Upload
indhucs
View
797
Download
7
Embed Size (px)
Citation preview
Power System Operation and Control
Load Variations and Load Characteristics, Load Curves, Load Duration Curves, Reserves, Load Forecasting and Unit Commitment
IntroductionPower Station delivers power to large number of
customersCustomer’s need (or load) is never constantElectric Power cannot be stored and must be
consumed upon productionAt the same time, alternators give maximum
efficiency at their rated capacityProper Load prediction and calculations are key
to efficient design of power Station
Topics CoveredLoad Curve.Daily Load Curve Interpretation.Few important terms and factors.Load Duration Curves.Base Loads, Peak loads.Reserves.Load Forecasting.Unit Commitment.
Variable LoadDefinition: The load on a power station varies from time to
time due to uncertain demands of customers. This is known as Variable load on power station
Effects of Variable Load:Need for additional Equipment
◦ Eg: Equipment to handle raw materials during varying load conditions in thermal power station.
Increase in Production Cost ◦ Eg: Alternators of different capacities must be installed to get
maximum efficiency by operating at rated capacity.
Load Curves
Definition: The curve showing variation of load on a power station w. ref. to time
Daily Load Curve Variation of load on a day plotted on
an hourly basis
Monthly Load Curve Variations of load in a month –
Plotted using daily load curves used to fix rates of
energy
Yearly Load Curve Extrapolated using monthly load
curves used to determine annual Load Factor 0 4 8 12 16 20 240
1
2
3
4
5
6
7
Load Curve
Hours
Load in M
W
Noon
Daily Load Curve Interpretation Shows variation of load on power
station on a day Units generated in a day = Area (in
kWh) under the daily load curve Highest point on curve Maximum
demand on the station for the day
Helps in
◦ Selecting Size and number of generating units
◦ Preparing operating schedule of the station
hrs
curvedailyunderkWhinAreastationtheonLoadAverage
24
)(
DemandMax
LoadAverageFactorLoad
Important Terms and Factors Connected Load: Sum of continuous rating of
all equipments connected to supply system Maximum Demand: Greatest demand of
Load on the power station during a given time
◦ usually <1◦ vital in determining capacity of plant equipment
Average load or Average Demand: Average of loads occurring on a power station in a given period
LoadConnected
DemandMaximumFactorDemand
8760
)(
)(
24
)(
yearaingeneratedkWhunitsofNoLoadavgYearly
monthainHours
monthaingeneratedkWhunitsofNoLoadavgMonthly
hrs
dayaingeneratedkWhunitsofNoLoadavgDaily
Important Terms and Factors – contd..
◦ always <1◦ Used for determining overall cost/unit
generation◦ Higher the load factor lesser the cost /
unit
◦ always > 1◦ Greater diversity factor lesser cost of generation of power
◦ Indicative of reserve capacity of the plant
TdemandMax
hrsTingeneratedunits
DemandMax
LoadAvgFactorLoad
stationpowerondemand
demandsindividualofSumFactorDiversity
max
max
8760
)(
'max
CapacityPlant
outputkWhAnnualFactorCapacityAnnual
hrsTinCapacityPlant
hrsTingeneratedUnitsDemandTotal
producedbeenvecouldthatenergy
producedEnergyActualFactorCapacity
Important Terms and Factors – contd..
Reserve Capacity = Plant Capacity – Max Demand.◦ Difference between L.F and C.F is indicative of reserve
capacity◦ If max demand = plant capacity, then L.F = C.F no reserve
capacity Unit Generated/Annum
useofhoursCapacityPlant
kWhinOutputStationFactorUsePlant
8760..
/
.
FLDemandMax
yearainhoursloadAvgannumgenunit
FLDemandMaxLoadAvg
DemandMax
LoadAvgFactorLoad
Load Duration CurveDefinition: When load elements of load curve are arranged in
order of descending magnitudes, the resulting curve is Load duration curve◦ Input is the load curve
◦ Max load is at left and decreasing loads are at right in descending order
◦ Area under load curve = Area under load duration curve
Base Load and Peak LoadThe unvarying load
which occurs almost the whole day Base Load
The varying peak demands of load over and above the base load Peak Load
Reserve Installed reserve is the amount of existing generation that is higher than that needed to
reliably meet a forecasted peak load
Spinning reserve is the unused capacity that can be activated by the system operator and
which is provided by generators synchronized to the network
Hot Reserve the reserve capacity that is synchronized to the grid system and should be
capable of meeting the demand within 10 minutes of a dispatch instruction. It is useful during
emergency conditions and unexpected load swings.
Cold or Non-Spinning Reserve capacity of generators not running at present that can be
ramped to capacity and synchronized to the grid within 10 minutes of a dispatch instruction
and should be capable of maintaining that output for at least two hours. Non-Spinning
Reserve is useful during emergency conditions
Unit CommitmentFdFd