Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Position Statement
Stansted to Braintree Rapid Transit System
Progress Report on Preliminary Concept and Feasibility Study
January 2019
i
Document Control Sheet
Document prepared by:
Daniel Nayrouz Transport Planning Victoria House Chelmsford CM1 1JR
T 0207 939 6241 E [email protected] W www.essex.gov.uk/highways
Record of Issue
Issue Status Author Date Check Date Review Date
1 Draft DN 02/10/2018 TA 03/10/2018 MW 03/10/2018
2 Draft DN 05/10/2018 TA 05/10/2018 MW 05/10/2018
3 Draft DN 04/01/2019 BF 04/01/2019 MW 04/01/2019
4 Draft DN 10/01/2019 BF 10/01/2019 MW 10/01/2019
5 Draft DN 16/01/2019 BF 16/01/2019 MW 18/01/2019
6 Final DN 30/01/2019 BF 30/01/2019 MW 30/01/2019
Approved for Issue By Date
Martin Whittles 30/01/2019
Distribution
Name Organisation Number of Copies
David Sprunt ECC 1 by email
Alan Lindsay ECC 1 by email
Jenny Jones Jacobs 1 by email
Report Title Stansted to Braintree Rapid Transit Study: Preliminary Concept and Feasibility Study
Project Number B3553R7A
Status Draft
Revision 6
Control Date 29 January 2019
ii
Limitation statement
This report has been prepared by Jacobs for the exclusive use of Essex County Council and the North Essex
Authorities of Uttlesford District Council, Braintree District Council, Colchester Borough Council and Tendring
District Council. It is issued in accordance with the provisions of the contract between Jacobs and Essex County
Council. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this report by any third party.
The analysis and forecasts contained in this report make use of information and input assumptions made
available to Jacobs at a point in time. As conditions change the analysis and forecasts would be expected to
change. Hence the findings set out in this report should be understood as relevant to that point in time when the
information and assumptions were made.
© Copyright 2019 Jacobs U.K. Limited. The concepts and information contained in this document are the property of Jacobs. Use or copying of this document in
whole or in part without the written permission of Jacobs constitutes an infringement of copyright
iii
Contents
Executive Summary ...................................................................................................................................... 1
1. Introduction ....................................................................................................................................... 2
2. Understanding the local context ..................................................................................................... 4
2.1 Uttlesford Draft Local Plan 2018-2033 ............................................................................................... 4
2.2 Stansted Airport Sustainable Development Plan ............................................................................... 5
2.3 The potential role of rapid transit ........................................................................................................ 5
3. Identifying objectives of rapid transit ............................................................................................ 7
3.1 Introduction ......................................................................................................................................... 7
3.2 Other drivers and considerations ....................................................................................................... 9
4. Route options and supporting measures .................................................................................... 10
4.1 Introduction ....................................................................................................................................... 10
4.2 Potential demand .............................................................................................................................. 10
4.3 Route opportunities and service configuration ................................................................................. 12
5. Rapid transit choices ..................................................................................................................... 19
5.1 Modes and characteristics ................................................................................................................ 19
5.2 Feasibility .......................................................................................................................................... 21
5.3 Examples of Bus Rapid Transit ........................................................................................................ 24
6. Conclusion ...................................................................................................................................... 28
Bus rapid transit
Guided bus rapid transit (GBRT)
Light rail transit (LRT or tram)
Tram-train and rail
iv
Figures
Figure 4-1: Stansted Employees' Place of Residence (SESAM Zones) .............................................................. 11 Figure 4-2: Percentage of Uttlesford commutes under 10km ............................................................................... 12 Figure 4-3: Segment 1 to be delivered by 2033 ................................................................................................... 13 Figure 4-4: Segment 2 to be delivered by 2033 ................................................................................................... 16 Figure 4-5: Colchester and Braintree subsystems in 2033 .................................................................................. 18 Figure 5-1: Use of infrastructure and guidance by different modes ..................................................................... 21 Figure 5-2: Luton-Dunstable Guided Busway Terminus ...................................................................................... 24 Figure 5-3: Cambridgeshire Guided Busway........................................................................................................ 24 Figure 5-4: Runcorn Unguided Busway ................................................................................................................ 25 Figure 5-5: Nantes Busway .................................................................................................................................. 25 Figure 5-6: BRT line in Metz ................................................................................................................................. 26 Figure A-1: Image of Runcorn BRT scheme ........................................................................................................ 29 Figure A-2: Zuidtangent BRT – Amsterdam (Source: BRTdata) .......................................................................... 30 Figure A-3: Image of Fastrack route ..................................................................................................................... 31 Figure A-4: Kent (Thameside) Fastrack scheme .................................................................................................. 32 Figure A-5: East London Transit Scheme ............................................................................................................ 33 Figure A-6: Weekly passenger breakdown for Stagecoach East (source: Stagecoach East) ............................. 35 Figure A-7: Proposed MetroBus route .................................................................................................................. 36 Figure A-8: Image of Crawley Fastway system .................................................................................................... 37 Figure A-9: Image of Manchester Metrolink ......................................................................................................... 39 Figure A-10: Edinburgh tram ................................................................................................................................ 40 Figure A-11: Coventry VLR system ...................................................................................................................... 41
Tables
Table 4-1: Stansted Airport to Easton Park .......................................................................................................... 13 Table 4-2: Within Easton Park .............................................................................................................................. 14 Table 4-3: Easton Park to Great Dunmow ............................................................................................................ 15 Table 4-4: Great Dunmow to WBGC .................................................................................................................... 16 Table 4-5: Within WBGC ...................................................................................................................................... 17 Table 4-6: WBGC To Braintree ............................................................................................................................ 17 Table 5-1: Service type characteristics ................................................................................................................. 19 Table 5-2: Services offered by rapid transit mode ................................................................................................ 19 Table 5-3: Infrastructure characteristics ............................................................................................................... 20 Table 5-4: Guidance systems ............................................................................................................................... 20 Table 5-5: Benefits of guidance systems .............................................................................................................. 20 Table 5-6: Initial assessment of options against objectives ................................................................................. 22 Table 5-7: Early assessment of strategic options ................................................................................................. 23 Table 5-8: Examples from Australia ..................................................................................................................... 27
1
Executive Summary
Jacobs has been commissioned by Uttlesford District Council and Essex County Council in conjunction with
Landsec and Manchester Airports Group (MAG) to undertake a feasibility study for a rapid transit system
between Stansted Airport and Braintree, stopping at Great Dunmow and the proposed Easton Park and West of
Braintree Garden Community developments. This local system could be part of the proposed rapid transit
system providing improved connectivity between Colchester, Marks Tey, Braintree and the proposed North
Essex Garden Communities (NEGCs), detailed in the North Essex Rapid Transit Study, submitted by Jacobs in
December 2017; or could be a standalone system. Accordingly, the feasibility of a rapid transit system linking
Braintree to Stansted Airport has been considered as a discrete scheme with the potential to be linked to a
comprehensive North Essex rapid transit system at a date in the future, should both the Uttlesford and North
Essex systems prove successful.
The Braintree to Stansted rapid transit system (RTS) would serve many of the Airport’s employees in Uttlesford
and neighbouring Braintree. MAG is seeking to accommodate up to 43 million passengers per year. It will also
help to alleviate congestion and environmental problems associated with over-reliance on private vehicles in
Uttlesford, whilst contributing to increased liveability, health and well-being.
Previously, the North Essex Rapid Transit Study indicated that a case could be made to roll out a system
incrementally. It is therefore considered appropriate to bring the Uttlesford section up to a comparable level of
detail as the other sections. This will ensure that the rapid transit proposal is co-ordinated with all available
relevant plans and strategies.
The study objectives are:
1. to review Uttlesford development and growth to identify potential demand and possible rapid transit hub
and spokes;
2. to identify indicative route opportunities and service configuration;
3. to review mode choice to support our approach to predicting how many trips will be attracted to the
different rapid transit options;
4. to determine options for implementation.
This report presents preliminary findings from the study by identifying the corridors and the potential feasibility of
such a service. The report explains why a bus-based rapid transit system, incorporating elements of dedicated
new links, would be the most suitable, flexible and affordable solution to pursue. It identifies centres that such a
system could connect: Stansted, Easton Park, Great Dunmow, West of Braintree garden community and
Braintree. And the report identifies the scale of development and growth which is expected over Uttlesford’s
Local Plan period until 2033, which supports the policy foundation of UDC to pursue a rapid transit system.
