Performance Assessment of Plant-Wide Control Systems

Embed Size (px)

Citation preview

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    1/13

    Performance Assessment of Plant-Wide Control Systems

    Document by:Bharadwaj

    Visit my website

    www.engineeringpapers.blogspot.comMore papers and Presentations available on above site

    Abstract: This paper addresses performance assessment of plant-wide control (PWC)

    systems, which is one of the important areas of PWC of industrial processes but has

    received very little attention in the past. Some of the performance measures in the literature

    are the steady-state disturbance sensitivity and the capacity-based economic approach.

    However, there are some limitations in the measures that have been proposed for

    performance assessment, from the plant-wide perspective. In this study, several measures

    based on plant dynamics are described and discussed for evaluating the performance of

    different PWC structures. These include overall process settling time based on absolute

    accumulation in the system, dynamic disturbance sensitivity, net variation from the nominal

    operating profit and deviation from the production target. These measures are then applied

    to two alternative control structures for a styrene monomer plant, in order to test their

    applicability. The results indicate that some of the presented measures are indeed effective

    for evaluating and comparing PWC structures.

    Keywords: Plant-wide control, Performance assessment, Settling time, Operating profit,

    Dynamic disturbance sensitivity, Deviation from the production target.

    Introduction

    PWC design is essential because of complex, integrated nature of many chemical plants.

    The development of a PWC system does not stop with the generation of the control

    structures. The dynamic performance of the alternative control structures generated must be

    evaluated in order to make the final control system selection. Thus, performance assessment

    of PWC systems is important but has not received much attention in the past, especially in

    the context of dynamic simulations.

    1

    http://www.engineeringpapers.blogspot.com/http://www.engineeringpapers.blogspot.com/
  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    2/13

    The presence of numerous combinations of controlled and manipulated variables in a

    process leads to many alternative control structures. In the preliminary steps of the control

    system development, steady-state and dynamic controllability measures such as relative gain

    array (RGA), condition number (CN), Neiderlinski Index (NI), singular value

    decomposition (SVD), etc. can be used for initial control structure screening. However, a

    few alternative control structures may still remain in the end, and more rigorous analysis is

    needed for the final selection to be made. Also, there is a possibility that measures like RGA

    and NI may fail, and result in poor closed loop performance, as has been proven in several

    case studies [1, 2]. These issues have led to the proposition of other performance measures

    that give more consistent results even for highly complex processes.

    Yi and Luyben [3] proposed a measure named steady-state disturbance sensitivity to

    screen alternative control structures. Control structures that require a large change inmanipulated variables to handle the disturbances are not recommended, as they are more

    prone to hit constraints and valve saturation limits. This measure can give us desirable

    results under normal circumstances, but the decision would be difficult to make in cases

    where the manipulated variable changes more for some disturbances and less for some other

    disturbances in one control structure as opposed to the other control structures. Also, the

    steady-state disturbance sensitivity does not consider the changes during the transient phase.

    Elliott and Luyben [4, 5] and Elliott et al. [6] devised a generic methodology called the

    capacity-based economic approach to compare and screen preliminary plant designs by

    quantifying both steady-state economics and dynamic controllability. They basically

    proposed a measure based on product quality regulation to measure the dynamic

    performance of alternative control structures. Specifically, they calculate the loss in plant

    capacity due to off-spec production. As with the previous measure, this approach is useful

    under some situations. However, it cannot be always applied as the off-spec product is

    assumed to be disposed, whereas the normal practice in industry is to recycle the off-spec

    product in order to avoid yield losses and additional cost of disposal. Also, product quality

    though important cannot be the only measure for evaluating the control system performance.

    The dynamic performance of all control loops in the whole plant has to be considered too.

    Keeping the above measures and limitations in mind, a new dynamic performance index

    called dynamic disturbance sensitivity (DDS) has been recently developed by Konda and

    Rangaiah [7]. DDS is equal to the sum of absolute accumulation of each and every

    component in the process since the onset of the disturbance(s). Konda and Rangaiah [7]

    have applied DDS to three different PWC structures of the toluene hydrodealkylation

    2

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    3/13

    (HDA) process and proven its effectiveness for PWC performance assessment and

    comparison. DDS measure offers several advantages over the other methods discussed

    above. However, one major drawback of it and many other measures is that they do not

    include the economic quantification of the dynamic performance.

