40
Piping Design Submissions - What not to Forget / Omit Presented by: Djordje Srnic Design Survey Manager ABSA the pressure equipment safety authority

Piping Pressure testing

Embed Size (px)

Citation preview

Page 1: Piping Pressure testing

Piping Design Submissions -

What not to Forget / Omit

Presented by:Djordje Srnic

Design Survey Manager

ABSA the pressure equipment safety authority

Page 2: Piping Pressure testing

1/19/2009 2

Objectives

Code requirements Submission requirementsWhat not to forget / omit

Page 3: Piping Pressure testing

1/19/2009 3

Hierarchy of Act and Regulations

Safety Codes Act

Regulations

Administrator’sDirectives andInterpretations

CSA B51

ASME Boiler andPressure Vessel

Codes

ASME Piping Codes

Other codes andStandards

Ministerial Orders

Page 4: Piping Pressure testing

1/19/2009 4

Alberta regulatory requirements

Safety Codes Act (Section 40)– Pressure Equipment Safety Regulation

(Alta Reg 49/2006)– Pressure Equipment Exemption Order

(Alta Reg 56/2006)

Page 5: Piping Pressure testing

1/19/2009 5

Owner’s Responsibilities

PESR 37– Do you ever ask yourself what your

responsibilities as a Plant Owner are under the Safety Codes Act and the Pressure Piping Codes that have been declared to be in force under the Act?

– Do you rely exclusively on your piping Contractor to meet all regulatory and Code requirements because he has the Certificate of Authorization from ABSA? If so, read the article PLANT PIPING – OWNER’S RESPONSIBILITIES in ABSA’s The Pressure News, Volume 5, Issue 4, Dec. 2000.

Page 6: Piping Pressure testing

1/19/2009 6

Information Bulletins and “The Pressure News”

Information Bulletins - Administrator may issue– Directives– Variances– Interpretations– Alerts

The Pressure News – ABSA’s publication that – Informs public– Provides interpretations & clarifications– Alerts public

Page 7: Piping Pressure testing

1/19/2009 7

CSA B51 – Boilers, Pressure Vessels and Pressure Piping Code

Clause 4.1 provides general requirements for registration of designs (including pressure piping designs).

Page 8: Piping Pressure testing

1/19/2009 8

ASME Code for Pressure Piping

Collectively under ASME B31– B31.1, Power Piping– B31.3, Process Piping– B31.5, Refrigeration Piping and Heat Transfer

Components– B31.9, Building Services Piping

Page 9: Piping Pressure testing

1/19/2009 9

Interpretations and Code Cases

Neither Interpretations nor Code Cases are mandatory parts of the Codes.Before trying to apply an Interpretation or Code Case, ensure that ABSA is amenable to its use.

Page 10: Piping Pressure testing

1/19/2009 10

Design Registration Requirements

PESR Sections 4, 14 & 16– Section 4 provides partial exemptions for

piping systems. It is not applicable for boiler external piping.

– Section 14 provides general requirements for design registrations and exemption for piping systems with Volume<500 l (0.5 m3)

– Section 16 provides requirements for piping design registration.

Page 11: Piping Pressure testing

1/19/2009 11

Piping Design Requirements

PESR 16(2) - The information referred to in subsection (1) must bear the stamp or seal of a professional engineer and the name of:

a) the owner of the design ; orb) the person who will be the manufacturer of

the pressure piping system.

Page 12: Piping Pressure testing

1/19/2009 12

Special design requirements

If piping design includes special design requirements, the submission needs to include them:

– Nonmetallic piping materials– Category M Fluid Service– High Pressure Piping– Safeguarding– Metallic Bellows Expansion Joints

Page 13: Piping Pressure testing

1/19/2009 13

Fittings in Pressure Piping Systems

PESR 16 & 17– Fittings must be registered (See Line 8 in

AB-96, General Engineering Requirements for Design & Registration of Pressure Piping Systems).

– Only fittings that are within the scope of registration may be used.

– Modifications or alteration of fittings is not allowed without re-registration of fitting design.

Page 14: Piping Pressure testing

1/19/2009 14

Safety Valve Requirements

PESR Section 38(3)

An owner of pressure equipment must ensure that the overpressure protection system is designed and maintained so that the maximum pressure in the pressure equipment does not exceed the prescribed limit of overpressure allowed in the applicable code declared in force by this Regulation.