A further report will explore, in more depth, the feasibility of a bus-based rapid transit system connecting
Stansted and Braintree. This will be able to draw on transport modelling and transport planning work that has
been carried on in parallel in North Essex. Nevertheless, it is hoped that this preliminary report helps to give
confidence that a rapid transit system for Uttlesford should be considered as part of the set of transport
measures available to support Local Plan objectives.
2
1. Introduction
This study has been commissioned to assess the potential benefits and feasibility of a rapid transit link between London Stansted Airport and Braintree via proposed new garden communities in Uttlesford and Braintree. There is a vision to deliver the rapid transit services on an incremental basis, tying in with the delivery of two new garden communities: Easton Park and West of Braintree, which are operating on different timescales. The segmented route options generated in this report will therefore guarantee the flexibility to be rolled out in conjunction with the completion of each development. This report will consider the options for different rapid transit solutions, and their contribution to integrated and sustainable transport between the airport and the two new garden communities. In particular, rapid transit could help to meet travel demand associated with development growth in the next Local Plan period to 2033 more sustainably. The proposed garden communities in Uttlesford and Braintree, when fully built out, will have a total population of over 55,000 residents. The transport capacity at each site, and any necessary transport mitigation measures, will be the subject of separate discussions and agreements between the developers and the planning and highway authorities in accordance with usual planning principles. Meanwhile, London Stansted Airport currently handles 28 million passengers per year and over half of its passengers and a third of staff arrive by public transport. It is a key public transport node within Uttlesford and West Essex. It is the single largest employment site in Essex, where 12,000 staff work. Approximately one third of workers come from the districts to the east of the airport, namely, Uttlesford. The Regulation 19 Uttlesford Local Plan provides for the growth of the Airport and a potential rapid transit link would support sustainable transport provision to and from the expanded Airport. The promotion of sustainable transport modes between the airport and nearby settlements will build upon existing sustainable transport measures to help reduce an overreliance on private vehicles in Uttlesford and Braintree, alleviating both the pressures on the road network and air quality degradation resulting from greenhouse gas emissions.
The study will build on the information and modelling carried out as part of the North Essex Rapid Transit Study,
focusing on the identification of rapid transit solutions between London Stansted Airport and the proposed
Easton Park and West of Braintree Garden Communities. Different modes of mass rapid transit will be assessed
for financial viability, scalability, flexibility, and adaptability to technological change.
This will involve assessing the need for and feasibility of a rapid transit link serving London Stansted Airport
development and growth plans to identify key centres of demand which will inform service configuration. It is not
proposed that the high level public transport assignment model and outline business case appraisal will be run
again for the options identified. This is because it is not considered cost-effective to recode the public transport
assignment model just for this section and in addition, it would be preferable to wait for the next version of the
transport model which is currently being substantially improved. Nevertheless, the study will include a task to
improve the modal split assumptions. That is, better estimating the proportion of trips that might be attracted to
the chosen form of rapid transit through a review of previous schemes and consideration of the number of local
trips for which the RTS provides a viable option.
Other feasibility studies prepared for the NEGC Rapid Transit Proposals between Stansted Airport and Easton
Park Garden Community will be considered throughout the Study.
The study will conclude by consideration of how a scheme can be taken forward and implemented. For
example, considering whether a standalone Stansted to Braintree line could be incrementally constructed in a
first and second implementation stage, and perhaps connecting to the wider North Essex system in subsequent
stages. This section will also provide an early stage indication of the financial viability of the concept and
challenges.
Accordingly, to meet the study objectives provided by the client the study will:
1. Review Uttlesford development and growth to identify potential demand and possible rapid transit hub and
spokes;
2. Identify route opportunities and service configuration;
3. Review mode choice to improve our approach to predicting how many trips will be attracted to the different
rapid transit options; and
4. Identify feasible and phased implementation approaches.
3
This report, however, only considers the first two of the above study objectives. The latter two study objectives
will be reported on in a later report, in order that it can informed by the latest transport modelling and transport
planning work being carried out for the North Essex authorities.
The key stakeholders in this study will be Essex County Council, Uttlesford District Council, Manchester Airport
Group (MAG) and LandSec. Other stakeholders that may need to be consulted in the course of the study
include Network Rail, Greater Anglia, Arriva and Braintree, Colchester and Tendring Councils.
4
2. Understanding the local context
This chapter presents a local vision for a rapid transit system connecting London Stansted Airport to Braintree
via Great Dunmow and the proposed Easton Park and West of Braintree garden communities. The local
planning and development context provides guidelines that enable us to select the most suitable options.
The rapid transit system aims to provide a practical alternative to travelling by private car. This desire to provide
an alternative is driven by congestion, environmental and health concerns as evidenced in the opportunities and
challenges identified in the Regulation 19 Uttlesford Local Plan 2018-2033.
2.1 Uttlesford Draft Local Plan 2018-2033
The Regulation 19 Uttlesford Local Plan’s Spatial Strategy announces plans to build three new garden
communities in the district: Easton Park, West of Braintree and North Uttlesford. The new communities require
high quality employment, services and facilities, whilst supporting “a high quality of life for all and creat[ing]
healthy, safe and vibrant places for living and working”.
At Easton Park, which will comprise 10,000 new dwellings, of which at least 1,925 will be delivered by 2033, the
Council is explicit in its aim to provide sustainable transport links to the Airport.
At the proposed West of Braintree Garden Community, a further 10,000 new dwellings will ultimately be
delivered, with the aim of delivering 3,470 by 2033. A range of local employment opportunities and services and
facilities including schools, health, retail and leisure will also be provided, and Uttlesford District Council will
work with Braintree District Council to masterplan and deliver the project.
The demand that will be generated by these new residential and employment zones will subject the road
network to increasing pressures in 2033, necessitating mitigation. The North Uttlesford Garden Community,
which will comprise 5,000 new homes in total, as well as employment opportunities, schools, health, retail and
leisure facilities, does not fall within our study area, though a future extension to incorporate it into the rapid
transit network proposed in this study should not be ruled out.
The Town and Country Planning Association’s (TCPA)’s Garden City Principles aim to enable shoulder
journeys, reduce the need to travel by car and make active and sustainable modes of travel the most attractive
forms of local transport. This feasibility study explores the prospect of providing a link between Stansted Airport
and Braintree, passing through the aforementioned garden communities, in two phases. Segment 1 in this study
refers to the section of the route between Stansted Airport and Great Dunmow, and Segment 2 refers to the
section of the route between Great Dunmow and Braintree town centre. It is anticipated that both segments
would be operational by 2033 but either segment could be brought into use prior to this date.
2.1.1 District Transport Study
Whilst high car ownership rates will continue to characterise Uttlesford due its rural setting, there are plans to
bolster public transport alternatives in neighbourhoods within the District with the best access to facilities, with
Great Dunmow identified as a key hub for better public transport connections. As such, any development that
generates “significant movement”, such as the proposed garden communities, will be located “where the need
to travel will be minimised and the use of sustainable transport modes can be maximised.” The travel plans
submitted alongside the applications to develop the garden communities will be required to detail strategies for
reducing reliance on cars in the masterplan process. Of specific relevance to the proposals in this report is
Policy TA4, which calls for rapid transit corridors to “support sustainable transportation connectivity between
Braintree, Great Dunmow, Stansted Airport and Bishop’s Stortford.”
Moreover, the District Transport Study notes the need to protect the Green belt and Countryside Protection
Zone (CPZ) from overdevelopment, as well as manage the environmental impact of Stansted Airport’s function
and activities. At the same time, the strategy to improve access to the Airport will be mindful of the need to
“enable further job growth”.
5
2.1.2 Air Quality Technical Planning Guidance – June 2018
The guidance in this report seeks to ensure consistency amongst applicants and developers regarding air
quality within Uttlesford, in accordance with the National Planning Practice Guidance and National Policy. One
of the key aims of the guidance is to “provide guidance on mitigation and offsetting of the impacts of a
development on air quality”. Specifically, a Travel Plan will be required for any development of more than 20
employees, encouraging staff and visitors to take up sustainable modes of transport wherever possible.