    Hence, a new economic measure based on deviation from the production target (DPT) of

    the main product during the transient period is proposed in this study. In addition, two more

    performance measures are discussed. These are the net variation in the plant operating profit

    and the process settling time based on overall absolute component accumulation. The basic

    idea behind these measures and their development are discussed, together with the

    procedure for their computation. These measures are then applied to two different control

    structures of the styrene monomer plant in order to test their applicability and usefulness.

    The rest of the paper is organized as follows: the next section discusses the various performance measures, namely, the process settling time based on overall absolute

    component accumulation, DDS, the net variation in the plant operating profit and DPT. The

    subsequent section discusses the application of these measures to the styrene plant together

    with an analysis of the results. The conclusions are finally presented in the last section.

    Performance Measures for PWC Systems

    A few performance measures based on plant dynamics are presented in this section. Not

    much has been said or discussed on what constitutes a good performance measure. A

    performance measure must be comprehensive (to include transients and steady-state

    performance), consistent and robust (i.e., less affected by controller fine-tuning), able to

    differentiate control structures, simple (to define and compute), and also give some

    indication of the economics and control effort of the control system. A good measure should

    meet most or all of these features.

    Process Settling Time Based on Overall Absolute Component Accumulation

    Settling time is defined as the time required for the process output to reach and remain

    within certain (5% or 1%) of the final steady-state value of the process variable [8].

    While this definition pertains to a single control loop, the question in a plant-wide context is

    how to define the settling time of a highly integrated chemical process plant with many

    controlled variables and controllers. We propose to calculate settling time based on transient

    profile of absolute accumulation of all components in the plant, which is defined as follows:

    3

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    4/13

    +=n

    nConsumptioGenerationOutflowInflowonaccumulatiAbsolute

    1

    (1)

    where n is the total number of components in the system. The inflow and outflow refers to

    the component flows in the input and output streams of the plant at any time. The settlingtime thus calculated indicates the time taken by the PWC system to bring the overall process

    to the steady state after the onset of the disturbance(s).

    Dynamic Disturbance Sensitivity (DDS)

    DDS is a new dynamic performance index developed by Konda and Rangaiah [7]. The basic

    idea is to make effective use of rigorous process simulators in the performance assessment

    of PWC systems. DDS makes use of the strong correlation between the overall control

    system performance and the sum of the individual component accumulations. When a

    process is affected by a disturbance, all the process variables go though different transients

    and ultimately reach steady state only when the overall accumulation of all the components

    in the plant becomes negligible. The time integral of sum of absolute accumulation of all

    components in the plant is a measure of the PWC system performance. Accordingly, DDS is

    defined as

    ( ) dticomponentofonaccumulatiabsoluteDDSst

    t ntoi = =

    =

    0 1

    (2)

    where ts is the time taken for the process to reach steady state. Obviously, a smaller value of

    DDS indicates better control.

    Net Variation in the Plant Operating Profit

    A profit function has been used in PWC methodologies for steady-state optimization. An

    example is the self-optimizing control procedure of Skogestad [9]. We propose to compute

    the operating profit during the transient state in the presence of disturbances. As it is

    possible that the operating profit may settle at a different value due to changes in the

    production rate, we propose using profit per unit production rate of the main product. This

    goes back to almost the same value at the final steady state conditions (see Figure 1). The

    net area gives an indication of the net variation in the plant operating profit. A positive

    number indicates an overall increase in the plant operating profit whereas a negative number

    indicates otherwise. A control system can be taken to be performing well if the computed

    area is either equal to or greater than zero.

    4

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    5/13

    Time

    US$/kgP

    roduct

    Steady-State

    Profit

    Positive Area

    Negative Area

    Fig. 1. Transient profile of profit per unit production rate due to a disturbance

    Deviation from the Production Target (DPT)

    There could be one possible drawback with the computation of the net variation in plant

    operating profit. It is possible to obtain a higher value of the computed area for an inferior

    control structure primarily due to the large magnitude of the initial production rate transient.

