropower Complex

(For Approval).

2.7.2 Status of Land Acquisition and Removal Compensation

After compensation adjustment, the investment of Tugutang Complex land

acquisition and resettlement amounts to be 434.63 million Yuan (excluding other cost,

basic contingencies and tariff). By the end of this M&E period, it had completed land

acquisition and resettlement investment of 394.32 million Yuan, accounting for 91% of

total investment. The investment includes 276.20 million Yuan in Hengnan County,

122.90million Yuan in Changning City and 35.40 million Yuan in Leiyang City.

1) Reservoir Area

Investment of 382.7682 million Yuan is planned, including 237.5691 million Yuan

for Hengnan County, 111.6995 million Yuan for Changning City and 33.4996 million

Yuan for Leiyang City.

By the end of this period of monitoring and evaluation, investment of 339.022

million Yuan has been accomplished for land acquisition and resettlement in reservoir

area, accounting for 88.57% of the total investment. It includes rural resettlement

compensation of 114.5687 million Yuan, accounting for 100%, compensation of

special works recovery and reconstruction of 68.046 million Yuan, accounting for

90%, and investment of protection work 155.6775 million Yuan, accounting for

81.14%. The cleaning of reservoir bottom was completed. The completion status of

each county and city is shown in Attachment Table 5 Status of Construction Land

Acquisition and Resettlement Compensation.

2) Dam Area

The planned investment is 42.5884 million Yuan, including 35.9123 million Yuan

for rural resettlement compensation, and 6.6761 million Yuan for special facility

Page 34: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

15

reconstruction.

By end of this M&E period, it has completed the investment of land acquisition

and resettlement at dam area of 42.3585 million Yuan, accounting for 99.46% of total

investment. It includes the entire rural resettlement compensation 36.0103 million

Yuan, accounting for 100%, and special facility reconstruction compensation

6.3482million Yuan, accounting for 95.09%. The compensation completion status is

shown in Attached Table 5 Status of Construction Land Acquisition and Resettlement

Compensation.

3) Construction Area of 1,000dwt berth

The planned investment is 4.3605 million Yuan for Yunji berth in Hengnan County

and the changed Songbai berth of Changning, including 3.5958 million Yuan for rural

resettlement compensation and 0.7647 million Yuan for special facility reconstruction.

By the end of this M&E period, land acquisition and resettlement for the changed

Songbai Berth had completed total investment of 4.0822 million Yuan ,accounting for

100%. (of which, 3.3175 million Yuan compensation is for rural resettlement). and

compensation for reconstruction of special facility 0.7647 million Yuan, accounting for

100%.

Yunji Berth in Hengnan County hasn't been implemented.

4)Women and Children Assistance Fund

The planned investment is 0.314 million Yuan, including 125,600 Yuan in

Hengnan County, 94,200 Yuan in Changning City and 94,200 Yuan in Leiyang City.

By end of this M&E period (end of June 2016), Women and Children Assistance

Plan of Hengnan County and Changning City is being implemented by providing work

skill training, such as special agricultural skill, cooking skill, household service, and

recommended employment, assisting the impoverished students for poor family, with

total investment of 299.8 thousand Yuan, accounting for 95.5% of total investment

amount ( 314 thousand Yuan).

5) Construction Area of New Water Source

This project investment is not incorporated in the Resettlement Plan Report,

which is entrusted to Hengnan County Tugutang Construction Coordination

Page 35: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

16

Headquarter by Hunan Water Transport construction and Investment Group Ltd

(HPWTCIG) for direct implementation.

By end of the third M&E period(end of December of 2014), it had completed the

investment 1.74312 million Yuan, including permanent land acquisition compensation

of 108,800 Yuan, temporary land compensation of 309,400 Yuan, crop compensation

of 340,400 Yuan, small scale facility compensation of 169,000 Yuan, land recovery

investment of 119,400 Yuan, fees and management cost of 696,120 Yuan.

2.7.3 Evaluation of Land Acquisition and Removal Compensation Payment

Compensation Standard during Implementation

The compensation standards implemented in this project firmly comply with

documentary standard issued by government described in Chapter 2.7.1.

In document issued by government, compensation of land acquisition is strictly

implemented as compensation standards specified in Resettlement Planning Report

and Supplementary Report of Adjusting Land Compensation Fees.

In Hengnan County, it considered to keep the same compensation standard with

that of other house removal for key projects, therefore, the compensation standard is

based on Compensation Method of House Removal on Collective Land in Hengyang

City(Hunan administrative issued document [2010]No. 54) and Crop compensation

Method on Collective Land in Hengyang City(Hengyang administrative issued

document [2010]No15). The local government gives the surplus fund after

implementing the compensation standards of Hengyang to the relocatees in form of

fund, as to avoid unfavorable impact on other construction project. M&E team

considered that the relocatee’s total compensation cost are not changed, and agreed

implementation of this scheme. Changning City and Leiyang City implement standard

specified in Resettlement Planning Report with no adjustment.

The compensation standard of crop is based on Compensation Standard of Crop

on Collective Land in Hengyang City(Hengyang administrative issued document

[2010]No.15). Standard specified in Resettlement Planning Report is implemented in

Changning City and Leiyang City.

Compensation of Land Acquisition and House Removal

According to site investigation by M&E personnel and interview on some affected

Page 36: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

17

people, the compensation payment procedure is as following:

Land acquisition compensation The County & city level resettlement

administrative organization and the land occupied group of village shall sign

compensation agreement as per rechecked affected land area, and the village

committee and township people's government shall sign and stamp as the third party.

After signing the agreement, the fund is transferred from the account of county

resettlement administrative organization to the special account of township financial

office, and the township organization make the distribution scheme and then

reimburse the fund to village committee account after disclosure without objection.

The village committee reimburses the fund to the group and household as per the

roster, the receiver give signature for confirmation.

Fund of House Removal and Private Crop Compensation: These funds are

reimbursed directly to the persons as per roster and personnel account by county &

city resettlement administrative organization.

The M&E result shows that the land acquisition and removal compensation is

reimbursed in an open and transparent way, without money deductions. The affected

people know the compensation fund account clearly, without objection, but due to

complicated fund appropriation procedure, the fund reach to account slowly.

Follow-up work: The M&E personnel found that some affected migrant workers

could not come back to receive the compensation funds, therefore, they entrust

relatives to receive the compensation funds by ID. The county level resettlement

organization shall pay return visit to confirm the household fund in hand of the

households, so as to avoid public complain. Procedure of compensation funds is

suggested to be simplified by HPWTCIG.

3. Evaluation on Administrative Organizations of Resettlement Implementation and their Operation Conditions

3.1 Organization Setup

Implementation of land acquisition and resettlement in Tugutang Navigation and

Hydropower Complex has management system focusing on governmental leadership,

taking charge by different levels, based on county and participation of project entity.

HPWTCIG is the project entity, which establishes Management Office for

Page 37: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

18

constructing Tugutang Navigation and Hydropower Complex in Yunji Town, Hengnan

County, which is divided into 6 departments of general office, engineering, Contract,

electrical and mechanical, reservoir area and environmental protection. Mr. Huang

Jinxing, Vice President of HPWTCIG acts as Head of Management Office and the

Principal in charge of construction of project. Land acquisition and resettlement of the

project is centralized to manage by Department of Reservoir area. Mr. Gan Maohui,

Vice Director of Management Office also acts as Director of Reservoir area

Department. Project Management Office mainly takes charge of treating all kinds of

resettlement-related problems and supervises implementation of local implementing

organization of resettlement and coordinates complaints of resettlers rapidly and

high-efficiently.

Administration of Reservoir Resettlement Development in Hunan Province is the

organization of guiding, coordinating, inspecting as well as supervising and managing

resettlement work.

Implementing organization for resettlement is People's Government in Hengyang

City, Hengnan County, Changning City (county-level city), Leiyang City (county-level

city) and specific executing organization is resettlement management organizations of

city and county levels.

People's Government of Hengyang City establishes leading group of resettlement

of Tugutang Navigation and Hydropower Complex, whose group leader is acted as by

Vice Mayor in charge of agriculture in Hengyang City, Mr.Chen Jin. Office is branched

in leading group, which is established inside Resettlement Bureau in Hengyang City.

Mr. He Liji, Director General of the Resettlement Bureau also acts as Office Director

and Mr. Liu Liangqi, Engineer-in-Chief takes charge of routine work in the Office.

Details about implementation agencies in Hengnan, Changning, and Leiyang are

as followed:

Hengnan County setups Coordinate Headquarters for Tugutang Navigation and

Hydropower Complex. County Party Secretary Mr. Zeng Xiangyue, acts as Political

Commissar, County Magistrate Mr. Zou Xiaomin, acts as Commander and Mr. Shen

Weiliang, Executive Vice County Mayor acts as Executive Deputy Commander. Four

functional departments of Office, engineering technology, land acquisition and

demolition and finance are branched under Headquarters.

Page 38: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

19

Changning City sets up Coordinate Headquarters for Tugutang Navigation and

Hydropower Complex. Mr. Guo Qingsong, Vice Mayor in charge of agriculture acts as

leading group leader and Office is a branch under leading group. The Work Office is

set in Resettlement and Development Bureau of Changning City, and the Office

includes three working teams, i.e. Resettlement Team, Engineering &Technical Team,

and General Affair Team. Mr. Lei Jide is Leader of the Resettlement Team and Mr. Liu

Huarong is Leader of the Engineering &Technical Team.

Leiyang City setup a Leadership Team for resettlement work of Tugutang

Navigation and Hydropower Complex. Mr. Liu Gesheng, Mayor also acts as Leader of

the leading group. The leadership team includes four offices, i.e. resettlement and

land acquisition office, engineering & technical office, policy and laws office, and

financial office.

Hunan Hydro & Power Design Institute is design unit of resettlement, which

establishes Design Representative Group of Xiangjiang Tugutang Navigation and

Hydropower Complex in Yunji Town, Hengnan County.

Hunan Xiangyi Resettlement Supervision Consultant Co. Ltd. is comprehensive

supervision organization of resettlement, which establishes comprehensive

supervision department in Yunji Town, Hengnan County.

As an independent external M&E unit, Hunan Yuhui Hydraulic and Hydropower

Construction Supervision and Consulting Co. Ltd establishes M&E department in

Yunji Town, Hengnan County.

3.2 Organization Responsibilities

3.2.1 Project Entity

HPWTCIG is the project entity with specific responsibilities as follows:

1) To entrust unit with survey &design qualification to compile detailed rules and

regulations on physical goods investigation, planning framework of resettlement and

programming of resettlement.