It follows that as more homes and employment areas are built in Uttlesford, where residents will continue to rely
heavily on the Airport for employment, maximising the sustainability of travel to work will be of paramount
importance to ensuring compliance with the guidance set out in this document.
2.2 Stansted Airport Sustainable Development Plan
Uttlesford District Council has resolved to grant planning permission, subject to a legal agreement, for the
expansion of Stansted Airport in coming years. Its owner, Manchester Airports Group (MAG), has aspirations for
the airport to handle 35 million per year by 2023 which is its maximum passenger limit under current planning
conditions. MAG has a longer-term aim to secure the lifting of the current planning cap and to this end Stansted
Airport held a consultation on a new Sustainable Development Plan in 2014.1 The recently conditionally
approved planning application sets out how Stansted’s single runway would develop to handle 43 million
passengers per year within pre-existing annual limits on the number of flights.
This growth would mean that the number of employees at the airport would significantly increase from the
current level of approximately 12,000-16,000. This does not include indirect employment at other locations near
the site. According to the 2015 London Stansted Airport Employee Travel Survey Analysis, employee travel to
the airport is predominantly by car (70.6%), with 15.1% of employees getting a coach or bus to work. Essex
County Council, Uttlesford District Council and MAG share the aim to increase the number of employees
travelling between Stansted Airport and the local area by sustainable modes of travel, with MAG stating its
commitment to ensuring “the right balance between growth and sustainability” in its Sustainable Development
Plan.
2.2.1 Bus and Coach Strategy – Sustainable Development Plan
The three key elements of this strategy, as outlined in the Surface Access chapter of MAG’s Stansted Airport
Sustainable Development Plan, are as follows:
a) To introduce new services where there is a business case;
b) To develop existing services; and
c) To increase patronage on all services to make the best use of available capacity and increase modal
share of buses.
Meanwhile, the Sustainable Development Plan’s policy on climate change acknowledges that the presence of
the airport can “have a significant influence over other activities which contribute to climate change”. One of
these contributing factors is travel to and from the airport by staff, and as such, promotion of public transport
use is a focal point of its strategy to reduce the direct and indirect causes of carbon emissions.
This feasibility study will address the business case for providing new bus services between the airport and the
proposed garden communities in Uttlesford and Braintree. There will also be discussion on the optimisation of
existing bus services to maximise patronage and minimise negative environmental impacts.
2.3 The potential role of rapid transit
This report will consider a range of rapid transit options to connect Stansted Airport with Braintree via Great
Dunmow and the proposed garden communities at Easton Park and West of Braintree. The characters of these
modes are compared and contrasted in further detail in Chapter 5. The modes under consideration are:
1 Airports Commission Final Report, July 2015, p.332
6
• Bus rapid transit (BRT);
• Guided bus rapid transit (GBRT);
• Tram (LRT); and
• Rail.
Local bus services would remain complementary to any new rapid direct route between major centres.
7
3. Identifying objectives of rapid transit
3.1 Introduction
The aspirations of Uttlesford District Council and Essex County Council Local Transport Objectives have been
assimilated to identify the objectives for the rapid transit service between Stansted Airport and Braintree town
centre.
The following objectives have been drawn up:
• To enable housing and employment growth in the District; and
• To offer high quality public transport as an attractive modal choice to new residents moving into the
Garden Communities (GC), in accordance with the TCPA’s Garden City Principles.
Two secondary objectives have also been drawn up:
• To offer high quality public transport as an attractive modal choice to new residents moving into other
new developments along and adjacent to the RTS corridors; and
• To enhance the availability of high quality public transport as an attractive modal choice for residents of
existing communities along and adjacent to the RTS corridors.
The sub-sections below summarise aspirations for the rapid transit system, which have been informed by
discussions with Uttlesford District Council.
3.1.1 Mode share aspirations for the Easton Park and West of Braintree Garden Communities
The Uttlesford Regulation 19 Local Plan sets a target of 60% of trips to be made by active and/or public
transport modes at the Easton Park and West of Braintree Garden Communities. Whilst a distinction is not
made between active and public transport modes, Uttlesford aims to achieve the highest possible mode shift
from private vehicle to public transport use, including the potential rapid transit amongst commuters to Stansted
Airport and onwards connections via rail for those using the Airport as a local transport interchange.
Research suggests that road and rail based rapid transit solutions have a similar capacity to generate
patronage when developed with the aim of triggering modal shift from private vehicles2. With behavioural
research indicating no preference for either one of BRT (bus rapid transit) or rail modes, the lower costs of BRT
can offer a more cost-effective solution. One example of improved bus travel in the form of BRT increasing
ridership is in Houston, Texas, where 30% of BRT users were new users, and 72% had switched from private
vehicle use3.
3.1.2 Aspirations for presence and visibility
Currently, for local journeys in Uttlesford, public transport accounts for 7.7% of journeys to work (based on data
from the 2011 Census). Maximising the share of journeys on a rapid transit system could therefore enable a
significant change in travel behaviour.
It is considered that the rapid transit system must be perceived as fundamentally different to a regular bus
service. While parts of the UK such as London and Brighton have achieved significant increases in bus share
over the last twenty years, the context of these examples is different to Uttlesford.
The new garden communities will be required to achieve substantial modal shift, necessitating incentives for
behavioural change amongst incoming residents. Unlike increased highway capacity, provision of sustainable
travel facilities is not guaranteed to increase their uptake. Therefore, for behavioural change to occur, rapid
transit needs to have a high level of presence and visibility. The BRT will sit alongside the requirement to
2 Satiennam, T. et al (2016) Potential for modal shift by passenger car and motorcycle users towards Bus Rapid Transit (BRT) in an Asian
developing city, International Association of Traffic and Safety Sciences, 39, 121-129. 3 Levison, H. et al (2003) Volume 1: Case Studies in Bus Rapid Transit, Transportation Cooperative Research Program, 1, 1-54.
8
reduce the need to travel, including by enabling self-contained communities, and making sustainable and active
travel the first choice wherever possible. As a BRT route connecting local centres in Uttlesford, stops will need
to be located to maximise accessibility and visibility within each of the garden communities and existing
settlements.
Design features of stations are key to accentuating the visibility of rapid transit schemes. For instance, the
Miami-Dade Busway and Los Angeles Metro Rapid lines benefit from state-of-the-art, eye-catching bus
canopies. Similarly, in Curitiba, Brazil, the glass tube-shaped bus stops have become symbolic of the city, and
inspired similar BRT systems across Latin America. This is now being repeated in schemes in the UK; of note is
the proposed Sprint BRT system in Birmingham.
3.1.3 Aspirations for quality
In using rapid transit to alter the perception of public transport, the quality of the offer is going to be an important
factor. This will be driven by a number of subjective factors such as look and feel, journey experience and ease
of use.
These can be influenced by consideration of:
• Supporting work and relaxation (tables, power sockets and refreshments for longer journeys);
• Journey information;
• Ease of payment and ticket systems; and
• Reliability in terms of journey times (using segregated routes where possible to avoid congestion)
Hence in selecting rapid transit options, it is considered appropriate to draw on examples that have
demonstrated that they can meet such criteria. In terms of appraising options consideration needs to be given to
the cost of ensuring such quality of service is deliverable.
One example of a high-quality service translating to high ridership on rapid transit is the BRT system in Curitiba,
Brazil, where the aforementioned tube-shaped bus stops serve as trunk and feeder lines at terminals, allowing
for fast, free transfers, and off-vehicle fare collection allows for quicker boarding of buses.
Furthermore, rapid transit, whether road or light rail based, offers the option of being partially or fully segregated
from road traffic, which ensures reliability of service in terms of journey times. The Croydon Tramlink, with a
fleet of 35 trams serving 39 stops along mostly segregated routes in the London Borough of Croydon and
surrounding areas, has operated a minimum of 98% of its scheduled services over the past 12 months, and has
had a minimum customer satisfaction of 90% over the same time period.
3.1.4 Aspirations for level of service
Assuming the rapid transit system connects the key community and economic centres and is perceived as high
quality, it still needs to meet a level of service in terms of frequency, journey time and capacity in order to be
considered as a practicable alternative to the private car.