    This issue is discussed in detail later in the next section. Hence, to overcome this

    shortcoming, we propose an indirect economic measure based on the production rate. The

    idea is to compute the DPT (of the main product) during the transient state by computing the

    net area as shown in Figure 2. DPT is defined as

    ( ) dtrateproductionettrateproductionactualDPTst

    t

    =

    =0

    arg (3)

    When the plant management wants to increase (decrease) the production rate, the new

    production target should be achieved at the earliest and any deviation from it is undesirable.

    So, total deviation from the production rate during the transient can be used as a

    performance measure of the control system. This can be calculated by the area under the

    transient in Figure 2 for a production rate change. On the other hand, when the plant is

    subjected to other unexpected disturbances, the computation of area is done based on the

    original production rate. The effectiveness of this measure in indicating relative control

    system performance is illustrated in the next section.

    5

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    6/13

    Time

    ProductionRate

    Over production

    Production ra

    Initial production rate

    Under Production

    Fig. 2. Production rate transient in the presence of disturbance(s)

    Application of the Performance Measures to the Styrene Monomer Plant

    Process Description and Simulation

    In the styrene process (Figure 3), fresh ethyl benzene (EB) and a part of the low-pressure

    steam (LPS) are mixed and then pre-heated in a feed-effluent heat exchanger (FEHE) using

    the reactor effluent stream. The remaining LPS is superheated in a furnace to 700-850C,

    and then mixed with the pre-heated mixture to attain a temperature of around 650C. It is

    then fed to two adiabatic plug-flow reactors (PFRs), in series with a heater in between, for

    the production of styrene. The six main reactions that occur in the reactors are as follows:

    22563256HCHCHHCCHCHHC + (4)

    42663256HCHCCHCHHC + (5)

    435623256CHCHHCHCHCHHC ++ (6)

    2422 422 HCOHCOH ++ (7)

    242 3HCOCHOH ++ (8)

    222 HCOCOOH ++ (9)

    The reactor effluent is cooled in the FEHE and then in a cooler before being sent to the

    three-phase separator, where the light gases are removed as the light products and water is

    removed as the heavy product. The intermediate organic layer is sent to two distillation

    columns for styrene separation from the other components. In the first column (i.e., product

    column), operating under vacuum to prevent styrene polymerization, styrene is removed as

    the bottom product, and the top product is sent to a second column (i.e., recycle column) to

    6

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    7/13

    separate un-reacted EB from the by-products, toluene and benzene. The un-reacted EB is

    then recycled back.

    For simulating the styrene plant in HYSYS, Peng-Robinson equation of state is chosen as

    it is very reliable for predicting the properties of hydrocarbon components over a wide range

    of conditions and appropriate for the components in the styrene process. The steady-state

    model of the styrene process is developed and optimized in HYSYS. The optimal

    conversion is 66.6%. The distillation columns are modeled by rigorous tray-by-tray

    calculations. Preliminary estimates of the number of trays and feed tray location for each

    column in the process are obtained by using the shortcut column in HYSYS, and then

    optimized using the rigorous calculations. The final steady-state flowsheet developed is

    shown in Figure 3.

    Dynamic Simulation of the Selected Control Structures

    Four different control structures have been recently developed for the styrene monomer

    plant [10]. We consider two of the control structures here; these are summarized in Table 1.

    HS is the control structure developed using the heuristics procedure of Luyben et al. [11].

    One of the characteristic features of this procedure is to control a flow somewhere in the

    recycle loop supposedly to overcome the snowball effect. IF is the control structure

    developed using the integrated framework of simulation and heuristics [12]. One of the main

    features of this procedure is the detailed analysis of the effects of recycle in order to

    overcome its negative impact on control system performance.

