Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Planning Committee Charter Update
Elliott Nethercutt, PC SecretaryPlanning Committee MeetingJune 7, 2016
RELIABILITY | ACCOUNTABILITY2
Planning Committee Charter Background and Proposed Enhancements
Background• Last charter update: November 2013• Change in NERC’s strategic direction drives the need for clarity
on processProposed Enhancements• Provide definitions and processes for deliverable approval,
endorsement, and acceptance• Define PC deliverables (e.g., white papers, technical reports,
technical reference documents)• Add clarity and consistency for PC subgroups (charter
alignment)• Add clarity for PC Executive Committee delegation responsibility
RELIABILITY | ACCOUNTABILITY3
Planning Committee Charter Update Proposed Development Schedule
• April: Introduced proposed charter addendum to PC Leadership and Executive Committee
• Late-May: Direction from NERC Legal Department regarding Board approval
• June 7-8 PC Meeting: Introduce proposed charter updates• June 20 – July 1: Two-week review period for the Planning
Committee• July 5-6: NERC staff responds to PC Comments• July 6-8: PC electronic vote for endorsement of charter for
Board approval• August 10-11: NERC Board of Trustees approval vote
RELIABILITY | ACCOUNTABILITY4
1 RELIABILITY | ACCOUNTABILITY
PC Annual ElectionMembers/Sectors Open or Up for Renewal
Member Name, Organization Sector Y/NGary T. Brownfield, Lower Colorado River Authority Investor-Owned Utility ?Arthur Iler, American Municipal Power, Inc. State/Municipal Utility YRuss Schussler, Georgia Transmission Corporation Cooperative Utility ?Stephane Talbot, Hydro Québec TransÉnergie Provincial Utility (CA) YDavid Jacobson, Manitoba Hydro Provincial Utility (CA) ?Brian Zavesky, Missouri River Energy Services Transmission Dependent Utility YRobert Ramaekers, Tenaska, Inc. Merchant Electricity Generator YSteven Huber, Public Service Enterprise Group Electricity Marketer ?Vacant Large End-Use Electricity Customer -John Hughes, Electricity Consumers Resource Council Large End-Use Electricity Customer NHerb Schrayshuen, Self-as Small End-User Small End-Use Electricity Customer ?Mark Sims, PJM ISO/RTO NVacant State Government -Vacant State Government -
NERC 2016 Summer Reliability AssessmentPooja Shah, NERC StaffPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
• 2016 Summer Reliability Assessment (2016 SRA) Process Layout – New Format for the SRA Key Findings Timeline
• Request the Planning Committee (PC) Accept the 2016 SRA
Introduction
RELIABILITY | ACCOUNTABILITY3
• Data Collection for 2016 SRA – Reliability Assessment Subcommittee (RAS) Minimal data requests and no narratives
• Data Validation – RAS and NERC Staff• RAS Meeting – April 2016 Area/Regional presentation on the upcoming summer Abbreviated Peer Review Key findings identified
• Report Development – NERC Staff• Comments/Review/Edits – incorporated from PC Members NERC Management RAS Members
Process
RELIABILITY | ACCOUNTABILITY4
New Format for Summer Assessment
Description of Region/Assessment Area
On-Peak and DeratedRenewable Capacity
Fuel mix for a Region/Assessment Area
Resource and Demand Table (Same as SRA Reports)
Key Findings
RELIABILITY | ACCOUNTABILITY5
• Anticipated Reserve Margin forecasted to be above the Reference Margin Level for all Assessment Areas and Regions
• Aliso Canyon Gas Storage Facility Outages remains a concern CAISO is working with relevant entities to ensure the expected days of load
shedding are minimized
Key Findings
RELIABILITY | ACCOUNTABILITY6
2016 SRA - Remaining Timeline
Deliverable Deadline Status
Send to PC for Review May 23 Complete
Incorporate PC Comments May 23 – June 6 Complete (withcomments rec’d to date)
Send to NERC Management for Review May 23 – June 6 Complete
Incorporate NERC Management comments May 23 – June 6 Complete
Send revision of SRA to PC for review of NERC Management edits/comments
May 31 Complete
PC Meeting: SRA Presentation and Vote for Approval June 7-8 Pending
Send report to Publications June 8 Pending
Send report to NERC Executive Management June 10 Pending
Report Release June 14 Pending
RELIABILITY | ACCOUNTABILITY7
Request PC Action: Accept 2016 Summer Reliability Assessment
RELIABILITY | ACCOUNTABILITY8
Pooja ShahSenior Engineer, Reliability Assessment404-446-9621 office | 404-710-0502 [email protected]
Gas-Electric Interdependency Special Short-Term Assessment
John Moura, Director, Reliability Assessment and System AnalysisOC/PC MeetingsJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
Introduction
• Gas-electric interdependency STSA: This first STSA was approved by the OC and PC in April and released in
May. Review of report highlights and findings
• Second STSA: NERC, in coordination with the Reliability Assessment Subcommittee
(RAS), the ERO RAPA is in the process of identifying an assessment topic. The PC and OC are invited to suggest topics for consideration
RELIABILITY | ACCOUNTABILITY3
Overview
• Industry continues to coordinate between the two industries Electric Natural Gas
• Historically, reliability concerns in winter Report finds summer season can also be impacted
• Aliso Canyon storage facility – will not be refueled for summer 2016
RELIABILITY | ACCOUNTABILITY4
• The electric and gas industries should consider mitigation measures – use of dual-fuel generators and firm natural gas delivery contracts.