While these factors will evolve as a system is designed, the aims for the system are:
• To have at least four services per hour at non-peak hours;
• Equivalent generalised cost between rapid transit and car;
• Sufficient capacity to accommodate forecast public transport demand; and
• Flexibility to expand and meet additional demand
Another aspect of level of service is network resilience so the rapid transit system can operate even though
there might be a disruption somewhere on the system.
9
These aspirations are explored further in the subsequent chapters by drawing on findings from rapid transit
systems elsewhere in order to consider options for Uttlesford.
3.2 Other drivers and considerations
Several other factors are likely to influence the choice of rapid transit system. In broad terms these address
wider sustainability issues; affordability and value for money; and opportunities arising from smart technologies.
3.2.1 Affordability and value for money
While bids can be made for capital costs if it is backed by a sufficiently robust business case, it would be
expected that a system would have sufficient demand to cover its operating and maintenance costs over the
long-term. There may be a requirement for some initial funding and support to begin service operation.
However, given concerns over inequalities, fare levels should be set at an accessible level. In terms of this
study, this can be reflected by using standard fare level assumptions with the economic appraisal. Therefore,
the more expensive systems, such as trams, will only be financially attractive if they can attract sufficient
demand to offset increased costs or receive a capital subsidy.
3.2.2 Innovation and smart technology
The draft Garden Community Development Planning Documents recognise the role that digital technology can
contribute to liveability. While smart living does not have to include a technological solution, it is recognised that
digital technologies often play a supporting role. In addition, Essex County Council is exploring ways such
innovations can support outcomes across the county.
In the context of the rapid transit system smart technology could be used to improve the user experience such
as through seamless ticketing and information systems; and contribute to efficiency and resilience through
energy optimisation and route optimisation. In time, driverless vehicles could be introduced which could further
drive down costs.
Within the transport sector, there has been a trend away from car ownership and towards on-demand transport
services such as Uber and cycle hire. There are also moves towards introducing non-petrol and autonomous
vehicles. However, at present, these innovations do not radically alter the pattern of demand or the need for
mass transit solutions.
10
4. Route options and supporting measures
4.1 Introduction
This section describes how indicative routes have been identified; how they could be phased; sections that are
segregated or mixed with car traffic; and an awareness of challenges and how they could be overcome.
Consideration is given to how the route interacts and services garden communities, based on the latest plans. It
should though be stressed that the route presented will merely serve as a basis for an initial view of the
practicability of the RTS concept. The shown routes must not be considered as a preferred option. It would be
expected there would be further refining of route choices and optioneering in subsequent planning phases,
which would also consider specific construction, traffic and environmental issues and, importantly, engage with
the local communities to seek their advice.
4.2 Potential demand
Several sources have been consulted to identify demand-generating areas along the route between Stansted
Airport and Braintree town centre, which has influenced our route choice:
• Bespoke trip growth analysis (September 2018);
• 2015 London Stansted Airport Employee Travel Survey Analysis;
• Regulation 19 Uttlesford Local Plan 2018-2033; and
• 2011 Census.
The trip growth analysis is described in Section 6 as it is integral to the assessment of financial feasibility.
4.2.1 2015 London Stansted Airport Employee Travel Survey Analysis
According to this survey of employees’ travel habits, 33.3% of the Airport’s 12,000 employees live in Uttlesford
and neighbouring Braintree, the two local authorities within which our study area lies. Figure 4-1 below further
breaks down the number of respondents who said they live in each SESAM Zone – that is zones as defined in
the surface access model for employment at Stansted.
11
Figure 4-1: Stansted Employees' Place of Residence (SESAM Zones)
The figure shows that there are large clusters of Stansted employees in Great Dunmow and Braintree. This can
be expected to rise upon delivery of the new garden communities in between the Airport and Braintree, as the
Airport’s annual passenger handling capacity and employment growth is forecast to grow until 2028. The
delivery of the garden communities, starting in 2033, will increase the likelihood of existing employees re-
locating to them, particularly if an enhanced and attractive transport option to the Airport is on offer.
4.2.2 Regulation 19 Uttlesford Local Plan 2018-2033
The Regulation 19 Uttlesford Local Plan’s Spatial Strategy sets out proposals to build three new garden
communities in the district: West of Braintree, Easton Park and North Uttlesford. The new communities require
high quality employment, services and facilities, whilst supporting “a high quality of life for all and creat[ing]
healthy, safe and vibrant places for living and working”.
The Easton Park development will comprise 10,000 new dwellings, of which at least 1,925 will be delivered by
2033. Such a substantial increase in the housing stock of the local area will subject the existing road network to
higher levels of traffic as people move between the new settlements and key areas of employment, including
Stansted Airport.
12
4.2.3 Census 2011 Travel to work data
Figure 4-2: Percentage of Uttlesford commutes under 10km
Figure 4-2 shows that the electoral wards in Uttlesford lying within our study area have some of the highest
proportions of commutes under 10km in the district. These include Great Dunmow North (39.7%), Great
Dunmow South (42.0%), Stansted South (43.4%) and Takeley and the Canfields (44.2%). Such distances are
better suited to rapid transit solutions such as light rail or bus.
4.3 Route opportunities and service configuration
At this stage of the study, only route corridors have been identified, since the development of options for route
alignments should be informed by a more detailed optioneering exercise. In addition, whilst this study focuses
on the planning of a rapid transit system between Stansted Airport and Braintree town centre, the emerging
proposal should note long terms options to potentially link to the proposed North Essex RTS. Initial ideas for
long term phasing are as follows:
• By 2026 – establish a core Colchester RTS linking the proposed Tendring Colchester Borders Garden
Community to the University, town centre and the rail station; and serving existing and new park and
ride facilities in Colchester.
• By 2033 – extending the Colchester RTS to the proposed Colchester Braintree Borders Garden
Community and Marks Tey,
• By 2033 – opening a separate section of the RTS linking Stansted Airport, Easton Park
development, the West of Braintree Garden Community and Braintree.
• By 2041 – joining the Colchester and Braintree sections of the RTS by creating a new section which will
be co-ordinated with any re-routing of the A12 and A120 trunk roads.
In the following subsections the logic of the Stansted to Braintree RTS section is described in more detail: how it
can be delivered in 2033; and how it could be adapted should, for example, the West of Braintree Garden
Community be delayed.
0%
10%
20%
30%
40%
50%
60%
13
4.3.1 Segment 1: London Stansted Airport to Great Dunmow
The rapid transit link between Stansted Airport and Braintree town centre has been segmented to offer flexibility
to be rolled out in conjunction with completion of developments at Easton Park and West of Braintree Garden
Communities on different timescales. This report refers to the section of the link between the Airport and Great
Dunmow as Segment 1, and the section between Great Dunmow and Braintree town centre as Segment 2. It is
anticipated that both segments would be operational by 2033 but either segment could be brought into use prior
to this date.
Figure 4-3: Segment 1 to be delivered by 2033
Table 4-1 to Table 4-6 present the characteristics of the different route sections.
Table 4-1: Stansted Airport to Easton Park
RT Route section Stansted Airport to Easton Park
Route
• The proposed Rapid Transit route would start at the existing Airport Bus Station The bus station is currently only accessed from the terminal roads via connections onto the A120 and B1256 at Takeley. A range of access options have been evaluated to/from Stansted Airport. During the detailed planning of the route these will be further evaluated and may include a new access or improving access from Coopers End Roundabout.
• Between the airport boundary and the north western boundary of Easton Park, the proposed route would run on a combination of dedicated two-lane bus road and existing carriageway.
14
Assumptions
• It is assumed that provision can be made within the existing Airport Bus Station for boarding, alighting and layover.
• It is assumed that rapid transit vehicles would be garaged and maintained off route.
New infrastructure
• The map shows an indicative line of the route that will comprise a two lane bus road between the airport boundary and Easton Park, with some new sections and some sections utilizing existing carriageway. This connection would also accommodate access for cyclists and pedestrians. (A similar facility has been provided at Gatwick Airport to enable local buses to access Perimeter Road North and serve North Terminal.)
• Between the airport boundary and the north western boundary of Easton Park, the proposed route would run on a combination of dedicated two-lane bus road and existing carriageway with provision for cyclists and pedestrians. The map shows an indicative alignment – the precise route will be as part of masterplanning for Easton Park, and in liaison with the Airport authorities.