    There are several main differences between the two control structures in Table 1. Firstly,

    throughput manipulation is achieved by changing EB feed flow in IF, while it is achieved by

    changing total EB flow (feed plus recycle) in HS. Secondly, the recycle flow is explicitly

    fixed in HS; this is achieved by controlling the total feed flow. Thirdly, IF utilizes the

    conversion controller as a result of the detailed analysis of the effects of recycle. Finally, the

    number of control loops is different: HS has 20 feedback control loops, while IF has 21

    control loops, 2 of which form a cascade loop. The two control structures are implemented

    in HYSYS dynamic mode; the controller tuning parameters are also given in Table 1.

    7

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    8/13

    Fig. 3. Steady-state HYSYS flowsheet of the styrene monomer process.

    Results and Discussion

    Both the control systems are analyzed for their relative performance for production rate and

    feed composition disturbances. The dynamic performance measures discussed in the

    previous section are employed to analyze their performance.

    Overall Process Settling Time

    Settling times based on overall absolute component accumulation are computed for both the

    control systems and presented in Table 2. The criterion for computing the settling time is

    that the overall absolute component accumulation should be below 1 kmol/h (= 0.84% of the

    styrene production rate of 120 kmol/h). The results in Table 2 show that IF performs better

    in terms of the settling times, for the disturbances studied. This means that this structure is

    able to attenuate the effect of disturbances quickly with smaller settling time for the

    disturbances considered. The overall absolute component accumulation is a good basis for

    computing settling time as it takes into account the entire plant performance during the

    transient state and not just individual process variables or control loops.

    8

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    9/13

    Table 1. HS and IF Control Structures for Styrene Plant

    Controlled Variable

    (See Figure 3 for

    Abbreviations)

    Manipulated Variable with Controller Parameters:

    Kc (%/%), Ti (min) in Brackets

    HS IF

    Reaction Section

    Total EB Flow EB Feed Flow (0.5, 0.3) -EB Feed Flow - EB Feed Flow (0.5, 0.3)

    PFR1 Inlet Steam/EB Ratio Steam Feed Flow (0.36, 0.035)

    LP1 Flow LP1 Flow (0.5, 0.3)

    EB Conversion - PFR1 Inlet T SP (0.1, 0.5)

    PFR1 Inlet Temperature Furnace Duty (0.11, 0.088)

    PFR2 Inlet Temperature Intermediate Heater Duty (0.54, 0.087)

    Phase Sep Temperature Cooling Water Flow (0.13, 0.14)

    Phase Sep Pressure Lights Flow (2, 10)

    Phase Sep Liquid % Level Organic Flow (18.8, 0.45)

    Phase Sep Aqueous %Level Water Flow (1.31, 0.12)

    Product Column

    Condenser Pressure Condenser Duty (2, 10)

    Condenser Level Distillate Flow (0.8) Distillate Flow (2)

    Reboiler Level Bottoms Flow (0.5) Bottoms Flow (1.5)

    Top Styrene Composition - Reflux Flow (0.5, 27.3)

    Reflux Flow Reflux Flow (0.5, 0.3) -

    Bottoms EB Composition Reboiler Duty (0.12, 108) Reboiler Duty (0.23, 54)

    Vent Flow Compressor Duty (0.5, 0.3)

    Recycle Column

    Condenser Pressure Condenser Duty (1.5, 30) Condenser Duty (2, 20)

    Condenser Level Reflux Flow (1.2) Reflux Flow (2)

    Reboiler Level Bottoms Flow (2)

    Top EB Composition Distillate Flow (0.43, 73.5)

    Bottoms Toluene Composition Reboiler Duty (6.54, 1.05)

    Table 2. Process Settling Times for HS and IF Control Structures based on Overall

    Absolute Accumulation Profile

    No. Disturbance Magnitude

    Settling Time (minutes) for

    Overall Absolute Accumulation

    HS IF

    d1

    Production Rate

    -5% 710 345

    d2 +5% 700 335

    d3 -20% 865 455

    d4 Feed Composition -2% 595 245

    9

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    10/13

    Dynamic Disturbance Sensitivity (DDS)

    Since the computation of DDS is also based on overall component accumulation as

    discussed earlier, it is imperative that the results based on both DDS and settling time based

    on accumulation be compared. Accordingly, DDS values are computed and presented in

    Table 3. Again, IF shows better performance than HS in terms of DDS. However, one major

    difference between settling time and DDS is the ability of the latter to track the transient

    behavior of the process variables. On the other hand, settling time ignores the magnitude of

    the absolute component accumulation during the transient state, and hence is not a

    comprehensive measure compared to DDS.

