Upload
bharadwaj-santhosh
View
219
Download
0
Embed Size (px)
Citation preview
8/3/2019 Performance Assessment of Plant-Wide Control Systems
1/13
Performance Assessment of Plant-Wide Control Systems
Document by:Bharadwaj
Visit my website
www.engineeringpapers.blogspot.comMore papers and Presentations available on above site
Abstract: This paper addresses performance assessment of plant-wide control (PWC)
systems, which is one of the important areas of PWC of industrial processes but has
received very little attention in the past. Some of the performance measures in the literature
are the steady-state disturbance sensitivity and the capacity-based economic approach.
However, there are some limitations in the measures that have been proposed for
performance assessment, from the plant-wide perspective. In this study, several measures
based on plant dynamics are described and discussed for evaluating the performance of
different PWC structures. These include overall process settling time based on absolute
accumulation in the system, dynamic disturbance sensitivity, net variation from the nominal
operating profit and deviation from the production target. These measures are then applied
to two alternative control structures for a styrene monomer plant, in order to test their
applicability. The results indicate that some of the presented measures are indeed effective
for evaluating and comparing PWC structures.
Keywords: Plant-wide control, Performance assessment, Settling time, Operating profit,
Dynamic disturbance sensitivity, Deviation from the production target.
Introduction
PWC design is essential because of complex, integrated nature of many chemical plants.
The development of a PWC system does not stop with the generation of the control
structures. The dynamic performance of the alternative control structures generated must be
evaluated in order to make the final control system selection. Thus, performance assessment
of PWC systems is important but has not received much attention in the past, especially in
the context of dynamic simulations.
1
http://www.engineeringpapers.blogspot.com/http://www.engineeringpapers.blogspot.com/8/3/2019 Performance Assessment of Plant-Wide Control Systems
2/13
The presence of numerous combinations of controlled and manipulated variables in a
process leads to many alternative control structures. In the preliminary steps of the control
system development, steady-state and dynamic controllability measures such as relative gain
array (RGA), condition number (CN), Neiderlinski Index (NI), singular value
decomposition (SVD), etc. can be used for initial control structure screening. However, a
few alternative control structures may still remain in the end, and more rigorous analysis is
needed for the final selection to be made. Also, there is a possibility that measures like RGA
and NI may fail, and result in poor closed loop performance, as has been proven in several
case studies [1, 2]. These issues have led to the proposition of other performance measures
that give more consistent results even for highly complex processes.
Yi and Luyben [3] proposed a measure named steady-state disturbance sensitivity to
screen alternative control structures. Control structures that require a large change inmanipulated variables to handle the disturbances are not recommended, as they are more
prone to hit constraints and valve saturation limits. This measure can give us desirable
results under normal circumstances, but the decision would be difficult to make in cases
where the manipulated variable changes more for some disturbances and less for some other
disturbances in one control structure as opposed to the other control structures. Also, the
steady-state disturbance sensitivity does not consider the changes during the transient phase.
Elliott and Luyben [4, 5] and Elliott et al. [6] devised a generic methodology called the
capacity-based economic approach to compare and screen preliminary plant designs by
quantifying both steady-state economics and dynamic controllability. They basically
proposed a measure based on product quality regulation to measure the dynamic
performance of alternative control structures. Specifically, they calculate the loss in plant
capacity due to off-spec production. As with the previous measure, this approach is useful
under some situations. However, it cannot be always applied as the off-spec product is
assumed to be disposed, whereas the normal practice in industry is to recycle the off-spec
product in order to avoid yield losses and additional cost of disposal. Also, product quality
though important cannot be the only measure for evaluating the control system performance.
The dynamic performance of all control loops in the whole plant has to be considered too.
Keeping the above measures and limitations in mind, a new dynamic performance index
called dynamic disturbance sensitivity (DDS) has been recently developed by Konda and
Rangaiah [7]. DDS is equal to the sum of absolute accumulation of each and every
component in the process since the onset of the disturbance(s). Konda and Rangaiah [7]
have applied DDS to three different PWC structures of the toluene hydrodealkylation
2
8/3/2019 Performance Assessment of Plant-Wide Control Systems
3/13
(HDA) process and proven its effectiveness for PWC performance assessment and
comparison. DDS measure offers several advantages over the other methods discussed
above. However, one major drawback of it and many other measures is that they do not
include the economic quantification of the dynamic performance.