2) To propose relevant city-level government to apply provincial government for

issuing notice on prohibition of construction projects newly increased and resettlement

Page 39: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

20

population in land occupation and inundated area in project (hereafter as "Banning

Construction Notice").

3) According to approved programming of resettlement, to sign an agreement of

resettlement with related government of city or county level and provincial

administrative organizations of resettlement.

4) To entrust qualified units to develop monitoring & evaluation together with

provincial administrative organizations of resettlement.

5) To entrust qualified units to develop relevant designing in implementation

phase of resettlement planning as well as entrusting design unit to assign Design

Representative in resettlement site.

6) According to resettlement plan and schedule needs of implementation of

resettlement, in the first ten-day period of October of this year, to submit next annual

resettlement task and planning proposal of fund use to government of city or county

level which have signed an agreement of resettlement.

7) In terms of annual plan of the Project fund, full submerge compensation shall

be timely allocated to special account for resettlement fund of provincial finance.

8) Responsible for reporting land use formalities for land occupation and

inundated area of the Complex.

9) As required to entrust design unit to prepare Adjustment Report of

Resettlement Plan.

10) To join phased acceptance and completed acceptance of resettlement and to

coordinate resettlement to implement inspection and audit work of compensation fee

for submerging by related national and provincial departments.

11) To participate dealing with problems, emergencies and remaining problems

arisen from implementation of resettlement, as well as to organize and coordinate

disposal of complaints of resettlers.

12) To undertake treatment costs produced by landslide, bank collapse,

immersion and sediment deposition resulted in operation of reservoir, overhead

Page 40: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

21

expense produced by operation of protective works and responsibilities of violation

and storage-exceeding.

3.2.2 Supervisory Agencies

Both managing resettlement in the Complex and making a guidance,

coordination, inspection as well as supervising resettlement made by government of

low-level and administrative organizations are in the charge of Hunan Reservoir

Resettlement Development & Administrative Bureau, with specific responsibilities as

follows:

1) Responsible for reviewing detailed rules and regulations on physical goods

investigation that are produced by land acquisition for construction of large and

medium-sized reservoir within this administrative region (hereafter as "detailed rules

and regulations on investigation"), as well as responsible for examination of planning

framework of resettlement and programming of resettlement.

2) As supervisor, to sign an agreement of resettlement with project entity and

related government of level of city or county.

3) To draw out administrative measures on compensation for land acquisition and

resettlement fund (hereafter as "compensation fee for inundation") together with

related departments; to manage compensation fee for inundation according to related

regulations as well as examine Annual Plan of Project Fund of Resettlement for

approval and transmit it down (hereafter as "Annual Plan of Project Fund").

4) To urge Project Entity make resettlement funds practicable, timely appropriate

the resettlement funds according to approved Annual Plan of Project Fund as well as

implementation scheduling and make supervision, inspection and audit to the

resettlement funds together with related departments.

5) To entrust qualified units to develop M&E work of resettlement together with

Project Entity.

6) To organize phased acceptance and completed acceptance of resettlement

according to administration authority.

Page 41: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

22

7) Responsible for organizing training of employability skills for resettlers and

business training for cadres of relocatee in this administrative region.

8) Responsible for coordinating treatment of major issues arisen from

resettlement as well as letters and visits from relocatees, timely reflect problems

arisen from resettlement to superior and related departments and assist government

of this level and low level to make social stability in reservoir area and resettlement

area.

3.2.3 People's Government of City and County Level and Administrative

Organizations of Resettlement

Government of city and county level is responsible for resettlement in this

administrative district. According to administration authority and on behalf of

government of this level, related departments of city and county level cooperate with

Project Entity and design unit to develop pre-planning and designing of resettlement,

prepare implementation plan and annual implementation plan of resettlement in this

administrative district together with Project Entity and Design Unit as well as take

charge of organizing specific implementation of the resettlement project. Specific

responsibilities are as follows:

1) Conscientiously implement the national resettlement policies, and carry out

resettlement work within the administrative district according to the laws.

2) On behalf of government of county level, to sign an agreement of resettlement

task and investment responsibility system with municipal government.

3) Formulate and report annual resettlement implementation plan and annual

resettlement fund use plan of the county.

4) Responsible for accomplishing resettlement tasks of the county according to

the approved annual resettlement implementation plan.

5) Responsible for splitting, management, redemption and settlement of

resettlement fund of the county.

6) Joint with related departments to direct bidding work of important or major

resettlement tasks.

7) Implement management on resettlement tasks according to the administration

Page 42: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

23

privileges.

8) With strict financial management, proper management and use of resettlement

funds, to accept inspection and audit from related departments.

9) Accept supervision and inspection of resettlement supervision or monitoring,

and provide assistance for related work.

10) Responsible for publicity of related national resettlement guidelines and

policies, doing well in ideological and political work of the resettled, timely and

properly handling problems and contradicts occurred in resettlement process, and

maintaining social stability in reservoir area.

11) Responsible for acceptance inspection of the resettlement work in the county,

and drafting inspection report.

12) Assist the project Owner in handling land acquisition procedures.

13) Implement other works assigned by superior resettlement authorities.

Below the county level, in towns with land acquisition and resettlement tasks, one

deputy town chief is assigned to be responsible for resettlement work in each town

(village). To enhance management responsibilities, the three county (city) level

people's governments signed Liability Form of Management by Objectives with the

village (township) governments with resettlement tasks. Such villages (townships) are

responsible for the resettlement work within their respective administration region,

which include: publicity of related national resettlement guidelines and policies, timely

and properly handling problems and contradicts occurred in resettlement process,

reception of appeal for help from relocatees, addressing complains from relocatees,

and delivering complains beyond their authority to superior departments. Cadres of

village committees are jointed trained by the county and the township; and cadres of

village committees and the group leaders are coordinated in propaganda and

mobilization of the resettlement work. Working crews from the county, the township

and the village came to the site to define land acquisition boundary, land acquisition

area, land classification, index of the reservoir submersion, compensation for special

facilities, and compensation standards of each village group, and split each

compensation fund into villages, groups and households.

3.2.4 Design Unit

Page 43: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

24

As design unit of the resettlement, Hunan Hydropower Design Institute has

specific responsibilities as follows:

1) Compile detailed rules and regulations on investigation, planning framework of

resettlement and programming of resettlement.

2) Assist local government in preparing implementation plan of resettlement and

breaking down index of each item of physical goods and compensation investment.

3) According to related regulations, undertake construction drawing design of

production arrangement of rural relocatees, infrastructure in population center,

infrastructure in towns, special projects and protective works, and deliver design

documents.

4) Appoint site design representative to take charge of disclosure of planning and

designing of resettlement, design change, technical guidance and other work.

5) Prepare work report of planning and designing of resettlement, and join in

acceptance work of resettlement.

6) Entrusted to prepare adjustment report of resettlement planning.

7) Accept supervision from provincial administrative organizations of resettlement

and the Client's, and coordinate doing related work well.

3.2.5 Supervision Unit of Resettlement

As a supervision organization of comprehensive supervision of resettlement and

special works, Hunan Xiangyi Resettlement Supervision Consultant Co. Ltd. has

specific responsibilities as follows:

Supervision Unit makes an overall control on schedule and quality of

implementation of resettlement and removal and construction of special installation as

well as release and use of resettlement fund, and carries out an acceptance for

completed works to ensure resettlement works smoothly accomplished according to

quality requirement and plan of implementation schedule.

1) Explain Implementation Plan Report and Construction Drawings of

resettlement to resettlement organizations of all levels and relocatees, and supervise

removal and production arrangement of relocatees as well as construction of special

installation as required of Contract documents, Construction Specifications and

Page 44: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

25

construction drawings.

2) Approve and make a joint examination of resettlement plan, complementation

plan, construction drawings and modified resettlement documents prepared by

resettlement organizations in county or village (town) as Contract stipulated.

3) According to requirement of planning report, Contract and construction

drawings, implement a proof test to transportation facilities, building materials and

special equipment used by resettlement as well as install quality, and supervise

resettlement organizations to submit design documents, completion report and testing

data on files for future reference.

4) According to requirement of planning design documents and construction

drawings, draft and issue implementation requirement to resettlement organizations,

relocatees and building Contractor, and reply all kinds of questions raised by

resettlement organizations and building Contractor during construction.

5) Check and account appropriation plan and payment amount, and pay with

the approval of the Owner.

6) According to requirement of supervision, fill in all types of specified forms that

will form technical files of supervision together with other technical files.

3.2.6 Monitoring & Evaluation Unit of Resettlement

As an independent external M&E unit, Hunan Yuhui Hydraulic and Hydropower

Construction Supervision and Consulting Co. Ltd has responsibilities as follows:

M&E of resettlement is an effective management means. Independent monitoring

is to provide evaluation of resettlement and inspect overall implementation work in an

extensive and far- reaching viewpoint to evaluate whether goal of resettlement has

been achieved. Independent monitoring agency will track resettlement activity, put

forward evaluation opinions and suggestions on overall process of resettlement and

recovery conditions of standard of production and living of relocatees as well as

provide early warning system to Engineering Management Department and provide

advice-reflect channel to relocatees to ensure resettlement planning and

implementation accord with requirement of national and local relevant regulations and

rules, so that all the expected goal of resettlement can be achieved.

Page 45: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

26

3.3 Operation Conditions of Organizations

3.3.1 Personnel Allocation

1) Management Office of Xiangjiang Tugutang Navigation and Hydropower

Complex is established by Project Entity in Yunji Town, Hengnan County. Department

of Reservoir Area is branched under Management Office and is responsible for

resettlement. Department of Reservoir Area is composed of 4 experienced staffs and

director of the department is acted by Mr. Gan Maohui, Vice Director of Management

Office.

2) Resettlement Leadership Team of Tugutang Navigation and Hydropower

Complex in Hengyang City is established with team leader is acted by Vice Mayor in

charge of agriculture in Hengyang, Mr. Chen Jin. Office is branched in Leadership

Team, which is established inside Resettlement Bureau in Hengyang City. Director

General of the Resettlement Bureau also acts as Office Director and Mr. Liu Liangqi,

Engineer-in-Chief takes charge of routine work in the Office equipped with 3

professionals.

3) Hengnan County setups Coordinate Headquarters for Tugutang Navigation

and Hydropower Complex. County Party Secretary Mr. Zeng Xiangyue, acts as

Political Commissar, County Magistrate Mr. Zou Xiaomin, acts as Commander and Mr.