    Table 3. DDS Values for HS and IF Control Structures

    No. Disturbance Magnitude DDS (kmol)HS IF

    d1

    Production Rate

    -5% 43 19

    d2 +5% 44 18

    d3 -20% 177 74

    d4 Feed Composition -2% 21 11

    Net Variation in the Plant Operating Profit

    The data for the profit function per unit production rate is collected and the net area

    indicated in Figure 1 is computed for both the control structures. This area that gives an

    indication of the net variation in the plant operating profit, is given in Table 4. For easier

    understanding, the net variation in profit per tonne of styrene is computed for the duration

    for which the simulation is run in all cases (2000 minutes, i.e., approximately 1.4 days) by

    the following equation:

    tonne

    kg

    hrstyrenekg

    hrVariationNet

    styrenetonneVariationNet

    1000

    min2000

    1min60$.$

    =

    (10)

    These values are also given in Table 4. A positive value indicates profit increase and

    vice-versa, and so a profit increase indicates better performance. As shown in Table 4, HS

    shows better performance for d1 and d3, even though the other performance measures

    applied so far indicate otherwise. This can be attributed to the greater production of styrene

    during the transient state (as a result of larger fluctuations in the process variables) which is

    manifested in higher profit. Actually, when the objective of the plant operator is to decrease

    styrene production in the case of d1 and d3, a higher amount of styrene produced during the

    10

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    11/13

    transient state is undesirable. The reason for this is that any excess amount of styrene

    produced cannot be sold easily given the lower demand. Thus, there is a major drawback

    with this economic measure as it does not take into account the over-produced amount of

    styrene during the transient state. Hence, as discussed in the previous section, an alternative

    economic measure (DPT) is evaluated next.

    Table 4. Net Variation in the Plant Operating Profit with Units of (a) $/(kg of

    Styrene/hr) and (b) $/(tonne of Styrene), for HS and IF Control Structures

    No. Disturbance MagnitudeNet Variation ($/kg/hr) Net Variation ($/tonne)

    HS IF HS IF

    d1

    Production Rate

    -5% 0.20 0.13 5.9 4.0

    d2 +5% -0.21 -0.12 -6.2 -3.7

    d3 -20% 0.76 0.50 22.7 15.1d4 Feed Composition -2% -0.013 0.00 -0.38 0.07

    Note: In this table, the largest value of the net variation for each disturbance is shown with grey background.

    Deviation from the Production Target (DPT) of Styrene

    The DPT of styrene over the duration of the total simulation time (2000 min) is computed.

    The results presented in Table 5 give a clear picture. For d1 to d3, the target production rate

    in equation 3 is the final production rate at the new steady-state. For d4, the target

    production rate in equation 3 is the original production rate. A positive value of DPTindicates over production, while a negative value indicates under production. Since both

    over and under production is undesirable, smaller (absolute) deviation from the desired

    production rate target indicates better performance. In general, IF shows better performance

    for all disturbances except d4. This means that a smaller amount of styrene over/under

    production is achieved with this control system. This translates into a lower loss due to

    unwanted amount of product being produced. Interestingly, IF shows poorer performance

    for d4. This could be due to the fixing of EB feed flow in IF, whereas it is allowed to vary in

    HS. For d4, this results in a 2% decrease in the fresh EB flow in IF as opposed to 0.75%

    decrease in the case of HS. The greater decrease in the fresh EB flow is manifested as a

    larger DPT as the styrene production rate is directly proportional to the fresh EB flow rate.

    General Assessment of the Performance Measures

    The performance measures presented in the previous section have been evaluated on two

    different control structures for the styrene plant in this section. In general, control structure

    IF performs better in terms of most of the measures except for the net variation in the plant

    11

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    12/13

    operating profit, where a clear picture does not emerge from the results. However, as

    discussed earlier, this measure does not indicate the superior performance of a control

    structure. Of all the measures presented, we recommend DDS (as it gives an indication of

    the ability of the control system in handling disturbances dynamically) and DPT (as it gives

    an indication of the economic performance of the control system).