Hence, a new economic measure based on deviation from the production target (DPT) of
the main product during the transient period is proposed in this study. In addition, two more
performance measures are discussed. These are the net variation in the plant operating profit
and the process settling time based on overall absolute component accumulation. The basic
idea behind these measures and their development are discussed, together with the
procedure for their computation. These measures are then applied to two different control
structures of the styrene monomer plant in order to test their applicability and usefulness.
The rest of the paper is organized as follows: the next section discusses the various performance measures, namely, the process settling time based on overall absolute
component accumulation, DDS, the net variation in the plant operating profit and DPT. The
subsequent section discusses the application of these measures to the styrene plant together
with an analysis of the results. The conclusions are finally presented in the last section.
Performance Measures for PWC Systems
A few performance measures based on plant dynamics are presented in this section. Not
much has been said or discussed on what constitutes a good performance measure. A
performance measure must be comprehensive (to include transients and steady-state
performance), consistent and robust (i.e., less affected by controller fine-tuning), able to
differentiate control structures, simple (to define and compute), and also give some
indication of the economics and control effort of the control system. A good measure should
meet most or all of these features.
Process Settling Time Based on Overall Absolute Component Accumulation
Settling time is defined as the time required for the process output to reach and remain
within certain (5% or 1%) of the final steady-state value of the process variable [8].
While this definition pertains to a single control loop, the question in a plant-wide context is
how to define the settling time of a highly integrated chemical process plant with many
controlled variables and controllers. We propose to calculate settling time based on transient
profile of absolute accumulation of all components in the plant, which is defined as follows:
3
8/3/2019 Performance Assessment of Plant-Wide Control Systems
4/13
+=n
nConsumptioGenerationOutflowInflowonaccumulatiAbsolute
1
(1)
where n is the total number of components in the system. The inflow and outflow refers to
the component flows in the input and output streams of the plant at any time. The settlingtime thus calculated indicates the time taken by the PWC system to bring the overall process
to the steady state after the onset of the disturbance(s).
Dynamic Disturbance Sensitivity (DDS)
DDS is a new dynamic performance index developed by Konda and Rangaiah [7]. The basic
idea is to make effective use of rigorous process simulators in the performance assessment
of PWC systems. DDS makes use of the strong correlation between the overall control
system performance and the sum of the individual component accumulations. When a
process is affected by a disturbance, all the process variables go though different transients
and ultimately reach steady state only when the overall accumulation of all the components
in the plant becomes negligible. The time integral of sum of absolute accumulation of all
components in the plant is a measure of the PWC system performance. Accordingly, DDS is
defined as
( ) dticomponentofonaccumulatiabsoluteDDSst
t ntoi = =
=
0 1
(2)
where ts is the time taken for the process to reach steady state. Obviously, a smaller value of
DDS indicates better control.
Net Variation in the Plant Operating Profit
A profit function has been used in PWC methodologies for steady-state optimization. An
example is the self-optimizing control procedure of Skogestad [9]. We propose to compute
the operating profit during the transient state in the presence of disturbances. As it is
possible that the operating profit may settle at a different value due to changes in the
production rate, we propose using profit per unit production rate of the main product. This
goes back to almost the same value at the final steady state conditions (see Figure 1). The
net area gives an indication of the net variation in the plant operating profit. A positive
number indicates an overall increase in the plant operating profit whereas a negative number
indicates otherwise. A control system can be taken to be performing well if the computed
area is either equal to or greater than zero.
4
8/3/2019 Performance Assessment of Plant-Wide Control Systems
5/13
Time
US$/kgP
roduct
Steady-State
Profit
Positive Area
Negative Area
Fig. 1. Transient profile of profit per unit production rate due to a disturbance
Deviation from the Production Target (DPT)
There could be one possible drawback with the computation of the net variation in plant
operating profit. It is possible to obtain a higher value of the computed area for an inferior
control structure primarily due to the large magnitude of the initial production rate transient.
