Planning and Scheduling - Bar Chart

Embed Size (px)

Citation preview

  • 7/24/2019 Planning and Scheduling - Bar Chart

    1/26

    Planning and SchedulingDr. Ir. HM. Agung Wibowo, MM, MSc

    Jati Utomo Dwi Hatmoko, ST, MM, MSc, PhD

  • 7/24/2019 Planning and Scheduling - Bar Chart

    2/26

    Definition(Collins English Dictionary)

    A detailed scheme, method, etc. for

    attaining an objective.

    A proposed usually tentative idea for doingsomething.

    A diagram or list showing work to be done,

    with associated times.

  • 7/24/2019 Planning and Scheduling - Bar Chart

    3/26

    Planning

    Planning is thus a general term

    which is used to encompass the

    ideas which are commonly refferedto as programming, scheduling and

    organising.

  • 7/24/2019 Planning and Scheduling - Bar Chart

    4/26

    The Aim of Planning

    Its aim can be defined to be makingsure that all work required tocomplete a project gets done :

    -In the correct order ;

    -In the right place ;-At the right time ;

    -By the right people and

    equipment ;

    -To the right quality ;

    -In the most economical, safe and

    environmentally acceptable

    manner.

  • 7/24/2019 Planning and Scheduling - Bar Chart

    5/26

    The who of planning

    Client

    Contractor

    Principal Consultant

  • 7/24/2019 Planning and Scheduling - Bar Chart

    6/26

    Constraint of planning

    Budget Consideration

    Type of Project

    Resources Consideration

  • 7/24/2019 Planning and Scheduling - Bar Chart

    7/26

    Planning and Control Cycle

    Plan work

    Correlation

    information Monitor

    Work

    Control

    External information

    (production rates,

    Head Office

    constraints etc.)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    8/26

    Techniques of Scheduling

    List of Activities

    Bar chart / Gantt Chart

    Critical Path Method (CPM)

    Precedence Diagram Network (PDM)

    PERT (Programme Evaluation & ReviewTechnique)

    Line of Balance Method

    Time Chainage Diagram (Mass HaulDiagram)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    9/26

    Copyright 2006 John Wiley& Sons, Inc. 9-9

    Project Scope

    Scope statement a document that provides an understanding,

    justification, and expected result of a project

    Statement of workwritten description of objectives of a project

    Work breakdown structure

    breaks down a project into components,subcomponents, activities, and tasks

  • 7/24/2019 Planning and Scheduling - Bar Chart

    10/26

    Copyright 2006 John Wiley& Sons, Inc. 9-10

    Work Breakdown Structure for Computer

    Order Processing System Project

  • 7/24/2019 Planning and Scheduling - Bar Chart

    11/26

    Copyright 2006 John Wiley& Sons, Inc. 9-11

    Organizational Breakdown Structure a chart that shows which organizational units are responsible for

    work items

    Responsibility Assignment Matrix shows who is responsible for work in a project

  • 7/24/2019 Planning and Scheduling - Bar Chart

    12/26

    What activities needed todo this work?

    Excavate base

    Blind base

    Formwork

    Reinforcement Concrete

  • 7/24/2019 Planning and Scheduling - Bar Chart

    13/26

    Copyright 2006 John Wiley& Sons, Inc. 9-13

    Project Scheduling

    Steps

    Define activities

    Sequence activities

    Estimate time /duration

    Develop schedule

    Excavate base

    Blind base

    Formwork

    Reinforcement

    Concrete

    (4d)

    (2d)

    (5d)

    (4d)

    (1d)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    14/26

    Bar Chart

    A bar chart shows the activities of a project andhow they are scheduled in time, by using lines orbars in proportional in length to the scheduledduration for the activity.Provides visual display of project scheduleGantt Chart / Bar ChartLinked Bar ChartResource Bar Chart

  • 7/24/2019 Planning and Scheduling - Bar Chart

    15/26

    ACTIVITYTIME (weeks)

    Week 1 Week 2 Week 3

    Excavate base (4d)

    Blind base (2d)

    Formwork (5d)

    Reinforcement (4d)

    Concrete (1d)

    BAR CHART (Gantt Chart)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    16/26

    Copyright 2006 John Wiley& Sons, Inc. 9-16

    | | | | |Activity

    Design houseand obtainfinancing

    Lay foundation

    Order andreceivematerials

    Build house

    Select paint

    Select carpet

    Finish work

    0 2 4 6 8 10Month

    Month1 3 5 7 9

    Example of Gantt Chart

  • 7/24/2019 Planning and Scheduling - Bar Chart

    17/26

    Gantt Chart(Mawdesley, 1997)

    Advantages ?Disadvantages ?

  • 7/24/2019 Planning and Scheduling - Bar Chart

    18/26

    Bar Chart

    Advantages & Disadvantages

    Advantages :

    1. Simple

    2. Easy to make

    3. Easy to understand, as it provides visual display of project

    schedule

    Disadvantages :

    1. No clear links between activities

    2. If delays occur, the impact on the project is not clear

  • 7/24/2019 Planning and Scheduling - Bar Chart

    19/26

    Linked Bar Chart(Mawdesley, 1997)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    20/26

    Resource Bar Chart (Mawdesley, 1997)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    21/26

    Check the plan(Mawdesley, 1997)

    A plan should be checked for:

    Completeness

    The sequence of the work

    The timing of the work

    The financial implications

    The use of resources

    The quality, safety and environmental

    implications

  • 7/24/2019 Planning and Scheduling - Bar Chart

    22/26

    Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10

    1.

    2.

    3.

    4.

    5.

    Make a simple project schedule using barchart

    Use only 5 activities

    (Work in groups of two)

    1. Define the scope of the project

    2. Make a list of activities3. Put the activities in order

    4. Define the durations of the activities

    5. Define when the activities starts

  • 7/24/2019 Planning and Scheduling - Bar Chart

    23/26

    Steps of making a bar chart

    1. Define the scope of the project

    2. Make a list of activities

    3. Put the activities in order

    4. Define the durations of the activities

    5. Define when the activities starts

    Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10

    1. Foundation

    2. Wall

    3. Windows & Doors

    4. Roof

    5. Finishing (tiles, painting

    walls, etc)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    24/26

    Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10

    1. Foundation

    2. Wall

    3. Windows & Doors

    4. Roof

    5. Finishing (tiles, painting

    walls, etc)

    predecessor successor

    foundation wall

    Linking activities in the project

    Finish to Start (FS)

  • 7/24/2019 Planning and Scheduling - Bar Chart

    25/26

    Network

    A network is a diagram showing allactivites which are needed to complete aproject and the order which they must

    be done.It therefore comprises two parts :

    The activities

    Some method of displaying thetechnological logic of construction.

  • 7/24/2019 Planning and Scheduling - Bar Chart

    26/26

    Network (Mawdesley, 1997)