    Table 5. DPT of Styrene for HS and IF Control Structures

    No. Disturbance MagnitudeDPT of Styrene (kg)

    HS IF

    d1

    Production Rate

    -5% 2329 1558

    d2 +5% -2275 -1376

    d3 -20% 8844 5656

    d4 Feed Composition -2% -2558 -5947

    Note: In this table, the smallest DPT of styrene for each disturbance is shown with grey background.

    A typical plant with a control system has many process and operating variables that have

    to be monitored, and it can be quite time-consuming and difficult to analyze and compare

    the numerous profiles of the different alternative control systems. Besides, such qualitative

    analysis is subjective. Hence, quantitative measures based on process dynamics such as

    presented here enable effective and easy analysis with minimal computational effort. All the

    calculations presented can be easily automated and done using a spreadsheet.

    Conclusions

    Several performance measures based on plant dynamics for assessing PWC systems have

    been presented in this work. The main aim of this is to present easier and more reliable

    quantitative tools for assessing different PWC structures. The feasibility of using these

    measures for performance assessment of PWC systems has been illustrated on two

    alternative control structures for the styrene plant. In particular, DDS and DPT are

    recommended in order to get an overall picture of PWC system performance covering

    various aspects.

    References

    1. He, M.J. and Cai, W.J., New Criterion for Control-Loop Configuration of Multivariable

    Processes,Ind. Eng. Chem. Res., 43, pp. 7057-7064 (2004).

    2. Xiong, Q., Cai, W.J. and He, M.J., A Practical Loop Pairing Criterion for Multivariable

    Processes,J. Proc. Cont., 15, pp. 741-747 (2005).

    12

  • 8/3/2019 Performance Assessment of Plant-Wide Control Systems

    13/13

    3. Yi, C.K. and Luyben, W.L., Evaluation of Plant-Wide Control Structures by Steady-

    State Disturbance Sensitivity Analysis, Ind. Eng. Chem. Res., 34, pp. 2393-2405

    (1995).

    4. Elliott, T.R. and Luyben, W.L., Capacity-Based Economic Approach for the

    Quantitative Assessment of Process Controllability during the Conceptual Design

    Stage,Ind. Eng. Chem. Res., 34, pp. 3907-3915 (1995).

    5. Elliott, T.R. and Luyben, W.L., Quantitative Assessment of Controllability during the

    Design of a Ternary System with Two Recycle Streams, Ind. Eng. Chem. Res.,35, pp.

    3470-3479 (1996).

    6. Elliott, T.R., Luyben, W.L. and Luyben, M.L., Application of the Capacity-Based

    Economic Approach to an Industrial-Scale Process,Ind. Eng. Chem. Res., 36, pp. 1727-

    1737 (1997).7. Konda, N.V.S.N.M. and Rangaiah, G.P., Performance Assessment of Plant-Wide

    Control Systems of Industrial Processes, Ind. Eng. Chem. Res., 46, pp. 1220-1231

    (2007).

    8. Seborg, E., Edgar, T.F. and Mellichamp, D.A.,Process Dynamics and Control, Wiley,

    New Jersey (2004).

    9. Skogestad, S., Control Structure Design for Complete Chemical Plants, Comput.

    Chem. Eng., 28, pp. 219-234 (2004).

    10. Vasudevan, S., Rangaiah, G.P., Konda, N.V.S.N.M. and Tay, W.H., Application and

    Evaluation of Three Methodologies for Plant-Wide Control of the Styrene Monomer

    Plant,Ind. Eng. Chem. Res., In press (2009).

    11. Luyben, W.L., Tyreus, B.D. and Luyben, M.L.,Plant-Wide Process Control, McGraw-

    Hill, New York (1998).

    12. Konda, N.V.S.N.M., Rangaiah, G.P. and Krishnaswamy, P.R., Plant-Wide Control of

    Industrial Processes: An Integrated Framework of Simulation and Heuristics,Ind. Eng.

    Chem. Res., 44, pp. 8300-8313 (2005).

    13