This issue is discussed in detail later in the next section. Hence, to overcome this
shortcoming, we propose an indirect economic measure based on the production rate. The
idea is to compute the DPT (of the main product) during the transient state by computing the
net area as shown in Figure 2. DPT is defined as
( ) dtrateproductionettrateproductionactualDPTst
t
=
=0
arg (3)
When the plant management wants to increase (decrease) the production rate, the new
production target should be achieved at the earliest and any deviation from it is undesirable.
So, total deviation from the production rate during the transient can be used as a
performance measure of the control system. This can be calculated by the area under the
transient in Figure 2 for a production rate change. On the other hand, when the plant is
subjected to other unexpected disturbances, the computation of area is done based on the
original production rate. The effectiveness of this measure in indicating relative control
system performance is illustrated in the next section.
5
8/3/2019 Performance Assessment of Plant-Wide Control Systems
6/13
Time
ProductionRate
Over production
Production ra
Initial production rate
Under Production
Fig. 2. Production rate transient in the presence of disturbance(s)
Application of the Performance Measures to the Styrene Monomer Plant
Process Description and Simulation
In the styrene process (Figure 3), fresh ethyl benzene (EB) and a part of the low-pressure
steam (LPS) are mixed and then pre-heated in a feed-effluent heat exchanger (FEHE) using
the reactor effluent stream. The remaining LPS is superheated in a furnace to 700-850C,
and then mixed with the pre-heated mixture to attain a temperature of around 650C. It is
then fed to two adiabatic plug-flow reactors (PFRs), in series with a heater in between, for
the production of styrene. The six main reactions that occur in the reactors are as follows:
22563256HCHCHHCCHCHHC + (4)
42663256HCHCCHCHHC + (5)
435623256CHCHHCHCHCHHC ++ (6)
2422 422 HCOHCOH ++ (7)
242 3HCOCHOH ++ (8)
222 HCOCOOH ++ (9)
The reactor effluent is cooled in the FEHE and then in a cooler before being sent to the
three-phase separator, where the light gases are removed as the light products and water is
removed as the heavy product. The intermediate organic layer is sent to two distillation
columns for styrene separation from the other components. In the first column (i.e., product
column), operating under vacuum to prevent styrene polymerization, styrene is removed as
the bottom product, and the top product is sent to a second column (i.e., recycle column) to
6
8/3/2019 Performance Assessment of Plant-Wide Control Systems
7/13
separate un-reacted EB from the by-products, toluene and benzene. The un-reacted EB is
then recycled back.
For simulating the styrene plant in HYSYS, Peng-Robinson equation of state is chosen as
it is very reliable for predicting the properties of hydrocarbon components over a wide range
of conditions and appropriate for the components in the styrene process. The steady-state
model of the styrene process is developed and optimized in HYSYS. The optimal
conversion is 66.6%. The distillation columns are modeled by rigorous tray-by-tray
calculations. Preliminary estimates of the number of trays and feed tray location for each
column in the process are obtained by using the shortcut column in HYSYS, and then
optimized using the rigorous calculations. The final steady-state flowsheet developed is
shown in Figure 3.
Dynamic Simulation of the Selected Control Structures
Four different control structures have been recently developed for the styrene monomer
plant [10]. We consider two of the control structures here; these are summarized in Table 1.
HS is the control structure developed using the heuristics procedure of Luyben et al. [11].
One of the characteristic features of this procedure is to control a flow somewhere in the
recycle loop supposedly to overcome the snowball effect. IF is the control structure
developed using the integrated framework of simulation and heuristics [12]. One of the main
features of this procedure is the detailed analysis of the effects of recycle in order to
overcome its negative impact on control system performance.