Stops • The only stops on this section would be at the airport bus station and
at the Easton Park local centre/micro-hub.
Other considerations • It may be necessary to review capacity and operation of the bus
station in the longer term.
Table 4-2: Within Easton Park
RT Route section Within Easton Park
Route • Link serving proposed Town Centre and two Village Centres. The
majority of the route would be on a dedicated alignment.
Assumptions
• It is assumed that the development of Easton Park would include a primarily dedicated east-west alignment for Rapid Transit; and that the majority of this would be independent of the road network and provide easy access to the three Centres.
New infrastructure
• The majority of the route would be on dedicated alignment.
• Masterplans for Easton Park do not yet include a route, and it is important that this is determined at an early stage in conjunction with development of the road network and place-making.
Stops
• Masterplanning for Easton Park would be expected to include a Town Centre and two Village Centres, and it is proposed that the Rapid Transit would have stops at each of these.
Other considerations
• Phased introduction of route as development proceeds. Sections of the route may potentially be used by local feeder services as development proceeds.
15
Table 4-3: Easton Park to Great Dunmow
RT Route section Easton Park to Great Dunmow
Route
• New link from Easton Park to the B184, or initially to the B1256 via the site access.
• Access to and through Great Dunmow is initially proposed via the existing road network along Stortford Road to the High Street and continuing either via Braintree Road or Chelmsford Road.
Assumptions
• The indicative plans for Easton Park include a link between the eastern boundary and the B184, and it is assumed that the rapid transit route would follow this link. An alternative in the interim is a route onto the B1256 via the main site entrance.
New infrastructure
• New a two-lane bus road between Easton Park and the B184, with associated provision for pedestrians and cyclists.
• Bus priority measures on Great Dunmow High Street, or in the interim a route onto the B1256 via the main site entrance.
Stops • Tesco and the adjacent School.
• Great Dunmow, High Street.
Other considerations
• It may be possible to develop a parallel Stansted – Easton Park – WBGC – Braintree service bypassing Great Dunmow centre via the B1256 but serving the GDS transport interchange.
16
4.3.2 Segment 2: Great Dunmow to Braintree town centre
Figure 4-4: Segment 2 to be delivered by 2033
Table 4-4: Great Dunmow to WBGC
RT Route section Great Dunmow to WBGC
Route • It is assumed that the Rapid Transit service would initially operate
either via the B1256 or the A120.
Assumptions • Provision of the proposed west facing access to the B1256 west of
Rayne to facilitate operation via the A120.
New infrastructure
• Provision of west facing access at A120/B1256 for Rapid Transit and HGVs.
• Bus priority measures to reduce traffic on the B1256 to Rapid Transit and local traffic only.
Stops • No intermediate stops are proposed between Great Dunmow and
WBGC.
Other considerations
• It will be necessary to review traffic levels on the A120 and B1256 corridor and consider bus priority measures and/or the provision of dedicated Rapid Transit infrastructure in the long term.
17
Table 4-5: Within WBGC
RT Route section Within WBGC
Route • Dedicated alignment west of Rayne through new development,
rejoining route into Braintree.
Assumptions
• It is assumed that the development of WBCG would include a dedicated alignment for rapid transit; and that this would be independent of the road network and provide easy access to the planned centres of the garden community.
New infrastructure
• New dedicated alignment.
• The indicative plans for WBGC do not yet include a route, and it is important that this is determined at an early stage in conjunction with development of the road network and green corridors.
Stops • Locations to be determined as plans are developed.
Other considerations
• Sections of the route may potentially be used by local feeder services as development proceeds. Future change and development will depend on interim routing assumptions and delivery of more infrastructure as the site is built out.
Table 4-6: WBGC To Braintree
RT Route section WBCG to Braintree
Route • Access to Braintree is initially proposed via the existing road network
along Rayne Road continuing to the bus and rail stations.
Assumptions
• The Rapid Transit alignment in WBGC would include a link to Braintree town centre in addition to the link at the A120/B1417 interchange.
New infrastructure • Possible bus priority and traffic calming measure in Braintree.
Stops
• Braintree bus station.
• Braintree rail station.
• Extension to Braintree Freeport possible.
Other considerations
• Creation of a dedicated Rapid Transit route into the centre of Braintree that provides access for pedestrians and cyclists.
• Further extension of Rapid Transit towards Colchester.
4.3.3 Phased introduction of service changes
The Stansted Airport – Great Dunmow -Braintree corridor is currently served by several local and express bus
routes. The introduction of RTS services to serve new development also enables changes and enhancements
to existing services, including the potential to divert routes to serve other new developments already under
construction. Should BRT infrastructure be created, it would be expected that the infrastructure can also be
18
used by existing bus services and existing operators would be involved in running BRT services. As a
consequence, a thorough review of BRT with existing services would be expected.
4.3.4 2033 to 2041 – Joining the Colchester and Braintree subsystems
By 2033 it is hoped that two successful subsystems will have been created as shown in the diagram below.
Figure 4-5: Colchester and Braintree subsystems in 2033
Alongside the Stansted to Braintree RTS, by 2033 there is potential for a new rapid transit route linking
Colchester Town Centre and Hythe, as well as a route linking the University of Essex Colchester Campus to the
proposed Colchester Tendring Borders Garden Community. The two subsystems can then be connected along
a corridor secured as part of the major A120 and A12 rerouting and upgrading.
19
5. Rapid transit choices
5.1 Modes and characteristics
5.1.1 Modes considered
This section compares five possible modes which could potentially be used to operate rapid transit services.
The characteristics of these modes are compared in the subsequent subsections. The modes under
consideration are:
• Bus rapid transit (BRT)
• Guided bus rapid transit (GBRT)
• Tram (LRT)
• Rail
5.1.2 Service type
There are four main service types, with characteristics as shown in Table 5-1.
Table 5-1: Service type characteristics
Service type Characteristics
Local transit Typical distance between stops in urban areas of ~400m
Urban mass transit Typical distance between stops in urban areas of ~1km
Semi-Express Mix of express links between urban centres with additional stops (~1km spacing) within the urban centres
Express Single stop in urban centre, express links in between
The range of rapid transit options under consideration cover all service types, however, no one rapid transit
option covers all the service types listed in Table 5-1. A rapid transit system connecting Stansted Airport, Great
Dunmow, Braintree and the proposed garden communities at Easton Park and West of Braintree fills a gap
between local bus-based transit and express services provided by rail and coaches. Table 5-2 details the
service types offered by each rapid transit mode.
Table 5-2: Services offered by rapid transit mode
Rapid Transit Mode
Local transit
Urban mass transit
Semi -express Express
BRT ✓ ✓ ✓
GBRT ✓ ✓
Tram/LRT ✓ ✓
Rail ✓
5.1.3 Infrastructure and guidance
There are three main categories of infrastructure used by rapid transit modes as summarised in Table 5-3.
20
Table 5-3: Infrastructure characteristics
Segregation Infrastructure type Characteristics
Unsegregated Shared Infrastructure open for use by several modes with no specific priority for any particular mode
Segregated
Reserved Separate identification or demarcation of infrastructure space for specific modes or categories of user
Dedicated Specially provided infrastructure for exclusive use of specified mode
In the case of rapid transit modes, the choice of infrastructure type is often determined by whether the transit
system is retrofitted into an existing transport system or is part of a new construction where space can be set
aside. Within these types of infrastructure there are two main types of guidance system shown in Table 5-4.
Table 5-4: Guidance systems
Guidance system Characteristics
Non-guided Vehicles are steered by driver who determines path followed
Guided Specially designed infrastructure which enables suitably equipped vehicles to follow a precisely defined path
Depending on the type of guideway used, it is possible to configure vehicles which can follow a guideway where
available, but they can also be steered by the driver on sections where there is no guideway provided, for
example guided buses. Guidance offers four significant benefits to public transport modes as described in Table
5-5.
Table 5-5: Benefits of guidance systems
Benefit of guidance Benefits
Capability
Guided vehicles can operate within a smaller spatial envelope such as tunnels and narrow trackways. They can also operate through restricted clearances at higher speeds than unguided vehicles.