• Risks to natural gas generation during summer season – not just a winter problem
• Expand gas-electric planning and coordination – current industry best practice in some areas
• Operational coordination between gas and electric industries decrease likelihood of wide-spread outage
Key Findings and Recommendations
RELIABILITY | ACCOUNTABILITY5
NERC’s Annual Long-Term Projection
2009 LTRA
2011 LTRA
2013 LTRA
2015 LTRA
320
330
340
350
360
370
380
390
400
410
420
430
440
450
460
470
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
GWTotal NERC-Wide On-Peak Gas-Fired Capacity
RELIABILITY | ACCOUNTABILITY6
Assessment Summary
• Generation Availability Risk Assessment• Assessment Period: Peak periods for Summer 2016, 2017;
Winter 2016/17, 2017/18• Short-term challenges related to natural gas infrastructure• Leverage existing studies from industry and Regions
Areas Highly-Dependent on Natural Gas-Fired Capacity
RELIABILITY | ACCOUNTABILITY7
Gas Availability Risk Assessment
Average Forced Non-Gas Outages
Average Forced Gas Outages
Maximum Forced Gas Outages (in excess of average)Gas-Fired
Capacity
Dual-FuelCapacity
Non-Gas-FiredCapacity
Based on GADS Performance Data
Extreme (90/10) Peak Load Forecast
Normal (50/50) Peak Load Forecast
Firm Import Capability
Separate Area-Specific NG ScenarioRefers to loss of a major pipelines during the peak
RELIABILITY | ACCOUNTABILITY8
Results – ISO-NE
ISO-NE Summer 2016 Gas Operational Risk
0
5
10
15
20
25
30
35
AnticipatedCapacity
Net Imports (Firm) At-Risk Capacity Extreme Scenario
GW
RELIABILITY | ACCOUNTABILITY9
Results - NYISO
NYISO Summer 2017 Gas Operational Risk
0
5
10
15
20
25
30
35
40
45
AnticipatedCapacity
Net Imports (Firm) At-Risk Capacity Extreme Scenario
GW
RELIABILITY | ACCOUNTABILITY10
Results - ERCOT
ERCOT Winter 2016/17 Gas Operational Risk
0
10
20
30
40
50
60
70
80
90
AnticipatedCapacity
Net Imports (Firm) At-Risk Capacity Extreme Scenario
GW
RELIABILITY | ACCOUNTABILITY11
Results – WECC CA/MX
CA-MX Winter 2017/18 Gas Operational Risk
0
10
20
30
40
50
60
AnticipatedCapacity
Net Imports (Firm) At-Risk Capacity Extreme Scenario
GW
RELIABILITY | ACCOUNTABILITY12
• Aliso Canyon is a critical element of the Los Angeles Basin natural gas delivery system Supports winter peak heating demand Maintains pressure in gas distribution system (More challenging with rapid
power plant ramping)
• Aliso Canyon currently has about 15 Bcf of working gas out of a total capacity of 86 Bcf
• Injections will not resume until safety testing or isolation of remaining 114 wells is completed
Aliso Canyon: Basics
RELIABILITY | ACCOUNTABILITY13
Aliso Canyon: LA Basin Power Supply
RELIABILITY | ACCOUNTABILITY14
• Fuel availability for local generation may be impacted for upcoming summer Gas system deliverability without Aliso Canyon Gas system outages (SoCal or on interstate pipelines) Exogenous factors affecting supply (e.g., cold weather) Curtailment priorities
• Generation resource adequacy 95% of in-basin generation vulnerable to gas curtailment Adequate generation resources exist to supply imports into the LA Basin,
but this does not take into account local deliverability issues
Aliso Canyon: Anticipated Interruptions
RELIABILITY | ACCOUNTABILITY15
Short-Term Special AssessmentProposed List of Topics for STSA #2
1. Accelerated Nuclear Retirements2. Off-Peak Load Seasonal Assessment3. August 2017 Solar Eclipse4. Variable Resource Curtailments5. Natural Gas Single Point of Failure Analysis
• Other topics are being considered by Regional stakeholder groups
RELIABILITY | ACCOUNTABILITY16
Phil Fedora, RAS Chair Planning Committee Meeting June 7-8, 2016
Reliability Assessment Subcommittee Status Update
RELIABILITY | ACCOUNTABILITY 2
June 10, 2016 LTRA data due
June 24, 2016 Draft Narratives Due
June 29-30, 2016 RAS Conference Call
July 1, 2016 Peer Review Comments Due
July 12-13, 2016 RAS Meeting – SERC office
July 22, 2016 Final Data & Narratives Due
July - September LTRA Report development by NERC Staff
Upcoming LTRA Milestones
Upcoming milestones for the development for the 2016 Long-Term Reliability Assessment (LTRA)
RELIABILITY | ACCOUNTABILITY 3
2016 Reliability Assessment Reports LTRA Overview
2016 Long-Term Reliability Assessment Primary/Supplemental Data and Informational Requests Ongoing MMWG coordination Incorporation of : Essential Reliability Services Measure 6 – Net Demand Ramping Variability Probabilistic Dashboard Results