There are several main differences between the two control structures in Table 1. Firstly,
throughput manipulation is achieved by changing EB feed flow in IF, while it is achieved by
changing total EB flow (feed plus recycle) in HS. Secondly, the recycle flow is explicitly
fixed in HS; this is achieved by controlling the total feed flow. Thirdly, IF utilizes the
conversion controller as a result of the detailed analysis of the effects of recycle. Finally, the
number of control loops is different: HS has 20 feedback control loops, while IF has 21
control loops, 2 of which form a cascade loop. The two control structures are implemented
in HYSYS dynamic mode; the controller tuning parameters are also given in Table 1.
7
8/3/2019 Performance Assessment of Plant-Wide Control Systems
8/13
Fig. 3. Steady-state HYSYS flowsheet of the styrene monomer process.
Results and Discussion
Both the control systems are analyzed for their relative performance for production rate and
feed composition disturbances. The dynamic performance measures discussed in the
previous section are employed to analyze their performance.
Overall Process Settling Time
Settling times based on overall absolute component accumulation are computed for both the
control systems and presented in Table 2. The criterion for computing the settling time is
that the overall absolute component accumulation should be below 1 kmol/h (= 0.84% of the
styrene production rate of 120 kmol/h). The results in Table 2 show that IF performs better
in terms of the settling times, for the disturbances studied. This means that this structure is
able to attenuate the effect of disturbances quickly with smaller settling time for the
disturbances considered. The overall absolute component accumulation is a good basis for
computing settling time as it takes into account the entire plant performance during the
transient state and not just individual process variables or control loops.
8
8/3/2019 Performance Assessment of Plant-Wide Control Systems
9/13
Table 1. HS and IF Control Structures for Styrene Plant
Controlled Variable
(See Figure 3 for
Abbreviations)
Manipulated Variable with Controller Parameters:
Kc (%/%), Ti (min) in Brackets
HS IF
Reaction Section
Total EB Flow EB Feed Flow (0.5, 0.3) -EB Feed Flow - EB Feed Flow (0.5, 0.3)
PFR1 Inlet Steam/EB Ratio Steam Feed Flow (0.36, 0.035)
LP1 Flow LP1 Flow (0.5, 0.3)
EB Conversion - PFR1 Inlet T SP (0.1, 0.5)
PFR1 Inlet Temperature Furnace Duty (0.11, 0.088)
PFR2 Inlet Temperature Intermediate Heater Duty (0.54, 0.087)
Phase Sep Temperature Cooling Water Flow (0.13, 0.14)
Phase Sep Pressure Lights Flow (2, 10)
Phase Sep Liquid % Level Organic Flow (18.8, 0.45)
Phase Sep Aqueous %Level Water Flow (1.31, 0.12)
Product Column
Condenser Pressure Condenser Duty (2, 10)
Condenser Level Distillate Flow (0.8) Distillate Flow (2)
Reboiler Level Bottoms Flow (0.5) Bottoms Flow (1.5)
Top Styrene Composition - Reflux Flow (0.5, 27.3)
Reflux Flow Reflux Flow (0.5, 0.3) -
Bottoms EB Composition Reboiler Duty (0.12, 108) Reboiler Duty (0.23, 54)
Vent Flow Compressor Duty (0.5, 0.3)
Recycle Column
Condenser Pressure Condenser Duty (1.5, 30) Condenser Duty (2, 20)
Condenser Level Reflux Flow (1.2) Reflux Flow (2)
Reboiler Level Bottoms Flow (2)
Top EB Composition Distillate Flow (0.43, 73.5)
Bottoms Toluene Composition Reboiler Duty (6.54, 1.05)
Table 2. Process Settling Times for HS and IF Control Structures based on Overall
Absolute Accumulation Profile
No. Disturbance Magnitude
Settling Time (minutes) for
Overall Absolute Accumulation
HS IF
d1
Production Rate
-5% 710 345
d2 +5% 700 335
d3 -20% 865 455
d4 Feed Composition -2% 595 245
9
8/3/2019 Performance Assessment of Plant-Wide Control Systems
10/13
Dynamic Disturbance Sensitivity (DDS)
Since the computation of DDS is also based on overall component accumulation as
discussed earlier, it is imperative that the results based on both DDS and settling time based
on accumulation be compared. Accordingly, DDS values are computed and presented in
Table 3. Again, IF shows better performance than HS in terms of DDS. However, one major
difference between settling time and DDS is the ability of the latter to track the transient
behavior of the process variables. On the other hand, settling time ignores the magnitude of
the absolute component accumulation during the transient state, and hence is not a
comprehensive measure compared to DDS.