Capacity Guided vehicles can be longer than unguided vehicles, enabling higher capacity per vehicle.
Exclusivity Depending on their design, the presence of guideways can deter use by other vehicle types.
Presence Guideways are present and visible to potential transport users at all times, and offer reassurance that services are available.
However, certain types of guideway, for example those requiring safety fencing or protruding above the road
surface, can increase severance, especially if designated crossing points are required for pedestrians and other
soft modes. The relationship between the modes under consideration in this study and infrastructure and
guidance systems is shown in Figure 5-1.
Fully guided modes (tram, tram-train and rail) require the necessary guidance to be in place for the full length of
all routes in the network, including access to stabling and maintenance facilities. This also constrains flexibility
to extend or alter routes as services can only commence when all the necessary infrastructure is in place.
21
A significant advantage of guided buses is that they can also operate on sections of route without guideways,
offering greater flexibility to extend or alter routes served. However, it should be recognised that tram tracks can
be flush with road surfaces, so it is possible to run trams on shared infrastructure. The physical presence of
tram lines also means that trams are more easily operated than buses in semi-pedestrianised settings.
Figure 5-1: Use of infrastructure and guidance by different modes
Examples of the above systems are provided in Appendix A, which build on the characteristics identified above.
5.2 Feasibility
Table 5-6 shows how the four mode options identified in Table 5-1 above align with the objectives identified in
Chapter 3. Each option has been given a score for each one the objectives. The scoring is based on a Red (1),
Amber (2), Green (3) system, where Green has the highest value and has most positive impact and conversely
Red has the most negative impact and has the lowest value assigned to it. Each option is scored by the
cumulative score that each option has, made up of scores against the study’s objectives.
The worst scoring option is the first option which fails to meet the objectives of the study. However, it should not
be ruled out since together with other options could contribute to enable housing and improve the transport
system. Similarly, the second option partially meets the objectives of the study. On the other hand, the following
four options are the best scoring options since they fully meet the study’s objectives.
22
Table 5-6: Initial assessment of options against objectives
Objectives BRT GBRT LRT Rail
To enable housing growth ✓ ✓ ✓ ✓
To offer high quality public
transport as an attractive modal
choice to new residents moving
into the Garden Community (GC)
✓ ✓ ✓ ✓
To offer high quality public
transport as an attractive modal
choice to new residents moving
into other new developments
along and adjacent to the North
East Rapid Transit (NERT)
corridors
✓ ✓ ✓ ✓
To enhance the availability of high
quality public transport as an
attractive modal choice for
residents of existing communities
along and adjacent to the NERT
corridors
✓ ✓ ✓ ✓
5.2.1 Additional sifting
All options considered above pass the initial assessment in that they meet the key objectives of the study. An
additional sift should therefore be undertaken to identify any ‘showstoppers’ which are likely to prevent an option
progressing at a subsequent stage in the process.
The Early Assessment and Shifting Tool (EAST) is a decision support tool that has been developed to
summarise and present evidence on options in a clear and consistent format.
EAST has been designed to be consistent with Transport Business Case principles in that the issues
respondents are asked to consider when assessing the economic impact of schemes are the same as those
that must be addressed in more detail in a full Transport Business Case. It is not intended to duplicate or
replace it.
The EAST tool has been used to aid in assessing systematically our options and demonstrate the process by
which a shortlist has been selected for further investigation. The process involves discarding options that
• Would clearly fail to meet the key objectives identified in Chapter 3;
• Do not fit with existing local, regional and national programmes and strategies, and do not fit with wider
government priorities;
• Would be unlikely to pass key viability and acceptability criteria (or represent significant risk) in that they are
unlikely to be:
o deliverable in a particular economic, environmental, geographical or social context;
o technically sound;
o financially viable;
o acceptable to stakeholders and the public.
23
Table 5-7 summarizes the results from the EAST tool. The Red/Amber/Green (RAG) scores for each one of the
cases, namely strategic, economic, managerial, financial, and commercial, provide a visual guide as to the
option’s impact.
Table 5-7: Early assessment of strategic options
Mode choice Strategic Economic Managerial Financial Commercial
BRT
GBRT
LRT
Rail
All four options fully meet the objectives of the study, since they would enable housing growth and improve the
public transport network. In terms of financial affordability, LRT and Rail options score lower than GBRT and
BRT options, with BRT being the most financially affordable option. A GBRT system is considered as a midway
offer between conventional bus and rail systems in terms of achieving a similar speed, capacity and design. The
differing factors between a BRT system and GBRT system are guidance, land uptake and speed. A GBRT
system typically runs on dedicated infrastructure (guideways) and hence tends to be more reliable and faster
than conventional buses, but also more expensive and less flexible. BRT systems may run on reserved or
dedicated infrastructure, and in some cases some sections may run on shared infrastructure. One of the key
drivers for choosing such a scheme is the flexibility that the system can provide. Since large levels of growth are
forecasted across a relatively large area and long period in Uttlesford, it is expected that a BRT system would
be attractive because of the flexibility it offers and that it can be delivered on an incremental basis.
The best scoring option is Option 1 (BRT) followed by Option 2 (GBRT). However, Option 2 is less financially
viable and provides less flexibility than Option 1, and in respect of the need to adapt to developments of
differing timescales, it has been ruled out. Similarly, Options 3 (LRT) and 4 (Rail), despite meeting the
objectives of the study to enable housing growth and improve the public transport network, have also been ruled
out due to their financial unviability.
However, it should be recognised that a completely segregated BRT system would be very close to a GBRT
system, but with more flexibility since normal buses would be able to use the infrastructure and costs and
retrofitting costs of vehicles would be avoided.
24
5.3 Examples of Bus Rapid Transit
5.3.1 Luton-Dunstable Guided Busway
Figure 5-2: Luton-Dunstable Guided Busway Terminus
Bus services along the Luton/Dunstable corridor were viewed as infrequent and unreliable. To tackle the
problem, Luton Borough Council has transformed the disused Luton-Dunstable railway into a fast-track Busway
- more than halving cross-conurbation journey times and leading to high passenger satisfaction on frequency
and journey times. The scheme has led to a 9% modal shift towards BRT in Dunstable.
5.3.2 Cambridgeshire Guided Busway
Figure 5-3: Cambridgeshire Guided Busway
The scheme links Cambridge with St Ives, Huntingdon and Northstowe (a proposed new town) to the north-
west, and with the M11 motorway to the south. The route includes two sections of guided operation, a bus-only
road and other places with on-street operation in conventional bus lanes. New park and ride sites have been
built at Longstanton and at St Ives, with a tarmac cycle track/bridleway alongside some sections of the route.
The final scheme includes bus priority and real-time passenger information system displays at busway bus
stops; and subsequent separate funding and works to better link those stops to local businesses for pedestrians
and cyclists. Since the busway became operational, a quarter of its ridership has shifted from private vehicle
use.
25
5.3.3 Kent Fastrack Busway
Kent Fastrack is an unguided bus service providing transport across Kent Thameside. Services run up to every
10 minutes offering a local transit service for local journeys from new and existing developments around
Dartford, Bluewater, Ebbsfleet and Gravesend. It also provides links to Ebbsfleet International station and
Bluewater shopping centre. This scheme has attracted 19% of its users from driving, whereas another 60% of
its users previously used regular bus services.
5.3.4 Runcorn Unguided Busway
Figure 5-4: Runcorn Unguided Busway
The Runcorn scheme opened in 1971 and operates on a segregated busway which is dedicated for buses only
on an unguided system. This scheme has initiated a 16% shift from public transport to BRT and a 75% shift
from car to BRT.
5.3.5 Nantes Busway
Figure 5-5: Nantes Busway
The Nantes Busway (line 4) is a bus rapid transit line operating in the city of Nantes, France. The service was
inaugurated in 2006 and is operated by Semitan. The line runs from Place Foch to Porte de Vertou on a
dedicated right-of-way, and interconnects with line 1 of the Nantes Tramway at Duchesse Anne Château
station. Four park & ride facilities have been built along the construction of the line to encourage passengers to
use public transport. Nantes Busway line 4 is NF certified (NF stands for French Norm). A victim of its own
success, Busway line 4 attracts higher ridership than Semitan expected, pushing the system to saturation.