Continuing need to clarify instructions: Distributed Generation On-Peak Capacity Transfer capability Planned Generation Tiers:
2016 Probabilistic Assessment Q1 – 2017 target release
RELIABILITY | ACCOUNTABILITY 4
Net Demand Ramping Variability Essential Reliability Services (ERS) Working Group working on: Ramping Screening Methodology – to be used in the LTRA for
identification of existing/potential ramping reliability concerns Identified LTRA ramping reliability concerns – to be considered
in the development of the ERS Sufficiency Guidelines
Essential Reliability Services Measure 6
RELIABILITY | ACCOUNTABILITY 5
Probabilistic Assessment Improvement Task Force Guideline Document Proposed Probabilistic Enhancements Probabilistic Metrics Study Year(s)/Frequency Scenario Analysis
Reliability Assessment Subcommittee Probabilistic Assessment Improvement Task Force
RELIABILITY | ACCOUNTABILITY 6
Remaining LTRA Timeline (as of May 23, 2016)
2016 LTRA Schedule Date Action Item
August 23-24 ERO RAPA Meeting: review of Regional responses to narrative questions September 2 Draft report sent to RAS (Prober dashboards NOT included) September 23 RAS comments due to NERC September 26-30 NERC responds to RAS comments October 4 RAS Meeting; Conference Call; Prober Team presents to RAS October 14 Prober dashboards/narratives due to NERC October 17-21 NERC incorporates Prober dashboards and addresses ERS Measure 6 in the report
October 21 LTRA sent to PC for review October 21-November 4 PC review period
November 4-8 NERC responds to PC feedback November 8 PC webinar for report endorsement November 8-18 NERC Editorial Review November 14-16 RAS Meeting; FRCC - Tampa FL; WRA/STSA/LTRA November 21 LTRA sent to NERC Executive Management, MRC, and ERO RAPA November 21-25 NERC Executive Management, MRC, and ERO RAPA review period November 25-28 NERC responds to feedback from NERC Executive Management and MRC
November 28 LTRA sent to NERC Board of Trustees November 28- December 5-6 (awaiting confirmation)
NERC Board of Trustees review period
December 5-8 (awaiting confirmation)
NERC Board of Trustees conference call to vote on report approval
December 8-13 NERC responds to feedback from Board of Trustees December 13 Target Release
RELIABILITY | ACCOUNTABILITY 7
Probabilistic Assessment Guidelines
Noha Abdel-Karim, PhD., Senior Engineer for Reliability AssessmentPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
• Background: Prepare Probabilistic Assessment Guidelines document to Identify modeling requirements and recommendations, and to support Regional scenarios to study emerging risks to reliability.
• Core Probabilistic Assessment Continuation of the individual area probability
assessments. Modeling consistency will be improved by following a
Probabilistic Assessment Guidelines document.
• NERC-Regional Coordinated Special Assessment Expand the probabilistic study efforts with NERC and the
Regions leading the development and evaluation efforts of additional scenario studies on reliability concerns related to the BPS higher risk areas identified in the LTRA.
Probabilistic Assessment Guidelines Document Overview
RELIABILITY | ACCOUNTABILITY3
• Core Probabilistic Assessment Metric Reporting Areas Metrics Descriptions Metric Calculations Probabilistic Study Reportingo Study Frequency and Study Years
Simulation software
• Coordinated NERC Regional Special Assessment Special Assessment Determination Roles and Responsibilities Modeling Requirements and
Scope of Work
• General Modeling Assumptions Load Modeling Capacity Modeling Emergency Operating Procedures Transmission Modeling Sensitivity and Scenario Modeling Data Preparation and Collection
ProbA Guidelines Document
RELIABILITY | ACCOUNTABILITY4
• Primary objectives• Enhancements Summary• Probabilistic Metrics• Assessment Frequency• Sensitivity and Scenario • Enhancement Applicable to the 2016 ProbA Development
Probabilistic Guidelines
RELIABILITY | ACCOUNTABILITY5
• Identify practices, requirements and recommendations needed to perform high-quality probabilistic resource adequacy assessments.
• Complement reserve margin analyses in NERC’s Long-Term Reliability Assessments by producing enhanced resource adequacy metrics and modeling approaches.