Shen Weiliang, Executive Vice County Mayor acts as Executive Deputy Commander.

Four functional departments of Office, engineering technology, land acquisition and

demolition and finance are branched under Headquarters with 25 staffs including 13

professionals.

4) Changning City setups Coordinate Headquarters for Tugutang Navigation and

Hydropower Complex. Vice Mayor in charge of agriculture, Mr. Guo Qingsong, acts as

leader of Leadership Team and Office is a branch under Leadership Team. The Work

Office is set in Resettlement and Development Bureau of Changning City, and the

Office includes three working teams, i.e. Resettlement Team, Engineering &Technical

Team, and General Affair Team with 12 staffs, 5 professionals included.

5) Leiyang City setup a Leadership Team for resettlement work of Tugutang

Navigation and Hydropower Complex. Mr. Liu Caosheng, Mayor, also acts as Leader

of the leading group. The leadership team includes four offices, i.e. resettlement and

land acquisition office, engineering & technical office, policy and laws office, and

Page 46: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

27

financial office, with 12 staffs including 4 professionals.

6) Hunan Hydro & Power Design Institute is design unit of resettlement, which

establishes Design Representative Group of Xiangjiang Tugutang Navigation and

Hydropower Complex in Yunji Town, Hengnan County with 5 professional staffs in the

group.

7) Hunan Xiangyi Resettlement Supervision Consultant Co. Ltd.is a

comprehensive supervision organization of resettlement, which establishes

comprehensive supervision department in Yunji Town, Hengnan County and includes

4 staffs in supervision department composed of 1 General Supervising Engineer, 2

Supervising Engineers and 1Supervisor.

8) As an independent external M&E unit, Hunan Yuhui Hydraulic and Hydropower

Construction Supervision and Consulting Co. Ltd establishes M&E Department in

Yunji Town, Hengnan County with 4 staffs which include 1 resettlement engineer, 2

engineers and 1 supervisor.

3.3.2 Installation Outfit

Corresponding installations, i.e. office occupancy, vehicles, office facilities and

communication equipment are outfitted in resettlement implementation organizations

of all the levels.

3.3.3 Personnel Training

To ensure implementation of resettlement of Tugutang Navigation and

Hydropower Complex can be smoothly developed, in beginning of March 2016,

Hengyang Resettlement Bureau organized resettlement management staffs in three

counties to carry out a technical training with more than 40 persons received training.

In end of March 2016, Management Organization of Resettlement of Hengnan County

organized staffs to present a technical training, with 15 persons received training. In

March of 2016, Management Organization of Resettlement of Changning City

organized staffs to present a technical training, with 86 persons received training. In

April of 2016, Management Organization of Resettlement of Leiyang City organized

staffs to present a technical training, with 10 person-times received training. Moreover,

Provincial Resettlement Bureau organizes Resettlement Bureau in City-level (County)

and each legal person of reservoir project (proposed and undergoing project),

representatives of design and supervision company to hold a resettlement experience

Page 47: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

28

exchange meeting and policy business training in Hongjiang of Huaihua city, with 150

persons receive the training. Meanwhile, to further strengthen communication and

coordination of all parties, Resettlement Bureau of City-level will organize to hold

monthly Joint Summary Conference in order to greatly improve management staffs of

resettlement capacity of coordinating and handling problems and bring positive effect

to smooth advancing resettlement work in reservoir area.

Professional training not only improves overall quality of the management

personnel of resettlement, but also promotes management level of implementation of

resettlement. Management personnel of resettlement learn and grasp resettlement

policy, laws & regulations and various professional knowledge, so that they can guide

production and development of relocatees and organize implementation of project so

as to assist relocatees in poverty alleviation on the premise of feasibly carrying out

various policies and guidelines of resettlement of the Party and the nation.

3.3.4 Evaluating Operation Conditions of Organizations

Resettlement organizations of Tugutang Navigation and Hydropower Complex

have reasonable personnel structure, perfect installation outfit, successful personnel

training and overall strong capacity of implementing resettlement plan by resettlement

management personnel. All constructional- participation units should consistently

learn ADB policy requirement of resettlement, better communicate with related ADB

experts to update information of resettlement, overall promote management level and

strengthen capacity construction of mechanism.

4 Monitoring & Evaluation of Measures on Restoration of Living Standard of Relocatees

4.1 Restoration Plan of Living Standard of Relocatees

According to approved Resettlement Planning, for relocatees who have lost

lands, measure on production arrangement, providing employment opportunity during

project construction, training of employability skills, allocation of living subsidy during

interim period can be taken to ensure living standard of the relocatees recover to that

before land acquisition with gradual improvement.

In manner of monetary compensation, production arrangement can be carried out

in the following measures: land compensation fund can be used to improve current

Page 48: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

29

cultivated land and plantation structure by relocatees to gradually increase living

standard; resettlement subsidy can be used to expand productive scale or engage in

service industry by relocatees to improve living standard; adjusting arrangement of

cultivated lands can be adopted to plant crops for relocatees in beneficial of that very

year; compensation fund for lands can be used to improve plantation structure and

irrigation conditions to make living standard of relocatees better than before.

Before implementing production arrangement, living standard of relocatees

cannot reach that of before; standard of living subsidy of 1000 Yuan/person is planned

during interim period with time limit of one year.

Construction in dam area of the Complex and special & protective works in

reservoir area needs great deal of labor forces and over 1000 employment

opportunities can be provided in construction of these works.

Production skill training of relocatees mainly trains on cultural knowledge and

practical technology to relocatees. Training of relocatees mainly adopts methods of

short-term training in combination with focused technical training. Various trainings of

practical technology are carried out to make certain relocatees grasp one or two

practical techniques, so as to bring other relocatees along become rich through

science and technology. Technical training costing 600,500 Yuan is planned with 60%

of them used for skills training of relocatees and 1200 person-times will be planned to

train. Training of science and technology for relocatees can all-round improve quality

of labor force, effectively improve production efficiency, reduce production cost,

increase technological content of works, improve capability of becoming rich of

relocatees in market economy, reinforce product competitiveness, so as to achieve

production-increasing of works and income-increasing of relocatees.

4.2 Implementation Conditions of Recovery Measures of Living

Standard of Relocatees

In order to provide more employment chance and income resource for the

relocatees, the project management department provides training and non-technical

work for the dam & reservoir area, and berth area during construction. According to

the investigation on the relocatees at dam & reservoir area, and berth area, the

project construction attracted many workers come to Pengci village, Binhe village, and

Songbai berth area, running canteen, restaurant, gasoline station, and house rent to

Page 49: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

30

increase their income. Firstly, the project department signed some employment

contracts with the local villagers, including wall painting, slope protection, wood &

cement work, garden greening and maintenance, which involves in contract amount of

1.34 million Yuan. The camps at left bank of dam area and access road of borrow area

were contracted by the Binhe village committee, which is amounted to be 11.60 million

Yuan. Signed contract (9.90million Yuan) with Xiangyang County government,

employing local villagers to undertake the bank protection and earthwork nearby.

Secondly, The villagers from Pengci village of Xiangyang Town and Binhe village of

Yunji Town in Hengnan County are responsible for earth transportation from land

reclamation in Bid section I & II, and auxiliary works, such as access road, drainage

ditch, slope protection, which involving investment of 2.4 million Yuan, resolving

labour output of 80 people. Thirdly, the cleaning and water spray of road surround the

reservoir construction area is contracted to the local villagers, with service fee 400

thousand Yuan, resolving the employment of more than 30 local elderly people and

women. Fourthly, The reservoir area involves in 252 special works, such as bank

protection, culvert gate, reclamation, road, and bridge, with total investment of 280

million Yuan. During the construction period, more than 4000 local villagers were

employed, achieving complete coverage of the workforce. The production technology

training is also in progress, besides, the government will provide 600 Yuan to each

affected relocatee as follow-up support funds (provide for 20 years, used for direct

economic compensation for project development, but not in implementation yet, and it

will be implemented after resettlement acceptance and approval of provincial

resettlement bureau).

In March 2016, the training of camellia cultivation was provided to 86 relocatees

from Shuikoushan town in Changning City, the training was held at Songbai Berth. It

planned to provide skill training at Binhe Village in the second half of 2016, and invest

3.65 million Yuan for social security support to the affected people, which will be

compensated to the relocatees who lose their 273.84 mu cultivated land due to

Songbai Terminal works, but not implemented yet. Regarding the follow-up works, the

project employer shall distribute the compensation cost to the affected people in an

early time.

Therefore, this evaluation shows that after built of dam area, reservoir area, and

Songbai berth area, the living standard of affected people are not lower compared

with the period before land acquisition, on contrary, it is constantly improving.

Page 50: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

31

4.3 Evaluation of Recovery Conditions of Relocatees Living

Standard

According to the resettlement monitoring result on one household (Mr. Peng

Lidong in Pengci Village) at dam area and 2 households (Mr. Zhong Chengfu & Zhu

Zhongjun) at reservior area, their houses are rebuilt into brick-concrete structure

house from the old brick-wood structure. Mr. Peng Lidong opens a store and

machinery maintenance shop under the advantage of much construction staff at the

dam area, his economic income has increased a lot, and he bought car, refrigerator,

and TV. As for the family of Mr. Zhong Chengfu and Zhu Zhongjun, their incomes

mainly from works in the city and agriculture work at home, their economic income are

not affected, and increased slightly.

The monitoring result shows the project doesn't reduce the living standard of

affected people at dam and reservoir area, besides, it promoted their housing

environment and economic income. The evaluation team considered that the

government has provided complete safeguard policy to the relocatees' rights and

interests. It suggests to further strengthen the training on aquaculture industry and

special agriculture, so as to lay a solid foundation for promoting economic income by

making use of reservoir to develop breeding industry and special agriculture in the

later period.

5 Alteration of Access Road at Songbai Berth and Execution

Songbai Berth is located in Songbai Town of northern Changning City. It is on the

right bank of middle Xiangjiang River and is about 16km upstream Tugutang Complex.