Buses are overcrowded at peak times and nearly full off-peak. Semitan tested the Hess LightTram in November
26
2009 to eventually increase capacity of the system and relieve overcrowding at peak times. Though that
solution was not implemented, Semitan decided to increase passage frequencies to less than 3 minutes at peak
times.
5.3.6 Bus Rapid Transit lines in Metz
Line A runs from Woippy to Borny and Line B from Saulcy Island, through the science and technology park, to
the new Mercy hospital. The two lines share a section comprising ten stops between the Sérot and Provence
boulevards, crossing the city centre and stopping at the railway station and new Pompidou-Metz centre.
Figure 5-6: BRT line in Metz
27
Table 5-8: Examples from Australia
System Mode Shift
Adelaide North East Busway4
Ridership Growth = 24%
% Passengers that previously drove = 40%
Sydney Liverpool Parramatta Transitway
Ridership Growth = 56% 47% of growth new
journeys
% Passengers that previously drove = 26%
Brisbane SE Busway Brisbane
Ridership Growth = 56% 17% new journeys
% Passengers who previously drove = 26%
SmartBus Route 901 Melbourne
Ridership growth = 42%
% Passengers who previously drove = 34%
SmartBus Route 902 Melbourne
Ridership Growth = 47%
% Passengers who previously drove 29%
SmartBus Route 903 Melbourne
Ridership Growth = 26%
%Passengers who previously drove 21%
4 Mode split: 10% Public Transport, 84% Private Transport, 6% Non-motorised User
28
6. Conclusion
This preliminary report and position statement has considered the development of a concept for a RTS linking Stansted Airport, Great Dunmow and Braintree via new garden communities at Easton Park and West of Braintree. While a range of modes – bus, guided bus, tram and trains – have been considered, the study has recommended that a bus based RTS, that is BRT, is the most feasible option. If BRT to be the chosen option, then the routes it would use could be incrementally developed. Initially, only limited sections of the route would be segregated, but as demand grows the level of segregation would increase. It should also be realised that a route optioneering exercise should be undertaken which will inform public consultation on the selection of any route. Therefore, the assumptions on routes given in this report should be treated as indicative. The next stage of the study will consider the feasibility of such a bus based rapid transit system by drawing on the parallel transport modelling and planning work being carried out for the North Essex authorities.
29
Bus rapid transit
Bus rapid transit systems typically run on reserved or dedicated infrastructure, and in some cases some
sections may run on shared infrastructure. Bus rapid transit is typically used for urban mass transit within
conurbations, and semi-express inter-urban and commuter services.
Example 1 – Runcorn Unguided Busway
The purpose of this scheme was to provide a high-quality and accessible bus system by offering a local transit
service which made buses competitive with private cars for local trips. The scheme has initiated a 16% shift
from public transport to BRT and a 75% shift from car to BRT (on surveyed routes).
Table A- 1: Runcorn Unguided Busway Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
The Runcorn scheme opened in 1971 and operates on a segregated busway which is dedicated for buses only
on an unguided system. This scheme was built in anticipation of surrounding development, and the Stansted to
Braintree scheme is likely to follow this notion and be built prior to or at the same time as residential
development.
Figure A-1: Image of Runcorn BRT scheme5
5 https://farm9.staticflickr.com/8539/8698427128_919fe9c302_b.jpg
30
Example 2 - Zuidtangent, Amsterdam
The Zuidtangent BRT system offers a direct route between Amsterdam Zuidoost, Schiphol Airport and Haarlem
Central Station. Buses operate on a frequent basis at every 6 minutes during the day with the end to end trip
taking approximately 60-70 minutes.
Table A- 2: Zuidtangent BRT Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
The scheme incorporates both dedicated (37km) and unsegregated sections of busway running on an unguided
system. Between Schiphol and Amsterdam Zuidoost, buses run mainly on public roads, including motorways,
with some unreserved sections. Some sections of the route are also used by local buses, with off-line stops to
enable express buses to overtake.
Since 2011, the service has been marketed as an integral part of the R-net (Randstad-net) system which
includes bus, BRT, tram and metro services. The system includes a dedicated tunnel under the runway to
access Schiphol airport, and has been designed for possible future upgrade to light rapid transit or tram
operation.
Figure A-2: Zuidtangent BRT – Amsterdam (Source: BRTdata)
31
Example 3 – Kent (Thameside) Fastrack
The purpose of the Kent (Thameside) Fastrack scheme is to provide a fast, reliable, efficient transport across
Kent Thameside. Services run up to every 10 minutes offering a local transit service for local journeys from new
and existing developments around Dartford, Bluewater, Ebbsfleet and Gravesend. It also provides links to
Ebbsfleet International station and Bluewater shopping centre.
Table A- 3: Kent (Thameside) Fastrack
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
The Fastrack scheme runs on a combination of shared and reserved infrastructure on an unguided system as
illustrated in Figure A-3.
Figure A-3: Image of Fastrack route6
Dedicated Fastrack services are operated by Arriva. However, from December 2017, the section of London
Buses route 96 between Dartford and Bluewater has been diverted to run on the Fastrack route. It previously
ran non-stop on the public road network, but now additionally serves Darent Valley Hospital with no increase in
overall journey time.
6 http://www.go-fastrack.co.uk/wp-content/uploads/2014/06/fastrack-route-map.pdf
32
Figure A-4: Kent (Thameside) Fastrack scheme7
Example 4 – East London Transit
East London Transit (ELT) is a network of services developed by Transport for London to meet the existing and
anticipated demand for public transport in East London caused by the Thames Gateway redevelopment.
Although originally conceived as a bus rapid transit system, it has limited segregation from other traffic and is
operated as part of the London Buses network. The original East London Transit opened in phases between
2010 and 2013, since when it has been further developed and extended.
Table A- 4: East London Transit Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
There are currently three routes, which combine on the core section between Barking town centre and the
Thames View Estate. Most of the routes run on unsegregated roads, with segregated sections in Barking Town
centre and short segregated sections within the existing Thames View Estate. Longer segregated sections are
being provided on extensions to serve new development into Barking Riverside, however there is no bus priority
or segregation at the signalised junction at Movers Way/River Road where the main access road from Barking
into Barking Riverside crosses the A13.
7 http://www.go-fastrack.co.uk/wp-content/uploads/2014/04/The-Bridge-1024x509.jpg?1512086410070
33
Figure A-5: East London Transit Scheme8
Much of the system has been developed by extending, upgrading and renumbering several pre-existing bus
routes which served the Thames View estate. Improvements include, higher frequency, longer hours of
operation, new rolling stock, and new links to the station at Dagenham Dock. When the system opened, the
buses carried a special livery. More recently, the introduction of new Routemasters resulted initially in operation
with unbranded buses, with displaced ELT branded buses transferred to other routes
Routes EL1 and EL2 operate through areas of Barking Riverside which have yet to be developed. In particular,
route EL1 has recently been extended to run every six minutes to serve a new school campus and is also
intended to attract demand as the surrounding area is built out.
Construction of an extension of the London Overground to Barking Riverside is expected to begin in early 2018,
with train services starting during 2021. It is anticipated that the local bus network will then be reconfigured to
serve the new station.
8 http://www.ukbusawards.org.uk/content/images/stories/2010-SLImages/INF-ELTransit.gif
34
Guided bus rapid transit (GBRT)
A GBRT system is considered as a midway offer between conventional bus and tram systems in terms of
achieving a similar speed, capacity and design. The differing factors between a BRT system and GBRT system
are guidance, land uptake and speed. A GBRT system typically runs on dedicated infrastructure (guideways)
and hence tends to be more reliable and faster than conventional buses.
Example 1 – Cambridgeshire Guided Busway
The Cambridgeshire GBRT system offers a semi-express service between Huntingdon, St Ives and Cambridge
(including the rail stations and Addenbrooks Hospital). It also serves 4 park and ride sites (St Ives, Longstanton,
Trumpington and Madingley Road). However, this unintentionally encourages drivers to travel to each of these
park and ride sites using the car. With this in mind, the potential mode shift away from the car is likely to be
limited.
This scheme predominantly operates on dedicated infrastructure, which allows speeds of up to 56mph to be
reached. However, sections of the busways are not dedicated, instead there are some reserved sections for
buses and taxis which are located in the historical city centre.