• Provide NERC and policy makers with far greater insight, understanding, and the perspectives on BPS reliability.
• Support regional scenarios to study reliability issues identified in the Long-Term Reliability Assessment.
ProbA Guidelines
RELIABILITY | ACCOUNTABILITY6
ProbA Guidelines
Enhancements Summary
NERC should develop and maintain documentation describing the establishment of Assessment Areas. 1
Regions and Assessment Areas should provide monthly reliability measures in their metrics calculations.2
Regions and Assessment Areas should incorporate seasonal variations in their load modeling.3
Regions and Assessment Areas should capture seasonalcapacity ratings in generation models.4
RELIABILITY | ACCOUNTABILITY7
ProbA Guidelines
Enhancements Summary
Flexibility should be maintained in transmission modelingfor each Assessment Area.5
Assessment Areas should coordinate with neighboring areasto determine the appropriate amount of capacity transfers.6
NERC, within the RAS, should determine candidate probabilistic sensitivity analysis and scenario models to study.7
RELIABILITY | ACCOUNTABILITY8
• Probabilistic Metrics Annual LOLH Monthly LOLH Annual EUE, both actual and normalized Monthly EUE, both actual and normalized
• Probabilistic Study Frequency and Study Years With inputs from the RAS, RAS-ProbA, PAITF and ERO-RAPAo Probabilistic assessment is on a biennial basis
Assessment Areas study both year 2 and 4 of the Long-Term Reliability Assessment (LTRA).
Year 2 reporting is to track and trend resource adequacy measures assessment to assessment.
ProbA Guidelines
RELIABILITY | ACCOUNTABILITY9
• Assess the impact of a change in an input (either load, transmission or resource-related) on resource adequacy metrics.
• The runs are performed by changing one input at-a-time in order to isolate the potential impact of each input.
• Ideally, the change in each input should be accompanied by an associated probability.
• The sensitivity modeling should be addressed within the Core Probabilistic Assessment framework.
• Assess the impact of changes in multiples inputs (either load, transmission or resource-related) on resource adequacy metrics.
• The runs are performed by changing multiple inputs at the same time
• Scenarios are likely to be identified in the LTRA or by sensitivity analysis results.
• The scenario modeling should addressthe reliability issues identified withinthe LTRA that impact resourceadequacy, within the Special-Coordinated Probabilistic Assessmentframework
ProbA Guidelines
Scenario ModelingSensitivity Modeling
RELIABILITY | ACCOUNTABILITY10
• 2016 ProbA Enhancements Monthly Probabilistic Measures Per guidelines, Assessment Areas describe in their narratives the
assumptions used to develop ALL modeling categories of their probabilistic studies.
ProbA Guidelines
RELIABILITY | ACCOUNTABILITY11
2016 ProbA Schedule
RELIABILITY | ACCOUNTABILITY12
• Request from the PC to: Assign PC Reviewers to the ProbA Guidelines document Seek PC Approval of the ProbA Guidelines document after an adequate
reviewing time and via an electronic vote
Actions
RELIABILITY | ACCOUNTABILITY13
Reliability Guideline:Reactive Power Planning and OperationsPlanning Committee Approval for Industry Comment
Bill Harm, PJMPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
• System Analysis and Modeling Subcommittee (SAMS) is asking the Planning Committee (PC) for approval of the “final draft” guideline for NERC posting for industry comment 45 days for industry comment period as per the PC Charter
• The SAMS sub-team will then reconvene to consider industry comments and develop final draft for PC approval This will be an industry developed NERC document
• Different than the previous Technical Issues Subcommittee (TIS) reactive white paper TIS forwarded a final document to the PC for approvalo Action items were incorporated in VAR-001, Var-002 and TPL-001
Reactive Guideline - Administrative
RELIABILITY | ACCOUNTABILITY3
• Provide guidance and direction related to modeling, study, and placement of reactive power resources to support robust voltage profiles. NERC’s mission of improved reliability through sharing industry practices
for planning and operating the BPS
• Guideline applies primarily to: Planning Coordinators Transmission Planners Transmission Operators Generator Operators Generator Owners Reliability Coordinators
Reactive Guideline - General
RELIABILITY | ACCOUNTABILITY4
• Two parts: Technical Document Appendices and References
• First part includes: Background on reactive planning and operations Summary of Relevant NERC standards o TPL-001o VAR-001; VAR-002o TOP-004
Technical discussion regarding reactive power analysiso Strategies center around the need for static and dynamic reactive power
resource planning and operational planning
Reactive Guideline - General
RELIABILITY | ACCOUNTABILITY5
• Assessment tools and techniques• Time frames – pre-contingency through disturbance and new
post contingency steady state Transient, midterm dynamics, long term dynamics, post contingency
steady state• Determining steady-state voltage limits and post-contingency
voltage deviations PV analysis QV analysis
• Transient Analysis
Reactive Guideline - Analysis
RELIABILITY | ACCOUNTABILITY6
• Fundamentals of voltage control and static and dynamic reactive resources
• Deriving voltage schedules on Trans system Typical Operating voltage schedules