The Berth has one 105m long berth, the length of berth apron is 80m. In the

original design scheme, the inlet and outlet is at the village road with low-grade and

narrow road, which is the only passageway for the 3,000 residents nearby; traffic and

pedestrian flows are relatively large, and there are more than 60 households closing

to the road; lots of facilities and landscapes along the road will be damaged; more

difficulties in land acquisition and demolition. In addition, there would be lots of

potential risks due to mixing of people and vehicles for terminal and access road

construction. Meanwhile, dusts and noise during the construction period would have

large impacts to production and living of nearby residents. secondly, lots of potential

risks for transportation in and out of the terminal. The terminal entrance (OP) is

Page 51: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

32

designed to locate at the gate of Songbai Fertilizer Plant, which forms a junction with

existing village road and Songwa Road. Traffic flows from these three directions joint

together and would easily result in traffic jams. In addition, more than 3,000 residents

and workers pass these area in the meantime, which would result huge potential risks.

Thirdly, the advantage of saving investment is not obvious. Comparing to connecting

with existing village road, the scheme of connecting Songwa road (provincial road)

from about 500m south to the terminal outlet(KL) only increases investment of no

more than three million Yuan. Meanwhile, the new scheme can be in connection with

the 500 thousand-ton Gold-Copper Project, which is in favor of the terminal

development. Therefore, Changning government organized related people to

investigate at site, and widely solicited opinions from local villagers, afterwards,

issued the Changning Government Document [2013] No.66 to HXND (present

HPWTCIG), pointing out to modify the construction scheme of access road of Songbai

kiloton terminal.

HPWTCIG paid great attention to the public opinions on terminal construction,

organizing specialists in Hunan province and related company to hold meeting about

dealing with access road at the Songbai kiloton terminal on 19th. Nov.2013. The

meeting has considered the reasonable opinion of local government, selected new

site for the terminal access road, and urged Hunan Communication Design Institute to

submit alteration drawing. Hunan Hydropower Design Institute (HHPDI) and

resettlement supervisor have re-investigated to the physical index within the land

acquisition scope (including terminal area and access road) of the modified Songbai

Berth, HHPDI also modified some chapters in the original planning report about

planning of land acquisition and resettlement at Songbai kiloton terminal.

After alteration, the Songbai Berth of Changning city takes permanent land

acquisition of 41.16 mu, including paddy field 31.65 mu, pond water surface 5.2 mu,

inland tidal flat 2.13 mu, rural residential land 1.2 mu and transportation land 0.99 mu.

The terminal access road is 471m long, 11m wide, involves in 2 villages (Qingnian

village, Shucai village) and 9 village group (Li group and Xinmin group in Qingnian

village, Laosi group, Tianjia group, Tangjia group, Laowu group, Si group, Hujia group,

and Mutang group in Shucai village). In order to accelerate water transport

development, achieve water transport between north and south, stimulate commodity

circulation, promote local economy, the people in Qingnian and Shucai village agreed

Page 52: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

33

to vacated the land to support the terminal construction through the process of

collective discussion, village consent and municipal government approval. Records of

the meeting are kept..

Evaluation of land acquisition activity

The monitoring personnel considered that after land acquisition at construction

area of Berth, the per capita cultivated land for the 2 groups in Qingnian village is

more than 0.5mu, and for the 7 groups in Shucai village is more than 0.3mu.

Moreover, most young rural labors work outside, and no complain happens, the

construction area keep social stability.

Compensation of land acquisition and house removal

After the scheme alteration, the permanent land acquisition in Songbai kiloton

terminal is 41.16mu, including paddy field 31.65mu and pond 5.2mu. 7 households

with 33 people are relocated with house removal of 2020.86 ㎡(including public house

60 ㎡ and private house 1960.86 ㎡).

Based on the new design alteration drawing, HPWTCIG organized related unit in

Changning city conducting re-investigation of physical index within the land

acquisition scope (including terminal area and access road) of the modified Songbai

Berth, and made statistic, publicity, review, and confirmation, and provided

confirmation as per the standard for reservoir area.

Overall cost for compensation of land acquisition of Songbai Berth after such

alteration is amounted to 5.2337 million Yuan, including compensation cost of rural

resettlement of 3.3175 million Yuan, compensation cost of special facilities of 0.7647

million Yuan, other costs of 0.4127 million Yuan, basic contingencies of 0.3596 million

Yuan and related taxes and charges of 0.3792 million Yuan.

By the end of the fifth monitoring and evaluation period (Dec.2015), each

compensation of the berth had been appropriated as per agreement. According to the

site investigation on the relocated residents they are very satisfied with the terminal

construction and resettlement (one household built house by himself; the other six

households have abandoned their old house, and bought new house at other place).

Page 53: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

34

6. Evaluation of Aid of Vulnerable Groups

6.1 Status Quo of Vulnerable Groups

Based on data provided by local government, conditions sampling-surveyed by

Monitoring Staff and the 6th Nationwide Census Data, affected dam construction area

of Tugutang Navigation & Hydropower Complex includes 2 towns, 4 villages and 18

groups with agricultural population of 2274, including females of 1075, accounting for

47.27%, 462 persons with ages from 0 to 14, accounting for 20.32%, 199 persons

with ages above 65, accounting for 8.75%. And there are 34 households with 94

persons have a per capita net income below RMB 1500 Yuan, accounting for 4.13%.

6.2 Vulnerable Groups Aid Plan

According to requirement of Asian Development Bank (ADB), aid plan of

vulnerable groups of the Complex and Gender Action Plan, mainly include:

1) Tugutang Navigation and Hydropower Complex: during construction and

operation of the Complex, local labor forces are employed and at least 20%

employment opportunities are provided to female labor forces with corresponding

training provided and equal pay for equal work between females and males;

2) Construction of Berths in Songbai Port and Yunji Port: Public consultation is

carried out on construction of the Complex with at least 50% of participant of females

and low-income groups; vocational educational organizations are employed to provide

non-agricultural skill training to local females and at least 500 trained females in the

two ports can obtain employment or self-employment;

3) Capacity Building of Navigation Management Organizations: Person specially

assigned in shipping company to be responsible for implementation of Gender Action

Plan; what's more, 80% of company staffs need training to accelerate gender

awareness.

4) Prevention and Propaganda of AIV and Aids;

5) Safeguard of laborer's authority;

6) Corresponding requirement in Resettlement Plan.

6.3 Assistance Implementation of Vulnerable Groups

1) Tugutang Navigation and Hydropower Complex: HPWTCIG had organized 227

Page 54: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

35

females to receive agricultural and non-agricultural technical trainings, including

plantation of lotus root, fish culture, rear service and catering services. Among the 227

training-received females, totally 96 employed in this project. During construction of

dam area, reservoir area and other areas, quite a part of local labor forces are

employed. There are females who participated simple labors with less technical skills,

and reasonable reward has been paid (details in Chapter 4.2).

2) Construction of Berths in Songbai Port and Yunji Port: Only Songbai Port is

under construction and construction of Yunji Port hasn't been implemented yet.

According to conditions seen and consulted on site of Songbai Port by Monitoring

Staff, ratio for population of low-income who participate in engineering is higher and 8

females participate in rear service of project department (store management, catering

and office work). In 2014, cooperated with Resettlement Bureau in Changning and

Songbai and Women Federations, HPWTCIG held a Women and Children Aid

Conference to express sympathy to 12 poor villagers and 12 underprivileged children

in Shucai Village and a student grant of RMB 6000 Yuan was allocated. Vocational

educational institution was employed to provide skill training to low-income groups

and females and this has been developed persistently since 2013. On February 1st,

2015, HPWTCIG organized Women Federations, Resettlement Bureau and relevant

Principals in Songbai Town and parts of villagers and female representatives in

Shucai Village to hold a symposium, consulting Implementation Plan of Assistance of

Women and Children in Changning City. After the symposium, 7 households of

resettlers have been visited with subsidy of 2000yuan granted to each household.

Total amounts are 14,000 Yuan. In March 2016, skill trainings were provided to 86

persons in Songbai berth construction area. Management Office of Construction of

Tugutang Complex had received more than 30 women of the right ages to engage in

catering, security and other jobs since these years ago. Next step is to prepare to

touch with local government, women federations and enterprises to deal with

employment of women of the right age. But female population that received training

and employment hasn't attended to 500 as required by ADB, the Employer will take

the lead to formulate feasible plan, and will complete the above-mentioned target by

multi-methods through initiating local government, enterprises, and social power.

3) Capacity Building of Navigation Management Organization: During

investigation, ADB Inspection Team believes partial staffs in Management Office of

Page 55: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

36

Tugutang Complex of HPWTCIG, who in charge of resettlement, not familiar with ADB

policy of resettlement. During consulting on site, HPWTCIG is known in fact, that has

maintained strict relation with ADB and World Bank during construction of many

projects before with better knowing resettlement policy of ADB and World Bank.

During midmonth of June in 2015,for purpose of more greatly reinforcing management

of project, better knowing more overall resettlement policy of ADB, experts from ADB

are particularly invited to train related management staffs and strengthen capacity

building of organization.

4) Prevention and Propaganda of AIV and Aids: Since commencement of project

construction, HPWTCIG has consistently developed prevention and propaganda of

AIV and Aids together with local hygiene department and provided physical

examination to associated personnel free of charge.

5) Protection of Laborer Rights: Rights of laborer can be better guaranteed based

on Labor Law together with local labor supervision department. Laborers can propose

complaints to labor supervision departments and local government. PMO of

HPWTCIG are actively planning and preparing to establish a set of efficient Complaint

and Grievance Mechanism (The complainant will directly report to associated

Principal of construction unit) to enable rights-protection-related problem of laborers

better solved for the first time.

6) Associated requirement in planning of resettlement: Compensation shall be

given to household with per capita living space less than 25m2to complement 25m2

housing area of wood and brick. Balance-subsidy shall be allocated for group of

villagers who obtains less land compensation than investment necessary for

production arrangement. Data based on HPWTCIG: From Year of 2012 to Year of

2016 three consultations were held by HPWTCIG, and six gender awareness training

workshops were organized in Changsha, Hengyang Municipality, and Hengnan

county with 306 representatives from HPWTCIG, Governmental Competent

Department of resettlement, women federations, disease control centers, and

contractors participating in. HPWTCIG, together with Resettlement Bureau in

Hengyang City, Women Federations in Hengyang City and associated units in

Hengnan County, Changning City and Leiyang City, developed Women and Children

Aid Implementation Plan in reservoir area, dam area and Songbai Berth and paid a

return visit on effect after implementation of the plan with satisfaction shown by the

Page 56: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

37

beneficiary. In 2013,HPWTCIG provided a student grant of RMB 10000yuan to 20

poverty students (including 12 female students).On September 19th of 2014,partial

staffs of HPWTCIG are organized to attend a Gender Awareness Symposium at

Changsha and totally 34 staffs listened to the symposium. In June of 2015, HPWTCIG

organized Hengnan County and Changning City to complete technical training of the

first batch of 60 women of the right age associated to catering, sanitation and so on.