Table A- 5: Cambridgeshire Guided Busway Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
The system demonstrates how a disused railway line can be utilised as a guideway for buses. The scheme
which opened in 2011 has seen increasing patronage on a year by year basis as illustrated in Figure A-6 which
provides a weekly breakdown of passenger numbers for Stagecoach East.
35
Figure A-6: Weekly passenger breakdown for Stagecoach East (source: Stagecoach East)
The busway operates on a guided system for the majority of the route, which as identified earlier, offers
capability, capacity, exclusivity and presence.
Example 2 – Bristol MetroBus
Bristol MetroBus system is planned to offer a smarter way of travelling that will speed up journey times, relieve
congestion and reduce levels of congestion. The MetroBus has been promoted as offering a new express bus
service along the 50km network9, and is therefore likely to provide single stop services in the city centre, with
express links in between.
Table A- 6: Bristol MetroBus Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
Part of the scheme will run on a disused railway line, making use of segregated busways (dedicated) and bus
lanes (reserved).
9 https://travelwest.info/metrobus
36
Figure A-7: Proposed MetroBus route10
Example 3 – Crawley Fastway
Fastway is promoted as the first bus rapid transit system in the world to be built outside a major city by a
partnership of local authorities and private companies with automatic vehicle location, pre-trip and in-trip
passenger information and automatic traffic signal priority from the start.
Table A- 7: Crawley Fastway Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
10 https://s3-eu-west-1.amazonaws.com/travelwest/wp-content/uploads/2013/08/metrobus_leaflet-map-June2016.pdf
37
Guidance Unguided Guided
The Fastway system provides a local transit service serving the Crawley, Gatwick Airport and Horley area.
Fastway operates along sections of dedicated guided busway and reserved bus lanes and has been specially
designed to speed past congestion hotspots and offers a comfortable, reliable and efficient alternative to travel
by car.11
A total of 1.5km of the route runs on guideway, offering some of the key benefits discussed above. Sections of
guideway have been used to prevent the use of certain road links between neighbourhoods by general traffic.
However, longer sections of guideways tend to work better than multiple short sections of guideways with
regards to achieving reliable journey times and faster services.
The routes run close to stations at Crawley, Three Bridges, Gatwick Airport and Horley, but interchange is of low
quality. When introduced, services through Gatwick Airport were able to run on non-public roads within the
airport perimeter, however security restrictions now mean that routes must stop at laybys on the main A23.
Figure A-8: Image of Crawley Fastway system12
11 http://www.fastway.info/about-fastway/ 12 https://www.google.co.uk/search?q=crawley+fastway&rlz=1C1GGRV_enGB774GB774&source=lnms&tbm=isch&sa=X&ved=0ahUKEwiL-
qPQsoTYAhVjKsAKHfiIAbAQ_AUIDCgD&biw=1680&bih=919#imgrc=71DPkLlss4MrLM:
38
Light rail transit (LRT or tram)
Although trams can present reputable levels of modal shift, such systems also incur high capital costs (costing
more than most bus-based systems) associated with transporting passengers to their ultimate destination, since
trams are limited in terms of their flexibility and therefore typically run on simple routes with few branch lines.
Costs can be categorised into construction, infrastructure, operations and maintenance. Tram and light rail
services are typically urban mass transit. Longer routes can offer semi-express services – for example between
suburbs and urban centres
Example 1 – Freiburg
Line extensions and development around the tramlines has resulted in approximately 80% of Freiburg’s
population living within 800m of a tram stop offering a local transit type of service. The type of infrastructure in
Freiburg varies between shared and dedicated, since all vehicles, cyclists and pedestrians can cross the tram
lines, yet the trams themselves run on specific routes with the guided rail system embedded into the ground.
Table A- 8: Freiburg LRT Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
Example 2 – Manchester Metrolink
The Manchester Metrolink was originally designed to take over two rail lines which required extensive
modernisation, and to provide a more affordable cross-city link than the proposed heavy rail line. It has
subsequently been expanded on new alignments to serve regeneration areas of the city and provide local links
to the airport.
Table A- 9: Manchester Metrolink Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
Thus, in comparison to the Freiburg scheme, the Metrolink provides longer distance services over a wider area.
However, more people are using buses than the Metrolink since the bus network is more extensive with a larger
proportion of residents living within walking distance from bus stops.
The Manchester Metrolink offers a frequent semi-express service, running on shared, on-street and dedicated
infrastructure using a guided system. However, because the original parts of the system serve repurposed rail
stations, the trams have high floors to align with standard height rail platforms. This means that stops at on-
street sections are much more intrusive than those for low-floor trams and cannot be shared with other modes.
39
Figure A-9: Image of Manchester Metrolink13
Example 3 – Edinburgh Tram (GBRT to LRT)
The Edinburgh Tram has been chosen as a key example due to the fact that part of the route originally operated
as a busway known as the ‘West Edinburgh Guided Busway’ or ‘Edinburgh Fastway’. The 1.5km guided busway
was built with a future tram network in mind. This flexibility and adaptability is one of the key advantages
associated with bus rapid transit-based systems. Essentially a ‘pre-tram’ system can test whether a tram system
would fit the forecasted demand. In time, the bus-based system can attract and increase passenger numbers,
and once a desired level of patronage is reached, it could be upgraded to a LRT system.
The Edinburgh Tram connects to multiple transport interchanges, including Edinburgh Airport, a park and ride
site at Ingliston, and connects with bus and rail services.
Table A- 10: Edinburgh Tram Characteristics
Service Type Local Urban mass transit Semi-Express
Infrastructure Type Shared Reserved Dedicated
Guidance Unguided Guided
The Edinburgh tram route covers 14km from York Place in the city centre to Edinburgh Airport. With 16 stops,
the system offers an urban mass transit system with stops approximately 1km apart. The trams run on guided
13 http://www.railtechnologymagazine.com/Rail-News/work-begins-to-transform-crumpsall-metrolink-stop-ahead-of-350m-expansion
40
dedicated infrastructure, which is also shared with other road users at junctions in order to enable all traffic to
turn.
Figure A-10: Edinburgh tram
Example 4 – Coventry Very Light Rail14
A new system known as ‘Very Light Rail’ (VLR) is currently being developed as part of a research project by the
University of Warwick. The system will use a state-of-the-art rail system which is claimed to be cheaper, quieter
and more environmentally friendly than anything currently available.
14 https://warwick.ac.uk/fac/sci/wmg/research/hvmcatapult/research/rail/vlr/
41
Figure A-11: Coventry VLR system
The project is funded by the Government’s Local Growth Fund through the Coventry and Warwickshire Local
Enterprise Partnership and West Midlands Combined Authority Devolution Deal (which is subject to approval of
the business case). It is claimed that this will use a state-of-the-art rail system which will be cheaper, quieter and
more environmentally friendly than anything currently available. Vehicles would be self-propelled using battery
technology only, removing the need for overhead line equipment. It is anticipated that VLR could come into
operation by 2025.
42
Tram-train and rail
A tram-train system offers a vehicle and service type that can operate in the street as a tram but can also
operate on standard railway lines. Tram-trains often share lines with intercity passenger rail and freight, to go
longer distances into the surrounding suburbs. One of the key issues with tram-trains is that they become less
effective for longer journeys since trams typically operate at slower maximum speeds than trains on shared
sections of track.
Tram-trains can offer semi-express services with the advantage of better penetration of urban centres than
heavy rail. Note, however, that the more common way of achieving this in the UK is for sections of heavy rail to
be disconnected from the main network and modified for tram operation, as in Manchester, Birmingham and
Croydon. This avoids issues of interoperability, electrification systems, and crashworthiness.
The potential of tram-train services and operation between Stansted Airport and Braintree is non-existent due to
the lack of an existing railway line connecting the Airport with Great Dunmow and Braintree.
Heavy rail is another mode to be considered in terms offering a capacity that supports travel demand in a
certain area. Rail often covers larger geographical areas. This mode can offer local stopping services as well as
express services dependent on the type of infrastructure in place. All trains operate on dedicated, guided
railway lines that are only shared in the case of the tram-train examples previously discussed. As there is no rail
capacity which coincides with the key corridors, this report does not give rail examples due to the financial
unviability of construction and operation.