• Generator voltage control Converting visible generator voltage to the transmission system
• Transient voltage response criteria• Protecting against voltage instability• Determining sufficient reactive resources and/or margins to
regulate voltage levels under normal and contingency conditions
Reactive Guideline – Voltage Criteria
RELIABILITY | ACCOUNTABILITY7
• Reactive power generation scheduling• Automatic voltage control modes• Coordination with static devices and other controls• Reactive Reserve Requirements• Dynamic reserves vs. static• Addressing “sufficient” reserves
Reactive Guideline – Voltage Control
RELIABILITY | ACCOUNTABILITY8
• Interface coordination between operating entities• Distribution of reactive resources among transmission,
distribution, and generation
Reactive Guideline –Interface Coordination
RELIABILITY | ACCOUNTABILITY9
2nd part of guideline includes:• Appendix A – Industry Reactive Power Planning Practices &
Procedures Analysis tools, techniques, planning horizons, and relevant reference
materials from an array of entities across North America How the information contained in the first part of the guideline is applied
in operations and planning
• Appendix B – Transient Voltage Response Criteria Practices Response criteria as per NERC Reliability Standard TPL-001-4 Requirement
R5 and a description of the criteria developed
Reactive Guideline – Appendices
RELIABILITY | ACCOUNTABILITY10
• 6/8/2016 - PC Approval for Posting for Industry Comments• 8/1/2015 - 45 Day Comment Period Complete (6/15 Posting)• 8/15-10/27 - Response to Comments & Document Revision• 10/27/2016 - SAMS Approve Final Draft at SAMS Meeting• 12/13/2016 - PC Final Approval
Reactive Guideline – Timeline
RELIABILITY | ACCOUNTABILITY11
Reliability GuidelinePower Plant Model Verification using PMUsPlanning Committee Approval for Industry Comment
Ryan D. Quint, NERCPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
• NERC Synchronized Measurement Subcommittee (SMS) is requesting Planning Committee (PC) approval for industry comment period of the Reliability Guideline for Power Plant Model Verification using PMUs
• The SMS will reconvene to address industry comments and develop final draft for PC approval in September
• Timeline: June 7-8: PC approval for posting for industry comment June 15-July 30: 45-day comment period August 1-Sept 1: SMS response to comments and edits to draft RG Sept PC Meeting: PC final approval
PPMV Guideline: Overview
RELIABILITY | ACCOUNTABILITY3
Drivers:• Provide technical guidance and direction for performing
disturbance-based verification using PMUs as one option for model verification
• Provide guidance for MOD-026 and -027 Requirement R2: The [GO] can use disturbance-based model verification as a form
of demonstrating that the modeled response matches actual response. However, this must also be accompanied by the other documentation and data required by Requirements R2, including manufacturer data, model structure and data, compensation settings, etc.
Requirement R3: The [TP] can use results from disturbance-based model verification to demonstrate that the current model being used does not accurately represent actual response.
Requirement R5: The [TP] can submit a request for model review using “technically justified” results “demonstrating that the simulated unit or plant response does not match the measured unit or plant response.”
PPMV Guideline:Drivers
RELIABILITY | ACCOUNTABILITY4
Applicability:• Transmission Planners• Planning Coordinators• Transmission Owners• Generator Owners
PPMV Guideline:Drivers
RELIABILITY | ACCOUNTABILITY5
• Document Covers: Fundamental need for representative models Power Plant Model Verification (PPMV) Offline Baseline Testing for pro forma Model Online Performance Monitoring Process for Model Validation Value Proposition for Disturbance-Based Verification Related NERC Reliability Standards Performing PMU-Based Model Verificationo Procedure Overviewo Measurement & Modeling Considerationso Event Selection
Disturbance-Based Verification Examples Library Appendix – Software Tools Guidelines
Power Plant Model Verification
RELIABILITY | ACCOUNTABILITY6
Phase Angle MonitoringTechnical Report Follow-Up and Approval
Ryan D. Quint, NERCPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
• NERC Synchronized Measurement Subcommittee (SMS) sought Planning Committee (PC) approval on Phase Angle Monitoring Technical Report at the March 2016 PC meeting. Questions about recommendations; wanted feedback from the Operating
Committee prior to approval. Convened review team to provide comments and address any concerns.
• Will describe changes and updates since last meeting.• NERC SMS is seeking final PC approval of Phase Angle Monitoring
Technical Report.
Background
RELIABILITY | ACCOUNTABILITY3
• The recommendations listed below are based on the assessment of phase angle monitoring, limit calculation, and alarming techniques. While the report focuses on practices in the Western Interconnection following the Pacific Southwest Outage, it was determined that these recommendations apply to all interconnections and entities performing the respective functions. The concepts of phase angle monitoring and alarming using both SCADA-based and time synchronized measurements for improved situational awareness apply to any Bulk-Power System.