And 18 women are helped to recommend for employment. In March 2016, HPWTCIG

organized 86 women attending fine breed camellia oleifera skill training, and

recommended employment for 12 people. The second batch of reclamation works in

reservoir area is about to construct. HPWTCIG requires local resettlement

government make a preferential arrangement for vulnerable groups in villages where

project is located (especially for women) with population no less than 100.

7 Relocatee Complaint and Grievance Mechanism Evaluation

7.1 Existing Grievance Mechanism

1) Grievance Channel

--- set citizen complaints offices of all levels such as county, city and province for

relocatees to receive, survey and deal with general grievance issues of relocatees;

--- the resettlement management organizations of all levels such as province, city

and town, being set up according to the laws, should perform the resettlement right of

supervising the lower level and handle the resettlement grievance issues;

--- the independent resettlement supervision or monitoring organization shall

monitor the resettlement implementation due to relevant national regulations, have the

duty to protect the relocatee's legal interests, handle and report the grievance of

affected relocatees to relevant organizations;

--- legal branches such as the administrative supervision, auditing, discipline

inspection, judicial and procuratorial departments are set for all levels of national,

provincial, city and county, to handle the resettlement cases violating laws and

disciplines.

2) Complaints procedure

The relocatees can report their resettlement complaints to the village committee.

The village committee (or the relocatees) can negotiate with local resettlement

Page 57: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

38

implementation organization directly; can also make complaints to upper level

resettlement implementation organization orally or in written form. The upper

resettlement implementation organization will record the complaints after receiving

them, and shall discuss and solve them with the village committee and local

resettlement implementation organization within 10 days. In the case the

contradictions and disputes cannot be solved by negotiation, the village committee

shall make complaints to the administrative organs with jurisdiction level-by-level

(such as project office, resettlement administrative organization, resettlement

supervision and monitoring organization, citizen complaints office, administrative

supervision, discipline inspection and procuratorial departments) by complaint

channel according to the Administrative Procedure Law of the People's Republic of

China, and can file a lawsuit to the People's Court when the solving results are not

satisfied. The village committee can also file lawsuit to the People's Court directly. The

resettlement implementation organization shall record and file all the complaints and

solutions.

According to the supervisors' on-site investigation, all the affected persons said

that they have known the complaint mechanism propaganda, the complaint channel

and procedure.

7.2 Proposed Grievance Mechanism

PMO of HPWTCIG proposed to establish a high efficiency grievance mechanism

(GRM) according to ADB requirement and relocatee demands. According to the M&E

personnel investigate, PMO appointed Mr. Gan Maohui as the principal of complaint

treatment center for resettlement issues. Hengyang resettlement office appointed Mr.

Liu Liangqi to contact with the complain treatment center. Changning resettlement

office appointed Mr. Lei Jide to contact with the complaint treatment center. It was

disclosed to the affected people by means of public notice about the contact

information of resettlement complaint treatment center and complaint submission

procedure.

The Grievance Mechanism efficiently addresses the relocatee complaint and

provide public resettlement consultation, thus HPWTCIG will get more understanding

of the relocatees' willing and the construction impact, and could timely take measures

to eliminate this impact to the greatest extent.

Page 58: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

39

According to the M&E personnel site investigation, the affected people are very

satisfied with this Grievance Mechanism and procedure.

7.3 Complaint Records

According to monitor's statistic, from Jan to June of 2016, the resettlement

organization at each level has received restatement complaints of 10 cases, of which,

8 cases have been resolved, and two cases are pending. Tugutang PMO of

HPWTCIG has received 4 complaint cases; 3 cases have been resolved, and one

case is pending. Hengnan County Tugutang construction headquarter received 3

complaint cases, all of them have been resolved. Changning Resettlement office

received 2 cases, 1 case is resolved, and one case is pending. Leiyang Resettlement

Office received 1 case, which had been resolved. The two pending cases are about

compensation for Changning Qinren hydropower station, which is still in discussion.

The relocatees' complaints can be basically summarized into the following

categories:

1) omissions of physical indicators;

2) omissions of reclamation required areas and crop compensation issues in

reclamation areas;

3)issues of public participation and information disclosure;

4) environmental impacts;

5) other issues.

Typical resolutions of relocatee's complains during this monitoring period.

1) Rebuilding of 72 landing stages: The site investigation show that these 72

landing stages were built before or at the beginning of China liberation period. At that

time, the land traffic infrastructure is very incomplete, and the transport vehicle is in

shortage, the villagers are mainly on foot, and commodities trade mostly done during

specific fairs. In recent years, the rural transport facilities have improved greatly. Due

to bridge construction, especially, "village-access" policy implement, the villagers

travel becomes more and more convenient, the priority are given to the public

transport vehicle(bus) or motorcycle. Shops or small supermarket exist everywhere,

the villagers could buy articles for daily use nearby. Most of the original landing stages

have been abandoned, and give compensation fee for 10000 Yuan/place. Regarding

Page 59: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

40

the landing stages that need to be restored, the design institute submitted the Design

Drawing of Landing Stage in March. 2014. During the construction of slope protection

and reclamation works in Tugutang reservoir, HPWTCIG respected the residents'

opinion, and built the landing stage, domestic dock and guardrail alongside river with

high standard. So far, there has built 135 landing stages and domestic docks, and built

guardrails of 7628m, which assures the villager's life and property safety and traffic

convenience and received good comments from the reservoir residents.

2) Protection of ancient camphor tree at Dazhou island: Dazhou island is a

central bar at Hengnan reservoir area, where grows two ancient camphor trees, but

the tree located ground elevation exceed the inundation level (58.0m) by 3m,

therefore, it is not listed into the inundation scope. The island residents think that the

tree root will long-term immerse in the water after project impounding, which will affect

its growing, they require HPWTCIG to take protection measures. HPWTCIG send

letter to Hunan forestry department in June 2015, and invite experts to make

assessment to the impoundment impacts on camphor trees and point out treatment

measures. Based on protection scheme proposed by forestry departments and the

experts, a scheme design was made by Forestry Investigation and Design Team of

Hengyang City, and construction was carried out by Hengyang Huayan Jianan

Engineering Co. Ltd. The protection scheme is accomplished at present.

3) Resettlement of affected small hydropower station: Hengyang Lijiang Power

Station has been abandoned before construction of Tugutang Complex. It has been

rebuilt, but not for power generation any more. There were four staff in Lijiang Power

Station, of which, two elderly staff has retired and received pension, the other two are

arranged to work at township power supply office. As to compensation to staffs in

Changning Qinren Hydropower Station, they required lump-sum compensation for

irrigation and compensation for power generation as per 130KMh/year (settlement

every year), which results uncommitted lump-sum compensation for the power

station. The issue is still under negotiation.

7.4 Effectiveness of Grievance

According to investigation of monitoring personnel, the reasonable appeals are

treated by each organization. Regarding the unresolved issues, it could give

explanation. The complainant are satisfied with the treatment result, our monitoring

department will follow up the treatment progress of compensation for Changning

Page 60: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

41

Qinren Hydropower station, and suggest PWTCIG could resolve it within the

commitment time.

8. Public Participation and Information Disclosure Evaluation

8.1 Public participation

The planning and implementation of this project relate closely with the public

participation. There are members from local groups attended the physical index

investigation during planning stage, and make disclosure and verification after

investigation (3 times disclosure and two times verification), when the public has no

objection to the index, it will be confirmed by the group, village, town, and county (city)

step by step. The resettlement method in the Resettlement outline and RP is also first

advised by the local relocatee, and then prepared by the design institute as per

advice, afterwards, will hold county and city hearing, listen to the public suggestion, at

last modify and improve the document. Many design scheme are also defined by

public meeting, for instance, water system restore scheme at dam area, protection

scheme of Quanxi ancient well, renovation scheme of reservoir culvert pump port,

renovation scheme of water intake well of Lijiang tap water factory, protection of

ancient trees in Dazhou Island, and compensation scheme of Qinren Hydropower

Station, etc. The resettlement work for this project represents the public intelligence.

The compensation reimbursement is also done by local resettlement

organization, participated by town, village group, and ownership personnel, hold

meeting to work out the allocation scheme, and then reimburse the compensation.

During compensation reimbursement, 2 representatives from county (city)

management organization, 1~2 township government representatives and leaders

from involved group participated. When verify the compensation amount, the head of

household or ownership unit representative (more than 2 people) participated in .

8.2 Information Disclosure

Before physical index investigation, Hunan Government issued Construction

Banning Notice to the whole inundation affected area, to inform the local residents

about the matters related to project construction; the local government disclosed the

project-related information through TV, broadcast, network, mobile louder speaker

and brochure. After physical index investigation, made three times disclosure to the

public, and then confirmed by each authorization level

Page 61: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

42

During construction, the local government disclosed the compensation standards

to the affected people. (See section 2.7.1). During compensation reimbursement, it

has disclosed and rechecked the physical index quantity, compensation standards,

and compensation amount, and distribute the fund in batches after getting signature

(with seal) of all the owners, groups, villages, and towns.

In case of construction that might affect the public safety (such as blasting,

transportation of reclamation soils), it also give the notice of affected scope, and

inform the public to take safety measures during this period, thus it assured the

people's life and property safety at the greatest extent.

8.3 Follow-up work

Expanding disclosure to the follow-up information as per Resettlement Plan.

Regarding the rebuilding schemes of small scale special facilities, drainage culvert,

tractor-bridge at reclamation area, and foot bridges, it will continue to listen to local

villagers' opinions and implement on the basis of these opinions.

9 Results of Monitoring and Evaluation

9.1 Evaluation of Resettlement Implementation

Permanent Land Requisition: land requisition at dam area, reservoir area,

Songbai Berth construction area, and New Water Source construction area had all

been completed, which assured navigation, impounding and power generation of

Tugutang Complex.

House removal: House removals at dam area, reservoir area, and berth

construction area had been completed, which achieved the goal.

Resettlement: production resettlement at reservoir area and dam area, and

house removal were all complied with the schedule, which met needs of the project

construction.

Temporary land requisition: temporary land requisition meets the schedule

requirements; compensation for requisitioned land has been paid; the affected people

have no complaint to it. Reclamation of 370 mu lands in reservoir area had been

completed and handed over to the villagers for cultivation. In Jan-Jun 2016, Hengnan

county has completed 120 mu land reclamation, but land recamation has not been

Page 62: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

43

implemented in Changning and Leiyang City.

