Upload
ahsan-shahid
View
222
Download
0
Embed Size (px)
Citation preview
7/31/2019 PM(Project Life Cycle)
1/22
Project Life Cycle
There is general agreement that most
projects pass through a four phase lifecycle under the following headings:
7/31/2019 PM(Project Life Cycle)
2/22
Concept and initiation Phase
The first phase starts the project by
establishing a need or opportunity for the
product, facility or service. The feasibility of
proceeding with the project is invested and on
acceptance moves to the next phase.
7/31/2019 PM(Project Life Cycle)
3/22
Design and Development Phase
The second phase uses the guidelines set by
the feasibility study to design the product and
develop detailed schedules and plans for
making or implementing the product.
7/31/2019 PM(Project Life Cycle)
4/22
Implementation or Construction Phase
The third phase implements the project as per
the base line plan developed in the previous
phase.
7/31/2019 PM(Project Life Cycle)
5/22
Commissioning and Handover Phase
The fourth phase confirms the project has
been implemented or built to the design and
terminates the project.
7/31/2019 PM(Project Life Cycle)
6/22
For example, consider a simple house building
project which passes through the following
phases:
7/31/2019 PM(Project Life Cycle)
7/22
Concept and initial Phase
The desire for a new develops into a need. The
options and alternatives are considered, and
the feasibility of the best options are
evaluated.
7/31/2019 PM(Project Life Cycle)
8/22
Design and Development Phase
The preferred option is now designed and
developed in detail, together with all the
associated planning of schedules,
procurement, resources and budgets. The land
and long lead items may be bought in this
phase.
7/31/2019 PM(Project Life Cycle)
9/22
Implementation or Construction Phase
The contracts are let and the house is built to
detailed plans developed in the previous
phase. Changes may be made to the original
baseline plan as problems arise or better
information is forth coming.
7/31/2019 PM(Project Life Cycle)
10/22
Commissioning and handover Phase
The building is inspected and approve. The
house is now ready to be handed over to the
owner and family.
7/31/2019 PM(Project Life Cycle)
11/22
The project life cycle definition will also
determine which transitional actions at the
end of the project are included and which are
not. In this manner, the project life cycle
definition can be used to link the project to
the ongoing operations of the performing
organization.
7/31/2019 PM(Project Life Cycle)
12/22
The phase sequence defined by most project life cyclesgenerally involves some form of technology transfer orhand-off such as requirements to design, construction
to operations, or design to manufacturing. Deliverablesfrom the preceding phase are usually approved beforework starts on the next phase. However, a subsequent
phase is sometimes begun prior to approval of theprevious phase deliverables when the risks involved are
deemed acceptable. This practice of overlappingphases is often calledfast tracking.
7/31/2019 PM(Project Life Cycle)
13/22
Project life cycles generally define:
What technical work should be done in eachphase (e.g., is the work of the architect part of
the definition phase or part of the executionphase?).
Who should be involved in each phase (e.g.,
concurrent engineering requires that theimplementor be involved with requirementsand design).
7/31/2019 PM(Project Life Cycle)
14/22
Project life cycle descriptions may be very
general or very detailed. Highly detailed
descriptions may have numerous forms,
charts, and checklists to provide structure and
consistency. Such detailed approaches are
often called project management
methodologies.
7/31/2019 PM(Project Life Cycle)
15/22
Most project life cycle descriptions share a
number of common characteristics:
Cost and staffing levels are low at the start,
higher towards the end, and drop rapidly as
the project draws to a conclusion. This pattern
is illustrated in Figure 21
7/31/2019 PM(Project Life Cycle)
16/22
The probability of successfully completing the
project is lowest, and hence risk and
uncertainty are highest, at the start of the
project. The probability of successful
completion generally gets progressively higher
as the project continues.
7/31/2019 PM(Project Life Cycle)
17/22
The ability of the stakeholders to influence the
final characteristics of the project product and
the final cost of the project is highest at the
start and gets progressively lower as theproject continues. A major contributor to this
phenomenon is that the cost of changes and
error correction generally increases as theproject continues.
7/31/2019 PM(Project Life Cycle)
18/22
Care should be taken to distinguish theproject
life cycle from theproductlife cycle. For
example, a project undertaken to bring a new
desktop computer to market is but one phaseor stage of the product life cycle.
7/31/2019 PM(Project Life Cycle)
19/22
Although many project life cycles have similarphase names with similar work productsrequired, few are identical. Most have four or five
phases, but some have nine or more. Even withina single application area there can be significantvariationsone organizations softwaredevelopment life cycle may have a single design
phase while anothers has separate phases forfunctional and detail design. Subprojects withinprojects may also have distinct project life cycles.
7/31/2019 PM(Project Life Cycle)
20/22
For example: an architectural firm hired to design anew office building is first involved in the ownersdefinition phase when doing the design and in theowners implementation phase when supporting the
construction effort. The architects design project,however, will have its own series of phases fromconceptual development through definition and
implementation to closure. The architect may even
treat designing the facility and supporting theconstruction as separate projects with their owndistinct phases.
7/31/2019 PM(Project Life Cycle)
21/22
Construction
Feasibilityproject formulation, feasibility studies, andstrategy design and approval. A go/no-go decision ismade at the end of this phase.
Planning and Designbase design, cost and schedule,contract terms and conditions, and detailed planning.Major contracts are let at the end of this phase.
Productionmanufacturing, delivery, civil works,installation, and testing. The facility is substantially
complete at the end of this phase.
Turnover and Start-upfinal testing and maintenance.The facility is in full operation at the end of this phase.
7/31/2019 PM(Project Life Cycle)
22/22
Pharmaceuticals
Discovery and Screeningincludes basic and appliedresearch to identify candidates for preclinical testing.
Preclinical Developmentincludes laboratory and animal
testing to determine safety and efficacy as well aspreparation and filing of an Investigational New Drug (IND)application.
Registration(s) Workupincludes Clinical Phase I, II, and IIItests as well as preparation and filing of a New Drug
Application (NDA). Post-submission Activityincludes additional work as
required to support Food and Drug Administration reviewof the NDA.