RevisionsRecommendations Header Paragraph
RELIABILITY | ACCOUNTABILITY4
• The contingency risk of interest is the outage of a transmission circuit and the phase angle difference across the out-of-service terminals of that line exceeding synchrocheck relay limits. This contingency and the pPost-contingency angle differences should be monitored in real-time. The Planning Coordinator and/or Reliability Coordinator should identify key transmission circuits for which this monitoring is required. It is recommended that awareness of synchrocheck relay limit exceedances be provided to system operators for EHV transmission circuits, where applicable, with nominal voltage greater than or equal to 345 kV.
Revisions:Recommendation #1
*NOTE: Recommendations 1 and 2 combined to avoid redundancy and to simplify.
RELIABILITY | ACCOUNTABILITY5
• Phase angle differences for potential contingency conditions should be monitored in real-time and compared against synchrocheck relay settings, if applicable, for all EHV transmission circuits using Real-Time Contingency Analysis (RTCA) tools. Any N-1 or credible N-2 or N-1-1 exceedances of these limits should be provided to the system operator for advanced notice of potential line restoration issues.
Revisions:Recommendation #2
*NOTE: No Changes Made.
RELIABILITY | ACCOUNTABILITY6
• Wide-area phase angle difference monitoring provides an additional layer of situational awareness for system operators, and wide-area limits based on known risks such as transient stability, voltage stability, small signal stability, or overloads can effectively be developed based on operations studies or advanced online applications. Utilities should consider extracting phase angle difference values during system studies for stability risks, in conjunction with conventional MW flow limits.
Revisions:Recommendation #3
*NOTE: No Changes Made.
RELIABILITY | ACCOUNTABILITY7
• Line-based phase angle difference monitoring and comparison against known synchrocheck limits is not presently a universally adopted operating practice. It is recommended that the NERC Synchronized Measurement Subcommittee (SMS), in coordination with the NERC Operating Committee (OC), explore how this practice could be used or more widely adopted by the industry.
Complete revision from…• Current industry standards do not explicitly require line-based phase angle
difference monitoring and comparison to known synchrocheck limits. Applicable NERC Reliability Standards should consider requiring real-time monitoring of phase angles and synchrocheck limit violations as a mandatory practice for Reliability Coordinators (RCs) and Transmission Operators (TOPs).
Revisions:Recommendation #4
RELIABILITY | ACCOUNTABILITY8
• In the Western Interconnection, phase angle difference is correlated to oscillatory stability issues particularly during high transfer conditions. Tools such as Mode Meter, Oscillation Detection, and Phase Angle Difference (PAD) tools provide advanced analytical capabilities to detect any oscillatory issues linked with phase angle stress. It is recommended that utilities continue pursuing advancements in these tools for further situational awareness.
Revisions:Recommendation #5
*NOTE: No Changes Made.
RELIABILITY | ACCOUNTABILITY9
• Presented the revised (from PC reviewers) recommendations and an overview of the technical report materials to the NERC Operating Reliability Subcommittee (ORS) General discussion of findings, takeaways and recommendations
• ORS agreed with the practice of monitoring phase angle differences exceeding synchrocheck relay settings in both pre-and post-contingency conditions
• No changes requested on the recommendations• General consensus of endorsement – not put to formal vote
NERC ORS Engagement
RELIABILITY | ACCOUNTABILITY10
Essential Reliability ServicesERSWG and DERTF
Brian Evans-Mongeon, ERSWG Co-ChairPlanning Committee MeetingsJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
2016 and 2017 Deliverables
2016 Deliverables:• Assist in process development for
approved measures• Whitepaper on methodology for
Essential Reliability Services (ERS) Measures Sufficiency Guidelines
• Final Report on Distributed Energy Resources
2017 Deliverable:• Final Report on ERS Measure Sufficiency
Guidelines
RELIABILITY | ACCOUNTABILITY3
• Frequency Support Sufficiency Guidelines – In progress Data Gathering for Measures 1-4 with Resources Subcommittee – In
progress
• Voltage Support Sufficiency Guidelines – In progress System Analysis and Modeling Subcommittee – Reactive Power Guideline
Revision Monitoring of Measure 7 with the Performance Analysis Subcommittee
(PAS) – Given priority work with the State of Reliability, PAS has not yet had time to work on Measure 7
• Ramping Needs ERS formed a new subgroup for screening of ramping concerns – Reliability
Assessment Subcommittee Subgroup will also develop Sufficiency Guidelines
Essential Reliability Services Working Group
RELIABILITY | ACCOUNTABILITY4
• Several conference calls and face-to-face meetings• Support from various industry experts• Draft report started Definition Modeling Operating Characteristics Review applicable NERC standards One immediate consideration: “Load Netting is BAD”
• DER Workshop with help from UVIG – In progress
Distributed Energy ResourcesTask Force