PRD to open before pressure exceeds MAWP. See section 38(2).

Page 15: Piping Pressure testing

1/19/2009 15

Safety Valve Requirements (cont’d)

PESR Section 38(1)An owner of pressure equipment must ensure it has overpressure protection that is

(a ) a pressure relief valve that meets the requirements of the ASME Code;

(b) other means of overpressure protectionacceptable to the Administrator.

Page 16: Piping Pressure testing

1/19/2009 16

Safety Valve Requirements (cont’d)

Other means of overpressure protection acceptable to the Administrator

– Rupture discs. Rupture disks must be UD Stamped.

– Code Case 2211 (moved in Section VIII, Div. 1 UW- 140). Protection by system design is not recommended because the Safety Codes Act and Regulations do not allow for this type of protection.

– Allowance for occasional variations above design conditions (Section 102.2.4 of B31.1 or Section 302.2.4 of B31.3) is not in line with PESR 38(2).

Page 17: Piping Pressure testing

1/19/2009 17

Safety Valve Requirements (cont’d)

Proposal for the use of other means of overpressure protection must

– Include technical justification for the use of the Code Case.– Demonstrate compliance with the Code Case.– Include the acceptance from the owner. – Provide proposal for adding a warning plate on a vessel

protected by CC-2211. It needs to state that vessel isProtected by Code Case 2211 Designed for specific operation condition and any change in operating conditions require the owner’s and ABSA’s acceptance.

– Vessel drawings submitted for registration need to include Code case number note that the MDR will include CC-2211 under “Remarks”Warning plate information.

Page 18: Piping Pressure testing

1/19/2009 18

Safety Valve Requirements (cont’d)

Different requirements for safety valves in

– ASME BPVC, Section I and ASME B31.1. See PG67 through PG-73 of Section I and 107.8 and 122.1.7(D) of B31.1.

– ASME BPVC, Section VIII, Div.1 and ASME B31.3. See UG-126 through UG-133 of Section VIII and 322.6 of B31.3.

Page 19: Piping Pressure testing

1/19/2009 19

Safety Valve Requirements (cont’d)

PESR Section 16(1)(c)Piping design submission must include– A list of pressure relief devices.– The pressure relief set pressures.

PESR Section 16(1)(i)Additionally, design surveyors may ask for:– Drawing (flow or line diagram) number that

shows the safety valve.– A list of pressure vessels protected by this

safety valve.

Page 20: Piping Pressure testing

1/19/2009 20

Hydrostatic Test

PESR Section 30

(1) All pressure piping leak tests must be conducted using the hydrostatic method.

(2) Despite subsection (1), the Administrator may accept, for a specific pressure piping system,alternative test methods that are allowed in a codeor standard that is declared in force.

(3) A pressure piping system shall not be tested at atemperature that is colder than its minimum design temperature.

(4) When conducting pressure tests, the ductile-to-brittletransition temperature and the possibility of brittlefracture must be considered by the contractor.

Page 21: Piping Pressure testing

1/19/2009 21

Hydrostatic Test (cont’d)

Hydrostatic testing of pressure piping systems is

– to verify the integrity and leak tightness of the piping system (purpose).

– The last physical quality test in the fabrication process to verify the system is safe to operate.

– Performed prior to placing the system in service. – Preferred mainly due to safety considerations and

for ease of finding leaks. Should a component fail during a hydrostatic test, the energy stored in the water is quickly dissipated.

Page 22: Piping Pressure testing

1/19/2009 22

Hydrostatic Test (cont’d)

Requirements for Boiler External Piping (BEP)

– BEP shall be hydrostatically tested in accordance with PG-99 of ASME BPVC, Section I

Page 23: Piping Pressure testing

1/19/2009 23

Hydrostatic Test (cont’d)

Alternative test Methods

– Pneumatic test– Hydrostatic-Pneumatic Test– Initial Service Leak Test– Sensitive Leak Test– Alternative Test Methods in Lieu of

Hydrostatic Leak Testing for a Closure or Tie-In Welds

Page 24: Piping Pressure testing

1/19/2009 24

Hydrostatic Test (cont’d)

Alternative test Method Procedures Must

– Provide technical justification for not completing the hydrostatic pressure test.

– Provide a written test procedure that will fully address the technical and safety considerations for the test.