Table 3. DDS Values for HS and IF Control Structures
No. Disturbance Magnitude DDS (kmol)HS IF
d1
Production Rate
-5% 43 19
d2 +5% 44 18
d3 -20% 177 74
d4 Feed Composition -2% 21 11
Net Variation in the Plant Operating Profit
The data for the profit function per unit production rate is collected and the net area
indicated in Figure 1 is computed for both the control structures. This area that gives an
indication of the net variation in the plant operating profit, is given in Table 4. For easier
understanding, the net variation in profit per tonne of styrene is computed for the duration
for which the simulation is run in all cases (2000 minutes, i.e., approximately 1.4 days) by
the following equation:
tonne
kg
hrstyrenekg
hrVariationNet
styrenetonneVariationNet
1000
min2000
1min60$.$
=
(10)
These values are also given in Table 4. A positive value indicates profit increase and
vice-versa, and so a profit increase indicates better performance. As shown in Table 4, HS
shows better performance for d1 and d3, even though the other performance measures
applied so far indicate otherwise. This can be attributed to the greater production of styrene
during the transient state (as a result of larger fluctuations in the process variables) which is
manifested in higher profit. Actually, when the objective of the plant operator is to decrease
styrene production in the case of d1 and d3, a higher amount of styrene produced during the
10
8/3/2019 Performance Assessment of Plant-Wide Control Systems
11/13
transient state is undesirable. The reason for this is that any excess amount of styrene
produced cannot be sold easily given the lower demand. Thus, there is a major drawback
with this economic measure as it does not take into account the over-produced amount of
styrene during the transient state. Hence, as discussed in the previous section, an alternative
economic measure (DPT) is evaluated next.
Table 4. Net Variation in the Plant Operating Profit with Units of (a) $/(kg of
Styrene/hr) and (b) $/(tonne of Styrene), for HS and IF Control Structures
No. Disturbance MagnitudeNet Variation ($/kg/hr) Net Variation ($/tonne)
HS IF HS IF
d1
Production Rate
-5% 0.20 0.13 5.9 4.0
d2 +5% -0.21 -0.12 -6.2 -3.7
d3 -20% 0.76 0.50 22.7 15.1d4 Feed Composition -2% -0.013 0.00 -0.38 0.07
Note: In this table, the largest value of the net variation for each disturbance is shown with grey background.
Deviation from the Production Target (DPT) of Styrene
The DPT of styrene over the duration of the total simulation time (2000 min) is computed.
The results presented in Table 5 give a clear picture. For d1 to d3, the target production rate
in equation 3 is the final production rate at the new steady-state. For d4, the target
production rate in equation 3 is the original production rate. A positive value of DPTindicates over production, while a negative value indicates under production. Since both
over and under production is undesirable, smaller (absolute) deviation from the desired
production rate target indicates better performance. In general, IF shows better performance
for all disturbances except d4. This means that a smaller amount of styrene over/under
production is achieved with this control system. This translates into a lower loss due to
unwanted amount of product being produced. Interestingly, IF shows poorer performance
for d4. This could be due to the fixing of EB feed flow in IF, whereas it is allowed to vary in
HS. For d4, this results in a 2% decrease in the fresh EB flow in IF as opposed to 0.75%
decrease in the case of HS. The greater decrease in the fresh EB flow is manifested as a
larger DPT as the styrene production rate is directly proportional to the fresh EB flow rate.
General Assessment of the Performance Measures
The performance measures presented in the previous section have been evaluated on two
different control structures for the styrene plant in this section. In general, control structure
IF performs better in terms of most of the measures except for the net variation in the plant
11
8/3/2019 Performance Assessment of Plant-Wide Control Systems
12/13
operating profit, where a clear picture does not emerge from the results. However, as
discussed earlier, this measure does not indicate the superior performance of a control
structure. Of all the measures presented, we recommend DDS (as it gives an indication of
the ability of the control system in handling disturbances dynamically) and DPT (as it gives
an indication of the economic performance of the control system).