RELIABILITY | ACCOUNTABILITY5
• ERSWG and DERTF continue to work on their end-of-year deliverables Meeting following the Standing Committees is here in St. Louis Workshop/Forum Another face-to-face meeting in Early August
• Monitoring of activities with other groups in progress Outreach to regulators for more involvement Still following IEEE 1547 FERC directives and initiatives
Next Steps
RELIABILITY | ACCOUNTABILITY6
Distributed Energy Resources Task Force (DERTF)
Planning Committee MeetingBrian Evans-Mongeon, ERSWG Co-Chairman June 8, 2016
RELIABILITY | ACCOUNTABILITY2
DERTF History
• The Task Force was formed in December 2015 under the umbrella of both Operating and Planning Committees (OC and PC)
• Task Force under the newly formed Essential Reliability Services Work Group
• DERTF Scope listed eight tasks• Finished product is a report approved by OC and PC and
submitted to BOT in December 2016• Membership is a representative of technical, renewable
developers, regulatory, and utility perspectives
RELIABILITY | ACCOUNTABILITY3
• DERs in to planning models and studies• Operational impacts in areas with high penetration of non-
controllable resources • Facilitate data collection efforts and propose recommendations
for improved data collection efforts in NERC• Identify and recommend potential reliability metrics• Recommendation for consistently modeling and assessing DER• Review existing NERC Reliability Standards and coordinate with
IEEE 1547 related efforts• Review the NERC Functional Model between each category and
or treatment within NERC.• Consider development of Reliability Guideline and/or SAR
Eight DERTF Scope Tasks
RELIABILITY | ACCOUNTABILITY4
ERSTF Work Plan
• Structure report outline to meet Scope requirements• Form groups of Subject Matter Experts to work each section
1. Definition of Distributed Energy Resources (DER) in context of report2. Typical electrical connections of DER3. Modeling of DER4. DER operating characteristics5. DER effects on the Bulk Electric System (BES)6. Applicable NERC Reliability Standards7. Recommendations
• Pull sections together into final report
RELIABILITY | ACCOUNTABILITY5
• Draft report contains Sections 1, 2, and 3• Progressing on Sections 4, 5, and 6• Next meeting of ERSWG/DERTF is 6/8-6/9• Plans for a DERTF workshop 8/2-8/3
DERTF Progress
RELIABILITY | ACCOUNTABILITY6
Impact of Device Protection & Control on Reactive Generator Effectiveness
David Till, Sr. Manager, Performance AnalysisPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
Introduction
• The PC is requested to add a technical reference on Reactive Generator protection & controls to the System Protection and Controls Subcommittee (SPCS) 2016 work plan. No other PC Subgroups are identified at this time.
• Bulk power system (BPS) penetration of dedicated reactive generators (FACTS, synchronous condensers) will likely increase significantly should dynamic voltage support from conventional resources be lost to their retirement.
• Reactive generator protective systems must reliably coordinate with those of other BPS elements for this scenario.
RELIABILITY | ACCOUNTABILITY3
STATCOM Serial #1 Station Service – Still a Common Achilles Heel?(Illustrative Non-P&C Issue Preventing Reliable Operation)
Station 500 kV Bank (1. Loss of 500 Bank is the Event that Threatens Area Voltage Collapse)
STATIC
SWITCHSTATCOMFACTS DEVICE
161-kV13-kV
480V
13-kV
161 kV
69 kV
Station 161 kV Bus
Distr. Sub 1
Primary SS (2. Primary SS unavailable when 500 kV bank trips)
Secondary SS (3. Secondary SS is subset of Primary SS)
Distr. Sub 2
13 kV
(4. STATCOM Supports 161 kV Bus voltage, but trips on loss of 480 V cooling pumps & control logic for any blip in SS, which occurs EVERY TIME the STATCOM is needed to mitigate voltage collapse!)
RELIABILITY | ACCOUNTABILITY4
Conclusion
• Intentional and comprehensive discussion on requirements for reliable device operation includes a strong P&C component for which only SPCS holds expertise, as well as broad understanding of other topics with which SPCS is familiar.
Request the PC assign a technical reference regarding this issue to the SPCS Work Plan
RELIABILITY | ACCOUNTABILITY5
Functional Model Advisory Group Update to the Planning Committee
Jerry Rust (FMAG co-chair) and Lacey Ourso (NERC staff)Planning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
Agenda
• Update regarding Functional Model Advisory Group (FMAG) 2016 project
• Discuss proposed revisions to the Functional Model (FM)• Obtain feedback from members of the Planning Committee
regarding proposed revisions
RELIABILITY | ACCOUNTABILITY3
Background Information
• Purpose of the Functional Model (FM): (1) provide a framework for development of Reliability Standards, and (2) describe each function and relationships between entities responsible for
performing tasks required for each function.
• Purpose of the FMAG: (1) maintain the FM to ensure the model correctly reflects the industry
today, and (2) evaluate and incorporate new and emergent reliability-related tasks
• Revisions to the FM: “The FMAG reports to the full SC and consults with and submits all revisions to the Functional Model and its associated Technical Document to the NERC Critical Infrastructure Protection Committee (CIPC), Operating Committee (OC), and Planning Committee (PC) for endorsement.”