Constructions of special works The progress of special works is slow and has

not reach the goal, so the relevant units shall actively fulfill their functions to catch on

the project progress and assure project quality.

Compensation payment The compensation standards for this project comply

with law and regulation. The compensation payment is open and transparent, without

any deduction, the affected people have a clear understanding to the compensation

amount, and it could get approval from audit department..

9.2. Evaluation on Resettlement Implementation & Management Organizations and Their Operation Conditions

The personnel structure of Tugutang Complex resettlement Implementation and

Management organization is arranged reasonably with complete facilities and good

staff training. The overall ability of the resettlement managing staff is good.

9.3 Monitoring & Evaluation on Measures for Restoration of Living Standard of Relocatees

The assessment shows that the affected people at dam & reservoir area, and

Songbai Berth area have improved their living standard in comparison with before

land requisition.

9.4. Evaluation on Aid to Vulnerable Groups

The Gender action for this project is in progress, and great achievement has

been made, but the assistance quantity has not meet the ADB requirement, it is

suggested to implement 2016 assistance plan as soon as possible.

9.5 Evaluation on Relocatee's Complaint and Grievance Mechanism

The Complaint and Grievance Mechanism is complete, the complained issues

can be received and treated. It is suggested that the treatment efficiency could be

improved and a high efficiency complaint and Grievance Mechanism be established.

9.6. Public Participation and Information Disclosure Evaluation

The affected people have the information right and participation right. The

participation and information disclosure reach a higher degree. It is suggested to take

more channels to assure the people at different level could have a thorough

understanding to the construction information.

Page 63: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

44

9.7 Problems and Follow-up Work

1) It is suggested to accelerate the second batch of reclamation works, and

ensure normal water impounding and power generations, and full play irrigation

benefits.

2) Strengthen the attention to the vulnerable groups, and endeavor to implement

the social responsibility.

3) Strengthen the publicity of resettlement policy, and promote the public

participation.

4) It is suggested to strengthen power station management, promote operation

efficiency and benefit.

5) Track the treatment progress of unsettled resettlement issues.

10 Compliance of Loan Agreement

SN. Main agreements for resettlement implementation in

Loan Agreement Compliance

1 Complete land approval and land requisition according to project schedule so that the Contractor can access the site for construction on time.

Conform.

2

The carrying-out of resettlement shall conform to national laws and regulations, ADB's security policy, and all the measures and requirements in the resettlement plan.

Conform.

3

Before land requisition and relocation (1) pay the compensation fund; (2) make livelihood recovery measures and production resettlement scheme according to the requirements of resettlement plan; (3) get the agreement of the affected people, confirm the relocation place of affected village and group.

Conform.

4 The inundation of country road and infrastructures due to project operation and other negative effects shall be handled and restored timely and effectively.

Conform

5 The project unit shall timely notify ADB the decisions about building bridges near Tugutang Navigation and Hydropower Complex.

Conform.

6 During project implementation, any significant change Conform.

Page 64: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

45

about resettlement influence shall notify ADB timely. The resettlement plan shall be modified and reported to ADB for approval if necessary.

7

The project unit shall have enough staff and budget (with special social and safeguard policy implementation department) to carry on resettlement according to the resettlement plan.

Conform.

8

Employ an individual external monitoring mechanism to prepare the semi-annual monitoring report and disclose the relevant information to the affected people within 3 months after the loan comes into effect.

Conform.

9

Within 3 months after the loan comes into effect, set up grievance and complaint mechanism according to the resettlement plan to solve the disputes and disagreements about resettlement and make written records.

Conform.

Page 65: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

46

Attached Table 1

Summary Table of Permanent Land Requisition

Land Type

Inundation influence land occupation of project Residential base requisition Total

Remark Planned This

Period Cumulative Planned

This Period

Cumulative Planned This

Period Cumulative Planned

This Period

Cumulative

(area-mu) (area-mu) (area-mu) (area-mu) (% of total)

Total 4959.23 4959.23 1501.88 1504.58 14.37 13.86 6475.48 6477.67 100.03%

I Reservoir area 4959.23 4959.23 637.52 637.52 8.96 8.96 5605.71 5605.71 100.00%

Collective Land (By Category)

4959.23 4959.23 637.52 637.52 8.96 8.96 5605.71 5605.71 100.00%

Farmland

subtotal 1496.35 1496.35 373.03 373.03 8.96 8.96 1878.34 1878.34 100.00%

Paddy Field

1047.09 1047.09 369.62 369.62 8.96 8.96 1425.67 1425.67 100.00%

Dry land

134.92 134.92 3.41 3.41 138.33 138.33 100.00%

Flood Land

314.34 314.34 314.34 314.34 100.00%

Water area and land for water facilities

281.8 281.8 281.8 281.8 100.00%

Garden Plot 8.5 8.5 8.5 8.5 100.00%

Forest Land 639 639 3.8 3.8 642.8 642.8 100.00%

Grassland 2510.61 2510.61 230.84 230.84 2741.45 2741.45 100.00%

Other lands 22.97 22.97 29.85 29.85 52.82 52.82 100.00%

II Dam area 818.45 818.45 3.7 3.7 822.15 822.15 100.00%

1 Collective Land (By Category)

741.87 741.87 3.7 3.7 745.57 745.57 100.00%

Farmland

subtotal 475.13 475.13 3.7 3.7 478.83 478.83 100.00%

Paddy Field

449.31 449.31 449.31 449.31 100.00%

Dry land

25.82 25.82 3.7 3.7 29.52 29.52 100.00%

Water area and land for water facilities

24.8 24.8 24.8 24.8 100.00%

Forest Land 186.2 186.2 186.2 186.2 100.00%

Page 66: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

47

Attached Table 1

Summary Table of Permanent Land Requisition

Land Type

Inundation influence land occupation of project Residential base requisition Total

Remark Planned This

Period Cumulative Planned

This Period

Cumulative Planned This

Period Cumulative Planned

This Period

Cumulative

(area-mu) (area-mu) (area-mu) (area-mu) (% of total)

Grassland 53.36 53.36 53.36 53.36 100.00%

Other lands 2.38 2.38 2.38 2.38 100.00%

2 Residential land

8 8 8 8 100.00%

3 Other land 68.58 68.58 68.58 68.58 100.00%

III kiloton dock construction area

37.26 39.96 1.71 1.2 37.84 41.16 108.77% Changed Contract

Price

Collective Land (By Category)

57.27 39.96 1.71 1.2 58.98 41.16 69.79%

Farmland

Paddy Field

31.65 31.65 1.71 1.2 33.36 32.85 98.47%

Flood Land

2.12 2.12 2.12 2.12 100.00%

Water area and land for water facilities

5.2 5.2 5.2 5.2 100.00%

Grassland 17.31 17.31

Other lands 0.99 0.99 0.99 0.99 100.00%

IV New Water source construction area

8.65 8.65 8.65 8.65 100.00%

Collective Land (By Category)

8.65 8.65 8.65 8.65 100.00%

Farmland

Paddy Field

7.61 7.61 7.61 7.61 100.00%

Dry land

0.64 0.64 0.64 0.64 100.00%

Other lands 0.4 0.4 0.4 0.4 100.00%

Page 67: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

48

Attachd Tabl2

Summary of Housing Demolition

Structure Type

Hengnan County Changning City Leiyang City Total

Remark Planne

d

This Perio

d

Cumulative

Planned

This Perio

d

Cumulative

Planned

This Perio

d

Cumulative

Planned This Perio

d Cumulative

(area - m2) (area - m2) (area - m2) (area - m2) (% of total)

Total 9122.6

3 9145.83

5953.35

5953.35 4318.5

2 3065.56

18864.46

18164.7

4 96.29%

I Reservoir area 2924.7 3206.3 3932.4

9 3932.49

4318.52

3065.56 11175.7

1

10204.35

91.31%

Private

1519.7

7 1801.37

2249.42

2249.42 3946.9

6 2694 7716.15 6744.79 87.41%

Framework 45.5 45.5 167.89 167.89 56.78 56.78 270.17 270.17 100.00

%

Brick-masonry

688.6 688.6 1538.8

5 1538.85

1439.21

533.94 3666.66 2761.39 75.31%

Masonry-timber

117.13 117.13 23.33 23.33 1651.2

2 1328.78 1791.68 1469.24 82.00%

earth-timber 2.24 2.24 2.24 2.24 100.00

%

Miscellaneous Room

668.54 668.54 519.35 519.35 305.28 280.03 1493.17 1467.92 98.31%

Basic 281.6 492.23 492.23 492.23 773.83 157.21

%

Public 1404.9

3 1404.93

1683.07

1683.07 371.56 371.56 3459.56 3459.56 100.00

%

Brick-masonry

1227.48

1227.48 1173.9

4 1173.94 334.9 334.9 2736.32 2736.32

100.00%

Masonry-timber

146.14 146.14 399.25 399.25 545.39 545.39 100.00

%

Miscellaneous Room

31.31 31.31 109.88 109.88 36.66 36.66 177.85 177.85 100.00

%

II Dam area 5939.5

3 5939.53 5939.53 5939.53

100.00%

Private

5778.6

3 5778.63 5778.63 5778.63

100.00%

Brick-masonr 2597.8 2597.85 2597.85 2597.85 100.00

Page 68: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

49

Attachd Tabl2

Summary of Housing Demolition

Structure Type

Hengnan County Changning City Leiyang City Total

Remark Planne

d

This Perio

d

Cumulative

Planned

This Perio

d

Cumulative

Planned

This Perio

d

Cumulative

Planned This Perio

d Cumulative

(area - m2) (area - m2) (area - m2) (area - m2) (% of total)

y 5 %

Masonry-timber

1955.05

1955.05 1955.05 1955.05 100.00

%

earth-timber 261.02 261.02 261.02 261.02 100.00

%

Miscellaneous Room

964.71 964.71 964.71 964.71 100.00

%

Public 160.9 160.9 160.9 160.9 100.00

%

Brick-masonry

160.9 160.9 160.9 160.9 100.00

%

III kiloton dock construction area

258.4 2020.8

6 2020.86 2219.26 2020.86 91.06%

Changed

Contract Price

Private

258.4 1960.8

6 1960.86 2219.26 1960.86 88.36%

Brick-masonry

258.4 338.4 338.4 596.8 338.4 56.70%

Masonry-timber

1201.3 1201.3 1201.3 1201.3 100.00

%

earth-timber 250.62 250.62 250.62 250.62 100.00

%

Miscellaneous Room

170.54 170.54 170.54 170.54 100.00

%

Public 60 60 60 60

Brick-concrete

60 60 60 60

Page 69: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

50

Attached Table 3

Table of Land Acquisition and Resettlement Influence

Impact type

Hengnan County Changning City Leiyang City Total

Remark Planne

d

Actual Planne

d

Actual Planne

d

Actual Planne

d

Actual

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d Cumulative

(Person)