– Be acceptable to the owner. The owner of the piping system must review the circumstances and decide to accept the risk of not hydrostatically testing the piping system

– Be reviewed and accepted by ABSA.

Page 25: Piping Pressure testing

1/19/2009 25

Hydrostatic Test (cont’d)

Do not forget that– Hydrostatic test is mandatory according to

Section 38(1) of PESR 49/2006.– Piping system shall be tested to ensure system

integrity and tightness.– When considering any alternative to the

hydrostatic test prescribed under the Safety Codes Act, all risks and consequences must be carefully and thoroughly evaluated.

– If alternative test method is proposed, it must be acceptable to the owner & ABSA

– Alternative tests shall be performed by personnel other than those performing the production work.

Page 26: Piping Pressure testing

1/19/2009 26

Piping Modules, Closure Welds and Tie-in Welds

Submissions to Design Survey must have the following:– List of all of the identified welds– Description of the procedure– Acceptance Criteria per ASME B31.3 344.7.1 and

additionallya. misalignment tolerancesb. gap tolerancec. preheats (if applicable)d. any additional NDE (MP, LPI)e. any other acceptability criteria for inspectors to

ensure weld is properly constructed– Full Radiography requirements (or phased array in lieu of –

Code Case 181) per 345.9.1– Hydrostatic testing requirements for all connection modules

before the start of welding.– Statement by Professional Engineer on the submission that

flexibility analysis per B31.3 345.9.2 has been addressed.

Page 27: Piping Pressure testing

1/19/2009 27

Piping Modules, Closure Welds and Tie-in Welds

Field inspection requirements include the following:– The final Closure weld acceptance in the field

must be pre-determined on a travel sheet with set acceptance criteria prior to making the closure weld.

– The closure welds must be kept away from high stressed locations.

– Each side of the closure weld MUST be hydrostatically tested

– Start-up procedure must take into account that you have welds which have not been hydrostatically tested. Caution is requested here.

Page 28: Piping Pressure testing

1/19/2009 28

Impact Testing requirements

Section 323.2.2 of ASME B31.3 specifies the lower temperature limits for listed materials.

Section 323.2.3 of ASME B31.3 specifies requirements for unlisted materials.

Section 323.3 of ASME B31.3 specifies Impact testing Methods and Acceptance Criteria.

Page 29: Piping Pressure testing

1/19/2009 29

Impact Testing requirements

Example of pipe calculations:

Pipe: NPS 10 Sch 80, material A106-B (curve B - Table A-1)P=1480 psi T=100 deg. F MDMT = -20 deg. FS=20000 psi CA=0.125”tnom = 0.594” tmin =0.519”

treq ={(1480)*(10.75)/[2*(20000+(0.4)*(1480)]}+0.125treq =0.386 +0.125 = 0.511”Calculated stress in pipe is Sp =19598 psi

Per table 323.2.2A, MDMT is -2.5 deg.F for Tnom = 0.594”Stress ratio r=19598/20000=0.98Per table 323.2.2B temperature reduction is 2 deg.FThe adjusted MDMT is -2.5 -2 = -4.5 deg. F

Impact testing is required.

Page 30: Piping Pressure testing

1/19/2009 30

Use of Unlisted Materials

ASME B31.1– Unlisted materials can not be used for

boiler external piping (BEP) according to section 123.1.2.

– For non-BEP, unlisted materials may be used if they satisfy all five requirements (A through E) of section 123.1.2.

– ABSA will require the owner’s acceptance for use of unlisted materials in accordance with 123.1.2(D).

Page 31: Piping Pressure testing

1/19/2009 31

Use of Unlisted Materials (cont’d)

ASME B31.3– Allows the use of unlisted materials

according to section 323.1.2.– The allowable stresses of unlisted

materials shall be defined in accordance with section 302.3.2.

Page 32: Piping Pressure testing

1/19/2009 32

Skid Packages not shown in the Piping Design Submission

Submissions to Design Survey must have the following:– Scope of registration– Information who will register skid

packages if they are not shown in the submission.

– Who is responsible for the joints between skid lines and the rest of the piping.

Page 33: Piping Pressure testing

1/19/2009 33

Where do things go wrong?