RELIABILITY | ACCOUNTABILITY4
2016 FMAG project
• Current version of the FM developed in 2009 and approved by the NERC Board in 2010.
• Focus of 2016 effort: FMAG asked to review recent NERC initiatives (Risk-Based Registration
initiative) and standard development projects (Alignment of Terms) to identify any changes or updates to the FM language
Identify other changes needed as a result of new and emergent reliability-related issues
RELIABILITY | ACCOUNTABILITY5
Project Timeline
• January 19-20: FMAG meeting to identify areas for focus • March 8: Inform committees (OC, PC, CIPC) of work underway,
and obtain initial feedback (specific to area of expertise) • March 17-18: FMAG meeting to develop revisions to the FM• April 13-15: FMAG meeting to develop revisions to FM and FMTD • June 7-8: Present proposed revisions to committee members (OC,
PC, CIPC) for the purpose of obtaining feedback • June 15-17: FMAG meeting to review and incorporate feedback
from committees (OC, PC, and CIPC), and revise FM and FMTD. • July/August: Post proposed revisions to FM and FMTD for
industry comment • September 13: Present final revisions to the FM and FMTD to
committees (OC, PC, and CIPC) for endorsement
RELIABILITY | ACCOUNTABILITY6
Proposed Revisions to the FM
• High-level overview of proposed revisions to the FM: Incorporated Glossary terms Consolidated ERO-related functions (Reliability Assurer function) Clarified planning functions (PC, TP and RP) Added cyber and physical security tasks (RC, BA, TOP, TO, IC, DP, GO
and GOP) Added TOP task related to performing switching operations Revised tasks to clearly identify what actions are required for an
Interchange transaction (IC, BA, TSP, PSE, and LSE) Clarified TSP task of acquiring Ancillary Services Clarified DP task includes delivery to end-use customer or distribution-
connected energy resource(s)
RELIABILITY | ACCOUNTABILITY7
Comments and Feedback
• Discuss comments and feedback of Planning Committee members regarding proposed revisions…
RELIABILITY | ACCOUNTABILITY8
Contact information
• Jim Cyrulewski (co-chair)[email protected]
• Jerry Rust (co-chair)[email protected]
• Lacey Ourso (NERC staff)[email protected]
Potential Reliability Impacts of EPA’s Clean Power Plan Phase II
John Moura, Director, Reliability Assessment and System AnalysisPlanning Committee MeetingJune 7-8, 2016
RELIABILITY | ACCOUNTABILITY2
Potential Reliability Impacts
• Developed through collaboration with stakeholders to inform policy discussions and highlight potential risks to BPS reliability
• Provides range of resource adequacy evaluations based on several potential cases using different models
• Provides framework for more granular studies at the state and regional level
RELIABILITY | ACCOUNTABILITY3
• Formed to advise NERC on assessment scope and goals• Representation
All NERC Regions ISO\RTOs and Planning Coordinators IPPs and Renewable Energy Producers Trade Organizations Power Marketers Consultants Canadian Representation
• Sub-group formed to author the recommendations document• Work with modelers to develop scenarios and assumptions
Planning Committee Advisory Group
RELIABILITY | ACCOUNTABILITY4
CPP Carbon Reduction Requirements
Acceleration of fundamental change in the electricity generation mix in the United States and transformation of reliability services, diversity, and flexibility
RELIABILITY | ACCOUNTABILITY5
Scenarios
RELIABILITY | ACCOUNTABILITY6
Expected Coal Capacity Decline
Coal capacity decline by up to 27 GWs
RELIABILITY | ACCOUNTABILITY7
Large Amount ofRenewable Integration
Tax credits and renewable portfolio standards drive renewables
-
20
40
60
80
100
120
140
160
180
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
Wind Solar
GW
Reference Case
CPP Base Case
RELIABILITY | ACCOUNTABILITY8
Demand Growth
Annual energy demand growth is expected to flatten
RELIABILITY | ACCOUNTABILITY9
Trading Case - Generation
Trading allowances provide market flexibility
RELIABILITY | ACCOUNTABILITY10
Planning
Planning should already be under way due to the need for new transmission and natural gas pipeline infrastructure
RELIABILITY | ACCOUNTABILITY11
Additional Areas for Analysis
• Operational dispatch and environmental constraints • Essential Reliability Services - Sufficiency Guidelines• Distributed Energy Resources Task Force• Increasing reliance on natural gas• Interconnection-wide studies• Regional/ISO/RTO studies
RELIABILITY | ACCOUNTABILITY12
Federal and State Efforts in Ensuring Reliability
• EPA, DOE, FERC Memorandum of Understanding
• NERC’s identification of reliability considerations in Reliability Considerations for Clean Power Plan Development
RELIABILITY | ACCOUNTABILITY13