(Person) (Perso

n) (Person)

(Person)

(Person) (Perso

n)

(Person)

(% of total)

I Reservoir area

Land loss influence

Total 3707 3707 2914 136 1230 866 205 463 7487 341 5400 72.13

%

Paddy field loss 3659 3659 2822 136 1138 854 205 451 7335 341 5248 71.55

%

Loss of Dry land 48 48 92 92 12 12 152 152 100.00

%

housing/structure loss influence

Dismantle/protection resettlement

17 25 26 36 160 7 126 203 7 187 92.12

%

No overlap Total (land loss + housing loss)

3724 3732 2940 1810 2940 1026 649 1026 7690 2459 7690 100.00

%

Severely Affected

relocated households loss 15% or more productive assets

3135 3135 2539 2539 631 631 6305 6305 100.00

%

Vulnerable groups

Poverty, disability and women as main mass

See detail in

5.1 Status of vulnerable group

II Dam area

Page 70: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

51

Attached Table 3

Table of Land Acquisition and Resettlement Influence

Impact type

Hengnan County Changning City Leiyang City Total

Remark Planne

d

Actual Planne

d

Actual Planne

d

Actual Planne

d

Actual

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d Cumulative

(Person)

(Person) (Perso

n) (Person)

(Person)

(Person) (Perso

n)

(Person)

(% of total)

Land loss influence

Total 405 405 405 405 100.00

%

Paddy field loss 389 389 389 389 100.00

%

Loss of Dry land 16 16 16 16 100.00

%

housing/structure loss influence

Relocation 80 90 80 90 121.25

%

No overlap Total (land loss + housing loss)

485 495 485 495 103.51

%

Severely Affected

relocated households loss 15% or more productive assets

312 219 312 312 219 312 100.00

%

Vulnerable groups

Poverty, disability and women as main mass

See detail in

5.1 Status of vulnerable group

III kiloton dock construction area

Changed

Contract Price

Land loss influence

Total 67 67 67 67 100.00

%

Page 71: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

52

Attached Table 3

Table of Land Acquisition and Resettlement Influence

Impact type

Hengnan County Changning City Leiyang City Total

Remark Planne

d

Actual Planne

d

Actual Planne

d

Actual Planne

d

Actual

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d

Cumulative

This Perio

d Cumulative

(Person)

(Person) (Perso

n) (Person)

(Person)

(Person) (Perso

n)

(Person)

(% of total)

Paddy field loss 67 67 67 67 100.00

%

housing/structure loss influence

Relocation 33 33 33 33 100.00

%

No overlap Total (land loss + housing loss)

100 100 100 100 100.00

%

Severely Affected

relocated households loss 15% or more productive assets

62 62 62 62 100.00

%

Vulnerable groups

Poverty, disability and women as main mass

See detail in

5.1 Status of vulnerable group

Attached Table 4

Compensation and Recovery of Temporary Land Occupation

Project Name Unit

Hengnan County Changning City Leiyang City Total

Remark Planned

Actual Planne

d

Actual Planne

d

Actual Planne

d

Actual

This Perio

Cumulative

This Perio

Cumulative

This Perio

Cumulative

This Perio

Cumulative

Page 72: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

53

d d d d

I Reservoir area

1. Temporary land occupation area

mu 3256.6

3 3256.63

1855.36

1855.36 553.94 553.94 5665.9

3 5665.93

In implementati

on

2. investment of temporary land occupation compensation

X10 thousand Yuan

560.38 560.38 318.77 318.77 91.89 91.89 971.04 971.04

including crop compensation

3. land recovery area

mu 1908.8

7 120 370 900.01 439.17

3248.05

120 370In

implementation

4. land recovery investment

X10 thousand Yuan

1061.26

130 400 555.56 199.66 1816.4

8 130 400

In implementati

on

II Dam area

1. Temporary land occupation area

mu 386.33 386.33 386.33 386.33

2. investment of temporary land occupation compensation

X10 thousand Yuan

206.96 206.96 206.96 206.96

3. crop compensation

X10 thousand Yuan

34.98 78.01 34.98 78.01

4. land recovery area

mu 179.58 179.58 In implementation

Page 73: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

54

5. land recovery investment

X10 thousand Yuan

141.47 141.47 In implementation

Ⅲ New water source construction area

1. Temporary land occupation area

mu 251.09 251.09 251.09 251.09

2. investment of temporary land occupation compensation

X10 thousand Yuan

30.97 30.97 30.97 30.97

3. crop compensation

X10 thousand Yuan

34.04 34.04 34.04 34.04

4. land recovery area

mu 106.32 106.32 106.32 106.32

5. land recovery investment

X10 thousand Yuan

11.94 11.94 11.94 11.94

6. compensation of the affected facilities

X10 thousand Yuan

16.9 16.9 16.9 16.9

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Page 74: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

55

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

Total 28230.45 509.91 27609.42 11587.59 1420.92 8684.24 3359.38 359.48 2456.90 43177.42 2290.31 38750.56 89.75%

I Reservoir area 23756.91 469.91 23186.70 11169.95 1412.92 8258.60 3349.96 359.48 2456.90 38276.82 2242.31 33902.20 88.57%

I. Rural resettlement compensation

6467.62 6468.00 3736.62 3736.62 1252.25 1252.25 11456.49 11456.87 100.00%

(I) Land compensation and resettlement fee

4972.99 4972.99 2782.17 2782.17 698.06 698.06 8453.22 8453.22 100.00%

(II) House compensation

171.85 171.85 258.83 258.83 305.10 305.10 735.78 735.78 100.00%

(3) Subsidy for housing poverty household

0.66 0.66 1.93 1.93 72.89 72.89 75.48 75.48 100.00%

(IV) Living subsidy during transition period

102.60 102.60 68.90 68.90 25.80 25.80 197.30 197.30 100.00%

(V) Subsidy for production resettlement

68.18 68.18 20.55 20.55 88.73 88.73 100.00%

(VI) Compensation for infrastructure

7.30 7.30 12.69 12.69 81.29 81.29 101.28 101.28 100.00%

(VII) Subsidy for relocation

1.02 1.40 1.56 1.56 10.92 10.92 13.50 13.88 102.81%

(8) Sporadic fruit tree and tomb

34.67 34.67 10.25 10.25 0.12 0.12 45.04 45.04 100.00%

(IX) Agriculture and subsidiary facilities

203.68 203.68 131.78 131.78 11.90 11.90 347.36 347.36 100.00%

(X) Rural small scale Hydropower facilities

904.67 904.67 447.96 447.96 46.17 46.17 1398.80 1398.80 100.00%

II. Compensation fee for rehabilitation and renovation of special works

5363.71 63.33 5221.60 1585.07 202.92 987.81 611.78 13.00 595.19 7560.56 279.25 6804.60 90.00%

(1). classified highway

289.06 50.00 226.00 80.16 80.16 369.22 50.00 306.16 82.92%

(2). Traffic Facilities Around Reservoir

1734.33 40.00 1594.30 718.44 65.00 423.01 518.59 13.00 502.00 2971.36 118.00 2519.31 84.79%

(3) Transmission facilities

50.65 10.00 48.57 25.77 15.00 15.00 3.20 3.20 79.62 25.00 66.77 83.86%

(4). Communication 23.33 13.33 23.33 72.92 72.92 72.92 9.83 9.83 106.08 86.25 106.08 100.00%

Page 75: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

56

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

Facilities

(5). Hydroelectric Facilities

3459.40 3459.40 478.88 250.88 3938.28 3710.28 94.21%

1. Medium Electric Pumping Station

769.40 769.40 769.40 769.40 100.00%

2. Sluice gate

1830.64 1830.64 144.88 144.88 1975.52 1975.52 100.00%

3. Water Pump House

80.00 80.00 80.00 80.00 100.00%

4. Small Hydropower Station

853.36 853.36 228.00 1081.36 853.36 78.92%

5. Water Tower

20.00 20.00 20.00 20.00 100.00%

6. Intake Well in Water Plant

6.00 6.00 6.00 6.00 12.00 12.00 100.00%

(6) cultural relics protection fee

96.00 96.00 96.00 96.00 100.00%

III. Protection work fee

11882.96 406.58 11454.48 5822.24 1210.00 3508.15 1481.59 342.14 605.12 19186.79 1958.72 15567.75 81.14%

(1) reservoir bank protection project

3130.46 3130.46 1581.65 1581.65 275.12 12.14 275.12 4987.23 12.14 4987.23 100.00%

1.Building works

2590.11 2590.11 1320.20 1320.20 210.96 210.96 4121.27 4121.27 100.00%

2. Temporary Projects

129.27 129.27 69.97 69.97 19.69 19.69 218.93 218.93 100.00%

3. Independent cost

411.08 411.08 191.48 191.48 44.47 12.14 44.47 647.03 12.14 647.03 100.00%

Land

Occupation Cost

121.35 121.35 27.96 27.96 11.33 11.33 160.64 160.64 100.00%

Page 76: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

57

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

Material Transfer

289.73 289.73 163.52 33.52 163.52 33.14 12.14 33.14 486.39 45.66 486.39 100.00%

(2) Lifting and filling project

8638.06 406.58 8209.58 4221.09 1210.00 1907.00 1206.47 330.00 330.00 14065.62 1946.58 10446.58 74.27%

1.Building works

4521.02 200.00 4233.00 2265.67 650.00 1082.00 654.23 140.00 140.00 7440.92 990.00 5455.00 73.31%

2. Temporary Projects

196.36 12.36 196.36 102.15 50.00 85.00 44.04 20.00 20.00 342.55 82.36 301.36 87.98%

3. Independent cost

3920.68 194.22 3780.22 1853.27 510.00 740.00 508.20 170.00 170.00 6282.15 874.22 4690.22 74.66%

Land

Occupation Cost

2153.22 114.22 2153.22 990.81 430.00 600.00 288.10 120.00 120.00 3432.13 664.22 2873.22 83.72%