Table 5. DPT of Styrene for HS and IF Control Structures
No. Disturbance MagnitudeDPT of Styrene (kg)
HS IF
d1
Production Rate
-5% 2329 1558
d2 +5% -2275 -1376
d3 -20% 8844 5656
d4 Feed Composition -2% -2558 -5947
Note: In this table, the smallest DPT of styrene for each disturbance is shown with grey background.
A typical plant with a control system has many process and operating variables that have
to be monitored, and it can be quite time-consuming and difficult to analyze and compare
the numerous profiles of the different alternative control systems. Besides, such qualitative
analysis is subjective. Hence, quantitative measures based on process dynamics such as
presented here enable effective and easy analysis with minimal computational effort. All the
calculations presented can be easily automated and done using a spreadsheet.
Conclusions
Several performance measures based on plant dynamics for assessing PWC systems have
been presented in this work. The main aim of this is to present easier and more reliable
quantitative tools for assessing different PWC structures. The feasibility of using these
measures for performance assessment of PWC systems has been illustrated on two
alternative control structures for the styrene plant. In particular, DDS and DPT are
recommended in order to get an overall picture of PWC system performance covering
various aspects.
References
1. He, M.J. and Cai, W.J., New Criterion for Control-Loop Configuration of Multivariable
Processes,Ind. Eng. Chem. Res., 43, pp. 7057-7064 (2004).
2. Xiong, Q., Cai, W.J. and He, M.J., A Practical Loop Pairing Criterion for Multivariable
Processes,J. Proc. Cont., 15, pp. 741-747 (2005).
12
8/3/2019 Performance Assessment of Plant-Wide Control Systems
13/13
3. Yi, C.K. and Luyben, W.L., Evaluation of Plant-Wide Control Structures by Steady-
State Disturbance Sensitivity Analysis, Ind. Eng. Chem. Res., 34, pp. 2393-2405
(1995).
4. Elliott, T.R. and Luyben, W.L., Capacity-Based Economic Approach for the
Quantitative Assessment of Process Controllability during the Conceptual Design
Stage,Ind. Eng. Chem. Res., 34, pp. 3907-3915 (1995).
5. Elliott, T.R. and Luyben, W.L., Quantitative Assessment of Controllability during the
Design of a Ternary System with Two Recycle Streams, Ind. Eng. Chem. Res.,35, pp.
3470-3479 (1996).
6. Elliott, T.R., Luyben, W.L. and Luyben, M.L., Application of the Capacity-Based
Economic Approach to an Industrial-Scale Process,Ind. Eng. Chem. Res., 36, pp. 1727-
1737 (1997).7. Konda, N.V.S.N.M. and Rangaiah, G.P., Performance Assessment of Plant-Wide
Control Systems of Industrial Processes, Ind. Eng. Chem. Res., 46, pp. 1220-1231
(2007).
8. Seborg, E., Edgar, T.F. and Mellichamp, D.A.,Process Dynamics and Control, Wiley,
New Jersey (2004).
9. Skogestad, S., Control Structure Design for Complete Chemical Plants, Comput.
Chem. Eng., 28, pp. 219-234 (2004).
10. Vasudevan, S., Rangaiah, G.P., Konda, N.V.S.N.M. and Tay, W.H., Application and
Evaluation of Three Methodologies for Plant-Wide Control of the Styrene Monomer
Plant,Ind. Eng. Chem. Res., In press (2009).
11. Luyben, W.L., Tyreus, B.D. and Luyben, M.L.,Plant-Wide Process Control, McGraw-
Hill, New York (1998).
12. Konda, N.V.S.N.M., Rangaiah, G.P. and Krishnaswamy, P.R., Plant-Wide Control of
Industrial Processes: An Integrated Framework of Simulation and Heuristics,Ind. Eng.
Chem. Res., 44, pp. 8300-8313 (2005).
13