Incomplete information in the submissionNo P. Eng. stamp on piping designsImproper application of - Pressure relief devices- Pressure piping testing requirements- Material specifications and flange classes- the low temperature rulesManual changes on drawings – improper revision practice Client’s failure to respond in a timely fashion

Page 34: Piping Pressure testing

1/19/2009 34

How can ABSA help?

We encourage pre-job meetings with EPC’s, owners, and suppliers for major projects to iron out areas that may be unclear (2 – 3 hours at ABSA’s head office)We are happy to answer phone or e-mail questions

Page 35: Piping Pressure testing

1/19/2009 35

How can you help?

Inform your vendors of the Alberta requirements.Keep in contact with your vendors to ensure that they are doing what they need to do to get their designs registered.Don’t permit shipment from the Manufacturer’s facility if there is no registration in place.

Page 36: Piping Pressure testing

1/19/2009 36

Selected Articles to Pressure Piping from “The Pressure News”

http://www.absa.ca/newsletter/default.aspx– Piping Systems Constructed Outside Alberta, Volume

7, Issue 3, Sep. 2002– Pressure Piping Construction Documents, Volume 9,

Issue 3, Sep. 2004.– Permit Requirements for the Construction of

Instrumentation Tubing Systems, Volume 13, Issue 3, Sep. 2008.

– Correction/Clarification Pressure Piping Systems (Threaded piping is treated similar to welded piping), Volume 7, Issue 3, Sep. 2002.

– Pressure Piping Not Over 0.5m3 In Capacity, Volume 8, Issue 2, June 2003.

– Plant Piping – Owner’s Responsibilities, Volume 5, Issue 4, Dec. 2000.

Page 37: Piping Pressure testing

1/19/2009 37

Selected Articles to Pressure Piping from “The Pressure News”

http://www.absa.ca/newsletter/default.aspx– Owner s Inspector must Inspect & Certify Piping Data

Report, Volume 13, Issue 3, Sep. 2008.– Failure of Low Pressure Piping, Volume 9, Issue 1,

Mar. 2004.– Special Considerations for Alternative Leak Testing for

Closure Welds of Pressure Piping Fabricated to ASME B31.3, Volume 9, Issue 3, Sep. 2004.

– Installation of Pressure Relief Valves , Volume 13, Issue 3, Sep. 2008.

– Isolation Valves In A Pressure Relief Path, Volume 10, Issue 3, Sep. 2005.

– Flare Lines and Flare Knockouts, Volume 9, Issue 3, Sep. 2003.

Page 38: Piping Pressure testing

1/19/2009 38

Selected Articles to Pressure Piping from “The Pressure News”

http://www.absa.ca/newsletter/default.aspx– Requirements for Boiler External Piping on ASME

Section I Power Boilers, Volume 10, Issue 3, Sep. 2005

– Pneumatic Test, Volume 7, Issue 2, June 2002.– Failure of 2˝

Y Strainer under Pneumatic Test,

Volume 10, Issue 1, June 2005.– Warning – Water Hammer Hazards, Volume 12,

Issue 2, June 2007.– Alert-Use of Registered Fittings, Volume 5, Issue

2, June 2000.– Alteration of Fittings, Volume 3, Issue 3, Sep.

1998.

Page 39: Piping Pressure testing

1/19/2009 39

Selected Articles to Pressure Piping from “The Pressure News”

http://www.absa.ca/newsletter/default.aspx– On Stream Leak Sealing of Flanges, Valves,

Volume 2, Issue 1, Feb. 1997– Positive Material Identification, Volume 11, Issue

4, Dec. 2006.– Alerts (Brass Valve Failure and Rig Boiler

Fatality), Volume 9, Issue 1, Mar. 2004.– Flange Gaskets (Incorrect specification and

installation), Volume 8, Issue 1, Mar. 2003.– Hydrostatic Testing can be Dangerous Too,

Volume 13, Issue 3, Sep. 2008.

Page 40: Piping Pressure testing

1/19/2009 40

Selected Information Bulletins & Alerts to Pressure Piping

http://www.absa.ca/IBIndex/default.aspx– Interpretation - Random Radiography for

designated lot of ASME B31.3 Piping, IB07-002– Pipe Nipple Failure, IB02-001– Brass Valve Failure in Power Boiler Service, IB04-

002– Alert to Pressure Equipment Owners and

Operators - Rig Boiler Fatality, IB04-003– Valve Failure (Stem came off due to improper

installation), IB04-005