Material Transfer

1767.46 80.00 1627.00 862.46 80.00 140.00 220.10 50.00 50.00 2850.02 210.00 1817.00 63.75%

(3) inundation treatment project

114.44 114.44 19.50 19.50 133.94 133.94 100.00%

1.Building works

42.51 42.51 7.09 7.09 49.60 49.60 100.00%

2. Temporary Projects

11.74 11.74 1.70 1.70 13.44 13.44 100.00%

3. Independent cost

60.19 60.19 10.71 10.71 70.90 70.90 100.00%

Land

Occupation Cost

50.64 50.64 8.47 8.47 59.11 59.11 100.00%

Material Transfer

9.55 9.55 2.24 2.24 11.79 11.79 100.00%

4. Reservoir bottom cleaning fee

42.62 42.62 26.02 26.02 4.34 4.34 4.34 72.98 4.34 72.98 100.00%

II Dam area 4258.84 40.00 4235.85 4258.84 40.00 4235.85 99.46%

I. Rural resettlement compensation

3591.23 3601.03 3591.23 3601.03 100.27%

Page 77: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

58

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

(I) Permanent land occupation

2722.82 2722.82 2722.82 2722.82 100.00%

(II) Temporary land occupation

383.41 383.41 383.41 383.41 100.00%

(III) House and auxiliary structures

342.09 342.09 342.09 342.09 100.00%

(IV) Sporadic fruit tree and tomb

7.06 14.81 7.06 14.81 209.77%

(V) Agriculture and subsidiary facilities

1.60 1.60 1.60 1.60 100.00%

(VI) Rural small scale Hydropower facilities

49.38 49.38 49.38 49.38 100.00%

(VII) Compensation of infrastructure facilities

39.57 39.57 39.57 39.57 100.00%

Residential base requisition

14.81 14.81 14.81 14.81 100.00%

Ground Leveling

24.00 24.00 24.00 24.00 100.00%

Water and electricity subsidies

0.76 0.76 0.76 0.76 100.00%

(VIII) Subsidy for relocation

4.80 6.85 4.80 6.85 142.67%

(IX) Living subsidy during transition period

40.50 40.50 40.50 40.50 100.00%

2. Rehabilitation and renovation fee of special facilities

667.61 40.00 634.82 667.61 40.00 634.82 95.09%

(I) Traffic facilities 28.86 28.86 28.86 28.86 100.00%

(II) Transmission facilities

41.08 41.08 41.08 41.08 100.00%

(III) Communication facilities

5.88 5.88 5.88 5.88 100.00%

Page 78: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

59

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

(IV) Water conservancy and hydropower facilities

591.79 40.00 559.00 591.79 40.00 559.00 94.46%

1. Sluice gate

10.00 10.00 10.00 10.00 100.00%

2. Water system recovery

581.79 40.00 549.00 581.79 40.00 549.00 94.36%

III kiloton dock construction area 27.83 408.22 408.22 436.05 408.22 93.62%

I. Rural resettlement compensation

27.83 331.75 331.75 359.58 331.75 92.26%

(1) Permanent land requisition

9.74 171.29 171.29 181.03 171.29 94.62%

(2) House and auxiliary building

18.04 128.07 128.07 146.11 128.07 87.65%

(3) Sporadic fruit tree 0.05 4.69 4.69 4.74 4.69 98.95%

(4) Rural small scale hydropower facilities

3.30 3.30 3.30 3.30 100.00%

(5) Infrastructure compensation

15.72 15.72 15.72 15.72 100.00%

(6) Removal Allowance

1.98 1.98 1.98 1.98 100.00%

(7) Living allowance during transition period

6.70 6.70 6.70 6.70 100.00%

II. Special facilities 76.47 76.47 76.47 76.47 100.00%

(I) Traffic facilities 5.50 5.50 5.50 5.50 100.00%

(2) electric power infrastructure

70.97 70.97 70.97 70.97 100.00%

IV Assistance Fund for Female and Children

12.56 12.56 9.42 8.00 17.42 9.42 31.40 8.00 29.98 95.48%

V New Water source construction 174.31 174.31 174.31 174.31 100.00%

I. Rural resettlement compensation

104.70 104.70 104.70 104.70 100.00%

Page 79: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

60

Attached Table 5

Investment of Land Acquisition and Resettlement Compensation

Compensation Investment Items

Hengnan County Changning City Leiyang City Total

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

Planned Accomplished.

This Period

Cumulative This

Period Cumulative

This Period

Cumulative This

Period Cumulative

(% of total)

(104 Yuan) (104 Yuan) (104 Yuan) (104 Yuan)

(1) Permanent land requisition

10.88 10.88 10.88 10.88 100.00%

(2) temporary used land

30.94 30.94 30.94 30.94 100.00%

(3). crop compensation

34.04 34.04 34.04 34.04 100.00%

(4) small-scale facilities compensation

16.90 16.90 16.90 16.90 100.00%

(5) land recovery 11.94 11.94 11.94 11.94 100.00%

2. fees and management fees

69.61 69.61 69.61 69.61 100.00%

Page 80: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

61

Attachment 1:

Name List of Monitoring and evaluation Meeting Staff

Tugutang project management department of HPWTCIG

Gan Maohui deputy director, director of reservoir area department

Li Mingyan member of reservoir area department

Xiao Yu member of reservoir area department

Tugutang design representative team of Hunan Hydro& Power Design Institute

Tan Lu leader of design representative team, engineer

Zeng Taihua engineer

Tugutang comprehensive supervision department of Hunan Xiangyi

Resettlement Construction Supervision and Consulting Co. Ltd

Qian Zhiyuan chief inspector, senior engineer

Huang Xing assistant engineer

project construction coordination office of Hengnan County Tugutang

Navigation and Hydropower Complex

Wang Wei deputy commander

Chen Dongsheng leader of project department

Xu Xianheng leader of land requisition and demolition department

Xie Lun leader of financial department

Zhang Xiaochu engineer

Changning city resettlement bureau

Deng Chenghua Director General

Lei Jide deputy bureau chief, leader of resettlement group

Liu Huarong leader of engineering and technology group

Yin Yun engineer

Resettlement Bureau of Leiyang City

Luo Youcheng chief deputy bureau director

Xie Guichao Staff

Attachment 2

Page 81: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

62

Main data content for supervision and evaluation consulting

1. Planning and Design Report of Land Acquisition and Resettlement for Hunan

Xiangjiang Tugutang Navigation and Hydropower Complex (approval version)

2. Supplement Report on Land Acquisition Compensation Adjustment for Hunan

Xiangjiang Tugutang Navigation and Hydropower Complex (approval version)

3. Resettlement Agreement of Hunan Xiangjiang Tugutang Navigation & Hydropower

Complex

4. Resettlement Supplement Agreement of Hunan Xiangjiang Tugutang Navigation &

Hydropower Complex

5.Notification about Issuing of Tugutang Navigation and Hydropower Complex

Resettlement Plan in Year 2015 by Hengyang Resettlement Bureau

6. Monthly Report for Hunan Xiangjiang Tugutang Navigation & Hydropower Complex

Resettlement Supervision (July ~ December, 2015)

7. House Demolition Agreement for Tugutang Navigation and Hydropower Complex

by Hengnan County

8. Land Acquisition Agreement by Hengnan County

9. Changning Reservoir Area Land Acquisition Compensation and Resettlement

Agreement for Tugutang Navigation and Hydropower Complex by Changning City

10. Changning City Construction Land Acquisition Resettlement Compensation

Agreement for Tugutang Navigation and Hydropower Complex by Changning City

11. Changning Reservoir Area Construction Land Acquisition Resettlement

Small-scale Special Works Compensation Agreement for Tugutang Navigation and

Hydropower Complex by Changning City

12. Land Acquisition Compensation and Resettlement Agreement for Tugutang

Navigation and Hydropower Complex by Leiyang City

13. Construction Land Acquisition Resettlement Compensation Agreement for

Tugutang Navigation and Hydropower Complex by Leiyang City

14. Payment document of Tugutang resettlement compensation fund of Hengnan

County

15. Payment document of Tugutang resettlement compensation fund of Changning

Page 82: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

63

City

16. Payment document of Tugutang resettlement compensation fund of Leiyang City

17. Contract of Reservoir Area Rising & Filling and Traffic work Construction in

Hengnan County for Tugutang Navigation and Hydropower Complex

18. Progress payment documents for the project construction.

19. Notice of resettlement scheme for Hengnan, Changning, and Leiyang

Page 83: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

64

Attachment 3

Name List of Affected People Being Consulted

Xintangzhan Village, Yunji Town, Hengnan County (Dam area)

Xie Weiguo Township cadre

Peng Xiaobing village cadre

Ouyang Feng affected villager in Piaotang group

Yang Guozhu affected villager in Tanggu group

Pengci Village, Xiangyang Town, Hengnan County (Dam area)

Xie Yuncheng town cadre

Peng Xiaogao village cadre

PengTiling, Peng Yalin, Peng Xiuping affected villager in Dawu group

Liu Kaixiu, Peng Zhongyuan, Qu Zhenghuo affected villager in Shani group

Songjiang Town, Hengnan County (Reservoir Are)

Wu Guohua affected villager in Dawu group, Yuebao village

Zhang Qing, Yang Gaoxi affected villager in Laojinpen group, Jinpen village

Mashi Village, Yanzhou Town, Changning City (Reservoir Are)

Qiu Jiansong affected villager in Fengxing group 2

Qiu Xiaogang affected villager in Fengxing group 1

Shucai village, Shuikoushan Office, Changning City (Songbai Kilo Ton Dock

construction area)

Liu Gongying, Chen Yiming, Wei Huamei

Yajiang Village, Daheyu, Leiyang City

Liu Gongping, Zhu Zhongjun affected villager in No.3 group

Page 84: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

65

Attachment 4: Site Photos

(1)Dam area

Page 85: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

66

(2)Special Work Construction

Taishan Simple Road bridge Reclamation canal construction at

at Xinhua village, Leiyang City Jinyu block B in Hengnan County

(3)M&E Personnel on-site consult

Page 86: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

67

(4)Training

Training to relocatees from Shucai Village at Songbai kiloton construction area

Provincial reservoir resettlement experience exchange meeting and business training

held in Huaihua Hongjiang City

Page 87: PRC: Hunan Xiangjiang Inland Waterway Transport Project · and Consulting Co. Ltd.(hereinafter called our company), as the independent external monitoring and evaluation unit, is

68

Attachment 5: Petition letter